Está en la página 1de 7

OKI PULP & PAPER MILL Project No.

P-OkiPL1
PROJECT
[OKIPL1] Document No. P-OkiPL1-100-01-FRM-XXX
Revision 00

Bringing Plant and Apparatus Under Page 1 of 7


The Safety Rules Issue Date February 10, 2016

Contents Page

1. OBJECTIVE

2. DEFINITIONS

3. CONDITIONS FOR ISSUE OF AN SRCC


2

4. GENERAL

5. RECORDS

6. KEYS

APPENDIX

A. SAFETY RULES CLEARANCE CERTIFICATE (4 SHEETS)


OKI PULP & PAPER MILL Project No. P-OkiPL1
PROJECT
[OKIPL1] Document No. P-OkiPL1-100-01-FRM-XXX
Revision 00

Bringing Plant and Apparatus Under Page 2 of 7


The Safety Rules Issue Date February 10, 2016

1. Objective

The objective of issuing a Safety Rules Clearance Certificate (SRCC) is to


advise all parties that the subject Plant or Apparatus is about to be made Live,
or pressurized with working fluid, or brought into service for the first time and by
virtue of this, any further work on this Plant or Apparatus constitutes a hazard.

2. Definitions

Definitions printed in bold type are defined in the Safety Rules.

3. Conditions For Issue of An SRCC

Before an SRCC (Appendix A) is issued, the Plant or Apparatus to be brought


under the Safety Rules must be:

(i) Completed System Punch List .


(ii) Clearly identified. The identification may be temporary but should be
securely fixed to the Plant or Apparatus.
(iii) Provided with means of isolation, which is lockable wherever possible.
(iv) Accessible, with free access to and from its surrounding area.
(v) Clearly defined. The terminal points of the Plant or Apparatus will be
tagged.

4. General

4.1 In general terms, the SRCC will be issued in advance of first energize
or pressurization with working fluid.

4.2 SRCCs shall wherever possible, be issued on a System basis and shall
take into account the need to complete the commissioning activities
within the terminal points.

SRCCs will only be issued for systems, which are substantially omplete.

To control this transfer from the construction phase to the


commissioning phase a System Punch List will be raised when Plant /
Apparatus construction is completed. The System Punch List will be
raised by the responsible Erection Group Nominee and presented to the
Commissioning Group Nominee.

4.3 Where part of a System is already under a SRCC and the balance of
the Plant / Apparatus In that System, is to be brought under the Safety
Rules, then a further SRCC shall be issued moving the terminal points
from those stated on the earlier certificate to those stated on the new
certificate. Reference shall be made to this on the new certificate.

4.4 System terminal points will be identified, Isolated wherever possible and
Tagged.
OKI PULP & PAPER MILL Project No. P-OkiPL1
PROJECT
[OKIPL1] Document No. P-OkiPL1-100-01-FRM-XXX
Revision 00

Bringing Plant and Apparatus Under Page 3 of 7


The Safety Rules Issue Date February 10, 2016
4.5 The Plant / Apparatus and the SRCC will be prepared by the
Commissioning Group Nominee responsible for that System as soon as
possible before that System is to be energized / pressurised in
accordance with the Isolation Procedure.

4.6 The Isolation of the Plant / Apparatus and the SRCC, shall be checked
and signed by the Manager nominated by the Site Manager who will
issue the SRCC to all nominated parties approximately two days before
the Plant / Apparatus is to be energized or pressurised. The Nominated
Parties will acknowledge receipt of the SRCC by signing the relevant
section of the SRCC.

4.7 Once a SRCC has come into force, work on the Plant / Apparatus is to be
carried out under the appropriate Safety Document or Verbal Instruction
in accordance with the Safety Rules.

4.8 The persons acknowledging receipt of the SRCC will be responsible for
ensuring that their staff are informed that the SRCC is being issued and
that all subsequent work will be conducted under the terms of the Safety
Rules.

5 Records

SRCCs will be identified thus:-

System / SRCC No i.e. /SRCC

and a register shall be retained by the Site Managers Nominee together with
the original of each SRCC.

6 Keys
Keys forming SRCC terminal point isolations shall be retained by the Site
Managers Nominee and secured in a dedicated uncommissioned Plant /
Apparatus key safe.
Appendix 1
(Sheet 1/4)
TANJUNG BIN POWER PLANT SAFETY RULES
SAFETY RULES CLEARANCE CERTIFICATE (SRCC)

UNIT Serial No.


SRCC NO.:

I hereby give notice that the Plant / Apparatus scheduled below is ready to be made live / charged with
working fluid / put into service and all subsequent work is to be conducted under the terms of the TANJUNG
BIN POWER PLANT SAFETY RULES.

Effective From Time: ______________ Date : _____________

Plant / Apparatus being made live / charged / put into service:-

ID Ref. ___________________________________________________________________

Description ___________________________________________________________________

Location ___________________________________________________________________

Type of System ___________________________________________________________________

Technical Group Manager or his nominee:-

Signed _____________________ Name __________________________ Date ________________

Commissioning Manager or his nominee:

I confirm that the Plant / Apparatus listed above is required to be SRCCs and I authorize their being made
live / charged with the working fluid / put into service after complete processing of this SRCC.

Signed _____________________ Name __________________________ Date ________________

Appendix 1
(Sheet 2/4)
TANJUNG BIN POWER PLANT SAFETY RULES
TERMINAL POINTS LOCKED AND TAGGED
UNIT Serial No.
SRCC NO.:

ID Description SRCC No. Subsequently Initials


Released By
** SRCC No.

* To be entered by Safety Controller releasing the key.

I confirm I have ensured with all involved parties that the Plant / Apparatus listed above is ready to be SRCCs and
all necessary terminal points listed above are made safe, locked and tagged.

Signed _____________________ Name __________________________Technical Group Nominee

Date _____________________ Time __________________________


Appendix 1
(Sheet )
TANJUNG BIN POWER PLANT SAFETY RULES
TERMINAL POINTS TO BE RELEASED ON OTHER SRCCS
UNIT Serial No.
SRCC NO.:

ID Description SRCC No. Name Initials


(*Note)

* Note: - 1 authorise the terminal points of previous SRCCs listed above and locked by myself or by my nominated
deputy, to be released.

PERMIT OFFICE

I confirm this SRCC has completed its process as required by local management instruction XX/XX/XX and the Plant
/ Apparatus identified on page 1 may be made live / charged with the working fluid / put into service from

Date : _________________ Time : ___________________

The circulation list has been completed


A completed SRCC Checklist is attached.
All termination points listed above are confirmed locked and tagged.
All keys are secured in a SRCC Key Safe No.: ___________ under control of the Permit Office and will
remain secured until released by a subsequent SRCC.

Signed _____________________ Name __________________________Senior Permit Engineer

Date _____________________ Time __________________________


Appendix 1
(Sheet 4/4)
TANJUNG BIN POWER PLANT SAFETY RULES
TERMINAL POINTS TO BE RELEASED ON OTHER SRCCS
UNIT Serial No.
SRCC NO.:
Acknowledgment

I acknowledge receipt of this SRCC and will fulfill my responsibility to ensure all relevant personnel, sub
contractors and all their relevant personnel under my control are informed that this SRCC is being issued
and that all subsequent work on the detailed Plant / Apparatus must be conducted under the Terms of
SZC POWER PLANT SAFETY RULES.

Organisation Name Signature Date Time

FL COMMISSIONING ________________ ___________ ____________

PB COMMISSIONING ___________________________ ____________

CLO2 COMMISSIONING ___________________________ ____________

ETP COMMISSIONING ___________________________ ____________

NAOH COMMISSIONING ___________________________ ____________

OXY.SO2.PAC COMMISSIONING ___________________________ ____________

PD COMMISSIONING ___________________________ ____________

WHP COMMISSIONING ___________________________ ____________

WTP COMMISSIONING ___________________________ ____________

LK COMMISSIONING ___________________________ ____________

RB COMMISSIONING ___________________________ ____________

RC COMMISSIONING ___________________________ ____________

TG COMMISSIONING ___________________________ ____________

VE COMMISSIONING ___________________________ ____________

HSSE COMMISSIONING ___________________________ ____________