CRONOGRAMA VALORIZADO DE OBRA

OBRA : CONSTRUCCION DE CANAL DE IRRIGACION SAN JOSE DE SUCRE


LUGAR : COLCA - FAJARDO - AYACUCHO
COSTO DIRECTO : 904,184.66
PLAZO DE EJECUCION DE OBRA
PRESUPUESTO DE
ITEM ACTIVIDADES MES 01 MES 02 MES 03 MES 04 MES 05 PARCIALES S/.
OBRA
30 DIAS 60 DIAS 90 DIAS 120.00 143 DIAS

1.0 OBRAS PROVISIONALES


01 OBRAS PROVISIONALES 10,231.89 10,231.89 10,231.89
2.0 BOCATOMA
01 TRABAJOS PRELIMINARES 3,449.05 3,449.05 3,449.05
02 MOVIMIENTO DE TIERRAS 31,064.42 31,064.42 31,064.42
03 OBRAS DE CONCRETO SIMPLE 32,781.84 11,473.64 21,308.20 32,781.84
04 OBRAS DE CONCRETO ARMADO 40,598.60 18,269.37 22,329.23 40,598.60
05 ENCOFRADO Y DESENCOFRADO 12,151.92 12,151.92 12,151.92
06 ACERO DE REFUERZO 19,738.66 19,738.66 19,738.66
07 ESTRUCTURAS METALICAS 13,584.96 5,433.98 8,150.98 13,584.96
3.0 ANTECANAL
01 TRABAJOS PRELIMINARES 97.09 97.09 97.09
02 MOVIMIENTO DE TIERRAS 3,850.69 3,850.69 3,850.69
03 REVESTIMIENTO DE CANAL 27,594.53 9,658.09 17,936.44 27,594.53
04 JUNTAS 544.43 163.33 381.10 544.43
05 CANAL DESRIPEADOR 10,393.72 10,393.72 10,393.72
4.0 CANAL PRINCIPAL
01 OBRAS PRELIMINARES 7,124.63 7,124.63 7,124.63
02 MOVIMIENTO DE TIERRAS 116,774.76 116,774.76 116,774.76
03 INSTALACION DE TUBERIAS 460,608.87 92,121.77 276,365.32 92,121.77 460,608.87
04 CAJAS DE INSPECCIN Y VOLTEO 15,562.83 6,225.13 9,337.70 15,562.83
05 TOMAS LATERALES 1,600.49 80.02 1,520.47 1,600.49
5.0 OBRAS DE ARTE 0.00 0.00
01 DESARENADOR 6,314.04 6,314.04 6,314.04
02 POZA DE CAPTACIN 766.29 766.29 766.29
CRONOGRAMA VALORIZADO DE OBRA

OBRA : CONSTRUCCION DE CANAL DE IRRIGACION SAN JOSE DE SUCRE


LUGAR : COLCA - FAJARDO - AYACUCHO
COSTO DIRECTO : 904,184.66
PLAZO DE EJECUCION DE OBRA
PRESUPUESTO DE
ITEM ACTIVIDADES MES 01 MES 02 MES 03 MES 04 MES 05 PARCIALES S/.
OBRA
30 DIAS 60 DIAS 90 DIAS 120.00 143 DIAS

03 CANOAS 3,418.48 3,418.48 3,418.48


04 RAPIDAS 2,136.29 1,709.03 427.26 2,136.29
05 TOMAS TIPICAS DE INGRESO Y SALIDA 6,665.04 5,332.03 1,333.01 6,665.04
06 VERTEDERO DE EXDENCIAS 3,833.92 3,833.92 3,833.92
07 DADOS DE CONCRETO 7,314.43 7,314.43 7,314.43
08 ALCANTARRILLAS DE CONCRETO ARMADO 35,544.17 21,326.50 14,217.67 35,544.17
09 CANAL DE PURGA 353.50 353.50 353.50
6.0 FLETE 22,377.30 11,188.65 11,188.65 22,377.30
7.0 IMPACTO AMBIENTAL 7,707.82 1,926.96 1,926.96 1,926.96 1,926.96 7,707.82

COSTO DIRECTO 904,184.66 56,219.00 80,446.36 335,552.34 317,391.88 114,575.08 904,184.66