RESUMEN DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYECTIS. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

ITEM DESCRIPCION UND METRADO

01.00
OBRAS PROVISIONALES,TRABAJOS PRELIMINARES , SEGURIDAD Y SALUD
01.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES
01.01.05 TRAZOS,NIVELES Y REPLANTEO
01.01.05.01 TRAZO Y REPLANTEO PRELIMINAR m 751.64
01.01.05.02 REPLANTEO DURANTE EL PROCESO m 751.64

02.00 ESTRUCTURAS
02.01 MOVIMIENTO DE TIERRAS
02.01.02 EXCAVACIONES
02.01.02.02 EXCAVACION DE ZANJAS Y ZAPATAS Rt<=2.0 Kg/cm2. Df =1.00 m. m
02.01.02.03 EXCAVACION DE ZANJAS Y ZAPATAS Rt<=2.0 Kg/cm2. Df =1.50 m. m 274.12
02.01.02.04 EXCAVACION DE ZANJAS Y ZAPATAS Rt<=2.0 Kg/cm2. Df =2.00 m. m 2,005.99

02.01.04 RELLENOS
RELLENO CON MATERIAL PROPIO COMPACTADO CON PLANCHA
02.01.04.01 m 2,121.01
VIBRATORIA 4HP.
02.01.04.02 ESCARIFICADO Y COMPACTADO DE SUB-RASANTE m 182.01

02.01.05 ELIMINACION DE MATERIAL EXCEDENTE


02.01.05.01 ACARREO INTERNO MATERIAL PROC. DE EXCAVACIONES m 206.82
02.01.05.02 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA m 206.82

02.02 OBRAS DE CONCRETO SIMPLE

02.02.01 CIMIENTOS CORRIDOS


02.02.01.01 CIMIENTOS CORRIDOS 1:10 +30%P.G. m 71.63
02.02.01.02 CIMIENTOS CORRIDOS 1:12 +30%P.G. m

02.02.02 SOLADOS
02.02.02.01 SOLADO E=4" DE CIMIENTO Y ZAPATAS C:H 1:12 m 613.48

02.02.03 SOBRECIMIENTO
02.02.03.01 SOBRECIMIENTOS CONCRETO C:H 1:8 + 25% P.M. f'c>=100Kg/cm2 m 12.27
02.02.03.02 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO m 182.91

02.03 OBRAS DE CONCRETO ARMADO

02.03.05 VIGAS DE CIMENTACION


RESUMEN DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYECTIS. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

ITEM DESCRIPCION UND METRADO

02.03.05.01 VIGAS DE CIMENTACION.- CONCRETO f'c=210 Kg/cm2 m3 4.65


02.03.05.02 VIGAS DE CIMENTACION.- ENCOFRADO Y DESENCOFRADO m2 23.23
02.03.05.03 VIGAS DE CIMENTACION.- ACERO f'y=4200 Kg/cm2 kg 604.06

02.03.02 SOBRECIMIENTO REFORZADO


02.03.02.01 SOBRECIMIENTO REFORZADO.- CONCRETO f'c=210 Kg/cm2 m 6.56
02.03.02.02 SOBRECIMIENTO REFORZADO.- ENCOFRADO Y DESENCOFRADO m 60.95
02.03.02.03 SOBRECIMIENTO REFORZADO.- ACERO f'y=4200 Kg/cm2 kg 326.51

02.03.03 ZAPATAS
02.03.03.01 ZAPATAS.- CONCRETO f'c=210 Kg/cm2 m 450.32
02.03.03.02 ZAPATAS.- ACERO f'y=4200 Kg/cm2 kg 63,631.79

02.03.05 MURO DE CONTENCION


02.03.05.01 MURO DE CONTENCION.- CONCRETO f'c = 210 kg/cm2 m 166.52
02.03.05.02 MURO DE CONTENCION.- ENCOFRADO Y DESENCOFRADO m 1,340.31
02.03.05.03 MURO DE CONTENCION.- ACERO Fy=4200 kg/cm2 kg 20,702.35

02.03.07 COLUMNAS
02.03.07.01 COLUMNAS.- CONCRETO f'c=210 Kg/cm2 m 70.20
02.03.07.02 COLUMNAS.- ENCOFRADO Y DESENCOFRADO m 1,069.39
02.03.07.03 COLUMNAS.- ACERO f'y=4200 Kg/cm2 kg 8,282.80

02.03.09 VIGAS
02.03.09.01 VIGAS.- CONCRETO f'c=210 Kg/cm2 m 20.71
02.03.09.02 VIGAS.- ENCOFRADO Y DESENCOFRADO m 221.82
02.03.09.03 VIGAS.- ACERO f'y=4200 Kg/cm2 kg 6,689.50

02.03.12 CANALETA DE DRENAJE PLUVIAL EN TECHO


02.03.12.01 CANALETA.- CONCRETO f'c=210 Kg/cm2 m 1.01
02.03.12.02 CANALETA.- ENCOFRADO Y DESENCOFRADO m 8.42
02.03.12.03 CANALETA.- ACERO f'y=4200 Kg/cm2 kg 28.65

02.03.13 LOSA MACIZA


02.03.13.01 LOSA MACIZA.- CONCRETO f'c=210 Kg/cm2 m 3.02
02.03.13.02 LOSA MACIZA.- ENCOFRADO Y DESENCOFRADO m 25.20
02.03.13.03 LOSA MACIZA.- ACERO f'y=4200 Kg/cm2 kg 121.32
RESUMEN DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYECTIS. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

ITEM DESCRIPCION UND METRADO


SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO

OBRAS PROVISIONALES,TRABAJOS PRELIMINARES ,


01.00
SEGURIDAD Y SALUD
01.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES

01.01.05 TRAZOS,NIVELES Y REPLANTEO


01.01.05.01 TRAZO Y REPLANTEO PRELIMINAR m 751.64

MC-01 1.00 1.00 4.40 8.73 38.41


MC-02 1.00 1.00 2.45 86.50 211.93
MC-03 1.00 1.00 1.75 29.05 50.84
MC-05 1.00 1.00 1.30 18.48 24.02
MC-06 1.00 1.00 1.75 17.45 30.54
MC-07 1.00 1.00 2.45 10.90 26.71
MC-08 1.00 1.00 4.40 8.15 35.86
MC-13 1.00 1.00 4.45 43.86 195.18

ingreso primaria 1.00 1.00 rea= 54.25 54.25


ingreso Tribuna Existente 1.00 1.00 rea= 27.20 27.20
ingreso Estacionamiento 1.00 1.00 rea= 41.98 41.98

caseta 1.00 1.00 rea= 14.74 14.74

01.01.05.02 REPLANTEO DURANTE EL PROCESO m 751.64


1.00 1.00 rea= 751.64 751.64

02.00 ESTRUCTURAS

02.01 MOVIMIENTO DE TIERRAS


02.01.02 EXCAVACIONES

02.01.02.02 02.01.02.02 02.01.02.02 6.30

caseta
vigas de cimentacion 1.00 2.00 4.82 0.40 0.80 3.08
1.00 3.00 1.63 0.60 1.10 3.22

02.01.02.03 EXCAVACION DE ZANJAS Y ZAPATAS Rt<=2.0 Kg/cm2. Df =1.50 m. m 274.12

ingresos
ingreso principal
zapata 1.00 1.00 10.05 4.65 2.00 93.47

ingreso Tribuna Existente


zapata 1.00 1.00 rea= 48.05 2.00 96.10

ingreso Estacionamiento
zapata 1.00 1.00 4.75 8.90 2.00 84.55
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO

02.01.02.04 EXCAVACION DE ZANJAS Y ZAPATAS Rt<=2.0 Kg/cm2. Df =2.00 m. m 2,005.99

cerco perimtrico
zapatas
MC-01 1.00 1.00 4.40 8.73 7.25 278.49
MC-02 1.00 1.00 2.45 86.50 4.00 847.70
MC-03 1.00 1.00 1.75 29.05 2.45 124.55
MC-05 1.00 1.00 1.30 18.48 2.10 50.45
MC-06 1.00 1.00 1.75 17.45 1.35 41.23
MC-07 1.00 1.00 2.45 10.90 4.15 110.83
MC-08 1.00 1.00 4.40 8.15 7.25 259.99
MC-13 1.00 1.00 4.45 43.86 1.50 292.77

02.01.04 RELLENOS

RELLENO CON MATERIAL PROPIO COMPACTADO CON PLANCHA


02.01.04.01 m 2,121.01
VIBRATORIA 4HP.
Excavacion Total 2,280.11 1.00 2,280.11
Descontar Volumen de Solados 61.35 -1.00 -61.35
Descontar volumen de cimiento corrido 71.63 -1.00 -71.63
Descontar Volumen de Zapatas 450.32 -1.00 -450.32
1696.81 1.25

02.01.04.02 ESCARIFICADO Y COMPACTADO DE SUB-RASANTE 182.01


ingresos
ingreso principal 1.00 1.00 rea= 41.98 41.98
ingreso primaria 1.00 1.00 rea= 54.25 54.25
ingreso secundaria 1.00 1.00 4.75 8.90 42.28
ingreso polideportivo 1.00 1.00 rea= 43.50 43.50

02.01.05 ELIMINACION DE MATERIAL EXCEDENTE


02.01.05.01 ACARREO INTERNO MATERIAL PROC. DE EXCAVACIONES m 206.82
Volumen total de excavacin 1.00 2,280.11 2,280.11
relleno con material propio -1.00 2,121.01 -2,121.01
159.10
esponjamiento 30% 1.30 206.82

02.01.05.02 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA m 206.82


Volumen total de excavacin 1.00 2,280.11 2,280.11
relleno con material propio -1.00 2,121.01 -2,121.01
159.10
esponjamiento 30% 1.30 206.82

02.02 OBRAS DE CONCRETO SIMPLE

02.02.01 CIMIENTOS CORRIDOS


02.02.01.01 CIMIENTOS CORRIDOS 1:10 +30%P.G. m 71.63
ingresos
ingreso principal
concreto ciclpeo 1.00 1.00 10.05 4.65 0.50 23.37

ingreso Tribuna Existente


concreto ciclpeo 1.00 1.00 rea= 54.25 0.50 27.13
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO

ingreso Estacionamiento
zapata 1.00 1.00 4.75 8.90 0.50 21.14

02.02.02 SOLADOS
02.02.02.01 SOLADO E=4" DE CIMIENTO Y ZAPATAS C:H 1:12 m 613.48
cerco perimtrico
zapatas
MC-01 1.00 1.00 4.40 8.73 38.41
MC-02 1.00 1.00 2.45 86.50 211.93
MC-03 1.00 1.00 1.75 29.05 50.84
MC-05 1.00 1.00 1.30 18.48 24.02
MC-06 1.00 1.00 1.75 17.45 30.54
MC-07 1.00 1.00 2.45 10.90 26.71
MC-08 1.00 1.00 4.40 8.15 35.86
MC-13 1.00 1.00 4.45 43.86 195.18

02.02.03 SOBRECIMIENTO

02.02.03.01 SOBRECIMIENTOS CONCRETO C:H 1:8 + 25% P.M. f'c>=100Kg/cm2 m 12.27

cerco perimtrico
cerco perimtrico tipo I, II, III, IV, V, VI
cimiento corrido 1.00 1.00 143.26 0.13 0.60 11.17

ingresos
ingreso principal 1.00 2.00 2.75 0.20 1.00 1.10

02.02.03.02 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO m caras 182.91


cerco perimtrico
cerco perimtrico tipo I, II, III, IV, V, VI
cimiento corrido 1.00 1.00 143.26 2.00 0.60 171.91

ingresos
ingreso principal 1.00 2.00 2.75 2.00 1.00 11.00

02.03 OBRAS DE CONCRETO ARMADO

02.03.05 VIGAS DE CIMENTACION


02.03.05.01 VIGAS DE CIMENTACION.- CONCRETO f'c=210 Kg/cm2 m3 4.65
caseta
Eje 1G VC-1(.40X.80) 2.00 4.82 0.40 0.80 3.08
3.00 1.63 0.40 0.80 1.56

02.03.05.02 VIGAS DE CIMENTACION.- ENCOFRADO Y DESENCOFRADO m2 caras 23.23


caseta
Eje 1G VC-1(.40X.80) 2.00 4.82 2.00 0.80 15.42
3.00 1.63 2.00 0.80 7.81

02.03.05.03 VIGAS DE CIMENTACION.- ACERO f'y=4200 Kg/cm2 kg Cant L (m) Elemen. Coefic. 604.06
caseta
Eje 1G, 2G VC-1(.40X.80)
ref. superior corrido 5/8" 2.00 6.02 3.00 1.55 55.99
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO
ref. corrido 1/2" 2.00 6.02 6.00 0.99 71.52
ref. inferior corrido 5/8" 2.00 6.02 3.00 1.55 55.99
estribos 2 3/8" 1@0.05, 7@0.10, R@0.25 2.00 2.00 1.88 35.00 0.56 147.39

Eje AG, AG', BG VC-1(.40X.80)


ref. superior corrido 5/8" 3.00 3.63 3.00 1.55 50.59
ref. corrido 1/2" 3.00 3.63 6.00 0.99 64.62
ref. inferior corrido 5/8" 3.00 3.63 3.00 1.55 50.59
estribos 2 3/8" 1@0.05, 7@0.10, R@0.25 3.00 2.00 1.88 17.00 0.56 107.39

02.03.02 SOBRECIMIENTO REFORZADO


02.03.02.01 SOBRECIMIENTO REFORZADO.- CONCRETO f'c=210 Kg/cm2 m 6.56
ingresos
ingreso principal 1.00 2.00 1.80 0.20 1.15 0.83

ingreso Tribuna Existente


corte A-A 1.00 1.00 0.67 0.24 1.40 0.23
corte B-B 1.00 1.00 0.62 0.24 1.40 0.21
corte C-C 1.00 1.00 1.20 0.24 1.40 0.40
corte 4-4 1.00 1.00 0.84 0.24 2.00 0.40
corte 5-5 1.00 1.00 0.84 0.24 2.00 0.40

ingreso Estacionamiento
corte A-A 1.00 1.00 1.53 0.24 1.40 0.51
corte B-B 1.00 1.00 1.53 0.24 1.40 0.51
corte 7-7 1.00 1.00 2.16 0.24 2.00 1.04
corte 8-8 1.00 1.00 2.76 0.24 2.00 1.32
caseta 0.00
Eje 1G, 2G 1.00 2.00 1.73 0.13 0.35 0.16
1.00 2.00 1.83 0.13 0.35 0.17
1.00 2.00 1.00 0.13 0.35 0.09
Eje AG, AG', BG 1.00 1.00 1.73 0.13 0.35 0.08
1.00 1.00 1.21 0.13 0.35 0.06
1.00 1.00 1.09 0.13 0.35 0.05
1.00 1.00 2.17 0.13 0.35 0.10

02.03.02.02 SOBRECIMIENTO REFORZADO.- ENCOFRADO Y DESENCOFRADO m caras 60.95


ingresos
ingreso principal 1.00 2.00 1.80 2.00 1.15 8.28

ingreso Tribuna Existente


corte A-A 1.00 1.00 0.67 2.00 1.40 1.88
corte B-B 1.00 1.00 0.62 2.00 1.40 1.74
corte C-C 1.00 1.00 1.20 2.00 1.40 3.36
corte 4-4 1.00 1.00 0.84 2.00 2.00 3.36
corte 5-5 1.00 1.00 0.84 2.00 2.00 3.36

ingreso Estacionamiento
corte A-A 1.00 1.00 1.53 2.00 1.40 4.28
corte B-B 1.00 1.00 1.53 2.00 1.40 4.28
corte 7-7 1.00 1.00 2.16 2.00 2.00 8.64
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO
corte 8-8 1.00 1.00 2.76 2.00 2.00 11.04
caseta
Eje 1G, 2G 1.00 2.00 1.73 2.00 0.35 2.42
1.00 2.00 1.83 2.00 0.35 2.56
1.00 2.00 1.00 2.00 0.35 1.40
Eje AG, AG', BG 1.00 1.00 1.73 2.00 0.35 1.21
1.00 1.00 1.21 2.00 0.35 0.85
1.00 1.00 1.09 2.00 0.35 0.76
1.00 1.00 2.17 2.00 0.35 1.52

02.03.02.03 SOBRECIMIENTO REFORZADO.- ACERO f'y=4200 Kg/cm2 kg Cant L (m) Elemen. Coefic. 326.51
ingresos
ingreso principal 2.00 1.80 6.00 0.56 12.10
ref. 3/8"@.20 2.00 1.15 9.00 0.56 11.59

ingreso Tribuna Existente


corte A-A
ref. 3/8"@.20 1.00 2.50 6.00 0.56 8.40
1.00 1.65 10.00 0.56 9.24
corte B-B
ref. 3/8"@.20 1.00 2.50 6.00 0.56 8.40
1.00 1.60 10.00 0.56 8.96
corte C-C
ref. 3/8"@.20 1.00 2.50 9.00 0.56 12.60
1.00 2.17 10.00 0.56 12.15
corte 4-4
ref. 3/8"@.20 1.00 2.50 7.00 0.56 9.80
1.00 1.82 10.00 0.56 10.19
corte 5-5
ref. 3/8"@.20 1.00 2.50 7.00 0.56 9.80
1.00 1.82 10.00 0.56 10.19

ingreso Estacionamiento
corte A-A
ref. 3/8"@.20 1.00 2.50 10.00 0.56 14.00
1.00 2.50 10.00 0.56 14.00
corte B-B
ref. 3/8"@.20 1.00 2.50 8.00 0.56 11.20
1.00 1.97 10.00 0.56 11.03
corte 7-7
ref. 3/8"@.20 1.00 2.50 14.00 0.56 19.60
1.00 3.15 10.00 0.56 17.64
corte 8-8
ref. 3/8"@.20 1.00 2.50 17.00 0.56 23.80
1.00 3.75 10.00 0.56 21.00
caseta
ref. vertical 3/8"@.20 2.00 6.49 2.00 0.56 14.55
ref. horizontal 3/8"@.20 2.00 0.85 25.00 0.56 23.80

ref. vertical 3/8"@.20 2.00 2.65 2.00 0.56 5.93


ref. horizontal 3/8"@.20 2.00 0.85 9.00 0.56 8.57
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO
ref. vertical 3/8"@.20 1.00 1.56 7.00 0.56 6.13
ref. horizontal 3/8"@.20 1.00 0.85 7.00 0.56 3.33

ref. vertical 3/8"@.20 1.00 1.44 7.00 0.56 5.66


ref. horizontal 3/8"@.20 1.00 0.85 6.00 0.56 2.86

02.03.03 ZAPATAS
02.03.03.01 ZAPATAS.- CONCRETO f'c=210 Kg/cm2 m 450.32
cerco perimtrico
zapatas
MC-01 1.00 1.00 4.40 8.73 0.60 23.05
MC-02 1.00 1.00 2.45 86.50 0.60 127.16
MC-03 1.00 1.00 1.75 29.05 0.60 30.50
MC-05 1.00 1.00 1.30 18.48 0.60 14.41
MC-06 1.00 1.00 1.75 17.45 0.60 18.32
MC-07 1.00 1.00 2.45 10.90 0.60 16.02
MC-08 1.00 1.00 4.40 8.15 0.60 21.52
MC-13 1.00 1.00 4.45 43.86 0.60 117.11

ingresos
ingreso principal
zapata 1.00 1.00 10.05 4.65 0.60 28.04

ingreso Tribuna Existente


zapata 1.00 1.00 rea= 48.05 0.60 28.83

ingreso estacionamiento
zapata 1.00 1.00 4.75 8.90 0.60 25.37

02.03.03.02 ZAPATAS.- ACERO f'y=4200 Kg/cm2 kg Cant L (m) Elemen. Coefic. 63,631.79
zapatas
MC-01
doble malla ref. 3/4"@.10 1.00 4.90 178.00 2.24 1,953.73
doble malla ref. 3/4"@.10 1.00 8.75 90.00 2.24 1,764.00
MC-02
doble malla ref. 3/4"@.10 1.00 2.95 1,732.00 2.24 11,445.06
doble malla ref. 3/4"@.10 1.00 86.50 52.00 2.24 10,075.52
MC-03
doble malla ref. 3/4"@.10 1.00 2.25 584.00 2.24 2,943.36
doble malla ref. 3/4"@.10 1.00 29.05 38.00 2.24 2,472.74
MC-05
doble malla ref. 3/4"@.10 1.00 1.80 372.00 2.24 1,499.90
doble malla ref. 3/4"@.10 1.00 18.48 28.00 2.24 1,159.07
MC-06
doble malla ref. 3/4"@.10 1.00 2.25 352.00 2.24 1,774.08
doble malla ref. 3/4"@.10 1.00 17.45 38.00 2.24 1,485.34
MC-07
doble malla ref. 3/4"@.10 1.00 2.95 220.00 2.24 1,453.76
doble malla ref. 3/4"@.10 1.00 10.90 52.00 2.24 1,269.63
MC-08
doble malla ref. 3/4"@.10 1.00 4.90 166.00 2.24 1,822.02
doble malla ref. 3/4"@.10 1.00 8.15 90.00 2.24 1,643.04
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO
MC-13
doble malla ref. 3/4"@.10 1.00 4.95 880.00 2.24 9,757.44
doble malla ref. 3/4"@.10 1.00 43.86 92.00 2.24 9,038.67

ingresos
ingreso principal
zapata
ref. superior 5/8"@0.25 1.00 11.45 20.00 1.55 354.95
1.00 5.35 42.00 1.55 348.29

ingreso Tribuna Existente


zapata
ref. superior 5/8"@0.25 1.00 16.40 15.00 1.55 381.30
1.00 4.00 61.00 1.55 378.20

ingreso estacionamiento
zapata
ref. superior 5/8"@0.25 1.00 9.65 20.00 1.55 299.15
1.00 5.45 37.00 1.55 312.56

02.03.05 MURO DE CONTENCION


02.03.05.01 MURO DE CONTENCION.- CONCRETO f'c = 210 kg/cm2 166.52

MC-01 1.00 1.00 8.73 seccin= 2.62 22.87


MC-02 1.00 1.00 86.50 seccin= 0.91 78.93
MC-03 1.00 1.00 29.03 0.20 2.20 12.77
MC-05 1.00 1.00 18.48 0.13 1.60 3.84
MC-06 1.00 1.00 17.42 0.20 2.60 9.06
MC-07 1.00 1.00 10.90 seccin= 0.91 9.95
MC-08 1.00 1.00 8.15 seccin= 2.52 20.54
MC-13 1.00 1.00 43.86 0.13 1.50 8.55

02.03.05.02 MURO DE CONTENCION.- ENCOFRADO Y DESENCOFRADO caras 1,340.31

MC-01 1.00 1.00 8.73 2.00 6.50 113.49


MC-02 1.00 1.00 86.50 2.00 3.65 631.45
MC-03 1.00 1.00 29.03 2.00 2.20 127.73
MC-05 1.00 1.00 18.48 2.00 1.60 59.14
MC-06 1.00 1.00 17.42 2.00 2.60 90.58
MC-07 1.00 1.00 10.90 2.00 3.65 79.57
MC-08 1.00 1.00 8.15 2.00 6.55 106.77
MC-13 1.00 1.00 43.86 2.00 1.50 131.58

02.03.05.03 MURO DE CONTENCION.- ACERO Fy=4200 kg/cm2 Cant L (m) Elemen. Coefic. 20,702.35
MC-01
ref. vertical
ref vertical doble malla 5/8"@.20 1.00 8.15 88.00 1.55 1,111.66
ref vertical doble malla 3/4"@.20 1.00 4.25 88.00 2.24 837.76
ref. horizontal
ref horizontal malla simple 1/2"@.30 1.00 8.73 33.00 0.99 285.21
ref horizontal malla simple 5/8"@.25 1.00 8.73 27.00 1.55 365.35
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO
MC-02
ref. vertical
ref vertical doble malla 5/8"@.20 1.00 87.30 42.00 1.55 5,683.23
ref. horizontal
ref horizontal malla simple 1/2"@.30 1.00 3.65 866.00 0.99 3,129.29

MC-03
ref. vertical
ref vertical doble malla 5/8"@.20 1.00 29.85 28.00 1.55 1,295.49
ref. horizontal
ref horizontal malla simple 1/2"@.30 1.00 2.70 292.00 0.99 780.52

MC-05
ref. vertical
ref vertical doble malla 5/8"@.20 1.00 19.28 22.00 1.55 657.45
ref. horizontal
ref horizontal malla simple 1/2"@.30 1.00 2.10 16.00 0.99 33.26

MC-06
ref. vertical
ref vertical doble malla 5/8"@.20 1.00 18.22 32.00 1.55 903.71
ref. horizontal
ref horizontal malla simple 1/2"@.30 1.00 3.10 26.00 0.99 79.79

MC-07
ref. vertical
ref vertical doble malla 5/8"@.20 1.00 11.70 42.00 1.55 761.67
ref. horizontal
ref horizontal malla simple 1/2"@.30 1.00 4.15 120.00 0.99 493.02

MC-08
ref. vertical
ref vertical doble malla 5/8"@.20 1.00 8.15 88.00 1.55 1,111.66
ref vertical doble malla 3/4"@.20 1.00 4.25 88.00 2.24 837.76
ref. horizontal
ref horizontal malla simple 1/2"@.30 1.00 8.73 33.00 0.99 285.21
ref horizontal malla simple 5/8"@.25 1.00 8.73 27.00 1.55 365.35

MC-13
ref. vertical
ref vertical doble malla 5/8"@.20 1.00 41.26 20.00 1.55 1,279.06
ref. horizontal
ref horizontal malla simple 1/2"@.30 1.00 2.00 205.00 0.99 405.90

02.03.07 COLUMNAS

02.03.07.01 COLUMNAS.- CONCRETO f'c=210 Kg/cm2 m 70.20

cerco perimtrico
columnas
cerco perimtrico tipo I, II, III, IV, V, VI 1.00 120.00 0.27 0.27 4.85 42.43

ingresos
ingreso principal
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO
C-0.40x1.00
corte 1-1 4.00 1.00 rea= 0.26 3.45 3.59
corte 2-2 4.00 1.00 rea= 0.34 6.40 8.70

C-0.24x1.00 1.00 2.00 1.00 0.24 5.00 2.40


C-0.24x0.24 1.00 2.00 0.24 0.24 5.00 0.58

ingreso Tribuna Existente


C1-24x24 1.00 13.00 0.24 0.24 3.70 2.77
C2-52x24 1.00 2.00 0.52 0.24 6.95 1.73
C3 1.00 2.00 rea= 0.27 6.95 3.72

ingreso estacionamiento
C1-24x24 1.00 8.00 0.24 0.24 5.10 2.35
Caseta
C1 1.00 4.00 0.42 0.13 3.33 0.73
C2 1.00 2.00 rea= 0.08 3.33 0.55
CA-1 1.00 6.00 0.25 0.13 3.33 0.65

02.03.07.02 COLUMNAS.- ENCOFRADO Y DESENCOFRADO m perim. 1,069.39

cerco perimtrico
columnas
cerco perimtrico tipo I, II, III, IV, V, VI 1.00 120.00 1.08 4.85 628.56

ingresos
ingreso principal
C-0.40x1.00
corte 1-1 4.00 1.00 4.60 3.45 63.48
corte 2-2 4.00 1.00 6.20 6.40 158.72

C-0.24x1.00 1.00 2.00 2.48 5.00 24.80


C-0.24x0.24 1.00 2.00 0.96 5.00 9.60

ingreso Tribuna Existente


C1-24x24 1.00 13.00 0.96 3.70 46.18
C2-52x24 1.00 2.00 1.52 6.95 21.13
C3 1.00 2.00 2.71 6.95 37.67

ingreso estacionamiento
C1-24x24 1.00 8.00 0.96 5.10 39.17
Caseta
C1 1.00 4.00 1.10 3.33 14.65
C2 1.00 2.00 1.54 3.33 10.26
CA-1 1.00 6.00 0.76 3.33 15.18

02.03.07.03 COLUMNAS.- ACERO f'y=4200 Kg/cm2 kg 8,282.80


cerco perimtrico Cant L (m) Elemen. Coefic.
cerco perimtrico tipo III
C-1
4 var. 1/2" 120.00 4.50 4.00 0.99 2,138.40
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO
estribos 3/8" 1@0.05, 6@0.10, r@0.25 120.00 1.02 24.00 0.56 1,645.06

ingresos
ingreso principal
C-0.40x1.00
corte 1-1
ref. vertical 83/8" 4.00 3.90 8.00 0.56 69.89
ref. vertical 161/2" 4.00 4.00 16.00 0.99 253.44
ref. horizontal 1/2" 4.00 1.40 28.00 0.99 155.23
estribos 3/8" 1@0.05, 5@0.10, r@0.25 4.00 1.06 44.00 0.99 184.69

corte 2-2
ref. vertical 163/8" 4.00 6.80 16.00 0.56 243.71
ref. vertical 161/2" 4.00 6.90 16.00 0.99 437.18
ref. horizontal 1/2" 4.00 1.80 52.00 0.99 370.66
estribos 3/8" 1@0.05, 5@0.10, r@0.25 4.00 1.06 68.00 0.99 285.44

C-0.24x1.00
ref. vertical 61/2" 2.00 6.00 6.00 0.99 71.28
estribos 3/8" 1@0.05, 5@0.10, r@0.25 2.00 2.54 28.00 0.56 79.65

C-0.24x0.24
ref. vertical 41/2" 2.00 6.00 4.00 0.99 47.52
estribos 3/8" 1@0.05, 5@0.10, r@0.25 2.00 1.02 28.00 0.56 31.99

ingreso Tribuna Existente


C1-24x24
ref. vertical 41/2" 13.00 5.00 4.00 0.99 257.40
estribos 3/8" 1@0.05, 5@0.10, r@0.25 13.00 1.02 28.00 0.56 207.92

C2-52x24
ref. vertical 61/2" 2.00 7.95 6.00 0.99 94.45
estribos 3/8" 1@0.05, 5@0.10, r@0.25 2.00 1.06 80.00 0.56 94.98

C3
ref. vertical 83/4" 2.00 8.35 8.00 2.24 299.26
ref. vertical 75/8" 2.00 8.15 7.00 1.55 176.86
estribos 3/8" 1@0.05, 5@0.10, r@0.25 2.00 2.86 40.00 0.56 128.13
2.00 2.18 40.00 0.56 97.66
2.00 0.44 80.00 0.56 39.42

ingreso estacionamiento
C1-24x24
ref. vertical 41/2" 8.00 5.60 4.00 0.99 177.41
estribos 3/8" 1@0.05, 5@0.10, r@0.25 8.00 1.02 28.00 0.56 127.95
Caseta
C-1 (.42x.13)
ref. vertical 41/2" 4.00 4.44 8.00 0.99 140.66
estribos 3/8" 1@0.05, 5@0.10, r@0.25 4.00 1.08 24.00 0.56 58.06
estribos 3/8" 1@0.05, 5@0.10, r@0.26 4.00 0.56 24.00 0.56 30.11

C-1 (.42x.13)
ref. vertical 41/2" 2.00 4.44 12.00 0.99 105.49
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO
estribos 3/8" 1@0.05, 5@0.10, r@0.25 2.00 1.08 24.00 0.56 29.03
estribos 3/8" 1@0.05, 5@0.10, r@0.25 2.00 0.94 24.00 0.56 25.27
estribos 3/8" 1@0.05, 5@0.10, r@0.25 2.00 0.25 48.00 0.56 13.44

CA-1
ref. vertical 41/2" 6.00 4.44 4.00 0.99 105.49
estribos 3/8" 1@0.05, 5@0.10, r@0.25 6.00 0.74 24.00 0.56 59.67

02.03.09 VIGAS
02.03.09.01 VIGAS.- CONCRETO f'c=210 Kg/cm2 m 20.71
cerco perimtrico
cerco perimtrico tipo I, II, III, IV, V, VI
viga de amarre 1.00 1.00 143.26 0.27 0.20 7.74

ingresos
ingreso principal
VH-1 (.40 x .40) 1.00 4.00 4.50 rea= 0.12 2.16
VH-2 (.40 x .40) 1.00 4.00 4.50 rea= 0.12 2.16
VA-104 (.24 x .70) 1.00 1.00 6.60 0.24 0.70 1.11
VA-204 (.24 x .70) 1.00 1.00 6.60 0.24 0.70 1.11
VB-302 (.13 x .45) 1.00 1.00 6.60 0.13 0.45 0.39

V-0.20 x 0.24 2.00 2.00 2.75 0.24 0.20 0.53

ingreso Tribuna Existente


corte A-A
VA-0.24 x 0.20 2.00 2.00 0.67 0.24 0.20 0.13
corte B-B
VA-0.24 x 0.20 2.00 2.00 1.10 0.24 0.20 0.21
corte C-C
VA-0.24 x 0.20 2.00 2.00 1.20 0.24 0.20 0.23
corte D-D
VA-0.24x0.40 1.00 2.00 7.05 0.24 0.40 1.35
corte 4-4
VA-0.24x0.40 1.00 2.00 0.84 0.24 0.20 0.08
corte 5-5
VA-0.24x0.40 1.00 2.00 0.84 0.24 0.20 0.08

ingreso estacionamiento
corte 2-2
V-2 1.00 1.00 2.41 0.24 0.20 0.12
corte A-A
V-2 1.00 2.00 1.55 0.24 0.20 0.15
corte B-B
V-2 1.00 2.00 0.99 0.24 0.20 0.10
corte 7-7
V-A, V-D 1.00 2.00 2.16 0.24 0.20 0.21
corte 8-8
V-A, V-D 1.00 2.00 2.76 0.24 0.20 0.26
Caseta
Eje 1G,2G
V1 (.13x.40) 2.00 1.00 0.53 0.13 0.34 0.05
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO
2.00 1.00 1.05 0.13 0.40 0.11
V2 (.13x.40) 2.00 1.00 1.83 0.13 0.40 0.19
V3 (.13x.40) 2.00 1.00 1.61 0.13 0.40 0.17
2.00 1.00 0.54 0.13 0.34 0.05
Corte 8-8
V4(Var.x.12) 1.00 1.00 2.63 0.50 0.12 0.16

Eje 1G',2G'
VB (.15xVar.) 2.00 1.00 6.11 0.15 0.30 0.55

Eje AG-AG, BG'-BG'


VB (.15xVar.) 2.00 2.00 0.47 0.15 0.30 0.08
1.00 1.00 1.73 0.15 0.30 0.08
1.00 1.00 2.17 0.15 0.30 0.10
Eje AG'-AG', BG-BG
V5'(.13x.40) 2.00 2.00 0.32 0.13 0.40 0.07
2.00 2.00 1.11 0.13 0.40 0.23

V6(.12xVar.) 4.00 1.00 1.31 0.52 0.12 0.33


4.00 1.00 0.46 0.52 0.12 0.11
Viguetas
VD (.13x.30)
Eje BG' 1.00 1.00 2.17 0.13 0.30 0.08
Eje 2G 1.00 1.00 0.83 0.13 0.30 0.03

VS (.13x.20)
Eje 2G 1.00 1.00 0.75 0.13 0.20 0.02
1.00 1.00 1.73 0.13 0.20 0.04
Eje AG 1.00 1.00 1.73 0.13 0.20 0.04
Eje AG' 1.00 1.00 1.21 0.13 0.20 0.03
Eje BG 1.00 1.00 1.09 0.13 0.20 0.03
Eje 1G 1.00 1.00 1.83 0.13 0.20 0.05

02.03.09.02 VIGAS.- ENCOFRADO Y DESENCOFRADO m caras 221.82

cerco perimtrico
cerco perimtrico tipo I, II, III, IV, V, VI
viga de amarre V-A 1.00 1.00 143.26 2.00 0.20 57.30

ingreso principal
VH-1 (.40 x .40) 1.00 4.00 4.50 2.40 43.20
VH-2 (.40 x .40) 1.00 4.00 4.50 2.40 43.20
VA-104 (.24 x .70) 1.00 1.00 6.60 2.00 0.70 9.24
VA-204 (.24 x .70) 1.00 1.00 6.60 2.00 0.70 9.24
VB-302 (.13 x .45) 1.00 1.00 6.60 2.00 0.45 5.94

V-0.20 x 0.24 2.00 2.00 2.75 2.00 0.20 4.40

ingreso Tribuna Existente


corte A-A
VA-0.24 x 0.20 2.00 2.00 0.67 0.40 1.07
corte B-B
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO
VA-0.24 x 0.20 2.00 2.00 1.10 0.40 1.76
corte C-C
VA-0.24 x 0.20 2.00 2.00 1.20 0.40 1.92
corte D-D
VA-0.24x0.40 1.00 2.00 7.05 0.40 5.64
corte 4-4
VA-0.24x0.40 1.00 2.00 0.84 0.40 0.67
corte 5-5
VA-0.24x0.40 1.00 2.00 0.84 0.40 0.67

ingreso estacionamiento
corte 2-2
V-2 1.00 1.00 2.41 0.40 0.96
corte A-A
V-A, V-D 1.00 2.00 1.55 0.40 1.24
corte B-B
V-2 1.00 2.00 0.99 0.40 0.79
corte 7-7
V-A, V-D 1.00 2.00 2.16 0.40 1.73
corte 8-8
V-A, V-D 1.00 2.00 2.76 0.40 2.21
Caseta
Eje 1G,2G
V1 (.13x.40) 2.00 1.00 0.53 2.00 0.22 0.47
2.00 1.00 1.05 2.00 0.28 1.17
V2 (.13x.40) 2.00 1.00 1.83 2.00 0.28 2.05
V3 (.13x.40) 2.00 1.00 1.61 2.00 0.28 1.81
2.00 1.00 0.54 2.00 0.22 0.47
Corte 8-8
V4(Var.x.12) 1.00 1.00 2.63 0.50 1.32
Eje 1G',2G'
VB (.15xVar.) 2.00 1.00 6.11 0.63 7.70
Eje AG-AG, BG'-BG'
VB (.15xVar.) 2.00 2.00 0.47 0.63 1.18
1.00 1.00 1.73 0.63 1.09
1.00 1.00 2.17 0.63 1.37
Eje AG'-AG', BG-BG
V5'(.13x.40) 2.00 2.00 0.32 2.00 0.28 0.72
2.00 2.00 1.11 2.00 0.28 2.50

V6(.12xVar.) 4.00 1.00 1.31 0.50 2.62


4.00 1.00 0.46 0.50 0.92
Viguetas
VD (.13x.30)
Eje BG' 1.00 1.00 2.17 2.00 0.30 1.30
Eje 2G 1.00 1.00 0.83 0.73 0.61
VS (.13x.20)
Eje 2G 1.00 1.00 0.75 2.00 0.20 0.30
1.00 1.00 1.73 2.00 0.20 0.69
Eje AG 1.00 1.00 1.73 2.00 0.20 0.69
Eje AG' 1.00 1.00 1.21 2.00 0.20 0.49
Eje BG 1.00 1.00 1.09 2.00 0.20 0.44
Eje 1G 1.00 1.00 1.83 2.00 0.20 0.73
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO

02.03.09.03 VIGAS.- ACERO f'y=4200 Kg/cm2 kg Cant L (m) Elemen. Coefic. 6,689.50
cerco perimtrico
cerco perimtrico tipo I, II, III, IV, V, VI
VA-1
ref. corrido 41/2" 2.00 313.98 4.00 0.99 2,486.72
estribos 1@0.05, 5@.10, 4@.15, rto .25 2.00 0.86 2,208.00 0.56 2,126.75

ingresos
ingreso principal

VH-1 (.40 x .40)


ref. horizontal 45/8" 4.00 4.50 4.00 1.55 111.60
ref. horizontal 83/8" 4.00 4.50 8.00 0.56 80.64
43/8" 1@0.05, 5@.10, rto .20 4.00 0.90 39.00 0.56 78.62

VH-2 (.40 x .40)


ref. horizontal 45/8" 4.00 4.50 4.00 1.55 111.60
ref. horizontal 83/8" 4.00 4.50 8.00 0.56 80.64
43/8" 1@0.05, 5@.10, rto .20 4.00 0.90 39.00 0.56 78.62

VA-104 (.24 x .70) 1.00 factor= 130.00 1.11 144.14


VA-204 (.24 x .70) 1.00 factor= 131.00 1.11 145.25
VB-302 (.13 x .45) 1.00 factor= 132.00 0.39 50.97

V-0.20 x 0.24
ref. horizontal 43/8" 4.00 3.25 4.00 0.56 29.12
43/8" 1@0.05, 5@.10, rto .20 4.00 0.76 21.00 0.56 35.75

ingreso Tribuna Existente

corte A-A
VA-0.24 x 0.20
ref. horizontal 41/2" 4.00 1.17 4.00 0.99 18.53
estribos 3/8" 1@0.05, 5@.10, rto .20 4.00 0.84 7.00 0.56 13.17

corte B-B
VA-0.24 x 0.20
ref. horizontal 41/2" 4.00 1.60 4.00 0.99 25.34
estribos 3/8" 1@0.05, 5@.10, rto .20 4.00 0.84 7.00 0.56 13.17

corte C-C
VA-0.24 x 0.20
ref. horizontal 41/2" 4.00 2.17 4.00 0.99 34.37
estribos 3/8" 1@0.05, 5@.10, rto .20 4.00 0.84 11.00 0.56 20.70

corte D-D
VA-0.24x0.40
ref. horizontal 41/2" 2.00 9.00 4.00 0.99 71.28
estribos 3/8" 1@0.05, 5@.10, rto .20 2.00 1.24 50.00 0.56 69.44
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO
corte 4-4
VA-0.24x0.20
ref. horizontal 41/2" 2.00 1.82 4.00 0.99 14.41
estribos 3/8" 1@0.05, 5@.10, rto .20 2.00 0.84 8.00 0.56 7.53

corte 5-5
VA-0.24x0.20
ref. horizontal 41/2" 2.00 1.82 4.00 0.99 14.41
estribos 3/8" 1@0.05, 5@.10, rto .20 2.00 0.84 8.00 0.56 7.53

ingreso estacionamiento

corte 2-2
V-2
ref. horizontal 41/2" 1.00 3.45 4.00 0.99 13.66
estribos 3/8" 1@0.05, 5@.10, rto .20 1.00 0.84 17.00 0.56 8.00

corte A-A
V-A, V-D
ref. horizontal 41/2" 1.00 2.50 4.00 0.99 9.90
estribos 3/8" 1@0.05, 5@.10, rto .20 1.00 0.84 17.00 0.56 8.00

corte B-B
V-A, V-D
ref. horizontal 41/2" 2.00 2.00 4.00 0.99 15.84
estribos 3/8" 1@0.05, 5@.10, rto .20 2.00 0.84 10.00 0.56 9.41

corte 7-7
V-A, V-D
ref. horizontal 41/2" 2.00 3.15 4.00 0.99 24.95
estribos 3/8" 1@0.05, 5@.10, rto .20 2.00 0.84 16.00 0.56 15.05

corte 8-8
V-A, V-D
ref. horizontal 41/2" 2.00 3.15 4.00 0.99 24.95
estribos 3/8" 1@0.05, 5@.10, rto .20 2.00 0.84 16.00 0.56 15.05
Caseta
Eje 1G
V1 (.13x.40)
ref. horizontal 41/2" 2.00 2.49 4.00 0.99 19.72
1@.05,resto @.15 c/e 2.00 1.02 10.00 0.56 11.42

V2 (.13x.40)
ref. horizontal 41/2" 2.00 2.49 4.00 0.99 19.72
estribos 3/8" 1@0.05, 7@.10, rto .25 2.00 1.02 18.00 0.56 20.56

V3 (.13x.40)
ref. horizontal 41/2" 2.00 2.49 4.00 0.99 19.72
1@.05,resto @.15 c/e 2.00 1.02 13.00 0.56 14.85

Eje 2G
V1 (.13x.40)
ref. horizontal 41/2" 2.00 2.49 4.00 0.99 19.72
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO
1@.05,resto @.15 c/e 2.00 1.02 10.00 0.56 11.42

V3 (.13x.40)
ref. horizontal 41/2" 2.00 2.49 4.00 0.99 19.72
1@.05,resto @.15 c/e 2.00 1.02 14.00 0.56 15.99

V2 (.13x.40)
ref. horizontal 41/2" 2.00 2.49 4.00 0.99 19.72
estribos 3/8" 1@0.05, 7@.10, rto .25 2.00 1.02 17.00 0.56 19.42

Corte 8-8
V4(Var.x.12)
ref. horizontal 41/2" 1.00 3.57 6.00 0.99 21.21
estribos 3/8" 1@0.05, 7@.10, rto .25 1.00 0.88 42.00 0.56 20.70

Eje 1G',2G'
VB (.15xVar.)
ref. horizontal 41/2" 2.00 6.43 4.00 0.99 50.94
estribos 3/8" 1@0.05, 7@.10, rto .25 2.00 0.88 10.00 0.56 9.86
estribos 3/8" 1@0.05, 7@.10, rto .25 c/e 2.00 0.88 18.00 0.56 17.74
estribos 3/8" 1@0.05, 7@.10, rto .25 c/e 2.00 0.88 17.00 0.56 16.76

Eje AG-AG, BG'-BG'


VB (.15xVar.)
ref. horizontal 41/2" 2.00 3.67 4.00 0.99 29.09
estribos 3/8" 1@0.05, 7@.10, rto .25 2.00 0.88 10.00 0.56 9.86
estribos 3/8" 1@0.05, 7@.10, rto .25 c/e 2.00 0.88 17.00 0.56 16.76

Eje AG'-AG', BG-BG


V5'(.13x.40)
ref. horizontal 41/2" 2.00 3.77 4.00 0.99 29.90
estribos 3/8" 1@0.05, 7@.10, rto .25 2.00 1.04 18.00 0.56 20.97
estribos 3/8" 1@0.05, rto.@10 2.00 1.04 4.00 0.56 4.66

V6(.12xVar.)
ref. horizontal 41/2" 4.00 2.57 6.00 0.99 61.05
estribos 3/8" 1@0.05, 7@.10, rto .25 4.00 0.88 32.00 0.56 63.08

Viguetas
VD (.13x.30)
Eje BG'
ref. horizontal 41/2" 1.00 1.79 4.00 0.99 7.10
estribos 3/8" 1@0.05, rto .15 c/e 1.00 0.84 9.00 0.56 4.23

Eje 2G
ref. horizontal 41/2" 1.00 1.60 4.00 0.99 6.35
estribos 3/8" 1@0.05, rto .15 c/e 1.00 0.84 6.00 0.56 2.82

VS (.13x.20)
Eje 2G
ref. horizontal 41/2" 1.00 1.37 4.00 0.99 5.41
estribos 3/8" 1@0.05, rto .15 c/e 1.00 0.64 6.00 0.56 2.15
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO
ref. horizontal 41/2" 1.00 2.28 4.00 0.99 9.03
estribos 3/8" 1@0.05, rto .15 c/e 1.00 0.64 13.00 0.56 4.66

Eje AG
ref. horizontal 41/2" 1.00 2.28 4.00 0.99 9.03
estribos 3/8" 1@0.05, rto .15 c/e 1.00 0.64 13.00 0.56 4.66

Eje AG'
ref. horizontal 41/2" 1.00 2.28 4.00 0.99 9.03
estribos 3/8" 1@0.05, rto .15 c/e 1.00 0.64 13.00 0.56 4.66

Eje AG'
ref. horizontal 41/2" 1.00 1.71 4.00 0.99 6.76
estribos 3/8" 1@0.05, rto .15 c/e 1.00 0.64 10.00 0.56 3.58

Eje BG
ref. horizontal 41/2" 1.00 1.71 4.00 0.99 6.76
estribos 3/8" 1@0.05, rto .15 c/e 1.00 0.64 10.00 0.56 3.58

02.03.12 CANALETA DE DRENAJE PLUVIAL EN TECHO


02.03.12.01 CANALETA.- CONCRETO f'c=210 Kg/cm2 m rea 1.01
Canaleta eje D-D,A-A 2.00 1.00 6.10 0.08 1.01

02.03.12.02 CANALETA.- ENCOFRADO Y DESENCOFRADO m 8.42


Perim.
Canaleta 1.00 1.00 1.38 6.10 8.42

02.03.12.03 CANALETA.- ACERO f'y=4200 Kg/cm2 kg 28.65


Densidad(Kg/m)
ref. longitudinal 8mm @ 0.20 1.00 6.00 6.10 0.40 14.64
ref. transversal 8mm @ 0.20 1.00 31.00 1.13 0.40 14.01

02.03.13 LOSA MACIZA


02.03.13.01 LOSA MACIZA.- CONCRETO f'c=210 Kg/cm2 m 3.02

2.00 2.88 3.88 0.12 2.68


1.00 2.37 0.61 0.12 0.17
1.00 2.37 0.61 0.12 0.17

02.03.13.02 LOSA MACIZA.- ENCOFRADO Y DESENCOFRADO m 25.20


2.00 2.88 3.88 22.32
1.00 2.37 0.61 1.44
1.00 2.37 0.61 1.44

02.03.13.03 LOSA MACIZA.- ACERO f'y=4200 Kg/cm2 kg 121.32


refuerzo logitudinal 3/8" @0.25m 1.00 2.00 2.08 10.00 0.56 23.30
1.00 2.00 2.77 7.00 0.56 21.72
refuerzo transversal 3/8" @0.25m 1.00 2.00 5.47 7.00 0.56 42.88
refuerzo logitudinal 3/8" @0.25m 1.00 2.00 2.15 7.00 0.56 16.82
refuerzo transversal 3/8" @0.25m 1.00 2.00 2.47 6.00 0.56 16.60
SUSTENTO DE METRADOS DE ESTRUCTURAS

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO
SUSTENTO DE METRADOS DE ARQUITECTURA

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO

03 ARQUITECTURA

03.01 MUROS Y TABIQUES


03.01.01 MURO DE LADRILLO KK TIPO IV SOGA M:1:1:4 E=1.5 cm m 798.46
cerco perimtrico
tipo I 1.00 17.00 8.19 2.90 403.77
tipo II 1.00 1.00 3.72 5.34 19.86
1.00 1.00 2.20 3.92 8.62
tipo III 1.00 1.00 5.52 5.35 29.53
tipo IV 1.00 1.00 6.24 3.36 20.97
tipo V 1.00 3.00 8.96 4.02 108.06
tipo VI 1.00 8.00 6.24 2.85 142.27
tipo VII 1.00 1.00 9.24 3.40 31.42
caseta
Eje 1G 1.00 1.00 1.73 2.80 4.84
1.00 1.00 1.83 2.30 4.21
1.00 1.00 1.00 1.20 1.20
Eje 2G 1.00 1.00 1.73 2.80 4.84
1.00 1.00 0.75 2.80 2.10
1.00 1.00 1.00 2.80 2.80
entre eje 1G-2G 1.00 1.00 1.00 2.80 2.80
Eje AG 1.00 1.00 1.77 1.20 2.12
Entre eje AG-BG 1.00 1.00 1.21 2.80 3.39
Eje BG 1.00 1.00 1.09 2.80 3.05
Eje BG' 1.00 1.00 2.17 1.20 2.60

03.01.02 MURO DE LADRILLO KK TIPO IV CABEZA M:1:1:4 E=1.5 cm m 45.35

ingresos
ingreso primaria
corte D-D 1.00 2.00 2.45 2.52 12.35
1.00 1.00 2.16 2.52 5.44
1.00 2.00 2.45 0.60 2.94
corte A-A 1.00 1.00 0.67 1.10 0.74
1.00 1.00 0.67 2.20 1.47
corte B-B 1.00 1.00 0.62 1.10 0.68
1.00 1.00 0.62 2.20 1.36
corte C-C 1.00 1.00 1.19 1.10 1.31
1.00 1.00 1.19 2.20 2.62

ingreso Tribuna Existente


corte A-A 1.00 1.00 1.53 1.10 1.68
1.00 1.00 1.53 2.20 3.37
corte B-B 1.00 1.00 0.99 1.10 1.09
1.00 1.00 0.99 2.20 2.18

ingreso Estacionamiento
corte D-D 1.00 1.00 1.69 2.64 4.46
1.00 2.00 0.87 2.10 3.65

03.01.05 ALAMBRE N8 REFUERZO HORIZONTAL EN MUROS kg 675.05


SUSTENTO DE METRADOS DE ARQUITECTURA

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO

ver metrado de muros


muro de soga 1.00 1.00 798.46
muro de cabeza 1.00 1.00 45.35
factor a usar 0.80 843.81
675.05

03.02 REVOQUES Y REVESTIMIENTOS

03.02.01 TARRAJEO MUROS INT.FROTACHADO MEZ.C:A 1:4,E=1.5 CM. m caras 1,687.62

cerco perimtrico
cerco perimtrico
tipo I 1.00 17.00 8.19 2.00 2.90 807.53
tipo II 1.00 1.00 3.72 2.00 5.34 39.73
1.00 1.00 2.20 2.00 3.92 17.25
tipo III 1.00 1.00 5.52 2.00 5.35 59.06
tipo IV 1.00 1.00 6.24 2.00 3.36 41.93
tipo V 1.00 3.00 8.96 2.00 4.02 216.12
tipo VI 1.00 8.00 6.24 2.00 2.85 284.54
tipo VII 1.00 1.00 9.24 2.00 3.40 62.83

Ingresos
ingreso primaria
corte D-D 1.00 2.00 2.45 2.00 2.52 24.70
1.00 1.00 2.16 2.00 2.52 10.89
1.00 2.00 2.45 2.00 0.60 5.88
corte A-A 1.00 1.00 0.67 2.00 1.10 1.47
1.00 1.00 0.67 2.00 2.20 2.95
corte B-B 1.00 1.00 0.62 2.00 1.10 1.36
1.00 1.00 0.62 2.00 2.20 2.73
corte C-C 1.00 1.00 1.19 2.00 1.10 2.62
1.00 1.00 1.19 2.00 2.20 5.24

ingreso Tribuna Existente


corte A-A 1.00 1.00 1.53 2.00 1.10 3.37
1.00 1.00 1.53 2.00 2.20 6.73
corte B-B 1.00 1.00 0.99 2.00 1.10 2.18
1.00 1.00 0.99 2.00 2.20 4.36

ingreso Estacionamiento
corte D-D 1.00 1.00 1.69 2.00 2.64 8.92
1.00 2.00 0.87 2.00 2.10 7.31
caseta
Eje 1G 1.00 1.00 1.73 2.00 2.80 9.69
1.00 1.00 1.83 2.00 2.30 8.42
1.00 1.00 1.00 2.00 1.20 2.40
Eje 2G 1.00 1.00 1.73 2.00 2.80 9.69
1.00 1.00 0.75 2.00 2.80 4.20
1.00 1.00 1.00 2.00 2.80 5.60
entre eje 1G-2G 1.00 1.00 1.00 2.00 2.80 5.60
Eje AG 1.00 1.00 1.77 2.00 1.20 4.25
Entre eje AG-BG 1.00 1.00 1.21 2.00 2.80 6.78
Eje BG 1.00 1.00 1.09 2.00 2.80 6.10
Eje BG' 1.00 1.00 2.17 2.00 1.20 5.21
SUSTENTO DE METRADOS DE ARQUITECTURA

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO

03.02.03 TARRAJEO EN COLUMNAS C:A 1:4 E=1.5 cm. m 1,069.39


cerco perimtrico
columnas
cerco perimtrico tipo I, II, III, IV, V, VI 1.00 120.00 1.08 4.85 628.56

ingresos
ingreso principal
C-0.40x1.00
corte 1-1 4.00 1.00 4.60 3.45 63.48
corte 2-2 4.00 1.00 6.20 6.40 158.72

C-0.24x1.00 1.00 2.00 2.48 5.00 24.80


C-0.24x0.24 1.00 2.00 0.96 5.00 9.60

ingreso Tribuna Existente


C1-24x24 1.00 13.00 0.96 3.70 46.18
C2-52x24 1.00 2.00 1.52 6.95 21.13
C3 1.00 2.00 2.71 6.95 37.67

ingreso Estacionamiento
C1-24x24 1.00 8.00 0.96 5.10 39.17
Caseta
C1 1.00 4.00 1.10 3.33 14.65
C2 1.00 2.00 1.54 3.33 10.26
CA-1 1.00 6.00 0.76 3.33 15.18

03.02.04 TARRAJEO EN VIGAS C:A 1:4 E=1.5 cm. m caras 198.99


cerco perimtrico
cerco perimtrico tipo I, II, III, IV, V, VI
viga de amarre V-A 1.00 1.00 162.75 2.00 0.20 65.10

ingreso principal
VH-1 (.40 x .40) 1.00 4.00 4.50 2.40 43.20
VH-2 (.40 x .40) 1.00 4.00 4.50 2.40 43.20
VA-104 (.24 x .70) 1.00 1.00 6.60 2.00 0.70 9.24
VA-204 (.24 x .70) 1.00 1.00 6.60 2.00 0.70 9.24
VB-302 (.13 x .45) 1.00 1.00 6.60 2.00 0.45 5.94

V-0.20 x 0.24 2.00 2.00 2.75 2.00 0.20 4.40

ingreso Tribuna Existente


corte A-A
VA-0.24 x 0.20 2.00 2.00 0.67 0.40 1.07
corte B-B
VA-0.24 x 0.20 2.00 2.00 1.10 0.40 1.76
corte C-C
VA-0.24 x 0.20 2.00 2.00 1.20 0.40 1.92
corte D-D
VA-0.24x0.40 1.00 2.00 7.05 0.40 5.64
SUSTENTO DE METRADOS DE ARQUITECTURA

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO

corte 4-4
VA-0.24x0.40 1.00 2.00 0.84 0.40 0.67
corte 5-5
VA-0.24x0.40 1.00 2.00 0.84 0.40 0.67

ingreso Estacionamiento
corte 2-2
V-2 1.00 1.00 2.41 0.40 0.96
corte A-A
V-A, V-D 1.00 2.00 1.55 0.40 1.24
corte B-B
V-2 1.00 2.00 0.99 0.40 0.79
corte 7-7
V-A, V-D 1.00 2.00 2.16 0.40 1.73
corte 8-8
V-A, V-D 1.00 2.00 2.76 0.40 2.21

03.02.09 VESTIDURA DE DERRAMES e=0.26 m 175.75


cerco perimtrico
cerco perimtrico tipo I, II, III, IV, V, VI 1.00 1.00 162.75 162.75
ingresos
ingreso principal 2.00 2.00 3.25 13.00

03.09 CARPINTERIA METALICA Y HERRERIA

03.09.01 PUERTAS Y VENTANAS METALICAS

03.09.01.01 REJA DE Fe 2.40 x 4.20 und 1.00


ingresos
ingreso principal 1.00 1.00 1.00

03.09.01.02 REJA DE Fe 2.60 x 1.80 und 2.00


ingresos
ingreso tribuna existente 1.00 2.00 2.00

03.09.01.04 REJA DE Fe 2.70 x 2.15 und 1.00


ingreso estacionamiento 1.00 1.00 1.00

03.09.03 BARANDAS REJAS Y TUBOS


MALLA ELECTROSOLDADA GALVANIZADA CON COCADA DE 2"x2"
03.09.03.02 m 90.50
h=2.00m
cerco perimtrico sobre MC-13 1.00 1.00 45.25 2.00 90.50

03.09.04 ELEMENTOS METALICOS ESPECIALES


03.09.03.08 REJA METALICA EN CERCO PERIMETRICO (h=1.00m) m 12.46
ingresos
ingreso principal 1.00 2.00 2.73 5.46
ingreso tribuna existente 1.00 4.00 0.80 3.20
ingreso estacionamiento 1.00 2.00 1.25 2.50
1.00 2.00 0.65 1.30

03.09.03.09 REJA METALICA EN CERCO PERIMETRICO (h=1.60m) m 17.36


ingresos
SUSTENTO DE METRADOS DE ARQUITECTURA

PROYECTO Cercos e Ingresos


I.E. NUESTRA SEORA DE LAS MERCEDES PAB. OE
UBICACIN AYACUCHO - HUAMANGA - AYACUCHO FECHA Dec-13
PROYEC. ING. PATRICK RICARDO VALDIVIA ORREGO
METRADO ING. ELIBERTO RUIZ VILLANUEVA

DIMENSIONES
ITEM DESCRIPCION UND CANT. ELEM. PARCIAL TOTAL
LARGO ANCHO ALTO

ingreso principal 1.00 2.00 2.73 5.46


ingreso tribuna existente 1.00 4.00 0.80 3.20
1.00 2.00 2.45 4.90
ingreso estacionamiento 1.00 2.00 1.25 2.50
1.00 2.00 0.65 1.30

03.12 PINTURA
PINTURA MUROS Y COLUMNAS INTERIORES C/LATEX (02
03.12.01 m 2,802.71
MANOS)
Muros Interiores 1.00 1.00 1,687.62
Columnas 1.00 1.00 1,069.39
1.00 1.00 175.75 0.26 45.70

PINTURA CIELORASO Y VIGAS C/LATEX (02 MANOS) INC.


03.12.03 m 221.82
ANDAMIO
Vigas 1.00 1.00 221.82