PETROLEOS MEXICANOS

NOBLE TOM JOBE


CALCULO DE TONELADAS - KILOMETROS
DAT O S G E N E RALE S

FECHA 4-Jun-11
DENS. 1.99 GR /CC LONG. DE LING. 28.5 MTS.
PROFUNDIDAD 5489 MTS. PESO AJ. D. COLLAR 137.08 KG / MT
PESO DEL BLOCK Y KELLY 40909 KGS. LONG. DE D. COLLAR 52.78 MTS

DATOS DE TUBERIA DE PERFORACION


TUBERIA DE PERFN. Y HW LB / FT KG / MT LONG. FACOR DE FLOT. AIRE FLOTADA
d/ collar 6 1/2" 92 137.08 52.78 0.746 7235.08 5400.97
hw 5" 50 74.50 256.57 0.746 19114.47 14268.89
tp 5" s 135 19.5# 19.5 29.06 2374.65 0.746 68995.46 51504.89
tp 5" g-105 25.6# 25.6 38.14 662.76 0.746 25280.32 18871.68
tp 5" -135 25.6# 25.6 38.14 2142.24 0.746 81713.60 60998.94
0.746 0.00 0.00
0.746 0.00 0.00
5541.78 202338.92 151045.36
PESO PROM. TP. FLOT.= 27.25575 KG /MT. PESO PROM. DE TP = 36.51 KG /MT
PESO D. COLLAR FLOT, = 5400.966 KGS. PESO D. COLLAR AIRE 7235.0824 KGS.
3962.4075658428 1767.15285166

PERFORANDO VIAJE REDONDO


PROF. DONDE INICIO A PERFORAR = 5430 MTS.
1739.426 VIAJE REDONDO = 1767.15 TON - KM
1098.11 TON - MILL
PERFORANDO = 83.18 TON -KM VIAJE SENCILLO = 883.58 TON - KM
51.69 TON - MILL 549.05 TON - MILL

CORRIENDO LINER VIAJE CORTO


PESO UNITARIO DEL LINER = 0 KG /MT. PROF. DEL V. CORTO 5194 MTS.
LONG. DEL LINER = 0 MTS. LONG. DEL V. CORTO 127 MTS.
LONG. DEL SOLTADOR = 0 MTS. PESO PROM. FLOT. TP 27.26 KG / MT.
0 -36.5115 102.3297834395 3962.40756584
CORRIENDO LINER = 859.49 TON-KM V. CORTO REDONDO = 22.33 TON - KM
534.0899 TON-MILL 13.87 TON - MILL
FACT V. CORTO SENCILLO = 11.16 TON - KM.
TON-KM A TON-MILLA X 0.6214 6.94 TON - MILL

Page 1
Sheet B

PETROLEOS MEXICANOS
N CARL NRBERGER
CALCULO DE TONELADAS - KILOMETROS
DATOS GE NE RALE S

FECHA 24-Feb-10
DENS. 1.33 GR /CC LONG. DE LING. 28.5 MTS.
PROFUNDIDAD 5141 MTS. PESO AJ. D. COLLAR 74.5 KG / MT
PESO DEL BLOCK Y KELLY 70000 KGS. LONG. DE D. COLLAR 65 MTS

DATOS DE TUBERIA DE PERFORACION


TUBERIA DE PERFN. Y HW LB / FT KG / MT LONG. FACOR DE FLOT. AIRE FLOTADA
TUBERIA 3 1/2" HW. 26 38.74 170.04 0.831 6587.35 5471.28
TUBERIA 3 1/2 G 15.5 15.5 23.10 749.76 0.831 17315.71 14381.96
TUBERIA 3 1/2 S 15.5 15.5 23.10 735.16 0.831 16978.52 14101.90
TUBERIA 5" X 25.6 25.6 38.14 400.79 0.831 15287.73 12697.58
TUBERIA 5" S 19.5 19.5 29.055 1855.61 0.831 53914.75 44780.15
TUBERIA 5" G 25.6 25.6 38.144 596.44 0.831 22750.61 18896.05
TUBERIA 5" S 25.6 25.6 38.144 503.2 0.831 19194.06 15942.07
5076 152028.73 126270.99
PESO PROM. TP. FLOT.= 24.87608 KG /MT. PESO PROM. DE TP = 29.95 KG /MT
PESO D. COLLAR FLOT, = 4022.051 KGS. PESO D. COLLAR AIRE 4842.5 KGS.
2405.1056024407 2125.32599842

PE RFORANDO V IAJE RE DONDO


PROF. DONDE INICIO A PERFORAR = 4588 MTS.
1833.597 VIAJE REDONDO = 2125.33 TON - KM
1320.68 TON - MILL
PERFORANDO = 875.19 TON -KM VIAJE SENCILLO = 1062.66 TON - KM
543.84 TON - MILL 660.34 TON - MILL

CORRIENDO LINER VIAJE CORTO


PESO UNITARIO DEL LINER = 0 KG /MT. PROF. DEL V. CORTO 5048 MTS.
LONG. DEL LINER = 0 MTS. LONG. DEL V. CORTO 93 MTS.
LONG. DEL SOLTADOR = 0 MTS. PESO PROM. FLOT. TP 24.88 KG / MT.
0 -29.9505 61.8777070064 2405.10560244
CORRIENDO LINER = 1048.32 TON-KM V. CORTO REDONDO = 26.77 TON - KM
651.4273 TON-MILL 16.63 TON - MILL
FACT V. CORTO SENCILLO = 13.38 TON - KM.
TON-KM A TON-MILLA X 0.6214 8.32 TON - MILL

Page 2