Está en la página 1de 3

Project: 2 storey Residential Meditterreanean Style

Location Ilocos
Owner: Mr. Giovanni

Bill of Quantities
Material Labor
Items Quantity Unit TOTAL AMOUNT
Unit Cost Amount Unit Cost Amount Total Unit Cost

STRUCTURAL
Excavation 20.00 cu.m. 350.00 7,000.00 350.00 7,000.00
Hauling 20.00 cu.m. 350.00 7,000.00 350.00 7,000.00
14,000.00
1. Concrete (5000psi)
a. Slabs 23.00 cu.m. 4,200.00 96,600.00 800.00 18,400.00 5,000.00 115,000.00
b. Column 7.90 cu.m. 4,200.00 33,180.00 800.00 6,320.00 5,000.00 39,500.00
c. Beams 10.43 cu.m. 4,200.00 43,806.00 800.00 8,344.00 5,000.00 52,150.00
d. Footing 10.40 cu.m. 4,200.00 43,680.00 800.00 8,320.00 5,000.00 52,000.00
258,650.00
2. Rebar
a. 10mm dia 1,220.00 kgs 33.00 40,260.00 7.00 8,540.00 40.00 48,800.00
b. 12mm dia 1,460.00 kgs 33.00 48,180.00 7.00 10,220.00 40.00 58,400.00
c. 16mm dia 1,490.00 kgs 33.00 49,170.00 7.00 10,430.00 40.00 59,600.00
d. 20mm dia 1,950.00 kgs 33.00 64,350.00 7.00 13,650.00 40.00 78,000.00
244,800.00
3. Formworks
a. 1 lot 50,000.00
50,000.00
4. Wall

Interior and Exterior Wall (CHB) including


plastering 194.00 sqm 500.00 97,000.00 200.00 38,800.00 700.00 135,800.00
135,800.00

ARCHITECTURAL
1. Wall
Painting 388.00 sqm 350.00 388.00 included included 350.00 122,500.00

Exterior wall stone cladding 100.00 sqm 1,200.00 120,000.00 300.00 30,000.00 1,500.00 150,000.00
272,500.00

2. Ceiling
Gypsum board installation
Moisture resistant (t&b) 11.00 sqm 400.00 4,400.00 300.00 3,300.00 700.00 7,700.00
Fire resistant for Kitchen 16.00 sqm 400.00 6,400.00 300.00 4,800.00 700.00 11,200.00
Painting (plastered ceiling) 85.00 sqm 350.00 29,750.00 350.00 29,750.00
48,650.00

3. Tiles

30x30 t&b floor tiles (assuming Php 40 tile/pc) 12.00 sqm 500.00 6,000.00 300.00 3,600.00 800.00 9,600.00
30x30 t&b wall tiles (900 mm ht) (assuming
Php 40 tile/pc) 24.00 sqm 500.00 12,000.00 300.00 7,200.00 800.00 19,200.00

60x60 floor tiles (assuming Php 140 tile/pc) 85.00 sqm 450.00 38,250.00 300.00 25,500.00 750.00 63,750.00

Gazebo and Outdoor area (pavers) 14.00 sqm 25.00 350.00 300.00 4,200.00 325.00 4,550.00
97,100.00
4. Window
Window for Stairs 6.00 sets 6,000.00 6,000.00 36,000.00
Resl windows 10.00 sets 8,000.00 8,000.00 80,000.00
T&b windows 5.00 sets 3,000.00 3,000.00 15,000.00
131,000.00
5. Doors
Main door 1.00 set 15,000.00 15,000.00 included included 15,000.00 15,000.00
Bedroom Doors 4.00 set 3,000.00 12,000.00 included included 3,000.00 12,000.00
Sliding Doors 4.00 set 10,000.00 40,000.00 included included 10,000.00 40,000.00
Gazebo door 4.00 set 3,000.00 12,000.00 included included 3,000.00 12,000.00
T&b door 5.00 set 2,000.00 10,000.00 included included 2,000.00 10,000.00
89,000.00

6. Roofing
Roof tiles 1.00 lot 50,000.00 50,000.00
Purlins and trusses 1.00 lot 50,000.00 50,000.00
100,000.00
ELECTRICAL

( assumed cost only since no elecl plan yet)


1. Wires and cables 1.00 lot included 50,000.00
Panel Board included included
Switches included included
Conduits included included
Lighting (receptacle and light) included included
Material Labor
Items Quantity Unit TOTAL AMOUNT
Unit Cost Amount Unit Cost Amount Total Unit Cost
50,000.00

PLUMBING AND SANITARY

1.PPR (potable water)


2. PVC (sewer/soil)
3. Water meter
4. Valves and Fittings 50,000.00
5. Fixtures (hcg or similar brands)
Water closet 5.00 set 5,000.00 25,000.00 500.00 2,500.00 5,500.00 27,500.00
lavatory 5.00 set 2,000.00 10,000.00 500.00 2,500.00 2,500.00 12,500.00
faucet 5.00 set 1,500.00 7,500.00 500.00 2,500.00 2,000.00 10,000.00
Shower 5.00 set 5,000.00 25,000.00 500.00 2,500.00 5,500.00 27,500.00
kitchen sink 2.00 set 2,000.00 4,000.00 500.00 1,000.00 2,500.00 5,000.00
faucet 3.00 set 2,000.00 6,000.00 500.00 1,500.00 2,500.00 7,500.00
90,000.00
140,000.00
MECHANICAL

1. Exhaust fan ( for t&b) 5.00 set 1,000.00 5,000.00 300.00 1,500.00 1,300.00 6,500.00
2. ACU (roughing ins) for bedrooms 5.00 set 1,000.00 5,000.00
11,500.00

METAL WORKS
Stair Railings 12.00 m 2,500.00 30,000.00
Nosing 15.00 sets 500.00 7,500.00
37,500.00

TOTAL CONSTRUCTION COST 1,680,500.00

Additional Items
Generator set 1.00 lot 40,000.00 40,000.00
Elevated Water Tank 1.00 lot 100,000.00 100,000.00

Swimming Pool incl. Quartzon floor and wall


finish, mosaic tiles, sandstone pool,
1.00 lot 900,000.00 900,000.00
waterproofing complete pipings,
electromechanical, surge tank

1,040,000.00

Prepared by:
Arch Alain Mel Crescini-Liwag
Material Labor
Items Quantity Unit TOTAL AMOUNT
Unit Cost Amount Unit Cost Amount Total Unit Cost

SUMMARY

STRUCTURAL
Excavation Hauling 14,000.00

1. Concrete (5000psi)
258,650.00
2. Rebar
244,800.00
3. Formworks
50,000.00
4. Wall
Interior and Exterior Wall (CHB) including plastering 135,800.00

ARCHITECTURAL
1. Wall
272,500.00

2. Ceiling
48,650.00

3. Tiles
97,100.00
4. Window
131,000.00
5. Doors
89,000.00

6. Roofing
100,000.00
ELECTRICAL
50,000.00

PLUMBING AND SANITARY

140,000.00
MECHANICAL

11,500.00
METAL WORKS
37,500.00

TOTAL CONSTRUCTION COST 1,680,500.00

Additional Items
Generator set 1.00 lot 40,000.00 40,000.00
Elevated Water Tank 1.00 lot 100,000.00 100,000.00

Swimming Pool incl. Quartzon floor and wall


finish, mosaic tiles, sandstone pool,
1.00 lot 900,000.00 900,000.00
waterproofing complete pipings,
electromechanical, surge tank

1,040,000.00

Prepared by:
Arch Alain Mel Crescini-Liwag

También podría gustarte