Está en la página 1de 12

citb.co.

uk

Health, safety and


environment test
For plumbing specialists (JIB)

GT 100
Official CITB
publication

2015
Introduction
About this booklet...........................................................................................................................2
What is included in this booklet?............................................................................................2
What is not included in this booklet?......................................................................................2
Revision material............................................................................................................................3
Where can I buy the revision book?.......................................................................................3
Why do I need to use a 2015 edition book?...........................................................................3 Introduction
Can I use a 2014 edition book?..............................................................................................3
What is in the different revision material formats?.................................................................4 Contents
What is on the DVD and download?.......................................................................................4 About this booklet 2
What is included in this booklet? 2
Where can I buy Safe start?...................................................................................................4
What is not included in this booklet? 2
How can I book a test?...................................................................................................................4
Revision material 3
Specialist plumbing (JIB) Where can I buy the revision book? 3
Test questions (GT 100) Why do I need to use a 2015 edition book? 3
Can I use a 2014 edition book? 3
Specialist plumbing (JIB) test questions........................................................................................6
What is in the different revision material
Safe start (GE 707) formats? 4
Introduction to Safe start (GE 707)..............................................................................................15 What is on the DVD and download? 4
Safe methods of working Safe start (GE 707)..........................................................................15 Where can I buy Safe start? 4

Contact information and useful links How can I book a test? 4

Contact information and useful links............................................................................................18

1
Introduction

About this booklet Revision material


This revision booklet is a companion product to the Health, safety and environment The revision material was fully reviewed before the launch of the new edition in
test revision material book (GT 100/15) to enable people to prepare for the Health, April 2015. A number of changes have been made including:
safety and environment specialist plumbing (JIB) test. new knowledge questions on Construction (Design and Management)

When you take your Health, safety and environment specialist plumbing (JIB) test Regulations 2015
you will be asked: revisions to the environment questions

12 behavioural case study questions
substantial changes to the core knowledge questions.

32 core knowledge questions

Where can I buy the revision book?
6 plumbing specialist activity questions.

CITB has developed a range of publications that present a detailed and
What is included in this booklet? comprehensive guide to the full range of topics covered in the test. They can be used
This revision booklet contains the following: to build awareness and understanding of the issues surrounding health and safety
on a construction site. They provide the context for the questions that are asked. To
all the plumbing (JIB) specialist activity questions and answers
 revise effectively for the test you should use the latest edition of the revision material.
plumbing information from the GE 707/14 (Safe start) publication. For further information and to buy these products:
Safe start (GE 707) provides easy to understand health, safety and environment
information. It supports operatives and specialists who are preparing for the CITB @ go online at www.citb.co.uk/hsanderevision
Health, safety and environment test through providing all the information that they
need to pass the test.
citb.co.uk citb.co.uk Why do I need to use a 2015 edition book?
C M

What is not included in this booklet Y


PMS ???
K

The new revision book was published in April 2015.


PMS ???
PMS ???
Health, safety and environment test
Health, safety and

Health, safety and environment test


PMS ???

This revision booklet does not contain the core knowledge section questions. You
Non-printing
For operatives and specialists
environment test
You will need this edition to prepare for tests taken after
Colours
COLOUR
The CITB Health, safety and environment test forms a key part of the requirement to obtain
COLOUR
a construction industry competency card. The test continues to be a vital tool in helping the
For operatives and specialists JOB LOCATION:

will need to prepare for the core knowledge questions as well as the plumbing (JIB)
industry to improve its health, safety and environmental standards. PRINERGY 3

31st May 2015 because of the level of changes which have


This revision book contains everything you need to know to book, prepare for and sit the Health,
safety and environment test for operatives and specialists including:
all the questions and answers

specialist activity questions.


the transcript from the Setting out film that supports the new behavioural case studies.
If you are preparing for the operative test there are five core knowledge sections to revise:
A: Legal and management
B: Health and welfare
D: High risk activities
E: Environment.
GT 100
Official CITB
been made to the core knowledge questions.
C: General safety publication

We do not publish the behavioural case studies because they are designed to test There are specialist tests, supported by their own additional specialist activity questions,
in the following areas:
supervisory lifts and escalators
2015

how you respond to health and safety situations on a construction site. They are
demolition tunnelling
highway works heating, ventilation,

For operatives and specialists


specialist work at height air conditioning and
refrigeration (HVACR).

based on the principles established in Setting out what you should expect from
There is also a revision DVD and a download available, which offers the
chance to work through the whole question bank, watch the film and
complete simulated tests. You can also revise using the smartphone app.
Separate publications support the Health, safety and environment

a site and what they expect from you. You should watch this film as part of your
test for managers and professionals so please ensure that you are
revising for the right test.

preparation: ISBN 978-1-85751-415-5


For more information on the test, to book
a test or to buy publications contact:

@ citb.co.uk/hsandetest

GT 100/15
0344 994 4488

@
9 781857 514155

go online at http://www.citb.co.uk/settingout
04/15

RRP 10.95

CSK-GT100-2015-Cover.indd 1 09/02/2015 15:14

citb.co.uk citb.co.uk Can I use a 2014 edition book?


C M

Y K
PMS ???
PMS ???

Health, safety and environment test


For operatives and specialists
Health, safety and environment test
Health, safety and The 2014 edition book can only be used if you are taking
PMS ???
PMS ???
Non-printing
Colours

environment test
your test before 31st May 2015. The 2014 book contains
Non-print 1
Non-print 2
The CITB Health, safety and environment test forms a key part of the requirement to obtain
JOB LOCATION:
a construction industry competency card. The test continues to be a vital tool in helping the
industry to improve its health, safety and environmental standards. For operatives and specialists PRINERGY 3

This revision book contains everything you need to know to book, prepare for and sit the Health,
safety and environment test for operatives and specialists including:


all the questions and answers
the transcript from the Setting out film that supports the new behavioural case studies.
the plumbing specialist (JIB). A revised test will be launched
If you are preparing for the operative test there are five core knowledge sections to revise:
A: Legal and management
B: Health and welfare
D: High risk activities
E: Environment.
GT 100
Official CITB
from 1st June 2015 after which the 2014 revision materials
become obsolete.
C: General safety publication
There are specialist tests, supported by their own additional specialist activity questions,
in the following areas: 2014
supervisory lifts and escalators
demolition tunnelling
plumbing or gas heating, ventilation, air
For operatives and specialists

highway works conditioning and refrigeration


(HVACR).
specialist work at height
There is also a revision DVD and a download available, which offers
the chance to work through the whole question bank, watch the film
and complete simulated tests. You can also revise using the
smartphone app.
Separate publications support the Health, safety
and environment test for managers and professionals so please
ensure that you are revising for the right test.

ISBN 978-1-85751-343-1
For more information on the test, to book
a test or to buy publications contact:

@ citb.co.uk/hsandetest
GT 100/14

0344 994 4488.


9 781857 513431 01/14

RRP 10.95

CSK-GT100-2014-Op-COV.indd 1 15/11/2013 13:41

2 3
Introduction

What is in the different revision material formats?

The revision material is available in a variety of formats. The table below outlines
what is available on which format of the 2015 edition of the revision material for the
Health, safety and environment test for plumbing specialists (JIB).

Does it contain the core Does it contain the plumbing


knowledge questions? specialist (JIB) questions?
Book Yes No
Specialist
DVD Yes Yes run a patch
plumbing (JIB)
Download Yes Yes run the update Contents
App Yes Yes run the update Test questions (GT 100)
Specialist plumbing (JIB) test questions 6

What is on the DVD and download? Safe start (GE 707)


The DVD and download offer an interactive package that includes: Introduction to Safe start (GE 707) 15
Safe methods of working Safe start (GE 707) 15
the Setting out film and a sample behavioural case study

all the knowledge questions in both book and practice formats

the real test tutorial

a test simulator all the functionality of the test with the real question bank.


Where can I buy Safe start?

Safe start provides easy to understand health, safety and environment information
along with practical guidance. Safe start supports specialists preparing for the
Health, safety and environment specialist plumbing (JIB) test by providing supporting
information you will require. You can buy publications online at www.shop.citb.co.uk
or call 0344 994 4122.

How can I book a test?


The easiest way to book your test is online or by telephone. You will be given the date
and time of your test immediately and offered the opportunity to buy revision material,
such as books, DVDs, downloads and apps. You should be able to book a test at
your preferred location within two weeks.
Contact information for how to book your test is on page 18 of this booklet.

4 5
Specialist plumbing (JIB)

4 7 10
Specialist plumbing (JIB)
You have been handling sheet lead. When bossing a sheet lead corner You are drilling a hole through a metal
How is some lead most likely to get in using lead-working tools, you: partition to receive a 15 mm pipe
your bloodstream? from a radiator. You need to wear eye
1 A are allowed to smoke during the
protection:
A By not using the correct respirator bossing process
While climbing a ladder, a colleague A when drilling overhead only
slips and falls about 2 m. They are B By not washing your hands B should not smoke during the
lying on the ground saying that their before eating bossing process B when the drill bit exceeds 20 mm
back hurts. What is the first thing that C By not changing out of your C should only smoke when your C always, whatever the
you should do? work clothes hands are protected with circumstances
A Go and put it in the accident book barrier cream
D By not wearing safety goggles D when drilling through concrete only
B Help them get up D are allowed to smoke if you are
5 wearing gloves 11
C Tell them to lie still and send
someone else to get a first aider The legionella bacteria that cause In plumbing work, what part of the
8
D Make sure there is nothing wrong legionnaires disease are most body could suffer long-term damage
with the ladder likely to be found in which of If breaking up a cast iron bath, which when hand bending copper pipe using
the following? of the following is the proper way to an internal spring?
2 protect your hearing?
A A boiler operating at a temperature A Elbows
of 80C A A portable stereo and head set
When using a blowtorch near to flexible B Hands
pipe lagging, you should: B A shower hose outlet B Cotton wool pads
C Back
A just remove enough lagging to C A cold water storage cistern C Ear defenders
carry out the work D Knees
containing water at 10C
D Rolled-up tissue paper
B remove the lagging at least 1 m D A WC toilet pan 12
either side of the work
9
6 When repairing a burst water main
C remove the lagging at least 3 m
either side of the work What item of personal protective using pipe-freezing equipment to
How are legionella bacteria passed on equipment (PPE), from the following isolate the damaged section of pipe,
D wet the lagging but leave it in place to humans? list, should be used when oxyacetylene you should:
welding?
A Through fine water droplets, such A always work in pairs when using
3 as sprays or mists A Ear defenders pipe-freezing equipment
What is the most likely risk of injury B By drinking dirty water B Clear goggles B never allow the freezing gas to
when cutting large diameter pipe? come into direct contact with
C Through contact with the skin C Green-tinted goggles
A Your fingers may become trapped surface water
between the cutting wheel and D From other people when they D Dust mask
C never use pipe-freezing equipment
the pipe sneeze
on plastic pipe
B The inside edge of the cut pipe D wear gloves to avoid direct contact
becomes extremely sharp to touch with the skin
C Continued use can cause muscle
damage
D Pieces of sharp metal could fly off

6 Answers: 1 = C 2 = B 3 = B 4 = B 5 = B 6 = A Answers: 7 = B 8 = C 9 = C 10 = C 11 = D 12 = D 7
Specialist plumbing (JIB)

13 16 18 20
You are drilling a 100 mm diameter While working, you come across a Which of the following statements is What is the preferred method of
hole for a flue pipe through a brick hard, white, powdery material that true? checking for leaks when assembling
wall with a large hammer drill. Which could be asbestos. What should liquefied petroleum gas (LPG)
A Both propane and butane are
combination of personal protective you do? equipment before use?
heavier than air
equipment (PPE) should you be
A While wearing a face mask, remove A Test with a lighted match
supplied with? B Butane is heavier than air while
the material and dispose of it
propane is lighter than air B Sniff the connections to detect the
A Gloves, breathing apparatus safely
smell of gas
and boots C Propane is heavier than air while
B Remove the material, putting it
butane is lighter than air C Listen to hear for escaping gas
B Ear defenders, face mask back after finishing the job
and boots D Both propane and butane are D Apply leak detection fluid to
C Stop work immediately and tell
lighter than air the connections
C Ear defenders, breathing your supervisor about the material
apparatus and barrier cream
D Dampen the material down with 19 21
D Barrier cream, boots and water and remove it before carrying
face mask out the work Apart from the cylinders used in What is the colour of propane
gas-powered forklift trucks, you should gas cylinders?
14 17 never see liquefied petroleum gas
A Black
(LPG) cylinders placed on their sides
When working with fibreglass roof Why is it important that operatives during use because: B Maroon
insulation, which of the following items know the difference between propane
A it would give a faulty reading on C Red or orange
of personal protective equipment and butane equipment?
the contents gauge, resulting
(PPE) should you wear? D Blue
A Propane equipment operates at in flashback
A Gloves, face mask and higher pressure
B air could be drawn into the cylinder, 22
eye protection
B Propane equipment operates at creating a dangerous mixture
B Boots, eye protection and lower pressure of gases The use of oxyacetylene equipment
ear defenders is not recommended for which of the
C Propane equipment is cheaper C the liquid gas would be at too following jointing methods?
C Ear defenders, face mask low a level to allow the torch to
D Propane equipment can be used
and boots burn correctly A Jointing copper pipe using
with smaller, easy-to-handle
hard soldering
D Barrier cream, eye protection cylinders D the liquid gas could be drawn
and face mask from the cylinder, creating a B Jointing copper tube using capillary
safety hazard soldered fittings
15 C Jointing mild steel tube
Where might you come across D Jointing sheet lead
asbestos?
A Insulation board around radiators
B Gaskets and seals on joints
C Rope seals on a boiler
D All of these answers

8 Answers: 13 = B 14 = A 15 = D 16 = C 17 = A Answers: 18 = A 19 = D 20 = D 21 = C 22 = B 9
Specialist plumbing (JIB)

23 26 29 32
Which of the following makes it When using a blowtorch, you should: When using oxyacetylene welding You are working in an occupied
essential to take great care when equipment, the bottles should be: building and have taken up six lengths
A stop using the blowtorch
handling oxygen cylinders? of 3 m floor boarding when you are
immediately before leaving the job A laid on their side
called away to an urgent job. What
A They contain highly flammable
B stop using the blowtorch at least B stood upright should you do?
compressed gas
one hour before leaving the job
C stood upside down A Leave the job as it is
B They contain highly flammable
C stop using the blowtorch at least
liquid gas D angled at 45 B Cordon off the work area before
two hours before leaving the job
leaving the job
C They are filled to extremely
D stop using the blowtorch at least 30
high pressures C Permanently re-fix the floorboards
four hours before leaving the job
and floor coverings
D They contain poisonous gas You are asked to join plastic soil pipes
27 in the roof space of a building using D Tell other workers to be careful
24 a strong-smelling hazardous solvent, while you are away
When using a blowtorch near to timber, but you have not been provided with
Which of the following is the safest you should: any respiratory protective equipment 33
place to store oxyacetylene (RPE). What should you do?
A carry out the work taking care not
gas-welding bottles when they are You are preparing to use an
to catch the timber A Just get on and do the job
not in use? electric-powered threading machine.
B use a non-combustible mat and B Use a dust mask Which of the following statements
A Outside in a special storage
have a fire extinguisher ready should apply?
compound C Sniff the solvent to see if it has any
C wet the timber first and have a ill-effects on you A The power supply should be
B In company vehicles
bucket of water handy 24 volts and the machine fitted
D Stop what you are doing and get with a guard
C Inside the building in a locked
D point the flame away from the out
cupboard
timber and have a bucket of sand B The power supply should be
D In the immediate work area, ready ready to put out the fire 31 415 volts and the machine fitted
for use the next day with a guard
28 You are required to replace
below-ground drainage pipework in an C Ensure your clothing cannot
25 get caught on rotating parts
What is the colour of an acetylene excavation, which is approximately
of the machine
When using a blowtorch to joint copper cylinder? 2.5 m deep. The trench sides show
tube and fittings in a domestic property, signs of collapse. What do you do? D Ear defenders should be available
A Orange
a fire extinguisher should be: and should be in good condition
A Get on with the work as quickly
B Black
A available in the immediate as possible
work area C Green
B Refuse to do the work until
B held over the joint while you are D Maroon the trench sides have been
using the blowtorch properly shored
C used to cool the fitting C Get a mate to help you so that they
can pass the materials down to you
D available only if a property
is occupied D Ensure that you do the work with a
rope around you so that you can be
pulled out

10 Answers: 23 = C 24 = A 25 = A 26 = B 27 = B 28 = D Answers: 29 = B 30 = D 31 = B 32 = B 33 = C 11
Specialist plumbing (JIB)

34 36 39 42
In terms of accident prevention, which The reason for carrying out temporary Which of the following statements is You need to move a cast iron bath that
two of the following are the most continuity bonding before removing and true? It is safe to transport workers to is too heavy to lift. You should:
important precautions when working in replacing sections of metallic pipework the workplace in the rear of a van if
A inform your supervisor and ask
the roof space of an occupied house? is to: the:
for assistance
A Safe foot access over the A provide a continuous earth for the A driver has a heavy goods vehicle
B get some lifting tackle
ceiling joists pipework installation licence
C give it another try
B Safe access into the roof space B prevent any chance of blowing B van is fitted with temporary seating
using a stepladder or ladder a fuse D try and find someone to give you
C van is fitted with proper seating
a hand
C Check that the roof space is free C maintain the live supply to the and seatbelts
from hornets nests electrical circuit
D driver has a public service vehicle 43
D The roof space must be fitted with D prevent any chance of corrosion to licence
a light socket and switch the pipework When installing a flue liner in an
40 existing chimney, you should:
E Carry out a test to see if the
plasterboard ceiling will support 37 A insert the liner from ground level,
Which is the safest method of taking
your weight pushing it up the chimney
You are required to re-fix a section of long lengths of copper pipe by van?
external rainwater pipe using a power B work in pairs and insert the liner
35 A Tying the pipes to the roof with
drill in wet weather conditions. Which from roof level, working off the roof
copper wire
type of drill is most suitable?
When replacing an electrical immersion C work in pairs and insert the liner
B Someone holding the pipes on the
heater in a hot water storage cylinder, A Battery-powered drill from roof level, working from roof
roof rack as you drive along
what should you do to make sure that ladders or a chimney scaffold
B Drill with 110 volt power supply
the electrical supply is dead before C Putting the pipes inside the van
starting plumbing work? D break through the chimney in
C Drill with 240 volt power supply with the ends out of the passenger
the loft area and insert the liner
window
A Switch off and disconnect the D Any mains voltage drill with a from there
supply to the immersion heater power breaker D Using a pipe rack fixed to the roof
of the van 44
B Switch off and cut through the
electric cable with insulated pliers 38
41 You are asked to move a cast iron
C Switch off and test the circuit What piece of equipment would you boiler some distance. What should
use to find out whether a section of If lifting a roll of Code 5 sheet lead, you do?
D Switch off, isolate the supply at the solid wall that you are about to drill into what is the first thing you should do?
mains board and test the circuit A Get a workmate to carry it
contains electric cables?
A Weigh the roll of lead
B Drag it
A A neon screwdriver
B Have a trial lift to see how heavy
C Roll it end-over-end
B A cable tracer it feels
D Use a suitable trolley or other
C A multimeter C Assess the whole task
manual handling aid
D A hammer and chisel D Ask your workmate to give you
a hand

12 Answers: 34 = A, B 35 = D 36 = A 37 = A 38 = B Answers: 39 = C 40 = D 41 = C 42 = A 43 = C 44 = D 13
Specialist plumbing (JIB)

45 48 Introduction to Safe start (GE 707)


If working on a plumbing job where You arrive at a job that involves using Plumbing related work is highly specialised and potentially dangerous. All such work must
noise levels are rather high, who ladder access to the roof. You notice be properly planned, only carried out by trained and competent contractors and adequately
would you expect to carry out noise the ladder has been painted. You supervised as necessary.
assessment? should:
No-one should attempt to work on any gas pipework or equipment unless they are a Gas Safe
A A fully qualified plumber A only use the ladder if it is made registered engineer.
of metal
B Your supervisor
C The site engineer
B only use the ladder if it is made ! Poorly thought out or executed gas-related work activities can kill.
of wood
D A competent person
C only use the ladder if wearing
rubber-soled boots to prevent Safe methods of working Safe start (GE 707)
46 slipping
Safe working must include giving due attention and:
You are fixing sheet lead flashing D not use the ladder, and report the
to a chimney on the roof of a busy matter to your supervisor 
looking after equipment and hand tools to ensure they are safe to use, including carrying
out simple repairs (such as replacing a split file handle) where this is practical
town centre shop. What is the most
important thing you must do? 49 
being aware that cutting large diameter pipes will leave extremely sharp insides to the pipe
A Pull the ladder onto the roof to 
leaving all places of work in a safe condition if they have to be left unoccupied, particularly
When dismantling lengths of cast iron
prevent the public from climbing up if working in domestic premises where the occupier may not be risk-aware
soil pipe at height, you should:
B Make provision for protecting the 
ensuring safe access to any place of work and that the workplace itself is safe to occupy
A work in pairs, break the length (for example using a ladder or stepladder if accessing the loft space of a domestic premises
public from objects that could fall
at the collar and remove the and ensuring that there is safe foot access over the joists)
C Wear a face mask to protect you pipe section
from breathing the chimney fumes 
carrying out the transportation of people, equipment and materials in a safe and
B tie a rope to the pipe and pull the responsible manner, such as:
D Wear safety boots to prevent you section down. Shout below to 
only carrying people in the back of a van if it is fitted with factory-fitted seats
from slipping off the roof warn others and seat belts
C crack the pipe at the joint and carrying long lengths of tubing in a pipe-rack attached to the roof of a van
47 push it away, making sure the always wearing a seat belt, when one is provided, if driving construction plant
area is clear
You are removing guttering from a 
if the sides of an excavation are not supported and show signs of collapse, it must not be
large, single-storey, metal-framed D smash the pipe into sections entered by any person.
and cladded building. The job is using a hammer and remove it
likely to take all day. What is the most piece by piece Readers of this should also refer to the Common HVACR elements section
appropriate type of access equipment of Chapter F22 of Safe start (GE 707).
you could use?
A A ladder
B A mobile tower scaffold
C A putlog scaffold
D A trestle scaffold

14 Answers: 45 = D 46 = B 47 = B 48 = D 49 = A 15
Specialist plumbing (JIB)

What your site and employer should do for you


1. Provide you with a method of working that is safe and without risks to your health.

2. Ensure that a person with the necessary skills, knowledge and training supervises
the work.

3. Inform you of the significant hazards identified in the risk assessment.

4. The safe way of working will be in a method statement which will be explained to you. Contact information
5. At no time place you in danger. and useful links
6. Provide you with adequate instruction and training.
Contents
Contact information and useful links 18
What you should do for your site and employer
1. Follow the agreed safe system of work.

2. Not take risks with your or anyone elses health or safety.

3. Report any aspect of your work which you feel is unsafe.

4. Comply with any permit systems which are in operation.

16 17
Contact information and useful links

Contact information and useful links


For further information:

@ go online at www.citb.co.uk/hsandetest, or

telephone 0344 994 4488

About the test


different types of test available, structure of the test
Preparing for the test: revision materials
What version of the revision material do I need?
How do I buy revision materials?
Booking the test
Where can I take the test?
Do you provide special assistance, e.g. signer?
What are the test rules?
What services are available for Welsh speakers?

Published by CITB, Bircham Newton, Kings Lynn, Norfolk PE31 6RH

Construction Industry Training Board 1982

CITB is registered as a charity in England and Wales (Reg No 264289)


and in Scotland (Reg No SC044875)

First published 2015

CITB has made every effort to ensure that the information contained within this publication is
accurate. Its content should be used as guidance only and not as a replacement for current
regulations, existing standards or as a substitute for legal advice and is presented without any
warranty, either express or implied, as to its accuracy. In no event will CITB be liable for any
Plumbers Joint Industry Board for Plumbing and Mechanical Engineering Services (JIB-PMES)
damages arising from reliance upon its content.
For further information and to contact JIB:
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system
telephone 01480 476 925 or transmitted in any form or by any means, electronic, mechanical, photocopying, recording or
otherwise, without the prior permission in writing from CITB save that it may be read and saved

18 @ go online at www.jib-pmes.org by the original recipient, for whose private use it was originally intended.
19
citb.co.uk

Health, safety and environment test


For plumbing specialists (JIB)
The CITB Health, safety and environment test forms a key part of the requirement to obtain
a construction industry competency card. The test continues to be a vital tool in helping the
industry to improve its health, safety and environmental standards.
This revision booklet contains the following information to support you in your preparation for the
Health safety and environment specialist plumbing (JIB) test including:
all the plumbing (JIB) specialist activity questions and answers
plumbing information from the GE 707/14 (Safe start) publication.
This is a companion product for the Health, safety and environment revision material for
operatives and specialists (GT 100).
This revision booklet does not contain the core knowledge section questions. To revise the core
knowledge questions please use the Health, safety and environment test for operatives and
specialists (GT 100/15) revision material.
You dont need to use this booklet if you buy a DVD, download or app. There is a revision
DVD and a download available, which offer the chance to work through the entire
question bank (core knowledge and Plumbing (JIB)). These products also contain the
Setting out film and the option to complete simulated tests. You can also revise using
the smartphone app.

For more information on the test, to book


a test or to buy publications contact:

@ citb.co.uk/hsandetest

0344 994 4488



04/15

NOT FOR RETAIL SALE

También podría gustarte