Está en la página 1de 13

Welcome to

Electric Power Systems


Wind farm

Source: balticcable.com
HVDC

www.iea.lth.se/eks
Olof Samuelsson
Olof.Samuelsson@iea.lth.se 1 Olof Samuelsson 2

This lecture Blackout!


What is a blackout?
1. Initial fault
2. New power flow situation
3. Loads and generators disconnected
4. Restoration
About the course
Single line diagram
Per unit normalization
Olof Samuelsson 3 Olof Samuelsson 4

1
What is a blackout? Sweden 23 September 2003
Initiating event Initiating event
Fault (short-circuit) or malfunction Two-phase short-circuit at substation
Disconnection of faulted part Final stage
Problem spreads Voltage collapse
Lines overload and disconnect
4 Million people affected
Collapse and blackout
Stability limit is reached Restoration time 1.5-6.5 h
Restoration

Olof Samuelsson 5 Olof Samuelsson 6

Starting point Sequence of events


P Sweden 15 000 MW

12:35
Nuclear plant Oskarshamn
Disconnector fails 12:30 -1200 MW
O1 and O2 out of service
Nuclear plant Ringhals O3 1200 MW
in Horred substation O3 Emergency stop
R1 out of service 12:35 -1800 MW
R2 870 MW R3 and R4 to house
R3 and R4 2x900 MW operation

Import from Danmark


450 MW
Karlshamnsverket out of
service (48 h startup)

Nuclear plant Barsebck


(B1 and) B2 out of service

Olof Samuelsson 7 Olof Samuelsson 8

2
Blackout! System frequency

12:37 Voltage collapse


The blackout is a fact

Olof Samuelsson 9 Olof Samuelsson 10

Pantograph type disconnector


Restoration

14:00
400 kV network intact

13:46
Denmark allowed to
reconnect to Sweden 15:30
(max 200 MW). Gas turbines in South
Sweden in operation.
Karlshamnsverket
starting.
19:05
Last customers in
Open: Closed: Denmark brought on -line 18:20
Most Sydkraft
customers on-line
isolate for maintenance carry load current
visual open -circuit
Olof Samuelsson 11 Olof Samuelsson 12

3
USA 14 August 2003 System split into islands
Initiating event
Generator shutdowns
Final stage
Voltage collapse
50 Million people affected
Restoration time up to 30 h

Olof Samuelsson 13 Olof Samuelsson 14

Area hit by blackout Italy 28 September 2003


Initiating event
Two lines trip in stormy weather
All lines into Italy lost one by one
Final stage unknown
58 Million people affected
Restoration time 16.5 h

Olof Samuelsson 15 Olof Samuelsson 16

4
Italy blackout Famous blackouts
USA 2 July 1996
Line into tree, voltage collapse, report 2 August
USA 10 August 1996
Line into tree, angle instability, 7.5 million
Sweden 27 December 1983
Disconnector failed, voltage collapse
USA 1965 The great blackout
Generator trip, angle instability, 30 million
See Textbook chapter 13
Olof Samuelsson 17 Olof Samuelsson 18

Post mortem analysis Video 10 August 1996


Pre-fault operating state Hot weather
Generator and line status Line sags into tree
Sequence of events Other lines overload
Digital fault recorders 4 island networks
Time of breaker openings
Time uncertainty
Fast analysis with new tools
Large amounts of information
Sweden: Windpower trips cause/effect?
Olof Samuelsson 19 Olof Samuelsson 20

5
Fault handling Events at fault
Detect fault
Isolate fault Fault occurs
Isolate fault and minimum part of the system Isolate fault
Neighboring parts back to normal Remove fault
Component can fail, larger area affected Restore service
Remove fault and repair damage Automatic reclosing
Lightning strikes only temporary Light back in <1s
Restore service
Olof Samuelsson 21 Olof Samuelsson 22

Detect fault current Interrupt current


Moving contacts apart not enough
Relay protection Arc current flows through arc (ionized air)
Measures U and I Extinguish arc, AC current passes zero
Detects fault Fuse
Controls breaker Measures current!
Earth fault protection Manually replaced
Relay protection + small breaker Circuit breaker
Disconnector
Olof Samuelsson 23 Olof Samuelsson 24

6
Disconnector Circuit breaker
Interrupts large current
Arcing at opening
Cooling
of disconnector
carrying too large Pressurized air, oil
current Remote control
Protection
Control center
For small current, cannot extinguish arc
Hidden breaking point

Source: Nicklasson
Manual control
Visual open-circuit for safety Challenge: Several kA
Challenge: Open construction unprotected
Olof Samuelsson 25 Olof Samuelsson 26

Transmission and distribution Bridging distances


Generation
|
Transmission Transmission
|
Distribution Hundreds of km
|
Consumption Hundreds of MW
Economical V 15 P
SE: 130, 220, 400 kV
High reliability
Source: vattenfall.se Meshed network

Olof Samuelsson 27 Olof Samuelsson 28

7
Reach addresses Radial network
Distribution Line length SE 1996 Distribution Infeed
400 kV 9851 km
Distance few km
130- 220 kV 19740 km Tree shape Line
SE: 10, 20, 50 kV 30-70 kV 21100 km Single infeed
Radial network 10-20 kV 152000 km Node
400 V 280000 km Many supply points
Reliability
City Countryside
Single fault
interrupts service
0,4 kV Load

Olof Samuelsson 29 Olof Samuelsson 30

Meshed network N-1 reliability criterion


Transmission Intact system has N components
Meshing Withstand loss of any single
Many infeeds Generator
Many supply points Line or cable
Many paths for power Transformer
Reliability Busbar (interconnection point)
N-1 criterion No overload on remaining components
Major outages: N-1 turns into N-2
Olof Samuelsson 31 Olof Samuelsson 32

8
Power flow in PowerWorld Stability limits
Angle instability
Active power imbalance
Mechanical generator dynamics excited
Generator loses synchronism
Generator disconnected
Voltage instability
Lack of reactive power
Overload of power lines
Loads disconnected
Olof Samuelsson 33 Olof Samuelsson 34

Restoration Blackout and course modules


Blackstart generating units Problem spreads
Batteries and diesel for starting 1. Load flow
Energizing lines Blackout when stability limit is reached
Careful with voltage 2. Voltage stability, power system control
Adding little load 3. Angle stability, synchronous generators
Limited control capacity Short-circuits initiate problems
Adding generation and load 4. Relay protection and symmetrical faults
Restoration important, how to practice? 5. Unsymmetrical faults

Olof Samuelsson 35 Olof Samuelsson 36

9
A course module Learning sequence
Tuesday: Lecture Demonstrate need for knowledge
Thursday: Hand exercise Learn theory
Work in pairs Lecture
Small system in detail by hand Practice principle
Monday: Computer exercise Hand exercise
Work in pairs Practice principle in practice
Large system in detail with computer Computer exercise
Large system simplified by hand

Olof Samuelsson 37 Olof Samuelsson 38

Other activities Schedule


Laboratory exercises
W Monday Tuesday Thursday
Power in AC networks
1 L1 L2 E1 Lecture
Synchronous generator
2 SV1 L3 E2 Exercise
Study visits 3 C1 L4 E3 Computer
Real-time simulator, Malm Hgskola
4 C2 L5 E4 Study Visit
Substation in Lund
5 C3 L/E5 L/E6
Current topics lecture 6 C4 L/E7 L/E8
7 C5 SV2 L6
Olof Samuelsson 39 Olof Samuelsson 40

10
Rooms Textbook
Mondays 13-15 J. D. Glover & M. Sarma:
M:E Power System Analysis and Design
E:Neptunus, E:Pluto Brooks-Cole, US, 2002
Tuesdays 15-17
M:B 3rd ed, ISBN 0-53495-367-0
Thursdays 13- 15 Akademibokhandeln today
E:1406 this week Internet cheap but slow
M:E
M:E other weeks Olof

PowerWorld CD included
Notice board
Lab 7
Olof Samuelsson 41 Olof Samuelsson 42

Assumed knowledge Substation


Parts of a power system
Generator, line, transformer
Source: Lakervi & Holmes

Three-phase voltage and currents


AC power
Electric machinery basics
Matlab/Simulink

Olof Samuelsson 43 Olof Samuelsson 44

11
Substation functions Single line diagram symbols
Three-phase component Comment
Busbar No impedance
Voltage transformation (reduction) Three-phase line Line with impedance
Power transformer Power transformer US:
Switchyard for network configuration Generator
Busbars, circuit breakers, disconnectors Load
Circuit breaker US: Open Closed
Monitoring point for control center Disconnector
Potential and current transformers Surge arrester Overvoltage protection
Fuses and other protection Current transformer
Potential transformer
Olof Samuelsson 45 Olof Samuelsson 46

Substation layout Per unit normalization


Normalize to nominal value
Source: Lakervi & Holmes

Example: 11 kV at 10 kV bus
V p.u.=V actual /V base =11kV/10kV=1.1p.u.
p.u. indicates if situation is normal
Voltage levels comparable
Simplifies transformer calculations

Olof Samuelsson 47 Olof Samuelsson 48

12
Per unit base values
Theoretically
Any two of S, V, I and Z
Practically
System MVA base + One voltage base
Three-phase: Sbase/(v3V base) => Ibase
V base2/Sbase=> Zbase
Transformer turns ratio => voltage base
on other side of transformer
Olof Samuelsson 49

13

También podría gustarte