Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Source: balticcable.com
HVDC
www.iea.lth.se/eks
Olof Samuelsson
Olof.Samuelsson@iea.lth.se 1 Olof Samuelsson 2
1
What is a blackout? Sweden 23 September 2003
Initiating event Initiating event
Fault (short-circuit) or malfunction Two-phase short-circuit at substation
Disconnection of faulted part Final stage
Problem spreads Voltage collapse
Lines overload and disconnect
4 Million people affected
Collapse and blackout
Stability limit is reached Restoration time 1.5-6.5 h
Restoration
12:35
Nuclear plant Oskarshamn
Disconnector fails 12:30 -1200 MW
O1 and O2 out of service
Nuclear plant Ringhals O3 1200 MW
in Horred substation O3 Emergency stop
R1 out of service 12:35 -1800 MW
R2 870 MW R3 and R4 to house
R3 and R4 2x900 MW operation
2
Blackout! System frequency
14:00
400 kV network intact
13:46
Denmark allowed to
reconnect to Sweden 15:30
(max 200 MW). Gas turbines in South
Sweden in operation.
Karlshamnsverket
starting.
19:05
Last customers in
Open: Closed: Denmark brought on -line 18:20
Most Sydkraft
customers on-line
isolate for maintenance carry load current
visual open -circuit
Olof Samuelsson 11 Olof Samuelsson 12
3
USA 14 August 2003 System split into islands
Initiating event
Generator shutdowns
Final stage
Voltage collapse
50 Million people affected
Restoration time up to 30 h
4
Italy blackout Famous blackouts
USA 2 July 1996
Line into tree, voltage collapse, report 2 August
USA 10 August 1996
Line into tree, angle instability, 7.5 million
Sweden 27 December 1983
Disconnector failed, voltage collapse
USA 1965 The great blackout
Generator trip, angle instability, 30 million
See Textbook chapter 13
Olof Samuelsson 17 Olof Samuelsson 18
5
Fault handling Events at fault
Detect fault
Isolate fault Fault occurs
Isolate fault and minimum part of the system Isolate fault
Neighboring parts back to normal Remove fault
Component can fail, larger area affected Restore service
Remove fault and repair damage Automatic reclosing
Lightning strikes only temporary Light back in <1s
Restore service
Olof Samuelsson 21 Olof Samuelsson 22
6
Disconnector Circuit breaker
Interrupts large current
Arcing at opening
Cooling
of disconnector
carrying too large Pressurized air, oil
current Remote control
Protection
Control center
For small current, cannot extinguish arc
Hidden breaking point
Source: Nicklasson
Manual control
Visual open-circuit for safety Challenge: Several kA
Challenge: Open construction unprotected
Olof Samuelsson 25 Olof Samuelsson 26
7
Reach addresses Radial network
Distribution Line length SE 1996 Distribution Infeed
400 kV 9851 km
Distance few km
130- 220 kV 19740 km Tree shape Line
SE: 10, 20, 50 kV 30-70 kV 21100 km Single infeed
Radial network 10-20 kV 152000 km Node
400 V 280000 km Many supply points
Reliability
City Countryside
Single fault
interrupts service
0,4 kV Load
8
Power flow in PowerWorld Stability limits
Angle instability
Active power imbalance
Mechanical generator dynamics excited
Generator loses synchronism
Generator disconnected
Voltage instability
Lack of reactive power
Overload of power lines
Loads disconnected
Olof Samuelsson 33 Olof Samuelsson 34
9
A course module Learning sequence
Tuesday: Lecture Demonstrate need for knowledge
Thursday: Hand exercise Learn theory
Work in pairs Lecture
Small system in detail by hand Practice principle
Monday: Computer exercise Hand exercise
Work in pairs Practice principle in practice
Large system in detail with computer Computer exercise
Large system simplified by hand
10
Rooms Textbook
Mondays 13-15 J. D. Glover & M. Sarma:
M:E Power System Analysis and Design
E:Neptunus, E:Pluto Brooks-Cole, US, 2002
Tuesdays 15-17
M:B 3rd ed, ISBN 0-53495-367-0
Thursdays 13- 15 Akademibokhandeln today
E:1406 this week Internet cheap but slow
M:E
M:E other weeks Olof
PowerWorld CD included
Notice board
Lab 7
Olof Samuelsson 41 Olof Samuelsson 42
11
Substation functions Single line diagram symbols
Three-phase component Comment
Busbar No impedance
Voltage transformation (reduction) Three-phase line Line with impedance
Power transformer Power transformer US:
Switchyard for network configuration Generator
Busbars, circuit breakers, disconnectors Load
Circuit breaker US: Open Closed
Monitoring point for control center Disconnector
Potential and current transformers Surge arrester Overvoltage protection
Fuses and other protection Current transformer
Potential transformer
Olof Samuelsson 45 Olof Samuelsson 46
Example: 11 kV at 10 kV bus
V p.u.=V actual /V base =11kV/10kV=1.1p.u.
p.u. indicates if situation is normal
Voltage levels comparable
Simplifies transformer calculations
12
Per unit base values
Theoretically
Any two of S, V, I and Z
Practically
System MVA base + One voltage base
Three-phase: Sbase/(v3V base) => Ibase
V base2/Sbase=> Zbase
Transformer turns ratio => voltage base
on other side of transformer
Olof Samuelsson 49
13