CUADRO DE AVANCE

DESCRIPCION UND

PERFORACION METROS

INYECCION METROS

RESUMEN DE PERFORACION DE TALADROS LARGOS


BARRAS /TALADROS
TOTAL TOTAL
TOTAL OBSERVACIONES Y
FECHA TURNO FASE NIVEL LABOR SECCION METROS METROS N. PERSONAL
1 2 3 4 5 N BARRAS DESCRIPCION
PERFORADOS ACUMULADO

12/20/2016 Da SOST 4340 S/N 340 0 21 21 25.00 25.00 2


12/20/2016 Noche SOST 4340 S/N 340 0 21 21 21 63 75.00 100.00 2
12/21/2016 Da SOST 4340 S/N 340 0,1. 21 21 42 50.00 150.00 2
12/21/2016 Noche SOST 4340 S/N 340 1 21 21 21 21 84 100.00 250.01 2
12/22/2016 Da SOST 4340 S/N 340 2 21 21 21 63 75.00 325.01 2
12/22/2016 Noche SOST 4340 S/N 340 2 21 21 42 50.00 375.01 2
12/23/2016 Da SOST 4340 S/N 340 3 21 21 21 63 75.00 450.01 2

12/23/2016 Noche SOST 4340 S/N 340 3,4 21 21 21 21 84 100.00 550.01 2

CAPACITACION DE
12/24/2016 Da SOST 4340 S/N 340 0 0 0 0 0 0 0 0.00 550.01 INSTALACION DE CABLE 2
BOLTING.

12/24/2016 Noche SOST 4340 S/N 340 4,5 21 21 21 63 75.00 625.01 2

12/25/2016 Dia SOST 4340 S/N 340 5 21 21 21 63 75.00 700.01 2


12/25/2016 Noche SOST 4340 S/N 340 5,6 21 21 21 63 75.00 775.02 2
12/26/2016 Dia SOST 4340 S/N 340 6 21 21 21 21 84 100.00 875.02 2
12/26/2016 Noche SOST 4340 S/N 340 7 21 21 21 63 75.00 950.02 2
12/27/2016 Dia SOST 4340 S/N 340 7,8 33 21 54 64.29 1014.31 2
12/27/2016 Noche SOST 4340 S/N 340 8,9 30 21 21 21 21 114 135.72 1150.02 2
CAPACITACION DE
12/28/2016 Dia SOST 4340 S/N 340 0 0.00 1150.02 INSTALACION DE CABLE 2
BOLTING GUARDIA "B"

12/28/2016 Noche SOST 4340 S/N 340 9 21 21 21 63 75.00 1225.02 2


12/29/2016 DIA SOST 4340 S/N 340 9,10 21 21 21 21 84 100.00 1325.03 2
OPERADOR NO ASISTIO A
12/29/2016 Noche SOST 4340 S/N 340 0 0.00 1325.03 TRABAJAR POR MOTIVO DE 2
SALUD.

12/30/2016 Dia SOST 4340 S/N 340 10,11 21 42 42 105 125.00 1450.03 2
12/30/2016 Noche SOST 4340 S/N 340 11,12 21 21 21 63 75.00 1525.03 2
12/31/2016 Dia SOST 4340 S/N 340 12 21 21 25.00 1550.03 2
DEFICIENCIA EN
12/31/2016 Noche SOST 4340 S/N 340 12 21 14 35 41.67 1591.70 CUMPLIMIENTO MOTIVO DE 2
AO NUEVO.

1/1/2017 Dia SOST 4340 S/N 340 12,13 21 28 42 91 108.34 1700.03 2


1/1/2017 Noche SOST 4340 S/N 340 13,14 42 42 21 105 125.00 1825.04 2
1/2/2017 Dia SOST 4340 S/N 340 14,15 21 42 42 105 125.00 1950.04 2
1/2/2017 Noche SOST 4340 S/N 340 15,16 42 42 84 100.00 2050.04 2
PROBLEMAS DE
1/3/2017 Dia SOST 4340 S/N 340 16 21 21 42 50.00 2100.04 ATASCAMIENTO DE BARRA 2

1/3/2017 Noche SOST 4340 S/N 340 16,17 21 21 42 84 100.00 2200.04 2


1/4/2017 Dia SOST 4340 S/N 340 17,18 21 42 21 84 100.00 2300.05 2
1/4/2017 Noche SOST 4340 S/N 340 18 21 21 21 63 75.00 2375.05 2
1/5/2017 Dia SOST 4340 S/N 340 19 21 21 21 21 84 100.00 2475.05 2
PROIBLEMAS CON EL
1/5/2017 Noche SOST 4340 S/N 340 19, 20 10 21 42 73 86.91 2561.96 CARRUSEL 2
1/6/2017 Dia SOST 4340 S/N 340 20, 21 21 42 32 95 113.10 2675.05 2
1/6/2017 Noche SOST 4340 S/N 340 21, 22 21 42 42 105 125.00 2800.06 2
1/7/2017 Dia SOST 4340 S/N 340 22, 23 21 42 42 105 125.00 2925.06 2
1/7/2017 Noche SOST 4340 S/N 340 23, 24 21 42 42 105 125.00 3050.06 2
1/8/2017 Dia SOST 4340 S/N 340 24, 25 21 21 42 84 100.00 3150.06 2

1/8/2017 Noche SOST 4340 S/N 340 25 21 21 21 63 75.00 3225.06 FALTA ACEITE HIDRAULICO 2

TOTAL 546 546 546 546 525 2709.0 3225.1 3225.1


DE AVANCES CABLE BOLTING
PROGRAMA

19775

19775

RESUMEN DE INSTALACION DE CABLES BOLTING.


TALADROS INYECTADOS PLANCHUELAS TOTAL TOTAL TOTAL
OBSERVACIONES Y
FECHA TURNO FASE NIVEL LABOR SECCION CONJUNTO ACUM. METROS METROS
1 2 3 4 5 DESCRIPCION
CUA BARRIL PLANCHUELAS INYECTADOS ACUMULADOS

12/23/2016 Da SOST. 4340 S/N 340 0 25 25 50 50.00


12/24/2016 Dia SOST. 4340 S/N 340 0 25 25 25 75 125.00
12/25/2016 Da SOST. 4340 S/N 340 1,2 25 50 25 25 125 250.00
12/26/2016 Da SOST. 4340 S/N 340 1,2 25 25 25 25 100 350.00
12/28/2016 Da SOST. 4340 S/N 340 3 25 25 25 25 100 450.00
12/28/2016 Da SOST. 4340 S/N 340 3,4 25 25 25 75 525.00
COLOCADO DE
12/29/2016 Da SOST. 4340 S/N 340 5 5 0 525.00 PLANCHUELAS.

TALADRO (2) TAPADO SE


12/29/2016 Noche SOST. 4340 S/N 340 4 25 25 25 25 25 5 125 650.00 REQUIERE PERFORAR.

12/30/2016 Da SOST. 4340 S/N 340 4, 5,6 25 25 25 25 5 100 750.00

TALADRO 4 DE LA
12/30/2016 Noche SOST. 4340 S/N 340 6,7 25 25 25 25 5 100 850.00 SECCION 6 INGRESO 6
BOLSAS DE CEMENTO

12/31/2016 Dia SOST. 4340 S/N 340 7 25 25 5 50 900.00


12/31/2016 Noche SOST. 4340 S/N 340 5 0 900.00 falta de personal
1/1/2017 Dia SOST. 4340 S/N 340 5 0 900.00 falta de personal
COLOCADO DE
1/1/2017 Noche SOST. 4340 S/N 340 16 21 0 900.00 PLANCHUELAS.
1/2/2017 Dia SOST. 4340 S/N 340 16 37 0 900.00
1/2/2017 Noche SOST. 4340 S/N 340 7,8 25 50 25 100 1000.00

1/3/2017 Dia SOST. 4340 S/N 340 8,9 25 25 25 25 100 1100.00

1/3/2017 Noche SOST. 4340 S/N 340 9 25 25 25 25 100 1200.00


1/4/2017 Dia SOST. 4340 S/N 340 10 25 25 25 25 100 1300.00

1/4/2017 Noche SOST. 4340 S/N 340 10,11 50 25 25 100 1400.00

1/5/2017 Dia SOST. 4340 S/N 340 11,12 50 50 100 1500.00


1/5/2017 Noche SOST. 4340 S/N 340 12, 13 50 25 25 100 1600.00
1/6/2017 Dia SOST. 4340 S/N 340 13, 14 25 25 25 50 125 1725.00

1/6/2017 Noche SOST. 4340 S/N 340 14 25 25 25 25 100 1825.00

1/7/2017 Dia SOST. 4340 S/N 340 15, 16 25 25 25 25 25 125 1950.00


1/7/2017 Noche SOST. 4340 S/N 340 16 25 25 25 75 2025.00
1/8/2017 Dia SOST. 4340 S/N 340 17 25 25 25 25 100 2125.00
1/8/2017 Noche SOST. 4340 S/N 341 22

350.0 450.0 450.0 475.0 400.0 59 59 2125.0 2125.0


TOTAL
METROS METROS METROS METROS METROS PLANCHUELAS METROS Metros
TALACION DE CABLES BOLTING.
N. PERSONAL

3
3
3
2

3
3

3
3
3

3
3
3
2