Está en la página 1de 37

KENYA STANDARD KS 1876-1:2010

ICS 29.240.20

rd
da
an
St
ya
en
sK
da
Electrical power transmission and

ite
distribution Overhead power lines for

C
conditions prevailing in Kenya Part 1:
Code of practice
be
t to
No
g
tin
llo
Ba
for
rd

BALLOT DRAFT, MAY 2010


da
tan
aS
ny
Ke
aft
Dr

KEBS 2010 First Edition 2010


KS 1876-1:2010

rd
TECHNICAL COMMITTEE REPRESENTATION

da
The following organizations were represented on the Technical Committee:

an
Nairobi City Council, City Engineers Department.
Jomo Kenyatta University of Agriculture and Technology

St
Kenya Polytechnic
Kenya Power & Lighting Company
Fluid & Power Systems Ltd

ya
Ministry of Public Works and Housing
Ministry of Energy

en
Kenafric Industries Ltd
Power Technics Ltd

sK
Rural Electrification Authority
The Energy Regulatory Commission
Consumer Information Network

da
Kenya Association of Manufacturers
Institute of Engineers of Kenya
Kenya Electricity Generating Company Ltd

ite
ABB LTD
Switchgear & Controls Ltd

C
Power Controls Ltd
Communications Communication of Kenya

be
Instrument Ltd
Kenya Pipeline Company Ltd
Telkom Kenya Ltd
t to
Meteorological Department
Kenya Bureau of Standards Secretariat
No
g
tin

REVISION OF KENYA STANDARDS


llo

In order to keep abreast of progress in industry, Kenya standards shall be regularly reviewed. Suggestions
Ba

for improvement to published standards, addressed to the Managing Director, Kenya Bureau of Standards,
are welcome.
for
rd
da
tan
aS

Kenya Bureau of Standards, 2010


ny

Copyright. Users are reminded that by virtue of Section 25 of the Copyright Act, Cap. 12 of 2001 of the Laws of Kenya, copyright
subsists in all Kenya Standards and except as provided under Section 26 of this Act, no Kenya Standard produced by Kenya Bureau of
Ke

Standards may be reproduced, stored in a retrieval system in any form or transmitted by any means without prior permission in writing
from the Managing Director.
aft
Dr

ii KEBS 2010 All rights reserved


KENYA STANDARD KS 1876-1:2010
ICS 29.240.20

rd
da
an
St
ya
en
sK
da
ite
Electrical power transmission and

C
distribution Overhead power lines for

be
conditions prevailing in Kenya Part 1:
Code of practice
t to
No
g
tin
llo
Ba
for

KENYA BUREAU OF STANDARDS (KEBS)


rd

Head Office: P.O. Box 54974, Nairobi-00200, Tel.: (+254 020) 605490, 69028000, 602350, Mobile: 0722202137/8, 0734600471/2;
Fax: (+254 020) 604031
da

E-Mail: info@kebs.org, Web:http://www.kebs.org

KEBS Coast Region KEBS Lake Region KEBS North Rift Region
tan

P.O. Box 99376, Mombasa 80100 P.O. Box 2949, Kisumu 40100 P.O. Box 2138, Nakuru 20100
Tel: (+254 041) 229563, 230939/40 Tel: (+254 057) 23549,22396 Tel: (+254 051) 210553, 210555
Fax: (+254 041) 229448 Fax: (+254 057) 21814
E-mail: kebs-msa@swiftmombasa.com E-mail: kebs-ksm@swiftkisumu.com
aS
ny
Ke
aft
Dr

KEBS 2010 All rights reserved iii


KS 1876-1:2010

rd
FOREWORD

da
This Kenya standard was prepared by the Switchgear and Distribution Equipment in accordance with the
procedures of the Bureau and is in compliance with Annex 3 of the WTO/TB Agreement.

an
This standard was prepared to enable competent and prescribed persons to design safe and cost-effective
power lines by its quoting of the statutory requirements applicable and indicating the current technology and

St
practice related to Kenyan conditions. It is not intended to be a textbook on the design of overhead lines for
Kenyan conditions but to draw attention to the various factors which should be borne in mind in the design

ya
and construction of power lines and to indicate ways and means of overcoming certain of the difficulties that
can be encountered.

en
It also provides guidance when the optimization of power lines is required for the varying climatic conditions

sK
within Kenya and for which exemption from the OHS Act, 2007, is necessary.

In the development of this standard, the South African Standard, SANS 10280:2001, Overhead power lines

da
for conditions prevailing in South Africa Code of practice, was extensively consulted. Assistance derived
from this source is hereby acknowledged.

ite
Normative and informative annexes

C
A 'normative' annex is an integral part of a standard, whereas an 'informative' annex is only for information
and guidance.

be
t to
Summary of development
No

This Kenya Standard, Amendments issued since publication


g

having been prepared


Amd. No. Date Text affected
by the Switchgear and
Distribution
Equipment Technical
tin

Committee was first


approved by the
llo

National Standards
Council in June 2010
Ba
for
rd
da
tan
aS
ny
Ke
aft
Dr

iv KEBS 2010 All rights reserved


KS 1876-1:2010

rd
Contents

da
1 Scope .................................................................................................................................................... 1

an
2 Normative references ........................................................................................................................... 1
3 Definitions ............................................................................................................................................. 1

St
4 General requirements ........................................................................................................................... 3
4.1 Standards to be observed .................................................................................................................... 3

ya
4.2 Basic conditions of design .................................................................................................................... 3
4.3 Protection against hazards ................................................................................................................... 4

en
4.4 Combined and parallel routes............................................................................................................... 5
4.5 Inductive and electrostatic interference with communication circuits ................................................... 6

sK
4.6 Electrolytic corrosion............................................................................................................................. 7
5 Conductors and earth wires .................................................................................................................. 7

da
5.1 Material ................................................................................................................................................. 7
5.2 Maximum tensions ................................................................................................................................ 8
5.3 Joints .................................................................................................................................................. 10

ite
6 Supports and fittings ........................................................................................................................... 10

C
6.1 Factors of safety ................................................................................................................................. 10
6.2 Design loading .................................................................................................................................... 10

be
6.3 Loading due to broken conductors ..................................................................................................... 12
6.4 Erection loads ..................................................................................................................................... 13
t to
6.5 Foundations ........................................................................................................................................ 14
6.6 Insulators and fittings .......................................................................................................................... 15
6.7 Clearances .......................................................................................................................................... 16
No

6.8 Stay wires ........................................................................................................................................... 19


7 Crossings ............................................................................................................................................ 20
g

7.1 Crossings over roads, railways, tramways and communication lines ................................................ 20
7.2 Crossings over water .......................................................................................................................... 20
7.3 Joints in crossings .............................................................................................................................. 21
7.4 Crossings over other services ............................................................................................................ 21
tin

8 Earthing .............................................................................................................................................. 21
llo

8.1 Support structures for power lines ...................................................................................................... 21


8.2 Fittings ................................................................................................................................................ 21
Ba

8.3 Earth wires .......................................................................................................................................... 21


9 Procedure to be adopted before the construction of power lines ....................................................... 23
9.1 General ............................................................................................................................................... 23
for

9.2 Environmental impact ......................................................................................................................... 23


9.3 Telecommunications authority ............................................................................................................ 23
rd

9.4 Appropriate road authority .................................................................................................................. 23


9.5 Civil Aviation Authority ........................................................................................................................ 23
da

9.6 Other electricity supply authorities...................................................................................................... 23


Annex A (normative) Principal Acts, ordinances, regulations and instructions pertaining to overhead power
tan

lines ............................................................................................................................................................ 24
Annex B (normative) Guidance on power lines and communication circuits ................................................. 25
aS

Annex C (informative) Clearances required for power lines that cross other services .................................. 31
ny
Ke
aft
Dr

KEBS 2010 All rights reserved v


Dr
aft
Ke
ny
aS
tan
da
rd
for
Ba
llo
tin
g
No
t to
be
Cite
da
sK
en
ya
St
an
da
rd
KENYA STANDARD KS 1876-1:2010

rd
da
an
Electrical power transmission and distribution Overhead power lines

St
for conditions prevailing in Kenya Part 1: Code of practice

ya
1 Scope

en
This Kenya Standard identifies the various factors to be taken into account in the design and construction of
overhead power lines, and indicates ways and means of overcoming certain of the difficulties that can be

sK
encountered.

2 Normative references

da
The following referenced documents are indispensable for the application of this Kenya Standard. For dated

ite
references, only the edition cited applies. For undated references, the latest edition of the referenced
document (including any amendments) applies.

C
ISO 11303, Corrosion of metals and alloys Guidelines for selection of protection methods against
atmospheric corrosion

be
ISO 12944, Paints and varnishes Corrosion protection of steel structures by protective paint systems
t to
ISO 14713, Protection against corrosion of iron and steel in structures Zinc and aluminium coatings
Guidelines
No

ISO 17834, Thermal spraying Coatings for protection against corrosion and oxidation at elevated
temperatures
g

ISO 19840, Paints and varnishes Corrosion protection of steel structures by protective paint systems
Measurement of, and acceptance criteria for, the thickness of dry films on rough surfaces
tin

KS 1886, Electrical power transmission and distribution Transmission structure foundation Design and
testing
llo

KS 1889, Electrical power transmission and distribution Installation of foundations for transmission line
Ba

structures Guide

IEC 60383-1, Insulators for overhead lines with a nominal voltage above 1 000 V Part 1: Ceramic or glass
for

insulator units for a. c. systems Definitions, test methods and acceptance criteria

IEC 60815, Guide for the selection of insulators in respect of polluted conditions
rd

IEC 60071-1, Insulation co-ordination Part 1: Definitions, principles and rules


da

IEC 60071-2, Insulation co-ordination Part 2: Application guide


tan

IEC 60826, Loading and strength of overhead transmission lines


aS

3 Definitions
ny

For the purposes of this standard the following definitions apply:

3.1
Ke

basic insulation level (BIL)


A specific insulation level, expressed in kilovolts, to which the complete system is designed and constructed.
aft

This insulation level includes the line pole insulation to earth at every pole, the insulation levels of the
switchgear, line isolators and reclosers, and the insulation level of substations connected to the system,
including their transformers.
Dr

KEBS 2010 All rights reserved 1


KS 1876-1:2010

rd
3.2

da
communication lines
Lines that convey information by electrical means

an
3.3
earthed

St
So connected to the general mass of earth that, where practicable, when contact is made anywhere on the
line between a live conductor and earthed metal, the resultant current is not less than that required to

ya
operate the devices which interrupt the supply to the line

en
3.4
extra-high voltage (EHV)

sK
A set of nominal voltage levels in the range 220 kV < Un < 400 kV

3.5

da
factor of safety (of any component)
The ratio of a component's failing load to the maximum working load for which it is designed

ite
3.6
footing resistance

C
The resistance between a structure and earth

be
3.7
high voltage (HV)
A set of nominal voltage levels in the range 44 kV < Un < 220 kV
t to
3.8
low voltage (LV)
No

A set of nominal voltage levels that are used for the distribution of electricity the upper limit of which is
generally accepted to be an a.c. voltage of 1 000 V (or a d.c. voltage of 1 500 V)
g

3.9
medium voltage (MV)
A set of nominal voltage levels in the range 1 kV < Un < 44 kV that lie above low voltage and below high
tin

voltage

3.10
llo

power line
An overhead line erected to convey electrical energy for any purpose other than communication, but
Ba

excluding the overhead contact or catenary wires of an electric traction system.

3.11
for

service connection
The conductors between the supplier's mains and the customer's installation. In the case of an overhead
rd

service connection, this means the conductor between a supply-line pole and the customer's installation.
da

3.12
standard specification
tan

A Kenya Standard specification issued in terms of the Standards Act, Cap 496 of the Laws of Kenya

3.13
aS

stay
A steel wire, rope or rod, working under tension, that connects a point of a support to a separate anchor
ny

3.14
telecommunications authority
Ke

the Communications Commission of Kenya

3.15
aft

ultra-high voltage (UHV)


A set of nominal voltage levels in the range Un > 400 kV, that are used in power systems for the bulk
Dr

transmission of electricity.

2 KEBS 2010 All rights reserved


KS 1876-1:2010

rd
4 General requirements

da
4.1 Standards to be observed

an
4.1.1 Equipment and materials

St
All equipment and materials used for power lines shall comply with applicable standard specifications. When
specifying materials, it is essential to ascertain the number and date of the latest specification, since

ya
specifications are revised and superseded from time to time.

en
The latest specifications should be applied where practical, and the number and date of all specifications
used shall be stated, to avoid legal difficulties of interpretation and risks to the designer.

sK
4.1.2 Statutory requirements

da
Unless exemption has been obtained from the authorities concerned, all power lines shall comply with the
relevant statutory requirements (see Annex A).

ite
4.2 Basic conditions of design

C
Where it is considered appropriate to use any of the design conditions set out in this standard that might be
at variance with the Occupational Health and Safety Act, relevant permission should be sought from the

be
Directorate of Occupational Health and Safety. t to
Alternative design conditions might provide less stringent design criteria, but will also result in a reduction of
the safety margins associated with the line. Whether such a reduction is significant requires professional
judgement by a competent person, as defined in the OHS Act.
No

NOTE The factors involved in these design conditions are discussed in 4.2.1 to 4.2.5 (inclusive).

4.2.1 Maximum wind velocity and minimum temperature for design loads
g

A review of temperature and wind conditions in Kenya (see Annex D) indicates that
tin

a) maximum wind velocities seldom exceed 115 km/h but wind velocities of up to 160 km/h have been
recorded,
llo

b) minimum temperatures seldom drop below -5 C but temperatures as low as -15 C have been
Ba

recorded, and

c) low temperatures are associated with low wind velocities, while maximum wind velocities are usually
for

associated with temperatures between 10 C and 15 C.

In view of (c) above, it is not necessary to design power lines to withstand the loads resulting from the
rd

combined effects of the lowest possible temperature and the highest possible wind velocity. At minimum
temperatures, the wind velocity is typically 10 km/h to 14 km/h and can be disregarded. It is therefore
da

recommended that a power line be designed to withstand the combined effects of the basic conditions of a
minimum conductor temperature of -5 C, without win d, or a maximum wind velocity of 115 km/h, and a
tan

conductor temperature of 15 C.

4.2.2 Maximum conductor temperature for design sag and clearance


aS

Conductors can be operated at temperatures of up to 80 C for short periods without serious loss of st rength
and this temperature is used in determining the thermal rating of a conductor.
ny

It is often impossible (owing to voltage drop) and usually uneconomic to operate a conductor at a current of
Ke

more than about half its thermal rating and, therefore, except for infrequent emergency conditions, conductor
temperatures are unlikely to approach the value of 80 C in practice. The minimum clearances shall be
determined at a conductor temperature of 50 C and at a swing angle that corresponds to a wind pressure of
aft

500 Pa acting on the effective projected area, provided that, where, under normal conditions, power line
conductors operate at a temperature above 50 C, th e clearance at the higher temperature at which the
Dr

conductors operate shall be in accordance with the clearance indicated in Annex C.

KEBS 2010 All rights reserved 3


KS 1876-1:2010

rd
Current general practice is to use a maximum conductor temperature of not less than 60 C when a line is

da
being templated.

an
4.2.3 Design wind pressure

The wind pressure on power lines depends on many variable factors, such as the gust component of the

St
wind, the height of the supporting structure and of the conductor, and the shape of the power line
components.

ya
Since the governing factors vary in each particular case, it is not possible to state exactly what pressure

en
corresponds to a given maximum wind velocity.

sK
In practice, high-velocity winds are never constant but are made up of a steady component on which an
alternating gust component is superimposed.

da
In the case of a power line conductor, the force on a span of conductor owing to a gust will be less than that
calculated, on the assumption that the maximum wind velocity occurs over the entire span. This is because
the width of a gust is limited. Hence, in the case of conductors, a gust factor of 0.6 is used in calculating wind

ite
pressure. In the case of structures, it is assumed that a gust will affect the entire structure, and hence no
gust factor is applied.

C
In the case of structures of height up to 20 m, the methods given in KS 1877 and KS 1878-3 should be used

be
for calculating wind pressure.

In the case of structures of height between 20 m and 50 m, a realistic basic wind pressure (BWP) in the case
t to
of a wind of maximum velocity 115 km/h is 1 170 Pa for all span lengths. The actual design wind pressures
(DWP) that should be applied to the different line components are calculated as shown in 6.2.1 and 6.2.2.
In the case of structures of height exceeding 50 m, specialist design is needed.
No

NOTE 1 See KS 1877 and KS 1878-3 for guidance on designing wooden pole structures for MV and LV lines.
NOTE 2 In the case of structures of height exceeding 50 m, specialist designs are needed.
g

Numerous methods and references exist for the determination of the wind pressure to be used, based on the measurement of wind
velocities. Many of these methods are empirical and might not reflect local conditions.

4.2.4 Ice loading


tin

The formation of ice on power lines is a rare occurrence in Kenya and is therefore not included in the basic
llo

design conditions.
Ba

In isolated areas where ice is known to occur, it is usually possible to use lines designed for basic conditions
of no ice and to use shorter spans adjusted for the increase in weight due to ice, to ensure that the required
clearances and a reasonable factor of safety will be obtained under ice-loaded conditions.
for

The increase in diameter owing to ice can be disregarded, since the corresponding wind velocities are low.
rd

Further information is contained in KS IEC 60826.


da

4.2.5 Unusual conditions


tan

The basic conditions of design and the factors of safety recommended in this standard have been so chosen
that a design that embodies these basic conditions should be able to withstand, with a reduced but adequate
factor of safety, any unusual conditions that can be visualized in Kenya, provided that these conditions occur
aS

infrequently.

If power lines are to be erected in areas where conditions are frequently more onerous than assumed in the
ny

basic design conditions, consideration should be given to modifying the design specifications accordingly.
Ke

4.3 Protection against hazards

4.3.1 Calculation of swing


aft

The conductor swing shall be determined in accordance with Annex C or shall satisfy the conditions of 4.4.1,
and the most onerous condition shall be used to determine the design clearance.
Dr

4 KEBS 2010 All rights reserved


KS 1876-1:2010

rd
4.3.2 Proximity to buildings

da
Where the erection of power lines over or near to buildings is unavoidable, the clearance from the building to

an
the nearest live conductor shall be not less than that determined in accordance with Annex C.

4.3.3 Proximity to explosive magazines

St
To comply with the statutory requirements, when a power line is erected in the vicinity of an explosive

ya
magazine, the power line shall be separated from the magazine by a horizontal distance of not less than:

en
a) 15 m in the case of power lines that have spans of up to 30 m;

sK
b) 20 m in the case of power lines that have spans exceeding 30 m and up to 150 m; and

c) 30 m in the case of power lines that have spans exceeding 150 m.

da
It might be necessary to increase this distance if so required.

ite
4.3.4 Service connections

C
Where service connections are required, they shall be provided in accordance with applicable regulations
recommended by the Energy Regulatory Commission.

be
4.3.5 Anti-climbing devices
t to
Power line supports that can readily be climbed unaided shall be adequately protected to prevent
unauthorized persons from reaching a live conductor.
No

Anti-climbing devices should be installed as low as possible, but not within 3 m of the ground.

4.3.6 Power lines erected parallel to a tram route or trolley-bus route


g

If a power line is erected parallel to a tram route or trolley-bus route, the elevation and location of the
conductors should, wherever practicable, be such that contact cannot be made with a trolley boom that has
tin

left its trolley wire.

4.4 Combined and parallel routes


llo
Ba

4.4.1 Independent structures

If an overhead communication line and a power line or if two power lines are erected parallel to each other
for

along the same route, the separation between lines shall be such that, with both lines healthy, the clearance
between any conductor of the higher-voltage line and any conductor or earth wire of the lower-voltage line is
never less than the minimum phase-to-phase clearance applicable to the higher-voltage line.
rd

This clearance shall be maintained for all conditions up to maximum sag and maximum sideswing of the
da

conductors of either line, assuming that the other line remains in the templated position for still air, and
maximum sideswing occurs at design wind pressure at a minimum conductor temperature of the higher of 40
tan

C and 30 C lower than the templating temperature.

4.4.2 Common structures


aS

If lines are erected one above the other on common structures, the higher-voltage line shall be above the
lower-voltage line or communication line, and the vertical separation between the nearest conductors of any
ny

two lines shall be in accordance with the phase-to-phase clearances given in Annex C for the higher-voltage
line. It is recommended that the conductors of an LV overhead line be in vertical configuration in order to
Ke

maximize the chance of the occurrence of a permanent fault with resultant isolation, should a wire break.
NOTE 1 Particular attention to ensure compliance with statutory clearances (see Table C.1 of Annex C) will be necessary in cases
where a higher-mounted line could operate at full load (maximum sag) with a lower-mounted line at ambient temperature.
aft

An aerial bundled conductor may be considered to be an insulated cable for determining clearances.
Dr

KEBS 2010 All rights reserved 5


KS 1876-1:2010

rd
4.4.3 Protective earthing of parallel lines under construction

da
The degree of earthing protection required for a given line under construction is dependent upon the degree
of exposure to electrical hazards that exist within the construction area. For a project in an area exposed to

an
one or more energized lines where electrical contact could occur, extensive earthing requirements are
needed. The methods used for earthing depend on the degree of exposure to electrical hazards and on the
soil conditions at the site. For adequate protection of personnel, all equipment, conductors, anchors and

St
structures within the work area shall be bonded together and to earth. All earthing devices shall be so sized
as to withstand the largest induced current that could be expected owing to fault current on the energized

ya
line. The clamps selected for earthing cables shall have a current capability equal to that of the cable. The
earthing connection to ground shall be so arranged as to ensure its continuity in the event of disconnection

en
of any equipment earthing conductor.
NOTE Even where electrical contact is not considered a hazard, it is necessary to provide sufficient earthing such that electric shock

sK
caused by induced voltages from a nearby energized line is avoided.

4.5 Inductive and electrostatic interference with communication circuits

da
4.5.1 Submission to the telecommunications authority

ite
Details of all proposed power lines shall be submitted to the telecommunications authority for approval. The
way in which application is to be made is set out in Clause 9.

C
4.5.2 Noise induction

be
In general, the power required to operate communication equipment is very little and its operation can be
t to
impaired by relatively small voltages induced in the wires of a communication circuit that is parallel to a
power circuit.
No

Harmonics both of voltage and of current can be particularly objectionable, since the former cause
electrostatic interference and the latter cause electromagnetic interference with communication circuits. The
telecommunications authority is prepared to assist in carrying out tests to determine the presence and
g

magnitude of harmonics in a supply system if interference from this source is suspected. Telephone noise
can be mitigated to some extent by the application of a well-designed and well-coordinated transposition
system to the communication circuits.
tin

The horizontal separation between the power line and the telephone line should be in accordance with
Figures B.1, B.2, B.3 and B.4 of Annex B.
llo

See Annex B for further information.


Ba

4.5.3 Minimum separating distances from a safety aspect


for

4.5.3.1 Induced voltages that result from the proximity of an electricity supply plant can appear on systems
and equipment other than those intended for communication. Personnel who have access to such systems
and equipment shall be able to work in safety at all times. The distance between the power-frequency carrier
rd

and other systems (telecommunications, railways, pipelines, etc.) shall grant the level of immunity required in
safety regulations (see Annex A), without reference to the power-frequency carrier operator. These limits
da

require that induced voltages shall not exceed


tan

a) an r.m.s. voltage of 50 V in steady state,

b) an r.m.s. voltage of 430 V on power lines where an earth fault is cleared in more than 0.5 s,
aS

c) an r.m.s. voltage of 1 000 V on power lines where an earth fault is cleared in 0.35 s to 0.5 s, or
ny

d) an r.m.s. voltage of 1 200 V on power lines where an earth fault is cleared in less than 0.35 s.
Ke

4.5.3.2 Wherever practical, the separation between lines shall be such that, should either line overturn, it will
not touch any part of the adjacent line. If this separation cannot be provided, the supports of the line that
could touch the other line shall be designed to withstand the broken-wire condition of 6.3.
aft
Dr

6 KEBS 2010 All rights reserved


KS 1876-1:2010

rd
4.6 Electrolytic corrosion

da
In areas where d.c. traction services exist, there is a risk that stray currents might enter the earthing system
of a power line at one point, be transmitted along its earth wires or counterpoise and leave at some remote

an
point where the power line crosses, or is close to, a buried pipeline or cable route. Where this possibility
exists, agreement should be reached with the authority responsible for the other service, with regard to

St
protective measures to reduce the risk of electrolytic corrosion to the metalwork of either system. The
protective measures adopted will depend on the particular circumstances, but will usually take the form of
separating the two systems by an agreed minimum distance and providing interposing insulating material.

ya
Corrosion protection measures shall comply with ISO 11303, ISO 12944, ISO 14713, ISO 17834 and ISO
19840

en
5 Conductors and earth wires

sK
5.1 Material

da
5.1.1 Corrosion

All conductors and earth wires shall be of materials that have adequate corrosion resistance to the

ite
atmosphere to which they are likely to be exposed in service, or shall be suitably protected against corrosion.
Copper should always be installed below aluminium because copper salts washed down by rain will attack

C
aluminium. Particular attention should be paid to the possibility of corrosion where dissimilar metals are in
contact with one another.

be
5.1.2 Minimum size
t to
The minimum size of the conductor or, in the case of high-voltage lines, the minimum size of the bundle,
shall be determined by the following key factors:
No

a) the thermal rating (power transfer capacity) that is necessary, including consideration of the effects of
contingency outages on other system lines (reliability and stability criteria); and
g

b) the short-circuit current.

The size of the phase single conductor or of the phase bundle shall be selected to limit voltage drop, audible
tin

noise, radio interference, television interference and loss due to corona.


llo

5.1.3 Current-carrying capacity


Ba

5.1.3.1 Operational states

The following are the three main operational states for which current-carrying capacity calculations can be
for

done:

a) long duration/normal operation: it is preferable to limit the conductor temperature to between 50 C and
rd

60 C.
da

b) emergency operation: where it is expected that normal current-carrying capacity will be exceeded
temporarily for more than 20 min, a steady-state conductor temperature of up to 80 C can be assumed.
tan

c) short-duration emergency operation: where temperatures exceeding 80 C are assumed, the thermal
behaviour shall be assumed to be adiabatic.
aS

5.1.3.2 Calculation method


ny

Conventional calculation of current-carrying capacity is based on an approach that uses fixed, conservative
assumptions of meteorological data.
Ke

5.1.3.3 Copper conductors


aft

In the case of copper conductors, the normal operating temperature limits should not be exceeded.
Dr

KEBS 2010 All rights reserved 7


KS 1876-1:2010

rd
5.2 Maximum tensions

da
5.2.1 Limits

an
5.2.1.1 Statutory limits

St
The maximum tension in conductors and earth wires under the basic conditions of design (i.e. a temperature
of -5 C and a wind pressure of 700 Pa on a shape f actor of 0.6 of the projected area (see 4.2.3)) is limited to
be not more than 40 % of the breaking strength of the conductors or earth wires under high wind and low

ya
temperature conditions. This tends to lead to the use of high steel content conductors (aluminium
conductors, steel reinforced (ACSR)), which increase the mass and require stronger supports.

en
5.2.1.2 Alternative limits

sK
A more reasonable limit for maximum tension than that stated in 5.2.1.1 is an initial tension of 70 % of the
conductor's ultimate strength. Tensions should be calculated both

da
a) at the highest wind pressure, at a conductor temperature of 15 C, and

ite
b) at a minimum conductor temperature of -5 C, wit hout wind.

C
In practice, the conductor tension will usually be limited by the vibration limiting requirements (see 5.2.1.3),
and, generally in the initial stage after construction, does not exceed 40 % of the conductor's ultimate

be
strength.

5.2.1.3 Reduced limits to avoid fatigue failure due to vibrations


t to
Conductors and earth wires can vibrate, for instance, when subjected to steady low-velocity winds in open
terrain. One of the principal factors that lead to failure due to fatigue is the tension in the conductor during
No

periods of vibration.

Particularly in the case of copper conductors, the fatigue resistance of the metal depends to a large extent
g

on the cold working to which the conductor was subjected during manufacture.

If there is a possibility of conductor vibration, the risk of failure due to fatigue should be reduced by using a
tin

lower conductor tension than the maximum permitted by the statutory regulations.
llo

Tension limits for copper conductors, aluminium conductors, steel reinforced (ACSR), all aluminium alloy
conductors (AAAC) and steel earth wires, which are representative of commonly used conductors, are given
Ba

in 5.2.1.3.1 to 5.2.1.3.3. Since vibration takes place at low wind velocities, the limitations are all imposed on
a "no-wind" basis.
for

5.2.1.3.1 Copper conductors

The tension at 15 C should not exceed 26 % of the ultimate tensile strength of the conductor.
rd

5.2.1.3.2 ACSR and AAAC conductors


da

If vibration dampers are not used and the lines have relatively short spans, typically under 200 m, the initial
tan

tension at -5 C should not exceed 25 % of the ulti mate tensile strength of the conductor.

When vibration dampers are used, the following limitations are recommended:
aS

a) the initial tension at -5 C should not exceed 3 3.3 % of the ultimate tensile strength of the conductor;
ny

b) the initial tension at 15 C should not exceed 2 5 % of the ultimate tensile strength of the conductor; and
Ke

c) the final tension at 15 C should not exceed 20 % of the ultimate tensile strength of the conductor.
NOTE Whereas three limitations are recommended, it should be remembered that only one is effective in limiting the tension at any
given span. Limitation (a) above is introduced to ensure that the tension at the minimum design temperature of-5 C is kept within limits
aft

and is effective for very short spans where the effects of changes in temperature are large. Limitation (b) above limits the tension for
intermediate spans and limitation (c) above provides a greater safety margin for lines with long spans.
Dr

8 KEBS 2010 All rights reserved


KS 1876-1:2010

rd
Additional dampers are not required for bundled conductors if the tension is below a certain value 7,
proportional to the conductor weight:

da
T = 1 800 Mc

an
where

St
T is the limiting tension, in newtons; and

ya
Mc is the conductor weight per metre, in newtons per metre.

en
In the case of single conductors, it is not economical to use this value to limit initial tensions, and current
practice is to limit the final tensions. Initial tensions are limited by the support structure capacity on short

sK
spans.

5.2.1.3.3 Steel earth wires

da
In the case of galvanized steel earth wires of minimum breaking strength in the range 700 MPa to 1100 MPa,
the maximum tension at 15 C should be such that th e stress in the earth wire does not exceed 180 MPa.

ite
This criterion permits the use of tensions (at 15 C) of the following percentages of minimum breaking

C
strength:

be
a) 700 MPa wires: 25 %; and

b) 1 100 MPa wires: 15%.


t to
Earth wires are often strung to match, approximately, the sag of the conductors, and, when the conductors
are strung to the tension limits recommended for vibration, the earth wire tension limits stated above are
No

usually not exceeded. If the limits are exceeded, satisfactory performance can usually be obtained by the
addition of a damping device to the earth wires.
g

Because the conductors generally have a higher thermal expansion coefficient than the earth wire, in cold
weather the clearance between the two will reduce if the line is not operational. This could lead to flashovers
when the line is energized. As an additional safety margin and also to improve the shield angle at midspan,
tin

earth wires should sag to 85 % of the sag of the conductors.

5.2.2 Sag charts


llo

Generally, the sag charts required will depend on the limits chosen for conductor tensions. Sag information
Ba

should be obtained from the manufacturer of the chosen conductor, in order to produce charts.

The correction table for increased time between stringing and regulating should also be obtained from the
for

manufacturer of the chosen conductor.


rd

It is important that the tensions and assumptions used in templating also be used in the sag charts, and vice
versa, otherwise reduced clearances or excessive tensions can result.
da

5.2.3 Creep
tan

Over a period of time, the tension in a conductor tends to reduce to a value below that at which it was initially
strung, owing to creep or non-elastic stretch. The amount of creep that will be experienced depends upon
aS

the conductor tension, the procedure adopted during stringing and the electrical loading and temperature
experienced by the conductor in service. Copper conductors and steel earth wires are occasionally
prestretched before erection, to reduce the tendency to creep.
ny

In the case of aluminium conductors, it is usual to prepare initial (or stringing) charts and final charts in which
Ke

a maximum allowance is made for creep. Since the actual creep might be small and never reach the final
value, it is advisable to limit the tension to the maximum that will avoid vibration problems, rather than to
initial tensions (see 5.2.1.3). This, however, is costly, and a trade-off between initial vibration problems and
aft

extra-high supports is required.


Dr

KEBS 2010 All rights reserved 9


KS 1876-1:2010

rd
5.3 Joints

da
5.3.1 All joints shall be such that their current-carrying capacity exceeds that of the conductors that are
being joined. Tension joints shall have a breaking strength of at least 95 % of that of the conductor.

an
5.3.2 In areas that are conducive to corrosion, it is good practice to coat the joined ends and fill the fittings

St
with chemically inert corrosion-inhibiting paste.

6 Supports and fittings

ya
NOTE Guy wires that form an integral part of a guyed structure (as opposed to a self-supporting structure) are not dealt with in this

en
standard.

sK
6.1 Factors of safety

6.1.1 Minimum factors of safety

da
The factors of safety to be applied vary according to the type of structure and the type of load (see Table 1).

ite
The factors of safety given in Table 1 shall be applied in all cases where the basic conditions of design in this
standard are applied.

C
6.1.2 Wooden structures

be
Continuously loaded wooden members are those that have appreciable stresses applied to them all the time,
normally owing to bending. They include cross-arms placed in bending stress due to the mass of conductors
t to
and insulators, or by the application of longitudinal forces in the conductors at stayed angle and terminal
structures. Heavily loaded members of this type tend to take on a gradually increasing set owing to such
forces and accordingly larger factors of safety are required.
No

Members that have end-on loading due to the mass of conductors etc., are not considered to fall into the
class of continuously loaded members, because the stresses due to this kind of loading are small. Non-
g

continuously loaded members are those that are only intermittently or periodically stressed, for example
poles subjected to bending stresses due to wind.
tin

6.1.3 Other metal structures (e.g. aluminium)

The same factors of safety apply as for steel (see Table 1).
llo
Ba

6.1.4 Composite structures

The individual components of composite structures shall have factors of safety as specified for the relevant
for

materials in 6.1.2 and 6.1.3.


rd

6.2 Design loading


da

The total load on a support consists of transverse loads due to wind pressure on the conductors, earth wires,
insulators and fittings and on the support itself; vertical loads due to the mass of these items; transverse and
tan

longitudinal loads due to the tension in conductors and earth wires; and transverse, longitudinal and vertical
loads due to the tension in stay wires.
aS

6.2.1 Wind loads on wires

The transverse load on a support due to wind pressure on a conductor or earth wire may be assumed to be
ny

given by:
Ke

T1 = DWP d L1 K 0.6

where
aft

T1 is the transverse load, in newtons;


Dr

10 KEBS 2010 All rights reserved


KS 1876-1:2010

rd
DWP is the basic design wind pressure, in pascals;

da
d is the diameter of the wire, in metres;

an
L1 is the wind span, i.e. the sum of the adjacent half spans on each side of the support, in
metres; and

St
K is the shape factor for conductors = 0.6.

ya
A gust factor of 0.6 is used (see 4.2.3).

en
Table 1 Minimum factors of safety for various structure types

sK
1 2 3 4
Type of structure Factor of safety
Based on type- Based on Based on
tested structure ultimate breaking modulus of

da
strength rupture
Steel lattice structures and cross-arms 2.5 2.5
Solid-drawn steel poles 2.0 2.5

ite
Welded steel poles and steel poles with swaged or telescopic 2.2 2.5
joints
Stay-wire assemblies 2.5 2.5

C
Reinforced concrete spun poles 2.4 3.5
Mechanically vibrated reinforced concrete structures and 2.5 3.5

be
components
Other types of reinforced concrete structures and components 2.75 3.75
Wooden members not continuously loaded 3.5 4.41) 2.7
6.751)
t to
Wooden members subjected to continuous loading 5.5 4.5
1)
Recommended values.

NOTE In the case of steel lattice structures and steel components such as built-up cross-arms and bracing members, the factor
No

of safety shall be 2.5 on tested failing load or, when calculated, on tensile strength of tension members and on crippling strength of
compression members.

For templating clearances, it is necessary to allow for the possibility that maximum creep might occur and therefore the final sag
g

curves shall be used to check that the required clearances are obtained (see 6.7). When absolutely necessary, the effect of creep
can be overcome by resagging the conductors.

6.2.2 Wind loads on supports


tin

The transverse load due to wind pressure on the support itself may be assumed to be given by:
llo

T2 = K A DWP
Ba

where
for

T2 is the transverse load, in newtons;

K is a shape factor equal to 0.6 for round, elliptical or hexagonal poles, 1.0 for objects that
rd

present a full flat profile and 1.5 for lattice structures;


da

A is the projected area of the side of the structure on which the wind is assumed to act, in
square metres; and
tan

DWP is the basic design wind pressure, in pascals.


aS

6.2.3 Wind loads on insulators and fittings

The transverse load due to wind pressure on insulators and fittings may be assumed to be 0.6 times the
ny

projected area, in square metres, of the side of the insulators and fittings on which the wind is assumed to
act, multiplied by the actual design wind pressure, in pascals.
Ke

6.2.4 Vertical loads due to conductors


aft

The vertical load on a support due to the mass of a conductor or earth wire may be assumed to be given by:
Dr

KEBS 2010 All rights reserved 11


KS 1876-1:2010

rd
V = 9.81 W L2,

da
where

an
V is the vertical load, in newtons;

W is the mass of conductor per metre, in kilograms per metre; and

St
L2 is the mass span, i.e. the sum of the adjacent half spans on each side of a support, in

ya
metres.

en
6.2.5 Vertical loads due to supports, insulators and fittings

sK
The vertical load due to insulators, fittings and the support itself is that due to the mass of these items
applied at the appropriate point.

da
6.2.6 Normal loads due to conductor tension

In a line of approximately equal span lengths, the following loads are produced by conductor tension:

ite
a) longitudinal load on terminal structures :T

be
b) transverse load at angle structures : 2T sin
2
t to
c) tension in stay wire of terminal structure : T cosec

d) vertical load on terminal structure : T cot


No

where
g

T is the sum of maximum tensions in the conductors and earth wires, in newtons;

is the angle of deviation of the line, in degrees; and


tin

is the angle between the stay wire and the vertical, in degrees.
llo

6.2.7 Loads due to differential tension


Ba

In lines of unequal spans, there will be differences in the tension in different spans in conditions other than
those existing at the time of stringing. These differences will be balanced at suspension structures by
movement of the insulator strings but cannot be balanced at fixed intermediate points and at strain
for

structures, except by movement of the structure itself. The unbalanced load from this cause is not likely to
exceed 30 % of the tension in the wires at 15 C in still air. Where considerable differences in span length
rd

are likely to be encountered, it is recommended that provision for unbalanced longitudinal load on strain
structures be made in the design.
da

This provision shall include load cases where the wind is assumed to act perpendicular to the longest span
tan

of a strain tower.

6.2.8 Horizontal loads due to stay wires


aS

Where stay wires are used, they are usually designed to counteract the normal loads imposed on a structure
by tension in the conductors and earth wires. The horizontal component of tension in the stay wires can
ny

therefore be assumed to be equal to, and opposite to, the load discussed in 6.2.6.
Ke

6.3 Loading due to broken conductors

The statutory regulations (see Annex A) do not lay down any requirements regarding broken conductor
aft

conditions, except in the case of crossings (see Clause 7). The question of what provision should be made
for broken conductor conditions in the design of a power line is therefore a matter of individual choice.
Dr

12 KEBS 2010 All rights reserved


KS 1876-1:2010

rd
The greatest load that could be imposed on a structure owing to a broken conductor would occur under the
most onerous design conditions (see 4.2.1) and, if it is assumed that the breakage of a conductor applies a

da
load of the impact type, it could theoretically have a maximum magnitude of twice the conductor tension
under these conditions.

an
In practice, a load of this magnitude does not occur because of the way in which a conductor breaks, the
movement of insulator strings and structures, slippage of the conductor in the clamps, etc.

St
In the case of a line that has a single conductor per phase, the assumptions given in Table 2 in respect of

ya
the loads imposed on the structures that support the span in which the break occurs, expressed as
percentages of the maximum design load at a temperature of -5 C and when subjected to a wind pressure

en
of 700 Pa, are typical and can be used in most circumstances.

sK
Table 2 Loads imposed on structures owing to conductor breakage

1 2 3

da
Type of structure Load imposed on structure, as a percentage of maximum design load
Conductor attachment point Earth wire attachment point
Strain 100 100

ite
Suspension 70 100

C
The number of wires assumed to break simultaneously is again a matter of choice, but when broken
conductor conditions are allowed for in the design of structures, the most common practice is to allow for the

be
breakage of any one conductor or earth wire.

Since the incidence of conductor breakage is rare, it is not necessary to provide a large margin of safety and
t to
it is normal practice, when designing for broken conductor conditions, to provide a factor of safety of the
greater of 1.5 and 50 % of that called for in 6.1.
No

Structures are more likely to collapse or to be sabotaged than to have broken conductors, and so the design
for broken conductors needs to prevent a cascade of weak suspension structures from occurring up to the
g

next strain structure. Current practice is to apply a longitudinal load to one conductor attachment, and to one
earth wire attachment point, of a magnitude equal to the broken conductor load. This might not prevent a
second structure from collapsing, but will prevent a successive cascade. These loads are less severe than in
a situation in which all conductors are broken, and can yield a considerable saving in structure costs.
tin

6.4 Erection loads


llo

The design of a power line might allow the conductors and earth wires to be sagged to the design tension on
Ba

one side only of a strain structure, or the design might impose a limitation on the unbalanced loads that could
be applied to part or to the whole of that structure. The design shall allow for the mass of the linesmen and
their equipment. During the erection, maintenance or repair of a line, it is necessary to make due allowance
for

for unbalanced loads on strain structures, or on suspension structures fitted with temporary backstays, to
ensure that such work is performed in a way that ensures that applied loads do not exceed the strength of
the structure. Proper training of linesmen and the development of suitable techniques can minimize the
rd

impact of these additional loads on the structure design.


da

When a design does allow for the conductors and earth wires to be strung on one side only of a strain
structure, the design should allow for the following conditions:
tan

The conductor tension during erection would normally be that at about 15 C in still air and the strai n
structure should be capable of withstanding the load due to this tension, with a factor of safety of 1,5. It is
aS

possible, however, that the worst design conditions could occur in the period when the structure is strung
on one side only. To allow for this possibility, where provision is made for erection conditions, the
structure should be capable of withstanding the load due to conductor tension, at a temperature of -5 C
ny

and when subjected to a wind pressure of 700 Pa, with a nominal factor of safety of, say, 1.2.
Ke

Provision should also be made on all types of structures for the mass of the linesmen and their equipment
on the cross-arms. It is therefore recommended that all structures be capable of withstanding, with a
factor of safety of 1.5, the normal vertical loads plus an additional mass of 150 kg to 300 kg, depending
aft

on the size of the line, at each conductor attachment point. Consideration should also be given to the
vertical component of loads due to backstaying (if used).
Dr

KEBS 2010 All rights reserved 13


KS 1876-1:2010

rd
6.5 Foundations

da
6.5.1 Basic requirements

an
Structures shall be so set in the ground that they are capable of withstanding, without appreciable movement

St
in the ground and with an adequate factor of safety, the forces imposed by the loading on the structure under
normal or broken conductor or erection conditions. For more information, see KS 1886 and KS 1889.

ya
6.5.2 Type of foundation

en
Foundations of the concrete block or steel grillage type are generally used for lattice structures whereas

sK
wooden or steel poles are usually set direct in the ground and are provided, where necessary, with base
plates to resist upward and downward forces, and with kicking blocks or rings of concrete around the poles
to resist lateral forces.

da
Foundations for stays may consist of steel plates or reinforced concrete anchors.

ite
Generally, piles should only be used in good soils or rock, to resist either upward or downward forces.
Permissible skin friction values for design purposes will depend on the quality of the material under

C
consideration. For information on pile foundations, see KS 1886 and KS 1889.

be
6.5.3 Design assumptions

For checking resistance to downward or lateral forces, it is commonly assumed that, in the case of an
t to
ordinary soil and at the average foundation depths, the safe bearing pressure is about 200 kPa although the
value could be three or four times this value in hard rocky soil and, perhaps, one-third of this value in sandy
or boggy ground. In the case of wooden poles, foundation failure before pole failure is desired, and a value
No

of 345 kPa can be assumed. Wherever practicable, an appropriate value should be determined by site tests.

For checking resistance to upward forces, it is commonly assumed that the density of ordinary soil is about 1
g

3
600 kg/m and the angle to the vertical of the sides of the frustum of earth-resisting uplift may be taken as
25 in good soils to 0 in poor soils.
tin

6.5.4 Design basis


llo

In the case of poles set direct in the ground or structures that have single foundations in which the depth is
great compared with the width, the lateral earth pressure that results from the maximum lateral forces
Ba

applied to the pole or structure can be calculated from the following formula:

12 P( H + 0.67L )
m=
for

kWL2

where
rd

m is the earth pressure, in pascals;


P is the resultant maximum lateral load on the structure, in newtons;
da

H is the height above ground at which P acts, in metres;


L is the depth of the bearing face of the foundation, in metres;
tan

W is the width of the bearing face of the foundation, in metres; and


k is 1 for foundations of plane face, and 0.85 for circular foundations.
aS

NOTE The bearing face is that face that resists the lateral forces.

The maximum downward earth pressure is obtained by dividing the total vertical load (see 6.2.4, 6.2.5 and
ny

6.2.6) by the area of the base of the foundation. If the foundation is subjected to an overturning moment in
addition to the downward vertical load, then toe pressure could be the critical bearing case.
Ke

If calculations indicate that the maximum bearing pressure exceeds the permissible value assumed for the
soil in question, the bearing area of the foundation shall be increased.
aft
Dr

14 KEBS 2010 All rights reserved


KS 1876-1:2010

rd
In the case of poles, an increased bearing area in the lateral direction is often obtained by the addition of
kicking blocks at the bottom and at a point below ground level that is equal to one-third of the buried depth of

da
the pole, while an increased bearing area at the bottom is obtained by the addition of base plates.
The effective bearing area can also be increased by consolidating the area around the pole with soil, cement

an
or concrete or by the use of boulders firmly rammed into the hole.

Foundations shall be so designed that the mass of the foundation and the portion of the mass of the

St
structure which acts on the foundation plus the mass of earth-resisting uplift (see 6.5.3) are sufficient to
counteract, with an adequate factor of safety, the upward forces that might be applied.

ya
Upward forces owing to transverse, longitudinal or unsymmetrical vertical loads can arise on structures that

en
have more than one foundation and can also arise on all types of structures if the tensions in the conductors
and earth wires under normal, broken conductor or erection conditions have upward components. In the

sK
case of poles that are set direct in the ground and are subjected to a lateral load, the maximum earth
pressure can be calculated using the above formula. Should the value so calculated exceed permissible
lateral bearing values, then either the bearing area in the lateral direction shall be increased, or stays shall

da
be used. The effective bearing area can be increased by either consolidating the area around the pole with a
soil-cement mix or concrete, or by the addition of concrete rings at the bottom and at a point below ground
level that is equal to one-third of the buried depth of the pole.

ite
If a limit-states design approach is being used, foundations should be designed with a factor of safety of not

C
less than 2, to resist forces that arise from normal loading. Alternatively, a factor of safety shall be used that
is at least equal to that used for the structure (see 6.1) and that can resist forces that arise from broken

be
conductor or erection conditions, with the reduced factors of safety appropriate to these conditions (see 6.3
and 6.4).
t to
6.6 Insulators and fittings

6.6.1 Mechanical strength requirements


No

The mechanical strength of insulators and fittings used in strain structures should be such that they are at
least as strong as the minimum breaking strength of the phase or earth conductor to which they are
g

attached.

When conductors or earth wires are suspended in intermediate structures, the normal load on the
tin

suspension assembly owing to the vertical load of the wires and fittings, is small. The strength of suspension
assemblies should be such that a factor of safety of at least 1.5 is provided under the loading imposed under
llo

broken conductor conditions (see 6.3).


Ba

6.6.2 Electrical insulation levels and footing resistance requirements

The basic insulation level required for a transmission line of a given voltage depends on many factors, such
for

as the anticipated magnitude of voltages caused by switching surges or faults, the altitude of the line, the
possibility of contamination of insulators and the desired degree of immunity from lightning.
A discussion of these factors is beyond the scope of this standard, but it can be stated in general that the
rd

amount of insulation used on a line is a compromise between cost and service reliability.
da

Minimum insulation levels are given in Table 3, but it is emphasized that the insulation of each line should be
designed for its specific conditions. The list of insulation levels is in accordance with IEC 60071-1 and IEC
tan

60071-2. There is a slight deviation on the 66 kV and 330 kV levels, where slightly higher lightning and
switching voltage withstand levels were selected, based on specific experience of South African lightning
conditions.
aS

NOTE The designed line insulation levels will determine line equipment clearances. The minimum safety phase-to-earth clearances
shown in column 3 of Table C.1 of Annex C should not be interpreted as specifying line equipment clearances.
ny

In the range of rated voltage that is within the scope of this standard, there are three ranges with distinctive
insulation criteria and therefore insulation levels. They are given in 6.6.2.1 to 6.6.2.3.
Ke

6.6.2.1 Range A, for line voltages less than 52 kV


The main criterion is only the lightning impulse overvoltages, which can be severe when the load is
aft

disconnected on the low-voltage winding of a transformer connected to a transmission line. This impulse
voltage is usually reduced by the use of surge arresters.
Dr

KEBS 2010 All rights reserved 15


KS 1876-1:2010

rd
6.6.2.2 Range B, for 44 kV to 220 kV lines

da
The main criteria are the rated lightning impulse voltage and the rated 60 s power-frequency voltage, which
cover all internal overvoltages. The assumed footing resistances are

an
a) 132kV:20 , and

St
b) 220 kV: 30

ya
6.6.2.3 Range C, for 275 kV to 765 kV lines

en
The main criterion is the switching overvoltage (representing internal overvoltages), including the rated
lightning impulse overvoltages, based on footing resistances of

sK
a) 275 kV: 30 ,

da
b) 400 kV: 40 , and

c) 765 kV: 50 .

ite
The assumed insulation level factor is the ratio k between the rated impulse withstand voltage, and the

C
normal operation voltage divided by the safety factor. For example, for a 400 kV line

be
1050
k= = 3 .1
400 /1.2
t to
For conditions that deviate from those that are specified, the application of specific rated withstand voltages
is needed.
No

6.6.3 Insulation levels in polluted areas


g

The criteria for insulation coordination in conditions of pollution are based on IEC 60815 and on the
corresponding proposed creepage distances.

6.7 Clearances
tin

6.7.1 Vertical clearance to ground and structures


llo

The electrical conductors of supply lines (excluding overhead service connections) shall be so supported and
Ba

sagged that, measured at 50 C and in still air, th e minimum clearance above ground or to a structure is in
accordance with the values in columns 5 to 9 of Table C.1 of Annex C.
for

6.7.2 Horizontal clearances

Except in the case of low-voltage lines of insulated wire of a type approved by the Chief Inspector of
rd

Machinery, the horizontal clearance between any live conductor and a structure or the ground, measured at
50 C or at the maximum normal operating temperatur e and with maximum sideswing due to wind, shall be
da

in accordance with column 9 of Table C.1 of annex C.


tan

6.7.3 Minimum live-line working clearances

The minimum live-line working clearances are the clearances given in columns 10 and 11 of Table C.1 of
aS

Annex C, and assume a minimum safety distance calculated for still air and the maximum overvoltage which
corresponds with conditions under which live-line work is allowed, plus the ergonomical physical distance,
assumed to be 0.5 m as an average. It is related to the minimum distance between the linesman and live
ny

parts, and also to the minimum clear insulated stick length.


Ke

6.7.4 Clearance to earthed metal of support (tower-top clearances) (see Table C.1 of annex C)

In the design of supporting structures, the clearance has to be checked for three different conditions:
aft

a) still air: values in column 12. This corresponds to the maximum overvoltage due to lightning;
Dr

16 KEBS 2010 All rights reserved


KS 1876-1:2010

rd
b) normal (average) swing: values in column 13. This corresponds to the maximum switching over-voltage;

da
and

an
c) maximum swing: values in column 14: This corresponds to the maximum normal operating voltages.

In the case of an insulator string that is not movable perpendicular to the line direction (V-string, post-

St
insulators), only clearances for still air conditions are relevant.

ya
In the case of overvoltages that differ significantly from the values for which rated insulation levels were
established (see Table 3), or of different coincidences of overvoltages on the line and wind velocity,

en
equivalent clearances have to be calculated for all three conditions, using as a basis the safety clearance
values from column 3 of Table C.1 of annex C. (See also clause C.1 of Annex C.)

sK
Over reasonably level terrain, the swing angle of a suspension insulator string is likely to exceed 50 to the
vertical, and care shall be taken to ensure that vertical clearances to cross-arms and also horizontal

da
clearances to the body of the structure are maintained. The use of alloy conductors will lead to larger swing
angles than the equivalent ASCR conductors under the same conditions. Also, the smaller the diameter of
the conductor used, the more likely that the swing angle will exceed 50. Structures that support litt le vertical

ite
load, for example in a valley, will have larger swings and might need to be replaced by strain structures.

C
The swing angle of a jumper will vary with the length, mass and diameter of the conductor, and clearances
shall be checked for the maximum swing. Long jumpers might require the use of intermediate insulators or

be
stiffeners to avoid the risk of their swinging too close to the structure metalwork.
t to
No
g
tin
llo
Ba
for
rd
da
tan
aS
ny
Ke
aft
Dr

KEBS 2010 All rights reserved 17


St
ya
KS 1876-1:2010

en
Table 3 Minimum insulation levels for overhead lines

sK
1 2 3 4 5 6 7 8 9 10 11 12
Highest system r.m.s. System nominal System fault Rated peak Rated peak Phase-to-phase Rated peak 60 s r.m.s. Creepage distance over external insulation for line, in
voltage r.m.s. voltage level lightning impulse switching impulse ratio to the switching power- accordance with IEC 60815

da
withstand withstand voltage phase-to-earth impulse frequency mm
voltage (phase-to-earth) peak value withstand withstand Lightly Medium Heavily Very heavily
voltage voltage polluted polluted polluted polluted areas

ite
(phase-to- (phase-to- areas areas areas
phase) earth)

C
kV kV kA kV kV kV kV

be
12 11 751) 28 192 240 300 372

24 22 1251) 50 384 480 600 744

t to
36 33 1701' 70 576 720 900 1 116

48 44 20 250 95 770 960 1 200 1 500

No
72 66 20 350 140 1 150 1400 1 800 2200

100 88 25 380 150 1 600 2000 2500 3100

g
145 132 40 550 230 2320 2900 3600 4500

245 220 40 850 360 3920 4900 6100 7600

tin
300 275 50 1 050 850 1.5 1 300 4800 6000 7500 9000

362 330 50 1 300 950 llo 1.5 1425 5800 7200 9000 11 000
Ba
420 400 50 1425 1 050 1.5 1 550 6700 8400 10500 13000

800 765 50 2100 1 550 1.6 2400 12800 16000 20000 25000
for

1)
For unearthed lines with nominal system voltages of 11 kV, 22 kV and 33 kV, current practice is to achieve an insulation level of 300 kV.
rd
da
tan
aS

KEBS 2010 All rights reserved 18


ny
KS 1876-1:2010

rd
6.7.5 Clearance between phase conductors

da
To allow for a certain amount of out-of-phase swinging of phase conductors, it is usual to allow clearances

an
that exceed the values given in column 4 of Table C.1 of Annex C, between conductors of different phases of
a transmission line.

St
The allowance made is based on experience, and many empirical formulae have been used in this respect
by various authorities.

ya
All methods are based on the same general principle, that the spacing, in metres, is given by:

en
Dd + C c

sK
where

da
Dd is the differential conductor displacement, in metres, which depends on the wind
characteristics, the span length and the conductor characteristics; and

ite
Cc is the phase-to-phase clearance, in metres, which depends on the conditions on which the
calculations are based. This can be the clearance for the maximum expected overvoltage

C
(see column 9 of Table C.1 of Annex C), or the phase-to-phase clearance for the normal
operating voltage.

be
A more sensitive approach needs to assume, in the calculation of incremental movement, the sag of the
conductor (or tension), the length of the suspension string and the actual position between conductors in the
t to
span.

A simple formula for the spacing, in metres, which can be used to determine a reasonable horizontal spacing
No

between phase conductors of lines in a flat configuration and with the tensions recommended in 5.2, is:

5L + C
g

where
tin

L is the span length, in kilometres; and

C is the phase-to-phase clearance, in metres, as given in column 4 of Table C.1 of Annex C.


llo

In the case of lines with vertical configuration and with triangular configuration, the required spacing depends
Ba

on the configuration but would normally be less than 5L + C, owing to conductors' not being in the same
horizontal plane. In the vertical plane, conductor spacing shall take into account movement of conductors
during fault conditions, and could therefore exceed the phase-to-phase clearance.
for

6.8 Stay wires


rd

6.8.1 Purpose of stays


da

If a line is designed to have structures supported by stay wires, the stay wires are used to relieve the
tan

structure of the horizontal loading that is imposed by the tension in the conductors and earth wires.

Loads due to conductor and earth wire tension can arise from normal loading (see 6.2.6 and 6.2.7), or from
aS

broken conductors (see 6.3), or can be caused by erection loading (see 6.4).

6.8.2 Strength of stays


ny

6.8.2.1 Factor of safety


Ke

The applicable safety factors shall be used.


aft

The strength of any stay wire used should be such that its ultimate tensile strength is at least 2.5 times the
maximum tension calculated as indicated in 6.2.6 for normal conditions.
Dr

KEBS 2010 All rights reserved 19


KS 1876-1:2010

rd
6.8.2.2 Broken conductors

da
If stay wires are used to withstand loading due to a broken conductor or to erection conditions, the factor of
safety may be reduced, but the ultimate strength should be at least 1.5 times the maximum tensile force

an
calculated as indicated in 6.2.6 for the appropriate condition.

6.8.2.3 Stay rods

St
Higher factors of safety should be used for stay rods than for stay wires, especially where threaded portions

ya
are in tension. A factor of safety of 2.5 should be used for stay rods and one of at least 3 for their threaded
portions.

en
6.8.3 Location of stays

sK
Wherever practicable, a stay should be attached to the structure at the point of application of the load which
it is designed to counteract and should extend in a direction opposite to that of this load.

da
The location should be such that the clearance from the stay wire to any live parts of the line under all design
conditions is not less than the appropriate phase-to-earth clearance given in Annex C.

ite
Wherever practicable, stay wires should not pass under, over or near communication lines or the associated

C
poles. Where this is unavoidable, stays should be installed in such a way that linesmen working on the poles
or wires of the communication line cannot come closer than the appropriate phase-to-earth clearance to any

be
portion of the stay that could become alive under fault conditions.

6.8.4 Stay guards


t to
As stays are vulnerable to mechanical damage and can constitute a danger to pedestrian and vehicular
traffic, all stays near public paths and roadways should be fitted with stay guards. The stay guards should
No

enclose the stay wire from the top of the stay rod or bow to a point 2 m above the ground, should be of width
at least 50 mm and should be so coloured as to be conspicuous by day and by night.
g

6.8.5 Stay insulation

It is advisable to include insulation in the stay where the introduction of a stay will affect the BIL (see 3.1) of a
tin

structure. If a standard stay insulator would not provide adequate BIL, an insulated rod shall be used.
llo

7 Crossings
Ba

7.1 Crossings over roads, railways, tramways and communication lines

If the crossing span is strained off at each end, the crossing would not be affected by damage to the
for

conductors beyond the crossing. It is, therefore, unnecessary to fit arcing horns or armour rods to the live
end of insulators on strain or intermediate structures beyond the crossing span. In the crossing span itself,
however, arcing horns are required where the conductor would be damaged in the event of a flashover.
rd

Conventional armour rods shall not be used where the conductor is secured to a rigid insulator by means of
da

a preformed tie, because in the event of a breakage, the conductor can slide through the ungritted armour
rods and the crossing span clearance would consequently be reduced to below the minimum of 4.5 m. To
tan

overcome this problem, a full-wrap preformed twin tie should be used, which, in addition to fixing the
conductor securely to the rigid insulator, also protects the conductor against damage in the event of
flashover.
aS

7.2 Crossings over water


ny

No specific statutory requirements exist for crossings over water and, in general, normal ground clearances
should be provided. However, where such crossings are made over rivers, dams or lakes, which are, or
Ke

could be, used as recognized sailing waters, it is recommended that a clearance of 2.5 m plus the relevant
minimum outdoor clearance (see Annex C) be provided over the tallest boat mast likely to be encountered
on such water under conditions of normal high-water level and maximum conductor sag.
aft
Dr

20 KEBS 2010 All rights reserved


KS 1876-1:2010

rd
The tallest boat mast to be encountered on inland waters is not likely to exceed 15.5 m. Checks should,
however, be carried out for the particular stretches of waters that are to be crossed.

da
7.3 Joints in crossings

an
It is recommended that no joints be made in either the conductors or the earth wires of a crossing span at

St
the time of erection.

7.4 Crossings over other services

ya
Crossings over other services shall be in accordance with responses to the submissions required by Clause

en
9.

sK
8 Earthing

8.1 Support structures for power lines

da
Statutory regulations require that all metal power line structures and any metalwork on wooden or concrete
structures that could accidentally become alive and is accessible, i.e. within 2.4 m of the ground, be earthed.

ite
This requirement is satisfied by metal structures that have steel grillage foundations, since the structure is
connected to earth through its own metal legs.

C
In the case of steel structures on concrete foundations, it is usual practice to bond the structure to buried

be
earth conductors. t to
The effectiveness of the earthing of a structure can be determined by measuring its resistance to earth,
using a suitable instrument. If this resistance is so high that the structure is not earthed (see 3.4), a
supplementary earthing system should be provided. Guidance on the value of earth resistance required for
No

footings is given in 6.6.2. In addition, in the case of terminal structures, a footing resistance of less than 10
is recommended. Similarly, for the second, third and fourth structures from a substation, a footing resistance
of less than 20 is recommended.
g

It is generally not practicable to provide a sufficiently low earth resistance to ensure that there will be no
hazard to life in the event of a fault in a structure. The risk can, however, be reduced by the use of fast and
reliable protection so that the dangerous condition exists for only a short time, i.e. that taken by the
tin

protective devices to interrupt the supply to the line.


llo

8.2 Fittings
Ba

Power line fittings that are more than 2.4 m above ground do not have to be earthed.

If the ends of insulator assemblies attached to cross-arms of non-conducting material are not earthed or if
for

metal cross-arms mounted on structures of non-conducting material are not earthed, the line will have
maximum insulation to earth and therefore the best performance against flashovers caused by overvoltages.
rd

On the other hand, if contamination or puncture of line insulation permits the flow of heavy leakage currents
over wooden cross-arms or poles, these cross-arms or poles can become charred and can eventually fail.
da

8.3 Earth wires


tan

8.3.1 Purpose
aS

Earth wires are provided on power lines to reduce the number of outages caused by lightning, and to provide
a return path for earth fault currents.
ny

8.3.2 Position
Ke

To reduce the number of outages caused by lightning, earth wires should be located above the phase
conductors in such a position that the cover angle, i.e. the angle to the vertical from a line joining the earth
wire and the phase conductor, is reasonably small.
aft
Dr

KEBS 2010 All rights reserved 21


KS 1876-1:2010

rd
On the other hand, the height of the earth wire above ground should be as low as possible, to minimize the
number of lightning strokes that will strike the line.

da
The lightning strokes can appear anywhere along the line. However, the metal structures tend to attract a

an
greater proportion of strokes because they are higher. The midspan attracts a lower proportion of strokes
because it is closer to earth.

St
In the case of metal support structures, 60 % of strokes to the line can be considered as terminating on the
structure.

ya
Insulated support structures attract fewer lightning strokes. In this case, only 40 % of strokes terminate on

en
the structure.

sK
In the case of a single earth wire, a low cover angle can only be achieved by so increasing the height of the
earth wire that the best position represents a compromise that gives an acceptable cover angle but keeps
the earth wire reasonably low.

da
Cover angles in the range 30 to 45 are commonly u sed in the case of single earth wire systems. The
higher value is associated with low lightning activity, structure heights below the range of 25 m to 30 m and

ite
less important power lines.

C
If two earth wires are used, they can be located to give low cover angles to the outer conductors of the line
by spreading the earth wires apart instead of raising them vertically.

be
It is therefore common practice, when two earth wires are used, to provide the outer conductors with cover
angles of 30 or less, the height of the earth wire s being as low as possible, consistent with giving good
t to
protection, say 60 cover angle, to the conductors between the earth wires.

If earth wires are only used to provide a return path for earth fault currents, they should preferably be located
No

below the line conductors so that, if a conductor breaks, there is a possibility that it will make contact with the
earth wire.
g

8.3.3 Earthing of earth wires

The voltage imposed by a lightning stroke on an earth wire will rise rapidly to a value such that flashover will
tin

occur from the earth wire to the phase conductors close to the point where the lightning strikes, unless the
lightning current is by-passed to earth through a low impedance.
llo

The lightning protection that is provided by an earth wire therefore depends on how well and how frequently
the wire is earthed. For this reason, earth wires installed as lightning protection should be connected to earth
Ba

at each power line support, either through the support in the case of metal supports, or by an earthing
conductor in the case of supports of non-conducting materials.
for

To avoid flashover across the line insulation in a structure owing to the high voltage on the earth wire, the
resistance to earth should be as low as possible. In the case of a 22 kV line with the insulator assemblies
rd

earthed at the point of attachment to the cross-arms, flashovers across the line insulators might be expected
for
da

a) 50 % of the lightning strokes that terminate on the earth wire when the resistance to earth is 10
tan

b) 80 % when the resistance to earth is 20 and


c) 98 % (or virtually all strokes) when the resistance to earth is 50 .
aS

Since it is often difficult to attain an earth resistance of less than 50 earth wires are seldom economically
justified to improve the lightning performance of lines that operate at 22 kV or at lower voltages.
Where wooden poles are used as supports on lines that operate below 33 kV, lightning protection can
ny

generally be improved by omitting earth wires and leaving the insulator assemblies unearthed, thus keeping
the insulation level as high as possible. This form of construction has the disadvantage that a direct stroke to
Ke

a pole can cause it to shatter, but the probability of this happening is reasonably low.
Earth wire insulators that comply with IEC 60383-1 and that are fitted with a spark gap set to 6 mm shall be
aft

installed in the following circumstances:


a) at terminal structures not connected to the main substation earth mat;
Dr

22 KEBS 2010 All rights reserved


KS 1876-1:2010

rd
b) at traction substation terminal structures;
c) on the second, third, fourth and fifth structures from the substation if any or all of these structures have

da
footing resistances of less than 10 ; and

an
d) at all structures within 800 m of electrified railway tracks or metal pipelines where the power line either
crosses, or runs parallel to, the railway or pipeline.

St
9 Procedure to be adopted before the construction of power lines

ya
9.1 General

en
Attention is drawn to the necessity of notifying the appropriate authorities in accordance with statutory
requirements (see Annex A) before starting the construction of any new power line or an extension of any

sK
existing line.

The procedure to be adopted will vary according to the line route conditions and will necessitate the

da
submission of a written notification to one or more of the authorities given in 9.3 to 9.9 (inclusive).

9.2 Environmental impact

ite
Cognizance should be taken of the Environmental Management Coordination Act, EMCA, 1998.

C
9.3 Telecommunications authority

be
In every case, and not less than one month before any construction is started, the owner of a proposed
t to
power line shall submit a written notification, in duplicate, to the telecommunications authority, giving the
following particulars of the proposal:
No

a) a map or plan indicating the position of the entire length of proposed power line in relation to
topographical features and its distance from existing communication lines, roads and railways;
b) the proposed operating voltage and, if a future change is contemplated, the ultimate operating voltage
g

between conductors;
c) a sketch showing the typical arrangement of the line conductors and earth wires and their heights above
ground;
tin

d) the location of any power line transpositions;


llo

e) the location of any taps off the power line;


f) the maximum time for an earth fault to be cleared;
Ba

g) the maximum current in the event of an earth fault;


h) the maximum operating current of the route; and
for

i) the type of earth conductor used on the route.


rd

9.4 Appropriate road authority


da

When the proposed power line is to be constructed over, or within the reserve of, a public road, permission
tan

shall be sought from the appropriate road authority.

9.5 Civil Aviation Authority


aS

It is necessary that proposals for the construction of any power line be submitted to the Civil Aviation
Authority, to ensure that the provisions of the Aviation Act are met. This is necessary to avoid creating
ny

obstructions in the vicinity of existing or proposed aerodromes or airports.


Ke

9.6 Other electricity supply authorities


If the proposed power line is to be constructed over, or within the servitude of, another electricity supply
aft

authority, the permission of that authority shall be sought, and the safety clearances adhered to.
Dr

KEBS 2010 All rights reserved 23


KS 1876-1:2010

rd
Annex A

da
(normative)

an
Principal Acts, ordinances, regulations and instructions pertaining to overhead
power lines

St
The Advertising on Roads and Ribbon Development Act, 1940 (Act 21 of 1940).

ya
The Air Navigation Regulations issued in terms of the Aviation Act, 1962 (Act 74 of 1962).

en
The Electricity Act, 1987 (Act 41 of 1987).

sK
The Environment Conservation Act, 1989 (Act 73 of 1989).

da
The Explosives Act, 1956 (Act 26 of 1956).

The Fencing Act, 1963 (Act 31 of 1963).

ite
The Forest Act, 1984 (Act 122 of 1984).

C
The Minerals Act, 1991 (Act 50 of 1991), and subsequent amendments and regulations issued thereunder.

be
The Occupational Health and Safety Act, 1993 (Act 85 of 1993), and subsequent amendments and
regulations issued thereunder.
t to
The Post Office Act, 1958 (Act 44 of 1958), and the Postmaster-General's regulations issued in terms of that
Act.
No

Highway Commission; Road Ordinance.


g
tin
llo
Ba
for
rd
da
tan
aS
ny
Ke
aft
Dr

24 KEBS 2010 All rights reserved


KS 1876-1:2010

rd
Annex B

da
(normative)

an
Guidance on power lines and communication circuits

St
ya
B.1 General

en
This guidance has been prepared to provide authorities with sufficient information to enable them to conduct
a survey that will enable the suitable positioning of power lines in relation to overhead communication
circuits, having regard to noise interference in the latter circuits.

sK
B.2 Approval of the Telecommunications Authority

da
The erection of a power line in conformity with this guide does not imply the automatic approval of the
Telecommunications Authority. It is essential that the supply authority submit details of all power proposals in

ite
terms of the relevant Act.

C
B.3 Co-ordination of transpositions

be
While it is desirable to co-ordinate overhead communication line transpositions with power line
transpositions, or other discontinuities in the power line, in practice, irregular or slanting exposures make
such co-ordination difficult or of little value. Experience has shown that, provided that a communication line is
t to
frequently transposed, the co-ordination of transpositions is of secondary importance. However, it is required
that the supply authority indicate all proposed power line transpositions on the plan of the proposed power
line when submitting it for approval.
No

B.4 Minimum separating distances


g

The minimum horizontal separating distances between power lines and communication lines shall be
determined from the curves given in figures B.1, B.2, B.3 and B.4. These curves have been based on
considerations of the inductive and electrostatic interference with communication circuits.
tin

B.4.1 Maximum range of curves


llo

Since these curves apply to power line exposures not exceeding 48 km in length, the curves shall not be
extrapolated.
Ba

B.4.2 Several exposures in series


for

In practice, it is generally found that topographical features at power line crossings over communication lines
do not permit the exact minimum separating distances being maintained throughout the exposure. Where a
particular power line and a particular communication line are involved in this way, the curves may be applied
rd

to each of the resulting exposures separately. The separating distances given by the curves should,
da

wherever practicable, be increased by a factor of 1.5, or as near to this as possible, to cater for the additive
effect of several exposures in series.
tan

B.4.3 Telephone interference factors (TIP)


aS

In the case of power line voltages up to and including 33 kV, a TIP of 10 % has been used. In the case of
lines of a higher voltage, a TIP of 5 % has been adopted, since it is likely that interfering factors (such as
phase balance, wave form, etc.) are more closely controlled on such lines.
ny

B.4.4 Psophometric noise


Ke

The curves are based on the recommendations of the International Telecommunication Union (CCITT),
namely that the noise induced in a communication circuit should not exceed 2 mV e.m.f. when the noise is
aft

measured with a psophometer fitted with the CCITT telephone weighting network. The 2 mV e.m.f. is
equivalent to 1 mV potential difference, as measured on the psophometer.
Dr

KEBS 2010 All rights reserved 25


KS 1876-1:2010

rd
B.5 Ultimate terminal of power line route

da
If, in submitting a power line proposal to the Telecommunications Authority for approval, the supply authority
is aware that the power line might be extended beyond the immediate proposal at some future date, the

an
probable ultimate terminal of the power line route should be indicated by the supply authority.

B.6 Power line and communication line crossings

St
The power line route should cross the communication line route as nearly as possible at right angles. Where

ya
this is impracticable, the following deviations from a right-angle crossing are permitted, provided that the
terms of B.4.2 are observed:

en
Table B.1 Maximum deviation angles on communication line crossings

sK
1 2
Voltage of route Permissible deviation from right angle

da
Below 48 kV 45
48 kV and above 30

ite
B.7 Power line faults

C
Where power line faults are likely to cause acoustic shock of serious proportions, the supply authority
concerned and the Telecommunications Authority should co-operate in providing preventive measures.

be
B.8 Exposures exceeding 48 km in length
t to
Where the power line proposal involves exposures exceeding 48 km in length, the supply authority should
refer the project to the Telecommunications Authority after a preliminary survey but before a detailed survey.
No

It will then be possible to indicate the minimum separations with greater accuracy in each particular case.

B.9 Radio receiving stations


g

If power lines exceeding 44 kV have to be erected in the vicinity of radio receiving stations, the separation
required between the power line and the radio receiving aerials is of the order of 1.5 km. This separation
depends on several factors, and the appropriate authority (usually the Telecommunications Authority) will
tin

indicate, in the case of every proposal, what the separation should be.
llo
Ba
for
rd
da
tan
aS
ny
Ke
aft
Dr

26 KEBS 2010 All rights reserved


KS 1876-1:2010

rd
da
an
St
ya
en
sK
da
C ite
be
t to
No
g
tin
llo
Ba
for
rd
da
tan
aS
ny

Figure B.1 Power line separation distance versus exposure to parallel communication lines (up to
33 kV)
Ke
aft
Dr

KEBS 2010 All rights reserved 27


KS 1876-1:2010

rd
da
an
St
ya
en
sK
da
C ite
be
t to
No
g
tin
llo
Ba
for
rd
da
tan
aS
ny

Figure B.2 Power line separation distance versus exposure to parallel communication lines (from
Ke

44 kV to 132 kV)
aft
Dr

28 KEBS 2010 All rights reserved


KS 1876-1:2010

rd
da
an
St
ya
en
sK
da
C ite
be
t to
No
g
tin
llo
Ba
for
rd
da
tan
aS

Figure B.3 Power line separation distance versus exposure to parallel communication lines (from
ny

275 kV to 400 kV)


Ke
aft
Dr

KEBS 2010 All rights reserved 29


KS 1876-1:2010

rd
da
an
St
ya
en
sK
da
C ite
be
t to
No
g
tin
llo
Ba
for
rd
da
tan
aS

Figure B.4 Power line separation distance versus exposure to parallel communication lines (for
ny

765 kV)
Ke
aft
Dr

30 KEBS 2010 All rights reserved


KS 1876-1:2010

rd
Annex C

da
(informative)

an
Clearances required for power lines that cross other services

St
C.1 Table C.1 shows the minimum clearances.

ya
C.2 The values in Table C.1 are based on the assumption that clearances will be determined for a
minimum conductor temperature of 50 C and for a sw ing angle that corresponds to a wind pressure of 500

en
Pa: provided that where, under normal conditions, power line conductors operate at a temperature above 50
C, the clearance at the higher temperature at whic h the conductors operate is in accordance with the
clearance indicated in the table.

sK
C.3 The minimum safety clearances in column 3 of Table C.1 should not be interpreted as specifying line

da
equipment clearances. The line equipment clearances are based on the equipment insulation level for the
appropriate voltage level of the power line, the latter being chosen to ensure a flashover across the
insulation of the line rather than from the line to other objects within the basic clearance in the case of an

ite
overvoltage.

C
Table C.1 Minimum clearances for power lines that cross other services

be
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Highest System Safety Safety Minimum vertical clearances Minimum live- Tower-top clearances
system nominal clearance clearance line working
r.m.s. r.m.s. phase-to- phase-to- clearances
t to
voltage voltage earth phase m m m
kV kV m m Outside In Roads in To To Phase- Phase- Still air Normal Maximum
town- town- townships, communica- buildings, to- to- conditions swing swing
No

ships ships and tion lines or poles and earth phase


proclaimed between structures,
roads, power lines not part of
railways, and cradles power
g

tramways lines
1 4.9 5.5 6.1 0.6 3.0
7.2 6.6 0.15 0.2 5.0 5.5 6.2 0.7 3.0
12 11 0.20 0.3 5.1 5.5 6.3 0.8 3.0
tin

24 22 0.32 0.4 5.2 5.5 6.4 0.9 3.0


36 33 0.43 0.5 5.3 5.5 6.5 1.0 3.0
48 44 0.54 0.61 5.4 5.5 6.6 1.1 3.0 0.8 1.1 0.54 0.5 0.15
llo

72 66 0.77 0.89 5.7 5.7 6.9 1.4 3.2 0.9 1.3 0.77 0.71 0.20
100 88 1.00 1.14 5.9 5.9 7.1 1.6 3.4 1.0 1.5 1.00 0.92 0.24
Ba

145 132 1.45 1.68 6.3 6.3 7.5 2.0 3.8 1.2 1.9 1.45 1.30 0.35
245 220 2.1 2.7 7.0 7.0 8.2 2.7 4.5 1.7 2.8 2.1 1.88 0.6
300 275 2.5 3.6 7.4 7.4 8.6 3.1 4.9 2.0 3.4 2.5 2.2 0.7
362 330 2.9 4.3 7.8 7.8 9.0 3.5 5.3 2.3 4.1 2.9 2.6 0.86
for

420 400 3.2 4.8 8.1 8.1 9.3 3.8 5.6 2.8 4.8 3.2 2.9 1.0
800 765 5.5 8.9 10.4 10.4 11.6 6.1 8.5 5.5 9.7 5.5 5.2 1.9
d.c. _ 3.7 _ 8.6 8.6 9.8 4.3 6.1
rd

533 kV 1)
1)
Maximum voltage to earth, for which insulation is designed.
da

NOTE The assumption on which the values are based is given in clause C.2.
tan
aS
ny
Ke
aft
Dr

KEBS 2010 All rights reserved 31

También podría gustarte