02 MOVIMIENTO DE TIERRAS
02.01 EXCAVACION DE ZAPATAS EN ROCA SUELTA BAJO AGUA, CON MAQUINARIA 2 5.75 4.00 5.88 135.24
02.02 EXCAVACION MASIVA MANUAL PARA ESTRUCTURAS 2 30% 40.57 40.57
02.03 EXCAVACION DE CIMIENTOS MURO DE ENCAUSAMIENTO EN ROCA SUELTA 4 6.00 4.00 3.80 91.20
02.04 RELLENO CON MATERIAL PROPIO Y COMPACTADO, CON EQUIPO 2.25 16.00 3.00 3.50 168.00
02.05 ELIMINACION DE MATERIAL EXCEDENTE 2.25 8.00 4.00 1.00 32.00
03 CONCRETO CICLOPEO
03.01 CONCRETO CICLOPEO FC=175 KG/CM2 + 70% P. G. FALZA ZAPATA 2 5.75 4.00 0.50 11.50
03.02 CONCRETO FC=175 KG/CM2 +40 % PG. MURO DE ENCAUSAMIENTO
4 area estribo 15.472 15.47
4 area estribo 6.525 6.53
Volumenes 4 Apromedio 10.999 6.00 65.99
03.03 ENCOFRADO Y DESENCOFRADO MURO DE ENCAUSAMIENTO (2 usos)
Area muro de encausamiento mayor 13.70
Area muro de encausamiento menor 8.30
Area muro de encausamiento Promedio 4 11.00 7.00 77.00
Tapa 4 6.54 7.00 45.78
04 CONCRETO ARMADO
4.01 LOSA DE CIMENTACION
04.01.01 CONCRETO F'C=245 KG/CM2. PARA LOSA DE CIMENTACION 2 5.75 4.00 1.00 23.00
04.01.02 ACERO F'Y=4200 Kg/cm EN LOSA DE CIMENTACION 1 1,961.1 1,961.10
4.02 COLUMNAS
04.02.01 CONCRETO F'C=280 KG/CM2 EN COLUMNAS 4 2.20 0.55 8.20 9.92
04.02.02 ACERO F'Y=4200 Kg/cm EN COLUMNAS 1 6,802.7 6,802.68
04.02.03 ENCOFRADO Y DESENCOFRADO CARA VISTA EN COLUMNAS 4 5.55 8.20 45.51
4.03 PLACAS
04.03.01 CONCRETO F'C=280 KG/CM2 EN PLACAS 2 3.65 0.20 6.20 4.53
04.03.02 ACERO F'Y=4200 Kg/cm EN PLACAS 1 1,511.7 1,511.69
04.03.03 ENCOFRADO Y DESENCOFRADO CARA VISTA EN PLACAS 2 7.70 6.20 47.74
4.04 VIGAS PRINCIPALES
04.04.01 CONCRETO F'C=280 KG/CM2 EN VIGAS PRINCIPALES 2 30.00 0.55 1.85 30.53
04.04.02 ACERO F'Y=4200 Kg/cm EN VIGAS PRINCIPALES 1 11,316 11,316.10
04.04.03 ENCOFRADO Y DESENCOFRADO CARA VISTA EN VIGAS PRINCIPALES 2 30.00 4.25 127.50
4.05 VIGAS DIAGRAGMA
04.05.01 CONCRETO F'C=280 KG/CM2 EN VIGAS DIAGRAGMA 4 3.65 0.40 1.10 1.61
04.05.02 ACERO F'Y=4200 Kg/cm EN VIGAS DIAFRAGMA 1 516.49 516.49
04.05.03 ENCOFRADO Y DESENCOFRADO CARA VISTA EN VIGAS DIAFRAGMA 4 3.65 2.60 9.49
4.06 VIGAS DE CORONACION
04.06.01 CONCRETO F'C=280 KG/CM2 EN VIGAS DE CORONACION 2 3.65 2.20 0.50 4.02
04.06.02 ACERO F'Y=4200 Kg/cm EN VIGAS DE CORONACION 1 613.70 613.70
04.06.03 ENCOFRADO Y DESENCOFRADO CARA VISTA EN VIGAS DE CORONACION 2 3.65 2.70 9.86
4.07 TABLERO SUPERIOR
04.07.01 CONCRETO F'C=280 KG/CM2 EN TABLERO SUPERIOR 1 34.90 4.75 0.22 36.47
04.07.02 ACERO F'Y=4200 Kg/cm EN TABLERO SUPERIOR 1 3,689.1 3,689.06
Tablero Borde 2 5.80 3.65 0.22 4.66
Tablero Central 3 5.60 3.65 0.22 4.50
04.07.03 ENCOFRADO Y DESENCOFRADO EN TABLERO SUPERIOR
Tablero Borde 2 5.80 3.65 21.17
Tablero Central 3 5.60 3.65 20.44
ITEM DESCRIPCION N de MEDIDAS Parcial
Veces Largo Ancho Alt.Prom.
4.08 VEREDAS
04.08.01 CONCRETO F'C=280 KG/CM2 EN VEREDAS 2 34.90 1.05 0.20 7.33
04.08.02 ACERO F'Y=4200 Kg/cm EN VEREDAS 1 1,388.1 1,388.06
04.08.03 ENCOFRADO Y DESENCOFRADO EN VEREDAS 2 34.90 0.90 31.41
4.09 COLUMNETAS
04.09.01 CONCRETO F'C=280 KG/CM2 EN COLUMNETAS 30 0.20 0.15 0.90 0.03
04.09.02 ACERO F'Y=4200 Kg/cm EN COLUMNETAS 1 176.50 176.50
04.09.03 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS 30 0.70 0.90 0.63
06 FALSO PUENTE
06.01 CONCRETO CICLOPEO FC=140KG/CM2 + 30 % PM. 1 4.75 1.05 1.00 4.99
06.02 ENCOFRADO Y DESENCOFRADO 1.0 2,800 2,800.00
08 OBRAS VARIAS
08.01 SELLADO DE JUNTAS 2 35.00 35.00
08.02 DRENAJE CON TUBERIA PVC SAP 3" 26 0.80 0.80
08.03 BARANDA METALICA TUB. F G 2" 6 34.90 34.90
09 PINTURA
09.01 PINTURA ESMALTE EN COLUMNETAS 30 0.70 0.90 0.63
09.02 PINTURA EN BARANDAS METALICAS 2 98.00 98.00
09.03 PINTURA ESMALTE EN SARDINELES DE PUENTE 2 34.90 0.20 6.98
10 FLETE
10.01 FLETE TERRESTRE 1 1.00 1.00
10.02 FLETE TRANSPORTE LOCAL 1 1.00 1.00
11 OBRAS DE SEALIZACION
11.01 CARTELES DE SEALIZACION 1 1.00 1.00
12 PLACA RECORDATORIA
12.01 PLACA RECORDATORIA 1 1.00 1.00
6.00.00 APOYOS
6.01.00 APOYO FIJO 2 1.00 1.00
6.02.00 APOYO MOVIL 2 1.00 1.00
10.00.00 FLETE
10.01.00 MOVILIZACION Y DESMOVILIZACION EQUIPO 1 2.00 2.00
10.02.00 FLETE TRANSPORTE LOCAL 1 4.00 4.00
60.00 m2
48.00 m2
146.00 m2
1.00 GLB
1.00 GLB
40.00 ML
1.00 und
189.34 m3
81.14 m3
364.80 m3
378.00 m3 635.28
72.00 m3
23.00 m2
263.96 m3 307.96
61.89
26.10
263.96 44.00
245.56 m2 2 usos
308.00
183.12
46.00 m3
1,961.10 kg
39.69 m3
6,802.68 kg
182.04 m2
9.05 m3
1,511.69 kg
95.48 m2
61.05 m3
11,316.1 kg
255.00 m2
6.42 m3
516.49 kg
37.96 m2
8.03 m3
613.70 kg
19.71 m2
36.47 m3
3,689.06 kg
9.31
13.49
103.66 m2
42.34
61.32
Total Und. Observ.
14.66 m3
1,388.06 kg
62.82 m2
0.81 m3
176.50 kg
18.90 m2
122.15 m2
19.90 m2
5.0 m3
2,800.0 m2
3.00 und
18.00 und
5.00 und
70.00 m
20.80 m
209.40 m
18.90 m2
196.00 m
13.96 m2
1.00 GLB
1.00 GLB
1.00 und
1.00 und
32.00 M2 32.00
126.00 M3 126.00
54.00 M3 54.00
42.00 M3 42.00
216.00 M3 216.00
10.00 M.L 10.00
Total Und. Observ.
30.00 M 30.00
M3 179.63
30.66 M3
25.40 M3
15.88 M3
42.34 M3
0.72 M3
30.84 M3
4.74 M2
3.41 M2
4.08 M2
4.28 M
3.65 M
3.97 M
64.63 M3
M2 203.62
51.10 M2
45.26 M2
4.32 M2
51.46 M2
42.60 M2
8.88 M2
48.00 M2 48.00
56.00 M2 56.00
52.50 M2 52.50
3.56 M3 3.56
M2 25.18
24.30 M2
0.88 M2
1,034.93 KG 1,034.93
25.18
24.30 M2
0.88 M2
2.06 M3 2.06
M2 4.62
2.50 M2
2.12 M2
303.51 KG 303.51
2.50 M2 4.62
2.12 M2
9.56 M3 9.56
M2 29.22
7.96 M2
15.66 M2
5.60 M2
1,207.18 KG 1,207.18
3.00 ML 3.00
5.84 M2 5.84
Total Und. Observ.
ML 24.80
17.00 ML
7.80 ML
6.2 M2 6.23
9.0 ML 9.00
55.00 M3 55.00
68.00 M3 68.00
55.00 M3 55.00
1,961.1
967.092
936.920
6,802.68
2,985.440
895.632
895.632
900.480
483.840
443.520
1,511.69
462.726
674.784
330.150
11,316.1
2,858.400
327.128
182.784
112.896
179.200
857.520
2,858.400
111.600
161.280
1,429.200
444.640
80.600
49.600
516.100
356.720
143.360
117.600
152.880
46.592
516.487
189.952
134.400
46.500
130.592
631.703
301.720
311.584
3,689.06
699.205
1,045.785
860.560
976.066
1,388.06
537.850
373.984
206.118
229.680
176.501
53.760
117.600