Documentos de Académico
Documentos de Profesional
Documentos de Cultura
OPERATION GUIDELINES
1. INTRODUCTION
CONTENTS
1.1 AIMS
1.2 REVISIONS
1. INTRODUCTION
1.1 AIMS
This Guideline is intended to provide information on the operations
of Civil & Structural Engineering Division for engineer and technical
staff in CPG Consultants office. It is particularly aimed at new
members of staff but is also intended as a reference Guideline for
existing staff members.
1.2 REVISIONS
It is intended that this Guideline will be revised from time to time to
accommodate improvements to standards or systems. It would be
helpful if staff could provide feedback on the Guideline and report
difficulties, errors or omissions to their principal engineers.
Updates will be issued as new revisions on a page-by-page basis.
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
1. INTRODUCTION
A) BACKGROUND
In the process of developing the new QMS documents for CPG Consultants
to cater for ISO9000: 2000, it was realized that while the QMS takes care of
the quality part of the work, knowledge sharing and teaching elements for
the purpose of guiding the staff in the routine work processes are lacking. It
was felt that there was a need to re-look into some of the existing guidelines
prepared by PWD previously.
One such document was the Office Manual (OM) of the four main services,
namely Architecture, C&S, M&E and QS. The existing Model Programme
with explanatory notes and also the Roles of PM/PD and Consultants would
also be referred to. Other supporting documents like SIA Contract, Master
Agreement, Staff Handbook, etc. were included as reference documents as
well.
From the existing QAM, QAP and OM it can be seen that while each
discipline had their own work processes laid out as a guide to the
individual Division staff members, there is a lack of a guide to the
Multi-Discipline Process for major projects handled by CPG
Consultants.
1. INTRODUCTION
The MPFC will serve as the LINK to connect the Process Flow of the
four Services, i.e. Arch, C&S, M&E, QS.
C) Model Programme
The Gantt chart will compliment the MPFC and serves as a visual
presentation of Project Schedule in a Time-Line format.
The RPTM will thus replace the PM/PD document and the Explanatory
Notes for the Model Programme.
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
1. INTRODUCTION
Concept Concept
Schematic Design Schematic Design Schematic Design Design Development
Design and Tenders
Design Design Design Design Development
Development Development Development Construction
M&E
Structural
Notes:
1) Definition of stages and key tasks within each stage is consistent with descriptions in SIA.
2) Activities and explanatory notes from Model Program had been incorporated into PIPD.
3) Scope from M&E and Structural from Model Program had been incorporated into PIPD
4) Roles and Duties of Consultants had been incorporated into RTPM
5) TLS and MA stages had not been incorporate
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
1. INTRODUCTION
A) INTRODUCTION
1. INTRODUCTION
1) Preliminary Services
2) Schematic Design
3) Design Development
4) Contract Documentation
5) Construction
6) Final Completion
The six main stages are similar to those found in the SIA Contract
Document, and would be adopted by the QA Committee in the
updating the QA system to meet the ISO 9000: 2000 Standards.
Key tasks within each of the six main stages were also identified by the
various disciplines and incorporated into the MPFC.
1) The leading consultant for the project shall assume the role of the
PD.
3) When Civil PE is QP for building, the Civil PE shall assume the role
of PD and shall make the necessary submissions to the relevant
authorities.
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
1. INTRODUCTION
The document was drawn up for the case of a Public Sector Building
Project with the PM and the PD appointed at the commencement of
the project. Modification to the roles and duties of the team members
are required for public sector projects and private sector projects with
the following arrangements:
1. INTRODUCTION
1) The clients appoint the specialists direct and the works are
carried out as direct contracts. In this case, the PM would
appoint and manage the specialists. However, PD and other
consultants would be required to work with the specialists on
technical coordination, such as provisions of space and
services. CPG Consultants would try to get additional fees for
such works.
1. INTRODUCTION
Architect
Acoustic Specialist
Interior Design
Cladding
Landscape Architect
Conservation
Fire Engineering (affecting architectural layout.)
Mechanical
Fire Engineering (As part of Mechanical Engineering
works)
PD
Non-Hospital Kitchen Equipment
Material Handling
Waste disposal
CFD for Air-conditioning & Mechanical Ventilation
System
Electrical
Lighting Specialist
Security System Specialist
Computer Network System Specialist
Quantity Surveyor
- If applicable
1. INTRODUCTION
1. INTRODUCTION
Microsoft Excel
Worksheet