PINDAAN 3/2013 1

ASPHALT PLANT CHECKLIST (DRUM MIX)

Asphalt Plant :..........................................

Date :

No. ACTIVITIES YES NO


BITUMEN, AGGREGATES, MIX DESIGN & LAB EQUIPMENT
1 PAST RECORDS
Aggregate approval/test results.
Bitumen approval/test results.
Mix design approval (including trial lay).
Binder content, aggregate gradation & Marshall test results.
Satu (1) ujian setiap 200 tan asphalt.
2 BITUMEN
Source of bitumen approved.
M Bitumen diuji sepenuhnya di independent lab berdasarkan MS 124 dan
semua keputusan ujian lulus.
3 AGGREGATES
Source of coarse aggregate approved.
M Agregat kasar diuji sepenuhnya di independent lab berdasarkan
JKR/SPJ/1988 atau JKR/SPJ/2008 dan semua keputusan ujian lulus.
Source of fine aggregate approved.
M Agregat halus diuji sepenuhnya di independent lab berdasarkan
JKR/SPJ/1988 atau JKR/SPJ/2008 dan semua keputusan ujian lulus.
M Each aggregate is stored in a separate stockpile.
Stockpile of fine aggregate is kept under a waterproof roof
M
structure.
4 MIX DESIGN
Mix design prepared and approved by KPPS/JD.
M Laporan rekabentuk campuran hendaklah disertakan dengan kelulusan
bitumen dan agregat di atas.
5 LABORATORY TEST EQUIPMENT
M Is a laboratory available?
Is the laboratory capable to carry out the following tests?
M Bitumen content.
M Aggregate gradation.
M Thickness.
M Density.
Equipped with the following laboratory test equipment;
M Penetration.
M Ring & Ball Softening Point.
M Flash Point.
PINDAAN 3/2013 2

No. ACTIVITIES YES NO


Equipped with laboratory test equipment to determine binder
content of bituminous tack coat (i.e. grade of tack coat).
M Kuari mestilah menyediakan tiga (3) beaker berisipadu 1 liter (low form)
dan tiga (3) glass rod selain oven dan balance walaupun tidak
membekalkan tack coat dan menjalankan kerja paving.
Have laboratory test equipment been checked and
certified/calibrated (annually)?
M Date checked .
Certified by .
Is copy of certification/calibration available?
6 QC SYSTEM
QC system is available.
Competent quality officer is available.
PLANT OPERATIONS
7 COLD FEED BINS
Cold feed system shall consist of not less than 5 bins with
suitable capacity.
M Each aggregate is stored in a separate cold bin.
M No spill over of aggregates into adjacent bins.
Each bin is equipped with a control gate and measuring feeder
for accurate blending of aggregates on to cold feed collecting
conveyor.
Cold feed system shall incorporate a device for moisture
compensation capable of producing an accurate and continuous
blend of aggregates from the cold feed bins.
Separate dry storage is provided for mineral filler.
Equipped with a screen of size 50 mm to discard oversized
M
aggregates before entering the drum mixer.

8 DRUM MIXER

Drum mixer shall be inclined, oil-fired and sufficiently insulated.


Samples of aggregates can be obtained before entering the drum
mixer eg. from the link conveyor.
Fresh mixed asphalt is delivered and stored in a surge silo
through a proper conveyor system.
9 PLANT SETTING
Computer able to display details of mixing proportion (and flow
rate) according to approved mix design, and mix temperatures.
The accuracy of aggregates, filler and bitumen flow rates have
been checked and verified.
Print out of recent mix production (< 1 month) which shows the
M
aggregates, filler and bitumen tonnages is available.
The accuracy of the plant setting as displayed on the computer
M
screen have been checked and verified.
PINDAAN 3/2013 3

No. ACTIVITIES YES NO


10 BITUMEN STORAGE TANK
Have means of indicating the volume of bitumen at all times.
Have means of drawing off samples.
Provides for continuous circulation of hot bitumen through
the bitumen feeding system and back into the bitumen storage
tank.
The end of the return line discharging into the bitumen storage
tank shall be kept submerged in the bitumen to prevent oxidation
of the returning hot bitumen.
A thermometer is fitted to the bitumen storage tank or bitumen
M
feed line.
Have thermometers been checked and certified/calibrated
(annually)?
M Date checked .
Certified by .
Is copy of certification/calibration available?
Bitumen storage tank and bitumen feeding system are equipped
M
with heating system and insulating jackets.
11 LORRY TRANPORTER SCALES
Has weigh bridge been checked and certified/calibrated
(annually)?
M Date checked .
Certified by .
Is copy of certification/calibration available?

Note: M Mandatory

Remarks:
......
.

Is the plant qualified to produce asphalt for use in JKR paving works?

YES NO

Nota: i) YES semua item mandatori DIPATUHI dan minimum 50% daripada item bukan mandatori LULUS.
ii) NO mana-mana item mandatori TIDAK DIPATUHI atau minimum 50% daripada item bukan mandatori GAGAL.

Auditor: Auditee:


(Name: ) (Name: )
(Organisation: ) (Organisation: )
Head of Audit Team
PINDAAN 3/2013 4

The Members of Audit Team

1. Name: ..
Organisation: .....

2. Name: ..
Organisation: ..

3. Name: ..
Organisation: ..

4. Name: ..
Organisation: ..

5. Name: ..
Organisation: ..