SECRETARIA DE INFRAESTRUCTURA
ANALISIS DE PRECIOS UNITARIOS PARA EL DEPARTAMENTO DEL
CESAR-SUBREGION AGUACHICA
Calle 16 No 12 - 120 - Telefax: (5) 5749671 - e-mail:
obras@gobcesar.gov.co - Valledupar, Cesar.
CONSULTOR: JORGE GOMEZ PAVAJEAU
FECHA: MAYO DE 2011
ITEMS DESCRIPCION UN
XI RIEGO
269.00 SUMINISTRO E INSTALACION DE TUBERIA DE 2" PVC RDE 41,
ML
INCLUYE ACCESORIOS
270.00 SUMINISTRO E INSTALACION DE TUBERIA DE 3/4" PVC, INCLUYE ML
ACCESORIOS
271.00 SUMINISTRO E INSTALACIN DE VALVULAS BAYONETAS DE 3/4"
X 3/4", INCLUYE ANCLAJE EN CONCRETO DE 3000 PSI -INCLUYE UN
SILLA DE 3/4X3/4"
272.00 SUMINISTRO DE LLAVE BAYONETA DE 3/4X3/4" UN
273.00 SUMINISTRO DE ASPERSORES METALICOS DE 3/4" UN
274.00 POZO ARTEZIANO 2.00, CONCRETO 1:2:3 PAREDES CON
ESPESOR .15, REFUERZO EN HIERRO DE 1/4 CADA .15 ML
HORIZONTAL Y 3/8 CADA .60 VERTICAL
XII INSTALACIONES HIDRAULICAS
275.00 SUMINISTRO E INSTALACIN MICROMEDIDOR VOLUMTRICO 1/2" UN
CLASE B
276.00 SUMINISTRO E INSTALACIN DE LLAVES DE CONTROL DE 2" EN
BRONCE TIPO RED WHITE O SIMILAR, INCLUYE ACCESORIOS PARA UN
INSTALACIN
277.00 RED SUMINISTRO PVC 1 1/2 ML
278.00 RED SUMINISTRO PVC 1 ML
279.00 RED SUMINISTRO PVC 2 ML
280.00 RED SUMINISTRO PVC 3 ML
281.00 PUNTO HIDRAULICO PVC PRESION DE 1/2" UN
282.00 RED AGUAS LLUVIAS PVC 4 ML
283.00 BAJANTE AGUAS LLUVIAS PVC 3 ML
284.00 RED SUMINISTRO PVC 1/2 ML
285.00 RED SUMINISTRO PVC 3/4 ML
286.00 RED ACUEDUCTO PVC 8 RDE 41 UNION PLATINO ML
GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
ANALISIS DE PRECIOS UNITARIOS PARA EL DEPARTAMENTO DEL
CESAR-SUBREGION AGUACHICA
Calle 16 No 12 - 120 - Telefax: (5) 5749671 - e-mail:
obras@gobcesar.gov.co - Valledupar, Cesar.
CONSULTOR: JORGE GOMEZ PAVAJEAU
FECHA: MAYO DE 2011
ITEMS DESCRIPCION UN
XV ACABADOS Y PINTURAS
387.00 LACA TRANSPARENTE SOBRE MADERA M2
388.00 ESTUCO ACRILICO M2
389.00 DILATACIONES EN ESTUCO ML
390.00 ESTUCO M2
391.00 HUELLA Y CONTRAHUELLA EN PIEDRA CHINA INCL. PIRLAN Ml
DESARROLLO .42MT
392.00 MURO EN GRANITO FUNDIDO ABUZHARDADO-MORTERO 1:4 M2
393.00 MURO EN PIEDRA CHINA ABUZHARDADA M2
394.00 MURO EN PIEDRA CHINA LAVADA M2
395.00 VINILO 1 MANO, PINTURA TIPO 1 VINILTEX O SIMILAR EN M2
MANTENIMIENTOS O ADECUACIONES
396.00 VINILO 2 MANOS, PINTURA TIPO 1 VINILTEX O SIMILAR EN M2
MANTENIMIENTOS O ADECUACIONES
397.00 VINILO 3 MANOS, PINTURA TIPO 1 VINILTEX O SIMILAR EN M2
MANTENIMIENTOS O ADECUACIONES
398.00 VINILO 3 MANOS, PINTURA TIPO 1 VINILTEX O SIMILAR NUEVA M2
399.00 PINTURA LTEX ACRLICO TIPO 1, PARA CUBIERTA EN LAMINA
M2
FIBRO CEMENTO
GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
ANALISIS DE PRECIOS UNITARIOS PARA EL DEPARTAMENTO DEL
CESAR-SUBREGION AGUACHICA
Calle 16 No 12 - 120 - Telefax: (5) 5749671 - e-mail:
obras@gobcesar.gov.co - Valledupar, Cesar.
CONSULTOR: JORGE GOMEZ PAVAJEAU
FECHA: MAYO DE 2011
ITEMS DESCRIPCION UN
400.00 PROTECCION FACHADAS CON SIKA TRANSPARENTE 5 LQUIDO
INCOLORO CON BASE EN SILICONAS QUE
PROTEGE CONTRA LA PENETRACIN DEL AGUA LLUVIA EN M2
FACHADAS
12,909.00
6,704.00
23,387.00
15,074.00
39,960.00
837,535.00
109,010.71
187,960.00
13,308.00
9,723.00
17,935.00
38,968.00
17,862.00
25,378.00
13,338.00
6,644.00
8,296.00
56,145.00
VR. UNITARIO
31,920.00
39,857.00
1,911,352.00
1,648,981.00
1,007,066.00
3,976,713.00
704,338.00
VR. UNITARIO
861,649.00
192,057.00
54,088.00
45,909.00
80,150.00
33,719.00
5,683.00
8,876.00
55,731.00
93,827.00
358,912.00
477,712.00
204,681.00
1,197,236.00
140,179.00
581,547.00
14,943.00
321,935.00
VR. UNITARIO
447,811.00
1,684,547.00
1,303,237.00
792,043.00
762,253.00
228,728.00
1,661,469.00
437,139.00
2,928,191.00
14,376,123.00
5,212,699.00
VR. UNITARIO
1,235,037.00
26,642,167.00
2,364,290.00
2,734,470.00
200,722.00
1,274,393.00
109,312.00
267,726.00
164,144.00
33,195.00
VR. UNITARIO
46,490.00
71,051.00
10,396,291.00
12,184,769.00
827,481.00
827,481.00
923,601.00
804,801.00
VR. UNITARIO
392,436.00
483,156.00
677,556.00
210,285.00
134,201.00
9,649.00
712,100.00
779,500.00
4,778,711.00
997,289.00
VR. UNITARIO
1,838,554.00
2,933,051.00
VR. UNITARIO
2,318,337.00
403,428.00
318,815.00
195,816.00
197,223.00
30,816.00
30,326.00
175,705.00
117,142.88
92,288.00
VR. UNITARIO
810,780.00
164,509.00
143,212.00
700,000.00
365,000.49
83,914.00
162,000.00
11,502.00
190,725.00
VR. UNITARIO
1,004,331.00
252,449.00
263,935.00
336,623.00
267,685.00
209,049.00
600,099.00
492,099.00
112,961.00
444,721.00
396,757.00
463,396.00
VR. UNITARIO
5,912,197.00
94,547.00
35,843.00
8,796.00
12,138.00
1,287.00
3,780.00
40,800.00
67,776.00
50,558.00
50,558.00
2,349.00
3,941.00
5,062.00
6,850.00
6,218.00
VR. UNITARIO
8,756.00
37,560.38
38,010.38
15,621.00
10,282.00
7,607.00
20,404.00
4,781.00
3,974.00
10,205.00
7,345.00
9,944.00
22,164.00
39,390.00
66,697.00
73,969.00
37,860.00
46,293.00
63,936.00
VR. UNITARIO
166,757.00
115,997.00
94,694.00
102,350.00
120,710.00
88,310.00
203,291.00
63,323.00
227,146.00
177,574.00
675,685.00
295,602.00
554,061.00
104,610.00
56,228.00
95,123.00
97,430.26
8,472.00
929,487.00
VR. UNITARIO
683,635.00
506.00
39,802.00
15,931.00
16,521.00
39,805.00
870,749.00
494.00
2,506.00
1,881.00
VR. UNITARIO
3,972.00
32,241.00
4,040,716.00
3,253,227.00
38,863.00
61,150.13
3,519.98
17,676.00
24,638.00
44,116.00
3,483,720.00
74,259.00
VR. UNITARIO
168,898.00
83,402.00
115,802.00
160,580.00
236,653.00
30,000.00
9,902.00
9,594.00
15,869.00
VR. UNITARIO
15,869.00
481,917.00
187,107.00
185,535.00
2,794,530.00
325,935.00
7,718,216.00
VR. UNITARIO
7,909,289.00
7,310,917.20
22,256,193.36
613,605.00
126,497.00
324,886.00
365,882.00
43,104.00
173,429.00
177,129.00
226,650.00
VR. UNITARIO
347,580.52
243,960.16
82,940.02
102,905.40
88,560.65
103,530.65
50,509.78
60,889.78
381,441.35
78,961.83
648,110.05
50,192.00
209,290.94
39,939.56
320,000.00
320,000.00
41,000.00
41,000.00
10,000.00
VR. UNITARIO
41,000.00
41,000.00
20,000.00
40,000.00
80,000.00
2,000.00
8,000.00
220,000.00
8,000.00
8,000.00
8,000.00
8,000.00
8,000.00
15,000.00
40,000.00
80,000.00
40,000.00
40,000.00
40,000.00
50,000.00
40,000.00
VR. UNITARIO
50,000.00
40,000.00
40,000.00
8,000.00
80,000.00
8.00
8.00
3.00
2.00
2.00
2.00
3.00
5.00
4.00
15.98
44.49
39.14
31.85
21.24
58.70
VR. UNITARIO
94.89
111.62
150.87
86.00
108.81
137.60
126.24
134.31
161.77
96.87
108.35
74.75
45.75
82.24
30.66
40.21
69.81
13.60
58.49
GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
PRECIOS DE REFERENCIA PARA EL DEPARTAMENTO DEL CESAR
LISTADO DE MATERIALES-VALLEDUPAR
Calle 16 No 12 - 120 - Telefax: (5) 5749671 - e-mail:
obras@gobcesar.gov.co
FECHA: MAYO - DEValledupar,
2011 Cesar.
ITEMS DESCRIPCION UN
ESTACA DE MADERA UN
ALGARROBILLO 4"X2"X3.00MT UN
ALGARROBILLO 2"X2"X3.00MT UN
TABLA 1''X12"X3.00MT ALGARROBILLO UN
TABLA 1''X12"X3.00MT TOLUA UN
TABLA 1''X4"X3.00MT ALGARROBILLO UN
TABLA 1''X10"X3.00MT ALGARROBILLO UN
TABLA 1''X8"X3.00MT ALGARROBILLO UN
ALGARROBILLO PIE
TOLUA PIE
CEDRO PIE
ROBLE PIE
CARRETO PIE
ABARCO PIE
EQUIPO DE TOPOGRAFIA (INCLUYE TRANSITO, NIVEL Y
MES
COMPLEMENTARIOS)
CADENERO 1 MES
CADENERO 2 MES
TOPOGRAFO MES
TOPOGRAFO DIA
TRANSPORTE MATERIAL M3/KM
MEZCLA DENSA MDC -2 M3
TRANSPORTE MEZCLA M3
VIBROCOMPACTADOR TIPO DINAPAC CA 15 HR
CINTA SEGURIDAD DE 75 MM X 500 MTS ML
BOMBN PLASTICO (20 USOS) UN
TELA VERDE ESTABILIZADA 2.1 M2
TRANSPORTE MOTONIVELADORA h
MOTONIVELADORA CAT 12-F h
MOTO 120G HR
VOLQUETA 6 M3 vj
CARGADOR FRONTAL d
RETROEXCAVADORA J.D 510 h
COMPRESOR DE 2 MARTILLOS h
AGUA DE CARROTANQUE lt
VIBRO DINAPAC HR
CARROTANQUE HR
VIBROCOMPACTADOR TIPO RANA d
PUNTILLA CON CABEZA 2 1/2" 104UN/LB LB
PUNTILLA CON CABEZA 2" 159UN/LB lb
PUNTILLA CON CABEZA 3/4 a 1" lb
ITEMS DESCRIPCION UN
PUNTILLA CON CABEZA 1 1/ 2 a 3 1/2" lb
ALAMBRE NEGRO NO.18 105ML/KG kg
ACERO DE REFUERZO PDR-40 kg
ACERO DE REFUERZO PDR-60 kg
ACERO DE 1/4 CORRUGADA ml
ACERO DE 1/4 CORRUGADA kg
ACERO DE 3/8 CORRUGADA ml
ACERO DE 3/8 CORRUGADA kg
ACERO DE 1/2 CORRUGADA ml
ACERO DE 1/2 CORRUGADA kg
ACERO DE 5/8 CORRUGADA ml
ACERO DE 5/8 CORRUGADA kg
ACERO DE 3/4 CORRUGADA ml
ACERO DE 3/4 CORRUGADA kg
ACERO DE 3/4 LISO kg
ACERO DE 1 CORRUGADA kg
ANGULO DE 2.5X2.5X1/4* ml
ANGULO DE 2X2X1/4* ml
ANGULO DE 2X2X1/8* ml
PLATINA DE 1 1/2" x1/4"-20X20CM ML
ALAMBRE GALVANIZADO #10-14ML/KG KG
GAVIONES 2X1X1 CAL 13 UN
SEGUETA NICHOLSON UN
TRAMPA DE GRASAS UN
TANQUE SEPTICO 2000 LTS UN
CAJA DE DISTRIBUCION UN
Formaleta metlica para Cmara Circular Da
TAPA MANJOL 60CM X 60 UN
BLOQUE CONCRETO 10X20X40 UN
BLOQUE CONCRETO 12X20X40 UN
BLOQUE CONCRETO 15X20X40 UN
BOVEDILLA 20X20X40 UN
CALADOS DE CEMENTO UN
BLOQUE CONCRETO SPLIT COLOR 15X19X39-12,5 M2 UN
BLOQUE CONCRETO SPLIT GRIS 15X19X39-12,5 M2 UN
BLOQUE ESTRUCTURAL CONCRETO SPLIT COLOR 15X19X39-12,5 M2 UN
BLOQUE ESTRUCTURAL CONCRETO SPLIT GRIS 15X19X39-12,5 M2 UN
BLOQUE CONCRETO ESTRUCTURAL 20X19X39 UN
BLOQUE CONCRETO ESTRUCTURAL 15X19X39 UN
BOVEDILLA CONCRETO 15X20X50 UN
BOVEDILLA CONCRETO 20X20X50 UN
BOVEDILLA CONCRETO 25X20X50 UN
BOVEDILLA CONCRETO 30X20X50 UN
BOVEDILLA CONCRETO 30X20X60 UN
SARDINEL ACHAFLANADO A10 .20 X .80 X .50H TIPO IDU O SIMILAR UN
TABLERO ACRILICO UN
MALLA CON VENA .50X2.00 M2
CUBIERTA TERMOACUSTICA TRAPEZOIDAL A 360 LONG 2.44 M-AREA
UN
UTIL 1.656 M2
TORNILLOS TPF 3/4 UN
TORNILLOS AUTOPERFORANTE 7/8 UN
CUBIERTA ARQUITECTONICA ACESCO TZA CAL. 30 LONG 2.44 M-
UN
AREA UTIL 1.679 M2
ITEMS DESCRIPCION UN
CABALLETE PARA CUBIERTA TERMOACUSTICA TRAPEZOIDAL 27MM
UN
2.00X.60
CUBIERTA ARQUITECTONICA ACESCO TZA CAL. 30 LONG 2.44 M-
UN
AREA UTIL 1.679 M2
CUBIERTA ARQUITECTONICA ACESCO TZA CAL. 30 LONG 3.05 M-
UN
AREA UTIL 2.18 M2
SOLDADURA 6011X1/8 kg
PERFIL GALVANIZADO PHR-C 160X60 CAL. 14 UN
PERFIL GALVANIZADO PHR-C 220X80 CAL. 14 UN
PERFIL GALVANIZADO PHR KG
CABALLETE EN ASBESTO CEMENTO UN
GANCHOS UN
AMARRES N. 16 UN
LAMINA ONDULADA BARROCA FIBROCEMENTO No. 8 AREA UTIL
UN
2.30 M2
LAMINA ONDULADA ASBESTO CEMENTO No. 6 AREA UTIL 1.479 M2 UN
CANALETA 90 FIBROCEMENTO LONG 6.00ML AREA UTIL 5.2325 M2 UN
FIJADOR DE ALA CANALETA UN
TORNILLO FIJADOR CANALETA UN
TUBO ESTRUCTURAL COLMENA 200 X 70 X 4,0MM X 6MTS UN
TUBO ESTRUCTURAL COLMENA 60 X 40 X 3,0MM X 6MTS UN
REJILLAS EN PERFIL I DE 6"-LONG. 1.00ML ANCHO .76ML, RERFILES
ESPACIADOS CADA .07MT UN
REJILLAS EN PERFIL I DE 4"-LONG. 1.00ML ANCHO .76ML, RERFILES
ESPACIADOS CADA .07MT UN
CINTA SIKA 10 (30,00 ML) mL
CINTA SIKA 15 (30,00 ML) mL
CINTA SIKA 22 (15,00 ML) mL
SIKA-2 (5.5 KG) kg
SIKA TRANSPARENTE 5 (5 KG) KG
SIKA TRANSPARENTE 10 (5KG) KG
ESTUKA ACRILICO (30KG) kg
SIKA IMPER MUR X 4KG KG
PLASTOCRETE DM X 4,5KG kg
SIKASET L X 230KG kg
ANTISOL ROJO (16KG) Kg.
SIKA-1 (20 KG) kg
MANTO EDIL ESTNDAR 3MM M2
ALUMOL (16 KG) kg
SIKA 101 BLANCO (10KG) kg
SIKA 101 GRIS (10KG) kg
IGASOL CUBIERTA (20 KG) kg
SELLO DE POLIURETANO ELASTOMERICO DE ALTO DESEMPEO-TIPO
Ml
SIKAFLEX 15 LM SL O SIMILAR (22,70 KG)
CORDON DE ESPUMA PARA FONDO DE JUNTA 10MM -TIPO SIKAROD
Ml
O SIMILAR (1097ML)
PERFIL U DE ALUMINIO 3/8 X 3/8 ML
ITEMS DESCRIPCION UN
ICOPOR 1 CM/DENS.20/1.24X.62 M2
PERFIL EN T ALUMINIO 1/2 X 1/2 ML
NGULO CIELO FALSO ALUMINIO 1'X 1" ML
LAMINA DRY-WALL PLANO IMPORTADA UN
LAMINA DRY-WALL PLANO NACIONAL UN
FIBERGLASS DURACUSTIC 5/8 M2
MACHIMBRE m2
ESTRUCTURA DE SOPORTE m2
LAMINA PLANA FIBROCEMENTO 1.22X1.22 UN
CARAPLAST M2
LUBRICANTE KG
ANGULOS UN
OMEGAS UN
PRINCIPALES UN
PERFIL PARAL PARA MUROS EN DRY-WALL UN
SUPERMASTIK CTE
CINTA UN
TORNILLOS UN
TORNILLOS CORTOS UN
LAMINA SUPERBOARD #8 2.44X1.22 UN
LAMINA SUPERBOARD #6 2.44X1.22 UN
CLAV0 DE ACER0 LB
BALDOSA GRANITO .33X.33 M2
CEMENTO BLANCO kg
PULIDA PISOS BALDOSA DE GRANITO M2
REPULIDA DE PISOS Y BRILLADA M2
MARMOL NEGRO .40X1.00 SUMINISTRO Y COLOCACION ML
MARMOL TRAVERTINO .20X1.00 SUMINISTRO Y COLOCACION ML
MARMOL TRAVERTINO .05X1.00 PARA ESQUINERO AMBOS LADOS
ML
SUMINISTRO Y COLOCACION
MARMOL VERDE SALTAN DE .22 CON REMATES LATERALES CURVOS
ML
POR AMBOS LADOS, SUMINISTRO Y COLOCACION
PULIDA PISOS MARMOL O GRANITO FUNDIDO M2
CERMICA CORONA EGEO M2
CERAMICA MACEDONIA M2
PEGACOR BLANCO kg
PEGACOR GRIS kg
PEGACOR MAX PORCELANATO BLANCO * 25 KG kg
PEGACOR MAX GRIS * 25 KG kg
TABLN VITRIFICADO .33 X .33 M2
TABLN VITRIFICADO .30 X .30 M2
TABLN VITRIFICADO .25 X .25 M2
TEJA DE BARRO REDONDA 33 M2 M2
TEJA DE BARRO AMAZONA ANCLAJE CON AMARRE 10 M2 M2
CERMICA DUROPISO CORONA ALTO TRAFICO M2
CONCOLOR BLANCO NACAR 5 KG PORCELANATO kg
CONCOLOR 5 KG BLANCO NACAR O SIMILAR kg
ITEMS DESCRIPCION UN
PORCELANATO .60X.60 DE PRIMERA CALIDAD M2
ZOCALO DE GRESS H=7.5CM ml
GRANITO NO. 3 VARIOS COLORES 40KG bt
PIEDRA CHINA No. 3 BULTO X 10KG bt
DILATACION DE BRONCE ML
PIRLAN BRONCE ML
ESQUINERO DE ALUMINIO 6.00ML UN
ADOQUIN CONCRETO 10X20X8 GRIS-50 UN/M2 UN
ADOQUIN CONCRETO 10X20X8 COLOR-50 UN/M2 UN
ADOQUN GRES 10X20X6 COLOR-50 UN/M2 UN
ADOQUN GRES 10X20X6 GRIS-50 UN/M2 UN
ADOQUN GRES 10X20X.04-50 UN/M2 m
LOCETA CUADRATICA GRIS .40X.40 TIPO IDU, INCL. TRANSPORTE m
LOCETA CUADRATICA COLOR .30X.30X.06 TIPO IDU, INCL.
m
TRANSPORTE
LOCETA TOPEROL GRIS .30X.30X.06 TIPO IDU, INCL. TRANSPORTE m
LOCETA CUADRATICA DE .40X.40, TOPEROL, OLAS Y RALLAS GRIS .
m
30X.30X.06 TIPO IDU, PUESTA EN OBRA
LOCETA PREPULIDA GRIS CUADRATO, OLAS Y RALLAS .30X.30X.06
m
TIPO IDU, PUESTA EN OBRA
LOCETA PREPULIDA COLOR CUADRATO, OLAS Y RALLAS .30X.30X.06
m
TIPO IDU, PUESTA EN OBRA
LOCETA ARCO COLOR .30X.30X.06 TIPO IDU, INCL. TRANSPORTE m
PIEDRA LAJA m3
GUARDERA LATERAL H=.10 GB
PLATINA METLICA CR 2" x 1/4" ML
VARILLA METLICAS 1/2" kg
VARILLA METLICAS 3/8" kg
PINTURA ELECTROSTTICA GRIS RAL 7010 GL
ASFALTO kg
LEA UNIDA
TABLETA DE GRESS LISA 25X7 COLOR ALMENDRA, ARENA Y
M2
MATIZADA
UNIN 2" PR UN
TUBERIA RDE 41 DE 2" UNION MECANICA m
UNIN 3/4" PR UN
TUBERIA RDE 26 DE 3/4" m
ADAPTADOR HEMBRA PVC PRESION DE 3/4" UN
SILLA DE 3/4X3/4" UN
VALVULA BAYONETA DE 3/4" X 3/4" UN
LLAVE DOBLE SEGURO DE BAYONETA DE 3/4X3/4" UN
ASPERSOR DE 3/4" METALICO UN
MICROMEDIDOR VOLUMTRICO 1/2" TIPO B UN
VLVULA ANTIFRAUDE DE 20 MM (1/2") UN
ADAPTADOR HEMBRA PVC PRESION DE 3/4" UN
ADAPTADOR MACHO PVC PRESION DE 3/4" UN
ADAPTADOR HEMBRA PVC PRESION DE 1/2" UN
ITEMS DESCRIPCION UN
ADAPTADOR MACHO PVC PRESION DE 1/2" UN
ADAPTADOR HEMBRA PVC PRESION DE 1" UN
ADAPTADOR MACHO PVC PRESION DE 1" UN
TUBO PRESIN /21 PVC 1 1/2 ML
CODO 90 PRESIN PVC 1 1/2 UN
UNIN PRESIN PVC 1 1/2 UN
TUBO PRESIN /13.5 PVC 1 ML
CODO 90 PRESIN PVC 1 UN
UNIN PRESIN PVC 1 UN
UNIN PRESIN PVC 3 UN
UNIN PRESIN PVC 2 UN
TUBO PRESIN /21 PVC 2 ML
CODO 90 PRESIN PVC 2 UN
CODO 90 PRESIN PVC 3 UN
TUBO PRESIN /21 PVC 3 ML
CODO 90 PRESIN PVC 1/2 UN
TUBO PRESIN /9 PVC 1/2 ML
TUBO PRESIN /11 PVC 3/4 ML
CODO 90 PRESIN PVC 3/4 UN
TUBO PRESIN /41 PVC 8 ML
LUBRICANTE 500GR PARA PVC UN
TUBO CONDUIT 1" ML
TUBO CONDUIT 1/2" ML
TUBO CONDUIT 3/4" ML
TUBO CONDUIT 1 1/2" ML
TUBO CONDUIT 2" ML
TUBO CONDUIT 3" TIPO PESADO ML
CURVA CONDUIT 1" UN
CURVA CONDUIT 1/2" UN
CURVA CONDUIT 3/4" UN
CURVA CONDUIT 1 1/2" UN
CURVA CONDUIT 2" UN
CURVA CONDUIT 3" DE GRAN RADIO UN
ADAPTADOR TERMINAL CONDUIT 1/2 UN
CABLE DE COBRE TIPO THWN No 12 M
CABLE 7 HILOS # 10 THWN ML
CABLE 7 HILOS # 8 THWN ML
CABLE 7 HILOS # 6 THWN ML
CABLE 7 HILOS # 4 THWN ML
CABLE 7 HILOS # 2 THWN ML
CABLE DE COBRE TIPO THWN 1/0 M
CABLE DE COBRE DESNUDO No 2 M
CABLE DE COBRE DESNUDO No 2 /0 AWG M
CABLE DE COBRE TIPO THWN No 4/0 M
CABLE TIPO ACSR No 1/0 ( RAVEN ) M
ALAMBRE COBRE THW 14 AWG THHN/NN ML
ALAMBRE DE COBRE No 12 ML
ITEMS DESCRIPCION UN
ALAMBRE DE COBRE No 8 ML
ALAMBRE DE COBRE No 10 ML
ALAMBRE TELEFNICO 2X22 TRENZADO ML
CABLE DE COBRE TIPO THWN 500 MCM M
CABLE TIPO XLPE No 1/0 PARA 15 KV M
LAMPARA TIPO DJK DE 150W S UN
LAMPARA ROY ALPHA TIPO CALIMA II 150 W S, INCL. FOTOCELDA Y
UN
BOMBILLO
LAMPARA ROY ALPHA TIPO CALIMA II 250 W S, INCL. FOTOCELDA Y
UN
BOMBILLO
LAMPARA ROY ALPHA TIPO CALIMA II 250 W MH R UN
LAMPARA ROY ALPHA TIPO RAP 70 W S UN
LAMPARA ARAMIS SCHREDER, REFLECTOR 1627 DE ALUMINIO
ABRILLANTADO Y ANODIZADO Y PLACA DE AUXILIARES ELECTRICOS.
BALASTO TIPO REACTOR (208/220V) Y ACCESORIOS ELECTRICOS UN
PARA SODIO ALTA PRESION 70W (INCL. UNICAMENTE BOMBILLA DE
SODIO ALTA PRESION 70W TUBULAR)
PROYECTOR RADIAL 2 SCHREDER, REFLECTOR 1640 EN ALUMINIO
ABRILLANTADO Y ANODIZADO Y PLACA DE AUXILIARES ELECTRICOS.
BALASTO TIPO REACTOR (208/220V) Y ACCESORIOS ELECTRICOS UN
PARA SODIO 150W (INCL. UNICAMENTE BOMBILLA DE SODIO ALTA
PRESION 150W TUBULAR)
POSTE CILINDRICO EN ACERO GALVANIZADO SCHREDER SEXTANTE
DE 4,5 MT, BRAO SENCILLO APTO PARA INSTALAR PROYECTOR UN
RADIAL 2 Y LUMINARIA ARAMIS, INCL. BASE Y PERNOS DE ANCLAJE.
BOMBILLO SODIO 250 W UN
BOMBILLO SODIO 150 W UN
REFLECTOR RCG DE 400W A 220V MH R ALTA PRESION, CON
UN
BOMBILLA MARCA PHILLIPS O SILVANIA ( COMPLETO )
REFLECTOR RCG DE 1000W A 220V S-CWA ALTA PRESION, CON
UN
BOMBILLA MARCA PHILLIPS O SILVANIA ( COMPLETO )
FOTOCELDA INCL. BASE UN
BRAZO TUBO GALVANIZADO DE 1 1/2" X 1.2MT UN
BUSHING 4 A 3" UN
POSTE GALVANIZADO DE 4"X6.00MT- INCL. FLANCHE CON
UN
ANTICORROSIVO Y ACABADO ESMALTE
POSTE GALVANIZADO DE 3"X2.00MT- CON ANTICORROSIVO Y
UN
ACABADO ESMALTE
POSTE GALVANIZADO CUADRADO 9CM X 9CM X 3ML UN
POSTE GALVANIZADO DE 2" X 3M CON FLANCHE UN
TOMA TRIFSICA 50 AMP UN
TOMA TRIFSICA 20 AMP UN
INT. SENC. PILOTO LUM UN
INT. SENC. LUM UN
INT. DOBLE LUM UN
INT. TIMBRE. LUM UN
TOMA DOBLE LEVINTON ORIG UN
ITEMS DESCRIPCION UN
TOMA DOBLE LUM UN
TOMA TELEFNICA UN
TOMA COAXIAL TV UN
TOMA HOSPITALARIA, CON POLO A TIERRA UN
TOMA BIFASICO 20 AMP UN
LMPARA SLIM 2X32 BALAZO ELECTRONICO UN
ROSETA (PLAFON) UN
VENTILADOR DE ASPA UN
CAJA OCTAGONAL GALVANIZADA UN
CAJA RECTANGULAR 2 X 4 GALVANIZADA UN
CAJA 4X4 UN
TORNILLO LMINA DIAM. 3/8 UN
TORNILLOS 5/8"X4" UN
CAMIN GRANDE
ELEMENTOS DE CONEXIN Y MONTAJE GL
PONCHADORA HIDRULICA UN
VEHCULO LIGERO
CAMIN CANASTA UN
ESCALERA 12MT D
CAMION PEQUEO
GRA HIDRULICA UN
TABLERO CON LLAVE 12 CIRCUITOS, UN
TACO TERMOMAGNTICO UNIPOLAR HQP 20 A UN
TACO TERMOMAGNTICO BIPOLAR HQP 30 A UN
TABLERO CON LLAVE 12 CIRCUITOS, ESPACIO TOTALIZADOR UN
POSTE DE CONCRETO DE 12 M X 1050 KGF UN
CRUCETA DE MADERA INMUNIZADA CON QUIMICO DE 4" X4" X
UN
2,40M
DIAGONAL EN VARILLA RECTA DE 3/4"X 0,78 M UN
SILLA PARA CRUCETA DE MADERA UN
ESPARRAGO DE 5/8" X 20 " UN
PERNO DE MAQUINA DE 5/8" X 12" UN
PERNO DE MAQUINA DE 1/2" X 6" UN
PERNO DE MAQUINA DE 5/8" X 8" UN
ARANDELA CUADRADA DE 2" X 2" PARA 5/8" UN
ARANDELA CUADRADA DE 2" X 2" PARA 1/2" UN
CINTA BAND IT DE 3/4" M
HEBILLA PARA CINTA BAND IT DE 3/4" UN
COLLARIN PARA TRANSFORMADOR DE 6" - 7" UN
CONECTOR AMOVIBLE PARA CABLE 1/0 UN
CONECTOR CON ESTRIBO DE COBRE UN
CONECTOR TIPO CUA PARA CABLE No 1/0 UN
CORTACIRCUITOS 15 KV, 100A ,430 mm UN
TUERCA DE OJO ALARGADA PARA 5/8" UN
GRAPA TIPO PISTOLA PARA CABLE DEL No 4 HASTA EL No 2/0 UN
CAPACETE PARA TUBO DE 3" UN
AISLADOR SINTETICO DE 15 KV UN
ITEMS DESCRIPCION UN
TUBO CONDUIT GALVANIZADO DE 1/2" X 3ML UN
TUB. CONDUIT GALVANIZADA DE 3" X 3ML UN
TUBO CONDUIT GALVANIZADO DE 1 1/2" X 3ML UN
FUSIBLE TIPO SOGA DE 20 AMPERIOS A 15 KV TIPO K UN
VARILLA DE COBRE DE 5/8" X 1.8M UN
VARILLA DE COBRE DE 5/8" X 2.4M UN
SOLDADURA CADWELL PTOS
BOLSA DE FABIGEL DE 50 KG UN
CORTACIRCUITOS 15 KV, 100A ,430 mm UN
PARARRAYO TIPO DISTRIBUCIN CLASE 12KV UN
TERMINAL PREMOLDEADO PARA 15 KV Y CABLE No 1/0 ( E ) JG
TAPA Y MARCO DE 1,20M X 0,70 M EN ANGULO GALVANIZADO DE
UN
3" TAPA EN CONCRETO DE 3500 PSI
CELDA DE ENTRADA O SALIDA PARA M.T. 17,5 KV ( LUMINEX ) UN
CELDA DE MEDIDA EN MEDIA TENSION CON 3 TCS Y 3 TPS UN
MEDIDOR ELECTRONICO (NORMA ELECTRICARIBE S.A. E.S.P.) UN
ELEMENTOS DE MONTAJE Y CONEXIN GL
CELDA DE SECCIONAMIENTO Y PROTECCION FUSIBLE DE 16 A.
UN
ALTURA 2000mm, ANCHO 1100 mm y PROFUNDIDAD 1200 mm
CELDA DE PARA ALOJAR TRAFO DE POTENCIA DE 300 KVA. ALTURA
UN
2000mm, ANCHO 1800 mm y PROFUNDIDAD 1500 mm
TRAFO TRIFASICO DE 300 kVA A NIVEL DE 13,2 KV/ 220 -127 V UN
TRANSFORMADOR MONOFASICO DE 5 kVA UN
TRANSFORMADOR MONOFASICO DE 10 kVA UN
TRANSFORMADOR MONOFASICO DE 15 kVA UN
TRANSFORMADOR MONOFASICO DE 25 kVA UN
TRANSFORMADOR MONOFASICO DE 37.5 kVA UN
TRANSFORMADOR MONOFASICO DE 50 kVA UN
TRANSFORMADOR MONOFASICO DE 75 kVA UN
TRANSFORMADOR MONOFASICO DE 100 kVA UN
TRANSFORMADOR TRIFASICO DE 15 kVA UN
TRANSFORMADOR TRIFASICO DE 30 kVA UN
TRANSFORMADOR TRIFASICO DE 45 kVA UN
TRANSFORMADOR TRIFASICO DE 75 kVA UN
TRANSFORMADOR TRIFASICO DE 112.5 kVA UN
TRANSFORMADOR TRIFASICO DE 150 kVA UN
TRANSFORMADOR TRIFASICO DE 225 kVA UN
TRANSFORMADOR TRIFASICO DE 300 kVA UN
FOSO PARA EL ACEITE Y PLATINAS MONTAJE DEL TRAFO UN
TRANSFORMADOR TRIFASICO DE 75 kVA UN
TRANSFORMADOR TRIFASICO DE 30 Kva 13.2 UN
TERMINAL PARA PONCHAR TIPO 3M PARA CABLE 2/0 UN
CARCAMO DE 0,5M ANCHO X0.4M PROF. ( CON TAPA EN LAMINA
ML
COLD ROLLED DE 3MM
TABLERO GENERAL SEGN DISEO UN
BREAKER INDUSTRIAL DE 3X600A - 600V TIPO LAL UN
BREAKER INDUSTRIAL DE 3X400A - 240V TIPO Q4L-3400 UN
ITEMS DESCRIPCION UN
BREAKER INDUSTRIAL DE 3X60A - 240V TIPO FAL UN
BREAKER INDUSTRIAL DE 3X50A - 240V TIPO FAL UN
BREAKER INDUSTRIAL DE 3X40A - 240V TIPO FAL UN
BREAKER INDUSTRIAL DE 3X30A - 240V TIPO FAL UN
BREAKER INDUSTRIAL DE 3X20A - 240V TIPO FAL UN
BREAKER INDUSTRIAL DE 3X100A - 240V TIPO FAL UN
BREAKER INDUSTRIAL DE 3X800A - 600V TIPO MAL UN
BREAKER INDUSTRIAL DE 3X125 A - 240 V TIPO Q2L UN
BREAKER INDUSTRIAL DE 3X150 A - 240 V TIPO Q2L UN
TABLERO TRIF. TIPO NTQ DE 24 CTOS CON ESPACIO PARA
UN
TOTALIZADOR BARRAJE 225A 240V
BREAKER ENCHUFABLE 1x20 A UN
BREAKER ENCHUFABLE 2x20 A UN
BREAKER ENCHUFABLE 3x30 A UN
TABLERO TRIF. TIPO NTQ DE 24 CTOS BARRAJE 225A 240V UN
TABLERO TRIF DE 30 CTOS BARRAJE 225A 240V CON PUERTA,
UN
CHAPA, CERRADURA Y ESPACIO PARA TOTALIZADOR
TABLERO TRIF DE 30 CTOS BARRAJE 225A 240V CON PUERTA,
UN
CHAPA, CERRADURA
TABLERO TRIF DE 12 CTOS BARRAJE 225A 240V CON PUERTA,
UN
CHAPA, CERRADURA
TABLERO TRIF DE 18 CTOS BARRAJE 225A 240V CON PUERTA,
UN
CHAPA, CERRADURA
TABLERO TRIF DE 18 CTOS BARRAJE 225A 240V CON PUERTA,
UN
CHAPA, CERRADURA Y ESPACIO PARA TOTALIZADOR
TOMA PARA TRANSMISIN DE VOZ Y DATOS RJ 45 UTP CAT. 6. UN
CABLE UTP CATEGORA 6 M
CABLE UTP 4 PARES M
CABLE TELEFONICO DE 10 PARES M
LIBRO ETIQUET .190 DATOS UN
TOMA RJ45 -110 JACK SNAP UN
WALL PLATE AJUSTE SENCILL UN
AISLADOR DE PIN DE ANSI 55-1 UN
PORTA AISLADOR 3 PUESTO UN
ACCES.T P/BANDEJA T ESCAL UN
ANCLAJE DE CUA. x 2. 3/4" UN
BANDEJA PORTA CAB. ESCALERA 30X30 UN
SOPORTE P/BANDEJA PORTA CAB UN
CANALETA METAL C/DIVIS .10 X4 UN
CLAVO ALTA VELOCIDAD 1" x 1/4" UN
TAPA TROQUEL METAL 2 ORIF UN
TORNILLO TIRAFONDO DE 4X 3/8 " UN
CHAZOS DE PLASTICOS 1/4 ' ESTRIADO UN
ACCES.T P/CANALETA PLAST. UN
CANALETA PLASTICA AJOVER 10 X4 ML
BANDEJA RACK C/16 TOM. ELE UN
DUCTO VERT .80"P/MANEJ.CABLE UN
ITEMS DESCRIPCION UN
DUCTO METALICO S. DIVISORIO 30X8 UN
ANCLAJE CHAZO EXP. 1/2 x 2 3/4" UN
GABINETE .600 x.400 x 2.50 UN
PATCH CORD AMP QUANTUM (CAT6) UN
PATCH PANEL AMP 24 PUERTOS CAT 5E UN
PLOTEO UN
FOTOCOPIAS GB
DISEOS MES
PRESUPUESTO MES
ESTUDIOS DE CONEXIN DE 5 A 100 kVA UN
CONSULTORIA DE PROYECTOS DE 5 A 100 kVA UN
REVISION DE INSTALACION DE ENLACE DE 5 A 100 kVA UN
DESCARGOS POR CUENTA DEL CLIENTE DE 5 a 100 kVA UN
VENTANA 744 ANOLOCK-VIDRIO BRONCE UNA NAVE FIJA Y UNA
UN
CORREDIZA 1.00X1.20
VENTANA 744 ANOLOCK-VIDRIO BRONCE UN CUERPO SUPERIOR
UN
PROYECTANTE Y UN CUERPO INFERIOR FIJO .50X1.20
VENTANA 744 ANOLOCK-VIDRIO BRONCE DOS NAVES FIJAS Y DOS
UN
CORREDIZAS 2.00X1.20
VENTANA 744 ANOLOCK-VIDRIO BRONCE UNA NAVE FIJA Y UNA
UN
CORREDIZA 2.00X2.00
VENTANA 744 ANOLOCK-VIDRIO BRONCE DOS NAVES FIJAS Y DOS
UN
CORREDIZAS 2.00X2.00
VENTANA 744 ANOLOCK-VIDRIO BRONCE DOS NAVES BATIENTES
UN
2.00X2.00
BANDA DE CAUCHO ML
VISOR EN VIDRIO 0.20*0.35 UN
PUERTA EN ALUMINIO M2
VIDRIO TEMPLADO 10MM m2
VIDRIO TEMPLADO 6MM m2
VIDRIO TEMPLADO 5MM m2
VIDRIO TEMPLADO 4MM m2
BISAGRA PIVOTANTE UN
CONTRAMANIJA UN
MANIJA Y CERRADURA UN
VIDRIO 4MM M2
BISAGRAS COBRIZADA 3" UN
PUERTA PIZANO 0.60 O SIMILAR UN
VIDRIO 5MM M2
BISAGRAS COBRIZADA 3" UN
PUERTA PIZANO 0.80 O SIMILAR UN
CERRADURA SCHLAGE OFICINA A 50WS BELL WOOD GOLD O
UN
SIMILAR
CERRADURA SCHLAGE BAO A 40S BELL WOOD GOLD O SIMILAR UN
VENTANA CORREDIZA 1.2X1.2 M2
LMINA COLD ROLLED CAL.18 2.00X1.00 UN
DIVISION DE BAO EN ACERO GALVANIZADO M2
ITEMS DESCRIPCION UN
TUBO CUADRADO DE 1" CAL. 18 m
NGULO HIERRO 3/4 X 1/8 mL
TUBO RECTANGULAR DE 3" X 1 1/4" CAL. 18 ML
BISAGRA ALUMINIO EXT 3 UN
HIERRO CUADRADO 10 MM UN
VENTANA PROYECTANTE .60X.60 UN
VENTANA ALUMINIO FIJA M2
TUBO NEGRO CERRAMIENTO 2" CAL 16 1.5MM ML
TUBO GALVANIZADO AGUA 1 1/2" - 3MM ML
WASH PRIMER GL
MARCO DE MADERA ml
RECUBRIMIENTO EN PLOMO m2
PUERTA TRIPLEX 2.00*1.00 UN
VIDRIO PLOMADO m2
LAMINA DE PLOMO m2
TORNILLO GOLOSO 1X3/16" UN
GUASA D 3/16" UN
MACHIMBRE m2
ESTRUCTURA DE SOPORTE m2
ANTICORROSIVO 507 GRIS gl
ESMALTE SINTET gl
SELLADOR M 140 O SIMILAR gl
DISOLVENTE THINNER CORRIENTE gl
LIJA DE AGUA 965 SUPER UN
LACA TRANSPARENTE MATE PRIMERA CALIDAD gl
YESO PIRAMIDE O SIMILAR 25KG bt
CAOLIN EMPERADOR O SIMILAR 25KG bt
PIEDRA CHINA NO. 3 bt
ESQUINERO BRONCE m
GRANITO NO. 3 bt
CEMENTO BLANCO kg
PIRLAN ALUMINIO m
PERFIL U ALUMINIO 3/8 X 3/8 un
VINILTEX GL
VINILTEX CTE
PINT. KORAZA 2650 GL
PINTU COA PINTUCO GL
ITEMS DESCRIPCION UN
DISOLVENTE PARA EPOXICAS GL
EQUIPO DE PROTECCION GAFAS, MASCARA CON FILTRO DE
UN
SEGURIDAD
MARMOLINA BTO
ACRONAL KG
LATECOL KG
SILICATO KG
GRANITO KG
CARBONATO KG
COLORCEL DE ETERNIT O SIMILAR GL
GRANIPLAST A TODO COSTO M2
ESMALTE PARA EXTERIORES gl
PINTURA ACRILICA PURA PARA TRAFICO GL
ESFERAS REFLECTIVAS KG
DISOLVENTE (3%) ACRILICO GL
TEFLON UN
LLAVE TERMINAL 97722 GRIVAL O SIMILAR DE JARDN UN
ADAPTADOR MACHO 1/2 UN
ADAPTADOR MACHO 3/4 UN
CHEQUE CORTINA R/W 1/2" O SIMILAR UN
CHEQUE DE 3/4"-RED WHITE O SIMILAR UN
CHEQUE CORTINA R/W 1" O SIMILAR UN
CHEQUE CORTINA R/W 1 1/2" O SIMILAR UN
CHEQUE CORTINA R/W 2" O SIMILAR UN
CHEQUE CORTINA R/W 3/4" O SIMILAR UN
LLAVE PASO R/WHITE 1/2 UN
LLAVE PASO R/WHITE 3/4 O SIMILAR UN
LLAVE PASO R/WHITE 1 O SIMILAR UN
LLAVE PASO R/WHITE 1 1/2 O SIMILAR UN
LLAVE PASO R/WHITE 2 O SIMILAR UN
ADAPTADOR MACHO 1" UN
MANGUERA CONEXIN FLEXIBLE UN
LAVAPLATOS 100 X 50 INOXIDABLE SOBREPONER UN
LAVAPLATOS 62 X 48 INOXIDABLE EMPOTRAR UN
GRIFERIA LAVAPLATOS KIT LP MZ PRAKTI O SIMILAR-INCL. DESAGUE UN
LAVAMANOS AVANTI DE COLG UN
LAVAMANOS DE SOBREPONER MARCELLA BLANCO O SIMILAR SIN
UN
GRIFERIA
LAVAMANOS ACUACER DE COLG UN
GRIFERIA LLAVE AUTOMATICA QK23051 PARA LAVAMANOS O
UN
SIMILAR
GRIFERIA PRYSMA 4" O SIMILAR UN
SANITARIO AVANTI UN
SANITARIO ACUACER UN
SANITARIO BALTIC CON FLUXOMETRO UN
ORINAL MEDIANO CON GRIFERIA UN
ORINAL MEDIANO CON FLUXOMETRO UN
ITEMS DESCRIPCION UN
TELEDUCHA CORRIENTE BL UN
DUCHA PRISMA ECONOMICA O SIMILAR UN
DUCHA ANTIVANDALICA UN
DUCHA BALANCE PRESION UN
INCRUSTACIONES PORCELANA: TOALLERO, PAPELERA, JABONERA,
jg
GANCHO ELITE O SIMILAR
SECADOR DE MANOS ELECTRICO UN
BARRAS DE SEGURIDAD, PARA MINUSVALIDOS LONG. .75MT,
UN
ACABADO CRMADO EN ACERO INOXIDABLE
BARRAS DE SEGURIDAD, PARA MINUSVALIDOS LONG. .45MT,
UN
ACABADO CRMADO EN ACERO INOXIDABLE
REJILLA SOSCO 3X2 UN
TANQUES AJOVER 2000 LTS UN
FLOTADOR 3/4" EN BRONCE UN
FLOTADOR 1" EN BRONCE UN
TANQUE PLASTICO 1.000LT UN
SUINGLEA H=,60 UN
ALAMBRE DE PUAS GALVANIZADO CAL. 12.5 m
POSTE CERCA 10 X 10 CM 210 KG/CM2 UN
CONCERTINA DE 14"- ROLLO 6ML ML
TUBO GALVANIZADO AGUA 2 1/2" ML
TUBO GALVANIZADO CERRAMIENTO 2 1/2"X 2.3MM ML
TUBO GALVANIZADO CERRAMIENTO 2"X 2.0MM ML
MALLA ESLABONADA 60 MM X 2.00 M2
CINTA DE ENMASCARAR 1/2" RLL
PORTERA MULTIFUNCIONAL UN
MALLA BASKET UN
MALLA MICROFUTBOL UN
PORTERA MULTIFUNCIONAL UN
MALLA ELECTROSOLDADA E-050 .25X.25 - ,82 KG /M2 M2
CINTA SIKA 22 mL
CAMPAMENTO METALICO UN
GRUA Hr
SACO DE FIQUE+ACCESORIOS UNd
ARBOL NATIVO UNd
PALMERA REAL ALTURA NO MENOR DE 3 MTS. UNd
ABONO M3
GRAMA M2
CARRETILLA BUGGY UN
SIKA O SIMILAR IMPERMEABILIZANTE DE CONCRETOS KG
SUMINISTRO E INSTALACION DE SEALES VERTICALES DE TRANSITO
DE ACUERDO AL MANUAL SOBRE DISPOSITIVOS PARA EL CONTROL
DE TRANSITO EN CALLES Y CARRETERAS EN COLOMBIA Y DEMAS UND
NORMAS COMPLEMENTARIAS
ITEMS DESCRIPCION UN
SUMINISTRO E INSTALACION DE SEALES VERTICALES DE TRANSITO
DE ACUERDO AL MANUAL SOBRE DISPOSITIVOS PARA EL CONTROL UND
DE TRANSITO EN CALLES Y CARRETERAS EN COLOMBIA Y DEMAS
NORMAS COMPLEMENTARIAS
SUMINISTRO E INSTALACION DE SEMAFOROS INCLUYEN LA
UND
INTALACION ELECTRICA PARA PODER OPERAR
SUMINISTRO E INSTALACION DE CANECAS DE BASURA SEGN
DISEO PLANOS UND
2,326,000.00
1,088,000.00
946,000.00
1,751,000.00
81,000.00
650.00
245,000.00
5,000.00
105,000.00
81.76
56,050.00
1,500.00
70,000.00
127,200.00
70,000.00
80,000.00
220,000.00
69,600.00
27,090.00
12.00
90,000.00
49,820.00
40,600.00
2,000.00
2,000.00
2,734.00
VR. UNIT
1,581.00
2,734.00
3,000.00
2,350.00
511.16
1,966.62
1,333.33 8,000.00
2,388.06 8,000.00
2,250.00 13,500.00
2,250.00 13,500.00
3,666.67 22,000.00
2,363.05 22,000.00
5,833.33 35,000.00
2,609.99 35,000.00
3,131.99 42,000.00
2,307.05 55,000.00
20,000.00
14,166.67
7,500.00
4,134.00
3,886.00
42,206.00
1,783.00
2,597.24 2,239.00
15,127.56 13,041.00
17,105.36 14,746.00
8,658.24 7,464.00
9,739.36 8,396.00
5,043.68 4,348.00
12,157.96 10,481.00
65,679.20 56,620.00
31,668.00 27,300.00
8,217.44 7,084.00
10,220.76 8,811.00
1,749.28 1,508.00
2,169.20 1,870.00
5,282.64 4,554.00
2,525.32 2,177.00
1,528.88 1,318.00
1,850.20 1,595.00
6,628.24 5,714.00
5,025.12 4,332.00
12,273.96 10,581.00
5,580.76 4,811.00
7,050.48 6,078.00
36,223.32 31,227.00
VR. UNIT
35,744.24 30,814.00
22,110.76 19,061.00
29,245.73 25,211.83
42,515.35 36,651.17
62,860.40 54,190.00
72,642.49 62,622.83
97,364.60 83,935.00
158,953.06 137,028.50
291,520.85 251,311.08
845,819.80 729,155.00
1,386,351.96 1,195,131.00
1,634,709.12 1,409,232.00
21,159.56 18,241.00
23,665.16 20,401.00
65,535.36 56,496.00
113,746.73
644,564.78
98,580.50
10,440.00
232,000.00
1,288.00
1,388.00
1,488.00
1,750.00
700.00
3,080.00
2,044.00
3,294.00
2,845.00
2,780.00
2,181.00
1,400.00
1,800.00
2,700.00
2,900.00
3,200.00
27,144.00
120,000.00
4,872.00
55,723.00
1,200.00
1,200.00
20,442.00
VR. UNIT
27,529.00
20,442.00
25,571.00
7,324.00
108,000.00
155,000.00
3,180.00
17,123.00
250.00
100.00
59,777.00
22,000.00
228,623.00
1,951.00
3,398.00
425,140.00
111,940.00
750,000.00
420,000.00
11,252.00 337,560.00
20,068.00 602,040.00
34,568.00 518,520.00
10,556.00 58,058.00
31,552.00 157,760.00
41,426.00 207,130.00
1,902.40 57,072.00
10,450.00 44,080.00
7,192.00 32,364.00
4,292.00 987,160.00
10,637.19 170,195.00
5,742.00 114,840.00
7,705.67 69,351.00
19,256.00 308,096.00
3,596.00 35,960.00
3,085.60 30,856.00
4,002.00 80,040.00
30,170.22
684,864.00
545.20
598,084.00
1,582.00
VR. UNIT
3,480.00
1,250.00
1,250.00
17,000.00
17,000.00
11,240.00
20,000.00
3,000.00
12,593.00
4,000.00
3,000.00
2,000.00
3,200.00
3,200.00
6,879.00
37,000.00
8,000.00
18.00
18.00
47,197.00
35,437.00
3,712.00
44,802.00
1,044.00
10,000.00
8,500.00
120,000.00
90,000.00
60,000.00
150,000.00
15,000.00
19,900.00
27,900.00
1,248.00
796.00
2,384.00
1,888.00
17,980.00
17,780.00
14,300.00
28,050.00
25,000.00
18,000.00
4,200.00
2,860.00
VR. UNIT
34,900.00
3,000.00
15,704.00
1,660.00
3,538.00
17,400.00
8,200.00
724.18
759.50
669.42
629.40
27,500.00
46,132.00
46,132.00
48,617.00
57,295.00
48,800.00
35,000.00
5,000.00
5,318.00
2,250.00
2,388.06
86,900.00
1,972.00
800.00
23,950.00
2,854.76 2,461.00
3,572.03 3,079.33
426.88 368.00
2,249.82 1,939.50
591.60 510.00
2,900.00
7,500.00
9,100.00
37,000.00
74,940.00
13,000.00
591.60 510.00
525.48 453.00
327.12 282.00
VR. UNIT
290.00 250.00
1,317.76 1,136.00
1,100.84 949.00
7,426.32 6,402.00
4,735.12 4,082.00
1,741.16 1,501.00
4,571.56 3,941.00
1,318.92 1,137.00
696.00 600.00
13,990.76 12,061.00
2,854.76 2,461.00
11,387.72 9,817.00
7,759.24 6,689.00
28,919.96 24,931.00
24,640.72 21,242.00
421.08 363.00
2,544.85 2,193.83
3,388.36 2,921.00
673.96 581.00
43,860.57 37,810.83
13,099.88 11,293.00
2,813.00 2,425.00
1,549.76 1,336.00
2,030.00 1,750.00
5,541.32 4,777.00
8,522.52 7,347.00
9,023.25 7,778.67
1,811.92 1,562.00
598.56 516.00
955.84 824.00
4,617.96 3,981.00
8,524.84 7,349.00
24,162.80 20,830.00
301.60 260.00
2,179.64
3,135.48
4,542.56
6,999.44
10,791.48
16,753.88
27,351.64
15,726.12
31,306.08
53,586.20
3,892.96
1,048.64
1,060.00
VR. UNIT
3,870.92
1,730.00
1,038.20
138,480.80
56,670.64
386,280.00
391,722.72
455,522.72
399,842.72
480,240.00
971,152.00
528,148.00
1,937,200.00
25,000.00
20,000.00
605,520.00
1,418,680.00
20,000.00
35,000.00
27,840.00
354,743.00
79,600.00
120,000.00
161,268.00
11,463.00
6,049.00
8,004.00
5,567.00
7,852.00
5,429.00
2,029.00
VR. UNIT
4,298.00
1,927.00
4,986.00
13,774.00
5,634.00
61,800.00
1,369.00
140,000.00
858.00
826.00
1,717.00
100.00
3,200.00
19,063.00
10,500.00
6,250.00
13,650.00
80,000.00
25,000.00
16,949.00
65,833.00
180,000.00
10,000.00
30,000.00
290,000.00
881,600.00
71,000.00
9,000.00
4,000.00
7,000.00
4,500.00
3,500.00
4,500.00
2,800.00
2,600.00
3,500.00
700.00
16,000.00
25,000.00
12,000.00
26,000.00
115,000.00
6,000.00
16,000.00
38,000.00
56,000.00
VR. UNIT
21,171.00
211,390.28
72,692.56
4,000.00
78,000.00
125,000.00
16,000.00
273,000.00
115,000.00
110,000.00
650,000.00
169,221.38
2,800,000.00
12,605,430.00
1,500,000.00
50,000.00
5,059,084.00
1,100,000.00
21,397,824.00
2,996,280.00
3,058,804.00
3,533,012.00
4,487,112.00
5,793,620.00
6,967,772.00
9,136,624.00
13,507,620.00
6,054,272.00
7,349,412.00
9,124,444.00
11,432,148.00
14,670,404.00
18,289,488.00
21,643,860.00
25,951,520.00
250,000.00
8,600,000.00
5,800,000.00
15,000.00
131,200.00
1,500,000.00
3,004,600.00
1,474,910.00
VR. UNIT
350,000.00
350,000.00
350,000.00
350,000.00
350,000.00
390,000.00
4,072,000.00
280,000.00
300,000.00
385,000.00
9,000.00
29,000.00
76,000.00
290,000.00
380,000.00
270,000.00
210,000.00
240,000.00
420,000.00
30,000.00
1,509.00
1,914.00
2,000.00
24,520.00
10,000.00
8,200.00
50,000.00
26,000.00
38,705.90
10,000.00
49,874.20
22,919.32
33,000.00
110.00
14,000.00
5,000.00
100.00
17,000.00
27,000.00
286,000.00
66,999.00
VR. UNIT
12,122.00
1,000.00
257,346.00
14,268.00
186,000.00
12,000.00
100.00
2,000,000.00
2,000,000.00
159,300.00
99,200.00
271,000.00
250,000.00
144,000.00
150,000.00
360,000.00
480,000.00
600,000.00
680,000.00
4,500.00
6,500.00
230,000.00
116,000.00
26,000.00
22,000.00
19,000.00
52,000.00
40,500.00
65,000.00
16,500.00
2,484.00
73,617.00
19,000.00
2,262.00
75,209.00
21,480.00
21,027.00
110,000.00
51,381.00
700,000.00
VR. UNIT
2,527.00
2,319.00
5,685.00
2,484.00
19,465.00
105,000.00
123,000.00
6,823.00
16,512.00
49,068.00
140,000.00
180,000.00
41,600.00
62,000.00
11,020.41
12,653.06
10,000.00
11,379.31
120,000.00
75,000.00
85,000.00
78,000.00
80,000.00
95,000.00
98,000.00
VR. UNIT
2,800,000.00
3,400,000.00
54,000.00
8,000.00
45,553.00
45,553.00
53,200.00
1,500.00
370,000.00
270,000.00
55,000.00
78,000.00
11,500.00
#REF!
125,001.60
5,800,000.00
70,000.00
120.00
70.00
17,000.00
2,800.00
31,154.00
63,687.00 15,184.00
45,553.00 1,871.88
15,599.00 3,540.78
1,300.00 2,531.28
45,553.00 33,233.90
15,307.00 45,437.31
9,060.00 101,799.15
1,660.00
17,400.00 162,878.64
10,424.00 61,079.49
980.00 57,748.36
2,722.00
9,492.00
57,751.00
283,001.00
68,875.00
115,942.00
VR. UNIT
26,000.00
80,000.00
11,265.00
7,598.00
8,751.00
7,615.00
300.00
450.00
42,751.00
6,728.00
68,501.00
75,216.00
25,000.00
26,500.00
406.00
13,606.00
225.04
408.32
28,947.00
54,288.00
61,022.00
106,978.00
157,320.00
38,764.00
27,530.00
35,396.00
51,128.00
103,590.00
165,998.00
854.92
2,490.00
130,300.00
83,300.00
69,900.00
77,900.00
94,900.00
64,900.00
185,000.00
55,400.00
175,900.00
130,000.00
579,900.00
241,900.00
469,900.00
VR. UNIT
71,000.00
35,900.00
219,900.04
285,132.64
69,900.00
364,900.04
111,900.56
89,900.00
3,820.00
550,000.00
45,900.00
88,500.00
330,000.00
500.00
378.22
32,480.00
11,000.00
29,576.00
19,842.00
12,283.00
10,700.00
3,316.00
4,200,000.00
10,000.00
104,000.00
2,100,000.00
2,064.46
31,900.00
2,500,000.00
80,000.00
5,000.00
40,000.00
70,000.00
17,000.00
12,000.00
250,000.00
5,975.00
150,000.00
VR. UNIT
120,000.00
2,500,000.00
250,000.00
6,550,000.00
605,000.00
605,000.00
227,586.21
5,030,000.00
88,800.00
54,668.40
44,400.00
19,200.00
32,800.80
21,867.60
32,800.80
13,120.80
68,400.00
84,000.00
38,400.00
36,000.00
36,000.00
7,980.00
2,763.60
10,200.00
6,240.00
9,000.00
5,113.20
3,296.40
264,000.00
540,000.00
4,800.00
VR. UNIT
24,000.00
38,556.00
39,384.00
55,800.00
88,800.00
65,601.60
54,668.00
43,734.40
21,867.20
32,800.80
21,867.20
32,800.80
13,120.32
60,000.00
57,000.00
127,680.00
38,760.00
52,920.00
114,000.00
114,000.00
30,000.00
252,000.00
7,980.00
38,400.00
57,600.00
48,000.00
7,980.00
13,860.00
168,000.00
90,000.00
VR. UNIT
36,000.00
36,000.00
7,980.00
2,763.60
10,200.00
6,240.00
9,000.00
5,113.20
5,113.20
36,000.00
84,000.00
10,200.00
2,280,000.00
1,140,000.00
540,000.00
24,000.00
27,600.00
4,800.00
90,000.00
520,000.00
91,000.00
260,000.00
320,000.00
85,000.00
30,000.00
55,555.49
22,904.97
1,300.00
15,885.00
15,885.00
1,784.00
GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
PRECIOS DE REFERENCIA PARA EL DEPARTAMENTO DEL
CESAR
ANALISIS DE PRECIOS UNITARIOS PARA EL DEPARTAMENTO
DEL CESAR-SUBREGION AGUACHICA
Calle 16 No 12 - 120 - Telefax: (5) 5749671 - e-mail:
obras@gobcesar.gov.co - Valledupar, Cesar.
TABLA DE INCREMENTOS PARA MUNICIPIOS,
CORREGIMIENTOS Y VEREDAS
CONSULTOR: JORGE GOMEZ PAVAJEAU
DISTANCIA (KM): % MAYO DE 2011
XII
INSTALACIONES HIDRAULICAS
275 SUMINISTRO E INSTALACIN
UN
MICROMEDIDOR VOLUMTRICO 1/2"
CLASE B
MICROMEDIDOR VOLUMTRICO 1/2" TIPO B UN 1.00 74,940.00
XIII
INSTALACIONES ELECTRICAS
287 ACOMETIDA 2 No. 6 + 1 No. 8-DUCTO
ML
PVC DE 1 "
SOLDADURA PVC LIQUIDA 1/4 UN 0.01 65,679.20
TUBO CONDUIT 1" ML 1.00 2,813.00
CABLE COBRE THW 8 AWG ML 1.00 4,542.56
CABLE COBRE THW 6 AWG ML 2.00 6,999.44
DESPERDICIO % 0.05 21,682.84
TRANSPORTE % 0.08 22,766.98
HERRAMIENTAS MENORES %MO 0.03 7,117.97
MANO DE OBRA BB hc 0.42 16,947.54
XIV
CARPINTERIA MADERA-METALICA
Y ALUMINIO
GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
PRECIOS DE REFERENCIA PARA EL DEPARTAMENTO DEL
CESAR
ANALISIS DE PRECIOS UNITARIOS PARA EL DEPARTAMENTO
DEL CESAR-SUBREGION AGUACHICA
Calle 16 No 12 - 120 - Telefax: (5) 5749671 - e-mail:
obras@gobcesar.gov.co - Valledupar, Cesar.
TABLA DE INCREMENTOS PARA MUNICIPIOS,
CORREGIMIENTOS Y VEREDAS
CONSULTOR: JORGE GOMEZ PAVAJEAU
DISTANCIA (KM): % MAYO DE 2011
XV
ACABADOS Y PINTURAS
387 LACA TRANSPARENTE SOBRE MADERA M2
SELLADOR M 140 O SIMILAR gl 0.02 45,553.00
DISOLVENTE THINNER PINTUCO O SIMILAR gl 0.02 15,599.00
LIJA DE AGUA 965 SUPER UN 1.00 1,300.00
LACA TRANSPARENTE MATE PRIMERA
gl 0.04 45,553.00
CALIDAD
DESPERDICIO % 0.05 4,345.16
TRANSPORTE % 0.08 4,562.42
HERRAMIENTAS MENORES %MO 0.03 3,756.19
MANO DE OBRA CC hc 0.21 17,717.89
390 ESTUCO M2
YESO PIRAMIDE O SIMILAR 25KG bt 0.01 15,307.00
CAOLIN EMPERADOR O SIMILAR 25KG bt 0.09 9,060.00
CEMENTO GRIS kg 0.26 400.00
LIJA DE AGUA 965 SUPER UN 0.02 1,300.00
DESPERDICIO % 0.05 1,098.47
TRANSPORTE % 0.08 1,153.39
ANDAMIO TUBULAR d 0.50 812.00
HERRAMIENTAS MENORES %MO 0.03 2,065.91
MANO DE OBRA CC hc 0.12 17,717.89
GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
PRECIOS DE REFERENCIA PARA EL DEPARTAMENTO DEL
CESAR
ANALISIS DE PRECIOS UNITARIOS PARA EL DEPARTAMENTO
DEL CESAR-SUBREGION AGUACHICA
Calle 16 No 12 - 120 - Telefax: (5) 5749671 - e-mail:
obras@gobcesar.gov.co - Valledupar, Cesar.
TABLA DE INCREMENTOS PARA MUNICIPIOS,
CORREGIMIENTOS Y VEREDAS
CONSULTOR: JORGE GOMEZ PAVAJEAU
DISTANCIA (KM): % MAYO DE 2011
XVI
APARATOS SANITARIOS-LLAVES
DE CONTROL
412 LLAVE TERMINAL CROMADA 1/2 GRIVAL
UN
O SIMILAR
TEFLON UN 0.30 406.00
DESPERDICIO % 0.05 121.80
LLAVE TERMINAL 97720 GRIVAL O SIMILAR
UN 1.00 13,606.00
DE JARDN
GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
PRECIOS DE REFERENCIA PARA EL DEPARTAMENTO DEL
CESAR
ANALISIS DE PRECIOS UNITARIOS PARA EL DEPARTAMENTO
DEL CESAR-SUBREGION AGUACHICA
Calle 16 No 12 - 120 - Telefax: (5) 5749671 - e-mail:
obras@gobcesar.gov.co - Valledupar, Cesar.
TABLA DE INCREMENTOS PARA MUNICIPIOS,
CORREGIMIENTOS Y VEREDAS
CONSULTOR: JORGE GOMEZ PAVAJEAU
DISTANCIA (KM): % MAYO DE 2011
XVII
VARIOS EXTERIORES Y PARQUES
439 TRAZADO Y REPLANTEO EN ML
CERRAMIENTOS
ESTACA DE MADERA UN 0.30 300.00
PUNTILLA CON CABEZA 2 lb 0.00 1,595.00
DESPERDICIO % 0.05 94.31
TRANSPORTE % 0.08 99.02
TOPGRAFO ms 0.00 1,411,550.00
HERRAMIENTAS MENORES %MO 0.03 250.16
MANO DE OBRA AA hc 0.02 12,507.79
477
JUEGOS DIDACTICOS TIPO 1.
CARPINTERIA DE MADERA MADERA
ROLLIZA INMUNIZADA AL VACO DE
PINO PATULA, ACABADO DE LA MADERA
CON BASE SELLADOR Y BARNIZ SOLAR
Estacones de 3.00 mts x 5" UND 17.00 88,800.00
Estacones de 2.50 mts x 5" UND 5.00 54,668.40
Estacones de 1.5 mts x 5" UND 4.00 44,400.00
Estacones de 1.00 mts x 3.5" UND 24.00 19,200.00
Estacones de 1.5 mts x 4" UND 10.00 32,800.80
Estacones de 1.00 mts x 4" UND 27.00 21,867.60
GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
PRECIOS DE REFERENCIA PARA EL DEPARTAMENTO DEL
CESAR
ANALISIS DE PRECIOS UNITARIOS PARA EL DEPARTAMENTO
DEL CESAR-SUBREGION AGUACHICA
Calle 16 No 12 - 120 - Telefax: (5) 5749671 - e-mail:
obras@gobcesar.gov.co - Valledupar, Cesar.
TABLA DE INCREMENTOS PARA MUNICIPIOS,
CORREGIMIENTOS Y VEREDAS
CONSULTOR: JORGE GOMEZ PAVAJEAU
DISTANCIA (KM): % MAYO DE 2011
478
JUEGOS DIDACTICOS TIPO 2.
CARPINTERIA DE MADERA MADERA
ROLLIZA INMUNIZADA AL VACO DE
PINO PATULA, ACABADO DE LA MADERA
CON BASE SELLADOR Y BARNIZ SOLAR
POSTES DE 4.00MT X 5" UND 6.00 88,800.00
Estacones de 3.00 mts x 5" UND 50.00 65,601.60
Estacones de 2.50 mts x 5" UND 10.00 54,668.00
Estacones de 2.00 mts x 5" UND 4.00 43,734.40
GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
PRECIOS DE REFERENCIA PARA EL DEPARTAMENTO DEL
CESAR
ANALISIS DE PRECIOS UNITARIOS PARA EL DEPARTAMENTO
DEL CESAR-SUBREGION AGUACHICA
Calle 16 No 12 - 120 - Telefax: (5) 5749671 - e-mail:
obras@gobcesar.gov.co - Valledupar, Cesar.
TABLA DE INCREMENTOS PARA MUNICIPIOS,
CORREGIMIENTOS Y VEREDAS
CONSULTOR: JORGE GOMEZ PAVAJEAU
DISTANCIA (KM): % MAYO DE 2011
XVIII
CABLEADO ESTRUCTURADO
489 AISLADOR DE PIN ANSI 55-1 JGO
AISLADOR DE PIN DE ANSI 52-1 UN 1.00 50,000.00
PORTA AISLADOR 3 PUESTO UN 1.00 26,000.00
HERRAMIENTA ELCTRICA %MO 5.00 6,609.54
MANO DE OBRA EE hc 0.33 20,028.91
GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
PRECIOS DE REFERENCIA PARA EL DEPARTAMENTO DEL
CESAR
ANALISIS DE PRECIOS UNITARIOS PARA EL DEPARTAMENTO
DEL CESAR-SUBREGION AGUACHICA
Calle 16 No 12 - 120 - Telefax: (5) 5749671 - e-mail:
obras@gobcesar.gov.co - Valledupar, Cesar.
TABLA DE INCREMENTOS PARA MUNICIPIOS,
CORREGIMIENTOS Y VEREDAS
CONSULTOR: JORGE GOMEZ PAVAJEAU
DISTANCIA (KM): % MAYO DE 2011
VR. PARCIAL
12,909.00
476.74
1,313.58
633.36
3,572.03
299.79
503.64
177.95
5,931.64
6,704.00
71.29
656.79
316.68
2,249.82
164.73
276.74
86.43
2,881.08
MAYO DE 2011
VR. PARCIAL
23,387.00
328.40
158.34
449.96
591.60
2,900.00
2,525.19
347.67
7,500.00
1,184.09
215.57
7,185.76
15,074.00
8.12
0.41
9,100.00
728.68
152.53
5,084.26
MAYO DE 2011
VR. PARCIAL
39,960.00
37,000.00
2,960.00
837,535.00
406,902.81
38,837.31
22,287.01
37,442.17
9,671.81
322,393.54
109,010.71
74,940.00
13,000.00
5,500.00
MAYO DE 2011
VR. PARCIAL
275.00
7,497.20
467.00
213.54
7,117.97
187,960.00
1,183.20
8.12
59.57
165,998.00
13,379.91
213.54
7,117.97
13,308.00
7,426.32
47.35
394.08
MAYO DE 2011
VR. PARCIAL
190.01
290.77
417.43
701.28
111.85
3,728.46
9,723.00
4,571.56
13.19
328.40
158.34
116.23
259.39
435.77
111.85
3,728.46
17,935.00
11,387.72
77.59
328.40
158.34
476.74
621.44
MAYO DE 2011
VR. PARCIAL
1,044.02
111.85
3,728.46
38,968.00
1,313.58
633.36
2,098.61
289.20
24,640.72
1,448.77
2,433.94
177.95
5,931.64
17,862.00
842.16
656.79
316.68
2,544.85
218.02
366.28
376.24
12,541.18
MAYO DE 2011
VR. PARCIAL
25,378.00
2,627.17
1,266.72
97.39
842.29
12,157.96
849.58
1,427.29
177.95
5,931.64
13,338.00
7,050.48
301.51
1,313.58
633.36
464.95
781.11
81.35
2,711.61
6,644.00
2,544.85
210.54
328.40
MAYO DE 2011
VR. PARCIAL
158.34
162.11
272.34
86.43
2,881.08
8,296.00
3,388.36
336.98
656.79
316.68
234.94
394.70
86.43
2,881.08
56,145.00
43,860.57
2,308.98
262.00
2,321.58
3,900.25
101.69
3,389.51
MAYO DE 2011
VR. PARCIAL
31,920.00
328.40
2,813.00
4,542.56
13,998.88
1,084.14
1,821.36
213.54
7,117.97
39,857.00
328.40
2,813.00
4,542.56
20,998.32
1,434.11
2,409.31
213.54
7,117.97
MAYO DE 2011
VR. PARCIAL
1,911,352.00
911,045.44
70,000.00
22,021.44
354,743.00
79,600.00
27,840.00
192,057.00
1,101.07
132,672.64
MAYO DE 2011
VR. PARCIAL
3,503.06
116,768.57
1,648,981.00
783,445.44
70,000.00
14,501.00
354,743.00
192,057.00
725.05
113,237.72
MAYO DE 2011
VR. PARCIAL
3,503.06
116,768.57
1,007,066.00
480,240.00
20,000.00
8,389.12
120,000.00
192,057.00
419.46
65,688.45
3,503.06
116,768.57
MAYO DE 2011
VR. PARCIAL
3,976,713.00
971,152.00
528,148.00
MAYO DE 2011
VR. PARCIAL
1,937,200.00
7,852.00
16,960.00
8,389.12
192,057.00
10,870.31
18,890.27
110,000.00
5,102.75
170,091.70
MAYO DE 2011
VR. PARCIAL
704,338.00
605,520.00
3,180.00
1,572.96
1,000.00
287.65
48,924.85
1,277.27
42,575.62
MAYO DE 2011
VR. PARCIAL
861,649.00
386,280.00
161,268.00
192,057.00
8,480.00
4,194.56
1,000.00
683.73
60,317.06
1,379.67
45,988.85
MAYO DE 2011
VR. PARCIAL
192,057.00
119,183.68
4,134.00
12,800.00
25,850.00
858.00
774.88
598.56
8,180.03
13,790.33
171.48
5,715.94
54,088.00
656.79
8,004.00
7,748.80
826.00
858.00
603.20
1,369.00
10,600.00
MAYO DE 2011
VR. PARCIAL
5,243.20
1,242.60
2,972.13
406.74
13,558.03
45,909.00
656.79
2,029.00
603.20
10,600.00
7,748.80
598.56
826.00
5,243.20
1,272.53
2,366.25
406.74
13,558.03
80,150.00
61,800.00
400.00
MAYO DE 2011
VR. PARCIAL
20.00
4,977.60
377.25
12,575.08
33,719.00
603.20
1,927.00
656.79
5,191.00
598.56
7,748.80
826.00
739.92
1,463.30
406.74
13,558.03
5,683.00
2,029.00
162.32
101.69
3,389.51
8,876.00
MAYO DE 2011
VR. PARCIAL
4,986.00
398.88
101.69
3,389.51
55,731.00
13,774.00
656.79
603.20
5,243.20
10,600.00
7,748.80
598.56
826.00
1,272.53
3,305.85
323.36
10,778.64
93,827.00
15,497.60
598.56
5,546.00
MAYO DE 2011
VR. PARCIAL
10,600.00
34,600.00
1,717.00
656.79
3,097.65
5,785.09
458.09
15,269.74
358,912.00
180,000.00
60,000.00
60,000.00
24,000.00
1,016.85
33,895.09
MAYO DE 2011
VR. PARCIAL
477,712.00
290,000.00
60,000.00
60,000.00
32,800.00
1,016.85
33,895.09
204,681.00
656.79
858.00
603.20
598.56
10,812.00
5,348.06
7,903.78
826.00
140,000.00
MAYO DE 2011
VR. PARCIAL
900.93
13,480.59
660.95
22,031.81
1,197,236.00
881,600.00
140,179.00
35,000.00
65,833.00
2,173.51
72,450.41
140,179.00
85,131.20
4,256.56
7,151.02
1,271.07
42,368.86
581,547.00
MAYO DE 2011
VR. PARCIAL
142,000.00
36,000.00
8,000.00
21,000.00
4,500.00
14,000.00
168,000.00
18,000.00
48,000.00
56,000.00
10,400.00
2,542.35
1,546.73
51,557.81
14,943.00
12,029.25
508.47
MAYO DE 2011
VR. PARCIAL
70.06
2,335.37
321,935.00
12,029.25
156,000.00
25,000.00
15,442.34
3,304.77
110,159.03
447,811.00
12,029.25
156,000.00
240,000.00
1,158.70
38,623.45
MAYO DE 2011
VR. PARCIAL
1,684,547.00
345,000.00
330,000.00
440,331.36
21,171.00
14,000.00
2,800.00
16,000.00
78,000.00
71,000.00
18,000.00
4,000.00
75,000.00
36,000.00
4,500.00
7,000.00
4,500.00
32,000.00
MAYO DE 2011
VR. PARCIAL
11,200.00
5,200.00
22,667.90
4,257.56
141,918.72
1,303,237.00
230,000.00
220,000.00
361,700.76
21,171.00
14,000.00
2,800.00
8,000.00
78,000.00
71,000.00
MAYO DE 2011
VR. PARCIAL
18,000.00
4,000.00
50,000.00
24,000.00
4,500.00
7,000.00
4,500.00
32,000.00
11,200.00
5,200.00
22,701.62
3,304.77
110,159.03
792,043.00
650,000.00
6,825.00
6,250.00
3,756.36
MAYO DE 2011
VR. PARCIAL
125,211.83
762,253.00
650,000.00
6,825.00
6,250.00
2,888.67
96,289.16
228,728.00
178,512.52
9,293.95
10,500.00
4,237.25
762.64
25,421.31
MAYO DE 2011
VR. PARCIAL
1,661,469.00
1,190,083.44
330,000.00
24,162.80
38,000.00
10,500.00
7,627.05
1,779.49
59,316.40
437,139.00
13,201.44
0.00
28,147.14
MAYO DE 2011
VR. PARCIAL
139,765.16
14,302.04
9,110.72
169,221.38
29,899.83
975.47
32,515.56
2,928,191.00
2,800,000.00
8,474.50
3,486.89
116,229.64
MAYO DE 2011
VR. PARCIAL
14,376,123.00
12,605,430.00
1,500,000.00
10,500.00
118,643.00
4,122.83
137,427.62
5,212,699.00
5,059,084.00
MAYO DE 2011
VR. PARCIAL
33,898.00
3,486.89
116,229.64
1,235,037.00
1,100,000.00
50,847.00
2,452.14
81,738.00
26,642,167.00
25,951,520.00
250,000.00
190,630.00
131,666.00
3,447.13
MAYO DE 2011
VR. PARCIAL
114,904.34
2,364,290.00
345,974.64
375,000.00
64,000.00
1,092,000.00
15,000.00
6,250.00
151,857.97
9,151.67
305,055.77
2,734,470.00
688,733.76
375,000.00
64,000.00
MAYO DE 2011
VR. PARCIAL
1,092,000.00
15,000.00
6,250.00
179,278.70
9,151.67
305,055.77
200,722.00
131,200.00
10,496.00
1,719.19
57,306.42
1,274,393.00
MAYO DE 2011
VR. PARCIAL
830,884.80
276,961.60
2,903.19
55,537.48
93,302.97
431.15
14,371.52
109,312.00
67,015.52
10,791.48
8,522.52
4,316.48
62.50
7,256.68
330.48
11,015.90
267,726.00
MAYO DE 2011
VR. PARCIAL
160,758.60
54,703.28
9,023.25
11,224.26
62.50
18,861.75
381.32
12,710.66
164,144.00
109,406.56
16,753.88
8,522.52
6,734.15
62.50
11,318.37
330.48
11,015.90
MAYO DE 2011
VR. PARCIAL
33,195.00
18,170.24
3,135.48
2,813.00
1,205.94
100.00
2,033.97
167.07
5,568.96
46,490.00
27,997.76
4,542.56
2,813.00
1,767.67
100.00
2,977.68
183.24
6,107.89
MAYO DE 2011
VR. PARCIAL
71,051.00
43,165.92
6,999.44
5,541.32
2,785.33
100.00
4,687.36
226.35
7,545.05
10,396,291.00
1,500,000.00
3,004,600.00
1,474,910.00
MAYO DE 2011
VR. PARCIAL
350,000.00
1,750,000.00
350,000.00
350,000.00
350,000.00
390,000.00
25,000.00
763,560.80
6,250.00
2,387.47
79,582.27
12,184,769.00
MAYO DE 2011
VR. PARCIAL
1,500,000.00
3,004,600.00
560,000.00
3,500,000.00
2,100,000.00
300,000.00
700,000.00
390,000.00
25,000.00
16,949.00
6,250.00
2,387.47
79,582.27
MAYO DE 2011
VR. PARCIAL
827,481.00
385,000.00
108,000.00
58,000.00
152,000.00
5,000.00
56,640.00
1,830.33
61,011.15
827,481.00
385,000.00
108,000.00
MAYO DE 2011
VR. PARCIAL
58,000.00
152,000.00
5,000.00
56,640.00
1,830.33
61,011.15
923,601.00
380,000.00
126,000.00
58,000.00
228,000.00
5,000.00
63,760.00
1,830.33
61,011.15
MAYO DE 2011
VR. PARCIAL
804,801.00
270,000.00
126,000.00
58,000.00
228,000.00
5,000.00
54,960.00
1,830.33
61,011.15
392,436.00
210000
54,000.00
58,000.00
5,000.00
26,160.00
1,143.96
MAYO DE 2011
VR. PARCIAL
38,131.97
483,156.00
240000
108,000.00
58,000.00
5000
32,880.00
1,143.96
38,131.97
677,556.00
420000
108,000.00
58,000.00
MAYO DE 2011
VR. PARCIAL
5000
47,280.00
1,143.96
38,131.97
210,285.00
6,049.00
94,064.40
21,796.40
28,130.00
7,501.99
800.00
12,667.34
1,143.96
38,131.97
134,201.00
30,000.00
MAYO DE 2011
VR. PARCIAL
10,563.00
7,748.80
2,415.59
800.00
4,122.19
2,287.92
76,263.94
9,649.00
2,000.00
2,030.00
201.50
500.00
378.52
132.19
4,406.36
712,100.00
12,000.00
100.00
500,000.00
200,000.00
MAYO DE 2011
VR. PARCIAL
779,500.00
159,300.00
99,200.00
271,000.00
250,000.00
4,778,711.00
4,487,112.00
33,750.00
65,833.00
5,592.69
186,422.97
MAYO DE 2011
VR. PARCIAL
997,289.00
14,175.00
13,650.00
828,000.00
68,466.00
2,126.15
70,871.54
1,838,554.00
MAYO DE 2011
VR. PARCIAL
2,933,051.00
MAYO DE 2011
VR. PARCIAL
2,318,337.00
403,428.00
121,800.00
104,000.00
40,500.00
65,000.00
26,504.00
MAYO DE 2011
VR. PARCIAL
1,328.84
44,294.71
318,815.00
26,388.00
7,125.00
13,572.00
1,675.65
147,234.00
80,514.00
22,120.69
587.93
19,597.52
195,816.00
15,832.80
4,275.00
6,786.00
MAYO DE 2011
VR. PARCIAL
1,005.39
73,617.00
66,711.60
13,458.22
411.55
13,718.27
197,223.00
15,832.80
3,325.00
6,786.00
957.89
73,617.00
69,012.00
13,562.46
411.55
13,718.27
30,816.00
MAYO DE 2011
VR. PARCIAL
21,480.00
1,718.40
221.86
7,395.29
30,326.00
21,027.00
1,682.16
221.86
7,395.29
175,705.00
144,000.00
11,520.00
587.93
19,597.52
MAYO DE 2011
VR. PARCIAL
117,142.88
90,100.00
8,000.00
554.65
18,488.23
92,288.00
3,369.04
3,115.40
3,119.80
6,368.70
1,193.85
26,154.45
2,166.06
3,638.98
27,292.38
462.21
MAYO DE 2011
VR. PARCIAL
15,406.86
164,509.00
2,434.95
1,171.84
7,165.42
28,259.55
4,347.00
26,600.00
6,368.70
4,991.68
4,066.96
6,832.49
51,243.66
612.42
20,414.09
810,780.00
700,000.00
58,800.00
MAYO DE 2011
VR. PARCIAL
0.00
494.56
16,485.34
143,212.00
2,434.95
1,171.84
7,165.42
51,381.00
4,347.00
6,368.70
4,991.68
3,893.03
6,540.29
32,701.45
647.09
21,569.60
MAYO DE 2011
VR. PARCIAL
700,000.00
30,000.00
500,000.00
5,000.00
63,461.71
101,538.29
365,000.49
MAYO DE 2011
VR. PARCIAL
10,000.00
310,000.00
2,000.00
16,539.27
26,461.22
83,914.00
33,090.50
4,394.40
1,557.70
3,184.35
1,559.90
2,189.34
3,678.10
18,390.48
462.21
15,406.86
162,000.00
MAYO DE 2011
VR. PARCIAL
150,000.00
12,000.00
11,502.00
585.92
519.23
5,138.10
1,061.45
519.97
391.23
3,286.36
190,725.00
82,560.00
12,000.00
1,910.61
MAYO DE 2011
VR. PARCIAL
4,394.40
1,962.72
1,247.92
2,547.48
8,326.05
62,445.39
388.25
12,941.76
1,004,331.00
14,175.00
13,000.00
828,000.00
68,414.00
2,351.70
78,390.09
252,449.00
69,012.00
MAYO DE 2011
VR. PARCIAL
21,480.00
7,452.00
73,617.00
6,559.63
6,559.63
4,331.25
4,776.53
1,169.93
15,596.64
1,220.22
40,674.10
263,935.00
78,213.60
21,480.00
7,452.00
75,209.00
7,288.48
MAYO DE 2011
VR. PARCIAL
7,288.48
4,331.25
4,776.53
1,169.93
16,576.74
1,169.38
38,979.35
336,623.00
111,600.00
83,510.20
53,200.00
28,800.00
6,670.13
1,459.39
-
MAYO DE 2011
VR. PARCIAL
22,819.18
831.97
27,732.34
267,685.00
74,880.00
72,734.69
53,200.00
28,800.00
6,670.13
456.00
-
-
901.30
30,043.37
MAYO DE 2011
VR. PARCIAL
209,049.00
64,226.25
53,200.00
6,786.00
7,788.50
3,662.00
1,500.00
6,670.13
7,799.50
15,921.75
8,377.71
14,074.55
554.65
18,488.23
600,099.00
500,000.00
40,000.00
60,099.07
MAYO DE 2011
VR. PARCIAL
492,099.00
400,000.00
32,000.00
60,099.07
112,961.00
81,900.00
8,000.00
7,192.00
462.21
15,406.86
444,721.00
157,500.00
104,000.00
40,500.00
65,000.00
MAYO DE 2011
VR. PARCIAL
29,360.00
1,408.57
46,952.40
396,757.00
73,617.00
55,200.00
21,480.00
7,452.00
8,024.56
1,637.90
132,365.80
23,982.18
2,126.15
70,871.54
463,396.00
73,617.00
57,500.00
21,480.00
7,452.00
MAYO DE 2011
VR. PARCIAL
10,699.42
1,637.90
189,094.00
28,918.42
2,126.15
70,871.54
5,912,197.00
5,800,000.00
3,267.89
108,929.56
94,547.00
70,000.00
1,800.00
1,050.00
5,828.00
462.21
15,406.86
35,843.00
17,850.00
MAYO DE 2011
VR. PARCIAL
2,800.00
1,652.00
394.40
13,146.67
8,796.00
911.06
311.98
1,300.00
1,822.12
217.26
364.99
112.69
3,756.19
12,138.00
3,804.80
104.00
195.44
328.34
406.00
212.61
7,087.15
MAYO DE 2011
VR. PARCIAL
1,287.00
15.31
81.54
10.40
26.00
6.66
11.19
406.00
21.26
708.72
3,780.00
153.07
815.40
104.00
26.00
54.92
92.27
406.00
61.98
2,065.91
MAYO DE 2011
VR. PARCIAL
40,800.00
1,261.60
1,867.18
2,856.00
17,400.00
1,169.24
1,964.32
415.99
13,866.17
ML EXP ,40
67,776.00 36,909.00
7,223.84 2,889.54
3,734.36 1,493.74
17,748.00 7,099.20
1,394.00 557.60
1,505.01 602.00
2,528.42 1,011.37
979.88 391.95
32,662.54 22,863.78
50,558.00
2,988.00
MAYO DE 2011
VR. PARCIAL
3,734.36
6,800.00
1,394.00
745.82
1,252.97
979.88
32,662.54
50,558.00
2,988.00
3,734.36
6,800.00
1,394.00
745.82
1,252.97
979.88
32,662.54
2,349.00
577.51
156.00
36.68
61.61
MAYO DE 2011
VR. PARCIAL
406.00
32.35
1,078.48
3,941.00
1,155.02
143.00
64.90
109.03
406.00
60.09
2,002.89
5,062.00
1,732.53
156.00
94.43
158.64
406.00
73.25
MAYO DE 2011
VR. PARCIAL
2,441.52
6,850.00
3,465.06
173.25
291.07
406.00
73.25
2,441.52
6,218.00
2,351.31
117.57
197.51
649.60
84.51
2,817.14
MAYO DE 2011
VR. PARCIAL
8,756.00
4,732.80
236.64
397.56
487.20
84.51
2,817.14
37,560.38
5,632.50
22,794.00
4,375.50
3,807.50
900.00
50.88
38,010.38
5,632.50
22,794.00
4,375.50
MAYO DE 2011
VR. PARCIAL
3,807.50
1,350.00
50.88
15,621.00
4,181.14
209.06
351.22
660.00
297.66
9,922.02
10,282.00
4,131.64
206.58
347.06
487.20
148.83
4,961.01
7,607.00
4,132.50
206.63
347.13
406.00
MAYO DE 2011
VR. PARCIAL
73.25
2,441.52
20,404.00
4,637.68
520.00
257.88
433.25
3,200.00
406.00
318.92
10,630.73
4,781.00
1,962.72
98.14
164.87
74.42
2,480.50
MAYO DE 2011
VR. PARCIAL
3,974.00
1,246.16
5.20
62.57
105.11
74.42
2,480.50
10,205.00
911.06
311.98
325.00
1,822.12
168.51
283.09
185.93
6,197.72
7,345.00
2,165.36
MAYO DE 2011
VR. PARCIAL
132.59
156.00
122.70
206.13
132.88
4,429.47
9,944.00
1,910.61
311.98
650.00
143.63
241.30
131.11
6,555.62
22,164.00
121.80
6.09
13,606.00
MAYO DE 2011
VR. PARCIAL
1,098.71
213.54
7,117.97
39,390.00
580.00
121.80
35.09
28,947.00
2,374.71
213.54
7,117.97
66,697.00
525.48
121.80
32.36
54,288.00
4,397.41
213.54
7,117.97
73,969.00
525.48
121.80
MAYO DE 2011
VR. PARCIAL
32.36
61,022.00
4,936.13
213.54
7,117.97
37,860.00
580.00
121.80
35.09
27,530.00
2,261.35
213.54
7,117.97
46,293.00
525.48
121.80
32.36
35,396.00
2,886.05
213.54
MAYO DE 2011
VR. PARCIAL
7,117.97
63,936.00
1,100.84
121.80
61.13
51,128.00
4,192.94
213.54
7,117.97
166,757.00
1,044.00
4,980.00
301.20
130,300.00
10,930.02
559.27
18,642.30
115,997.00
1,044.00
4,980.00
MAYO DE 2011
VR. PARCIAL
301.20
83,300.00
7,170.02
559.27
18,642.30
94,694.00
69,900.00
5,592.00
559.27
18,642.30
102,350.00
522.00
2,490.00
150.60
77,900.00
6,485.01
431.15
14,371.52
MAYO DE 2011
VR. PARCIAL
120,710.00
522.00
2,490.00
150.60
94,900.00
7,845.01
431.15
14,371.52
88,310.00
522.00
2,490.00
150.60
64,900.00
5,445.01
431.15
14,371.52
203,291.00
185,000.00
MAYO DE 2011
VR. PARCIAL
14,800.00
101.69
3,389.51
63,323.00
55,400.00
4,432.00
101.69
3,389.51
227,146.00
1,044.00
2,490.00
176.70
175,900.00
14,368.86
966.01
32,200.33
177,574.00
1,044.00
2,490.00
176.70
130,000.00
MAYO DE 2011
VR. PARCIAL
10,696.86
966.01
32,200.33
675,685.00
1,044.00
2,490.00
176.70
579,900.00
46,688.86
1,321.91
44,063.61
295,602.00
1,044.00
52.20
241,900.00
19,439.70
966.01
32,200.33
554,061.00
1,044.00
52.20
MAYO DE 2011
VR. PARCIAL
469,900.00
37,679.70
1,321.91
44,063.61
104,610.00
71,000.00
5,680.00
813.48
27,116.07
56,228.00
35,900.00
2,872.00
508.43
16,947.54
95,123.00
69,900.00
1,044.00
MAYO DE 2011
VR. PARCIAL
5,675.52
538.93
17,964.40
97,430.26
89,900.00
313.20
7,217.06
0.00
0.00
8,472.00
80.00
4.00
3,820.00
312.32
123.95
4,131.81
MAYO DE 2011
VR. PARCIAL
929,487.00
550,000.00
45,900.00
54,288.00
70,792.00
3,678.36
3,557.78
177.89
58,271.52
4,159.85
138,661.71
683,635.00
330,000.00
45,900.00
54,288.00
MAYO DE 2011
VR. PARCIAL
70,792.00
3,678.36
3,557.78
177.89
40,671.52
3,919.50
130,650.15
506.00
90.00
4.31
4.72
7.92
141.16
7.50
250.16
39,802.00
1,000.00
MAYO DE 2011
VR. PARCIAL
1,966.77
148.34
16,240.00
15,601.65
2,796.54
59.66
1,988.74
15,931.00
11,000.00
378.22
568.91
955.77
88.19
2,939.63
16,521.00
10,700.00
600.00
565.00
135.60
MAYO DE 2011
VR. PARCIAL
4,520.00
39,805.00
9,921.00
10,700.00
600.00
5,837.57
1,352.93
2,272.92
377.18
254.65
8,488.40
MAYO DE 2011
VR. PARCIAL
870,749.00
3,968.00
20,116.48
95,215.36
96,523.25
136,368.00
194,783.53
MAYO DE 2011
VR. PARCIAL
249,696.00
74,078.00
494.00
90.00
4.31
4.72
7.92
11.27
375.62
2,506.00
1,128.24
1,175.00
10.60
185.11
MAYO DE 2011
VR. PARCIAL
5.00
1.77
1,881.00
846.18
881.25
7.95
138.83
5.00
1.77
3,972.00
1,128.24
1,245.50
150.00
118.69
211.39
5.00
32.42
1,080.79
MAYO DE 2011
VR. PARCIAL
32,241.00
9,025.92
11,750.00
84.80
1,668.86
4,750.00
4,961.01
4,040,716.00
3,400,000.00
10,000.00
104,000.00
164,181.60
294,254.53
1,988.74
66,291.29
3,253,227.00
MAYO DE 2011
VR. PARCIAL
2,800,000.00
10,000.00
104,000.00
35,025.41
235,922.03
1,988.74
66,291.29
38,863.00
24,323.20
2,064.46
1,319.38
231.10
2,235.05
986.00
7,703.43
61,150.13
36,546.62
MAYO DE 2011
VR. PARCIAL
150.00
4,166.40
900.00
200.00
2,000.01
6,610.53
10,576.57
3,519.98
2,568.00
95.69
100.00
130.72
100.00
202.14
323.43
17,676.00
11,252.00
136.70
MAYO DE 2011
VR. PARCIAL
569.44
956.65
138.66
4,622.06
24,638.00
20,068.00
112.50
1,009.03
1,695.16
51.05
1,701.83
44,116.00
34,568.00
136.70
1,735.24
2,915.19
138.66
4,622.06
MAYO DE 2011
VR. PARCIAL
3,483,720.00
2,500,000.00
578,730.60
246,298.45
4,622.06
154,068.57
74,259.00
42,565.60
4,800.00
3,760.00
4,090.05
554.65
18,488.23
MAYO DE 2011
VR. PARCIAL
168,898.00
32,000.00
5,000.00
90,000.00
10,160.00
924.41
30,813.71
83,402.00
40,000.00
24,000.00
5,120.00
415.99
13,866.17
MAYO DE 2011
VR. PARCIAL
115,802.00
70,000.00
24,000.00
7,520.00
415.99
13,866.17
160,580.00
25,539.36
34,045.20
1,315.95
3,045.03
5,115.64
9,000.00
2,403.47
80,115.66
MAYO DE 2011
VR. PARCIAL
236,653.00
138,642.24
19,975.00
12,689.38
22,500.00
1,247.96
41,598.51
30,000.00
30,000.00
MAYO DE 2011
VR. PARCIAL
0.00
0.00
9,902.00
225.00
3,900.00
3,000.00
570.00
50.00
2,156.96
9,594.00
225.00
3,900.00
3,000.00
570.00
50.00
1,848.82
MAYO DE 2011
VR. PARCIAL
15,869.00
462.21
15,406.86
15,869.00
462.21
15,406.86
481,917.00
42,224.00
250,528.96
12,750.00
15,275.15
MAYO DE 2011
VR. PARCIAL
25,662.25
65,000.00
7,000.00
1,848.82
61,627.43
187,107.00
150,000.00
10,945.44
547.27
12,919.42
369.76
12,325.49
MAYO DE 2011
VR. PARCIAL
185,535.00
120,000.00
31,133.70
1,556.68
12,215.23
600.87
20,028.91
2,794,530.00
2,500,000.00
MAYO DE 2011
VR. PARCIAL
31,133.70
1,556.68
7,626.39
254,213.14
325,935.00
250,000.00
31,133.70
1,556.68
22,615.23
600.87
20,028.91
7,718,216.00
MAYO DE 2011
VR. PARCIAL
6,550,000.00
316,201.60
15,810.08
550,560.93
8,319.70
277,323.42
7,909,289.00
605,000.00
605,000.00
227,586.21
MAYO DE 2011
VR. PARCIAL
5,030,000.00
715,102.08
35,755.10
577,475.47
3,302.05
110,068.48
7,310,917.20
1,509,600.00
273,342.00
177,600.00
460,800.00
328,008.00
590,425.20
MAYO DE 2011
VR. PARCIAL
98,402.40
813,489.60
136,800.00
84,000.00
38,400.00
72,000.00
36,000.00
47,880.00
96,726.00
10,200.00
24,960.00
36,000.00
10,226.40
9,889.20
MAYO DE 2011
VR. PARCIAL
264,000.00
1,080,000.00
72,000.00
48,000.00
38,556.00
39,384.00
90,000.00
55,800.00
48,780.00
170,262.40
549,386.00
22,256,193.36
532,800.00
3,280,080.00
546,680.00
174,937.60
MAYO DE 2011
VR. PARCIAL
174,937.60
328,008.00
787,219.20
590,414.40
2,860,229.76
240,000.00
114,000.00
255,360.00
38,760.00
105,840.00
MAYO DE 2011
VR. PARCIAL
228,000.00
228,000.00
30,000.00
252,000.00
103,740.00
38,400.00
57,600.00
48,000.00
39,900.00
MAYO DE 2011
VR. PARCIAL
116,424.00
168,000.00
90,000.00
72,000.00
36,000.00
95,760.00
525,084.00
183,600.00
49,920.00
72,000.00
25,566.00
25,566.00
36,000.00
672,000.00
81,600.00
2,280,000.00
1,140,000.00
MAYO DE 2011
VR. PARCIAL
1,620,000.00
96,000.00
220,800.00
576,000.00
180,000.00
154,224.00
118,152.00
90,000.00
55,800.00
48,780.00
826,988.80
1,545,022.00
613,605.00
520,000.00
3,891.71
41,911.34
194.59
MAYO DE 2011
VR. PARCIAL
1,386.62
46,220.57
126,497.00
91,000.00
3,891.71
194.59
7,606.90
693.31
23,110.29
324,886.00
260,000.00
3,891.71
194.59
21,126.90
1,155.51
38,517.14
MAYO DE 2011
VR. PARCIAL
365,882.00
320,000.00
3,891.71
194.59
25,926.90
462.21
15,406.86
43,104.00
732.40
9,944.00
36.62
7,000.00
739.53
24,650.97
173,429.00
85,000.00
MAYO DE 2011
VR. PARCIAL
30,000.00
1,701.83
56,727.52
177,129.00
120,000.00
1,663.94
55,464.68
226,650.00
160,000.00
1,941.26
64,708.80
347,580.52
166,666.48
151,172.82
15,173.33
520.00
520.00
MAYO DE 2011
VR. PARCIAL
520.00
6,660.25
184.88
6,162.74
243,960.16
47,655.00
104,841.00
15,173.33
713.60
520.00
520.00
3,353.39
2,073.32
69,110.53
82,940.02
50,000.00
26,000.00
330.48
6,609.54
MAYO DE 2011
VR. PARCIAL
102,905.40
5,805.89
21,200.00
50,871.68
12,147.24
709.02
354.51
11,817.06
88,560.65
33,000.00
330.00
14,000.00
20,000.00
1,001.45
200.29
20,028.91
103,530.65
33,000.00
300.00
14,000.00
35,000.00
1,001.45
MAYO DE 2011
VR. PARCIAL
200.29
20,028.91
50,509.78
2,550.00
27,000.00
330.00
400.58
200.29
20,028.91
60,889.78
2,550.00
27,000.00
210.00
10,500.00
400.58
200.29
20,028.91
381,441.35
4,000.00
286,000.00
69,008.97
2,002.89
MAYO DE 2011
VR. PARCIAL
400.58
20,028.91
91,773.60
40,000.00
15,273.72
14,668.36
1,201.73
600.87
20,028.91
648,110.05
4,000.00
286,000.00
69,008.97
265,066.38
2,002.89
2,002.89
20,028.91
50,192.00
29,962.80
200.29
20,028.91
MAYO DE 2011
VR. PARCIAL
209,290.94
187,860.00
1,001.45
400.58
20,028.91
39,939.56
245.20
10,300.00
8,364.00
1,001.45
20,028.91
GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
PRECIOS DE REFERENCIA PARA EL DEPARTAMENTO DEL
CESAR (5) 5749671 - e-mail:
Calle 16 No 12 - 120 - Telefax:
obras@gobcesar.gov.co - Valledupar, Cesar.
FECHA: MAYO DE 2011
CONSULTOR: JORGE GOMEZ PAVAJEAU
MATERIALES BASICOS
CEMENTO GRIS kg 400.00
PIEDRA M3 45,000.00
ARENA M3 30,000.00
GRAVILLA FINA M3 50,000.00
AGUA lt 12.72
TRITURADO INCL. TRANSPORTE CANTERA A 64KM M3 80,000.00
ABONO M3 30,000.00
REVUELTO M3 33,000.00
RELLENO SELECCIONADO M3 30,000.00
RELLENO GRANULAR-SUB-BASE M3 30,000.00
RELLENO GRANULAR-BASE M3 40,000.00
LADRILLO AGUACHICA 10X20X30 UN 800.00
LADRILLO BOCADILLO .19x.15x.09 UN 350.00
LADRILLO A LA VISTA .07X.09X.25 CORAL 56 M2 UN 850.00
LADRILLO A LA VISTA .07X.09X.25 ESFUMADO 56 M2 UN 760.00
LADRILLO A LA VISTA .07X.09X.25 VITRIFICADO 56 M2 UN 1,100.00
LADRILLO 9X19X30 UN 780.00
ALGARROBILLO PIE 1,200.00
ABARCO PIE
TOLUA PIE 4,000.00
CARRETO PIE 3,000.00
RETIRO ESCOMBROS M3 16,000.00
EQUIPOS
ANDAMIOS DIA 812.00
CERCHAS METALICAS DIA 190.00
PARALES METALICOS 3 Y 4MT DIA 190.00
TABLONES DIA 464.00
TABLERO DE MADERA .70 X 1.40 (CHAZAS) DIA 232.00
GUARDERAS .40 X 1.40 DIA 245.00
TABLEROS PARA MUROS .40 X 1.45 DIA 640.00
CORTADORA PAVIMENTO 5CM ML 5,800.00
MEZCLADORA, RANA, VIBRADOR, MOTOBOMBA SIN OPERADOR DIA 64,000.00
ANALISIS BASICOS
MORTERO 1:3 M3
CEMENTO GRIS kg 450.00 400.00
AGUA lt 220.00 12.72
ARENA M3 1.09 30,000.00
HERRAMIENTAS MENORES d 0.03 8,509.13
AYUDANTE ALBAILERA (A) hr 1.50 5,672.75
MORTERO 1:4 M3
CEMENTO GRIS kg 352.00 400.00
AGUA lt 185.00 12.72
ARENA M3 1.16 30,000.00
HERRAMIENTAS MENORES d 0.03 8,509.13
AYUDANTE ALBAILERA (A) hr 1.50 5,672.75
MORTERO 1:5 M3
CEMENTO GRIS kg 300.00 400.00
AGUA lt 150.00 12.72
ARENA M3 1.20 30,000.00
GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
PRECIOS DE REFERENCIA PARA EL DEPARTAMENTO DEL
CESAR (5) 5749671 - e-mail:
Calle 16 No 12 - 120 - Telefax:
obras@gobcesar.gov.co - Valledupar, Cesar.
FECHA: MAYO DE 2011
CONSULTOR: JORGE GOMEZ PAVAJEAU
HERRAMIENTAS MENORES d 0.03 8,509.13
AYUDANTE ALBAILERA (A) hr 1.50 5,672.75
MORTERO 1:4 IMPERMEABILIZADO M3
CEMENTO GRIS kg 352.00 400.00
AGUA lt 185.00 12.72
ARENA M3 1.16 30,000.00
SIKA-1 (20 KG) IMPERMEABILIZANTE INTEGRAL PARA
MORTEROS. IMPERMEABILIZACIN kg 16.66 5,742.00
95,661.72
255.27
8,509.13
286,436.00
190,000.00
2,544.00
16,800.00
60,000.00
8,328.00
255.27
8,509.13
250,309.00
152,000.00
2,416.80
18,000.00
60,800.00
8,328.18
255.27
8,509.13
263,337.00
170,000.00
2,544.00
20,100.00
53,600.00
8,328.18
255.27
8,509.13
255,818.00
140,000.00
2,289.60
16,650.00
67,200.00
12,586.00
8,328.18
255.27
8,509.13
243,232.00
140,000.00
2,289.60
16,650.00 229124.75
67,200.00
8,328.18
255.27
8,509.13
229,655.00
120,000.00
2,162.40
14,400.00
76,000.00
8,328.18
255.27
8,509.13
203,437.00
90,000.00
1,844.40
16,500.00
78,000.00
8,328.18
255.27
8,509.13
184,523.00
64,000.00
1,780.80
19,650.00
82,000.00
8,328.18
255.27
8,509.13
205,941.00
100,800.00
2,098.80
18,750.00
67,200.00
8,328.18
255.27
8,509.13
16,558.93
4,071.43
2,544.64
9,942.86
6,548.70
1,824.00
1,012.70
3,712.00
178,440.00
11,400.00
167,040.00
258,360.00
7,800.00
250,560.00
97,200.00
13,680.00
83,520.00
121,166.00
39,368.00
11,664.45
70,133.70
156,659.00
39,368.00
39,368.00
51,578.24
11,664.45
14,680.00
6,840.00
2,200.00
4,640.00
13,680.00
4,400.00
9,280.00
12,866.00
2,485.71
9,280.00
1,100.00
9,700.00
4,200.00
5,500.00
56,050.00
4,800.00
51,250.00
38,625.00
4,800.00
33,825.00
7,220.00
6,400.00
820.00
169,221.38
82,292.80
23,065.71
6,598.00
1,603.14
2,544.28
1,247.92
3,520.56
48,348.97
140,439.90
63,786.80
24,826.92
3,299.00
1,687.52
2,544.28
1,247.92
2,921.77
40,125.69
GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
PRECIOS DE REFERENCIA PARA EL DEPARTAMENTO DEL
CESAR (5) 5749671 - e-mail:
Calle 16 No 12 - 120 - Telefax:
obras@gobcesar.gov.co - Valledupar, Cesar.
FECHA: MAYO DE 2011
TARIFAS MANO DE OBRA Y PRESTACIONES SOCIALES 2011.
1.-SALARIOS DE MANO DE OBRA
PRESTACIONES BASE
Cesantias E 10.00% 718,421
Intereses Cesantias 12.00% 86,210
Vacaciones 15 Dias A 50.00% 267,800
Primas 30 Dias C 100.00% 599,560
OTROS COSTOS
Botas y Overol 82,500 3.00 247,500
Seguro Colectivo D 0.50% 32,582
SEGURIDAD SOCIAL
Pensiones D 12.00% 781,976
Medicina Familiar D 8.50% 553,900
Riesgos Profesionales D 5.60% 364,922
APORTES SENA
Aporte Ordinario D 2.00% 130,329
F.I.C Nota 4 18.00% 138,154
OTROS APORTES
I.C.B.F D 3.00% 195,494
Subsidio Familiar D 4.00% 260,659
NOTAS:
1.- Subsidio de transporte solo se paga hasta sueldos de 2 salarios minimos mensules legales vigentes.
2.- Subsidio de transporte anual = Subsidio mensual / 30 x (365 dias-18 fiestas - 3 permisos- 15 dias vacaciones).
3.- Porcentajes solo son validos para actividades de construccion. Para otros empleados se debe utilizar 30 dias de cesantia y 2.2%
(promedio para empresas de bajo riesgo).
4.- Un salario minimo por cada 40 trabajadores. El valor se obtiene asi: (Salario minimo x 12 / 40) / Salario annual estudiado.
5.- El crecimiento promedio del PIB entre 2005 y 2006 fue superior al 4%y por ello la cotizacion a pensiones por parte del patrono durante
2009 debe aumentar al 12%, segun lo dispuesto por la ley 297 del 2003.
* Todos los porcentajes estan relacionados con el salario para 365 dias.
* Los 18 feriados hacen referencia a los dias feriados que de lunes a viernes tendra 2009.
NOTAS:
Los factores de sobrecostos se utilizan para valorizar el tiempo efectivo que un obrero dedica a su labor y refleja el costo del tiempo durante
el cual no esta trabajando pero si esta devengando.
Si se toma como base la hora calendario, se incrementa 24.57% para obtener la hora efectiva.
Si se toma como base la hora laboral, se incrementa 6.83% para obtener la hora efectiva.
NOTAS:
Jornal = sueldo mensual x 12 meses / 365 dias.
100.00%
11.35%
10.98%
1.32%
4.11%
9.20%
4.09%
0.50%
12.00%
8.50%
5.60%
2.00%
1.80%
3.00%
4.00%
67.10%
s).
s de cesantia y 2.2%
ual estudiado.
r parte del patrono durante
BREROS CON UN
100.00%
116.61%
124.57%
556200
6767100
743027.58
0
METRO CUBICO
CANTIDAD DE ARENA, CEMENTO, BALASTO Y RESISTENCIAS QUE SE OBTIENEN
CEMENTO ARENA BALASTO AGUA LITROS
MEZCLA KILOS SACOS M3 M3 Agr. Hum. Agr. Sec.
1.2.2 420 8.5 0.670 0.670 180 200
1. 2. 2 1/2 380 7.5 0.600 0.760 170 190
1. 2. 3 350 7 0.555 0.835 160 180
1. 2. 3 1/2 320 6.5 0.515 0.900 160 180
1. 2. 4 300 6 0.475 0.950 145 170
1. 2 1/2. 4 280 5.5 0.555 0.830 145 170
1. 2 1/2. 4 1/2 260 5.25 0.520 0.940 140 160
1. 3. 3 300 6 0.715 0.715 145 170
1. 3. 4 280 5.25 0.625 0.825 140 165
1. 3. 5 230 4.5 0.555 0.975 135 160
1. 3. 6 210 4 0.500 1,000 130 155
1. 4. 7 175 3.5 0.555 0.975 120 145
1. 4. 8 160 3.25 0.655 1,025 110 140
En redes de Gas:
Dimetro de la tubera Ancho de zanja (m)
20 mm a 180 mm 0,40
200 m a 315 mm 0,60
Para dimetros mayores a los contemplados en estas tabla, el ancho de la zanja ser igual al
dimetro exterior de la tubera ms 0,40 m a cada lado. Para las domiciliarias de acueducto y
gas se utilizar un ancho de zanja de 0,40 m.
El ancho de las excavaciones se incrementar cuando se requiera entibado de acuerdo con el
espesor determinado para ste.
Cuando se presenten derrumbes la Interventora definir el tipo de cimentacin a utilizar de
acuerdo con las nuevas condiciones de la zanja.
1.1.2. Profundidad de las Zanjas. Las zanjas para la colocacin de las tuberas de redes de
servicios tendrn las profundidades indicadas en los planos, incluyendo las requeridas para la
cimentacin. Cuando en la ejecucin de las zanjas se emplee equipo mecnico, las
excavaciones se llevarn hasta una cota de 0,20 m por encima de la indicada en los planos.
Se excavar el resto por medios manuales y en forma cuidadosa, para no alterar el suelo de
fundacin y nivelar el fondo de la excavacin, de tal manera que la distribucin de esfuerzos
sea uniforme en la superficie de apoyo del tubo y evitar que ste quede sometido a esfuerzos
de flexin.
Si los materiales encontrados a las cotas especificadas de colocacin de las tuberas no son
aptos para la instalacin de las mismas, la excavacin se llevar hasta la profundidad indicada
por la Interventora, quien tambin definir el material de apoyo a utilizar. Esta sobreexcavacin
y entresuelo se medirn y pagarn de acuerdo con los tems correspondientes.
Las excavaciones en roca se llevarn hasta una cota de por lo menos 0,10 m por debajo de la
indicada en los planos, el volumen adicional excavado se llenar con material seleccionado que
sirva de apoyo uniforme y adecuado. Los precios de estas actividades se pagarn en los tems
respectivos.
E SE OBTIENEN
A LOS 24 DIAS
KG/CM2 LB/IN2
250 3555
240 3400
220 3130
210 3000
200 2850
190 2700
180 2560
170 2400
160 2280
140 2000
120 1700
110 1560
100 1420