Está en la página 1de 3

PLANILLA DE METRADAOS

PROYECTO :
UBICACIN :
PROPIETARIO:

PART DECRIPCION METRADO


UNID NUM LARGO ANCHO ALTURA SUB TOT. TOTAL
1.00.00 GUARDIANIA Y ALMACEN
1.01.00 TRABAJOS PRELIMIARES
1.01.01 TRAZO NIVELACION Y REPLANTEO m2 45.10
1 6.40 4.40 28.16
1 4.40 3.85 16.94
1.01.02 CARTEL DE OBRA DE 2.40x3.60 unid 1 1.00 1.00
1.02.00 MOVIMIENTO DE TIERRAS
1.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS
HASTA 1.00 m EN TERRENO NORMAL m3 8.53
EJE 1 1 7.70 0.40 0.70 2.16
EJE 2 1 4.55 0.40 0.70 1.27
EJE 3 1 3.55 0.40 0.70 0.99
EJE A 1 5.55 0.40 0.70 1.55
EJE B 1 5.55 0.40 0.70 1.55
EJE C 1 3.55 0.40 0.70 0.99
1.02.02 RELLENO COMPACTADO (MAT. PRESTAMO) m3 2.44
EJE 1 1 7.70 0.40 0.20 0.62
EJE 2 1 4.55 0.40 0.20 0.36
EJE 3 1 3.55 0.40 0.20 0.28
EJE A 1 5.55 0.40 0.20 0.44
EJE B 1 5.55 0.40 0.20 0.44
EJE C 1 3.55 0.40 0.20 0.28
1.03.00 OBRAS DE CONCRETO SIMPLE
1.03.01 CIMIENT. CORRID. MEZCLA 1:10, C:H +30%PG m3 6.09
EJE 1 1 7.70 0.40 0.50 1.54
EJE 2 1 4.55 0.40 0.50 0.91
EJE 3 1 3.55 0.40 0.50 0.71
EJE A 1 5.55 0.40 0.50 1.11
EJE B 1 5.55 0.40 0.50 1.11
EJE C 1 3.55 0.40 0.50 0.71
1.03.02 SOBRE CIMIENTO
1.03.02.1 ENCOFRADO Y DESENCOFRADO NORMAL
PARA SOBRECIMIENTOS m2 2 26.15 0.30 15.69 15.69
1.03.02.2 CONCRETO 1:8, C:H +25% PM m3 1 26.15 0.30 0.15 1.18 1.18
1.03.03 FALSO PISO DE 3" DE CONCRETO 1:8 m2 41.80
ALMACEN 1 5.00 3.00 15.00
GUARDIANIA 1 4.00 3.00 12.00
VEREDAS (FRONTIS) 1 10.25 0.70 7.18
VEREDA(LATERAL Y POSTERIOR) 1 19.05 0.40 7.62
1.04.00 OBRAS DE CONCRETO ARMADO
COLUMNAS
1.04.01.1 ENCOF. Y DESNCOF. NORMAL EN COLUMNAS m2 8 2.95 0.60 14.16 14.16
1.04.01.2 CONCRETO EN COL. Fc=175 Kg/Cm2 m3 8 2.95 0.15 0.15 0.53 0.53
1.04.01.3 ACERO CORRUGADO DE 3/8" EN COLUMNAS kg 32 2.18 69.60 69.60
1.04.01.4 ACERO LISO DE 1/4" EN COLUMNAS kg 160 0.18 28.00 28.00
1.05.00 MUROS Y TABIQUES
1.05.1 TABIQUERIA DE MADERA (CHAPAS) m2 69.25
EJE 1 1 7.00 2.95 20.65
PART DECRIPCION METRADO
UNID NUM LARGO ANCHO ALTURA SUB TOT. TOTAL
EJE 2 1 4.00 2.95 11.80
EJE 3 1 3.00 2.95 8.85
EJE A 1 4.85 2.95 14.31
EJE B 1 4.85 2.95 14.31
EJE C 1 3.00 2.95 8.85
PUERTAS -4.56
VENTANAS -4.96
1.06.00 TECHOS
ESTRUCTURA DE MADERA
1.06.1 VIGA DE MADERA DE 6"X6" m 1 22.00 22.00 22.00
1.06.2 VIGA DE MADERA DE 4"X6" m 1 6.30 6.30 6.30
1.06.3 LISTONES DE MADERA DE 3"X3" m 1 70.00 70.00 70.00
1.06.4 VARETAS DE MADERA DE 2"X1" m 1 64.00 64.00 64.00
1.06.5 CUBIERTA CON TEJA ANDINA (1.16X0.72m) m2 47.52
ALMACEN 1 6.40 4.40 28.16
GUARDIANIA 1 4.40 4.40 19.36
2.00.00 LINEA DE CONDUCCION (CANAL)
2.01.00 EXCAVACION DE CAJA DE CANAL
EN MATERIAL COMUN m3 55.30
PARA MEJORAM DE BASE 1 184.34 0.37 0.20 13.64
CAJA DE CANAL 184.34 0.76 0.37 0.40 41.66
2.02.00 RELLENO COMPACTADO CON MAT PRESTAMO m3 1 184.34 0.37 0.20 13.64 13.64
2.03.00 CONCRETO fc=175Kg/Cm2 P/REVEST e=0.075m m3 1 184.34 1.28 0.08 17.70 17.70
2.04.00 SELLADO DE JUNTAS DE DILAT. CON ASFALT m 54 1.28 69.12 69.12
3.00.00 OBRAS DE ARTE ( CAPTACION)
3.01.00 EXVACION P/CIMENTACION m3 40.83
PARA MUROS DE ENCAUSAMIENTO 2 7.97 1.00 2.00 31.88
PARA BARRAJE 1 6.00 4.97 0.30 8.95
3.02.00 C CIMIENTO MURO, fc=140Kg/Cm2+40%PG m3 2 7.97 1.00 1.20 19.13 19.13
3.03.00 C MURO, fc=175Kg/Cm2+25%PM m3 2 7.97 1.00 0.30 15.54 15.54
3.04.00 C BARRALE, fc=175Kg/Cm2+40%PG m3 1 6.00 1.50 0.80 7.20 7.20
3.05.00 C SOLADO, fc=140 Kg/Cm2+40%PG m3 1 6.00 3.47 0.30 6.25 6.25
3.06.00 COMPUERTA METALICA DE 1.50x0.50 (C/Izaje) Unid 1 1.00 1.00
4.00.00 ESTANQUES
4.01.00 MOVIMIENTO DE TIERRAS
4.01.01 CORTE PARA NIVELACION TERRENO m3 1 22.00 17.00 1.00 374.00 374.00
4.01.02 EXCAVACION PARA CIMENT ESTANQUES 192.80
ESTANQUES ALEVINOS m3 1 8.30 2.50 0.30 6.23
ESTANQUES CRECIMIENTO Y ENGORDE m3 2 20.30 5.50 0.50 111.65
ESTANQUE CIRCULAR m3 1 47.12 5.30 0.30 74.92
4.01.03 RELLENO COMPACTADO CON MAT PRESTAMO m3 98.76
ESTANQUES ALEVINOS 1 8.30 2.50 0.20 4.15
ESTANQUES CRECIMIENTO Y ENGORDE 2 20.30 5.50 0.20 44.66
ESTANQUE CIRCULAR 1 47.12 5.30 0.20 49.95
4.02.00 OBRAS DE CONCRETO SIMPLE
4.02.01 ENCOFRADO Y DESENCOFRADO DE MUROS
DE ESTANQUES m2 324.80
ALEVINOS 8 7.00 0.80 44.80
CRECIMIENTO Y ENGORDE 12 20.00 1.00 240.00
16 2.50 1.00 40.00
4.02.02 C fc=140Kg/Cm2 LOSA DE FONDO m3 47.90
ESTANQUES ALEVINOS 2 8.00 1.00 0.10 1.60
ESTANQUES CRECIMIENTO Y ENGORDE 4 20.00 2.50 0.10 20.00
ESTANQUE CIRCULAR 1 47.12 5.30 0.10 24.97
LOSA CANAL (ALIMENTACION Y SALIDA) 1 59.15 0.30 0.08 1.33
PART DECRIPCION METRADO
UNID NUM LARGO ANCHO ALTURA SUB TOT. TOTAL
4.02.03 C fc=175Kg/Cm2 MUROS m3 45.95
ESTANQUES ALEVINOS 1 28.90 0.90 0.15 3.90
ESTANQUES CRECIMIENTO Y ENGORDE 1 141.80 1.10 0.15 23.40
ESTANQUE CIRCULAR 0.00
1 30.47 1.10 0.15 5.03
1 62.83 1.10 0.15 10.37
MUROS DE CANAL(ALIMENTACION Y SALIDA) 2 59.15 0.28 0.10 3.25