AREA DE CONSTRUCCIONES
OBRA:
RUBRO:
DETALLE: ADOQUINADO
EQUIPOS
DESCRIPCION CANTIDAD A TARIFA B COSTO HORA C=A*B
SUBTOTAL M
MANO DE OBRA
DESCRIPCION JORNAL/HR
CANTIDAD A COSTO HORA C=A*B
(CATEG.) B
ADOQUINADO
PEON 6.00 3.26 19.56
AYUDANTE DE ALBAIL 1.00 3.30 3.30
ALBAIL 1.00 3.30 3.30
INSPECTOR DE OBRA 1.00 3.66 3.66
SUBTOTAL N
MATERIALES
DESCRIPCION UNIDAD CANTIDAD A
Cemento ROCAFUERTE KG 0.50
arena negra M3 0.05
adoquin gris 300 KG/CM2 M2 1.05
SUBTOTAL O
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD A
SUBTOTAL P
TOTAL COSTOS DIRECTOS X=(M+N+O+P)
INDIRECTOS Y UTILIDAD
OTROS COSTOS INDIRECTOS
FECHA COSTO TOTAL DEL RUBRO
VALOR OFERTADO
HOJA 001 DE 1
PRECIOS UNITARIOS
UNIDAD:
COSTO
HORA C=A*B RENDIMIENTO R
D=C*R
0.2684
0.2684
COSTO
HORA C=A*B RENDIMIENTO R
D=C*R
OQUINADO
19.56 0.1800 3.5208
3.30 0.1800 0.5940
3.30 0.1800 0.5940
3.66 0.1800 0.6588
5.3676
COSTO
TIDAD A PRECIO UNIT. B
C=A*B
0.50 0.14 0.0700
0.05 12.50 0.6250
1.05 12.95 8.5100
9.2050
COSTO
TIDAD A TARIFA B
C=A*B
0.0000
14.9200
30.00% %X 4.4760
%X 0.0000
19.3960
19.40
FIRMA
OFERENTE
SIEMPRE CON 4 DECIMALES
PUCE
AREA DE CONSTRUCCIONES
OBRA:
RUBRO:
DETALLE: BORDILLO
EQUIPOS
DESCRIPCION CANTIDAD A TARIFA B COSTO HORA C=A*B
HERRAMIENTA MANUAL
CONCRETERA DE 1 SACO A GASOLINA
SUBTOTAL M
MANO DE OBRA
DESCRIPCION JORNAL/HR
CANTIDAD A COSTO HORA C=A*B
(CATEG.) B
SUBTOTAL N
MATERIALES
DESCRIPCION UNIDAD CANTIDAD A
CEMENTO KG 24.50
ARENA NEGRA M3 0.06
RIPIO M3 0.08
CLAVOS 2,4 KG 0.08
- U 0.15
- U 0.44
- U 0.44
- U 0.37
ACEITE QUEMADO GL 0.08
AGUA M3 0.03
SUBTOTAL O
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD A
SUBTOTAL P
TOTAL COSTOS DIRECTOS X=(M+N+O+P)
INDIRECTOS Y UTILIDAD
OTROS COSTOS INDIRECTOS
FECHA COSTO TOTAL DEL RUBRO
VALOR OFERTADO
HOJA 001 DE 1
PRECIOS UNITARIOS
UNIDAD:
COSTO
HORA C=A*B RENDIMIENTO R
D=C*R
0.3636
0.3636
COSTO
HORA C=A*B RENDIMIENTO R
D=C*R
7.2723
COSTO
TIDAD A PRECIO UNIT. B
C=A*B
24.50 0.14 3.4300
0.06 12.50 0.7125
0.08 0.0000
0.08 0.0000
0.15 0.0000
0.44 0.0000
0.44 0.0000
0.37 0.0000
0.08 0.0000
0.03 0.0000
4.1425
COSTO
TIDAD A TARIFA B
C=A*B
0.0000
18.4300
30.00% %X 5.5290
%X 0.0000
23.9590
23.96
TIEMPO EN MESES
RUBRO UNIDAD CANTIDAD PU PT MES 1
ADOQUINADO M2 2864 14.92 42730.88 954.67
14243.63
BORDILLO M2 716 18.43 13195.88 238.67
4398.63
TOTAL= 55926.76
INVERSION PARCIAL
AVANCE PARCIAL
INVERSION ACUMULADO
AVANCE ACUMULADO
MPO EN MESES
MES 2 MES 3
954.67 954.67
14243.63 14243.63 PRECIO
238.67 238.67
4398.63 4398.63 PRECIO
TOTAL= 55926.76
515.52 64.44
250.6 31.325
PU Total Ptotal
19.40 55561.6
23.96 17155.36
72716.96
RUBRO UNIDAD CANTIDAD PU PT
ADOQUINADO M2 2864 14.92 42730.88
BORDILLO M 716 18.43 13195.88
TOTAL= 55926.76
COSTO HORARIO =
HORA HOMBRE =
COEFICIENTE =
COEF CORREGIDOS =
TOTAL HH
6217.098
19.984
6237.082
ADOQUIN MATERIAL PETREO
TOTAL PU PT PU PT
15370.5152 8.51 24372.64 0.63 1790
5204.8188 0.00 0 1.99 1424.84
6217.098
20595.318
MAQUINARIA Y EQUIPO COMP NO PRINC
PU PT PU PT TOTAL
0.00 0 0.43 1231.52 42764.6752
1.87 1338.92 7.30 5226.8 13195.3788
Coeficientes valores
Mano de Obra B p1 0.368
Adoquin C p2 0.436
Material Petreo D p3 0.057
Maquinaria y equipo E p4 0.024
Componentes no Principales X px 0.115
Suma 1.000
1 Costo propoiedad
3 Costo Operacin
(M.O, Combustible, lubricantes, filtros, piezas
de desgaste, neumaticos o tren de rodaje)
4 Costo de reparacin
+ ( 0.368 B1 + 0.436
B0
COSTO HORARIO
Maquinaria
STO HORARIO
% (depende de quien hace el analisis)
Suma 1
Salarios
Coeficiente
Indices para MO mayo. 2016
E.O. E2 (PEON) 0.616 3.26
E.O. D2 (A & AY) 0.286 3.3
E.O. B3 (I) 0.095 3.66
MEL 0.003 3.35
TOTAL 1.000
Suma 1
B B1 + C C1
B0 C0
Relacion indie a
coeficiente
Indice base Indice a la fecha la fecha/indice
reajustado
base
Mayo. 2016 Enero. 2017
3.311 3.463 1.046 0.385
250.66 268.94 1.073 0.467
446.6 449.38 1.006 0.058
192.46 187.54 0.974 0.023
104.59 104.94 1.003 0.116