For
Installation of uPVC Drainage
System
(Wet areas-Office building)
Date
Description
05-03-16
Prepare
d
AJ
Checke Approv
d
ed
YH
AA
Purpose
a)
a)
3
a)
QA/QC personnel main task is to ensure the quality of work and materials
delivered to site as per specifications, drawings, manufacturers
recommendations, site instructions and latest applicable local and
international standards.
b)
The project engineer-in-charge is responsible for carrying out detailed
engineering and manpower planning within the scope of contract,
preparation, review of shop drawings and materials take-off leading to
the procurement as per approval by the consultant.
c)
Site engineer is responsible for daily site work coordination and briefs
supervisors daily tasks to be undertaken.
d)
Safety officer ensures and enforce appropriate measures to protect,
prevent and provide safety to both lives and properties on site.
e)
Storekeeper shall inspect materials delivered for any damage and/ or
discrepancy before advising QA/ QC for inspection.
He shall be responsible for proper storage of the materials received on
site.
4
b)
a)
b)
c)
Check all pipes and fittings for damage before any installation.
Safety Precautions
a)
b)
Always wear PPE for personal safety and protection within project site.
c)
Always wear proper eye goggles and dust mask while undertaking
concrete drilling works.
Work Procedure
For below ground pipes:
a)
b)
c)
d)
Level the trenches as per required levels and must be free from stone
and other foreign materials.
e)
Lay the pipes as per the invert levels and slope shown in the approved
shop drawing and according to the position of sanitary fixtures.
f)
Clean all inside portion of all fittings and pipes to be connected by PVC
cleaner before joining and apply enough amount of PVC cement to each
joint.
g)
Back fill the trench with approved materials leaving open the pipe joints
and prepare for leak test.
Leak test procedure:
a)
All horizontal pipes shall be tested after installation by filling up the pipes
with water up to 1.5 meters head after plugging all openings. The whole
piping will be observed for 2 hours for leakage. If any leakage is found in
pipes or fittings, the same will be removed and repaired immediately.
b)
e)
For this project, the only above ground portion is the vertical vent pipe to
the roof and the fixation to sanitary fixtures.
b)
This portion can be included in the leak test as described in the below
ground pipes.