Documentos de Académico
Documentos de Profesional
Documentos de Cultura
TOMAS
Editors: Tricia Lacuesta
Lorenzo Luigi Gayya
Cristopher Reyes
Macky Siazon
Janine Arenas
Ninna Bonsol
Lloyd Javier
ALTERNATIV
E DISPUTE
RESOLUTIO
N
Recent Jurisprudence
Table of Contents
Republic Act No. 9285
Doctrine of Separability 6
E.O. No. 1008
1 | Page
2 | Page
3 | Page
4 | Page
5 | Page
6 | Page
Doctrine of Separability
JORGE GONZALES and PANEL OF ARBITRATORS v. CLIMAX MINING LTD.,
CLIMAX-ARIMCO MINING CORP., and AUSTRALASIAN PHILIPPINES MINING
INC.
G.R. No. 161957 January 22, 2007, Tinga, J.
The doctrine of separability or severability enunciates that an arbitration
agreement is independent of the main contract. The arbitration agreement is to be
treated as a separate agreement and the arbitration agreement does not
automatically terminate when the contract of which it is part comes to an end.
Facts:
Two petitions arose from one addendum contract entered into by the parties.
In one, the Court held that the DENR Panel of Arbitrators has no jurisdiction over the
complaint for the annulment of the said contract as it should have been brought to
the regular courts. The petitioner claims that the DENR Panel had jurisdiction as the
case involves a mining dispute. Climax claims that it should not be brought for
arbitration under RA 876 on the ground that the arbitration clause in the Addenum
Contract should be treated mutually exclusive from the other terms of the contract
and a claimed rescission of the main contract does not avoid the duty to arbitrate.
Issue:
Whether arbitration is the proper recourse.
Ruling:
Yes. The Court held that R.A. No. 876 explicitly confines the court's authority
only to the determination of whether or not there is an agreement in writing
providing for arbitration. In the affirmative, the statute ordains that the court shall
issue an order "summarily directing the parties to proceed with the arbitration in
accordance with the terms thereof." If the court, upon the other hand, finds that no
such agreement exists, "the proceeding shall be dismissed."
7 | Page
8 | Page
9 | Page
10 | P a g e
Spouses Rune and Lea Stroem (Spouses Stroem) entered into a contract with
Asis-Leif & Company, Inc. (Asis-Leif) whereby the later undertook to build a house for
Spouses Stroem. The contract includes a performance bond issued by Stronghold
Insurance Company, Inc. (Stronghold) securing the obligation thereby binding itself
solidarily liable with Asis-Leif in case the later failed to perform its obligation. Due to
the failure of Asis-Leif to finish the project despite demands, Spouses Stroem
rescinded the agreement. Later, Spouses Stroem filed a complaint for breach of
contract and for sum of money with a claim for damages against Asis-Leif, Ms.
Cynthia Asis-Leif, and Stronghold.
The RTC rendered a judgment in favor of the Spouses Stroem and ordered
Stronghold to pay the spouses. Both parties appeal to the CA which affirmed the
decision of the RTC with modification as to the amount of attorneys fees. Hence this
petition. Before the SC, Stronghold contends that RTC never acquired jurisdiction of
the case in view of the arbitration clause in the agreement and the lower court
should have ordered the parties to proceed with the arbitration.
Issues:
2. Whether the CIAC has exclusive jurisdiction over the controversy between
the parties.
Ruling:
1. Yes. When a dispute arises from a construction contract, the CIAC has
exclusive and original jurisdiction. Construction has been defined as referring to "all
on-site works on buildings or altering structures, from land clearance through
completion including excavation, erection and assembly and installation of
components and equipment." In this case, there is no dispute as to whether the
11 | P a g e
2. Yes. A performance bond, which is meant "to guarantee the supply of labor,
materials, tools, equipment, and necessary supervision to complete the project," is
significantly and substantially connected to the construction contract and, therefore,
falls under the jurisdiction of the CIAC. Although not the construction contract itself,
the performance bond is deemed as an associate of the main construction contract
that it cannot be separated or severed from its principal. The Performance Bond is
significantly and substantially connected to the construction contract that there can
be no doubt it is the CIAC, under Section 4 of EO No. 1008, which has jurisdiction over
any dispute arising from or connected with it.
12 | P a g e
13 | P a g e
14 | P a g e