Model Review Matrix

Required by
Review Stage

30% Review

60% Review

90% Review

Process Studies

Complete

-----

-----

PFD & Mass Balance

IFE

IFC

-----

P&IDs

IFA

IFE

IFC

HAZOP

-----

Complete

-----

Line Sizing

Critical Lines Complete

Complete

-----

Line Designation
Table (LDT)

IFA

IFE

IFC

Piping Specifications

Approved

-----

-----

Valves

Preliminary data for NPS 6


and above

Approved data for NPS 4


and above.

Certified data for all NPS


sizes.

Specialty Items

Preliminary data for NPS 6


and above

Approved data for NPS 4


and above.

Certified data for all NPS


sizes.

Equipment

Preliminary

Approved

Certified

Instruments

Preliminary

Approved

Certified

Plot Plan

IFA

IFE

IFC

Piping Specifications

Calc wall complete

-----

-----

Equipment Layout

Major equipment modeled


to preliminary information.

Equipment locations
finalized and modeled to
approved information.

Equipment modeled to
certified information.

Piping Stress Analysis

NPS 6 and above critical


lines stressed. Other lines
under review.

All NPS critical lines


stressed. Other lines under
review.

NPS 4 and above lines


stressed. Other lines under
review.

Piping Design

NPS 6 and above lines are


modeled and submitted to
stress. (See Note 1.)

NPS 4 and above lines


modeled and submitted to
stress.

All NPS line sizes modeled


and submitted to stress. Field
welds and hydrotest vents
and drains modeled.

Supports

All major temporary steel


modeled.

All temporary steel


modeled.

-----

Tracing Manifolds/
Utility Stations/ Eye
Wash/ Safety Showers

Not Started.

Preliminary locations
modeled.

Firm locations modeled.

Process Design

Vendor Info.

Piping Design

Model Review Matrix (Contd)


Required by
Review Stage

30% Review

60% Review

90% Review

Escape routes, roads,


paved areas and drainage.

30% model review


comments.

60% model review


comments.

Maintainability, e.g.,
davits, monorails and
cranage, access between
equipment, width and
height requirements under
racks.

Maintainability. Pay
particular attention to
removal clearances, e.g.,
exchanger bundle
removals, O/H cranes
above split casings, etc.

-----

Operability, e.g., platform


access.

Operability, e.g., valve


heights, chain operators
and rising stem
requirements.

-----

Constructability, e.g., road


access, crane reaches.

Constructability, e.g., field


erected piping, module
installation.

Field weld and hydrotest vent


and drain locations.

Future piperack
requirements, e.g., widths,
number of levels.

-----

-----

Main structures.

Minor structures.

Fireproofing of structures.

Preliminary identification
of platforms, ladders,
walkways and staircases.

Platforms, ladders,
walkways and staircases.
Davits, monorails and
cranage.

-----

Routing of NPS 6 and above


critical lines.

Routing of all NPS critical


lines and other lines as
required.

Routing of all NPS line sizes


as required.

Pump piping.

Pump piping.

-----

Modularization vs. field


erected piping.

Sample Points identified

Tracing Manifold locations.

-----

Utility Station locations.

-----

-----

Eye Wash and Safety


Shower locations.

-----

Inline instruments and


piping configurations.

Inline instruments and


piping configurations, and
vessel mounted
instruments (if available).

Minor instrument locations,


e.g., PI and TI, and vessel
mounted instruments.

Review Objectives

Ground Rules
1. The cut-off point of NPS 6 and above is a judgment call. Some areas, racks for instance, may require that NPS 2 and above be
modeled at this stage.
2. All model review comments are to be addressed immediately following the model review.
3. No changes to approved or frozen items are allowed without Project Engineering approval.
4. The following guidelines have been established for initiating a change. Personal preference is not an acceptable reason:
- Design does not meet the design criteria.
- Design does not meet accepted design practice.
- Design does not meet plant operating standards or client standards for operability, maintainability, fire protection, safe
isolation of equipment, or safety requirements.
- Design does not meet "What-if" review recommendations.