Documentos de Académico
Documentos de Profesional
Documentos de Cultura
crossmark
A R T I C L E I N F O
A BS T RAC T
Keywords:
Power system operations
Intermittent renewable energy
Dispatch optimization
Investment decisions
Ancillary services
Generation investments, especially large-scale variable renewable energy, requires careful scrutiny of the state
of the power system. Power system planning and operations in a developing country like Bangladesh can often
achieve signicant improvements in economics and security of supply, through modest and prudent
investments. A review of the Bangladesh power sector is presented in this paper that highlights: (a) changes
to dispatch protocols to undertake fuel-constrained dispatch optimization and ancillary services co-optimization
and pricing; (b) issues related to the allocation of natural gas between sectors; and (c) a technology neutral
investment framework. The study uses an hourly dispatch and ancillary services co-optimization model that also
optimizes short to medium term investment decisions. The results demonstrate Bangladesh can: (a) reduce its
production costs by 63% through more ecient dispatch; (b) reduce production costs by 77% by using an
additional natural gas quota of 212 mmcfd (or a 23% increase); and (c) should have invested in power import
and baseload gas/coal rather than expensive solar PV projects (proposed in 2011 at substantially higher cost at
the time). When a carbon price is imposed in the model, the implied break even cost to justify the solar program
is very high in excess of $150/tonne.
1. Introduction
Developing countries face a set of planning and operational
challenges that are often very dierent from those in OECD nations.
Solutions to these challenges may require going back to basics, or
making incremental changes at modest cost rather than sweeping
changes in technology requiring large investments. A careful scrutiny of
power system operations and investment requirements is needed
before adopting large-scale variable renewable generation. If, for
instance, the power system is reliant on a manual dispatch and
frequency control - exposing it to very high frequency uctuations
and out-of-merit dispatch of expensive power stations adding
signicant grid-connected solar and/or wind may expose the system
to additional system instability. It is important that careful planning
precedes the introduction of renewables in the system so that it yields
the maximum benets. A case study for Bangladesh conducted as part
of this analysis highlights some of these issues where the 11 GW power
system is completely reliant on a manual dispatch and frequency
control system. System frequency routinely varies by more than 1 Hz
Correspondence to: The World Bank, 1818H St NW, Washington DC, United States.
E-mail address: dchattopadhyay6@gmail.com (D. Chattopadhyay).
http://dx.doi.org/10.1016/j.rser.2016.10.016
Received 12 October 2015; Received in revised form 11 July 2016; Accepted 14 October 2016
1364-0321/ 2016 Elsevier Ltd. All rights reserved.
T. Nikolakakis et al.
T. Nikolakakis et al.
energy supply forecasts, e.g., wind and solar forecasts in day-ahead and
in real-time; (b) exibility of the non-renewable supply as well as
demand response; and (c) pricing mechanism to pay for exibility.
References [2830] for instance discuss signicant enhancements on
both fronts in theoretical modelling as well as their implementation in
real-life markets. These issues are important even in capacity surplus
systems because exibility cannot be assumed to be automatically
available, and in fact may come at a signicant opportunity cost
[30,36]. There are in fact signicant challenges faced in systems where
the penetration increased rapidly as was the case in Germany [37],
South Australia [38], Spain [39], Ireland [40], etc. However, these
issues are critically important in systems where the demand-supply
balance, even without variable renewables, has been tight as is the case
in most developing countries. Any variability in renewable energy can
have a profound impact on supply and hence prices as the case study
for India [27] amply demonstrates. Spinning reserve in such decient
systems can come at a very signicant premium an issue that must be
examined carefully.
The analytical model employed for this study combines fuel
constrained economic dispatch [19] with co-optimization of ancillary
services [1923] together with a consideration of intermittent generation resources [27]. An extension of the model to include capacity
expansion decisions is also implemented. Capturing the interaction
among these components is important to prioritize operation and
investment decisions, especially in a heavily fuel and capacity constrained system like Bangladesh as has been demonstrated through a
case study. The issue of high opportunity cost of spinning reserve in
Bangladesh is also examined in this analysis.
T. Nikolakakis et al.
Indices.
g
r
t
Input Parameters.
Cost of generation (Taka/MW h).
Cg,
CAPg,
De-rated capacity (MW).
ACng
Annualized capex of new gen. (Taka/MW/year).
Dt
Duration of time period (hour or half-hour).
HRg,
Heat rate (average) in MMBTU/MW h.
Demandr,t Hourly/half-hourly demand for region r (MW).
GasLimit Gas limit in mmcf.
SRMAXg, Max spinning reserve in 6 s (MW).
SolarAvt, Solar resource availability in t (MW).
VoLL
Value of lost load (Taka/MW h).
Variables
NCapng New generation capacity (MW).
Pg,t
Dispatch or power output (MW).
SRg,t
Spinning reserve (MW) from subset of generators SR(g).
Fr, ,r,t
Flows across regions (MW).
Sg,t
Gas consumed by ST and CCGTs (mmcf).
Ur,t
Unserved MW in region r.
1. Considered the spinning reserve to just one class namely the most
restrictive 6 s reserve;
2. Assumed a 45 slope for both joint ramping (Eq. (6)) and joint
capacity (Eq. (5))constraints, which is somewhat relaxed condition
at least for some units that may be more ramp constrained;
3. Used enablement point (i.e., level of P where the unit is allowed to
provide any SR) of zero;
4. Used SRMax values from similar units in other countries. SRMax is
restricted to zero for the two coal units and some of the older units
that are unlikely to be able to provide reserve;
5. Assumed a system wide spinning reserve requirement (Eq. (7))
although considering the weak transmission system there may well
be a local spinning reserve requirement in East and West regions of
the country.
Z=
g,t
Pg, t . Cg. Dt +
r,t
Ur , t . Dt . VoLL
(1)
g {ST , CCGT}, t
(2)
(3)
SRg, t SRMAXg
(4)
Pg, t + SR g, t Capg
(5)
SRg, t Pg, t
(6)
SRg, t SRReqt
g SRg
(7)
653
T. Nikolakakis et al.
Z=
g, t
r,t
Ur , t . Dt .VoLL
(8)
Relevant operational constraints for coal, ST, CCGT also apply for
new generating units. Solar generation from PV plants in addition also
need to follow the resource availability, namely,
Psolar , tSolarAvt
(9)
654
Hourly dispatch and availability data for 2014 was obtained from
the NLDC [1].
A 3 node representation is used - East and West Bangladesh and an
HVDC interconnection from India on the West at Bheramara [6,7].
Simplied ancillary services model as discussed before with two coal
units and older ST units disabled from providing any fast reserve.
In 2014, the average gas allocation was around 919 mmcfd which
has been used a constraint, although the analysis also explored
expanded gas availability scenarios to show the benets of additional
gas.
There is no spinning reserve standard for Bangladesh at the
moment. Covering the maximum ow on the HVDC interconnection
which the single biggest source of supply (467 MW) would require
6.3% of spinning reserve at peak. This is relatively high/expensive
and therefore the analysis also considers lower standards starting
with 2.5% or 185 MW of fast spinning reserve.
Solar availability on an hourly basis is available from NASA which is
analyzed through NREL's SAM model [41]. Fig. 3 shows the average
DNI for the month which shows quite poor availability averaging
T. Nikolakakis et al.
Table 1
Comparison of generation level and cost for 2014.
Category of generation
Acual
Optimal
Taka/kW h
GWh
m Taka
GWh
m Taka
< 1 Taka/kW h
15 Taka/kW h
510 Taka/kW h
1020 Taka/kW h
> 20 Taka/kW h
TOTAL
Average generation cost (Taka/
kW h)
19,818
15,154
5323
4598
863
45,757
15,697
25,418
50,882
68,914
21,338
182,249
3.98
32,272
13,485
45,757
25,616
18,515
44,131
0.96
3.3 kW h/sqm/day for six months from MayOct (for Avg series).
The 20 year minimum variability is much worse taking it down to
2.4 kW h/sqm/day for May-Oct. This obviously raises a signicant
question on the value of 500 MW of solar capacity in the country
that for 6 months which include the peak demand (summer) months
would yield in the worst case less than 10% capacity factor. Although
inclusion of DHI which is relevant for solar PV projects would
improve eective energy yield, capacity factors of actual solar PV
installations in West Bengal with similar solar prole are crosschecked. It conrmed very close match of capacity factors also in the
range of 1516% that result for the average irradiance data in
Fig. 3.1
One of the issues that is often cited in the Bangladesh power sector
since 2011 is the reduced availability of gas overall and, in particular,
for power generation. The daily gas production in 2014 was
2800 mmcfd of which only 919 mmcfd was allocated for power
generation, excluding around 300 mmcfd for captive power generation
[42].
The gas consumption corresponding to the Optimal scenario is
1161 mmcfd compared to 919 mmcfd consumed for the Actual dispatch. Given the massive reduction in cost, the gas allocation policy,
especially allocating for gas for inecient usage including small captive
power stations ahead of larger ecient generators, should be revisited.
In order to understand the relative impact of dispatch eciency and
gas supply constraints, two cases are created using two intermediate
Constrained Optimal scenarios restricting the total gas supply to 919
and 1000 mmcfd (Fig. 5). With gas limited to 919 mmcfd, i.e., at the
5. Discussion of results
5.1. Comparison of actual and optimal dispatch
The Actual dispatch for 2014 is compared with the Optimal
dispatch estimated using the model (1)(3), i.e., ignoring any spinning
reserve and investment issues as well as gas constraints. Total system
cost is Tk 182 billion (USD 2.2 billion) in Actual compared to Taka 44
billion (USD 0.55 billion) in the Optimal, showing a staggering
potential to reduce costs by Taka 138 billion (or USD 1.65 billion)
i.e., by 76%.
1
Detailed data for the solar projects is available in a study conducted jointly by CEA
and MNRE. The demonstration plant data for solar in 20102011 is available online:
http://mnre.gov.in/le-manager/UserFiles/Grid_Solar_Demo_Performance.pdf. The
sole solar PV plant in Jamuria, Asansol, West Bengal. It has in fact historically yielded
less than 13%. CEA had undertaken a detailed study of all big cities in India (available on
www.cea.nic.in Kolkata was reported to have an average capacity factor of 15.5%).
655
T. Nikolakakis et al.
Fig. 6. Spinning reserve prices for dierent reserve targets (Taka/kW h).
evening peak for the 5% reserve scenario. It is evident that the system
needs some form of investment to provide fast reserve. Considering the
increase in cost with higher reserve requirement, almost any form of
new investment including new OCGT or even a pump-storage project
will prove economic. That said, there are cheaper alternatives such as
interruptible load and demand response that should be explored.
A major part of the existing gas generation assets are ageing and as
such the maximum generation potential has been capped to 43 TW h,
allowing for some expansion of gas production from Chevron in 2015/
16. All scenarios assume a 4% spinning reserve requirement.
5.4. Investment analysis
In order to assess investment opportunities in the short to medium
term over the next 3 years, a new scenario is constructed with 20%
higher demand (i.e., 55 TW h pa) and a 4% spinning reserve requirement with new investment options including coal, CCGT, OCGT and
the solar program. Each of these options has been limited to 500 MW
essentially the next set of big investments that might eventuate in the
country.
Table 3 sets out key cost, gas consumption and capacity addition
outcomes for a select set of scenarios. These scenarios in essence posit
(a) two alternative gas availability regimes including the current state
of limited gas availability around ~919 mmcfd as previously estimated
for 2014, and a maximum 1131 mmcfd (or 43 TW h) scenario; and (b)
solar 500 MW program (at $2200/kW in 2014 for Bangladesh) xed
versus an optimized capacity mix.
Table 2
Comparison of generation level and cost for 2014.
No spin
3%a
4%
5%
44360
0
0
44362
1.4
158
0.001
45043
89.2
210
0.343
48052
405
263
1.479
656
T. Nikolakakis et al.
Table 3
Comparison of investment scenarios.
Scenario
System cost
(bill. Taka)
Gas (mmcfd)
New capacity
(MW)
150.7
919
130.7
919
103.2
1131
92.6
1131
Solar 500,
Import 500
OCGT 50
Coal 500
Import 500
Solar 500,
Import 470
OCGT 15
Import 500,
Coal 100
if solar is not included into the mix, that can bring down the annual
cost to Taka 130.7 billion even under a gas constrained scenario
(Scenario 2), i.e., a cost reduction of Taka 20 billion or USD 250
million pa. It will take a CO2 price in excess of USD 80 per tonne for the
solar option to break even with the coal plant. Even if one were to
assume the solar program would cost only half as much with a
reduction in solar panels and eliminating some of the o-grid
components, the break-even CO2 price of $40/tonne would still be
deemed high in the current carbon market regime. The solar scenario
also requires 50 MW of OCGT capacity to be brought in to provide
additional spinning reserve that is needed an issue that has been
explained further later in this section;.
5.4.2. Comparison of scenarios 3 and 4
An increased availability of gas implies far less oil/diesel based
generation and hence much lower overall cost for both scenarios.
Hence, the dierence of system cost between with and without solar
scenarios is also lower because lower capacity factor of solar does not
translate into higher diesel/oil based generation. Higher availability of
gas also lowers the requirement for spinning reserve down to 15 MW.
Nevertheless, the dierence in system cost is still very signicant at
Taka 10.6 billion pa (or USD 135 million pa). The optimized capacity
scenario (4) requires far less coal compared to gas constrained scenario
(2). As such, the implied break even cost of carbon is very high in
excess of $150/tonne. Again this suggests adding a carbon price even
the High carbon price path promulgated in the recent World Bank
Guideline [43] will not support addition of the solar program. This
conclusion holds even if the cost of the program falls to a quarter of the
original estimate in this instance.
6. Concluding remarks
The planning and operational requirements for power systems in
developing countries have not always benetted from structured
analyses, especially when it comes to soft measures. Modern technologies have often been thrust onto these systems at considerable
expense without readying the system and related institutions and
markets. We nd that there are often simple, incremental changes to
operational/planning practices that may yield substantial benets that
may go unnoticed for many years.
Bangladesh power system operation and planning practices highlight these issues. Bangladesh has limited generation capacity and even
more limited domestic natural gas supply. The dispatch protocols are
manual resulting in unnecessarily relying on very expensive fuel oil and
diesel based generators. A comparison of actual and optimal hourly
657
T. Nikolakakis et al.
658