Documentos de Académico
Documentos de Profesional
Documentos de Cultura
I. INTRODUCTION
Manuscript received November 05, 2013; revised February 04, 2014; accepted March 16, 2014. Date of publication April 11, 2014; date of current version January 21, 2015. Paper no. TPWRD-001259-2013.
The authors are with ABB Power Transformer Plant, St. Louis, MO 63120
USA (e-mail: ramsis.girgis@us.abb.com; mats.s.bernesjo@us.abb.com).
Color versions of one or more of the figures in this paper are available online
at http://ieeexplore.ieee.org.
Digital Object Identifier 10.1109/TPWRD.2014.2313295
AND
TAP
0885-8977 2014 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission.
See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
GIRGIS AND BERNESJ: CONTRIBUTIONS TO DIFFERENCES BETWEEN ON-SITE AND FACTORY-MEASURED NOISE LEVELS OF POWER TRANSFORMERS
TABLE I
ON-SITE VERSUS FACTORY MEASUREMENTS, dB (A)
the transformer tested 3.2 dB greater than the factory measurement. For this transformer design, the 2.5% overexcitation corresponds to a 2.6 dB increase in core noise level. In other words,
the transformer would have measured 63.3 dB (A) (65.9 2.6)
on-site if it were operating on the rated voltage of the transformer. This level is within 0.6 dB of the factory measurement.
The second transformer is a 336 MVA, 230
2.5% 69
16
0.625% 13.8 kV autotransformer. The user reported
much higher noise and vibration levels on-site compared
to other transformers of the same design that are located in
other substations. In order to investigate the perceived higher
noise levels, on-site noise measurements were performed. The
measured core noise level on-site was 3 dB higher than that
measured in the factory [80.4 versus 77.4 dB (A)]. At the
time of the on-site noise measurement, this transformer was
fed from the power grid at 238.6 kV while the de-energized
HV winding tap changer and the onload tap changer (OLTC)
of the transformer were set at tap positions that caused 3.7%
higher core excitation when compared to the core excitation
during the factory tests. For this transformer design, the 3.7%
overexcitation corresponds to 4.7 dB. In other words, the
transformer on-site would have measured 75.7 dB (A) (80.4
4.7) if it was operating at the same level of core excitation as
at the factory. This level is 1.7 dB the factory measurement.
This 1.7 dB difference can be attributed to the fact that factory
noise-level measurements using the sound pressure measuring
method, according to IEEE Standard C57.12.90 Section 13 [3],
are inflated by sound reflections from walls of the test area.
For this size of transformers, using the corresponding equation
in [4], the wall sound reflection error is estimated to be in the
range of 1.52 dB.
III. CONTRIBUTION OF THE LOAD
In the factory, no load and load noise are measured separately
at rated voltage and rated current; respectively. The two sound
power levels are added to predict the total noise level of the
transformer. However, this assumes that the vibrations and the
resulting sound power are independent.
First, under actual operating conditions, the transformer is
generally loaded to a certain percent of its rated power. Load
noise, corresponding to the load on the transformer, adds to the
no load noise of the transformer. The impact of load noise on the
total noise of the transformer at the site depends on the percent
load and the relative magnitudes of no load and load noise for
the design. Load noise increases significantly with load; therefore, its contribution to the total noise of the transformer is only
significant for large power transformers and low no-load noise
transformers when highly loaded [6].
An indirect impact of the transformer load on its total noise
level is the impact of load on core noise. Depending upon the
83
power factor of the load and the direction of the power flow, the
magnetic flux density in portions of the core may be lower or
higher than the rated flux density. This is caused by the superposition of stray flux returning from the windings to the main flux
in the core. The result may be a higher or lower core noise level;
which would cause the transformer noise level on-site to differ
from that measured in the factory. As an example, in a step-up
transformer, inductive loading on the outermost winding results
in an increase of the flux density in the core while capacitive
loading results in a lower flux density.
This situation was experienced when on-site noise measurements were made on a 150 MVA, 138 16 0.625% 47.3 14.1
kV transformer that was loaded at about 50% of its rated power.
At 100% voltage and rated tap position, the total transformer
noise measured 2.6 dB lower than the core noise level measured
in the factory. In this example, because of the low load on the
transformer, the contribution of load noise to the total noise of
the transformer was negligible. Therefore, the 2.6 dB was determined to be partially attributed to the lower than rated total
flux density in the transformer core yokes under load. The other
part of this difference was due to the generic error caused by
wall sound reflections in the noise measurements made in the
factory using the sound pressure measuring method.
In addition, the internal voltage drop in the transformer windings is proportional to load current which, in turn, can result in
higher or lower than rated core excitation depending on the tap
changing settings of the transformer; which, in turn, causes a
variation in the transformer noise level. In the transformer example before, the tap changing setting was such that the load
did not affect core excitation to any appreciable amount.
IV. CONTRIBUTION FROM NOISE OF AUXILIARY
TRANSFORMERS AND REACTORS
A significant number of power transformers; especially in
North America, are equipped with a preventive autotransformer
(PA); that allows the manufacturer to design a power transformer with additional means of regulating the L.V. winding
under load. The PA consists of a gapped core reactor which provides the current limiting impedance for reactance type On Load
Tap Changers. The core is excited only when the tap changer is
set at the odd positions (referred to as the bridging positions).
Under these conditions, the core of the PA is commonly excited
and the amount of the excitation depends on the tap changer position. The PA is part of the transformer design and is located
in the transformer oil compartment as an auxiliary device. However, in Factory Acceptance Tests, transformer core noise is typically measured at 100% voltage and with the OLTC at its nominal tap; in which the PA core is not excited. However, when the
transformer is operating on-site, the tap changer could very well
be set at a bridging position which would energize the PA and
generate additional noise.
Being small in size, the Sound Power level of a PA is typically
very small compared to the Sound Power level of the main transformer. Therefore, the noise level of the transformer is typically
not impacted by the noise of the PA. However, if for design, material, or construction reasons, the noise level of the PA is excessive, the noise level of the transformer operating at a bridging
84
TABLE II
ON-SITE TRANSFORMER NOISE MEASUREMENT AT BRIDGING
NONBRIDGING TAP POSITIONS, dB (A)
VERSUS
higher loads and is a function of the size, design, and construction of the reactor. In these circumstances, the measured noise
level on-site may deviate from the level reported during the final
factory acceptance tests.
V. CONTRIBUTION FROM VIBRATIONS OF STRUCTURES
ATTACHED TO THE TRANSFORMER
External mechanical structures are often solidly attached to
Power Transformers; especially generator step up transformers.
The vibrations of the transformer tank are transmitted mechanically to these structures causing them to vibrate excessively in
some cases when the frequency of the vibrations coincide with,
or is in a close vicinity of, the mechanical resonance frequency
of the structure. The noise generated by these vibrations adds to
the total noise level of the transformer when measured on-site.
A very good example of this situation is a 110 MVA,
230 8 1.25% 34.5 kV wind-farm transformer that measured 11.9 dB higher noise level on-site compared to what
was measured in the factory. Investigations performed to
determine the contributors to this difference, together with
detailed noise and vibration measurements using the Sound
Intensity measuring method, showed that 3.2 dB was due to a
2.7% core overexcitation. Another 1.5 to 2 dB was caused by
sound buildup around the transformer due to sound reflections
from adjacent fire walls (as will be explained in Section VI of
this paper). The remaining 5 to 6 dB was found to be caused
by excessive vibrations of the metallic structure covering the
bus duct connecting the LV bushings of the transformer to the
generator.
Fig. 2 below presents both factory and on-site noise-level
measurements around the transformer. The much higher noise
levels measured on-site correspond to measuring positions 16 to
25; with the highest difference noted at stations 20 to 22 which
are located just below the bus-duct. This is further confirmed by
on-site noise measurements around the transformer using both
the sound intensity and sound pressure measuring methods, [7],
[8]. These measurements are presented in Fig. 3 below for the
400 Hz 1/3-Octave frequency component.
Fig. 3 clearly indicates that the significantly higher noise
levels measured using the Sound Pressure method at stations
17 to 21 are due to noise external to the transformer. This
frequency component was found to be the main contributor to
this difference. This indicates that the excessive vibrations of
the bus-duct structure were caused by mechanical resonance
GIRGIS AND BERNESJ: CONTRIBUTIONS TO DIFFERENCES BETWEEN ON-SITE AND FACTORY-MEASURED NOISE LEVELS OF POWER TRANSFORMERS
85
Fig. 3. On-site noise measurements of the 400 Hz 1/3-Octave frequency component of the transformer noise.
This is a very common contributor to higher noise levels measured on-site versus. factory. In the example described in Section II of this paper, two 70 MVA transformers were located in
close proximity of each other with a fire wall in between. One
transformer was several dB noisier than the other.
Detailed on-site measurements; using both the sound intensity and sound pressure methods, showed that the higher noise
transformer contributed 1.5 to 2 dB to the noise measurements
of the lower noise transformer. Conversely, the lower noise
transformer contributed only about 0.5 dB to the noise measurements of the higher noise transformer.
In another substation; where three large single-phase power
transformers were located in close vicinity of each other with
only fire walls in between, it was found that the other two transformers contributed about 1.5 dB to the measured noise level
of the third transformer when measurements are made using the
sound pressure measuring method.
B. Contribution of Ambient Noise
One of the common contributors to the on-site noise-level
measurement using the Sound Pressure measuring method is
ambient noise and other sources of noise in the area. An example to demonstrate this effect is a case where measurements
were made on two different sites, one with minimal ambient
noise and one with higher ambient noise. The noise levels of the
transformers in these sites were measured at 2 m distance from
the transformers using both the Sound Pressure and Sound Intensity measuring methods. The measurements were made outside the near-field area around the transformer so that the difference between the readings obtained with the two sound measuring methods is a measure of the contribution of only the ambient noise to noise-level measurements using the Sound Pressure measuring method.
Table III below presents a summary of these measurements
for the main frequency components of the transformer noise.
The table shows practically no contribution of ambient noise for
the transformer located in the low ambient area. Conversely, the
contribution of the ambient noise is 3.3 dB in the higher ambient
86
TABLE III
DIFFERENCE BETWEEN MEASUREMENTS USING THE SOUND PRESSURE AND
SOUND INTENSITY MEASURING METHODS AT TWO DIFFERENT LOCATIONS
TABLE IV
ON-SITE VERSUS FACTORY NOISE-LEVEL MEASUREMENTS
low core noise transformer. Upon reviewing the factory measurements and examining possible mechanical resonances, the
factory measured noise levels were found to be within 12 dB
of the calculated noise level of the transformer. Extensive investigations, and analysis of the on-site noise levels concluded
that this large difference is not caused by anything wrong
with the transformer. Having the highest difference between
factory and on-site noise levels at the 500 Hz octave indicated
a significant increase in the core excitation level. At the time,
possible dc current flowing into the neutral of the transformer
was suspected to be the cause of this excessive noise level. This
was based on the signature of the transformer noise on-site.
Subsequent to this conclusion, the user measured the dc current
at the neutral of the transformer bank. The measurements
showed that approximately 0.751 A dc was present. When
calculations were made of the increase of the noise level of
the different frequency components of core noise of this transformer due to this level of dc, it was confirmed that this level of
dc produces an increase of the core noise of this design almost
identical to the magnitude of the on-site measured increase in
the noise level as shown in Table IV above.
IX. CONTRIBUTION OF MOUNTING
During factory acceptance testing, transformers are typically
mounted on a structural support consisting of an air cushion
platform, wooden blocks, metallic frame, etc. Neither IEC
nor IEEE describes how the transformer should be mounted
during the noise test. On-site, power transformers are typically
mounted on a concrete pad or on a metallic structure; which
is different than the way the transformer is mounted during
the factory testing. Extensive investigations performed by
the authors of this paper showed that some of the individual
frequency components of core and load noise are significantly
affected by how the transformer is mounted. The lower the
frequency, the higher the impact [9]. The impact on the total
noise level of the transformer in dB (A) is typically low for
core noise.
An excellent example of this effect is a 336 MVA, 230
16 0.625% 69/13.1 kV autotransformer. This transformer was
tested for core noise in the factory and the measurements were
compared with the on-site measurements when it was lightly
loaded and fans not running. Table V presents a summary of
these measurements.
The table shows that, other than the 125 Hz component, the
on-site measurements are very close to those measured in the
factory. The 125 Hz component, however, tested 9.6 dB higher
than the corresponding factory measurement. Based on extensive measurements on effect of mounting on transformer noise,
GIRGIS AND BERNESJ: CONTRIBUTIONS TO DIFFERENCES BETWEEN ON-SITE AND FACTORY-MEASURED NOISE LEVELS OF POWER TRANSFORMERS
TABLE V
ON-SITE VERSUS FACTORY NOISE MEASUREMENTS
87
this 9.6 dB difference in the 125 Hz component between factory and on-site is attributed to the difference in mounting of
the transformer.
X. CONTRIBUTIONS OF OTHER FACTORS
Factors, other than those presented in Sections IIIX above,
may contribute to differences between transformer noise levels
measured on-site and those measured at the factory acceptance
tests. Below are some of these factors:
A. Operating Temperature of the Transformer
Comprehensive measurements have shown that, for some
core materials and certain operating conditions, higher core
temperatures cause the core noise level of transformers to be
higher than that measured at no-load conditions in the factory.
Also, higher winding and structural parts temperatures under
load affect the clamping stresses on the windings and, therefore, can affect the part of the transformer load noise caused
by axial winding vibrations. At this time, limited measurements
were performed by the authors to quantify the noise increase
caused by this factor. More details on the impact of the operating temperature on both core and load noise are planned to be
presented in a future paper.
B. Current and Voltage Harmonics
During factory acceptance testing, Industry Standards require
voltage and current to be sinusoidal. The presence of current
and/or voltage harmonics on-site would increase the total noise
level of the transformer. This contribution is typically very small
as limits are typically maintained on the harmonic distortion
of the bus voltage. In cases where harmonic currents are injected in windings of transformers and reactors by power electronic devices, load noise increases. This increase is typically
significant in applications where current harmonics are of high
magnitudes. In those cases, the effect on the overall noise level
of the transformer in dB (A) can be significant as higher frequency components of the transformer noise are attenuated less
by A-weighting.
C. Remanent Core Magnetization
Remanent flux has a similar effect on the core noise level to
that produced by dc currents. During factory testing, great care
is taken to ensure that the remanent flux originating from impulse testing (mainly switching impulse), or resistance measurements, is dissipated prior to performing the transformer noise
tests.
88
[3] IEEE Standard Test Code for Liquid Immersed Distribution, Power,
and regulating Transformers, IEEE C57.12.90-2010, 2010.
[4] Power transformersPart 10: Determination of Sound Levels, IEC
60076-10:2001.
[5] R. Girgis and M. Bernesj, Appropriate test conditions proposed for
industry standards of measuring transformer noise, presented at the
IEEE Power Energy Soc. Conf., Minneapolis, MN, USA, Jul. 28, 2010.
[6] R. Girgis, M. Bernesj, and J. Anger, Comprehensive analysis of load
noise of power transformers, presented at the IEEE Power Energy Soc.
Conf., Calgary, AB, Canada, Jul. 2009.
[7] R. Girgis, K. Garner, M. Bernesj, and J. Anger, Measuring no-load
and load noise of power transformers using the sound pressure and
sound intensity methodsPart I: Outdoors measurements, presented
at the IEEE Power Energy Soc. Conf., Pittsburgh, PA, USA, Jul. 2008.
[8] R. Girgis, K. Garner, M. Bernesj, J. Anger, and D. Chu, Measuring
no-load and load noise of power transformers using the sound pressure and sound intensity methodsPart II: Indoors measurements,
presented at the IEEE Power Energy Soc. Conf., Pittsburgh, PA, USA,
Jul. 2008.
[9] R. Girgis, M. Bernesj, S. Thomas, J. Anger, D. Chu, and H. Moore,
Development of ultra-low transformer noise technology, IEEE
Trans. Power Del., vol. 26, no. 1, pp. 228234, Jan. 2011.
R. Girgis (LF11) received the Ph.D. degree
in electrical engineering from the University of
Saskatchewan, Saskatoon, SK, Canada, in 1978.
He has more than 45 years of R&D experience in
the area of power, distribution, and high frequency
transformers, rotating machines, and pulse power
components. He has published and presented more
than 70 scientific papers in IEEE, IEE, CIGRE,
and other international journals. He co-authored
chapters in two electrical engineering handbooks on
Transformer Design and Transformer Noise.
Dr. Girgis is the chairman of the IEEE Transformers Standards Task Force
revising the IEEE Noise Measuring Standards C57.12.90, section 13. He is the
past Technical Advisor representing the U.S. National Committee in the IEC
Technical Committee 14. He is presently the Research and Development manger
at the Power Transformer Division, ABB, St. Louis, MO,. USA. He is also the
leader of the global ABB R&D activities in the area of transformer core performance and Co-Leader of the global ABB R&D activities in the transformer
noise area.