Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Gantt Verificación Gas - v2
Gantt Verificación Gas - v2
Task Name
Finish
Predecessors
Resource
Names
September
11/09
04/09
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
9 days
NA Tue 20/09/16
E. Torres
2 days
NA
Fri 09/09/16
3 days
NA Wed 14/09/16 7
E. Torres
E. Torres
2 days
NA
Fri 16/09/16 8
NA Mon 19/09/16 9
1 day
3 days
NA Wed 21/09/16
2 days
NA Tue 20/09/16
1 day
25/09
02/10
09/10
16/10
IESA
E. Torres
IESA
E. Torres
E. Torres
E. Torres
E. Torres
E. Torres
E. Torres
1 day
16 days
PERIODO DE REVISN Y ENTREGA DE
DOCUMENTOS
Tiempo de revisin por la Norma Mexicana 15 days
1 day
Entrega de documentos a SKF
IESA
IESA
E. Torres
IESA
October
18/09
E. Torres
IESA
IESA
IESA
Autoridad
IESA
Autoridad
Task
Project Summary
Inactive Milestone
Progress
Split
External Tasks
Inactive Summary
Manual Summary
Deadline
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 1
23/10