Documentos de Académico
Documentos de Profesional
Documentos de Cultura
www.criticalpoint.co.uk
Intellectual Property
This document is the Intellectual Property of
Critical Point Ltd
This document is supplied for the personal use
of the recipient and is not to be copied, edited,
transmitted or broadcast in part or in whole
without the prior permission of Critical Point
Ltd.
www.criticalpoint.co.uk
Below Specification
Below Quality
www.criticalpoint.co.uk
+ Below Specification
+ Below Quality
www.criticalpoint.co.uk
Often Low
Excessive Wastage
Slow Progress
Costly
www.criticalpoint.co.uk
Business Impact:
Product Expensive
Late to Market
Customer Dissatisfaction
Reputation
Project Failure & Slow Costly Projects Cripples Business
www.criticalpoint.co.uk
Below Specification
Below Quality
www.criticalpoint.co.uk
Until now
www.criticalpoint.co.uk
90%+ on time
www.criticalpoint.co.uk
10
www.criticalpoint.co.uk
What is CCPM?
A transportable set of interlinked techniques and
11
www.criticalpoint.co.uk
What is CCPM?
A transportable set of interlinked techniques and
www.criticalpoint.co.uk
What is CCPM?
A transportable set of interlinked techniques and
www.criticalpoint.co.uk
What is CCPM?
A transportable set of interlinked techniques and
www.criticalpoint.co.uk
What is CCPM?
A transportable set of interlinked techniques and
www.criticalpoint.co.uk
What is CCPM?
A transportable set of interlinked techniques and
www.criticalpoint.co.uk
What is CCPM?
A transportable set of interlinked techniques and
Any Sector
17
Task-Level
Contingency
Poor Measures
& Control
Critical Path
Multi-tasking
18
www.criticalpoint.co.uk
Deadline
Schedule
Task-Level
Contingency
Poor Measures
& Control
Critical Path
Multi-tasking
19
www.criticalpoint.co.uk
09/09
22/09 23/09
1/10
13/10
Planned Completion
13/09
1/09
09/09 10/09
10/09
22/09
14/09 15/09
14/09 15/09
23/09
22/09 23/09
20/09 21/09
03/10
04/10
30/09 1/10
09/10
13/10
15/10
www.criticalpoint.co.uk
www.criticalpoint.co.uk
Deadline
Date
Task
Missed
Time-Saving
22
www.criticalpoint.co.uk
Planned
5 days
Early Finish
Gain Lost
7 days
3d
3d
5 days
5 days
5 days
5 days
2 days added
to schedule
5 days
No benefit
to schedule
www.criticalpoint.co.uk
www.criticalpoint.co.uk
Summary
Dates attempt a rigid structure on a variable situation
25
www.criticalpoint.co.uk
CCPM
Schedule
Task-Level
Contingency
Poor Measures
& Control
Critical Path
Multi-tasking
26
www.criticalpoint.co.uk
09/09
22/09 23/09
13/09
1/09
09/09 10/09
10/09
22/09
14/09 15/09
14/09 15/09
23/09
22/09 23/09
20/09 21/09
1/10
03/10
www.criticalpoint.co.uk
13/10
04/10
30/09 1/10
09/10
13/10
15/10
CCPM Schedule
09/09
13/09
1/09
19/10
30/12
10/09
www.criticalpoint.co.uk
CCPM Schedule
Potential
Early Finish
Deadline
Date
Task
29
www.criticalpoint.co.uk
CCPM Schedule
Potential
Early Finish
Deadline
Date
Task
www.criticalpoint.co.uk
CCPM Schedule
Potential
Early Finish
Task
www.criticalpoint.co.uk
CCPM Schedule
Actual
Early Finish
Task
32
www.criticalpoint.co.uk
CCPM Schedule
www.criticalpoint.co.uk
CCPM Schedule
www.criticalpoint.co.uk
CCPM Schedule
Summary
Very few internal due dates
Work carried out on an as soon as possible basis
A Relay Race (not a Train Schedule)
Early finishes reduce timescales & cost
Flexible structure for a variable environment
Few due dates means few / no schedule updates
CCPM values speed over working to fixed dates
35
www.criticalpoint.co.uk
CCPM
Schedule
Task-Level
Contingency
Poor Measures
& Control
Critical Path
Multi-tasking
36
www.criticalpoint.co.uk
www.criticalpoint.co.uk
Task-Level Contingency
Confidence in own ability
How Much
Contingency?
Known Unknowns
Specification Stability
Easy Life
Fear of Failure
Estimate chopping
Confidence in Spec.
Unknown Unknowns
37
www.criticalpoint.co.uk
Task-Level Contingency
Confidence in own ability
Interruptions
Easy Life
A Guess
Fear of Failure
Multi-tasking
Known Unknowns
Specification Stability
Estimate chopping
Confidence in Spec.
Unknown Unknowns
38
Task-Level Contingency
Effect 1- An Extended Schedule
www.criticalpoint.co.uk
Task-Level Contingency
Effect 2 Student Syndrome
Scheduled
Start
Deadline
Date
Work
Contingency
Actual
Start
www.criticalpoint.co.uk
Task-Level Contingency
Effect 2 Student Syndrome
Scheduled
Start
Deadline
Date
Work
Actual
Start
Contingency decreased
41
www.criticalpoint.co.uk
Task-Level Contingency
Effect 2 Student Syndrome
Scheduled
Start
Deadline
Date
Work
Other
work
Big
Problem
www.criticalpoint.co.uk
Task-Level Contingency
Effect 2 Student Syndrome
Scheduled
Start
Deadline
Date
Work
Other
work
Big
Problem
www.criticalpoint.co.uk
Task-Level Contingency
Effect 3 Unprotected Project End-Date
Planned Completion
Delayed Completion
www.criticalpoint.co.uk
Task-Level Contingency
Effect 4- Unmanaged Time
45
www.criticalpoint.co.uk
Task-Level Contingency
Effect 4 Unmanaged Time
www.criticalpoint.co.uk
www.criticalpoint.co.uk
CCPM
Schedule
Task-Level
Contingency
Poor Measures
& Control
Critical Path
Multi-tasking
48
www.criticalpoint.co.uk
CCPM
Schedule
Project-Level
Contingency
Poor Measures
& Control
Critical Path
Multi-tasking
49
www.criticalpoint.co.uk
50
www.criticalpoint.co.uk
www.criticalpoint.co.uk
www.criticalpoint.co.uk
www.criticalpoint.co.uk
Project Buffer
www.criticalpoint.co.uk
Project Buffer
www.criticalpoint.co.uk
Buffer
Status
Project Buffer
www.criticalpoint.co.uk
Buffer
Status
Project Buffer
www.criticalpoint.co.uk
www.criticalpoint.co.uk
CCPM
Schedule
Project-Level
Contingency
Poor Measures
& Control
Critical Path
Multi-tasking
59
www.criticalpoint.co.uk
Task A
Task B
Task F
Task G
Task H
Task I
Task C
Task D
Task J
www.criticalpoint.co.uk
Task A
Task B
Task F
Task G
Task H
Task I
Task C
Task D
Task J
61
www.criticalpoint.co.uk
Task E
Task A
Task B
Task H
Task I
Task C
Task D
Task G
Task J
www.criticalpoint.co.uk
Task B
Task D
Task J
www.criticalpoint.co.uk
Task B
Task D
Task J
www.criticalpoint.co.uk
Task B
Task D
Task J
www.criticalpoint.co.uk
Scope Cut
Scope Cut
Task A
Task B
Scope Cut
Task H
Task D
Task J
www.criticalpoint.co.uk
67
www.criticalpoint.co.uk
CCPM
Schedule
Project-Level
Contingency
Poor Measures
& Control
Critical Path
Multi-tasking
68
www.criticalpoint.co.uk
CCPM
Schedule
Project-Level
Contingency
Poor Measures
& Control
Critical Chain
Multi-tasking
69
www.criticalpoint.co.uk
Task A
Task B
Task F
Task G
Task H
Task I
Task C
Task D
Task J
www.criticalpoint.co.uk
Task H
Task A
Task G
Task F
Task B
Task I
Task C
Task D
Task J
www.criticalpoint.co.uk
Task H
Task A
Task G
Task F
Task B
Task I
Task C
Task D
Task J
www.criticalpoint.co.uk
Task H
Task A
Task G
Task F
Task B
Task E
Task I
Task C
Task F
Critical Chain
Task D
Task J
Task G
Critical Path
Task H
Task A
Task B
Task C
Task I
Task D
Task J
www.criticalpoint.co.uk
Task A
Task B
Task E
Task F
Task G
Task H
Task I
Task C
Task F
Task D
Critical Chain
Task J
Task G
Critical Path
Task H
Task A
Task B
Task C
Task I
Task D
Task J
www.criticalpoint.co.uk
75
www.criticalpoint.co.uk
CCPM
Schedule
Project-Level
Contingency
Poor Measures
& Control
Critical Chain
Multi-tasking
76
www.criticalpoint.co.uk
With Multi-tasking:
3d
3d
Task 2: 9 days
Task 3: 9 days
Day 9
3d
27 Days
Day 24
3d
3d
3d
3d
3d
3d
31 Days
www.criticalpoint.co.uk
Summary
www.criticalpoint.co.uk
CCPM
Schedule
Project-Level
Contingency
Poor Measures
& Control
Critical Chain
Single-tasking
79
www.criticalpoint.co.uk
80
www.criticalpoint.co.uk
Task 2: 9 days
Task 3: 9 days
27 Days
www.criticalpoint.co.uk
Good Multi-Tasking
Non-Project / background, no dependencies or deadlines.
Training/education. QA tasks. Flexi-time.
Bad Multi-Tasking
Double-booked on overlapping tasks.
Covering Additional / Support roles.
Ugly Multi-Tasking
Personnel allocated simultaneous project tasks.
Endemic, cultural.
82
www.criticalpoint.co.uk
Summary
It improves quality
83
www.criticalpoint.co.uk
CCPM
Schedule
Project-Level
Contingency
Poor Measures
& Control
Critical Chain
Single-tasking
Multi-tasking
84
www.criticalpoint.co.uk
85
www.criticalpoint.co.uk
www.criticalpoint.co.uk
www.criticalpoint.co.uk
Summary
88
www.criticalpoint.co.uk
CCPM
Schedule
Project-Level
Contingency
Good Measures
Visible Control
Critical Chain
Single-tasking
Multi-tasking
89
www.criticalpoint.co.uk
90
www.criticalpoint.co.uk
E
B
91
www.criticalpoint.co.uk
+3
B
C
+3
92
www.criticalpoint.co.uk
Buffer
Remaining
+3 +3
A
+3
B
C
+3
www.criticalpoint.co.uk
Buffer
Remaining
+3 +3 +5
A
+3
B
D
+5
+3
Early Report
www.criticalpoint.co.uk
95
www.criticalpoint.co.uk
96
www.criticalpoint.co.uk
97
www.criticalpoint.co.uk
98
www.criticalpoint.co.uk
www.criticalpoint.co.uk
Project-Level
Contingency
Good Measures
Visible Control
Critical Chain
Single-tasking
Multi-tasking
Yes but not just these; CCPM fixes a bigger problem and the
reason that past improvements have not succeeded
100
www.criticalpoint.co.uk
Vicious
Circles
101
www.criticalpoint.co.uk
Task-Level
Contingency
Poor Measures
& Control
Deadline
Schedule
Critical Path
Multi-tasking
www.criticalpoint.co.uk
Schedule
Changes
Poor Measures
& Control
Deadline
Schedule
Critical Path
Schedule
Changes
Schedule
Changes
Multi-tasking
Schedule
Changes
103
www.criticalpoint.co.uk
Schedule
Changes
Poor Measures
& Control
Deadline
Schedule
Critical Path
Schedule
Changes
Schedule
Changes
Multi-tasking
Schedule
Changes
www.criticalpoint.co.uk
Schedule
Changes
Poor Measures
& Control
Deadline
Schedule
Critical Path
Schedule
Changes
Schedule
Changes
Multi-tasking
Schedule
Changes
www.criticalpoint.co.uk
Schedule
Changes
Poor Measures
& Control
Deadline
Schedule
Schedule
Changes
Critical Path
Schedule
Changes
Multi-tasking
Schedule
Changes
106
www.criticalpoint.co.uk
CCPM Solutions
Schedule
Changes
Project-Level
Contingency
Schedule
Changes
Rem. Duration
Visible Control
CCPM
Schedule
Critical Chain
Schedule
Changes
Schedule
Changes
Single-tasking
Schedule
Changes
www.criticalpoint.co.uk
Schedule
Changes
Rem. Duration
Visible Control
CCPM
Schedule
Critical Chain
Schedule
Changes
Schedule
Changes
Single-tasking
Schedule
Changes
www.criticalpoint.co.uk
Project-Level
Contingency
Rem. Duration
Visible Control
CCPM
Schedule
Critical Chain
Single-tasking
www.criticalpoint.co.uk
Traditional Problems:
Deadline Scheduling
Task-Level Contingency
Critical Path
Multi-tasking
Poor Measures & Control
Schedule Volatility
Problem Perpetuation
Poor Work Environment
= Terminal Mediocrity
CCPM Solutions:
Flexible Scheduling
Project-Level Contingency
Critical Chain
Single-tasking
Good Measures & Control
Schedule Stability
Solution Constancy
Good Work Environment
= Progressive Excellence
110
www.criticalpoint.co.uk
Programme
& Portfolio
Myth
Achieving Terminal
Mediocrity on a
Large Scale
111
www.criticalpoint.co.uk
112
www.criticalpoint.co.uk
Overloaded Programme
1. Project Time-Slicing
Project 1: 9mths
Project 2: 9mths
Project3: 9mths
27 mths
mth 9
mth 23
Project Fragmentation:
3mths
3mths
3mths
3mths
3mths
3mths
3mths
3mths
3mths
30 mths
www.criticalpoint.co.uk
Overloaded Programme
1. Project Time-Slicing
Project 1: 9 mths
Project 2: 9mths
Project3: 9mths
27 mths
9 mths
21 mths
3mths
3mths
3mths
3mths
3mths
3mths
3mths
3mths
3mths
30 mths
www.criticalpoint.co.uk
Project 1
Project 2
Project 3
Project 4
Project 5
Project 6
Frequently great pressure to start more projects Often ignoring the realities of resource capacity
115
Overloaded Programme
2. Simultaneous Projects
www.criticalpoint.co.uk
Exterior View
Overloaded Programme
2. Simultaneous Projects
Reality at Working Level
Project 1
Project 2
Project 3
Project 4
Project 5
Project 6
www.criticalpoint.co.uk
Exterior View
Overloaded Programme
Reality at Working Level
Project 1
Project 2
Project 3
Project 4
Project 5
Project 6
www.criticalpoint.co.uk
Exterior View
Overloaded Programme
Reality at Working Level
Project 1
Project 2
Project 3
Project 4
Project 5
Project 6
www.criticalpoint.co.uk
Overloaded Programme
Exterior View
Project 1
Project 2
Project 3
. . . .?
. . . .?
. .?
Project 4
. .?
Project 5
Project 6
. .?
www.criticalpoint.co.uk
Summary
Delays
Loss of Completion Predictability
120
Critical
Consulting
Point Consulting
Critical Point
www.criticalpoint.co.uk
www.criticalpoint.co.uk
Overloaded Programme
Exterior View
Project 1
Project 2
Project 3
. . . .?
. . . .?
. .?
Project 4
Project 5
Project 6
. .?
. . .?
www.criticalpoint.co.uk
Overloaded Programme
Exterior View
Project 1
Project 2
Project 3
. . . .?
. . . .?
. .?
Project 4
Project 5
Project 6
. .?
. . .?
www.criticalpoint.co.uk
124
www.criticalpoint.co.uk
www.criticalpoint.co.uk
Solution:
Start new projects only when capacity allows
126
www.criticalpoint.co.uk
Solution Summary:
Prioritise !
Stagger project starts to avoid major contention
127
www.criticalpoint.co.uk
Project A
Project B
Priority 5
Project C
Priority 3
Project D
Priority 2
Priority 1
Project E
Project F
Priority 6
128
www.criticalpoint.co.uk
Priority 1
Project 1
Project 2
Priority 2
Project 3
Priority 3
Project 4
Priority 4
Project 5
Project 6
Priority 5
Priority 6
129
www.criticalpoint.co.uk
Project 1
Project 2
Project 3
Project 4
?=
Project 5
Project 6
130
www.criticalpoint.co.uk
Project 1
Project 2
Project 3
Project 4
?=
Project 5
Project 6
131
www.criticalpoint.co.uk
Project 1
Project 2
Project 3
Project 4
Project 5
Project 6
132
www.criticalpoint.co.uk
KR
KR
KR
KR
KR
KR
133
www.criticalpoint.co.uk
KR
KR
KR
KR
www.criticalpoint.co.uk
KR
KR
KR
KR
KR
KR
135
www.criticalpoint.co.uk
KR
KR
KR
KR
136
www.criticalpoint.co.uk
www.criticalpoint.co.uk
137
80%
Proj C
70%
Proj A
60%
50%
40%
30%
Proj E
Proj B
20%
Proj F
10%
0%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
www.criticalpoint.co.uk
The Evidence
for CCPM
139
www.criticalpoint.co.uk
High Tech /
Medtronic, Inc.
Microsoft
Motorola
Numonyx
Philips Semiconductors
Pioneer
Qualcomm
RSA Security
SanDisk
Sapient
Seagate Technology LLC
Sony Ericsson
Spirent Communications
Sprint
Sun Microsystems
Symbian
Tadiran Spectralink
Tektronix
TT Technologies
Tundra Semiconductor
Workscape
Xerox Corporation
Business Education
Ashridge Management College
Project Management Institute
London Business School
+ Over 160 Universities
Life Sciences
Abbott Labs
Adirondack Surgery
AHIS-St. Vincent Health
AMGEN
Andover Healthcare Inc.
Arterain Medical
Baxter
Boston Scientific
Central Dupage Health
Bovis Pharmaceuticals
Converge Medical Inc.
Cytori Therapeutics, Inc.
Edwards Lifescience
Ethicon
Gambro Healthcare
GlaxoSmithKline
Johnson & Johnson
Medtronic
Merck Medco Managed Care
Pfizer
Pharmacia
Roche Diagnostics
Spectranetics
Tenet Health Care
Tyco Healthcare
United Behavioral Health
Vascore Medical
140
Ventana
www.criticalpoint.co.uk
Industrial
ABB
Accoat
Advanced Energy Technology
Alcan
Alfa Lava
American Rubber Products
Applied Plasmonics
AREVA
Atomic Energy of Canada .
Balfour Beatty
Bimba Manufacturing
Bosal
Bosch Rexroth Ltda.
Brice Manufacturing
BVR Technologies Company
C.F. Roark Welding.
Callaway Golf
Celite Corporation s
Conoco
Corning Cable Systems
Cueros Industrializados
DaimlerChrysler UK
Danfoss
Delta Faucet Company
Detroit Diesel Reman-West
DuPont
Eastman Kodak Company
Industrial/
ExxonMobil Chemical
Fisher Controls
Fluid Brasil Sistemas
Fluke Corporation
Fuel Cell Energy
GE Industrial Systems
Hach
Honda
ITT Corporation
Kawasaki Heavy Industries,
M&M Precision Systems
Marshall Industries
Merichem Chemicals
Milwaukee Forge
Rail care
Raychem
Rolls Royce
Siemens
Sylvania
Unilever
Tata
UPC Technology
Volvo
www.criticalpoint.co.uk
www.criticalpoint.co.uk
Results:
Japanese Government
After having used it in 2,523 public works projects in 2007
and over 4,000 projects in 2008, the Japanese government
now requires that CCPM be used on all public works
projects (approximately 20,000 projects per year).
142
www.criticalpoint.co.uk
Professional Recognition
www.criticalpoint.co.uk
Professional Recognition
Conference Presentation
Critical Chain Project Management using Microsoft Project and Prochain:
Implementing Project Portfolio Management.
1985
1990
1995
2000
2005
2010
145
www.criticalpoint.co.uk
www.criticalpoint.co.uk
Last Word
Critical Chain Project Management presents us with an opportunity to plan
projects well for maybe the very first time. We should make sure that we
break with our old traditions of how we have done things in the past, and replan our projects from scratch.
But planning is only half the story. The real power of CCPM comes from the
control afforded during the execution or deployment of the job. Buffer status
and buffer management allows us unprecedented feedback on the progress
of the project and where to focus attention and where not.
And maybe this is the most important factor in the whole approach.
We have a totally new and systemic way to manage projects. We should
make the very most of this opportunity.
147
www.criticalpoint.co.uk
148
www.criticalpoint.co.uk