Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Process Optimization
Prepared by
LinnhoffMarch, lnc.
9800 Richmond Avenue, Suite 560
Houston, TX 77042
May 1995
REPORT SUMMARY
PINCH TECHNOLOGY/PROCESS OPTIMIZATION
Volume 7: Case Study - A Wax Extraction Plant
A wax extraction plant case study demonstrates how process
integration or pinch technology can identify practical and costeffective ways to substantially reduce energy costs. Suggested costsaving measures include steam and power system improvements,
yield improvement, reduction of NOx emissions and optimum heat
exchanger network design. Low capital cost projects were
identified to improve wax yield by 8%, increase refrigeration
capacity by 10%and reduce steam usage by 22%.
Industrial
Demand-side Planning
KEYWORDS
Pinch technology
Heat recovery
Energy efficiency
Heat pumps
End use
Industry
PROJECTS
RP3879-4
EPRI Project Manager: K. R. Amarnath
Customer Systems Division
Contractor: Linnhoff March, Inc
For further information on EPRI research programs, call EPRI
Technical Information Specialists (415) 855-2411.
.\r
Prepared by
Linnhoff March, Inc.
9800 Richmond Avenue, Suite 560
Houston, TX 77042
Prepared for
Electric Power Research Institute
3412 Hillview Avenue
Palo Alto, CA 94304
ABSTRACT
industrial manufacturing facilities in the United States are facing increasing competition
in today's global marketplace. In order to protect their industrial manufacturing base,
many electric utility revenues have adopted the strategy of providing technical
assistance to help selected customers improve their competitive position.
Petrowax Corporation produces high grade waxes for use in a variety of commercial
and consumer markets. Petrowax was keen to modernize its facilities in order to
reduce operating costs, increase manufacturing flexibility, and to achieve compliance
with a NO, abatement order at minimum capital cost.
The present study employed the techniques of Pinch Analysis to identify a
comprehensive process improvement strategy that improved wax yield by 8%,
debottlenecked refrigeration capacity by I O % , and reduced total steam demand by
22%. Operating margins are projected to improve by over $1 MM/yr. Furthermore, the
reduced fuel requirement automatically reduced NO, emissions, enabling compliance
with the NO, abatement order without installing expensive end-of-pipe controls.
Past studies undertaken by EPRl in cooperation with member utilities have shown
comparable results over a broad range of industries.
...
Ill
EXECUTIVE SUMMARY
2.
3.
4.
iv
.
.
The potential for steam savings through heat recovery in the PDA plant is
minimal.
A new hydrotreater to replace the existing bauxite filter system would not be
economical, and is not recommended; it would be better t o continue with the
existing system.
The economics of cogeneration at this site are not good, since the cost of fuel
to generate one k w h of power exceeds the sale price of that kwh.
Overall economics for the proposed HEN retrofits are summarized below:
Payback
MEK
I
I
Tank Insulation
Total
4.2
I
I
1.0
2.0
I
I
The predicted savings represent 22% of total site energy costs. The actual
savings will be somewhat higher, if credit is taken for savings in labor,
maintenance, etc. from shutting down t w o boilers.
Accordingly, we suggest that Petrowax pursue a 2-stage revamp strategy.
Staae 1
vi
CONTENTS
Page
Section
iv
introduction .........................................................................................
Background and Objectives .............................................................................
1-1
1-1
1-2
1-2
1-2
1-3
1-4
1.4
....................................................................................
1-5
Deliverables
2
2-1
2-1
Process Description ..........................................................................
CHP System .................................................................................... 2-1
Capital Costs ...................................................................................
3
2-4
Results ................................................................................................
3-1
3-1
3-1
3-4
3-9
3-20
3-22
CONTENTS
Section
viii
Page
Offsites ........................................................................................
Combined Heat and Power System ....................................................
3-23
3-23
.4-1
FIGURES
Figure
Page
3.1
3.2
3.3
2-2
2.3
3-5
3-6
3-7
3.4
3.5
3.6
3.7
3.8
2.1
2.2
3.9
3.1Oa Recommended HEN Retrofit for MEK (Flowsheet) ................................
3.10b Recommended HEN Retrofit for MEK (Flowsheet) ................................
3 . 1 0 ~ Recommended HEN Retrofit for MEK (Flowsheet) ................................
3.11 Simplified Flowsheet of PDA Process .................................................
3-13
3-14
3-15
3-16
3-17
3-18
3-21
IX
TABLES
Table
3.1
3.2
Page
LIST OF ABBREVIATIONS
BPD
BW
Btu
DT
EPRl
GCC
HEN
HMB
HP
HRSG
HVGO
CHP
cw
gpm
IBP
K
KW
KWH
LPW
MEK
MM
MP(S)
MVR
MW
Megawatts
MWH
Megawatt-hours
Million
xi
LIST OF ABBREVIATIONS
NOX
PCI
PDA
Nitrogen Oxides
PCI Engineers Inc, Houston, TX
Propane De-Asphalting
PO
Rf g
Press Oil
Refrigeration (ammonia)
SCFD
SW
TBP
Slack Wax
VDU
VGO
xii
I
INTRODUCTION
This study was begun in April 1994, and completed in July 1994.
b)
c)
1-1
introduction
Consistent with this background, the objectives of the energy study were to
determine the optimum steam and power generation strategy for the Smethport
site under the following scenario:
Modified process - MEK unit debottlenecked, bauxite filters replaced
by hydrotreating, and vacuum distillation unit operated at maximum
yield.
Reduction in process steam demand through heat integration (pinch
analysis), tank insulation, and possible replacement of steam by
electricity in certain applications.
0
The study report should be sufficiently comprehensive and detailed for Petrowax
to make a sound decision on how to proceed forward with the modernization
program.
Scope of Work
Linnhoff March, Inc. was contracted to provide the following services:
A.
Task I
- Data Collection
During this same site visit, LMI was to obtain or develop the following
information to be used as the Design Basis:
1-2
a.
b.
Develop Heat and Material balance models of both the process and
the CHP system using appropriate software tools.
il
lntroduction
c.
Initial estimates of the size and/or overall heat transfer coefficients for
each heat exchanger.
d.
e.
f.
C.
1.
b.
c.
d.
e.
f.
g.
h.
i.
Introduction
1.
2.
D.
1.
2.
3.
E.
Task 5 - Reports
1.
2.
3.
1-4
A.
B.
introduction
Deliverables
1.
2.
3.
Report.
4.
Innovator.
1-5
2
STUDY BASIS
CHP System
The plant Combined Heat and Power (CHP) system is depicted schematically
in Figure 2-2. It consists of 4 steam boilers, all operating at 240 psig:
There are 3 steam headers - 240 psig, 140 psig, and 25 psig. A number of
small backpressure steam turbines are used t o drive process pumps and
2- 1
Y
N
VGO
Crude Oil
Feedstock
I
3
VDU
Side
r
I
Dewaxed Oil
Crude
...
LTu
Vac. Bottoms
treating
(new)
+-
Resin
(asphalt)
Figure 2-1
Process Block Flow Diagram
Deresined oil
Waxes
Study Basis
BFW
Desuperheat
Direct to
Process
J.
240 Ib IT
>
Direct t o
Process
140 Ib
I
Desuperheat
ii
25 Ib - 1
V
Flash
Tank
Direct to
Process
'
Condensate
LOSSES
-=
BFW makeup
Figure 2-2
CHP System Schematic
2-3
>
Study Basis
@ $3.80/Klb
First 25,000Ib/hr
@ S I .80/Klb
This yields an average steam price of $2.81/Klb for the first 60,000 Ib/hr of
savings. No distinction is made between the cost of MP and LP steam, as
the power credit between those t w o levels is quite small and does not affect
any of the conclusions. Cooling costs were taken t o be $0.5O/MMBtu.
Capital Costs
For purposes of pinch analysis, it was assumed that all heat exchangers
would be Shell & Tube carbon steel, for which the installed cost can be
represented as
$ = 10000
The capital cost of gas turbines with HRSGs was taken t o be:
MMS = 0.82
2-4
1.16 (MW)
3
RESULTS
The plant analysis was broken down into several distinct tasks, which will
be described in turn.
Vacuum Distillation Unit
The model was validated by comparing simulation output with several sets
of plant data. Very good agreement was obtained with process flow rates
and compositions, except that we could not get an exact match on the
column temFerature profile.
The results of three significant runs are summarized in Table 3-1.
Case 1:
Case 2:
Case 3:
Case 2 represents the maximum yield increase possible (8.5%) at the given
column pressure conditions while maintaining present product quality
specifications. This benefit is achieved a t the cost of 3.0 MMBtu/h
increased heat input to the base of the column. Since this heat must be
supplied at a high enough temperature to strip off the desirable fraction, one
would have to increase fuel t o the furnace. If the additional duty is supplied
through the furnace, the outlet temperature will be 910OF. It will be
necessary to verify whether this is feasible, both with regard to possible
3-1
'
Results
Table 3-1
Summary of VDU Simulation Results
Case 2
(Increase Reflux &
Stm)
Case 1
(Base)
Case 3
(Column
High vac
I
I
1.547
0
.
8
5
7
1
1.161
3.00
25 1
275
705
439
529
80
205
519
210
1475
1624
1620
61 5
I 127 product
J '
6
2
9
1
641 /79 1
1 (5/95%loF
1 140 product
(5/95%)"F
7 5 7/8 7 5
7 7 2/8 73
77 1/873
844/970
845/970
845/970
'
152 product
(5/95%)OF
93 7/ 1090
160 product
(5/95 %) O F
~
Note:
3-2
Feed rate is the same in all cases; product flow rates have been
scaled t o show relative magnitude only in order t o protect
confidential client information.
'
(b)
(c)
(d)
30
Most lube oil vacuum columns operate at a pressure drop of 20
mm Hg. The actual AP is considerably higher, indicating possible
fouling (coking) or other mechanical pinches in the column, and may
account for some of the discrepancies between simulated and
measured data.
3-3
Results
Current
1,800
Proposed
1,800
I
82
90
324
180
8.6
11.6
2,700
2,700
0.1507
0.1907
1.29
1.29
- VDU
- PDA
11.3
14.3
17.4
9.7
- Combined
28.7
24.0
4.7
- Savings (avg)
In short, the energy cost of 3 MMBtu/hr due t o increasing VDU yield is more
than offset by reduced steam cost in the PDA plant.
Pinch Analysis
3 -4
'
Results
I0
v)
vc
P
T
3-5
'
.,
Results
9
cv
'0
'Eo
9
F
'd
.
r
9
'(v
.9
Eo
.9
W
E3
c\l
I a J
m u
.
I
-
0
0
3-6
In
0
0
d
0
0
cv
I
I
'
Results
m a
I E
m o
IL
9)
M a
3 6
3 -7
Air
Utility
cost
K$/yr
0.48
218
MMBtu/h
cw
LPS
Oil
Existing (base case)
8.60
Target @ D T = 8 0
5.51
7.92
0.48
160
Savings
3.09
-0.96
2.11
58
(27%)
(27%)
-0.96 10.03
n/a
(36%)
As far as energy savings go, the impact on the CHP system is fairly minimal.
It can be seen, though, that through proper process integration, the furnace
can be debottlenecked by 3 MMBtu/h, which is almost exactly the amount
of extra heat required t o obtain a yield increase of 8% (per section 3.1.I).
The VDU process GCC shows clearly that on a stand-alone basis, a large
amount of heat at fairly high temperatures (300-450'F) must be dumped
into cooling water. A t the same time, there are other processes at the site
where steam is being used t o supply fairly low level heat. This suggests
opportunities for inter-unit heat integration.
The most obvious and convenient use for surplus VDU heat is for
wastewater heating, which currently requires 10,000Ib/hr steam. If this is
done, almostthe entire cooling water duty in VDU can be eliminated, and
nearly 9000 Ib/hr of LP steam saved. When cross-unit heat integration is
employed, the combined savings are significantly greater, as follows:
Existing
oil I
8.60
8.37
1
I 10.03 I 0.48 I
cw I
Air
cost
KS/vr
427
MMBtu/h
LPS I
Design
5.55
127
Savings
3.05
8.37
10.03
0.48
300
(35%)
I (70%)
Note that direct process steam consumption has been excluded from the
foregoing cost comparison, as it does not change.
Several retrofit strategies are possible - eg. minimize repiping, maximize
operating flexibility, optimize utilization of existing HX surface, etc. The
3 -8
Results
repiping 4 interchangers
switching 5 coolers from cooling water to wastewater
It should be noted that the recommended retrofit does not involve purchase
of any new equipment, just redeployment of existing equipment.
Furthermore, four of the existing heat exchangers would be rendered
surplus, and become available for use in other services. Capital costs are
difficult t o estimate, since they will involve mainly piping and controls, but
are estimated to be less than $300K, for a I-year payback.
(b)
3-9
Results
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
;
I
I
I
'
00
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
'?I
I
I
I
I
I
---
h
I
I
i- - - I-I
I
I
I
I
I
I
3-10
I
I
I
I
Ri
rrjl
&
I
I
I
I
I
I
I
I
I
I
I
I
I
1
LO
I
I
I
I
I
I
I
1
I
Tu,
I------l
I
I
.rl
I
;
*aJ
l a
Results
Y-
3-1 I
w
c
t3
Dry
Solvent
Tank
I
sw
Stripper
Storage
Figure 3-6
Simplified Flowsheet of De-Oiling Process
LP 196'
Flash
I
slackwax
9
'
HP
Flash
08,Feb,95 11:59
File:MEK422.ST2
350-
300-
250-
W
I
c
0.00E00
1.00E07
Figure 3-7
Composite Curves
2.00E07
MEK
3.00E07
4.00E07
5.00E07
Enthalpy [Btu/hr]
6.00E07
7.00E07
8.0
07
w
I
450-
02,Nov,94 13:32
File:MEK422.ST2
HP steam
400-
350-
LP steam
300-
250-
200-
150-
100-
Cooling water
50Refrigeration
00.0
5.0dE06
Figure 3-8
Grand Composite Curve
1.OdE07
1&E07
Enthalpy [Btulhr]
2.0dE07
2.5dE07
3.O
07
MEK
I
02,Nov.94 17:06
File:MEK42HP1.ST2
Page 111
SUPERTARGETVB3.01 SN1020
73.
E32
37.
E2641.
100.
N2
100.
et Solvent Dilution
H:1166624.0
ry Solvent Chilling
Flash Vapors
P Flash Vapors
H:23M:
150.
E6
ilProduct
8.0
100.
olvent Vapors
14.4
170
lax Product
t-iltrate Heating
.O. Feed
IP Flash Feed
.W. Remelt
eboiler Feed
H:4225603.0
vaporator Feed
:ooling Water
Figure 3-9
Recommended HEN Retrofit for MEK (Grid)
Results
3-16
t '
'
Results
3-17
Results
3-18
' 9
~~~
Results
'
Proposed
- actual
3.97
MMBtu/h
LPS
CW
Rfg
cost
KWyr
3.1
22.8
12.6
988
4.55
2.35
9.4
11.3
536
15.7
0.75
13.4
1.3
452
3.97 20.22
Existing
Savings
MPS
Io
Direct process steam consumption for stripping has been excluded from
utility steam duties.
The recommended retrofit was developed using a "minimum repipe"
philosophy. In other words, existing matches were left intact as much as
possible even if they were not optimally placed. New exchangers were
added, or existing units redeployed, only when absolutely essential to
achieve the desired savings.
The new
E-
26
1 new MVR heat pump
9
3-19
Results
MPS
I
I
I
I
MMBtu/h
LPS
cw
I
I
0
13.7
cost
K$/yr
Rfg
(1.76)
268
2.0
45
45
0.5
11
-2
(0.55)
1.20
27
Process steam duties for MEK, PO and wax stripping remain unchanged.
The difference in energy savings between the heating and cooling duties
(16.44 vs 14.60) is attributed t o the vapor compression work. The MVR
heat pump consumes 686 HP (512 kW) of additional power, which reduces
net operating cost savings by $102,00O/yr from $450,00O/yr to
$348,00O/yr.
Capital costs (installed) are estimated t o be about $1.5 MM, giving an
overall payback of over 4 years. While this does not meet Petrowax's
hurdle rate for new investments, this revamp is critical t o achieving the
strategic objective of reducing NOx emissions by shutting down one or more
of the existing boilers.
3-20
1 7
11,
Results
ti
Y-
3-2 1
The main conclusion for present purposes was that the potential steam
savings in PDA are small compared to total site steam consumption, and
therefore a future HEN retrofit will not impact the design of the CHP system.
Wax Finishing
The existing wax purification process involves bauxite filtration, with total
utility costs estimated to be between $300-350 K/year.
The possibility of replacing this process with a new hydrotreater was
investigated. Two options were considered:
Purchase/build new unit
Retrofit existing mothballed platf ormer
For a wax hydrofinishing rate matched to current operations, capital and
operating costs were obtained from the literature, as follows:
Capital Cost (new):
$2.7- 4.2 M M
Operating Costs
With a payback on expected savings over 10 years, this does not seem
attractive. The second alternative, involving reuse of the existing
platformer, fared no better. According to vendors who specialize in this
technology, it would be impractical t o retrofit the existing platformer
equipment.
Finally, it will be necessary in both cases to build a small hydrogen plant on
site to ensure a secure supply. Assuming a 1 MM SCFD plant capacity, the
capital cost would be about $3 MM. The impact on site utilities would be
minimal.
To summarize, the operating costs for a hydrofinishing process would be
roughly comparable to the existing bauxite filtration process. The minimum
total capital investment required will be about $6.5 MM. Clearly, the
3-22
Net Savings =
lo
14.132
I
I 2.907
I
10.102
I
I $1.123MM/yr
I
I
3-23
'U
Results
$2.2 MM
$2.94 MM/yr
negative
Capital Cost =
Averaae Enerav Cost =
Payback vs Option Zero =
$25.2 MM (installed)
$3.51 MM/w
I negative
ODtion 3: Redace Boilers with GT and Fired HRSG The gas turbine size is
smaller than in Option 2, because fired HRSGs produce relatively more
steam. The power export t o Penelec will be about 6.6 MW. Once again the
economics are unfavorable.
GT Capital Cost =
Average Energy Cost =
Payback vs Option Zero =
$10.8 MM (installed)
$3.77 MM/yr
negative
The three cogeneration options are compared against Option Zero in Table
3-2. None of them showed favorable economics. This is because gas costs
are relatively high at $3.14 per MMBtu, and electrical export credits are low.
A quick calculation makes this abundantly clear. Assuming a heat rate of
10,000 Btu/kwh, the power export credit is 2.1 C/kwh, whereas the cost of
gas is 3.2C/kwh. Under this economic environment, cogeneration cannot
possibly be attractive.
3-24
>
Results
Table 3-2
Comparison of Cogeneration Options
ODtion Number
1
2
#I ,#2
#I ,#2
No
No
1 .I3
21
8.6
none
unfired
unfired
fired
2.2
25.2
10.8
Fuel
2.11
Electricity
0.80
2.91
2.36
0.58
2.94
6.05
12.541
3.51
4.48
(0.711
3.77
nla
-0.03
-0.60
-0.86
GT Size, M W
HRSG Type
Capital Cost, MMS
Energy Cost, MMS/yr
Savings, MMSIyr
3 -25
4- 1
Stage 1
Stage 2
While the stand-alone economics of MEK revamp are not very attractive,
this project is essential in order t o enable shutting down boilers #3 and 4
and achieve low-cost NO, reduction.
4-2
( 1