Está en la página 1de 51

DPR

Sl.No.

Location

Coal mill section

Coal mill section

Crusher Section

Pump house

HT DG

UNITED CEMENTS PVT. LTD.


NAUBISE-4, DHADING, NEPAL

DPR
Manpower Engaged

Description

SAIZ

E&I
Coal mill gas analyzer (KC & PC) air line connectivity through Pu pipe
from FR to scavenging pannel.

Coal mill gas analyzer bag filter outlet air line connectivity through PU
pipe from FR to scavenging pannel.
Limestone crusher started at 10:45 am and stopped at 1:15 pm.
240 sqmm AL power cable dressing work.
for diesel unloading related work.

1E+1K

T. LTD.

EPAL
DATE:26-03-2016
Manpower Engaged
GP BUILDERS

Status

UCPL

Mr. Suryabali
Mr.
Manish
Mr. Mohit

Compeleted

Mr. Suryabali
Mr.
Manish
Mr. Mohit

Compeleted

Mr. Kushwaha
Manish

Mr.

Mr. Kushwaha
Manish

Mr.

Mr. Kushwaha
Mr.
Manish
Mr. Mohit

Under progress
Compeleted

Remarks

DPR
Sl.No.

Location

Hopper feeding area

100BC2

100BC1

HT DG

Coal mill Section

Coal mill Section

Packing plant section

Water pump

Batching plant

10

Coal mill Section

11

CCR Transformer

UNITED CEMENTS PVT. LTD.


NAUBISE-4, DHADING, NEPAL

DPR
Manpower Engaged

Description

SAIZ

E&I
Faulty lights disconneted and removed in the following area2 Nos X 70 Watts lights from
100BC5.
6 Nos X 70 Watts lights from Raw
mill hopper.
these lights kept in CCR cable celler.

Mr. MUKESH

In 100 TR1 its reverse limit switch connection removed as per mech.
Requirment for shifting the limit switch.
Grinding machine connection given as per mech requirment.
Admin. Building power charged from HT DG auxi. Pannel with 4C X
25sqmm Cu cable.
For coal mill gas analyzer pannel earthing 70 mtrs. Cable laid from LC-4
RIO pannel and its cable gland and lugging work compeleted from RIO Mr. Gautam
pannel side.
For coam mill gas analyzer room 3c X 4sqmm cable laid about 80 mtrs.
From LC-4 spare feeder and cable gland , lugging and termination work
Mr. Gautam
compeleted.
Rolling machine connection given as per Mech. Requirement and trial
taken.
control cable dresssing work compeleted.
Batching plant instrument cheking in field and proxy switch, load cell
and limit switch checked.
5 Nos earth pit found by digging the soil with labour.
silica gel heated for obtaining the blue colour.

T. LTD.

EPAL
DATE:18-03-2016
Manpower Engaged
GP BUILDERS

Status

UCPL

Mr. Kushwaha
Munna

Mr.

Mr. Kushwaha
Munna

Mr.

Completed

Completed

Mr. Munna

Completed

Mr.Manish Mr.Sajjad
Mr.Sanjeev

Completed

Mr. Mustkim
Mr.
Mohit Mr.Harendra

Under Progress

Mr. Mustkim
Mr.
Mohit Mr.Harendra

Completed

Mr. Suryabali
Mr.
Vishal
Mr. Vishal
Mr. Faizan

Completed
Completed
Completed

Mr. Faizan

Completed

Mr. Raman

Completed

Remarks

DPR
Sl.No.

Location

Raw mill Section

Limestone Crusher

Limestone Crusher

100 TR1

Raw mill Hopper

Raw mill Hopper

UNITED CEMENTS PVT. LTD.


NAUBISE-4, DHADING, NEPAL

DPR
Manpower Engaged

Description

SAIZ

E&I
RTD cable laid about 35 mtrs for Raw mill outlet duct.Cable gland and
termination work compeleted.RTD fixed and conection done after that
checking from CCR and temp show 24 deg cel.

Mr. Gautam

Limestone crusher group trail taken about 15 minutes.


Limestone crusher started at 2:20 pm and stopped at 3:00pm.
100 TR1 its reverse limit switch connection done after mechnical
Clearence and trail taken by operating the tipper drive.
After mechnical clearence in 300WF2 load cell fixed calibrated the
weigh feeder with empty belt.
Faulty lights removed from raw mill hopper section.

Mr.Mukesh

T. LTD.

EPAL
DATE:19-03-2016
Manpower Engaged
GP BUILDERS

Status

UCPL

Mr. Manish
Mr.
Raman Mr.Munna

Completed

Mr. Manish
Martand

Completed

Mr.

Mr.Manish

Completed

Mr.Kushawaha

Completed

Mr. Raman
Mr.Munna
Mr.Kushawaha

Completed
Under progress

Remarks

DPR
Sl.No.

Location

Limestone Crusher

Limestone Crusher

Pump house

Clincker silo

Clincker silo

Coal mill section

Coal mill section

Kiln

Coal mill section

10
11

UNITED CEMENTS PVT. LTD.


NAUBISE-4, DHADING, NEPAL

DPR
Manpower Engaged

Description

SAIZ

E&I
100TCI its level sensor connection remove as per mech requirement and
level sensor kept at LC-3. Level sensor control cable also removed and
kept at site.
lime stone crusher started with group at 11:40am and stopped at
12:10pm.
200 mm cable tray fixing work for 240sqmm power cable in pump house.
One truck clincker loaded.
2 Nos 150 watts light fixed and connection given from field lighting DB
as per process requirement.
coal mill gas analyzer probe with heater mount in PC firing and KC
firing and Baghouse inlet side mounting work compeleted.
coal mill gas analyzer controller fitting work and wiring work with
service engineer.
For kiln inlet and PC firing gas analyzer pannel UPS supply given from
LC-3 UPS JB with 2c X 6sqmm cable about 70 mtrs.
For coal mill gas analyzer pannel UPS and Non UPS power cable gland
and termination work compeleted in feeder side and charged with 3P 32A
MCB in spare feeder.
Grinding ,welding machine connection given.
light connection given and diesel filling in 80KVA DG.

1K
1E

T. LTD.

EPAL
DATE:20-03-2016
Manpower Engaged
GP BUILDERS

Status

UCPL

Mr.Manish
Vishal

Mr.

Completed

Mr.Manish Mr.Suryabali

Completed

Mr.Suryabali Mr.Vishal

Completed

Mr.Suryabali Mr.Vishal

Completed

Mr.Manish Mr.Suryabali
Mr. Vishal

Completed

Mr. Faizan

Completed

Mr. Faizan

under progress

Mr. Mustkim
Mr.
Raman
Mr. Mohit

Completed

Mr. Mustkim
Raman
Mr. Vishal
Mr. Sajjad

Mr.

Completed

Remarks

DPR
Sl.No.

Location

Coal mill section

Blending Silo

Preheater

Raw mill hopper

Coal mill section

HT DG

Crusher section

Blending Silo

Preheater

UNITED CEMENTS PVT. LTD.


NAUBISE-4, DHADING, NEPAL

DPR
Manpower Engaged

Description

SAIZ

E&I
Coal mill gas analyzer for Kiln , PC and Baghouse outlet DI and AI
address identify in RIO pannel and given to Ajit SIR.
400BE1current transducer replaced with 600FN4 and given in line to
CCR.
400BE2 preheater bucket elevator trail taken for current transducer
checking purpose and transducer is ok.
In raw mill hopper all WF load cell adjustment work done.
Coal mill top bag filter its manometer removed for fixing in raw mill
outlet duct.
LT DG changeover switch there was flashed when operating the switch.
So 380 KVA connection removed from changeover switch and given to
main changeover switch in LT DG pannel.
Crusher section started many times as perprocess requirement.
Blending silo recirculation group started at 11:00 pm and stopped at
9:00am

cable tray work for PC gas analyzer.

T. LTD.

EPAL
DATE:24-03-2016
Manpower Engaged
GP BUILDERS

UCPL

Status

Mr.Suryabali Mr.Mohit

Completed

Mr.Suryabali Mr.Mohit

Completed

Mr.Suryabali Mr.Mohit

Completed

Mr. Faizan

Completed

Mr. Faizan

under progress

Mr.Suryabali Mr.Vishal
Mr. Sajjad

Completed

Mr. Faizan

Completed

Mr.Mustkim Mr.Martand
Mr. Manish
Mr.
Munna

Completed

Mr.Mustkim Mr.Martand
Mr. Manish
Mr.
Munna

Completed

Remarks

DPR
Sl.No.

Location

Coal mill section

Raw mill

Crusher section

Pump house

Gypsum yard

HT DG

Cement mill

Coal mill section

UNITED CEMENTS PVT. LTD.


NAUBISE-4, DHADING, NEPAL

DPR
Manpower Engaged

Description

SAIZ

E&I
Coal mill gas analyzer its DI and AI signal communicate with PLC.

For draft point Manometer fixed and pu pipe with connector also fixed
with pot and point in outlet duct.
Limestone crusher tripped two times due to winding tem high and
bearing tem high. So checked and found rtd wire loose in motor side.
NDE bearing side wire cut from the lug in RTD. After that given to
clearence fir start.
240 sqmm power cable dressing work.
Vibrator connection removed and dol starter removed from site. Vibrator
motor kept in CCR MCC room.
LT DG changeover switch connection work done with 380 KVA and
82.5 KVA DG.
Transformer neutral earthing value checked and value is 1.65 ohm. Body
earhing value 0.015 ohm.
PU pipe and its connector fixed from FRL to scavenging panel.

1E

1E

T. LTD.

EPAL
DATE:25-03-2016
Manpower Engaged
GP BUILDERS

Status

UCPL

Mr.Suryabali Mr.Manish
Mr. Vishal

Completed

Mr. Faizan

Completed

Mr. Vishal

Mr.Suryabali Mr.Faizan
Mr. Manish

Completed

Mr. Harendra

Under progress

Mr. Vishal

Completed

Mr. Faizan
Mr.
Harendra
Mr. Sajjad

Completed

Mr.Manish
Mr.
Suryabali
Mr. Vishal

Completed

Mr. Suryabali
Vishal

Mr.

Under progress

Remarks

UN

DPR
Sl.No.

Location

Coal mill section

Coal mill section

Crusher section

DPC & Cooler section

CSP TOP

PC Analyzer

PC Analyzer

Kiln Analyzer

UNITED CEMENTS PVT. LTD.


NAUBISE-4, DHADING, NEPAL

DPR
Description

E&I
Coal mill feeding group & main drive group trail work done before kiln lightup.

In coal mill 1100RVF12 ZSS controller problem. So change the new ZSS controller also trail from CCR
Lime stone crusher start 4 time as per process requiredments
DPC & cooler group trail work done before kiln lightup.
csp top penumetic gate 3 limit swith broken. So replacement work is underprogress
PC Analyzer for ring heater 3core 1.5 sq.mm 55 mtr cable laid & dressing work done from anlyzer to
probe also gland & termination done ,
for sample gas outlet PU pipe laid panet to out door of analyzer room.

water radiation blower body earthing work done & also gas sample PU pipe is laid from pannel to probe

TS PVT. LTD.

DING, NEPAL
DATE:27-03-2016
SAIZ

Manpower Engaged
GP BUILDERS

Status

UCPL

I
Mr.Mostkim Mr.Manish
Mr. Vishal

Completed

Mr. Manish

Completed

Mr. Mohit

Mr.Suryabali Mr.Martan

Completed

Mr.Suryabali Mr.Vishal

Completed

Mr.Suryabali Mr.Vishal

Under progress

Mr. Mostkim
Mr.
Harendra
Mr. mohit

Completed

Mr.Harendra
mohit
Mr. Suryabali
Vishal

Mr.
Mr.

Completed
Under progress

E:27-03-2016
Remarks

DP
Sl.No.

Location

CSP TOP

Kiln burner

pyrometer

Coal mill

cooler fan

diesel tank

PC Analyzer

kiln firing

kiln roller heat exchanger

10

Coal mill

11

Coal mill

12

Coal mill

13

Coal mill

14

Coal mill

15

PH Cyclone no 4

16

PC Analyzer

17

Coal mill

18

cooler section

19

kiln feed trail

UNITED CEMENTS PVT. LTD.


NAUBISE-4, DHADING, NEPAL

DPR
Description

E&I
CSP Top penumatic gate no 3 limit switch damage . So now limit switch change and taken inline & also all penumatic
gate trail taken from CCR
kiln firing system check before kiln lightup and kiln firing pump 1&2 taken in local by looping 3& 4 terminal in
panel.
pyrometer fixing work done with mechanical team
coal mill inlet & outlet lubrication pressure switch setting change 2.3 kg to 1 kg as per decision taken in daily
progress meeting.
500.BL1 overload triped due to power fluctuation. So checked the panel side and reset

diesel tank pump is not start. So cheked and find neutral missing. So give the proper supply to the diesel tank pump
motor
pc gas analyzer scavening panel to probe PU pipe 4mm. 10 mtr laid

kiln firing start at 2:16Pm


kiln roller heat exchanger pump one phase is missing , so checked find out MCC panel side loose connectin
,connection tightness was done , now ok
coal mill stat at 7:50 pm
coal mill gas analyzer probe cleaning and taken in line
coal mill KC & PC bin filling silide gate open & closed feedback problem , so interchange the PU pipe from FRL.

NIGHT SHIFT
Manish yadav , faizan , Raman , Aman bh
coal mill bagfilter solenoid valve not purging. So checked and find out pressure switch unhealthly due to air line jam,
so after cleaning the air line pressure switch healthly and purging in auto mode
coal mill 1100DC1& 1100DC2 bagfilter level sensor showing high in ccr . So checked and find out RIO pannel side
fuse burn . Now insert the fuse it is ok
cyclone no 4 cone temperature is not showing in ccr. So checked the thermocouple and find cable is open , so now
connection done now showing 129 degree c temp in ccr

pc gas analyzer probe cleaning work done and taken inline


one light is given in coal mill dump hopper as per process dept requiredment
500DPC1 triped in zss fault so checked and its timing adjust
kiln feed trail taken

NTS PVT. LTD.

ADING, NEPAL
DATE:28-03-2016
SAIZ

Manpower Engaged
GP BUILDERS

UCPL

Status

I
Mr.Suryabali Mr.vishal
Mr.Mostkim
Mr.Martand
Mr.Mohit
Mr.Mostkim
Mr.Mohit

Completed
Completed
Completed
Completed

Mr. R.M Kushwaha


Mr. harender

Completed

Mr.manish chaoudhary
Mr.martand

Completed

Mr.manish
chaoudhary Mr.mohit

Completed
Completed

Mr.manish chaoudhary
Mr.harendar

Completed
Completed

Mr.Suryabali
Mr.Mostakim
1

Mr.Mostkim

Completed

Mr.Faizan Mr.raman

Completed

GHT SHIFT
an , Raman , Aman bhai munna

Mr. Manish
Mr.faizan
Mr.Raman Mr.munna

Completed
Completed

Mr.Faizan Mr.manish
Mr.munna

Completed
Completed

Mr.Raman Mr.faizan

Completed

Mr. Manish
Mr.faizan MR.Munna

Completed

DATE:28-03-2016
Remarks

limit switch consumption

10 mtr. 4mm pu pipe consumption

DPR
Sl.No.

Location

Raw mill

Raw mill

PC Analyzer

200.WF3

PH FAN

LAB ROOM

Baghouse

kiln camera

Kiln inlett

10

Raw mill

Manish
11

CSP TOP

12

ESP

13

Baghouse

14

PH FAN

15

Coal mill

16

100BC3

17

Coal mill

UNITED CEMENTS PVT. LTD.


NAUBISE-4, DHADING, NEPAL

DPR
Description

Manpower E
SAIZ

E&I
DAY SHIFT
Raw mill inlet & outlet lubrication pressure switch setting change 2.5 kg to 1 kg as per
decision taken in daily progress meeting.
200.BC3 LC return by mech.deptt.

analyzer CO value is not showing in CCR , so checked and find out CJB side loose
connection problem . Now ok & also probe clean and taken inline
200WF3 motor direction is change in reverse for mech requiredment after mech work
complet again direction is change and taken in forward
Preheater fan 500 FN1 triped on the fault code 5 (temp high) , so checked the pannel
and reset, panel door opened
in lab room crusher is not start so cheked and find MPCB triped, now reset than start it
is ok taken normal current
raw mill baghouse DP is high. So checked the all Solenoid valve , SV is ok but popat
valve no 8 is not operated in manual. Mech jam problem. After mentanince it is ok
kiln camera commissioning work completed
kiln inlet draft -2mmWC is showing in ccr , so draft point GI pipe remove. Find near
GI pipe band was jam with dust . So cleaning was done after that darft is -50mmwc is
show in ccr and controller

1
1

three 400 watt light is fixing and connection done in raw mill frist & ground floor
1

NIGHT SHIFT
Manish yadav , surya bali , Raman , Manish choudhary, Am
Reject gate PU pipe damage due to hot clincker materail. So replace the new PU pipe
now ok
500CC2 tripped two times due to ZSS fault. So checked find problem in controller .
Now controller replace it is ok
Baghouse DP high so manually purging done 4 times

Preheater fan I/L duct thermocouple checked and cleaning work done

one light is given in coal mill dump hopper as per process dept requiredment
100BC3 triped in zss fault so checked and find target problem. Now adjust the target it
is ok
PC firing SFM impact plate cleaning work done

MENTS PVT. LTD.

DHADING, NEPAL
DATE:29-03-2016
Manpower Engaged
GP BUILDERS

Status

UCPL

E&I
AY SHIFT
Mr.Mostkim Mr.Sahazad

Completed

Mr. R.M Kushwaha


Mr. Mohit

Completed

Mr.Mostkim Mr.Mohit

Completed

Mr.Mostkim Mr.Mohit

Completed

Mr. Mostkim

Completed

Mr.Harendra

Completed

Mr.Mostkim Mr.Mohit

Completed

MR. Martand

Completed

Mr.AJIT Sir Mr.Mohit

Completed

Mr. R.M Kushwaha


Mr. harender sahajad

Completed

NIGHT SHIFT
Raman , Manish choudhary, Aman bhai munna
Mr.Suryabali Mr.raman
Mr. Manish
Munna

Mr.

Mr.Suryabali Mr.raman

Completed
Completed
Completed

Mr.manish chaoudhary
Mr.raman
Mr.munna
Mr. Manish

Mr. raman

Mr.Suryabali Mr.raman

Completed
Completed
Completed
Completed

DATE:29-03-2016
Remarks

7 mtr. 6mm pu pipe consumption


ZSS controller kana consumption

UNITED CEMENT

NAUBISE-4, DHAD

DPR
Sl.No.

Location

E&I
DAY SH
1

ESP

ESP

PH FAN

PC Analyzer

Coal mill

500.CC1

Raw mill

CSP TOP

Truck Tripler

10

PH blaster

11

PC &KC firing

12

500FN5 & 200BC1

13

DPC TOP

14

plant area

15

Compressor room

NIG
Manish yadav , surya bali , Raman , Manish choudhary, Aman
18

Coal mill

19

Cooler

20

500HC1

UNITED CEMENTS PVT. LTD.


NAUBISE-4, DHADING, NEPAL

DPR
Manpower Engaged
SAIZ GP BUILDERS

Description

E&I
DAY SHIFT
500 RVF1 overload triped, so check and start in local mode find out materail
jam problem ,after materail release by mech. Deptt motor running in normal
load
500 RVF2 Hopper level high showing in ccr , so check and find hopper level 1
high in field due to slide gate closed by mech for jam cleaning , so feedback of
hopper no 1&2 interchange . Now show hopper level high 1 in ccr

Preheater fan I/L duct thermocouple checked and cleaning work done
PC analyzer calibration is done and proble cleaning than taken in line
coal mill PC firing SFM impact plate blowering & calibaration done
500CC2 tripped on ZSS fault due to material jamming. So start in local
materail jam after 500RVF1 Matarial releases
raw mil triped in the fault of grease spary system. So checked the 300LQ3
showing the low level. After level sensor cleaning it is ok
Silde gate is not operated by CCR. So checked and found silde gate is
mechanically jam , manually operate solenoid valve than slide gate is open,
after hamring on gate than silde gate is operate from CCR
Truck Tripler limit switch damaged by truck driver ,informed by Niraj(process)
checked & found limit switch leaver not working ,limit switch repairing. After
repairing it is mount on same place. Now limit switch is working OK

preheater blaster controller hang,checked and found calibration out from


controller,blaster calibration completed ,After calibration it is working OK
PC and KC firing tripped dut to compressed air ,checked and found
compressor
by high
temperature.temperature
110overload
deg
500FN5 andtrip
200BC1
tripped
due to overload ,reset
and given
clearance to CCR

cable laying work,dressing glanding and cylinder connector and PU pipe fitting
proximity switch open and close mounting work completed in DPC TOP for
2
new one slide gate
welding machine and grinding machine connection work in different different
plant area
one exhaust fan mount and connection done in compressor room because high
1
temp
NIGHT SHIFT
Manish yadav , surya bali , Raman , Manish choudhary, Aman bhai munna
1100RVF6 tripped in zss fault. So checked and found zss contrtoller relay not
operated. So now new zss controller mounted. Now zss feedback is healthly in
CCR
vibrating machine connection was done as per procees requiredment
500HC1 LC is taken by mech.deppt. So now power and control supply is OFF
from MCC feeder.

TD.

L
DATE:30-03-2016

Manpower Engaged
UCPL

Status

Mr.Mostkim
Mr.harender

Completed

Mr.Mostkim
Mr.harender

Completed

Mr.Ajit sir
Mr.Mostakim

Completed

Mr.Ajit sir
Mr.Mostakim

Completed

Mr.vikash sir
Mr.Mostakim

Completed

Mr.Mostkim
Mr.kushwaha

Completed

Mr.Faizan
Mr.Kushwaha Mr.
Mohit

Completed

Mr.Faizan Mr.Mohit Completed

Mr.Faizan Mr.Mohit Completed

MR.Vikash
MR.Mostakim
Mr.mostakim
Mr.Kushwaha Mr.
Harender

Completed
Completed
Completed

Remarks

MR.Vikash MR.Mohit

Completed

Mr.sahajad
MR.harender

Completed

MR.harender

Completed

Completed
zss conroller consumption
Completed
Completed

UNITED CEM

NAUBISE-4, D

DPR
Sl.No.

Location

E
DAY SHIFT
1

300FN4
500HC1

PC Analyzer

Coal mill Baghouse

Cooler

Pyrometer

CCTV

RM Hopper

PC Firing

10

500FN11

11

400BE1

12

Packer

Kushwaha,Suryabali,Manish Yad

13

Preheater Calciner

14

Kiln Outlet

15

ESP fan

16

Cooler fan

17

PC Gas analyser

18

Coal mill Gas analyser

19

500FN11

20

ESP Transformer

21

Cooler

22

Motor Amps Reading

UNITED CEMENTS PVT. LTD.


NAUBISE-4, DHADING, NEPAL

DPR

Manpower Engag

Description

SAIZ

E&I
DAY SHIFT
300 FN4 bagfilter fan LC taken by mech department ,so now feeder control and power
OFF and also LC return by mech.deppt
500HC1 LC returned by mech after LC panel charge by electrical
pc preheater analyzer taken in line
Coal mill baghouse and bin pc and kc analyzer taken in line
Grade cooler sometimes reset due to trip condition ,process requirement
Pyrometer maintainance work done dut to not showing value in CCR. After cleaning &
adjustment working OK
CAMERA maintainance work with service engineer due to view not showing clear.
After cleaning working OK.
Raw mill hopper 1 level sensor maintainance work due to false indication in ccr.After
cleaning working OK.
PC firing trip due to presssure unhealthy checked and found mechanical FLR problem.
After mech. Work now working OK
500FN11 trip due to over load due damper open up to 60%, two times reset
400BE1 Boot level alarm showing in CCR checked and found some moisture fined
material was on boot level,clean boot level
Packer start 2:00 pm ,200 bags filled

NIGHT SHIFT
Kushwaha,Suryabali,Manish Yadav,Manish Choudhary,Raman,Harendra,Hari
In pre-heater calciner duct temperature not showing exact value so checked the
thermocouple there was variation in temperature.so changed the new thermocouple
after that showing exact temp. value in CCR
In kiln outlet ,burning zone temp. not showing in CCR so checked at site and its PU
pipe melt so change the new PU pipe and covered with rope after that temp. showing
in CCR
ESP fan tripped two times due to ESP inlet temp. high so fan started in local mode
from field at 900 rpm

500FN14 its rpm feedback not showing in CCR when rpm increases above 700.So
cheack and found that set point given from CCR ( PLC to source) is coming but speed
increase feedback not come in CCR. So as per requirement RPM maintained 1000 by
miliampere(14.5) checking.Its multiplier signal not working.

PC gas analyzer its probe cleaning maintainance many times during shift
Coal mill gas analyser its probe cleaning maintainance work done during shift
500FN11 its damper open as per process requirement about 90% and motor taken 80
amp. Current
ESP transformer charged from panel side
in cooler section blaster one solenoid not working so remove the solenoid from the
panel for maintainance but during maintanance found that its O ring seal damaged due
to this its not working
motor running current reading taken in register

DATE:31-03-2016
Manpower Engaged
GP BUILDERS

Mr.Mostkim
Mr.faizan

UCPL

Status

Completed

Mr.Mostkim
Mr.Mostkim
Mr.Mostkim

Completed
Completed
Completed
Completed

Mr.faizan

Completed

Mr.faizan
Mr.Mostkim
Mr.faizan
MR.mohit

Completed
Completed

Mr.faizan

Completed

Mr.Mostkim
Mr.faizan

Completed

Mr.faizan

Completed

Mr.faizan
Mr.mohit

Completed

an,Harendra,Hari

Mr.Suryabali
Mr.raman

Mr. Manish
raman

Completed

Mr.

Mr. Manish
Mr.
raman MR.Kushwaha

Completed

Completed

Remarks

Mr.Suryabali
Mr.raman MR.Manish
choudhary

Completed

Mr. raman MR.hari

Completed

Mr.Suryabali
Mr.harender

Completed

Mr. Manish
MR.Kushwaha
MR.Harender

Completed

Mr. Manish
MR.Kushwaha

Completed

Mr.Suryabali
Mr.raman MR.hari

Completed

MR.Manish choudhary
MR.Harender

Completed

También podría gustarte