Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Emmanouil Bakirtzis,
Anastasios Bakirtzis
Antonio De Bonis,
Joo P. S. Catalo
Politecnico di Torino
Torino, Italy
gianfranco.chicco@polito.it
I.
INTRODUCTION
The current evolution of electrical distribution systems and
microgrids, with the integration of distributed energy
resources (DER), smart metering and enhanced distribution
automation is providing radical changes on the overall
planning and operation of these systems [1,2]. The methods
for distribution system analysis are following these changes by
incorporating new models of the system components and new
findings for the solution procedures. The main novelties come
from the applications to small (and weak) electricity networks,
for which the additions of specific DER components for
distributed generation, demand response or distributed storage
may change even significantly the planning perspectives and
the operation modes.
Deterministic and probabilistic power flows are the basic
tools to carry out the network calculations. For these tools,
some of the main advances currently under study or
implementation refer to:
The application of tools for integrated analysis of
transmission and distribution systems (or of Medium
Voltage and Low Voltage distribution systems);
The analysis of radial and weakly-meshed networks with
multiple supply points, including the supply from external
systems and the individual, aggregated or scattered local
generators.
Create pattern
other modules
Network analysis
n=n+1
No
Yes
No
End
X1X 2
Start
X 2 X1
RX =
End
Z 2Z1
RZ =
Z N 1Z1
Z N Z1
Z1Z2
1
:
..
.. Z1Z N 1
.. Z 2Z N 1
:
:
..
1
X N 1 X1
X N X1
radial network
weakly-meshed network
meshed network
1
:
..
Z1Z N
Z 2Z N
:
(1)
Z N 1Z N
Z N Z 2 .. Z N Z N 1
1
The Cholesky factorization is then used to express the
correlation coefficient matrix as the product
(2)
R Z = L Z LTZ
where the superscript T denotes matrix transposition.
The generation of the correlated variables starts with the
extraction of N independent standard Normal random
variables, included in a vector g. The correlated Normal
variables are found by calculating the product z = L Z g .
B. Correlated random variables from other probability
distributions
If the probability distributions of the variables of interest
are not Normal, the above procedure has to be modified to
make it possible to handle any type of probability
distribution. At the beginning of the analysis, the N correlated
random variables X1, , XN (whose probability distributions
may be different from each other) are included in the vector x
and are assumed to have mean values X = X i ,..., X N and
correlation coefficient matrix
.. X1 X N 1
.. X 2 X N 1
:
:
..
1
X1X N
X2X N
:
(3)
X N 1 X N
X N X 2 .. X N X N 1
1
For the purpose of handling correlations, the central part
of the procedure remains the one described above, using the
random variables with Normal distribution and the Cholesky
transformation. To generalise the procedure, there are two
important steps to be added:
Step 1 At the beginning of the procedure indicated in
Section III.A, a mechanism has to be introduced to pass from
the correlation coefficient matrix R X (for the initial
probability distributions) to R Z (for the corresponding
Normal probability distributions). A dedicated mechanism
has been recently illustrated in [6]. This mechanism starts
from the definition of the correlation coefficient for the
original distribution
E X iX j Xi X j
XiX j =
(4)
Xi X j
E XiX j
(Zi2 2 Zi Z j Zi Z j + Z 2j )
2 1 Z2 Z
+ +
i j
e
1
1
FX (FZ (Z i )) FX FZ Z j
dZ i dZ j
=
2 1 Z2i Z j
( ( ))
(5)
The term E X i X j is an implicit function of the
correlation
coefficient
Z i Z j . Let
us
call
it
Zi Z j = E X i X j and construct the function
Zi Z j X i X j
f Zi Z j =
(6)
) {
( ) (
{
}
Xi X j
X 12 X 9 = X 9 X 12 = 0.1066.
The other load (at node 10) is assumed to follow a Beta
distribution not correlated with the other ones. In the other
feeders, all loads are assumed to be uncorrelated with each
other. Due to the structure of the system, the solution of the
central feeder is independent of what happens in the other two
feeders. The variation in time of the mean values of the
probability distributions at nodes 8, 9 and 12 in shown in Fig.
6. For the sake of simplicity, and without loss of generality,
the correlation coefficients among the pairs of nodes (8-9, 812 and 9-12) are kept constant and equal to the values
indicated in the next section.
S2
S1
S3
13
10 14
4
5 11
6
12
16
TABLE I
PARAMETERS OF THE WEIBULL DISTRIBUTIONS AT NODES 8, 9 AND 12.
node number
a [pu]
[pu]
[pu]
8
9
12
4.106
5.296
4.633
21.765
10.338
13.278
4.0057
5.0450
4.4563
0.2287
0.5882
0.4096
0.5893 0.1092
1
In this case, the results are relatively similar to the initial
ones, due to the fact that the Weibull probability distribution
fitting the initial data is not so different from a Normal
distribution having the same mean value and standard
deviation. In any case, the results have highlighted the
solution process. From the calculations, the numerical
evaluation of the double integral has presented some
criticalities when the correlation coefficient Z i Z j is very
close to unity, as in this case the lower side of Eq. (5)
approaches zero.
15
5
4
3
node 8
node 9
node 12
node 10
2
1
0
0
12
time (hours)
16
20
24
CDF
1
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
node 12
node 10
node 9
node 8
0.86
Fig. 7. Results of the calculation of the double integral in (5) for the
determination of the correlation coefficients among nodes 8, 9 and 12 with
Normal distribution.
Fig. 9. Voltages at the nodes of the central feeder in the same Monte Carlo
execution.
0.88
0.9
0.92
0.94
voltage (pu)
0.96
0.98
V. CONCLUSIONS
This paper has presented the structure of the computational
tool prepared to solve the network equations in a deterministic
and in a probabilistic framework, in the latter case considering
the correlation among groups of random variables. The
procedure needs a pre-processing module to obtain the
correlation matrix of the equivalent Normal distributions.
With this tool, it is possible to calculate the power flows
including the effects of correlations among loads or generation
from DER, such as wind/photovoltaic systems located in close
sites in which the power production can be correlated, e.g.,
through meteorological variables. The computational modules
built for power flow calculations in steady-state operation are
being linked with other modules for the analysis of transient
conditions, power quality, reliability and security.
ACKNOWLEDGMENT
The research leading to these results has received funding
from the European Union Seventh Framework Programme
FP7/2007-2013 under grant agreement no. 309048, project
SiNGULAR (Smart and Sustainable Insular Electricity Grids
Under Large-Scale Renewable Integration). Joo Catalo also
thanks FCT-Portugal and COMPETE for projects FCOMP-010124-FEDER-020282 (Ref. PTDC/EEA-EEL/118519/2010)
and PEst-OE/EEI/LA0021/2013.
REFERENCES
[1]
[2]
Fig. 10. Average value and standard deviation bands of the voltage at node
10.
[3]
[4]
[5]
Fig. 11. Average value and standard deviation bands of the voltage at node
12.
[6]
[7]
[8]