GPL-01-D&C
Document Details
Submission information
This document and its contents have been prepared by Downer and are intended solely for
Transport for New South Wales (TfNSW) information and use in relation to the Gosford Passing
Loops (GPL) Project.
Document Review
Document Approval
Signature
Revision Status
Rev
Date
28-03-13
Associated documents
Document Number
Title
Revision
Date
www.downergroup.com
Page 2
TABLE OF CONTENTS
terms and definitions ________________________________________________________________________ 5
1 introduction _____________________________________________________________________________ 7
2 purpose of the quality management plan (QMP) __________________________________________ 8
3 project description _______________________________________________________________________ 9
3.1 operational project purpose ________________________________________________________ 9
4 project milestones ______________________________________________________________________ 11
5 management representative ____________________________________________________________ 13
6 quality document control _______________________________________________________________ 14
6.1 introduction document control _____________________________________________________ 14
6.2 document storage ________________________________________________________________ 14
6.3 plan review _______________________________________________________________________ 14
6.4 revisions and amendments _________________________________________________________ 15
6.5 qmp submission ___________________________________________________________________ 15
6.6 control of quality records __________________________________________________________ 15
7 communicating the qmp _______________________________________________________________ 16
8 qmp references ________________________________________________________________________ 17
8.1 general ___________________________________________________________________________ 17
8.2 legal and regulatory _______________________________________________________________ 17
9 downer australia integrated management system (IMS) ___________________________________ 18
9.1 structure of the IMS ________________________________________________________________ 18
9.2 audit of the ims____________________________________________________________________ 19
10 project quality objectives, organisation & resources _______________________________________ 20
10.1 introduction _______________________________________________________________________ 20
10.2 quality management objectives ___________________________________________________ 20
10.3 project organisation chart _________________________________________________________ 21
10.4 project responsibilities______________________________________________________________ 21
11 project administration ___________________________________________________________________ 26
11.1 project filing and storage system ___________________________________________________ 26
11.2 project meetings, reviews and reports ______________________________________________ 26
11.3 construction programme __________________________________________________________ 26
11.4 control of drawings and specifications ______________________________________________ 26
11.5 managing variations _______________________________________________________________ 26
12 internal audits and planned inspections __________________________________________________ 27
12.1 project audits _____________________________________________________________________ 27
13 purchasing _____________________________________________________________________________ 28
13.1 suppliers and subcontractors _______________________________________________________ 28
13.2 site induction and training _________________________________________________________ 29
13.3 plant and equipment ______________________________________________________________ 29
www.downergroup.com
Page 3
www.downergroup.com
Page 4
Definitions
CAR
CEMP
CMP
Acronym for Contract Management Plan identifies how DA will deliver all
requirements within contract GPL-01-D&C. The plan provides an overview of
all of the management plans that will be developed and executed for the
duration of the project.
CLP
CoA
Compliance
audit
CSMP
DA-QA-FM
DA-QA-PR
DA-QA-RG
DA-QA-RI
DA-QA-TR
DirectorGeneral
DMP
Downer
Downer Australia
DP&I
EMP
GCC
Hold Point
Those points identified within the applicable Inspection and Test Plan,
beyond which the stated activity must not proceed within approval to
proceed from the nominated authority.
www.downergroup.com
Page 5
Definitions
IMS
Lot Checklist
ITP
Noncompliance
Nonconformance
(NCR)
NSFC
NCR
Plan
Principal, the
Project, the
QA
QMP
REF
Stakeholders
SWMS
TfNSW
www.downergroup.com
Page 6
1 INTRODUCTION
The Northern Sydney Freight Corridor (NSFC) Program is an initiative to improve capacity and
reliability for freight trains on the Main North Line between Sydney (Strathfield) and Hexham, west
of Newcastle.
The program is designed to:
Improve freight train access through northern Sydney
Relieve a serious bottleneck on the rail network
Create a more efficient freight rail network
Improve the reliability of passenger services on the Main North Line
Enable freight access during peak times
The Gosford Passing Loops project (the Project) is one of four projects as part of the wider NSFC
Program.
In October 2012, the Project was approved by the Deputy Director General Transport Projects,
Transport for NSW subject to Conditions of Approval (CoA).
In January 2013, Transport for NSW (TfNSW) appointed Downer EDI as the design and construct
contractor for the project.
www.downergroup.com
Page 7
www.downergroup.com
Page 8
3 PROJECT DESCRIPTION
The Project comprises the construction of two electrified passing loops and associated
infrastructure north of Gosford Station to allow for the passing of faster passenger trains while
freight trains are held on the mainline or in the reverse arrangement as deemed necessary.
The Project comprises two new tracks for the passing loops (and associated overhead wiring, civil
and structural works) between Gosford and Narara stations. The total new track length would be
approximately 4 kilometres (km) (approximately 2 km for both the Up and Down Refuges). The
new tracks would be constructed on the outside of the existing rail tracks and would generally be
accommodated within the existing rail corridor boundary (with the exception of a short section of
track between chainages 82.40 km and 82.70 km, which would require the eastern corridor
boundary to be widened by up to approximately 3 metres to facilitate the construction of the
track and other railway infrastructure).
The key features of the GPL include:
Three new pairs of bridges (six bridges in total) over Bradys Gully, Wingello Creek and Wyoming
Creek, adjacent to the existing rail bridges.
One new crossover on the Up Main (adjacent to Brooks Avenue, Wyoming, between chainages
83.50 km and 83.80 km) and one new turnout on the Down Refuge (adjacent to Brooks Avenue,
Wyoming, between chainages 83.60 km and 83.80 km).
Maintenance access roads and gates.
A combined services route (approximately 2 kilometres long) on the eastern side of the rail
corridor between Gosford Station and the Etna Street overbridge, and on the western side of the
rail corridor between the Etna Street overbridge and Narara Station.
Three underline crossings (buried services route allowing services/utilities to cross beneath the rail
tracks) and associated cable routes at proposal chainages 81.54 km, 81.97 km and 84.52 km.
The refurbishment of an existing Up Refuge between Gosford Station and the Etna Street
overbridge the removal of two existing maintenance sidings (referred to as the Down Loco Sidings
1 and 2), adjacent to Gosford Showground.
The removal of two existing crossovers and one turnout between Gosford Station and Gosford
Showground.
The refurbishment of one existing catchpoint adjacent to Gosford Showground.
Modifications to the existing signalling system at various locations between Gosford Station and
north of Narara Station (proposal chainages 81.00 km to 86.00 km).
The adjustment, relocation, protection and/or provision of services and utilities, including
overhead wiring, high and low voltage, telecommunications/control, and earthing/bonding
operation of the Project.
3.1
The fundamental purpose of the Gosford Passing Loops Project is to provide an alternative route
for freight trains, allowing them to be passed by faster passenger rolling stock.
www.downergroup.com
Page 9
www.downergroup.com
Page 10
4 PROJECT MILESTONES
For major project milestones, refer to the GPL Program that will be submitted as part of the
monthly report.
www.downergroup.com
Page 11
www.downergroup.com
Page 12
5 MANAGEMENT REPRESENTATIVE
The nominated Quality Management Representative for the Gosford Passing Loops Project is:
Name: Sheree Jones
Title: Quality Manager
Phone: 02 4918 7400
Mobile: 0418 493 503
Facsimile: 02 4918 7404
The Management Representative is contactable by telephone and/or email at all times during
the undertaking of the Contractors Activities and must be available to attend meetings at the
Principals office or at the Site within 48 hours of notice by the Principals Representative.
www.downergroup.com
Page 13
This document is authorised, distributed, amended and reviewed in accordance with DA-QAPR001 Document Management (included within the IMS). Records of distribution are maintained
by the Quality Manager.
All controlled copies of this document are registered in accordance with DA-QA-PR001
Document Management.
6.2
DOCUMENT STORAGE
PLAN REVIEW
This document shall be reviewed in response to reported issues and outcomes of internal or
external audits and/or changes to internal policies. In particular, a review will address:
Progress of Works
www.downergroup.com
Page 14
Revisions
All document revisions shall be made in accordance with DA-QA-PR001 Document Management
and with the authority of the Quality Manager.
Amendments
Amendments are only made as permitted under the contract.
When amendments are made, the entire document will be reissued and the revision number
updated. Registered recipients will automatically receive the new revision with advice on
amendments made.
Revised plans and associated documents will be issued together with a transmittal form and
recipients will ensure superseded versions are replaced and destroyed to prevent inadvertent use.
6.5
QMP SUBMISSION
The QMP will be submitted to the Principals Representative for review in accordance with the
requirements set out in the Contract.
6.6
The following controls will be implemented to manage quality records for the duration of the
project and for a period of five years from the Date of Completion. These controls satisfy TfNSW
quality requirements, and have been taken from TfNSW Standard Requirements TSR Q1 Quality
Management.
Downer will ensure that all quality records satisfy the requirements of the Contract
Downer will retain all product and service conformance records including the
Subcontractors service conformance records and certificates for a period of no less than
five years from the Date of Completion
Where requested by the Principals Representative, Downer will provide the Principals
Representative with copies of any Quality Records. Those Records which are not available
on-site, will be forwarded to the Principals Representative within 3 business days of the
request.
www.downergroup.com
Page 15
www.downergroup.com
Page 16
8 QMP REFERENCES
8.1
8.2
GENERAL
Legal and Regulatory compliance documents are managed within Downer Australia using a
number of centralised reference matrices. These detail the references applicable to all aspects
of the work to be carried out in the course of this contract.
Functional Area
Applicable Matrix
Environment
Health and Safety
Quality
www.downergroup.com
Page 17
9.1
The core of the IMS is a set of Downer Australia documents that reflect processes conducted
across all Australian business units. Key documents at the national level are:
Strategies, Objectives and Policies guide our business and how we conduct operations
Management Standards (MS) are the core national standards that cover the business
processes and risk controls. They describe the systems, methods and forms that are used to
plan, manage and control our processes and risk controls. They also define the minimum
standards we apply to our worksites in the areas of Health, Safety and the Environment
Handbooks provide information on how the IMS is used and operates and provide
specific information in key areas
Forms, Zero Harm Notifications, Risk Assessments, SWMS and other documents are the
details of the work we do, help control our risks and provide records
The IMS is hosted on the Downer Australia intranet, a business application available to all
employees and providing a set of key resources including:
Document management
Records management
Risk management
Incident reporting and investigation
Non-conformance management
Training provision and record management
www.downergroup.com
Page 18
The IMS is audited, and has been certified by, by an accredited 3rd Party organisation to verify
compliance with the above standards as well as legislative and regulatory requirements. A copy
of the certificate confirming the currency of certification is provided in Appendix A, and a
summary of the certification is reflected in the following table.
Compliance Area
Accreditation Standard
Audit Authority
Certificate Number
Quality Assurance
149150 QEC7718
www.downergroup.com
Page 19
Key Result
Area
Quality
Management
www.downergroup.com
Page 20
General
Communication
Systems of Work
Description of Responsibility
Liaise with the Safety, Environment & Quality Manager on any unique
activities that may require special operating standards or supervision.
Training
Zero Harm
(Safety &
Environment)
www.downergroup.com
Page 21
Description of Responsibility
Plan, manage and control project activities to assist the construction works
General
Communication
Zero Harm
(Safety &
Environment)
www.downergroup.com
Page 22
Communication
Zero Harm
(Safety &
Environment)
Description of Responsibility
Plan, coordinate and monitor the construction activities across the project
against project objectives
Liaise with the Safety, Environment & Quality Manager on any unique activities that
may require special operating standards or supervision
www.downergroup.com
Page 23
General
Communication
Zero Harm
(Safety &
Environment)
Description of Responsibility
All visitors onsite are inducted and registered and shall be accompanied
at all time while on site
Provide clear job instruction and methods to personnel for all tasks
performed
www.downergroup.com
Page 24
Safety, Quality
and
Environment
Description of Responsibility
www.downergroup.com
Page 25
11 PROJECT ADMINISTRATION
11.1 PROJECT FILING AND STORAGE SYSTEM
Refer to the Quality Document Control section of the QMP for information on electronic and
hard copy document storage and the nominated quality database
11.2 PROJECT MEETINGS, REVIEWS AND REPORTS
Project and subcontractor meetings will be held weekly on site and will be documented
according to Downer Project Management procedures.
Internal project meetings will be conducted on an as needs basis and minutes of those meetings
recorded and filed in accordance with DA-QA-PR001 Document Management.
The Weekly and Monthly will be prepared as per procedure DA-PM-PR020 Monthly Project
Reporting and Review and as stipulated in the Contract.
11.3 CONSTRUCTION PROGRAMME
The construction program will be handled according to procedure DA-PM-PR011 Project
Management Plans. Refer to the CSMP for further information on the management of the
Program. The program will be submitted as part of the monthly report.
11.4 CONTROL OF DRAWINGS AND SPECIFICATIONS
Refer to the Design Management Plan developed to meet the requirements of contract and TSR
T1 Technical Requirements.
11.5 MANAGING VARIATIONS
Contract variations will be managed according to procedure DA-PM-PR025 Managing Variations,
Delays and Disputes, and in accordance with the contract terms and conditions. No variations
will be implemented without written client approval or direction.
www.downergroup.com
Page 26
www.downergroup.com
Page 27
13 PURCHASING
Downer as the main contractor will manage all of the operating areas of the project and
subcontractors.
Downer will ensure that all relevant procurement processes (as outlined within Downers IMS
System) will be followed so that subcontractors are selected and appointed to deliver their
relevant scope of works and services in accordance with the contract.
Refer to the Contract Management Plan that stipulates that the requirements of the head
contract will be reflected in the subcontracts and will also ensure that these are also passed
down to lower tier subcontractors. The Contract Management Plan also provides a figure that
diagrammatically shows the hierarchy of contracts developed for the establishment of the
project.
13.1 SUPPLIERS AND SUBCONTRACTORS
Approved key subcontractors at the time of issue of the QMP are noted in the following table.
Subcontractor / Supplier Name
Scope
SMEC
WS Atkins International
Safety Assurance
DSS survey
DA-ZH-022 Visitor & Contractor Management is applied to ensure that all subcontractors perform
their duties to the required specified requirements for the duration of the project. The following
specific controls apply:
Assessment of subcontractors including past performance
Use of purchase orders and plant-hire/sub-contract agreements
Supervision and continuous monitoring of operations on site
Use of ITPs
Implementation of Downer management processes, Critical Risk Controls and other
process controls over work practices to ensure that subcontractor work is completed
safely and to specification.
All subcontractors are engaged and work on site under the Authority to Work Permit (ATWP)
system, as detailed in DA-ZH-022 Visitor & Contractor Management. A valid work permit is required
prior to a subcontractor undertaking any work on a Downer site.
www.downergroup.com
Page 28
www.downergroup.com
Page 29
www.downergroup.com
Page 30
www.downergroup.com
Page 31
2.
Design Manager reviews ITP and either sends back to Engineering Manager with
changes or approves
3.
Design Manager submits ITP to Project Manager for review and approval. Project
Manager either makes changes or provides approval ensuring that it satisfies all
relevant standards and specifications for the proposed works
4.
Once approved, the Project Manager will then submit to the Quality Manager
5.
6.
Once approved, the Quality Manager will enter the ITP into QAntrol
www.downergroup.com
Page 32
The ITP will then be undertaken by the engineer responsible for the work or the
approved representative and entered into QAntrol.
notification timeframes
www.downergroup.com
Page 33
www.downergroup.com
Page 34
www.downergroup.com
Page 35
www.downergroup.com
Page 36
www.downergroup.com
Page 37
www.downergroup.com
Page 38
Document Management
DA-QA-PR002
DA-QA-PR003
DA-QA-PR004
Management Review
DA-QA-PR005
DA-QA-PR006
DA-QA-PR007
Internal Audit
DA-QA-PR008
DA-QA-PR009
Records Management
DA-QA-FM001.2
DA-QA-FM001.3
DA-QA-FM001.4
DA-QA-FM001.5
Form template
DA-QA-FM001.6
DA-QA-FM001.7
DA-QA-FM001.8
DA-QA-FM001.9
DA-QA-FM003.1
DA-QA-FM003.2
DA-QA-FM003.3
DA-QA-FM004.1
DA-QA-FM005.1
DA-QA-FM005.2
CAR Register
DA-QA-FM007.2
www.downergroup.com
Page 39
DA-QA-FM007.4
DA-QA-FM007.5
DA-QA-FM008.1
DA-QA-FM009.1
Archive Register
DA-QA-FM009.2
Archive Register
DA-QA-FM009.3
Destruction Authority
www.downergroup.com
Page 40