FECHA

PROGRAMACION DE CON
CANTIDAD (M3)

JUEVES 03 DE MARZO 2016

JUEVES 03 DE MARZO 2016

SABADO 05 DE MARZO 2016

Monday, March 07, 2016

Tuesday, March 08, 2016

Wednesday, March 09, 2016

Thursday, March 10, 2016

Friday, March 11, 2016

Saturday, March 12, 2016

Los pedidos son bajo c

PROGRAMACION DE CONCRETO MAIZAL


HORA EN OBRA
TIPO DE CONCRETO RESISTENCIA
FLUIDO

3000

2:00 PM

FLUIDO

3000

4:00 PM

FLUIDO

3000

10:00:00 a.m

FLUIDO

3000

2:00 PM

FLUIDO

3000

2:00 PM

FLUIDO

3000

2:00 PM

FLUIDO

3000

2:00 PM

FLUIDO

3000

2:00 PM

FLUIDO

3000

2:00 PM

Los pedidos son bajo confirmacion

DESCRIPCION
CONCRETO PARA BARANDA K0+178K0+208 EJE 1
CONCRETO PARA BARANDA K0+208K0+238- EJE 1
CONCRETO PARA BARANDA K0+238K0+268 EJE 1
CONCRETO PARA BARANDA K0+238K0+268 EJE 1
CONCRETO PARA BARANDA K0+268K0+298- EJE 1
CONCRETO PARA BARANDA K0+298K0+305- EJE 1 y glorieta k0+00k0+023
CONCRETO PARA BARANDA glorieta
k0+023- k0+053
CONCRETO PARA BARANDA K0+075K0+105 EJE 2
CONCRETO PARA BARANDA K0+105K0+135 EJE 2