Project Name

Main Contractor

Bunga Sari Flour Mill - Cilegon


PT. Multi Kreasi Develindo

ANALISA PONDASI SILO


SILO SEMEN ( BERAT SENDIRI + ISI ) = 100 TON
TEBAL PONDASI YG DIRENCANAKAN = 0.7 M
KOEFISIEN GEMPA = 10%

=1.5

beton

= 2.5 t/m3

BERAT SILO + ISI = 100 TON

= 0.8 Kg/Cm
= P/A +q

= 8 t/m2

= 8 x (100/A) + 0.7 x 2.5


A = 100/(8-1.75)
=16
DIAMBIL UKURAN 4 x 4 m
CHECK TERHADAP MUATAN SEMENTARA
DAYA GEMPA :
H = 10% x G
= 10% x 100
= 10 Ton

323623324.xls

Bunga Sari Flour Mill Projects

BEKERJA PADA 15 Mtr DARI ALAS PONDASI


V = BERAT SILO + BERAT PONDASI
= 100 + 0.7 x 4 x 4 x 2.5
= 128 Ton
M=HxV
= 10 x 15
= 150 Ton
e=M/V
= 150 / 128
= 1.17
M > 1/6 B

max = 2/3 x (( V / by ( bx/2 ) - e ))


= 2/3 x (( 128 / 4 (2 - 1.17))
= ( 0.6 x (( 128 / 4 x 0.83 ))
= 23.1

max >

JADI

23.1 > 22.3

323623324.xls

check = OK