Facilities Master Plan

Recommendations Summary
Presented to the
El Paso ISD Board of Managers

January 21, 2015

Facilities Master Plan


Acknowledgements
EPISD Board of Managers
EPISD Administration and School Hosts
Community Steering Committee
Consultants

Facilities Master Plan


Agenda
Background
Goals and Considerations
Process Recap / Data Snapshot
Planning Considerations / Courses of Action

Recommendations
Overview
Cost, Prioritization, Phasing
Details

Facilities Master Plan


Goals
Facilities Plan to Support District Mission
Define Prioritized Capital Plan
Promote Districtwide Equity
Achieve Financial Sustainability
Preserve Public Trust
Also:
Simplify attendance patterns
Achieve vertical alignment of programs

Facilities Master Plan


Considerations
Recommendations focus on:
Operational actions (shift attendance boundaries, realign feeder
patterns, adjust grade configurations, consolidate schools)
Capital actions (reconstruction, renovations, additions)
Educational actions (new programs) were explored, and additional
integration with curriculum stakeholders is required.
Facilities Master Plan is intended as a living document to serve as blueprint
and framework for policy and action.

Facilities Master Plan


Process
1.
Project
Setup
(Feb-March)

2.
Data
Collection
(April-June)

3.
Data
Analysis and
Compilation
(July-Sept)

4.
Planning and
Outreach
(Oct-Jan)

5.
Implementation

Citizens Steering Committee


Review
Background
Data

Community
Dialog 1:
Educational
Framework

Facility
Options

Community
Dialog 2
(+5):
Vet Options

Recommend
ations

Facilities Master Plan


What is the data telling us?
Significant facility needs.
$504 million deferred maintenance w/in 5-year horizon (like for like).
Additional $348M in capital upgrades.
Average school age 48 years.
Enrollment is declining and migrating.
From 65k peak, 2014 enrollment of 59k, dropping to 54k by 2019.
School capacity surplus
76% capacity utilization districtwide
17k surplus seats (not including 8k in portables)
7

Facilities Master Plan


Data Snapshot
Grade

5-Yr
Facility
Cost ($M)

Other

9.7

20%

Elementary School

203.6

High School
Middle School
TOTAL

Perm
Capacity

2019 Proj
Enroll

28%

35,788

27,849

(2,368)

78%

7,939

181.1

34%

17,343

14,461

(2,139)

83%

2,881

107.5

28%

17,114

11,524

(732)

67%

5,590

70,810

53,916

(5,226)

504.2

5-yr FCI

30%

5-year
change

5 yr Proj
Util

76%

Surplus
(deficit)
capacity

16,894

Facilities Master Plan


Planning Considerations
Student Opportunity
Size / Capacity Utilization
Facility Condition / Repair Costs
Operational Costs, Program Offerings
Facility Age / Adequacy
Site acreage
Geography / Transportation
Community Input 4 out of 5 match!
9

Facilities Master Plan


Potential Courses of Action
Repair what you have.
Rebuild instead of repair.
Prioritize repairs based on severity.
Avoid repairs with consolidation or repurposing.
Balance capacity utilization with attendance boundary adjustments.
Balance capacity utilization with program offerings.

10

Master
Plan
DistrictFacilities
Planning
Areas
Data Conventions
Planning Areas
by geography and grade level
for convenience of scale.
Naming Convention:
area, grade, group
Eg, C.E.2 = Planning Area C,
Elementary Schools, Group 2
Eg, B.H.1 = Planning Area B,
High Schools, Group 1

11

Facilities Master Plan


Recommendations Overview

12

Facilities Master Plan


Recommendations Overview
Category

ES

MS

HS

Alt

TOTAL

2019
Notes
Enrollment

Lamar, Morehead, Douglass, Burleson, Burges,


Jefferson, Bassett, Ross, Burnet, Dowell, Bradley,
Andress

Rebuild

12

Rebuild/Convert to K-8

4,160 White, Lincoln, Bonham, Terrace Hills

Major Renovation

4,350 Coronado, El Paso, Irvin

Prioritized Renovations 38

10

58

10,623

34,783 Districtwide

Repurpose/Landbank

12

12

TOTAL

58

15

10

89

53,916

13

Bond, Roberts, Vilas, Beall, Alta Vista, Zavala,


MacArthur, Travis, Schuster, Collins, Fannin,
Newman

Facilities Master Plan


Costs

$852 M

$318 M

$504 M like for like


$348 M capital
upgrades

$405M avoided
repairs and upgrades
(rebuild, consolidate)

Prioritized Repairs &


Basic Upgrades

Prioritized Repairs &


Basic Upgrades

$129M in deferred
lower priority needs

14

+ $411 M
New
Construction
and Major
Renovations

=
$729M

(2014 dollars)

Facilities Master Plan


Prioritization and Phasing
Planning Areas phased as
groups due to interrelationship
of projects
Planning areas assigned a
consistent weighted score and
ranked based on utilization and
condition.

15

~2015 Bond ($261M)

~2018 Bond ($253M)

~2021 Bond ($216M)

Rebuild White as PK-8


Expand Terrace Hills as PK-8
Rebuild Lamar
Rebuild Douglass
Rebuild Bradley
Charles MS library conversion
Prioritized Renovations (A.E.2,
A.E.3, B.E.1, C.E.3, C.M.1)

Operational Actions

Vilas (to Aoy/Lamar)


Roberts (split to Herrera; Bond

and eventual Lincoln PK-8)


Alta Vista (to Coldwell, Crockett,
Moreno)

Balance Herrera and Guerrero


Feed Green to Morehead MS
Rezone Vilas South I10 to Aoy
Correct Alamo/Hart zone
Feed Dowell to Magoffin MS
16
Feed all Moreno to Armendariz

Rebuild Lincoln as PK-8


Rebuild Bonham as PK-8
Rebuild Morehead
Rebuild Bassett
Rebuild Ross
Rebuild Dowell
Rebuild Andress HS
Prioritized Renovations (A.E.1,
A.M1, B.E.4, B.M1, C.E.2, C.H.1)

Operational Actions

Beall (to new Douglass)


Fannin (to new Bradley)
Balance Douglass, Hart, Aoy

Coronado HS Major Renovation


El Paso HS Major Renovation
Jefferson HS Major Renovation
Burgess HS Major Renovation
Rebuild Burleson
Rebuild Burnet
Prioritized Renovations (A.H.1,
B.E.2, B.E.3, B.H.1, C.E.1)

Operational Actions

Bond (to new Lincoln PK8)


Newman (to new Terrace Hills
PK8)

Collins (to new Terrace Hills


PK8)
MacArthur (to new Bonham
PK-8)
Schuster (to new Dowell)
Zavala (to new Burleson)
Travis (to new Burnet)

$302M
~2015 Bond ($261M)

$339M
~2018 Bond ($253M)

$335M
~2021 Bond ($216M)

Rebuild White as PK-8


Expand Terrace Hills as PK-8
Rebuild Lamar
Rebuild Douglass
Rebuild Bradley
Charles MS library conversion
Prioritized Renovations (A.E.2,
A.E.3, B.E.1, C.E.3, C.M.1)

Operational Actions

Vilas (to Aoy/Lamar)


Roberts (split to Herrera; Bond

and eventual Lincoln PK-8)


Alta Vista (to Coldwell, Crockett,
Moreno)

Balance Herrera and Guerrero


Feed Green to Morehead MS
Rezone Vilas South I10 to Aoy
Correct Alamo/Hart zone
Feed Dowell to Magoffin MS
17
Feed all Moreno to Armendariz

Rebuild Lincoln as PK-8


Rebuild Bonham as PK-8
Rebuild Morehead
Rebuild Bassett
Rebuild Ross
Rebuild Dowell
Rebuild Andress HS
Prioritized Renovations (A.E.1,
A.M1, B.E.4, B.M1, C.E.2, C.H.1)

Operational Actions

Beall (to new Douglass)


Fannin (to new Bradley)
Balance Douglass, Hart, Aoy

Escalated costs
to time of
construction

Coronado HS Major Renovation


El Paso HS Major Renovation
Jefferson HS Major Renovation
Burgess HS Major Renovation
Rebuild Burleson
Rebuild Burnet
Prioritized Renovations (A.H.1,
B.E.2, B.E.3, B.H.1, C.E.1)

Operational Actions

Bond (to new Lincoln PK8)


Newman (to new Terrace Hills
PK8)

Collins (to new Terrace Hills


PK8)
MacArthur (to new Bonham
PK-8)
Schuster (to new Dowell)
Zavala (to new Burleson)
Travis (to new Burnet)

Facilities Master Plan


Community Dialogue Responses

Results are provided by planning area


in the Recommendations Report
96% of all EPISD schools had at least
one respondent affiliated with it

18

School Affliation
(in order of % of total respondents)
Coronado High School
Roberts Elementary School
Zav ala Elementary School
Putnam Elementary School
Schuster Elementary School
I rv in High School
Lincoln Middle School
Cielo Vista Elementary School
Andress High School
Franklin High School
Coldw ell Elementary School
Mesita Elementary School
El Paso High School
Bond Elementary School
Jefferson High School

English Spanish
157
6
75
54
52
61
91
10
38
14
49
1
37
5
39
0
32
0
28
4
26
5
31
0
26
0
21
1
19
2

Total
12.4%
9.8%
8.6%
7.7%
4.0%
3.8%
3.2%
3.0%
2.4%
2.4%
2.4%
2.4%
2.0%
1.7%
1.6%

Facilities Master Plan


Community Survey
Alignment
11 of 16
recommendations
matched preferred
option

Preferred
Option?

A.E.1

yes

Close Roberts - Boundary Changes

A.E.2

yes

Close Putnam - Feeder Alignment Boundary Changes

A.E.3

yes

Close Vilas - Boundary Changes Rebuild Lamar

Option 2

Close Roberts - Close Bond - Build K-8 @


40%
Zach White - Boundary Changes
Convery Zach White to a K-8 - Classroom
23%
Addition
Close Vilas - Repurpose as PreK Center 26% Boundary Changes - Close 1-2 more
Elementary Schools - Rebuild Lamar

Option 3

B.E.1

yes

B.E.2

yes

B.E.3

no

B.E.4

yes

B.M.1

new

B.H.1

yes

C.E.1

tie

Boundary Changes

yes

Repurpose Schuster for maintenance


facility - Rezone to Crosby and Dowell

C.E.3

no

Boundary Changes

C.M.1

new

Close Charles and consolidate with


Richardson -Build addition at
Richardson

24%

Close Charles and rezone to area middle


schools

35%

C.H.1

yes

Reconfigure Irvin

26%

Build new Irvin on site - Alternative (Close


Irvin and rezone to area high schools)

15% Build new Andress on site

25%

12%

Changes

yes

Close Alta Vista - Feeder Alignment Boundary Changes


Same as Option 1 but closing one more
elementary school

13%
31% Repurpose Coldwell as a K-8
5%

Rebuild Henderson & Burleson and


31%
convert to a K-8

Same K-8 option as Option 1 but building


the K-8 on MacArthur's site

9%

Rebuild Jefferson on site - Rebuild Burges


on site

42%

Rebuild Burnet - Alternative: close and


rezone to area schools

7% Rebuild Bliss

Close Burnet and Travis and build


9% new elementary school on Burnet

site

Close Schuster and Dowell, rebuild new


25% school on Schuster site - Alternative:

Close Lamar - Close 1-2 more


15% Elementary Schools - Boundary

A.H.1

Same as Option 1 but closing one more


elementary school

Option 4

39%

yes

Right-size Morehead
Major renovations to El Paso &
Coronado
Close Beall - consolidate with Douglass 43%
reconstruct Douglass - Boundary
changes
20 classroom addition to Milam 43%
Alternative: raze/build new
Close Zavala - Rebuild Cooley, Clardy
20%
and Burleson
Combine Bonham, MacArthur & Cielo
Vista as a K-8 on Bonham site - Rebuild 34%
Hawkins - Boundary Changes
Close Milam, convert to a K-8 - Close
Bassett, convert to a K-8
Only perform facility condition
21%
remedies

19%

A.M.1

C.E.2

19

Option1

40%

Rebuild new school on Dowell site


Close Fannin and consolidate with Bradley Convert Terrace Hills, Collins and Newman
42%
26%
to a K-8 on Terrace Hills site - Feeder
Alignment

31%

23%

Facilities Master Plan


Recommendation Details
High Schools A.H.1, B.H.1, C.H.1
Middle Schools A.M.1, B.M.1, C.M.1
Elementary Schools A.E.1-3, B.E.1-4, C.E.1.3

20

Facilities Master Plan


High Schools

21

Facilities Master Plan


High Schools

22

Facilities
Master
Plan
Planning
Area
A.H.1
RECOMMENDATIONS FROM OPTIONS

Planning Area A.H.1

Boundary Change
No boundary adjustments
Campus Reconstruction
Major Renovations to El Paso and
Coronado High Schools

3160 | 88%
2779 | 74%
2336 | -16%

Major Renovation at
Coronado HS

2538 | 99%
2506 | 79%
1994 | -20%

Franklin and Franklin 9th remain


unaffected in short term planning horizon
1078 | 88%
1234 | 74%
1111 | -10%

23

KEY
Program Capacity | Current Utilization
Current Enrollment | Proj. Utilization
Proj. Enrollment
| +/- % Enroll Change

Facilities
Master
Plan
Planning
Area
B.H.1
Planning Area B.H.1
RECOMMENDATIONS FROM OPTIONS
Boundary Change
No currently planned boundary changes

KEY
Program Capacity | Current Utilization
Current Enrollment | Proj. Utilization
Proj. Enrollment
| +/- % Enroll Change

Campus Reconstruction
Jefferson due to facility condition/modernization
Burgess due to facility condition/modernization

1505 | 95%
1435 | 85%
1275 | -11%

Austin and Bowie remain unaffected in short term


planning horizon

Major Renovation at
Burges HS

1376 | 83%
1145 | 74%
1025 | -10%
24

1339 | 78%
1041 | 65%
865 | -17%

1400 | 101%
1414 | 101%
1411 | ---

Major Renovation at
Jefferson HS

Facilities
Master
Plan
Planning
Area
C.H.1
Planning Area C.H.1
RECOMMENDATIONS FROM OPTIONS
1549 | 112%
1736 | 100%
1554 | -10%

Boundary Change - None


Campus Reconstruction
Rebuild Andress High on current site due to facility
condition/modernization needs
Rebuild Irvin; right size to magnet school offerings utilizing
reallocated 2007 Bond Funds
Chapin remains unaffected in long term planning horizon
(currently receiving field house and classroom addition from
2007 Bond Funds)

25

Rebuild
Andress HS
Major Reno at
Irvin HS

1738 | 85%
1480 | 72%
1246 | -16%

1661 | 110%
1831 | 99%
1644 | -10%

KEY
Program Capacity | Current Utilization
Current Enrollment | Proj. Utilization
Proj. Enrollment
| +/- % Enroll Change

Facilities Master Plan


Middle Schools

26

Facilities Master Plan

27

Facilities
Master
Plan
Planning
Area
A.M.1
Planning Area A.M.1
RECOMMENDATIONS FROM OPTIONS
Boundary Change
Bond to new Lincoln (Roberts to Herrera and new
Bond/Lincoln)
Campus Reconstruction
Lincoln MS and Bond ES become a pK-8
Rebuild Morehead due to
age/condition/modernization need

1200 | 60%
721 | 53%
630 | -13%

1482 | 80%
1183 | 82%
1209 | +2%

1244 | 75%
931 | 65%
804 | -14%
Rebuild Lincoln as pK-8
Combine with Bond Elementary

1174 | 68%
794 | 53%
626 | -21%
Rebuild Morehead
Rebuild to modernize learning environments

Brown, Hornedo and Wiggs remain unaffected in short


term planning horizon
1000 | 87%
869 | 76%
762 | -12%
28

KEY
Program Capacity | Current Utilization
Current Enrollment | Proj. Utilization
Proj. Enrollment
| +/- % Enroll Change

Facilities Master Plan


Planning Area A.M.1

29

Facilities
Master
Plan
Planning
Area
B.M.1
RECOMMENDATIONS FROM OPTIONS

Planning Area B.M.1

Boundary Change -None

Rebuild Bassett
Rebuild to modernize learning environments

Campus Reconstruction
Bassett due to facility
condition/modernization
Ross due to facility
condition/modernization
Bonham/MacArthur become a pK-8
campus
Henderson, Guillen and Armendariz
remain unaffected in short term
planning horizon

30

879 | 86%
756 | 85%
750 | -1%

1119 | 90%
1008 | 111%
1240 | +23%
933 | 78%
732 | 64%
598 | -18%

Rebuild Ross
Rebuild to modernize learning environments

1234 | 59%
724 | 61%
750 | +4%
1229 | 69%
847 | 62%
763 | -10%

KEY
Program Capacity | Current Utilization
Current Enrollment | Proj. Utilization
Proj. Enrollment
| +/- % Enroll Change

Facilities Master Plan


Planning Area B.M.1

31

Facilities
Master
Plan
Planning
Area
C.M.1
RECOMMENDATIONS FROM OPTIONS
Boundary Change
Rezone Students from Newman to new
Collins/Terrace Hills Campus

Planning Area C.M.1

1139 | 65%
737 | 87%
991 | +34%

Charles Modernization
Rebuild Library to modernize learning
environments in under utilized area of campus

Campus Reconstruction
Create pK-8 with Collins/Newman at
Terrace Hills
Magoffin, Canyon Hills and Richardson
remain unaffected in short term
planning horizon

980 | 67%
656 | 53%
519 | -21%
Rebuilt pK-8 at Terrace Hills
Collins/Newman and Terrace Hills combine to
create a modern pK-8 campus

1094 | 73%
795 | 55%
600 | -25%

32

1098 | 63%
695 | 51%
560 | -19%

KEY
Program Capacity | Current Utilization
Current Enrollment | Proj. Utilization
Proj. Enrollment
| +/- % Enroll Change

1308 | 62%
808 | 55%
721 | -11%

Facilities Master Plan


Planning Area C.M.1

33

Facilities Master Plan


Middle Schools

34

Facilities
Master
Plan
Planning
Area
A.E.1
RECOMMENDATIONS FROM OPTIONS
Boundary Change
Roberts to Bond and Herrera
Herrera and Guerrero to balance
enrollments (students east of I-10 to
Guerrero)

Campus Reconstruction
None
Kohlberg, Lundy, Polk and Tippin
remain unaffected in short term
planning horizon

Planning Area A.E.1

Lundy
Tippin
751 | 76% 963 | 78%
573 | 67% 749 | 73%
502 | -12% 706 | -6%
650 | 98%
636 | 84%
548 | -14%
609 | 86%
525 | 78%
475 |-10%
Boundary Change
Herrera and Guerrero to balance
enrollments (same as before Herrera)

676 | 64%
433 | 53%
359 | -17%
649 | 80%
519 | 73%
472 | -9%
Close Roberts Split Boundary
South of Thorn to K-8
North of Thorn to Herrera

35

KEY
Program Capacity | Current Utilization
Current Enrollment | Proj. Utilization
Proj. Enrollment
| +/- % Enroll Change

763 | 80%
607 | 65%
494 | -19%

615 | 101%
621 | 70%
428 | -31%

Facilities Master Plan


Planning Area A.E.1

36

Facilities
Master
Plan
Planning
Area
A.E.2
RECOMMENDATIONS FROM OPTIONS
Boundary Change
Green to Morehead for 100% feeder to
Coronado

Planning Area A.E.2


763 | 80%
607 | 65%
494 | -19%

388 | 114%
442 | 84%
324 | -27%

Campus Reconstruction
Option to Consider creating a modern
pK-8 Campus at Zach White
Putnam, Green, Western Hills, Rivera,
Johnson remain unaffected in short
term planning horizon

37

615 | 101%
621 | 70%
428 | -31%

562 | 83%
465 | 79%
446 | -4%
656 | 68%
447 | 69%
386 | -14%
Convert Zach White to pK-8
1,200 Student Capacity
100% Feeder to Coronado

KEY
Program Capacity | Current Utilization
Current Enrollment | Proj. Utilization
Proj. Enrollment
| +/- % Enroll Change

624 | 84%
523 | 70%
436 | -17%
Feeder Pattern Alignment
All of Green to Morehead
to Coronado

695 | 75%
523 | 59%
411 | -21%

636 | 64%
407 | 54%
344 | -15%

Facilities Master Plan


Planning Area A.E.2

38

Facilities
Master
Plan
Planning
Area
A.E.3
RECOMMENDATIONS FROM OPTIONS
Boundary Change
Balance enrollments between Lamar
and Mesita as a result of Vilas closure
Campus Reconstruction
Rebuild Campus at Lamar (FCI/age
indicate rebuild)

Planning Area A.E.3


Boundary Changes
Balance enrollments between Mesita and Lamar

956 | 88%
842 | 65%
625 | -26%

Rebuild Lamar
Reconstruct to address facility condition

698 | 83%
577 | 76%
528 | -8%
Close Vilas
Repurpose OR Sell for Non-District Use

542
509
513

440 | 58%
251 | 50%
219 | -14%

39

KEY
Program Capacity | Current Utilization
Current Enrollment | Proj. Utilization
Proj. Enrollment
| +/- % Enroll Change

725
494
469

858
535
467

712
553
485

Facilities Master Plan


Planning Area A.E.3

40

Facilities
Master
Plan
Planning
Area
B.E.1
RECOMMENDATIONS FROM OPTIONS
Boundary Change
Beall to Douglass
DouglassHartAoy To Balance
Enrollments
Vilas south of I-10 to Aoy
Correct Alamo/Hart Attendance Zone
Campus Reconstruction
Rebuild Campus at Douglass (FCI/age
indicate rebuild)
Close Beall

Planning Area B.E.1


KEY
Program Capacity | Current Utilization
Current Enrollment | Proj. Utilization
Proj. Enrollment
| +/- % Enroll Change

698
577
528

Close Beall (after Douglass rebuild)


Repurpose or Sell for Non-District Use

725 | 68%
494 | 65%
469 | -5%

Rebuild Douglass
Consolidate Beall into Rebuilt Douglass

542 | 94%
509 | 95%
513 | 1%

440 | 58%
251 | 50%
219 | -14%
Boundary Change
Vilas South of I-10 to Aoy ES

41

Boundary Changes
DouglassHartAoy
To Balance Enrollments

858 | 62%
535 | 54%
467 | -13%

712 | 78%
553 | 68%
485 | -12%

Facilities Master Plan


Planning Area B.E.1

42

Facilities
Master
Plan
Planning
Area
B.E.2
RECOMMENDATIONS FROM OPTIONS
Boundary Change
Close Alta Vista; Students move to
MorenoCrockettColdwell to
Balance Enrollments
Southwest area of Moreno to Wiggs
feeder to create 100% feeder to El
Paso High
Campus Reconstruction
Current 20-Classroom Addition in
construction at Milam funded from
2007 Bond

Planning Area B.E.2

KEY
Program Capacity | Current Utilization
Current Enrollment | Proj. Utilization
Proj. Enrollment
| +/- % Enroll Change

567 | 89%
506 | 76%
433 | -14%
550 | 72%
394 | 59%
323 | -18%
Milam Classroom Addition
20 classrooms currently under construction

530 | 98%
522 | 93%
492 | -6%

733 | 81%
594 | 71%
524 | -12%
950 | 110%
561 | 89%
841 | +50%

634 | 83%
527 | 78%
492 | -7%

469 | 81%
378 | 69%
324 | -14%
Close Alta Vista
Alta VistaMorenoCrockettColdwell

43

Facilities Master Plan


Planning Area B.E.2

44

Facilities
Master
Plan
Planning
Area
B.E.3
Planning Area B.E.3
RECOMMENDATIONS FROM OPTIONS
Boundary Change
Rezone student from Zavala to Burleson
Campus Reconstruction
Rebuild Burleson to modernize learning
environments (rezone students from
Zavala to Burleson)

Close Zavala
Repurpose or Sell for non district use

359 | 82%
296 | 73%
261 | -12%

Rebuild Burleson
Rebuild to modernize learning environments

45

889 | 64%
556 | 61%
540 | -3%

546 | 90%
490 | 86%
471 | -4%
700 | 812%
564 | 78%
545 | -3%

KEY
Program Capacity | Current Utilization
Current Enrollment | Proj. Utilization
Proj. Enrollment
| +/- % Enroll Change

Facilities Master Plan


Planning Area B.E.3

46

Facilities
Master
Plan
Planning
Area
B.E.4
RECOMMENDATIONS FROM OPTIONS

Planning Area B.E.4

Boundary Change
Bonham/MacArthur become single
attendance zone
Campus Reconstruction
Create modern pK-8 Campus at
Bonham (MacArthur)

922 | 82%
761 | 88%
813 | +7%
384 | 103%
512 | 107%
410 | -20%

Build New pK-8 at Bonham Site


Rebuild to modernize learning environments
and consolidate Bonham and MacArthur

394 | 81%
319 | 71%
279 | -13%

389 | 99%
383 | 105%
410 | +7%

47

KEY
Program Capacity | Current Utilization
Current Enrollment | Proj. Utilization
Proj. Enrollment
| +/- % Enroll Change

1184 | 60%
706 | 53%
625 | -11%

363 | 90%
325 | 80%
290 | -12%

Facilities Master Plan


Planning Area B.E.4

48

Facilities
Master
Plan
Planning
Area
C.E.1
RECOMMENDATIONS FROM OPTIONS

Planning Area C.E.1


498 | 112%
557 | 101%
503 | -10%

Boundary Change
Rezone Students from Travis to Burnet
after rebuild
Campus Reconstruction
Rebuild Burnet to accommodate Travis
Students
Close Travis

582 | 109%
633 | 102%
595 | -6%
Rebuild Burnet
Students from Travis rezoned to attend

Close Travis
Students move to New Burnet

KEY
Program Capacity | Current Utilization
Current Enrollment | Proj. Utilization
Proj. Enrollment
| +/- % Enroll Change
49

800 | 61%
485 | 49%
396 | -18%

336 | 99%
334 | 96%
323 | -3%
442 | 95%
421 | 95%
421 | 0%

607 | 118%
716 | 165%
1003 | +40%

Facilities Master Plan


Planning Area C.E.1

50

Facilities
Master
Plan
Planning
Area
C.E.2
RECOMMENDATIONS FROM OPTIONS

Planning Area C.E.2

Rebuild Dowell
650 Student Capacity with core for 800

Boundary Change
Rezone Students from Schuster to
Dowell
Campus Changes
Rebuild Dowell to accommodate
Schuster Students
Close Schuster

Close Schuster
Students move to New Dowell

340 | 84%
285 | 80%
271 | -5%
580 | 93%
541 | 79%
461 | -15%

688 | 80%
549 | 70%
480 | -13%

51

439 | 77%
340 | 66%
291 | -14%

KEY
Program Capacity | Current Utilization
Current Enrollment | Proj. Utilization
Proj. Enrollment
| +/- % Enroll Change

609 | 88%
535 | 74%
448 | -16%

589 | 92%
542 | 88%
520 | -4%

794 | 85%
672 | 76%
603 | -10%

Facilities Master Plan


Planning Area C.E.2

52

Facilities
Master
Plan
Planning
Area
C.E.3
RECOMMENDATIONS FROM OPTIONS
Boundary Changes
Rezone Students from Fannin to rebuilt
Bradley
Move Dowell to Magoffin Feeder
Pattern
Rezone Collins and Newman
attendance zones
Rezone Students from Tom Lea to
Barron to balance enrollments
Balance Barron, Bradley & Fannin
attendance zones
Campus Changes
Rebuild Bradley to accommodate
Fannin Students
Close Fannin
53

Planning Area C.E.3

Rezone Tom Lea


Students from Tom Lea rezoned to attend Barron

701 | 120%
843 | 140%
981 | +14%
659 | 78%
515 | 74%
488 | -5%

663 | 98%
649 | 103%
684 | +5%

393 | 99%
390 | 95%
372 | -5%

KEY
Program Capacity | Current Utilization
Current Enrollment | Proj. Utilization
Proj. Enrollment
| +/- % Enroll Change

Close Fannin
Students move to New Bradley

552 | 94%
519 | 82%
452 | -13%

596 | 92%
546 | 77%
459 | -16%

627 | 81%
507 | 63%
393 | -22%

Rebuild Collins/Newman/Terrace Hills as pK-8


Students from Travis rezoned to attend

Facilities Master Plan


Planning Area C.E.3

54