Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Task 1..............................................................................................................................................
I.
Projetc Defining................................................................................................................
Task 1
I. Draw the network diagram
For more details of Fencefall Ltds project network diagram, see in Appendix 1
II. Determining the timing of activities and the total float
1. The timing of activities
Similarly to Rory Burke (2003), Field and Keller in 2007 pointed out
that the timing of activities in project network diagram can be determined
by a forward pass and a backward pass, in which the starting or finishing
day of each activity can be identified.
a. Forward pass
A forward pass includes earliest start time (EST) and earliest finish
time (EFT) (Field & Keller, 2007). Earliest start time (EST) is defined as
the earliest date the activity can begin and earliest finish time (EFT) is
the earliest date the activity can end (Rickman, 2011, p.88). (See more
about explanation in Appendix 2a)
b. Backward pass
By doing backward pass through the network, it allows to determine
the latest start time (LST) and latest finish time (LFT) (Field & Keller,
2007).
Latest start time (LST) can be understood as the latest date the
activity can begin that still allow the project to be completed on time,
while latest finish time (LFT) is the latest date the activity can end that
still allow the project to be completed on time (Rickman, 2011, p.88).
(See more about explanation in Appendix 2b)
2. The total float
In 2003, Rory Burke gave the definition: Float is the measure of an
activitys flexibility, quantifying how many working days the activity can
be delays before it will extend the completion date of the project, or any
target finish dates.
However, it can be simplified as the difference between the latest
finish and the earliest finish (or latest start and earliest start) (Lester,
2013, p.144). The total float is determined by the formula:
Total float = latest start time (LST) earliest start time (EST)
Or Total float = latest finish time (LFT) earliest finish time (EFT)
Time of tasks is only as good as provided estimations, which probably does not fit
the real situation.
Significant node changes may cause critical path no longer valid.
It will become complicated if the project has more than one critical path.
Critical path and floats change, leading to the change in scheduling of personnel.
Focusing too much on network diagram may cause the project manager distracted
from other issues.
(For more explanation about network diagrams limitations, see more in
Appendix 4)
Words count: 628
Task 2
Introduction
Tennisright Limited is a SME company specialising in the supplying
groundwork equipment and materials for the construction of tennis courts.
At present, the company already has a storage facility and an office in
London, and is about on a project building another warehouse in
Sunderland. It is expected that the new storage facility, will get higher
revenue for the company and will create a new market. Being appointed
to the project manager, my responsibility is to prepare a report including
different aspects of the project, in order to follow up and to ensure the
project will be performed in the best possible manner with the least waste
of time and effort.
Main body
This report will be presented in the form of a basic project life cycle,
which was shown up by Weiss & Wysocki in 1994, and then updated by
Field & Keller in 2005 (see the model in Appendix 5). By applying to this
model, the project will be divided into 5 stages in order to identify and to
analyse relevant elements belonging to a project, such as processes or
administration.
I.
Project Defining
1. Project problem and opportunity
Technical: It can be seen clearly that there will be no serious problem in terms of
technology, resources or infrastructure needed to build a new storage facility in
Sunderland.
Legal: Building a new warehouse for the purposes storing holding the tennis court
materials and groundwork equipment is legal in Sunderland, and it must have
4. Stakeholders analysis
After determined the area that types of stakeholders belong to, a project
manager needs to adjust the interaction with each of them. In details:
Low power, low interest: These stakeholders could be Sunderland natives. Project
team needs to ensure that the activities of project have no negative impact on the
daily life of the natives and the local environment, so the team can ignore and
team need.
High interest, low power: They may be the team members at lower line or the
workforce. Normally, they directly do the activities and care about work
effectiveness, because of performance-related pay system. However, they all
follow the decisions made by the line of manager and have low power to the
7
II.
Project Planning
After the project is defined, the next phase is to give out a plan for
Tennisright Ltd in terms of project activities and estimated schedule, as
well as a resources and budget plan. Additionally, to make the plan of
resources and schedule easier to be estimated, the new warehouse of
Tennesright Ltd is assumed to be 200 meters square large.
Types of labour
Quantit
y
1
2
Project Manager
Administrator/Supervisor
Project team
Project team
1
5
3
4
5
6
7
8
s
Assistant
Architect
Technical engineer
Electrician
Security staff
Building worker
Project team
Outsource
Outsource
Outsource
Outsource
Outsource
3
1
3
2
3
15
5. Risk Management
Risk management is defined by Burke (2003) as the systematic
processes of identifying, analysing and responding to project risk trough
out the project life cycle.
There are many uncertainties that may be faced during progress of any
project, so a project manager needs to be well-prepared to be able to
identify and to deal with the risks. To manage the risk effectively, a
project manager of Tennisright Ltd can use the Tactical risk assessment
and management of Field and Keller:
Identifying Risks: Identify where the uncertainties come from, and the impact
they cause to the project, which may be prevented from achieving the goal.
Assessing Risks: Each risk is evaluated the probability of its happening and the
III.
Project Organising
10
After setting up a plan for the project, in order to organise the project
well and ensure tasks are fulfilled fluently, suitable leadership and
motivations need to be practiced effectively be the project manager.
Burke (2003) noted that: Leadership is about setting goals and
objectives and generating enthusiasm and motivation amongst the project
team, and stakeholders, to work towards those objectives. In the
situation of Tennisrights project, due to the fact that most of the
workforce are hired from outside the organisation for implementing a
project plan already set up by the project manager, so Consultative
Autocratic (discuss with individuals) seems to be the most appropriate
style. It means that the project manager discuss the problems in specific
jobs with the people executive in that jobs, then make the decision by his
own. It is a way to collect the useful ideas for references and make
employees feel more engaged to project and put more effort on
performance.
Besides leadership style, motivating people is also important when
project manager wants to push the team to work more effectively.
Building a new warehouse is a technical work, which is suitable to the
monetary reward. In 2009, Dan Pink dis a research in MIT University
about performance-related pay, and it gave the result that money is an
effective motivator for technical work, however it caused to the negative
effect to the work requiring cognitive skills. So that, incentive may be a
good motivator to encourage the labour perform better.
IV.
Project Execution
11
This phase is to implement the project plan created above. During the
progress of the project, team members need to keep information informed
to the project manager, so he can be able to follow up and to take control
over the project direction, ensuring it to follow the plan.
-
Time management: Each member should record the timing of each activity in a
timesheet, allowing the project manager to manage the time for completing each task.
Cost management: Refers to the process of identifying the expenses and costs of
V.
Project closing
Project closing can be considered as the confirmation that Tennisright
project has been completed with all activities fulfilled. The project
manager will hand over the project report to the business and
acknowledge the experiences can be learnt for the next project.
Conclusion
The project building a new warehouse in Sunderland of Tennisright Limited was
reported in form of a basic Product Life Cycle model, in which there are phases including
specific plan with activities and estimated schedule. Moreover, some techniques such as work
breakdown structure, project network diagram are used to emphasize the content and
12
importance of the plan. Also, leaderships and management techniques are practiced to lead
the team to effective performance and to control the uncertainties of the project.
Words count:1804
Appendix
Task 1: Fencefalls Project network diagram
1. The Network Diagram
13
Critical path
Non-critical path
14
15
3. The Gantt chart showing earliest date that the project can be
completed on
16
during the process (Springer, 2005). Therefore, to use this technique effectively, it is
necessary to not only consider the characteristics of the project, but also balance
between different aspects having impact on the process.
18
6.
19
20
21
Critical path
Non-critical path
22
Project manager
Unit cost
( per day)
145
Administrator/Supervisor
85
51
21,675
3
4
5
6
7
8
Assistant
Architect
Technical engineer
Electrician
Security staff
Building worker
Total ()
3
1
3
2
3
15
70
110
60
70
60
55
51
5
28
7
51
51
10,710
550
5,040
980
9,180
42,075
97,605
Quantity
Time
(days)
51
Total ()
7,395
No.
1
2
3
4
5
6
7
8
9
Construction
materials
Ventilation system
Wiring
Lights
Fire alarm
Shelves
Security system
Computer
Telephones
Total ()
Unit cost ()
1,000,000
10
650m
50
10 set
35
3
5
5
350
5
10
200
120
250
500
100
c.
Total ()
97,605
1,017,200
1,114,805
23
3,500
3,250
500
2,000
4,200
750
2,500
500
1,017,200
Risk
Chance
Impact
Weight
Response
category
Priority
Late design
10%
Avoid
Spoiled material
30%
Reduce
50%
Accept
Late transportation
40%
Transfer
Negative argument
40%
3.5
Reduce
Work accident
30%
Reduce
Materials stolen
30%
Reduce
24
Status
Review &
manage
Review &
manage
Not
managed
Review &
manage
Review &
manage
Review &
manage
Review &
manage
References
1. Burke, R. (2003) Project Mnagement, Planning and Control Techniques. John Wiley
and Sons.
2. Field, M., Keller, L. (2007) Project Management. Open University.
3. Lester, A. (2013) Project Management, Planning and Control. Butterworth
Heinemann.
4. Milosevic, D. (2003) Project Management Toolbox: Tools and Techniques for the
Practicing Project Manager. John Wiley and Sons.
5. Richard, L. (2002) Project Management Step-by-Step. AMACOM.
6. Richman, L. (2002) Project Management Step-by-Step. AMACOM.
7. Schwalbe, K. (2013) Information Technology Project Management. Cengage
Learning.
8. Springer, M. (2005) Project Management. Purdue University Press
9. Stelth, P. (2009) Projects Analysis through CPM (Critical Path Method). Isles
Internationale Universit (European Union)
10. Turner, R. (1993) Handbook of Project-Based Management. McGraw Hill.
25