Está en la página 1de 118

The Dow Chemical Company

May 2007 Progress Report


Tittabawassee River Reach D PCap
Geophysical Summary Report
Final Geotube Containment Facility Design
Drawings SPMD Study Summary

May 20,2007

Prepared by URS Corporation


Reach D Progress Report
Upper Tittabawassee River
The Dow Chemical Company
May 2007

This document represents the May 2007 Progress Report for the Reach D Pilot Correction
Project (PCAP).

During the period of April 20, 2007 through May 20, 2007, the following project activities have
taken place (item numbers refer to those outlined in the attached Gantt Chart):

Regulatory Submittals/Activities
ITEM 4: The geophysical contractor completed post-processing of data for the Reach D
Project site. A summary report provided by Tetra Tech is included as Attachment A.
ITEM 6/7: Results of chemistry testing on samples collected by ATS and their subcontractors
at several locations outside the flume sheet piling and from natural soils beneath the
anthropogenic Reach D deposit are included in Table 1.
MDEQ-WMD and URS staff discussed and came to an agreement on means to collect
additional data from natural soils beneath the Reach D anthropogenic deposit in the area
between the Railroad Bridge and the Dow Dam. These samples were obtained and results
are presented in Table 2. Data from original characterization work are included for reference
in Table 3. A description of results and a summary of findings are included as Attachment B.
ITEM 16: Pore water data collected from a temporary well screened within the impacted
sediment was summarized and submitted to the MDEQ-Water Bureau on April 30, 2007.
Initial dewatering pilot testing was completed. Laboratory testing was completed and results
were summarized and provided to the MDEQ-Water Bureau on May 8, 2007, for dewatering
pilot study water quality. These data are being used by the MDEQ-Water Bureau during its
review of the NPDES Permit modification request made by Dow.
ITEM 19: Development of the Semi-Permeable Membrane Device (SPMD) Study was
completed, with a summary of the proposed study included in this submittal;
ITEM 29: Dow submitted the Permit To Install to the MDEQ-Air Quality Division on May
3, 2007.
ITEM 32: The MDEQ approved the Permit To Install Construction Waiver on May 4, 2007.
ITEM 36: The Fugitive Dust Control Plan was submitted by Dow and approved by the
MDEQ during this reporting period.
ITEM 38: The Ambient Air Monitoring Program was near completion, due for submittal to
the MDEQ on May 21st.
ITEM 41: As part of mobilization activities, a Soil Erosion Permit for the project was
received from the City of Midland on April 26, 2007.

1 of 3
Pre-Construction Activities
Activities conducted during this period included the following:
ITEM 18: Receipt and acceptance of the dredging contractors Health and Safety Plan
(HASP);
ITEM 41: Initial mobilization activities included Dow contractor safety training and
orientation; and the ordering and delivery of sheet piling and HDPE pipe
ITEM 42: Some site preparation activities began under the auspices of the Permit To Install
Construction Waiver. These activities included the initiation of HDPE dredge line fusion on
May 10, 2007.
Test piles were driven on May 3rd and 4th to support the final sheet piling design. It is
noteworthy that as part of this design process, two subsurface water pipelines (30” and 36”
diameter) were identified in Reach D. This discovery has instigated a substantial amount of
unforeseen work that will be necessary to properly design the sheet piling system. This work
includes additional excavations, underwater inspections by divers, pipeline isolation
requirements, and contingency plan development.
Final design of the Geotube containment facility was complete. Final drawings are included
in this submittal for MDEQ review.
Dow received approval from the MDEQ on May 7th to begin construction of the Geotube
Containment Facility. Mobilization by the construction contractor began shortly thereafter,
with construction due to begin before the end of this reporting period.
Equipment for installation of the temporary sheet piling also began during this reporting
period, with construction also projected to begin before the end of this reporting period. Site
preparation construction activities are contingent on weather and ground conditions.

Items to Be Completed In the Next 30 Days


Dow anticipates submitting the Land and Water Management Permit Modification request.
From a construction perspective, Dow hopes to have construction completed on the HDPE
dredge line (with integrity testing), construction of the temporary sheet piling should be
complete, and construction of the Containment Facility is expected to be ongoing.
Follow-up sampling will be completed outside the 1939 flume sheet piling to confirm
preliminary findings.
In addition to the above activities, Dow is proposing a study to monitor chemical residues in the
Tittabawassee River using semi-permeable membrane devices (SPMDs). When placed in an
aquatic environment, SPMDs passively accumulate hydrophobic organic compounds, such as
polychlorinated dibenzo-p-dioxins and dibenzofurans (PCDDs/PCDFs), polychlorinated
benzenes, and other hydrophobic chemicals. Contaminants are passively accumulated in the
SPMDs in a manner similar to their bioconcentration in fish lipid, however the SPMDs provide
significant advantages over caged fish.

2 of 3
The objective of this study is to examine the time-integrated presence of selected chlorinated
organic chemicals in the water of the Tittabawassee River as measured by uptake in SPMDs.
The specific Tittabawassee River site location targeted for this monitoring study will be
upstream and downstream of Reach D, located near the Dow Dam. A summary of the proposed
study is presented as Attachment D.

Because this monitoring project is focused on gathering background river data on selected
chemicals, and sediment dredging and removal is scheduled to begin in mid-July 2007, this study
must be initiated no later than early June, contingent on the issuance of all necessary permits.

3 of 3
Attachment A

Upper Tittabawassee River


Hydrographic and Geophysical Survey
Reach D

By Tetra Tech
Upper Tittabawassee River
Hydrographic and Geophysical Survey
Reach D

Survey Report
May 7, 2007

Prepared by:
Tetra Tech EC, Inc.
19803 North Creek Parkway
Bothell, WA 98011
(425) 482 7600

Reach D Survey Report


Table of Contents

1 Overview................................................................................................................................ 1-1
2 System Setup.......................................................................................................................... 2-1
2.1 Interconnections........................................................................................................... 2-1
2.2 Device Offsets.............................................................................................................. 2-3
2.2.1 Hypack/Hysweep Offsets.................................................................................. 2-3
2.3 Sonar Mount................................................................................................................. 2-3
2.4 Geodesy Settings.......................................................................................................... 2-5
2.5 GPS Reference Station................................................................................................. 2-6
3 Bathymetry Results................................................................................................................ 3-1
4 Sub-Bottom Profile Results ................................................................................................... 4-1

List of Figures

Figure 2-1 - 8125 Multibeam Survey System.............................................................................. 2-2


Figure 2-2 - Multibeam Sonar on Side Mount............................................................................. 2-4
Figure 2-3 - SeaBat 8125, C3D Sidescan and SB-424 on TtEC Jet boat .................................... 2-5
Figure 3-1 - Tittabawassee River Reach D Bathymetry – April 2007......................................... 3-2
Figure 3-2 - Sediment Bedforms in Main Channel...................................................................... 3-3
Figure 3-3 - Scour Above South Pipe Bridge Support ................................................................ 3-3
Figure 4-1 - Edgetech SB-216 Towfish mount used for data collection in Reach D ................. 4-2
Figure 4-2 - Edgetech SB-424 data collected .............................................................................. 4-3
Figure 4-3 - SB-216 Subbottom Data .......................................................................................... 4-4
Figure 4-4 - Tittabawassee River Reach D Example Sub-bottom Profile ................................... 4-5

List of Tables

Table 1-1 - Survey Team ............................................................................................................. 1-1


Table 2-1 - Survey Equipment..................................................................................................... 2-1
Table 2-2 - Communications Settings.......................................................................................... 2-3
Table 2-3 - Sensor Offsets (feet).................................................................................................. 2-3
Table 2-4 - Survey Geodesy Settings........................................................................................... 2-5
Table 2-5 - OPUS and NGS Control............................................................................................ 2-6
Table 2-6 - Overlook Park (OL-001) OPUS Point QC Checks ................................................... 2-7

Reach D Survey Report Page iii


1 Overview
The following document describes a survey which was conducted for Ann Arbor Technical
Services (ATS), Ann Arbor, MI, by Tetra Tech EC, Inc (TtEC), in April, 2007, under contract
32907. The primary survey equipment included a multibeam sonar system, sub-bottom profilers
(SBP), sidescan sonar, and associated vessel navigation and attitude measurement equipment.
These systems were used to map site bathymetry and characterize the river bottom and
subbottom conditions to support sediment studies and potential remediation actions. Table 1-1
lists the personnel and their roles in the survey.

Table 1-1 - Survey Team


Name Project Role
Robert Feldpausch Project Manager/Senior Hydrographer
Richard Funk Senior Geophysicist
Burton Bridge Senior Hydrographer/Programmer
David Humes Hydrographer/RTK GPS Technician
Derek Oklejewicz RTK GPS/Subbottom Technician
Lou Schwartz Survey Vessel Captain

Reach D Survey Report Page 1-1


2 System Setup
The survey systems were installed on a 21 foot jet boat owned by TtEC. The equipment used for
the survey is shown in Table 2-1. Data sheets for the main survey systems are included in
Appendix C.

Table 2-1 - Survey Equipment


Sensor Type Manufacturer/Model
Multibeam Sonar RESON SeaBat 8125
Motion Sensor Applanix WaveMaster
Heading Applanix WaveMaster
Position Leica 1230 RTK GPS/ Applanix WaveMaster
Sub-bottom Profiler Edgetech 3100 w/SB-424 and SB-216 towfish
Sidescan Sonar Benthos C3D
Sound Speed Profilers Seabird SBE-19 and MicroCat

Data collection and navigation software, for the bathymetry and sidescan surveys, was
Hypack®/Hysweep®. The SBP data were collected using Edgetech 3100-P hardware and
Discover software v3.42.

Software settings for bathymetry data acquisition include the serial I/O configuration and sensor
offsets in Hypack, and Hypack Navigation device offsets in the HySweep hardware
configuration.

2.1 Interconnections

Figure 2-1 shows the data flow and communications setup for the devices which make up the
survey system. Table 2-2 lists the settings for each of the data communication links.

Reach D Survey Report Page 2-1


Figure 2-1 - 8125 Multibeam Survey System

Reach D Survey Report Page 2-2


Table 2-2 - Communications Settings
Device Communications link Settings
8125 SeaBat Network imagery data out Local IP 192.168.0.41
Remote IP 192.168.0.50
UDP base port 1032
8125 SeaBat UTC time sync in COM 1 – 9600, N, 8, 1
WaveMaster TSS1 roll, pitch, heave out 19200, N, 8, 1, 50 Hz update
motion
WaveMaster NMEA HDT heading 19200, N, 8, 1, 1 Hz update
heading
Leica position NMEA GGA position 19200, N, 8, 1, 10 Hz update
Leica time NMEA ZDA time 19200, N, 8, 1, 1 Hz update

2.2 Device Offsets

Device offsets are precisely defined for the multibeam sonar, attitude sensor and GPS antenna, so
that the Hypack/HySweep acquisition software can accurately convert the input sonar and
support sensor data into XYZ soundings on the earth.

2.2.1 Hypack/Hysweep Offsets

The following offsets, in feet, were used for the Hypack and HySweep sensors:

Table 2-3 - Sensor Offsets (feet)


Sensor Across Along Vertical
SeaBat 8125 4.49 -4.00 1.67
Motion Sensor (WaveMaster) 0.00 0.00 1.10
Hypack Navigation (Leica RTK antenna) 0.00 0.49 -6.49
Edgetech SB-424/216 towfish bow mount -1.4 12.6 -0.40
Edgetech SB-424 towfish stbd side mount 6.42 -0.50 -0.40

2.3 Sonar Mount

The sonar head was mounted to the vessel using a side mount pole, as shown in Figure 2-2. The
mount is rigidly attached to the side of the vessel. The sidescan system was mounted on a bow
mount, shown in Figure 2-3. This figure also shows the subbottom profiler towfish, which was
suspended from a pole mounted on the port bow.

Reach D Survey Report Page 2-3


Figure 2-2 - Multibeam Sonar on Side Mount

Reach D Survey Report Page 2-4


Figure 2-3 - SeaBat 8125, C3D Sidescan and SB-424 on TtEC Jet boat

2.4 Geodesy Settings

The geodesy settings shown in Table 2-4 were used for the project.

Table 2-4 - Survey Geodesy Settings


Parameter Setting
Grids State Plane NAD-83
Zone MI-2113 Michigan South
Distance Unit International Feet
Depth Unit International Feet
Ellipsoid NAD-83
Elevation NAVD-88

Reach D Survey Report Page 2-5


2.5 GPS Reference Station

At the time of the mobilization, the only pre-defined high quality survey control point in the area
was the National Geodetic Survey (NGS) FREELAND (PID OK0006) Primary Airport Control
Station located at the Tri-City International Airport. The NGS Data Sheet for this control is
provided in Appendix A.

Since no national or state agency control points were available in locations suitable for setting up
a RTK base station, the NGS Online Positioning User Service (OPUS) was used to establish
geodetic control points. Wade-Trim, a local survey company, provided two locations where they
had previously determined coordinates using RTK GPS. An RTK capable GPS was set up over
the points for a period of approximately 2 hours, throughout this period data were recorded. The
data were then transferred to NGS OPUS via the internet for processing. Based on this data NGS
OPUS provided the reports included in Appendix A, which were used for Reach D control.
Additional OPUS points were established for quality control (QC) purposes.

Table 2-5 presents the NGS control and OPUS points that were utilized and established.

Table 2-5 - OPUS and NGS Control


TtEC NAVD88
OPUS/NGS Easting Northing Elevation
Point ID Location (intl. ft) (intl. ft) (intl. ft)
OL-001 Overlook Park 13155390.928 761695.254 641.939
Bayliss Bayliss Street 13161664.873 768808.503 628.281
Munic-001 Gordinville St. 13168800.639 754254.256 618.278
Bridge
Freeland - PID MBS Airport 13196592.800 737331.583 667.854
OK00006

Reach D Survey Report Page 2-6


All OPUS points were subsequently checked with an RTK GPS rover system receiving
corrections from the Michigan Department of Transportation (MDOT) Continuously Operating
Reference Station (CORS) system. The overall system of reference stations, processing center
and communications links is referred to as the Michigan Spatial Reference Network (MSRN).
Table 2-6 shows the results of the QC checks performed on the Overlook Park OPUS point used
as the location for the base station.

Table 2-6 - Overlook Park (OL-001) OPUS Point QC Checks

Easting Northing Elevation


Correction/ Results Results Results Date
Tested by Difference (intl. ft) (intl. ft) (intl. ft) Performed
TtEC MSRN 13155390.932 761695.235 641.900 4/5/2007
DIFF 0.004 -0.019 -0.039
Wade-Trim MSRN 13155390.940 761695.264 641.848 4/3/2007
DIFF 0.012 0.010 -0.091
TtEC MSRN 13155390.874 761695.230 641.800 4/12/2007
DIFF -0.054 -0.024 -0.139

Reach D Survey Report Page 2-7


3 Bathymetry Results
The results from the multibeam bathymetry survey are shown in Figure 3-1 and in Appendix B.
The sonar used for the survey was a RESON SeaBat 8125, which provides a 1 degree beam
along track and a 0.5 across track beam at nadir. This system provides extremely high resolution
data which, when used in conjunction with comparable accuracy motion, heading and position
sensors, can show very fine detail in the morphology of the bottom and in the structure of man-
made objects, such as the sheetpile walls in the reach.

Several significant features are visible in the bathymetry in Reach D.

a. There appears to be a pipeline or similar structure crossing the river at approximately


station 52+75.
b. The high energy sections of the river channel have sediment waves with heights of up to
approximately 1 foot, as shown in Figure 3-2. Lower energy areas have correspondingly
less vertical structure. This indicates that the sediment heights may change significantly
over time.
c. The water flow has induced scour (i.e. sediment erosion) of approximately 3 to 4 ft
around the center channel supports for the Dow bridges within Reach D, as shown in
Figure 3-3.
d. The intake basin shows some ripple in the bottom that is the result of data artifacts.
These ripples are on the order of 0.05 to 0.15 feet and are most likely induced by the
motion sensor. While these small effects are within the heave measurement (high
frequency vertical displacements) accuracy specifications, the visualization software and
the data resolution make them more apparent.

Reach D Survey Report Page 3-1


Figure 3-1 - Tittabawassee River Reach D Bathymetry – April 2007

Reach D Survey Report Page 3-2


Figure 3-2 - Sediment Bedforms in Main Channel

Figure 3-3 - Scour Above South Pipe Bridge Support

Reach D Survey Report Page 3-3


4 Sub-Bottom Profile Results
An Edgetech 3100-P portable sub-bottom profiler, with swept frequencies, from 4 to 24 kHz,
transducer, was run concurrently with the multibeam sonar. This system operates at a low
frequency capable of penetrating bottom sediment and returning data that provides information
related to manmade and/or geologic structures on or underlying the river bottom. The depth to
which the system will operate and provide data is a function of the sonar frequency and the
characteristics of the material in the sub-bottom.

The 3100-P system consists of a towfish with in-water transducers and hydrophone receivers and
a shipboard processing system that received digital data from the towfish. For this project the
SB-424 towfish was suspended in a fixed position just forward of the bow along the port side of
the survey vessel (Figure 2-3) to enable data collection in very shallow water, as well as provide
the best possible positional data that fixed mounting offers. This same mount was adapted and
used for the SB-216 (Figure 4-1) during data collection on May 14. A small inflatable catamaran
was used to support the larger and heavier SB-216 towfish.

An acoustic pulse was generated by the transducers and acoustic reflections from the river sub-
bottom were received by the hydrophones. Data were transmitted via cable from the towfish to
the shipboard processing system workstation running Edgetech’s Discover software. The
processing system logged the return pulse signals and processed the data into time-based cross
sections of the acoustic response of the sub-bottom. By inputting the speed of sound measured at
the site (as determined with a Seabird SBE-19, 1427 ft/sec used) the time sections were
converted into pseudo-depth sections. Data were displayed as pseudo-depth cross sections of
acoustic response with time on a computer screen and logged to computer hard drive and then
transferred and archived to external data storage for permanent storage and later post-processing.

Figure 4-2 shows the only data collected behind the sheet pile wall to show any structure
(collected April 6th). Approximately three layers are discernable to a maximum depth of about
2.5 ft below the bottom. These layers were not compared to core data, but at 2.5 feet below the
bottom, it is not believed that the data extends to the ‘native’ material below the sediment
deposited in the flume. The bottom layer appears to have a gravel component while the
overlying sediment appears to be soft, fine grained material.

Data was collected with the more powerful, and lower frequency SB-216 on May 14th within the
flume area in Reach D. The results were no better than with the SB-424. The one file that spans
the largest area within the flume is presented in Figure 4-3. The May 14th SB-216 data were
colleted at approximately the same river stage as during the April 6th SB-424 data collection.

Figure 4-4 shows a representative sample of the SBP data collected during the survey outside of
the flume area. This survey line was in the main river channel and shows a clearly defined layer
below the existing river bottom. The blue surface is the under side of the digital terrain model
created from the bathymetry (within the IVS Fledermaus software). Data from within the water
intake basin does not show this layering.

Reach D Survey Report Page 4-1


Figure 4-1 - Edgetech SB-216 Towfish mount used for data collection in Reach D

Reach D Survey Report Page 4-2


Figure 4-2 - Edgetech SB-424 data collected

Reach D Survey Report Page 4-3


Figure 4-3 - SB-216 Subbottom Data

Reach D Survey Report Page 4-4


Figure 4-4 - Tittabawassee River Reach D Example Sub-bottom Profile

Reach D Survey Report Page 4-5


Appendix A. NGS Data Sheets / OPUS Solution Reports
NGS Freeland Control Point

The NGS Data Sheet. See file dsdata.txt for more information about the
datasheet. DATABASE = Sybase ,PROGRAM = datasheet, VERSION = 7.42
1 National Geodetic Survey, Retrieval Date = APRIL 5, 2007
OK0006
***********************************************************************
OK0006 FBN - This is a Federal Base Network Control Station.
OK0006 PACS - This is a Primary Airport Control Station.
OK0006 DESIGNATION - FREELAND
OK0006 PID - OK0006
OK0006 STATE/COUNTY- MI/SAGINAW
OK0006 USGS QUAD - AUBURN (1973)
OK0006
OK0006 *CURRENT SURVEY CONTROL
OK0006 ___________________________________________________________________
OK0006* NAD 83(1994)- 43 31 22.32418(N) 084 05 26.01391(W) ADJUSTED
OK0006* NAVD 88 - 203.553 (meters) 667.82 (feet) ADJUSTED
OK0006 ___________________________________________________________________
OK0006 X - 476,921.563 (meters) COMP
OK0006 Y - -4,607,649.372 (meters) COMP
OK0006 Z - 4,369,920.959 (meters) COMP
OK0006 LAPLACE CORR- -2.32 (seconds) DEFLEC99
OK0006 ELLIP HEIGHT- 169.32 (meters) (06/11/02) GPS OBS
OK0006 GEOID HEIGHT- -34.24 (meters) GEOID03
OK0006 DYNAMIC HT - 203.512 (meters) 667.69 (feet) COMP
OK0006 MODELED GRAV- 980,414.7 (mgal) NAVD 88
OK0006 OBS GRAVITY - 980,412.0 (mgal) GRAV_OBS
OK0006
OK0006 HORZ ORDER - A
OK0006 VERT ORDER - SECOND CLASS 0
OK0006 ELLP ORDER - FOURTH CLASS I
OK0006
OK0006.This mark is at Tri City Intl Airport (MBS)
OK0006
OK0006.The horizontal coordinates were established by GPS observations
OK0006.and adjusted by the National Geodetic Survey in July 1992..
OK0006
OK0006.The orthometric height was determined by differential leveling
OK0006.and adjusted by the National Geodetic Survey in June 1991..
OK0006
OK0006.The X, Y, and Z were computed from the position and the ellipsoidal
ht.
OK0006
OK0006.The Laplace correction was computed from DEFLEC99 derived
deflections.
OK0006
OK0006.The ellipsoidal height was determined by GPS observations
OK0006.and is referenced to NAD 83.
OK0006

Reach D Survey Report Page A-1


OK0006.The geoid height was determined by GEOID03.
OK0006
OK0006.The dynamic height is computed by dividing the NAVD 88
OK0006.geopotential number by the normal gravity value computed on the
OK0006.Geodetic Reference System of 1980 (GRS 80) ellipsoid at 45
OK0006.degrees latitude (g = 980.6199 gals.).
OK0006
OK0006.The modeled gravity was interpolated from observed gravity values.
OK0006.The observed gravity was obtained from relative gravimeter ties
OK0006.to the IGSN71 gravity network.
OK0006
OK0006; North East Units Scale Factor
Converg.
OK0006;SPC MI S - 224,738.686 4,022,321.472 MT 0.99996884 +0 11
16.4
OK0006;SPC MI S - 737,331.65 13,196,592.76 iFT 0.99996884 +0 11
16.4
OK0006;UTM 16 - 4,822,993.954 735,128.335 MT 1.00028009 +2 00
16.1
OK0006
OK0006! - Elev Factor x Scale Factor = Combined Factor
OK0006!SPC MI S - 0.99997345 x 0.99996884 = 0.99994229
OK0006!UTM 16 - 0.99997345 x 1.00028009 = 1.00025353
OK0006
OK0006: Primary Azimuth Mark Grid Az
OK0006:SPC MI S - APPOLD 067 32 14.2
OK0006:UTM 16 - APPOLD 065 43 14.5
OK0006
OK0006|---------------------------------------------------------------------
|
OK0006| PID Reference Object Distance Geod. Az
|
OK0006| dddmmss.s
|
OK0006| OJ1071 APPOLD APPROX.11.0 KM 0674330.6
|
OK0006| CH0217 FREELAND RM 1 07459
|
OK0006| CH0218 FREELAND RM 2 18113
|
OK0006| CH0216 FREELAND AZ MK 1823452.8
|
OK0006| OK0505 MIDLAND DOW CHEM N STACK APPROX.15.1 KM 3081227.0
|
OK0006|---------------------------------------------------------------------
|
OK0006
OK0006 SUPERSEDED SURVEY CONTROL
OK0006
OK0006 ELLIP H (07/24/97) 169.38 (m) GP( ) 2
1
OK0006 ELLIP H (07/31/92) 169.30 (m) GP( ) 1
1
OK0006 NAD 83(1986)- 43 31 22.31147(N) 084 05 26.03523(W) AD( ) 1

Reach D Survey Report Page A-2


OK0006 NAD 27 - 43 31 22.21629(N) 084 05 26.10915(W) AD( ) 1
OK0006 NAVD 88 (11/28/94) 203.55 (m) 667.8 (f) LEVELING 3
OK0006 NAVD 88 (09/30/91) 203.55 (m) 667.8 (f) LEVELING 3
OK0006 NGVD 29 (??/??/92) 203.732 (m) 668.41 (f) ADJ UNCH 2
0
OK0006
OK0006.Superseded values are not recommended for survey control.
OK0006.NGS no longer adjusts projects to the NAD 27 or NGVD 29 datums.
OK0006.See file dsdata.txt to determine how the superseded data were
derived.
OK0006
OK0006_U.S. NATIONAL GRID SPATIAL ADDRESS: 16TGP3512822994(NAD 83)
OK0006_MARKER: DS = TRIANGULATION STATION DISK
OK0006_SETTING: 7 = SET IN TOP OF CONCRETE MONUMENT
OK0006_SP_SET: CONCRETE POST
OK0006_STAMPING: FREELAND 1932
OK0006_MARK LOGO: CGS
OK0006_PROJECTION: RECESSED 15 CENTIMETERS
OK0006_MAGNETIC: N = NO MAGNETIC MATERIAL
OK0006_STABILITY: C = MAY HOLD, BUT OF TYPE COMMONLY SUBJECT TO
OK0006+STABILITY: SURFACE MOTION
OK0006_SATELLITE: THE SITE LOCATION WAS REPORTED AS SUITABLE FOR
OK0006+SATELLITE: SATELLITE OBSERVATIONS - May 30, 2004
OK0006
OK0006 HISTORY - Date Condition Report By
OK0006 HISTORY - 1932 MONUMENTED CGS
OK0006 HISTORY - 1948 SEE DESCRIPTION CGS
OK0006 HISTORY - 1955 SEE DESCRIPTION CGS
OK0006 HISTORY - 1957 SEE DESCRIPTION CGS
OK0006 HISTORY - 1958 SEE DESCRIPTION USGS
OK0006 HISTORY - 1966 GOOD NGS
OK0006 HISTORY - 1969 SEE DESCRIPTION CGS
OK0006 HISTORY - 1976 GOOD NGS
OK0006 HISTORY - 1980 GOOD MIDH
OK0006 HISTORY - 1987 GOOD NGS
OK0006 HISTORY - 19891023 GOOD NGS
OK0006 HISTORY - 19900426 GOOD NGS
OK0006 HISTORY - 19910108 GOOD LOCENG
OK0006 HISTORY - 19910108 GOOD LOCENG
OK0006 HISTORY - 19910625 GOOD NGS
OK0006 HISTORY - 19931004 GOOD NGS
OK0006 HISTORY - 19940512 GOOD NGS
OK0006 HISTORY - 19960507 GOOD MIDT
OK0006 HISTORY - 20010426 GOOD MIDT
OK0006 HISTORY - 20011203 GOOD NGS
OK0006 HISTORY - 20040511 GOOD INDIV
OK0006 HISTORY - 20040530 GOOD WADTRI
OK0006
OK0006 STATION DESCRIPTION
OK0006
OK0006'DESCRIBED BY COAST AND GEODETIC SURVEY 1932 (HCW)
OK0006'ABOUT 9 MILES NORTHWEST
OK0006'OF SAGINAW, 1 MILE
OK0006'EAST OF FREELAND, IN NW 1/4 SEC. 23, T. 13 N., R. 3 E., ON LAND

Reach D Survey Report Page A-3


OK0006'OWNED BY MR. WILLIAM WAGNER, 1 FOOT
OK0006'EAST OF EAST RIGHT-OF-WAY FENCE OF NORTH-AND-SOUTH
OK0006'CONCRETE ROAD, 29 FEET EAST OF CENTER LINE OF ROAD, 35
OK0006'FEET NORTH OF NORTHEAST
OK0006'CORNER OF CONCRETE CULVERT, AND ABOUT 20 YARDS WEST OF LARGE
OK0006'UNPAINTED BARN. TO REACH
OK0006'FROM SAGINAW RIVER BRIDGE, GO WEST 9.2 MILES ON U.S. ROUTE 10 TO
OK0006'POINT WHERE U.S. ROUTE 10
OK0006'GOES TO LEFT AND CONCRETE ROAD GOES TO RIGHT (NORTH) (THIS
OK0006'POINT IS 4.1 MILES NORTHWEST OF
OK0006'JUNCTION OF U.S. ROUTE 10 AND ROUTE M-47),
OK0006'TURN NORTH ONTO CONCRETE ROAD, AND GO 2.6 MILES TO
OK0006'STATION SITE OPPOSITE BARN.
OK0006'SURFACE AND UNDERGROUND MARKS ARE STANDARD DISK STATION MARKS IN
OK0006'CONCRETE, NOTES 1A AND
OK0006'7A. UPPER MARK PROJECTS 4 INCHES. REFERENCE AND AZIMUTH MARKS
OK0006'ARE STANDARD REFERENCE MARKS IN
OK0006'CONCRETE, NOTE 11A. NO. 1 PROJECTS 6 INCHES,
OK0006'IS 44 FEET NORTH OF NORTHEAST CORNER OF
OK0006'ABOVE-MENTIONED BARN, 6 FEET WEST OF NORTHWEST
OK0006'CORNER OF SMALL SHED, AND 136.95 FEET FROM STATION IN
OK0006'AZIMUTH 254 DEG. 58 MIN. NO. 2
OK0006'PROJECTS 5 INCHES, IS IN EAST RIGHT-OF-WAY FENCE, 28 FEET EAST OF
OK0006'CENTER LINE OF ABOVE-MENTIONED
OK0006'CONCRETE ROAD, ABOUT 50 YARDS SOUTHWEST OF SOUTHWEST CORNER
OK0006'OF BARN, AND 158.51 FEET FROM
OK0006'STATION IN AZIMUTH 1 DEG. 13 MIN. AZIMUTH MARK PROJECTS
OK0006'5 INCHES, IS 27 FEET WEST OF CENTER LINE OF
OK0006'NORTH-AND-SOUTH CONCRETE ROAD, 3 FEET
OK0006'NORTH OF TELEPHONE POLE, 15 FEET NORTHWEST OF NORTHWEST CORNER
OK0006'OF CONCRETE CULVERT, AND
OK0006'APPROXIMATELY 0.35 MILE FROM STATION IN AZIMUTH 2 DEG. 34 MIN. 49
OK0006'SEC.
OK0006
OK0006 STATION RECOVERY (1948)
OK0006
OK0006'RECOVERY NOTE BY COAST AND GEODETIC SURVEY 1948 (WIB)
OK0006'STATION IN EXCELLENT CONDITION.
OK0006'RECOVERED AS
OK0006'DESCRIBED IN SPECILA PUBLICATION 214, EXCEPT
OK0006'FOR THE FOLLOWING-
OK0006'
OK0006'ADD TO DESCRIPTION - 17 FEET SE OF THE SE CORNER OF A CONCRETE
OK0006'CULVERT.
OK0006'
OK0006'DELETE FROM DESCRIPTION - UPPER MARK PROJECTS 4 INCHES.
OK0006'THIS MARK IS NOW
OK0006'ABOUT 2 INCHES BELOW THE SURFACE OF THE GROUND.
OK0006'
OK0006'R.M. 1 IS TILTED OUT OF POSITION AND THE DISK IS ALSO
OK0006'CRACKED IN TWO
OK0006'PIECES. ONE HALF IS STILL FIRMLY ATTACHED TO THE
OK0006'CONCRETE POST, THE OTHER HALF IS
OK0006'LOOSE AND WILL SOMEDAY BE REMOVED.

Reach D Survey Report Page A-4


OK0006'DELETE REFERENCE TO SMALL SHED.
OK0006'
OK0006'R.M.S 2 AND 3 ARE IN GOOD CONDITION. RECOVERED AS DESCRIBED.
OK0006
OK0006 STATION RECOVERY (1955)
OK0006
OK0006'RECOVERY NOTE BY COAST AND GEODETIC SURVEY 1955 (LWQ)
OK0006'THE STATION, REFERENCE MARKS, AND AZIMUTH MARK WERE
OK0006'RECOVERED. ONE
OK0006'HALF OF THE DISK OF REFERENCE MARK 1 IS MISSING,
OK0006'AND REFERENCE MARK 2 IS TILTED.
OK0006'THE STATION AND AZIMUTH MARK ARE
OK0006'IN GOOD CONDITION. THE DESCRIPTIONS ARE ADEQUATE.
OK0006
OK0006 STATION RECOVERY (1957)
OK0006
OK0006'RECOVERY NOTE BY COAST AND GEODETIC SURVEY 1957 (LFV)
OK0006'STATION AND REFERENCE MARKS RECOVERED AS DESCRIBED,
OK0006'EXCEPT FOR THE
OK0006'FOLLOWING-
OK0006'
OK0006'BARN, SHED, AND CONCRETE CULVERT MENTIONED IN ORIGINAL DESCRIPTION
OK0006'NO LONGER EXIST.
OK0006'
OK0006'STATION RECOVERED IN GOOD CONDITION, 29.1 FT. E OF THE CENTERLINE
OK0006'OF A N-S ROAD,
OK0006'21.5 FT. S-SW OF A POWER POLE, 17.3 FT. SE OF
OK0006'THE S END OF A CULVERT UNDER THE
OK0006'N-S ROAD, AND 3.0 FT. W OF A FENCE.
OK0006'MARK IS FLUSH WITH THE GROUND.
OK0006'
OK0006'AZIMUTH MARK COULD NOT BE RECOVERED AFTER A THOROUGH SEARCH
OK0006'OF THE AREA. MARK
OK0006'WAS PROBABLY DESTROYED WHEN CULVERT UNDER THE
OK0006'ROAD WAS CHANGED, AND AREA IN
OK0006'VICINITY OF MARK WAS GRADED DURING
OK0006'CONSTRUCTION OF TRI-CITY AIRPORT.
OK0006'
OK0006'REFERENCE MARK 1 IS 57.0 FT. NW OF A POWER POLE, 45.6 FT. W
OK0006'OF A FENCE CORNER,
OK0006'1.5 FT. S OF A FENCE. MARK PROJECTS ABOUT 6
OK0006'IN. AND APPEARS TO HAVE BEEN SLIGHTLY
OK0006'DISTURBED.
OK0006'
OK0006'REFERENCE MARK 2 IS 119.6 FT S-SE OF THE S END OF THE CONCRETE
OK0006'CULVERT UNDER THE
OK0006'N-S ROAD, AND 28.2 FT. E OF THE CENTERLINE
OK0006'OF THE N-S ROAD. MARK PROJECTS
OK0006'ABOUT 6 IN. AND APPEARS TO HAVE
OK0006'BEEN SLIGHTLY DISTURBED.
OK0006'
OK0006'TO REACH THE STATION FROM THE STOP LIGHT AT THE INTERSECTION
OK0006'OF MAIN (U.S.
OK0006'ROUTE 10), AND WASHINGTON STREETS IN FREELAND, GO

Reach D Survey Report Page A-5


OK0006'1.7 MI. E ON WASHINGTON TO
OK0006'T-ROAD (S), TURN RIGHT AND GO 0.1 MI.
OK0006'S TO THE STATION ON THE LEFT.
OK0006
OK0006 STATION RECOVERY (1958)
OK0006
OK0006'RECOVERY NOTE BY US GEOLOGICAL SURVEY 1958
OK0006'STATION RECOVERED IN GOOD CONDITION.
OK0006'
OK0006'THE STATION IS LOCATED 1-1/2 MILES EAST OF FREELAND, ABOUT 1/2 MILE
OK0006'SOUTH OF TRI-CITY
OK0006'AIRPORT, NEAR CORNER SECS. 14, 15, 22, AND 23, T 13 N, R 3 E, 640
OK0006'FEET SOUTH AND 29 FEET EAST OF
OK0006'T-ROAD SOUTH, 68 FEET SOUTH OF A ROAD NORTHEAST, 21 FEET SOUTH
OK0006'AND 5 FEET WEST OF A POWER POLE, IN
OK0006'CONCRETE POST, A STANDARD U.S.C. AND G.S. DIKS,
OK0006'STAMPED FREELAND 1932.
OK0006
OK0006 STATION RECOVERY (1966)
OK0006
OK0006'RECOVERY NOTE BY NATIONAL GEODETIC SURVEY 1966
OK0006'1 MI E FROM FREELAND.
OK0006'ABOUT 9 MILES NORTHWEST OF SAGINAW, 1 MILE EAST OF FREELAND
OK0006'AT THE SOUTHWEST EDGE OF THE TRI-CITY AIRPORT, 2 FEET WEST OF
OK0006'A RIGHT OF WAY FENCE, 29 FEET EAST OF THE CENTERLINE OF A
OK0006'CONCRETE ROAD, 35 FEET NORTH OF THE NORTHEAST CORNER OF A
OK0006'CONCRETE CULVERT, 17 FEET SOUTHEAST OF THE SOUTHEAST CORNER
OK0006'OF A CONCRETE CULVERT. A STANDARD TRIANGULATION DISK STAMPED
OK0006'FREELAND 1932 SET IN THE TOP OF A CONCRETE POST ABOUT TWO
OK0006'INCHES BELOW THE SURFACE OF THE GROUND.
OK0006
OK0006 STATION RECOVERY (1969)
OK0006
OK0006'RECOVERY NOTE BY COAST AND GEODETIC SURVEY 1969 (WTJ)
OK0006'STATION RECOVERED AS DESCRIBED BY USGS IN 1958. RMS AND AZIMUTH NOT
OK0006'SEARCHED FOR.
OK0006'
OK0006'AIRLINE DISTANCE AND DIRECTION FROM NEAREST TOWN- 1.5 MILES E. OF
OK0006'FREELAND
OK0006
OK0006 STATION RECOVERY (1976)
OK0006
OK0006'RECOVERY NOTE BY NATIONAL GEODETIC SURVEY 1976 (RPD)
OK0006'RECOVERED IN GOOD CONDITION AS DESCRIBED.
OK0006'
OK0006'AIRLINE DISTANCE AND DIRECTION FROM NEAREST TOWN--1.0 MILE EAST OF
OK0006'FREELAND.
OK0006
OK0006 STATION RECOVERY (1980)
OK0006
OK0006'RECOVERY NOTE BY MI DEPT OF HIGHWAYS 1980 (GK)
OK0006'THE STATION WAS FOUND IN GOOD CONDITION.
OK0006'
OK0006'THE REFERENCE MARKS WERE FOUND IN GOOD CONDITION.

Reach D Survey Report Page A-6


OK0006
OK0006 STATION RECOVERY (1987)
OK0006
OK0006'RECOVERY NOTE BY NATIONAL GEODETIC SURVEY 1987 (RLR)
OK0006'STATION IS LOCATED ABOUT 9 MILES NORTHWEST OF SAGINAW,
OK0006'4 MILES SOUTHEAST OF MIDLAND AND 1 MILE EAST OF FREELAND
OK0006'AT THE SOUTHWEST EDGE OF THE TRI-CITY AIRPORT AND INSIDE
OK0006'A CHAIN-LINK FENCE AT THE JUNCTION OF A SERVICE ROAD AND THE
OK0006'OLD EXTENTION OF GARFIELD ROAD. IT IS A STANDARD NGS
OK0006'TRIANGULATION DISK SET INTO THE TOP OF A SQUARE CONCRETE
OK0006'MONUMENT ABOUT 6-INCHES BELOW THE SURFACE. LOCATED 10.66
OK0006'M., 35.0 FEET NORTH-NORTHEAST OF THE NORTH END OF CONCRETE
OK0006'HEADWALL OF A BOX CULVERT UNDER THE NORTH-SOUTH ROAD,
OK0006'9.144 M., 30.0 FEET EAST OF THE CENTER OF THE PAVED ROAD,
OK0006'6.096 M., 20.0 FEET SOUTH OF THE EAST END OF A CONCRETE
OK0006'CULVERT UNDER THE NORTH-SOUTH ROAD, 2.896 M., 9.5 FEET
OK0006'NORTH OF A UTILITY POLE, 0.610 M., 2.0 FEET SOUTH
OK0006'-SOUTHWEST AND 0.610 M., 2.0 FEET NORTH-NORTHEAST FROM TWO
OK0006'CARSONITE WITNESS POSTS.
OK0006'
OK0006'TO VISIT THIS STATION YOU WILL NEED TO CHECK WITH
OK0006'AIRPORT SECURITY FOR ESCORT ACROSS AIRPORT. PHONE
OK0006'(517) 695-5558, FIRE DEPARTMENT AND SECURITY OFFICE.
OK0006'
OK0006'RECOVERED AS DESCRIBED.
OK0006
OK0006 STATION RECOVERY (1989)
OK0006
OK0006'RECOVERY NOTE BY NATIONAL GEODETIC SURVEY 1989
OK0006'THE STATION IS LOCATED ABOUT 14.5 KM (9.00 MI) NORTHWEST OF SAGINAW,
OK0006'2.4 KM (1.50 MI) EAST OF FREELAND AND ON THE GROUNDS OF THE TRI-CITY
OK0006'AIRPORT. CALL AHEAD FOR SECURITY ESCORT, PHONE (517)695-5558.
OK0006'TO REACH THE STATION FROM THE JUNCTION OF COUNTY ROUTE 47 AND
OK0006'WASHINGTON ROAD IN THE TOWN OF FREELAND, GO EAST ON WASHINGTON ROAD,
OK0006'WHICH BECOMES FREELAND ROAD, FOR 2.2 KM (1.35 MI) TO A Y-FORK. TURN
OK0006'LEFT AND GO NORTH ON GARFIELD ROAD FOR 1.05 KM (0.65 MI) TO THE MAIN
OK0006'ENTRANCE ROAD TO TRI-CITY AIRPORT. TURN RIGHT AND GO SOUTHEASTERLY
OK0006'FOR 0.55 KM (0.35 MI) TO A STOP SIGN. CONTINUE STRAIGHT AHEAD TO THE
OK0006'GENERAL AVIATION TERMINAL, FAA AND AIRPORT ADMINISTRATION BUILDING
FOR
OK0006'0.25 KM (0.15 MI) TO A SECURED GATE AT THE NORTH END OF THE BUILDING.
OK0006'PUSH BUZZER TO CALL SECURITY AND OPEN GATE. PASS THROUGH THE GATE
AND
OK0006'PROCEED ACROSS TAXIWAY ONTO SERVICE ROAD LEADING SOUTHWEST, SOUTH AND
OK0006'SOUTHEAST FOR 1.55 KM (0.95 MI) TO A CROSSROAD, OLD EXTENTION OF
OK0006'GARFIELD ROAD AND THE STATION ON THE RIGHT.
OK0006'THE STATION IS A STANDARD CGS DISK SET IN THE TOP OF A 42 CM SQUARE
OK0006'CONCRETE MONUMENT RECESSED 18 CM BELOW THE GROUND. LOCATED 10.67 M
OK0006'(35.0 FT) NORTH-NORTHEAST OF THE NORTH END OF HEADWALL OF A BOX
OK0006'CULVERT UNDER THE NORTH-SOUTH ROAD, 9.15 M (30.0 FT) EAST OF THE
OK0006'CENTER OF THE PAVED ROAD, 6.1 M (20.0 FT) SOUTH OF THE EAST END OF A
OK0006'CONCRETE CULVERT UNDER THE ROAD, 2.9 M (9.5 FT) NORTH OF A UTILITY
OK0006'POLE, 0.6 M (2.0 FT) SOUTH OF A CARSONITE WITNESS POST AND 0.6 M
OK0006'(2.0 FT) NORTH OF A CARSONITE WITNESS POST.

Reach D Survey Report Page A-7


OK0006'DESCRIBED BY R.L. RAMSEY, TYPED BY HJS.
OK0006
OK0006 STATION RECOVERY (1990)
OK0006
OK0006'RECOVERY NOTE BY NATIONAL GEODETIC SURVEY 1990
OK0006'RECOVERED IN GOOD CONDITION.
OK0006
OK0006 STATION RECOVERY (1991)
OK0006
OK0006'RECOVERY NOTE BY LOCAL ENGINEER (INDIVIDUAL OR FIRM) 1991 (NCC)
OK0006'RECOVERED AS DESCRIBED.
OK0006
OK0006 STATION RECOVERY (1991)
OK0006
OK0006'RECOVERY NOTE BY LOCAL ENGINEER (INDIVIDUAL OR FIRM) 1991 (NCC)
OK0006'FOUND IN GOOD CONDITION AS DESCRIBED.
OK0006
OK0006 STATION RECOVERY (1991)
OK0006
OK0006'RECOVERY NOTE BY NATIONAL GEODETIC SURVEY 1991
OK0006'THE STATION IS LOCATED ABOUT 14.5 KM (9.0 MI) NORTHWEST OF SAGINAW,
OK0006'2.4 KM (1.5 MI) EAST OF FREELAND AND ON THE GROUNDS OF THE TRI-CITY
OK0006'AIRPORT. CALL AHEAD FOR SECURITY ESCORT, PHONE (517)695-5558.
OK0006'TO REACH THE STATION FROM THE JUNCTION OF COUNTY ROUTE 47 AND
OK0006'WASHINGTON ROAD IN THE TOWN OF FREELAND, GO EAST ON WASHINGTON ROAD,
OK0006'WHICH BECOMES FREELAND ROAD, FOR 2.2 KM (1.4 MI) TO A Y-FORK. TURN
OK0006'LEFT AND GO NORTH ON GARFIELD ROAD FOR 1.05 KM (0.65 MI) TO THE MAIN
OK0006'ENTRANCE ROAD TO TRI-CITY AIRPORT. TURN RIGHT AND GO SOUTHEASTERLY
OK0006'FOR 0.55 KM (0.34 MI) TO A STOP SIGN. CONTINUE STRAIGHT AHEAD TO THE
OK0006'GENERAL AVIATION TERMINAL, FAA AND AIRPORT ADMINISTRATION BUILDING
OK0006'FOR 0.25 KM (0.16 MI) TO A SECURED GATE AT THE NORTH END OF THE
OK0006'BUILDING. PUSH BUZZER TO CALL SECURITY AND OPEN GATE. PASS THROUGH
OK0006'THE GATE AND PROCEED ACROSS TAXIWAY ONTO SERVICE ROAD LEADING
OK0006'SOUTHWEST, SOUTH AND SOUTHEAST FOR 1.55 KM (0.96 MI) TO A CROSSROAD,
OK0006'OLD EXTENTION OF GARFIELD ROAD AND THE STATION ON THE RIGHT.
OK0006'MONUMENT IS RECESSED 18 CM BELOW THE GROUND. LOCATED 10.67 M
OK0006'(35.01 FT) NORTH-NORTHEAST OF THE NORTH END OF HEADWALL OF A BOX
OK0006'CULVERT UNDER THE NORTH-SOUTH ROAD, 9.15 M (30.02 FT) EAST OF THE
OK0006'CENTER OF THE PAVED ROAD, 6.1 M (20.0 FT) SOUTH OF THE EAST END OF A
OK0006'CONCRETE CULVERT UNDER THE ROAD, 2.9 M (9.5 FT) NORTH OF A UTILITY
OK0006'POLE, 0.6 M (2.0 FT) SOUTH OF A CARSONITE WITNESS POST AND 0.6 M
OK0006'(2.0 FT) NORTH OF A CARSONITE WITNESS POST.
OK0006
OK0006 STATION RECOVERY (1993)
OK0006
OK0006'RECOVERY NOTE BY NATIONAL GEODETIC SURVEY 1993 (CLS)
OK0006'THE STATION IS LOCATED ABOUT 14.5 KM (9.01 MI) NORTHWEST OF SAGINAW,
OK0006'2.4 KM (1.49 MI) EAST OF FREELAND, AND ON THE GROUNDS OF THE TRI-CITY
OK0006'AIRPORT. CALL AHEAD FOR SECURITY ESCORT, PHONE (517) 695-5558.
OK0006'
OK0006'TO REACH FROM THE JUNCTION OF STATE ROUTE 47 AND WASHINGTON ROAD IN
OK0006'FREELAND, GO EAST ON WASHINGTON ROAD, WHICH BECOMES FREELAND ROAD,
FOR
OK0006'2.2 KM (1.37 MI) TO A Y-FORK. TURN LEFT, NORTH, ON GARFIELD ROAD FOR

Reach D Survey Report Page A-8


OK0006'1.05 KM (0.65 MI) TO THE MAIN ENTRANCE ROAD TO THE TRI-CITY AIRPORT.
OK0006'TURN RIGHT, SOUTHEASTERLY FOR 0.55 KM (0.34 MI) TO A STOP SIGN.
OK0006'CONTINUE AHEAD TO THE GENERAL AVIATION TERMINAL, FAA AND AIRPORT
OK0006'ADMINISTRATION BUILDING FOR 0.25 KM (0.16 MI) TO A SECURED GATE AT
THE
OK0006'NORTH END OF THE BUILDING. PUSH BUZZER TO CALL SECURITY AND OPEN
OK0006'GATE. PASS THROUGH THE GATE AND PROCEED ACROSS TAXIWAY ONTO SERVICE
OK0006'ROAD LEADING SOUTHWEST, SOUTH, AND SOUTHEAST FOR 1.55 KM (0.96 MI) TO
OK0006'A CROSSROAD, OLD EXTENSION OF GARFIELD ROAD AND THE STATION ON THE
OK0006'RIGHT.
OK0006'
OK0006'STATION MARK IS A TRIANGULATION STATION DISK SET IN THE TOP OF A
OK0006'SQUARE CONCRETE POST RECESSED 15 CM BELOW THE SURFACE. IT IS 10.7 M
OK0006'(35.10 FT) NORTH-NORTHEAST OF THE NORTH END OF HEADWALL OF A BOX
OK0006'CULVERT UNDER THE NORTH-SOUTH ROAD, 9.15 M (30.02 FT) EAST OF THE
OK0006'CENTER OF THE PAVEC ROAD, 6.1 M (20.01 FT) SOUTH OF THE EAST END OF A
OK0006'CONCRETE CULVERT UNDER THE ROAD, 2.9 M (9.51 FT) NORTH OF A UTILITY
OK0006'POLE, 0.6 M (1.97 FT) SOUTH OF A FIBERGLASS WITNESS POST, AND 0.76 M
OK0006'(2.49 FT) NORTH OF A FIBERGLASS WITNESS POST.
OK0006
OK0006 STATION RECOVERY (1994)
OK0006
OK0006'RECOVERY NOTE BY NATIONAL GEODETIC SURVEY 1994 (CFS)
OK0006'NOTE--ESCORT REQUIRED TO REACH STATION.
OK0006'
OK0006'STATION IS LOCATED ABOUT 16 KM (9.95 MI) NORTHWEST OF SAGINAW, AT THE
OK0006'SOUTHWEST END OF THE TRI-CITY INTERNATIONAL AIRPORT, ABOUT 300 M
OK0006'(984.2 FT) NORTHWEST OF THE JET FUEL FARM, 150 M (492.1 FT) NORTHEAST
OK0006'OF THE PERIMETER FENCE, AT AN OLD ROAD JUNCTION, NEAR THE NORTHEAST
OK0006'CORNER OF SECTION 23, T 13 N, R 3 E. OWNERSHIP--TRI-CITY AIRPORT,
OK0006'8500 GARFIELD ROAD, BOX P, FREELAND, MI 48623. AIRPORT MANAGER IS
OK0006'ELIZABETH OWEN, PHONE 517-695-5555.
OK0006'
OK0006'TO REACH FROM THE OVERPASS AT THE JUNCTION OF US HIGHWAY 10 AND
OK0006'GARFIELD ROAD (2 KM SOUTHWEST OF AUBURN), GO SOUTH ON GARFIELD ROAD
OK0006'FOR 7.47 KM (4.65 MI) TO THE AIRPORT ENTRANCE ROAD ON THE LEFT. TURN
OK0006'LEFT, EAST, ON ROAD FOR 0.43 KM (0.25 MI) TO A ROAD RIGHT. TURN
OK0006'RIGHT, SOUTHEAST, ON ROAD FOR 0.23 KM (0.15 MI) TO THE EXECUTIVE
OK0006'TERMINAL BUILDING AND THE ADMINISTRATIVE OFFICE AND SECURITY OFFICE.
OK0006'
OK0006'STATION MARK IS A DISK SET IN THE TOP OF A 30-CM ROUND CONCRETE POST
OK0006'15 CM RECESSED BELOW GROUND IN OPEN HOLE. IT IS 8.9 M (29.2 FT) EAST
OK0006'OF A ROAD CENTER, 2.7 M (8.9 FT) NORTH OF A UTILITY POLE, 10.7 M
(35.1
OK0006'FT) NORTH-NORTHEAST OF THE NORTH END OF A CONCRETE CULVERT HEADWALL,
OK0006'5.9 M (19.4 FT) SOUTH-SOUTHEAST OF THE TOP CENTER OF A CONCRETE PIPE
OK0006'CULVERT, 0.7 M (2.3 FT) SOUTH OF A FIBERGLASS WITNESS POST, 0.8 M
(2.6
OK0006'FT) NORTH OF A FIBERGLASS WITNESS POST, AND 23.8 M (78.1 FT)
OK0006'SOUTH-SOUTHEAST OF THE CENTER OF THE ROAD JUNCTION.
OK0006'
OK0006'DESCRIBED BY G.R. HEID.
OK0006
OK0006 STATION RECOVERY (1996)

Reach D Survey Report Page A-9


OK0006
OK0006'RECOVERY NOTE BY MICHIGAN DEPARTMENT OF TRANSPORTATION 1996 (JAS)
OK0006'RECOVERED AS DESCRIBED.
OK0006
OK0006 STATION RECOVERY (2001)
OK0006
OK0006'RECOVERY NOTE BY MICHIGAN DEPARTMENT OF TRANSPORTATION 2001 (BHS)
OK0006'STATION WAS RECOVERED ON 04-03-2001 BY MICHIGAN DEPARTMENT OF
OK0006'TRANSPORTATION, BAY REGION, (BHS) IN GOOD CONDITION. STATION IS
OK0006'USUABLE FOR G.P.S. THERE HAS BEEN A REQUEST FROM THE AIRPORT
OK0006'MANAGER THAT THIS STATION BE RELOCATED, DUE TO THE FREQUENT USE,
OK0006'AND THE FACT THAT AND AIRPORT EXCORT HAS TO TAKE PERSONNAL
OK0006'USING THIS STATION OUT TO THE SITE, AS YOU ARE NEAR THE RUNWAYS OF
OK0006'THE AIRPORT.
OK0006'
OK0006'TYPED BY RONALD L. RAMSEY, NGS GEODETIC ADVISOR - MICHIGAN.
OK0006'
OK0006
OK0006 STATION RECOVERY (2001)
OK0006
OK0006'RECOVERY NOTE BY NATIONAL GEODETIC SURVEY 2001 (DB)
OK0006'THIS REPORT WAS SUBMITTED BY THE US POWER SQUADRONS.
OK0006
OK0006 STATION RECOVERY (2004)
OK0006
OK0006'RECOVERY NOTE BY INDIVIDUAL CONTRIBUTORS 2004
OK0006'RECOVERED IN GOOD CONDITION.
OK0006
OK0006 STATION RECOVERY (2004)
OK0006
OK0006'RECOVERY NOTE BY WADE-TRIM INCORPORATED 2004 (DJR)
OK0006'DESCRIPTION IS ADEQUATE

*** retrieval complete.


Elapsed Time = 00:00:00

Reach D Survey Report Page A-10


Overlook Park Opus Point Report

FILE: 00010951.07o 000109691

9999 OPUS DISCLAIMER OPUS DISCLAIMER OPUS DISCLAIMER OPUS DISCLAIMER


9999
9999 Your data file spans less than 2 hours. OPUS guidelines require a
9999 minimum data span of 2 hours and strongly recommend 4 hours to achieve
9999 best accuracies. However, due to popular demand by users, OPUS will
9999 accept data spans less than 2 hours, but does not provide any
guarantee
9999 to the accuracies or results. The results may be seriously degraded.
9999 OPUS software to deliver best accuracy results for short data spans is
9999 under development.
9999 With triming the first few epochs, some files that start out with
9999 2 hours and a few minutes of data may be reduced to just under 2
9999 hours, and this warning may be ignored
9999
9999 OPUS DISCLAIMER OPUS DISCLAIMER OPUS DISCLAIMER OPUS DISCLAIMER
9999
2005 NOTE: The IGS precise and IGS rapid orbits were not available
2005 at processing time. The IGS ultra-rapid orbit was/will be used to
2005 process the data.
2005
NGS OPUS SOLUTION REPORT
========================

USER: david.humes@tteci.com DATE: April 06, 2007


RINEX FILE: 0001095t.07o TIME: 01:31:37 UTC

SOFTWARE: page5 0612.06 master12.pl START: 2007/04/05 19:13:00


EPHEMERIS: igu14214.eph [ultra-rapid] STOP: 2007/04/05 21:01:00
NAV FILE: brdc0950.07n OBS USED: 3586 / 3685 :
97%
ANT NAME: LEIAX1202 NONE # FIXED AMB: 29 / 29 :
100%
ARP HEIGHT: 1.382 OVERALL RMS: 0.010(m)

REF FRAME: NAD_83(CORS96)(EPOCH:2002.0000) ITRF00


(EPOCH:2007.2598)

X: 463922.460(m) 0.011(m) 463921.740(m) 0.011(m)


Y: -4603806.959(m) 0.052(m) -4603805.596(m) 0.052(m)
Z: 4375318.901(m) 0.055(m) 4375318.826(m) 0.055(m)

LAT: 43 35 23.90849 0.005(m) 43 35 23.93864 0.005(m)


E LON: 275 45 15.23419 0.006(m) 275 45 15.20835 0.006(m)
W LON: 84 14 44.76581 0.006(m) 84 14 44.79165 0.006(m)
EL HGT: 161.500(m) 0.076(m) 160.413(m) 0.076(m)
ORTHO HGT: 195.663(m) 0.080(m) [Geoid03 NAVD88]

Reach D Survey Report Page A-11


UTM COORDINATES STATE PLANE COORDINATES
UTM (Zone 16) SPC (2113 MI S)
Northing (Y) [meters] 4830019.923 232164.713
Easting (X) [meters] 722337.435 4009763.155
Convergence [degrees] 1.89979870 0.08227489
Point Scale 1.00020809 0.99998259
Combined Factor 1.00018276 0.99995727

US NATIONAL GRID DESIGNATOR: 16TGP2233730020(NAD 83)

BASE STATIONS USED


PID DESIGNATION LATITUDE LONGITUDE
DISTANCE(m)
DG5936 HMLK HEMLOCK CORS ARP N432441.083 W0841414.486 19850.9
AJ5551 BAYR SAGINAW CORS ARP N432646.398 W0835330.210 32780.2
AF9510 SAG1 SAGINAW 1 CORS ARP N433743.089 W0835015.940 33218.3

NEAREST NGS PUBLISHED CONTROL POINT


OK0013 RV 112 N433608. W0841341. 1974.3

This position and the above vector components were computed without any
knowledge by the National Geodetic Survey regarding the equipment or
field operating procedures used.

Reach D Survey Report Page A-12


Appendix B. Tittabawassee River Reach D Bathymetry: April 2007
(Sheet 1 of 1)

Reach D Survey Report


Reach D Survey Report Page B-1
Appendix C. Equipment Data Sheets
The following are copies of the equipment data sheets provided by the manufacturers of some of
the systems used in the survey.

Reach D Survey Report


Reach D Survey Report Page C-1
Reach D Survey Report Page C-2
Reach D Survey Report Page C-3
Reach D Survey Report Page C-4
Reach D Survey Report Page C-5
Reach D Survey Report Page C-6
Reach D Survey Report Page C-7
Reach D Survey Report Page C-8
Attachment B

Summary of Natural Sub-Grade Soils Evaluation – Reach D Project


May 20, 2007
The Dow Chemical Company Reach D Project
Michigan Operations

Summary of Natural Sub-Grade Soils Evaluation – Reach D Project


May 20, 2007

Background

The Reach D Project Characterization Plan was submitted to MDEQ-Waste Management


Division (WMD) on March 19, 2007. That characterization plan indicated both shore-
based and land-based sampling activities to complete characterization of the project area.
Initial Reach D shore-based characterization samples collected March 12 and 13, 2007.
These data defined the contaminated deposit beneath the rip-rap material, and described
the level of contaminants present or absent in the sub-grade soils immediately beneath the
contamination. Results were presented to MDEQ April 2, 2007. Based on discussions at
that meeting, MDEQ requested that additional data be obtained to further describe
residual levels of contamination in the natural subgrade. MDEQ-WMD and URS staff
discussed means to collect additional data from natural soils beneath the Reach D
anthropogenic deposit in locations between the two bridges and in the area between the
railroad bridge and the Dow Dam. Data obtained north of the two bridges was deemed
sufficient.

River-based sampling was completed by ATS and their sub-contractors on April 10 and
11, 2007. These samples included sub-grade samples from beneath the anthropogenic
deposit between and south of the two bridges. A total of ten samples were able to be
tested for at least a partial list of the contaminants of concern. Results are summarized in
Table 1.

Methods

Follow-up shore-based sampling was conducted by URS and their sub-contractors on


April 19 and 20, 2007. This work included three additional soil borings with the purpose
of obtaining data from natural soils beneath the anthropogenic Reach D deposit. Fifteen
soil samples were obtained from these soil borings. Results are presented in Table 2.

Samples were subjected to testing to determine total concentrations of target list


constituents (those listed in Section 3.1.1 of the Reach D Characterization Plan). In
addition, R 299.5722 and RRD Operational Memorandum No. 2 – Attachment 2 (Soil
Leaching Methods) allows that leach testing can be used if soil concentrations exceed the
applicable generic criteria (presented in R 299.5746). R 299.5722(3) specifically
indicates that methods of leaching should be similar to those expected in the field. A
conservative test method (EPA method 1311, Toxicity Characteristic Leaching Protocol)
was selected to be more conservative than this approach to determine if the natural soils
would leach, even under acidic conditions. This approach was deemed to be
conservative, as acidic conditions are not present at the site, nor are they likely to occur in

mdc Page 1
The Dow Chemical Company Reach D Project
Michigan Operations

the future. Summary Tables present the results of leach testing, a full listing of leach
testing is provided as Attachment C to the May 2007 Reach D Monthly Progress Report.

Discussion

River-based Sampling
River-based sampling efforts inside of the flume were able to collect samples of the
natural clay soil layer just beneath the anthropogenic Reach D deposit. Samples RD-
51+00-IC-40, RD-51+50-IC-33, and RD-52+50-IC-20 (shown on Figure 1) are samples
of silty clay found beneath the anthropogenic deposit. Total soil concentrations from
these samples are all well below the MDEQ Generic Residential Groundwater Surface
Water Interface Criterion (GSI) for soil. Conservative leach testing showed leaching
under extreme conditions only in one sample. Detection limits for tetrachloroethene and
chlorobenzene were elevated too high in the samples to determine if the soils would leach
under these extreme conditions. Although no site-specific criterion for surface water
sediments has been specified under R 299.5730, these are soils beneath the river and
samples were well below the Generic soil GSI criterion, the data support completing the
removal action of the anthropogenic deposit, down to the elevation of the natural soils.

River-based sampling efforts were limited in the amount of information that could be
obtained. The presence of gravel and stiff clays minimized the ability to collect sufficient
samples to allow analysis in several locations. Several samples were attempted outside
the flume sheet piling, but were unable to obtain sufficient quantities of sediment for
testing. Samples from coring location RD-49+75-IC-45 (shown on Figure 1) from depths
ranging from 0.8 to 4.0 feet were not able to recover sufficient sample to allow testing for
volatile or semi-volatile compounds. A maximum estimated TEQ of 4,300 ppt was
detected from this set of samples. This coring was taken prior to results of high-resolution
bathymetry survey and it appears that this sample may have been obtained inside the
1939 flume sheet piling.

Samples from coring location RD-51+25-IC-50 were made down to a depth of 1.5 feet
using hand sampling tools from a floating platform by the River-based sampling crew.
Evidence of contamination from these samples was not identified.

Additional sampling is planned to occur at the time of this submittal in this are to confirm
the findings in samples from coring location RD-49+75-IC-45, and provide additional
data to evaluate the preliminary conclusion that contamination does not extend beyond
the 1939 flume sheet piling wall.

Shore-based Sample Results


Results from initial shore-based characterization are provided in Table 3 for comparison.

The shore-based sampling results indicate that the constituents of concern are present at
vastly lower concentrations than in the anthropogenic deposit above them. In addition,
although no site-specific criterion for surface water sediments has been specified under R

mdc Page 2
The Dow Chemical Company Reach D Project
Michigan Operations

299.5730, none of the natural soil samples (in Tables 2 and 3) contained concentrations
of the constituents of concern above MDEQ Generic Residential soil GSI criterion.
Three of the fifteen additional soil samples were able to be leached at levels above the
Generic GSI groundwater criterion using the conservative leach testing. Because these
soil samples were well below the Generic soil GSI criterion, the data support completing
the removal action of the anthropogenic deposit down to the elevation of the natural soils.

Conclusion

Removal of the natural sub-grade soils is not necessary, as the soil data are not above
MDEQ Part 201 Generic Residential Groundwater Surface Water Interface Criterion.
Leach testing, as allowed (but not specifically required) by R 299.5722 and RRD
Operational Memorandum No. 2 – Attachment 2 (Soil Leaching Methods) results
conservatively show that risk of discharge from the natural soils beneath the
anthropogenic Reach D deposit (after its removal) will be below allowable levels.

River-based sampling completed thus far has been problematic in that an insufficient
number of samples have been able to be tested for the constituents of concern. As stated
above, additional sampling is planned to occur at the time of this submittal to confirm the
findings in samples from coring location RD-49+75-IC-45, and provide additional data to
evaluate the preliminary conclusion that contamination does not extend beyond the 1939
flume sheet piling wall.

mdc Page 3
Attachment C

Monitoring of Chemical Residues in the Tittabawassee River Using Semi-Permeable


Membrane Devices (SPMDs)
Monitoring of Chemical Residues in the Tittabawassee River Using Semi-Permeable
Membrane Devices (SPMDs)

K.B. Woodburn, Toxicology, Environmental Research & Consulting,


1803 Building, The Dow Chemical Company, Midland, MI

INTRODUCTION

Semipermeable membrane devices (SPMDs) are passive sampling devices consisting of a


tubular low-density polyethylene membrane containing a thin film of a high-molecular
weight lipid (triolein). When placed in an aquatic environment, SPMDs passively
accumulate hydrophobic organic compounds, such as polychlorinated dibenzo-p-dioxins
and dibenzofurans (PCDDs/PCDFs), polychlorinated benzenes, and other hydrophobic
chemicals. SPMDs have been proposed as an alternative or a complement to traditional
bioaccumulation studies for assessing the levels of bioavailable hydrophobic organic
contaminants in aquatic environments [1-4]. Contaminants are passively accumulated in
the SPMDs in a manner similar to their bioconcentration in fish lipid [2]. The advantages
of SPMDs over the use of fish include: (a) they do not require feeding; (b) they do not
cannibalize one another or die from disease, predation, or lack of oxygen in the water; (c)
they will not move around or escape; (d) they are incapable of the metabolism and
depuration of hydrophobic chemicals that occurs in natural organisms, including fish; and
(e) they offer a simple, reproducible matrix for accumulating organic chemicals that is
relatively insensitive to differences in water quality [5-8]. Disadvantages of SPMDs
include differential accumulation of some compounds when compared to fish [9, 10].
Gale et al. [10] compared 28-day accumulated concentrations of PCDDs/PCDFs in caged
channel catfish (Icatalurus punctatus) and SPMDs in tributaries of the Saginaw River,
Michigan. These researchers observed SPMD/whole catfish ratio concentrations of
PCDDs/PCDFs ranging from 0.5 to 15.1 in samples from the Tittabawassee River and
comparable ratios of 0.5 to 22.0 for various congeners in SPMD/fish located in the
Shiawassee River. The authors confirmed the practicality of SPMDs to assess the
bioavailability of these contaminants in water. The authors concluded that “SPMDs
demonstrated the utility of in-situ passive sampling over inference of water
concentrations from accumulation in biota or partitioning with sediment” [10].

OBJECTIVE

The objective of this study is to examine the time-integrated presence of selected


chlorinated organic chemicals in the water of the Tittabawassee River, as measured by
uptake in SPMDs. Locations both upstream and downstream of the Dow Chemical
industrial site in Midland, MI will be studied. The specific Tittabawassee River site
location targeted for this monitoring study will be upstream and downstream of Reach D,
located near the Dow Dam. Sediment dredging and removal is scheduled to begin in
mid-July 2007 and this monitoring project is focused on gathering background river data
on selected chemicals.

MATERIALS AND METHODS


Test Device
The test device for this study will be the SPMD, available from Environmental Sampling
Technologies (EST) of St. Joseph, MO (1717 Commercial Drive, St. Joseph, MO 64503,
phone: 816-232-8860). The compounds of interest are selected chlorinated organic
substances that may be present in Reach D sediment and potentially released into the
water column; a list of these chemicals and their respective limits of detection (LOD) are
presented in Table 1.

Deployment or protection devices may also be used, if necessary, to ensure the integrity
of the SPMDs during study conduct. Each deployment device will contain one or more
SPMD, as needed, to obtain the desired or target chemical quantitation levels detailed in
Table 1. Each individual SPMD weighs approximately 4.58 g and contains 20% lipid, or
~0.915 g (1 mL) of triolein; two SPMDs constitute approximately 9.2 g total weight and
will be used as a single SPMD sample, as this mass is roughly equivalent to the mass of
fish tissue (10 g) generally analyzed in fish studies conducted on the Tittabawassee River.
The standard SPMDs are 2.5 cm wide x 90 cm long low density polyethylene tubes (70-
95 µm wall thickness), for a total surface area of ~450 cm2 or approximately 100 cm2/g-
SPMD. High purity (>95%) triolein will be used in the SPMDs from EST. SPMD
calibration data are generally based on the weight of the standard SPMD [9].

Experimental Design and Sampling


The length of the exposure will be from 20 to 40 days, targeting near 28 days, depending
on weather conditions and the timing of dredging activities on the river. A total of 12
SPMDs will be placed at each sampling site (4 replicate SPMDs at 3 sites per location),
to allow for an examination of the variability of accumulated residues at each sampling
location.

At the termination of exposure, the SPMDs will be shipped to EST in St. Joseph, MO for
extraction. One or more background or control SPMDs will be handled and analyzed at
study initiation to identify any background chemical residues that may be present during
the handling process. We will also have one or more newly-opened SPMDs extracted by
EST at the termination of the exposure period. This allows Dow to monitor any chemical
residues introduced into SPMDs by the overall EST-extraction process. All extracts will
be returned to Dow for chemical residue analysis.

Sampling Locations/Types and Number of Samples


There will be a total of four sample locations at which groups of SPMDs will be located;
the approximate sampling locations are shown on the map in Figure 1. The first site
(Location A) will be upstream of the Reach D location on the Tittabawassee River, just
downstream of the former location of Building 47 at Dow, near the site of the new
baseball diamond in Midland. Twelve SPMDs (4 reps x 3 locations across the river) will
be present. The remaining three sites will be:
• at Reach D (Location B) – four SPMDs within the sheet pile wall and four
SPMDs just outside the wall (total of eight SPMDs);
• immediately downstream of Reach D (Location C), just downriver of the Dow
Dam; twelve SPMDs (4 reps x 3 locations across the river) will be present;
• approximately 1-1.5 miles downstream of the Dow Dam and within the Dow
industrial site (Location D), just upstream of Dow’s wastewater 031 Outfall;
twelve SPMDs (4 reps x 3 locations across the river) will be present.

Except for Location B, where eight SPMDs will be used, twelve SPMDs will be placed at
each sampling location to help quantify the variability of accumulated residues; a total of
44 samples (with two SPMDs/sample or ~9.2 g/sample) will be needed for all sites. The
SPMDs will be placed in deployment cages for protection and attached to anchored poles
in the river to allow for a constant exposure location. The anchoring sites will be
approximately one foot (12”) or more off the bottom of the river.

At each location, on the terminal day of exposure, Tittabawassee River water samples
will be taken to analyze for constituents with water detection levels noted in Table 1;
specifically, the water samples will be analyzed for chlorobenzene, 1,2-dichlorobenzene,
1,4-dichlorobenzene, 1,2,4-trichlorobenzene, and hexachlorobutadiene. The water
sampling volume will be a minimum of 1-L for analytes analyzed as semi-volatile
compounds and 40-mL for analytes analyzed as volatile compounds. The sampling will
be in done in triplicate at each of the four locations for a total of 12 water samples. The
water samples will be taken in general accordance with a standard operating procedure
(SOP) regarding the collection of depth-integrated, aqueous samples from streams and
rivers not more than 15 feet in depth [11].

Chemical Analyses
SPMDs will be extracted by EST and returned to Dow for final analysis. The analytical
method for PCDD/PCDF analysis will be based on the U.S. EPA Method 1613B [12],
which involves isotope dilution methodology, purification by classical liquid
chromatography, and final analysis by high-resolution gas chromatography/high
resolution mass spectrometry (HRGC–HRMS). The remaining analytes in the SPMDs
will be determined by other methods, such as isotope dilution methodology, and some
purification prior to gas chromatography/mass spectrometry (GC/MS) analysis or other
appropriate analytical methods. Details of all analytical techniques will be provided in
the final study report.

River Conditions
Tittabawassee River water flow conditions, such as water flow and river gage height, will
be obtained from the United States Geological Survey (USGS) web page, available at:
http://waterdata.usgs.gov/mi/nwis/uv/?site_no=04156000&PARAmeter_cd=00065,00060 . Data on
Tittabawassee River gage height (feet) and streamflow (ft3/second or cfs) will be
collected daily over the exposure period. The USGS monitoring station on the
Tittabawassee River is located at Lat 43°35'43", Long 84°14'08", in NW1/4 NE1/4
sec.28, T.14 N., R.2 E., Midland County, Hydrologic Unit 04080201, on right bank 2,000
ft downstream from dam at Dow Chemical Co. in Midland, 0.7 mi upstream from
Bullock Creek, 1.4 mi downstream from Chippewa River, and 23 mi upstream from river
mouth.
USGS data on Tittabawassee River mean water flow per day are presented in Figure 2.
Average peak flow is generally in late March, while minimum flow is in mid-August; the
average flow for June is approximately 1,000 to 2,000 cfs. Collectively, the USGS data
may be used to characterize river conditions during the study and to allow for any follow-
up monitoring study to be evaluated against the river conditions at the time of the SPMD
exposures. Other water quality parameters, such as temperature, pH, alkalinity, etc., may
be available from the Dow Wastewater Treatment Plant and recorded in the data file for
the exposure dates.

Statistics
The stated objective of the study is to determine the time-integrated residues of certain
bioaccumulative chemicals in the Tittabawassee River over a several week timeframe.
As noted previously, the SPMD is not an accurate representation of a fish, but is a useful
tool to determine the environmental presence of aqueous hydrophobic chemicals.
Consequently, accumulated residues of compounds in SPMDs can not be compared to
accumulated fish chemical residues observed in previous Dow biouptake studies.
Individual chemical residue values, averages, standard deviations, and 95% confidence
limits will be reported for each sampling site location.

REFERENCES

1. Gale R, Huckins JN, Petty J, Peterman P, Williams L. 1997. Comparison of the


uptake of dioxin-like compounds by caged channel catfish and semipermeable
membrane devices in the Saginaw River, Michigan. Environ Sci
Technol. 31:178–187.

2. Huckins JN, Petty JD, Lebo JA, Orazio CE, Prest HF, Tillitt DE, Ellis GS,
Johnson BT, Manuweera GK. 1996. Semipermeable membrane devices (SPMDs)
for the concentration and assessment of bioavailable organic contaminants in
aquatic environments. In Ostrander GK, ed, Techniques in Aquatic Toxicology.
Lewis, Boca Raton, FL, USA, pp 625–655.

3. Huckins JN, Tubergen MW, Manuweera GK. 1990. Semipermeable membrane


devices containing model lipid: A new approach to monitoring the bioavailability
of lipophilic contaminants and estimating their bioconcentration potential.
Chemosphere. 20:533–552.

4. Hofelt CS, Shea D. 1997. Accumulation of organochlorine pesticides and PCBs


by semipermeable membrane devices and Mytilus edulis in New Bedford Harbor.
Environ Sci Technol. 31:154–159.

5. Petty JD, Huckins JN, Zajicek JL. 1993. Application of semipermeable membrane
devices (SPMDs) as passive air samplers. Chemosphere 27:1609–1624.
6. Prest HF, Huckins JN, Petty JD, Herve S, Paasivirta J, Heinonen P. 1995. A
survey of recent results in passive sampling of water and air by semipermeable
membrane devices. Mar Pollut Bull. 31:306–312.

7. Lebo J, Zajicek J, Huckins JN, Petty J, Peterman P. 1992. Use of semipermeable


membrane devices for in situ monitoring of polycyclic aromatic hydrocarbons in
aquatic environments. Chemosphere 25:697–718.

8. Wang Y, Wang Z, Liu J, Ma M, Belzile N. 1999. Monitoring priority pollutants in


the Yanghe river by dichloromethane extraction and semipermeable membrane
device (SPMD). Chemosphere 39:113–131.

9. SPMD Technology tutorial (3rd edition). 2002. Prepared by James Huckins et al.
Available at: http://wwwaux.cerc.cr.usgs.gov/spmd/SPMD-Tech_Tutorial.htm.

10. Gale, RW, Huckins, JN, Petty, JD, Peterman, PH, Williams, LL, Morse, D,
Schwartz, TR, and Tillitt, DE. 1997. Comparison of the uptake of dioxin-like
compounds by caged channel catfish and Semipermeable membrane devices in
the Saginaw River, Michigan. Environ. Sci. Technol. 31: 178-187.

11. LimnoTech. 2006. Depth integrated water sampling standard operating procedure
(SOP).

12. U.S. EPA Method 1613B, Chlorinated Dioxins by Isotope Dilution High
Resolution Gas Chromatography/High Resolution Mass Spectrometry. Report
821/B-94-005.
Table 1. List of chemicals of interest and maximum limits of detection (MLOD) for
SPMDs.

MLOD
Chemical SPMD Water Units
chlorobenzene TBD 5 ng/g (wet wt) or ng/mL (ppb)
12-dichlorobenzene TBD 5
14-dichlorobenzene TBD 5
124-trichlorobenzene TBD 5
1245-tetrachlorobenzene 1
1234-tetrachlorobenzene 1
Hexachlorobutadiene TBD
Pentachlorobenzene 10
Hexachlorobenzene 1
2378-TCDD 1 pg/g (wet wt) or ng/L (ppt)
12378-PeCDD 5
123478-HxCDD 5
123678-HxCDD 5
123789-HxCDD 5
1234678-HpCDD 5
OCDD 10
2378-TCDF 1
12378-PeCDF 5
23478-PeCDF 5
123478-HxCDF 5
123678-HxCDF 5
234678-HxCDF 5
123789-HxCDF 5
1234678-HpCDF 5
1234789-HpCDF 5
OCDF 10
TBD = To be determined
Figure 1. Map of the planned sampling sites on the Tittabawassee River.
Figure 2. Mean river flow (ft3/sec) as a function of Julian Day for the Tittabawassee
River. Source: U.S. Geological Service.

US Geological Survey: Tittabawassee River Mean Flow Rate (cfs) versus Julian
Day (Data: 1937 to 2006)
6,000
Tittabawassee River Mean Flow (ft3/sec)

5,000 29 March

4,000

3,000

2,000

1,000

15 August
0
0 50 100 150 200 250 300 350 400
Julian Day #
Attachment D

Complete Listing of Additional Leach Testing


Subgrade Soils
Attachment E

GeoTube Facility Plan Maps

También podría gustarte