PUNJAB INFRASTRUCTURE DEVELOPMENT BOARD

ANALYSIS OF RATE FOR BULK / PACKED BITUMEN SUPPLY VARIOUS TYPE COLLECTION OF BITUMEN FROM PANIPAT REFINERY

I
II

Viscosity Grade -10


( 80/100 grade)

Viscosity Grade-30
( 60/70 grade)

Crumb Rubber
III Modifed Bitumen 50
Crumb Rubber
IV Modifed Bitumen 55
Crumb Rubber
V Modifed Bitumen 60
Bitumen Emulsion VI Rapid Setting
Bitumen EmulsionVII Medium Setting
Bitumen EmulsionVIII Slow Setting

Add 1 % Labur cess

Grand Total

Cartage by Road Panipat


Refnery to middle of the
reach 321 Kms.@
Rs.1.50per.Metric tonne
per Kms.

Total

9
481.50

55132.50

0.00

55132

PMT

Packed 47305 6821.38 54126.38

### 3274.65 58483.55

481.50

58965.05

0.00

58965

PMT

45005 6489.72 51494.72

### 3115.43 55640.05

481.50

56121.55

0.00

56122

PMT

Packed 48105 6936.74 55041.74

### 3330.03 59472.60

481.50

59954.10

0.00

59954

PMT

44125 6362.83 50487.83

### 3054.51 54552.09

481.50

55033.59

0.00

55034

PMT

Packed 47475 6845.90 54320.90

### 3286.41 58693.73

481.50

59175.23

0.00

59175

PMT

### 3060.74 54663.36

481.50

55144.86

0.00

55145

PMT

Packed 41854 6035.35 47889.35 957.79 2897.31 51744.44

481.50

52225.94

0.00

52226

PMT

### 3046.21 54403.74

481.50

54885.24

0.00

54885

PMT

Packed 42044 6062.74 48106.74 962.13 2910.46 51979.34

481.50

52460.84

0.00

52461

PMT

36035 5196.25 41231.25 824.62 2494.49 44550.36

481.50

45031.86

0.00

45032

PMT

Packed 39985 5765.84 45750.84 915.02 2767.93 49433.78

481.50

49915.28

0.00

49915

PMT

36245 5226.53 41471.53 829.43 2509.03 44809.99

481.50

45291.49

0.00

45291

PMT

Packed 40195 5796.12 45991.12 919.82 2782.46 49693.40

481.50

50174.90

0.00

50175

PMT

34435 4965.53 39400.53 788.01 2383.73 42572.27

481.50

43053.77

0.00

43054

PMT

Packed 38385 5535.12 43920.12 878.40 2657.17 47455.69

481.50

47937.19

0.00

47937

PMT

Bulk
Bulk
Bulk
Bulk
Bulk
Bulk

44215 6375.80 50590.80


44005 6345.52 50350.52

10

( Amount in Rs.)

### 3060.05 54651.00

Bulk

Rates for
supply

44205 6374.36 50579.36

Bulk

Sub Total

Add @ 6.05%
Punjab Sale Tax

Add @ 14.42 %
Excise Duty
( inclusive of
Education cess )

Product
Basic Rate from
Panipat Refnery

Sl.
Nr.

Add @ 2 % Central
Sale Tax

Bitumen rates Ex. Panipat w.e.f. 01/01/2014

11

Lead Chart from Panipat to Plant & site of work


Panipat
Ropar Bye pass RD 0.0
Site of work
!_____388___ ! _____!_______________________5.60/2
Total =388+2x2.80

394.00 Say

394 Kms

Sub Divisional Engineer ,

Certifed that the lead provided in the analysis of rate is the shortest lead
and rate of bitumen provided in the analysis of rate is the latest rate.

Executive Enginereer,

BM

DBM& BC

TC

PRIMER

Provincial Sub Division


PWD
B&R,
Roopnagar.

Const. Division PWD B&R


Roopnagar.

CONVERSION FROM HOUR RATE TO TONNE-KM RATE


1 Transit Mixer (4.0/4.5 cum)
Rate of transit mixer per hour
Wt of concrete in one load
Analysis of time
Positioning of transit mixer at batching plant
Loading from batching plant
Maneuvering, reversing, turning for return
Waiting time, unforseen contingencies etc.
Total
Speed with load
Speed while returning empty
Hence distance travelled in one hour
Distance travelled in 53 minutes
Hence cost of (10.8 x 26.5) tonne-Km is
Cost per tonne-Km =

2 Transit Mixer (3.0 cum)


Rate of transit mixer per hour
Wt of concrete in one load
Analysis of time
Positioning of transit mixer at batching plant
Loading from batching plant
Maneuvering, reversing, turning for return
Waiting time, unforseen contingencies etc.
Total
Speed with load
Speed while returning empty
Hence distance travelled in one hour
Distance travelled in 53 minutes
Hence cost of (7.2 x 26.5) tonne-Km is
Cost per tonne-Km =

909
10.8 Tonne
1 Min
2 Min
2 Min
2 Min
7 Min
25 Km/hour
35 Km/hour
30 Km
26.5 Km
909
3.176101
Say
3.2

833
7.2 Tonne
1 Min
2 Min
2 Min
2 Min
7 Min
25 Km/hour
35 Km/hour
30 Km
26.5 Km
833
4.365828
Say
4.4

3 Truck 5.5 cum per 10 tonnes


Rate per tonne-Km
Rate of one load per km=
Analysis of time
Positioning of tipper at loading point
Loading by front end loader 1 cum bucket capacity @
25 cum per hour
Maneuvering, reversing, dumping and turning for return
Waiting time, unforeseen contingencies etc
Total
Speed with load
Speed while returning empty
Hence distance travelled in one hour
Distance travelled effectively in 1 hour (in 40 minutes)
Hence rate per hour
Say
3 Tipper 5 cum per 10 tonnes
Rate per tonne-Km

(2.4 tonne / cum)

3.00
22
1 Min
13 Min
2 Min
4 Min
20 Min
25 Km/hour
35 Km/hour
30 Km
20 Km
440
440

3.00

(2.4 tonne / cum)

Rate of one load per km=


Analysis of time
Positioning of tipper at loading point
Loading by front end loader 1 cum bucket capacity @
25 cum per hour
Maneuvering, reversing, dumping and turning for return
Waiting time, unforeseen contingencies etc
Total
Speed with load
Speed while returning empty
Hence distance travelled in one hour
Distance travelled effectively in 1 hour (in 40 minutes)
Hence rate per hour
Say

24
1 Min
13 Min
2 Min
4 Min
20 Min
25 Km/hour
35 Km/hour
30 Km
20 Km
480
480

Description
(A )OWNERSHIP CHARGES
i Factory cost including packing
ii deduct solvage value 15%( I)
iii Total investment to be depriciated (I)-(ii)
iv Economic life of machine in Hours
v Depreciation per hour
iii/iv
vi storage charges per hour (1% of v)
vii Total ownership charges
(B) OPERATIONAL CHARGES
i Repair chrges per hour including maintenance
and replacement of tyres (150% of v)
(C) RUNNING CHARGES
i Operators (per month wage)
ii Cleaner/ Helper (per month wage)
vii Wages per hour
(D) CONSUMPTION CHARGES/HOUR
i Diesel consumption/electrical consumption Rs 42/
ii Lubricating oil 10% of fuel cunsumption
iii Oil,grease,& cotton waste 10% of fuel consumption

(E) INTEREST & INSURANCE 10%

37.41

Water Tanker
70- hp

Wet Mix Plant


75 TPH

800,000
120,000
680,000
10,000
68
1
69

2,000,000
300,000
1,700,000
9,000
189
2
191

102

283

4,500
3,000
50

5,000
3,000
53

224
22
22
269

748
75
75
898

22

498

1,448

(F) OVERHEADS 8% on (A+B+C+D)


(Included in item rate analysis)
Rate/Hour

Generator Generator Generator Joint cutting Generator


250 KVA
125 KVA
100 KVA
machine
33 KVA
700000
105,000
595,000
10000
60
1
60

575000
86,250
488,750
10000
49
0
49

180000
27,000
153,000
10000
15
0
15

134

89

73

23

4,000
3,000
47

4,000
3,000
47

###
###
47

935
94
94
1,122

374
37
37
449

374
37
37
449

150
15
15
180

11

1,403

652

624

Market rate

1050000
157,500
892,500
10000
89
1
90

4,000
3,000
47

5000

266

(A) Usage Rates of Plant and Machinery


(based on 2010 Common Schedule of Rates, Public Works Department, Govt. of Punjab and
Premium @13% as on December 2011 as per notification dated 05 December 2011)
Sl. No.

Description of Machine

Activity

Output of
Machine

Output

Unit

Rate

P&M-001

Air Compressor

General Purpose

capacity in cfm

170/250

hour

319

P&M-002

Batching and Mixing Plant (a) 30 cum capacity

Concrete Mixing

cum/hour

20

hour

2232

P&M-003

Batching and Mixing Plant (b) 15 - 20 cum


capacity

Concrete Mixing

cum/hour

13

hour

1860

P&M-004

Bitumen Pressure Distributor

Applying bitumen tack coat

sqm/hour

1750

hour

1073

P&M-005

Bitumen Boiler oil fired

Bitumen Spraying

capacity in litre

1500

hour

198

P&M-006

Concrete Paver Finisher with 40 HP Motor

Paving of concrete surface

cum / hour

20

hour

2868

P&M-007

Concrete Pump of 45 & 30 cum capacity

Pumping of concrete

cum / hour

33 / 22

hour

256

P&M-008

Concrete Bucket

For Pouring concrete

capacity in cum

hour

16

P&M-009

Concrete Mixer (a) 0.4/0.28 cum

Concrete Mixing

cum/hour

2.5

hour

233

P&M-010

Concrete Mixer (b) 1 cum

Concrete Mixing

cum/hour

7.5

hour

233

P&M-011

Crane (a) 80 tonnes

Lifting Purpose

hour

1279

P&M-012

Cranes b) 35 tonnes

Lifting Purpose

hour

853

P&M-013

Cranes c) 3 tonnes

Lifting Purpose

hour

357

P&M-014

Dozer D - 80 - A 12

Spreading /Cutting / Clearing

cum/hour

300/ 150/250

hour

3720

P&M-015

Dozer D - 50 - A 15

Spreading /Cutting / Clearing

cum/hour

200/ 120/150

hour

2206

P&M-016

Emulsion Pressure Distributor

sqm/hour

1750

hour

800

P&M-017

Front End loader 1 cum bucket capacity

cum/hour

60 /25

hour

806

P&M-018

Generator (a) 125 KVA

Applying emulsion tack coat


Soil loading / Aggregate
loading
Genration of electric Energy

KVA

100

hour

652

P&M-019

Generator( b) 63 KVA

Genration of electric Energy

KVA

50

hour

535

P&M-020

GSB Plant 50 cum

Producing GSB

cum/hour

40

hour

1039

P&M-021

Hotmix Plant - 120 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

40

hour

23405

P&M-022

Hotmix Plant - 100 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

30

hour

17309

P&M-023

Hotmix Plant - 60 to 90 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

25

hour

13842

P&M-024

Hotmix Plant - 40 to 60 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

17

hour

11083

P&M-025

Hydraulic Chip Spreader

Surface Dressing

sqm/hour

1500

hour

2635

P&M-026

Hydraulic Excavator of 1 cum bucket

Soil Ordinary/Soil Marshy / Soil


Unsuitable

cum/hour

60 /60 /60

hour

1302

P&M-027

Integrated Stone Crusher 100THP

Crushing of Spalls

TPH

100

hour

8665

P&M-028

Integrated Stone Crusher 200 HP

Crushing of Spalls

TPH

200

hour

18228

P&M-029

Kerb Casting Machine

Kerb Making

Rm/hour

80

hour

310

P&M-030

Mastic Cooker

Mastic Wearing coat

capacity in tonne

hour

62

P&M-031

Mechanical Broom Hydraulic

sqm/hour

1250

hour

357

P&M-032

Motor Grader 3.35 mtr blade

cum/hour

200/200/50/50

hour

2395

P&M-033

Mobile slurry seal equipment

Surface Cleaning
Clearing /Spreading /GSB
/WBM
Mixing and laying slurry seal

sqm/hour

2700

hour

1008

P&M-034

Paver Finisher Hydrostatic with sensor control


100 TPH

cum/hour

40

hour

2674

P&M-035

Paver Finisher Mechanical 100 TPH

cum/hour

40/30

hour

975

P&M-036

Piling Rig with Bantonite Pump

Rm/hour

2 to 3

hour

5464

P&M-037

Pneumatic Road Roller

Rolling of Asphalt Surface

cum/hour

25

hour

1243

P&M-038

Pneumatic Sinking Plant

Pneumatic Sinking of wells

cum/hour

1.5 to 2.00

hour

4170

P&M-039

Pot Hole Repair Machine

Repair of potholes

cum/hour

hour

907

P&M-040

Prestressing Jack with Pump & access

Stressing of steel wires/stands

hour

129

P&M-041

Ripper

Scarifying

60

hour

28

P&M-042

Rotavator

Scarifying

cum/hour

25

hour

17

P&M-043

Road marking machine

Sqm/hour

100

hour

93

P&M-044

Smooth Wheeled Roller 8 tonne

cum/hour

70/25

hour

460

P&M-045

Tandem Road Roller

Road marking
Soil Compaction /BM
Compaction
Rolling of Aspalt Surface

Paving of DBM/ BM/SDC/


Premix
Paving of WMM /Paving of
DLC
0.75 m dia to 1.2 m dia Boring
attachment

cum/hour

cum/hour

30

hour

1144

Capacity in cum

5.5

km

6.78
0.678

P&M-046

Tipper - 5 cum

Transportation of soil, GSB,


WMM, Hotmix etc.

P&M-047

Tipper - 5 cum

Transportation of soil, GSB,


WMM, Hotmix etc.

Capacity in cum

5.5

tonne.km

Tipper - 5 cum

Transportation of soil, GSB,


WMM, Hotmix etc.

Capacity in cum

5.5

hour

P&M-048

Page 1 of 264

339

P&M-049

Transit Mixer 4.0/4.5 cum

Transportation of Concrete Mix


to site

cum/hour

4.5

hour

1017

P&M-050

Transit Mixer 4/4.5 cum

Transportation of Concrete Mix


to site

cum/hour

4.5

tonne.km

2.034

Transit Mixer 3.0 cum

Transportation of Concrete Mix


to site

cum/hour

hour

932.25

P&M-052

Transit Mixer 3.0 cum

Transportation of Concrete Mix


to site

cum/hour

tonne.km

1.8645

P&M-053

Tractor

Pulling

capacity in HP

50

hour

282.5

P&M-054

Tractor with Rotevator

Rate of Tractor + Rotevator

hour

282.5

P&M-055

Tractor with Ripper

Rate of Tractor 6+ Ripper

hour

282.5

P&M-056

Truck 5.5 cum per 10 tonnes

Material Transport

capacity/cum

4.5

km

24.5775

P&M-057

Truck 5.5 cum per 10 tonnes

Material Transport

capacity/cum

4.5

hour

315.27

P&M-058

Truck 5.5 cum per 10 tonnes

Material Transport

capacity/cum

4.5

tonne.km

2.45775

P&M-059

Vibratory Roller 8 tonne

Earth or soil / GSB / WBM

cum/hour

100/60/60

hour

P&M-060

Water Tanker

Water Transport

capacity in KL

hour

200

P&M-061

Water Tanker

Water Transport

capacity in KL

km

7.0625

P&M-062

Wet Mix Plant 60 TPH

Wet Mix

cum/hour

25

hour

1317.015

Sl. No.

Description of Machine

P&M-063

Air compressor with pneumatic chisel attachment for cutting hard clay.

hour

740.15

P&M-064

Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour

hour

25594.5

P&M-065

Belt conveyor system

hour

100

P&M-066

Boat to carry atleast 20 persons

hour

100

P&M-067

Cement concrete batch mix plant @ 175 cum per hour (effective output)

hour

14644.8

P&M-068

Cement concrete batch mix plant @ 75 cum per hour

hour

9153

P&M-069

Cold milling machine @ 20 cum per hour

hour

300

P&M-070

Crane 5 tonne capacity

hour

116.53125

P&M-071

Crane 10 tonne capacity

hour

233.0625

P&M-072

Crane 15 tonne capacity

hour

349.59375

P&M-073

Crane 20 tonne capacity

hour

466.125

P&M-074

Crane 40 T capacity

hour

932.25

P&M-075

Crane with grab 0.75 cum capacity

hour

1073.5

P&M-076

Compressor with guniting equipment along with accessories

hour

349.17

P&M-077

Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour.

hour

3661.2

P&M-078

Epoxy Injection gun

hour

100

P&M-079

Generator 33 KVA

hour

406.8

P&M-080

Generator 100 KVA

hour

762.75

P&M-081

Generator 250 KVA

hour

1906.875

P&M-082

Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method
of well sinking.

hour

1000

P&M-083

Joint Cutting Machine with 2-3 blades (for rigid pavement)

hour

200

P&M-084

Jack for Lifting 40 tonne lifting capacity.

day

500

P&M-085

Piling rig Including double acting pile driving hammer (Hydraulic rig)

hrs

5974.875

P&M-086

Plate compactor

hour

101.7

P&M-087

Snow blower equipment 140 HP @ 600 cum per hour

hour

1000

P&M-088

Texturing machine (for rigid pavement)

hour

500

P&M-089

Truck Trailor 30 tonne capacity

hour

847.50

P&M-051

Unit

1541

Rate

P&M-090

Truck Trailor 30 tonne capacity

t.km

0.678

P&M-091

Tunnel Boring machine

hour

5000

P&M-092

Vibrating Pile driving hammer complete with power unit and accessories.

hour

1000

P&M-093

Wet Mix Plant 100 TPH

hour

2195.025

P&M-094

Wet Mix Plant 75 TPH

2195.025

Page 2 of 264

(B) Labour
(based on PUNJAB GOVT. GAZ. (EXTRA), NOVEMBER 15,2012, DEPARTMENT OF LABOUR, (LABOUR BRANCH), No.
S.O. 94/C.A. 1111948/Ss.3and5/2012.-dated 15th November, 2012)
Sl. No.

Description of Labour

Unit

Rate

L-01

Blacksmith (IInd class)

day

230.00

L-02

Blacksmith (Ist class)/ Welder/ Plumber/ Electrician

day

264.50

L-03

Blaster (Stone cutter)

day

264.50

L-04

Carpenter I Class

day

264.50

L-05

Chiseller (Head Mazdoor)

day

264.50

L-06

Driller (Jumper)

day

264.50

L-07

Diver

day

264.50

L-08

Fitter

day

230.00

L-09

Mali

day

264.50

L-10

Mason (IInd class)

day

230.00

L-11

Mason (Ist class)

day

223.36

L-12

Mate / Supervisor

day

151.44

L-13

Mazdoor

day

136.69

L-14

Mazdoor/Dresser (Semi Skilled)

day

230.00

L-15

Mazdoor/Dresser/Sinker (Skilled)

day

164.69

L-16

Medical Officer

day

304.20

L-17

Operator(grouting)

day

264.50

L-18

Painter I class

day

223.36

L-19

Para medical personnel

day

264.50

(C) Materials
Sl. No.

Description

Unit

Rate

M-001

Stone Boulder of size 150 mm and below at Cruser Plant

cum

919

M-002

Supply of quarried stone 150 - 200 mm size for Hand Broken at site

cum

494.68

M-003

Boulder with minimum size of 300 mm for Pitching at Site

cum

494.68

M-004

Coarse sand at Mixing Plant

cum

828

M-005

Coarse sand at Site

cum

710.46

M-006

Fine sand at Site

cum

476.8

M-007

Moorum at Site

cum

461.9

M-008

Gravel/Quarry spall at Site

Cum

921

M-009

Granular Material or hard murrum for GSB works at Site

Cum

727.79

M-010

Granular Material or hard murrum for GSB works at Mixing Plant

Cum

461.9

Page 3 of 264

M-011

Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant

Cum

8.94

M-012

Filter media/Filter Material as per Table 300-3 (MoRT&H Specification)

Cum

894

Description

Unit

Rate at Plant
(HMP/Batching Rate at Site
)

M-013

Close graded Granular sub-base Material 53 mm to 9.5 mm

cum

867

836.17

M-014

Close graded Granular sub-base Material 37.5 mm to 9.5 mm

cum

867

867

M-015

Close graded Granular sub-base Material 26.5 mm to 9.5 mm

cum

867

867

M-016

Close graded Granular sub-base Material 9.5 mm to 4.75 mm

cum

867

867

M-017

Close graded Granular sub-base Material 9.5 mm to 2.36 mm

cum

867

836.17

M-018

Close graded Granular sub-base Material 4.75mm to 2.36 mm

cum

867

867

M-019

Close graded Granular sub-base Material 4.75mm to 75 micron mm

867

867

M-020

Close graded Granular sub-base Material 2.36 mm

cum

867

836.17

M-021

Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve.

cum

476.8

476.8

M-022

Coarse graded Granular sub-base Material 2.36 mm & below

cum

992.3

867

M-023

Coarse graded Granular sub-base Material 4.75mm to 75 micron mm

867

867

M-024

Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm

cum

867

867

M-025

Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm

cum

867

867

M-026

Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm

cum

867

867

M-027

Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm

cum

867

867

M-028

Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm

cum

867

867

M-029

Coarse graded Granular sub-base Material 53 mm to 26 .5mm

cum

867

867

M-030

Aggregates below 5.6 mm

cum

992.3

1066.89

M-031

Aggregates 22.4 mm to 2.36 mm

cum

1012

1001

M-032

Aggregates 22.4 mm to 5.6 mm

cum

1001

1001

M-033

Aggregates 45 mm to 2.8 mm

cum

968.6

968.6

M-034

Aggregates 45 mm to 22.4 mm

cum

1007.77

920.5

M-035

Aggregates 53 mm to 2.8 mm

990.25

990.25

M-036

Aggregates 53 mm to 22.4 mm

cum

959

959

M-037

Aggregates 63 mm to 2.8 mm

cum

982

982

M-038

Aggregates 63 mm to 45 mm

cum

949

949

M-039

Aggregates 90 mm to 45 mm

cum

938

938

M-040

Aggregates 10 mm to 5 mm

cum

1078.94

987

M-041

Aggregates 11.2 mm to 0.09 mm

cum

987

987

M-042

Aggregates 13.2 mm to 0.09 mm

cum

1001

1001

M-043

Aggregates 13.2 mm to 5.6 mm

cum

998.5

998.5

M-044

Aggregates 13.2 mm to 10 mm

cum

1103.6

1016.5

M-045

Aggregates 20 mm to 10 mm

cum

1103.6

1016.5

M-046

Aggregates 25 mm to 10 mm

cum

1103.6

986

M-047

Aggregates 19 mm to 6 mm

cum

1001

1001

M-048

Aggregates 37.5 mm to 19 mm

cum

956

956

M-049

Aggregates 37.5 mm to 25 mm

cum

1011.94

920.5

M-050

Aggregates 6 mm nominal size

cum

969

969

M-051

Aggregates 10 mm nominal size

cum

1005

1005

M-052

Aggregates 13.2/12.5 mm nominal size

cum

1028

1028

M-053

Aggregates 20 mm nominal size

cum

1028

1028

M-054

Aggregates 25 mm nominal size

cum

925

925

M-055

Aggregates 40 mm nominal size

cum

916

916

Sl. No.

Description

Unit

Rate

M-056

AC pipe 100 mm dia

metre

65

M-057

Acrylic polymer bonding coat

litre

485

M-058

Alluminium Paint

litre

132.61

Page 4 of 264

M-059

Aluminium alloy plate 2mm Thick

sqm

425

M-060

Aluminium alloy/galvanised steel

tonne

54574

M-061

Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards lettering, cost of angle iron,
cost of drilling holes, nuts, bolts etc.and signs as applicable

sqm

6064

M-062

Aluminium studs 100 x 100 mm fitted with lense reflectors

nos

546

M-063

Barbed wire

kg

65.56

M-064

Bearing (Cost of parts)

nos

1213

M-065

Bearing (Cast steel rocker bearing assembly of 250 tonne )

nos

50000

M-066

Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel
laminates by the process of vulcanisation,)

nos

15000

M-067

Bearing (Forged steel roller bearing of 250 tonne

nos

41309

M-068

Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces
against stainless steel mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all
components

nos

41309

M-069

Bearing (PTFE sliding plate bearing assembly of 80 tonnes )

nos

16378

M-070

Bearing (Supply of sliding plate bearing of 80 tonne)

nos

16378

M-071

Bentonite

kg

4.1

M-072

Binding wire

M-073

Bitumen ( CRMB 55)

tonne

55145

M-074

Bitumen (60-70 grade) VG -30

tonne

55132

M-075

Bitumen (80-100 grade ) VG-10

tonne

56122

M-076

Bitumen (Cutback )

tonne

47937

M-077

Bitumen (emulsion)

tonne

49915

M-078

Bitumen (modified graded)

tonne

38740

M-079

Brick

each

4.41818

M-080

C.I.shoes for the pile

kg

59.6

M-081

Cement

tonne

5000

M-082

Cold twisted bars (HYSD Bars)

tonne

45000

M-083

Coller for joints 300 mm dia

M-084
M-085
M-086

Copper Plate(12m long x 250mmwide)

M-087

Corrosion resistant Structural steel

M-088

Corrugated sheet, 3 mm thick, "Thrie" beam section railing

M-089

Credit for excavated rock found suitable for use

cum

37

M-090

Curing compound

liter

607

M-091

Delineators from ISI certified firm as per the standard drawing given in IRC - 79

each

834.4

M-092

Earth Cost or compensation for earth taken from private land

cum

28

M-093

Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit
conforming to clause 915.1 of IRC: 83 (part II),

M-094

Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each

M-095

Epoxy compound with accessories for preparing epoxy mortar

M-096

kg

100

nos

146

Compressible Fibre Board(20mm thick)

sqm

486

Connectors/ Staples

each

61

kg

290.55

tonne

46526

kg

49

metre

6064

100 nos

1456

kg

486

Epoxy mortar

kg

425

M-097

Epoxy primer

kg

417.2

M-098

Epoxy resin-hardner mix for prime coat

kg

486

M-099

Flag of red color cloth 600 x 600 mm

each

91

M-100

Flowering Plants

each

61

M-101

Galvanised MS flat clamp

nos

25

M-102

Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size.

sqm

122

M-103

Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long

kg

61

M-104

Gelatin 80%

kg

146

M-105

Geo grids

sqm

607

M-106

Geomembrane

sqm

607

M-107

Geonets

sqm

607

M-108

Geotextile

sqm

37.25

M-109

Geotextile filter fabric

sqm

37.25

M-110

GI bolt 10 mm Dia

nos

13

M-111

Grouting pump with agitator

hour

304

Page 5 of 264

M-112

Grass (Doob)

kg

M-113

Grass (Fine)

kg

13

M-114

HDPE pipes 75mm dia

metre

607

M-115

HDPE pipes 90mm dia

metre

607

M-116

Hedge plants

each

61

M-117

Helical pipes 600mm diameter

metre

2426

M-118

Hot applied thermoplastic compound

M-119

HTS strand

M-120

Joint Sealant Compound

kg

607

M-121

Jute netting, open weave, 2.5 cm square opening for seeding and Mulching

sqm

61

M-122

LDO for steam curing

litre

43

M-123

M.S. Clamps

nos

13

M-124

M.S. Clamps

kg

52.15

M-125

M.S.shoes @ 35 Kg per pile of 15 m

kg

M-126

Mild Steel bars

M-127

M-128

litre
tonne

Modular strip/box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto
140mm assembly comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements, support and
control system, all steel sections protected against corrosion and installed by the manufacturer or his authorised
representative
Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm box/box seal
joint assembly containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal, anchorage
elements, support and control system, all steel sections protected against corrosion and installed by the manufacturer or his
authorised representative

150
57453

37

tonne

47307.5

metre

1820

metre

1820

M-129

Nipples 12mm

nos

243

M-130

Nuts and bolts

kg

64.07

M-131

Paint

litre

192.81

M-132

Pavement Marking Paint

litre

117.16

M-133

Paving Fabric

sqm

225

M-134

Perforated geosynthetic pipe 150 mm dia

metre

182

M-135

Perforated pipe of cement concrete, internal dia 100 mm

metre

243

M-136

Pesticide

kg

1820

M-137

Pipes 200 mm dia, 2.5 m long for drainage

metre

243

M-138

Plastic sheath, 1.25 mm thick for dowel bars

sqm

61

M-139

Plastic tubes 50 cm dia, 1.2 m high

nos

3639

M-140

Polymer braids

metre

364

M-141

Pre moulded Joint filler,25 mm thick for expansion joint.

sqm

965

M-142

Pre-coated stone chips of 13.2 mm nominal size

cum

1213

M-143

Preformed continuous chloroprene elastomer or closed cell foam sealing element with high tear strength, vulcanised in a
single operation for the full length of a joint to ensure water tightness.

metre

668

M-144

Pre-moulded asphalt filler board

sqm

425

M-145

Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days

kg

49

M-146

Primer

kg

102.94

M-147

Quick setting compound

kg

364

M-148

Random Rubble Stone

M-149

RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia

metre

5000

M-150

RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia

metre

4452

M-151

RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia

metre

1149

M-152

Reflectorising glass beads

kg

75

M-153

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips)

metre

364

M-154

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips)

metre

364

M-155

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced
polymer/polymeric strips)

metre

364

M-156

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips)

metre

364

M-157

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips)

metre

364

M-158

Rivets

each

101.32

M-159

Sand bags (Cost of sand and Empty cement bag)

nos

M-160

Sapling 2 m high 25 mm dia

each

25

M-161

Scrap tyres of size 900 x 20

nos

364

M-162

Seeds

kg

243

M-163

Selected earth

cum

43

cum

Page 6 of 264

2604.51

M-164

Separation Membrane of impermeable plastic sheeting 125 micron thick

sqm

61

M-165

Sheathing duct

metre

304

M-166

Shrubs

each

M-167

Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing

cum

364

M-168

Sodium vapour lamp

each

1213

M-169

Square Rubble Coursed Stone

cum

2705.04

M-170

Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level

each

1213

M-171

Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level

each

1820

M-172

Steel drum 300 mm dia 1.2 m high/empty bitumen drum

nos

79

M-173

Steel helmet and cushion block on top of pile head during driving.

kg

61

M-174

Steel pipe 25 mm external dia as per

IS:1239

metre

182

M-175

Steel pipe 50 mm external dia as per

IS:1239

metre

364

M-176

Steel wire rope 20 mm

kg

61

M-177

Steel wire rope 40 mm

kg

M-178

Strip seal expansion join

metre

7500

M-179

Structural Steel

tonne

45000

M-180

Super plastisizer admixture IS marked as per 9103-1999

M-181

Synthetic Geogrids as per clause 3102.8 and approved design and specifications.

sqm

607

M-182

Through and bond stone

each

14.453

M-183

Tie rods 20mm diameter

nos

49

M-184

Tiles size 300 x 300 mm and 25 mm thick

each

15

M-185

Timber

cum

24255

M-186

Traffic cones with 150 mm reflective sleeve

nos

243

M-187

Tube anchorage set complete with bearing plate, permanent wedges etc

nos

6064

M-188

Unstaked lime

tonne

4500

M-189

Water

KL

10

M-190

Water based cement paint

litre

31

M-191

Welded steel wire fabric

kg

61

M-192

Wire mesh 50mm x 50mm size of 3mm wire

kg

61

M-193

Wooden ballies 2" Dia for bracing

each

61

M-194

Wooden ballies 8" Dia and 9 m long

each

91

M-195

Wooden packing

cum

12000

M-196

Wooden staff for fastening of flag 25 mm dia, one m long

each

122

Page 7 of 264

kg

61

44.7

Overheads for Road Works

10%

Contractors profit for Road Works

10%

Overheads for Bridge Works

20%

for input of Overheads or Contractors profit please type in collum C as like


below

Overheads for Bridge Works (Rehabilitation)

25%

Type symble of apostrope(') then input value then one space then symble
of percentage (%) for example '08 %

Contractors profit for Bridge Works

10%

Lead from Mixing Plant to working site

1 km

Lead for E/W borow area to site

20 km

Lead for fly ash from source to site

53 km

Page 8 of 264

Items No.

Summary of Rates calculated and used for analysis of rates of other items

Item 8.3

Printing new letter and figures of any shade (ii) English Roman

Item 8.8

Painting Two Coats on New Concrete Surfaces

Item 8.9

Unit

Rate

per cm height
per letter
sqm

40.00

0.30

Painting angle iron post two coats

sqm

46.00

Item 12.6 (B)

Cement mortor 1:2 (Excluding OH & CP)

cum

4,152.00

Item 12.6 (A)

Cement mortor 1:3 (Excluding OH & CP)

cum

3,425.00

Item 12.6 (D)

Cement mortor 1:6 (Excluding OH & CP)

cum

2,422.00

Item 12.7 (A )

Course Rubble masonary in cement mortor 1:3 (including OH & CP)

cum

6,211.00

Item 12.7 (Addl) B)

Random Rubble masonary in cement mortor 1:6 (including OH & CP)

cum

5,610.00

cum

4,228.00

cum

3,080.00

cum

3,390.00

cum

3,443.00

cum

4,650.00

cum

3,388.00

cum

3,667.00

cum

4,949.00

cum

3,614.00

cum

3,723.00

cum

3,740.00

cum

3,697.00

cum

3,641.00

cum

3,740.00

cum

3,686.00

cum

3,816.00

cum

3,952.00

cum

5,217.00

cum

3,838.00

cum

3,719.00

cum

3,558.00

cum

3,874.00

cum

3,712.00

cum

3,904.00

cum

3,743.00

cum

3,974.00

cum

5,260.00

Item 12.11 (C) iv

PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Batching Plant

cum

3,812.00

Item 12.11 (F) iv

PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant

cum

5,114.00

Item No. 3.13

Excavation for Structures (Manual Means)

cum

138.00

Item No. 3.13

Excavation for Structures (Mechenical Meanse)

cum

36.00

Item 14.1(A)

RCC Grade M20 for super-structure including OH & CP by Batching Plant

cum

5,317.00

Item 14.1(B)

RCC Grade M20 for super-structure including OH & CP by Batching Plant

cum

5,783.00

Item 14.1(E)

RCC Grade M20 for super-structure including OH & CP by Batching Plant

cum

6,171.83

Item 14.1(C)

RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching Plant

cum

4,428.00

Item 14.1(C)

RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching Plant

cum

3,690.00

Item 14.2 A

Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP

tonne

50,004.00

Item 13.6

Supplying, fitting and placing HYSD including OH & CP for sub-structure

tonne

65,101.00

Item 5.17

Fog Seal

sqm

53.00

Crack Prevention courses. Case-I Stress Absorbing Membrane (SAM) crack width less than 6 mm
Crack Prevention courses. Case-II Stress Absorbing Membrane (SAM) with crack width 6 mm to 9
mm
Crack Prevention courses. Case-III Stress Absorbing Membrane (SAM) crack width above 9 mm
and cracked area above 50 %

sqm

57.00

sqm

67.00

sqm

88.00

Item 5.21 Case-IV

Crack Prevention courses. Case-IV Bitumen Impregnated Geotextile

sqm

124.00

Item 5.15 Case-I

Slurry Seal Case-I 5 mm thickness

sqm

82.00

Item 5.15 Case-II

Slurry Seal Case-II 3 mm thickness

sqm

57.00

Item 5.15 Case-III

Slurry Seal Case III 1.5 mm thickness

sqm

35.00

Surface Dressing Case-I 19 mm nominal chipping size

sqm

104.00

Item 12.8 (A)


Item 12.8 (A)
Item 12.8 (B) PCC
Item 12.8 (C)
Item 12.8 (C) RCC
Item 12.8 (C)
Item 12.8 (D)
Item 12.8 (D)
Item 12.8 (D)
Item 12.8 (E)
Item 12.8 (E)
Item 12.8 (F)
Item 12.8 (F)
Item 12.8 (G)
Item 12.8 (G)
Item 12.8 (H)
Item 12.8 (H)
Item 12.8 (H)
Item 12.8 (H)
Item 12.11 (C) i
Item 12.11 (C) i
Item 12.11 (C) ii
Item 12.11 (C) ii
Item 12.11 (C) iii
Item 12.11 (C) iii
Item 12.11 (C) iv
Item 12.11 (C) iv

Item 5.21 Case-I


Item 5.21 Case-II
Item 5.21 Case-IV

Item 5.9 Case-I

PCC Grade M15 including OH & CP for Open Foundation by Mixer


PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Mixer
PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Mixer
RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Mixer
RCC Grade M20 including OH & CP for Open Foundation by Batching Plant
RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Batching Plant
PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Mixer
PCC Grade M25 including OH & CP for Open Foundation by Batching Plant
PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Batching Plant
RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Mixer
RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Batching Plant
PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Mixer
PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Batching Plant
RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Mixer
RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Batching Plant
RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Mixer
RCC Grade M35 including OH & CP for Open Foundation by Batching Plant

by
by
by

by
by

by
by
by
by
by
by
by
by

RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant
RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant
PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Mixer
PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Batching Plant
PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Mixer
PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Batching Plant
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Mixer
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Batching Plant
PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Mixer
PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant

Page 9 of 264

Item 5.9 Case-II

Surface Dressing Case-II 13 mm nominal size chipping

Page 10 of 264

sqm

85.00

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-2
SITE CLEARANCE
Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting of trees, including cutting of trunks,
branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 mtrs and earth
filling in the depression/pit.)

2.1
(i)
(ii)
(iii)
(iv)

Girth from 300 mm to 600 mm


Girth from 600 mm to 900 mm

each
each

137.00
259.00

Girth from 900 mm to 1800 mm

each
each

482.00
896.00

hectare

8636.00

hectare

49142.00

Girth above 1800 mm

2.2

Clearing Grass and Removal of Rubbish

2.3

Clearing and Grubbing Road Land .(Clearing and grubbing road land including uprooting rank vegetation, grass, bushes,
shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
materials and stacking of serviceable material to be used or auctioned up to a lead of 1000 metres including removal and
disposal of top organic soil not exceeding 150 mm in thickness.)

(ii)

By Mechanical Means
A

In area of light jungle


Dismantling of Structures (Dismantling of existing structures like culverts, bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting
the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of
1000 metres)

2.4

(i)

Lime /Cement Concrete


By Manual Means

I
A
B
C
II
A
B
(ii)

Lime Concrete, cement concrete grade M-10 and below


Cement Concrete Grade M-15 & M-20
Prestressed / Reinforced cement concrete grade M-20 & above
By Mechanical Means for items No. 202( b) & ( c)
Cement Concrete Grade M-15 & M-20
Prestressed / Reinforced cement concrete grade M-20 & above

cum
cum

212.00
247.00

cum

623.00

cum
cum

372.00
634.00

cum
cum

143.00
177.00

cum
cum

129.00
122.00

cum
cum

157.00
177.00

cum
cum
cum

143.00
136.00
129.00

cum
cum

143.00
343.00

tonne
tonne

836.00
603.00

tonne

6.00

Dismantling Brick / Tile work


A
B
C
D

(iii)
A
B
C
D
E
F
(iv)
(v)

In lime mortar
In cement mortar
In mud mortar
Dry brick pitching or brick soling
Dismantling Stone Masonry
Rubble stone masonry in lime mortar
Rubble stone masonry in cement mortar.
Rubble Stone Masonry in mud mortar.
Dry rubble masonry
Dismantling stone pitching/ dry stone spalls.
Dismantling boulders laid in wire crates including opening of crates and stacking dismantled materials.
Wood work wrought framed and fixed in frames of trusses upto a height of 5 m above plinth level
Steel work in all types of sections upto a height of 5 m above plinth level excluding cutting of rivet.

A
B
C
(vi)
A
B
(vii)
A
B

Including dismembering
Excluding dismembering.
Extra over item No( V ) A and( V ) B for cutting rivets.
Scraping of bricks dismantled from brick work including stacking.
In lime/Cement mortar
In mud mortar
Scraping of Stone from dismantled stone masonry
In cement and lime mortar
In Mud mortar

(viii)

Scarping plaster in lime or cement mortar from brick/ stone masonry

(ix)

Removing all type of hume pipes and stacking within a lead of 1000 metres including earthwork and dismantling of
masonry works.
A
B
C

Up to 600 mm dia
Above 600 mm to 900 mm dia
Above 900 mm

Page 11 of 264

1000
numbers

605.00

1000
numbers

216.00

cum

243.00

cum
sqm

51.00
8.00

metre

90.00

metre
metre

121.00
208.00

Summary of Rate Analysis


Item No.

Descriptions

2.5

Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal of dismantled materials up to a lead
of 1000 metres, stacking serviceable and unserviceable materials separately)

Unit

Rate

By Manual Means
A

Bituminous courses

cum

389.00

Granular courses
By Mechanical Means

cum

286.00

Bituminous course

II
A

cum

187.00

2.6

Dismantling of Cement Concrete Pavement (Dismantling of cement concrete pavement by mechanical means using
pneumatic tools, breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal
of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately)

cum

992.00

2.7

Dismantling Guard Rails (Dismantling guard rails by manual means and disposal of dismantled material with all lifts and
up to a lead of 1000 metres, stacking serviceable materials and unserviceable materials separately.)

metre

43.00

2.8

Dismantling Kerb Stone (Dismantling kerb stone by manual means and disposal of dismantled material with all lifts and up
to a lead of 1000 metre)

metre

10.00

2.9

Dismantling Kerb Stone channel (Dismantling kerb stone channel by manual means and disposal of dismantled material
with all lifts and up to a lead of 1000 metre)

metre

14.00

2.10

Dismantling Kilometre Stone (Dismantling of kilometre stone including cutting of earth, foundation and disposal of
dismantled material with all lifts and lead upto 1000 m and back filling of pit.)
each

199.00

each
each

121.00
24.00

A
B
C

5th KM stone
Ordinary KM Stone
Hectometre Stone

2.11

Dismantling of Fencing (Dismantling of barbed wire fencing/ wire mesh fencing including posts, foundation concrete, back
filling of pit by manual means including disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking
serviceable material and unserviceable material separately. )

metre

27.00

2.12

Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line 600 mm dia including disposal with all lifts and lead
upto 1000 metres and stacking of serviceable material and unserviceable material separately under supervision of
concerned department)

metre

74.00

metre

86.00

each

101.00

2.13

2.14

Removal of Cement Concrete Pipe of Sewer Gutter (Removal of cement concrete pipe of sewer gutter 1500 mm dia
under the supervision of concerned department including disposal with all lifts and up to a lead of 1000 metres and stacking
of serviceable and unserviceable material separately but excluding earth excavation and dismantling of masonry works.)

Removal of Telephone / Electric Poles and Lines (Removal of telephone / Electric poles including excavation and
dismantling of foundation concrete and lines under the supervision of concerned department, disposal with all lifts and up to
a lead of 1000 metres and stacking the serviceable and unserviceable material separately)

Page 12 of 264

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
3.1

Excavation in Soil by Manual Means. (Excavation for roadway in soil using manual means including loading in truck for
carrying of cut earth to embankment site with all lifts and lead upto1000 metres.)

cum

97.00

3.2

Excavation in ordinary rock by manual means (Excavation in ordinary rock using manual means including loading in a
truck and carrying of excavated material to embankment site with in all lifts and leads upto 1000 metres )

cum

133.00

3.3

Excavation in Soil with Dozer with lead upto 100 metres (Excavation for road way in soil by mechanical means including
cutting and pushing the earth to site of embankment upto a distance of 100 metres (average lead50 metres), including
trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections.)

cum

152.00

3.4

Excavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavation for roadway in ordinary rock by
deploying a dozer, 80 HP including cutting and pushing the cut earth to site of embankment upto a distance of 100 metres
( average lead 50 metres ), trimming bottom and side slopes in accordance with the requirements of lines, grades and cross
sections.)

cum

255.00

cum

292.00

3.6

Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto 1000 metres. (Excavation for
roadwork in soil with hydraulic excavator of0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom
and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment
location within all lifts and lead upto 1000m)

cum

45.00

3.7

Excavation in Ordinary Rockusing Hydraulic ExcavatorCK-90 and Tippers with disposal upto 1000 metres.
(Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in
tippers, transporting to embankment site within all lifts and lead upto 1000 m, trimming bottom and side slopes in
accordance with requirements of lines, grades and cross sections.)

cum

60.00

3.8

Excavation in Hard Rock (blasting prohibited) (Excavation for roadway in hard rock (blasting prohibited) with rock
breakers including breaking rock, loading in tippers and disposal within all lifts and lead upto 1000 metres, trimming bottom
and side slopes in accordance with requirements of lines, grades and cross sections.)
cum
cum

362.00
736.00

3.9

Excavation in Hard Rock (controlled blasting) with disposal upto 1000 metres (Excavation for roadway in hard rock
with controlled blasting by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with
requirements of lines, grades and cross sections, loading and disposal of cut road with in all lifts and leads upto 1000
metres )

cum

379.00

3.10

Excavation in Marshy Soil (Excavation for roadway in marshy soil with hydraulic excavator 0.9 cum bucket capacity
including cutting and loading in tippers and disposal with in all lifts and lead upto 1000 metres, trimming of bottom and side
slopes in accordance with requirements of lines, grades and cross sections.)

cum

51.00

3.11

Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal of unserviceable soil including excavation,
loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as per
clause 305.)

cum

46.00

3.12

Pre-splitting of Rock Excavation Slopes (Carrying out excavation in hard rock to achieve a specified slope of the rock
face by controlled use of explosives and blasting accessories in properly aligned and spaced drill holes, collection of the
excavated rock by a 80 HP dozer, loading in tipper by a front end loader and disposing of the material with all lifts and lead
upto 1000 m, all as specified in clause No. 303)

sqm

143.00

Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres (Excavation for roadway in hard rock
(requiring blasting) by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements
of lines, grades and cross sections, loading and disposal of cut road with in all lifts and leads upto 1000 metres )

3.5

A
B

Mechanised
Manual Method

Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides
and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work.)

3.13

(i)

Ordinary soil
A
B

Manual Means (Depth upto 3 m)


Mechanical Means (Depth upto 3 m)
Ordinary rock (not requiring blasting)

cum
cum

138.00
36.00

A
B

Manual Means (Depth upto 3 m)


Mechanical Means
Hard rock ( requiring blasting )

cum
cum

173.00
49.00

Manual Means
Hard rock ( blasting prohibited )

cum

360.00

Mechanical Means
Marshy soil
Manual means ( upto 3 m depth)

cum

472.00

cum

290.00

(ii)

(iii)
(iv)
(v)
A

Page 13 of 264

Summary of Rate Analysis


Item No.

Unit

Descriptions
B

Rate

cum

106.00

3.14

Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means (Scarifying the existing granular road
surface to a depth of 50 mm and disposal of scarified material within all lifts and leads upto 1000 metres. )

sqm

14.00

3.15

Scarifying existing bituminous surface to a depth of 50 mm by mechanical means (Scarifying the existing bituminous
road surface to a depth of 50 mm and disposal of scarified material with in all lifts and lead upto 1000 metres.)

sqm

4.00

Mechanical Means

3.16

Embankment Construction with Material Obtained from Borrow Pits (Construction of embankment with approved
material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and
compacting to meet requirement of table 300-2)

cum

249.00

3.17

Construction of Embankment with Material Deposited from Roadway Cutting (Construction of embankment with
approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures
graded and compacted to meet requirement of table 300-2)

cum

84.00

3.18

Construction of Subgrade and Earthen Shoulders (Construction of subgrade and earthen shoulders with approved
material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and
compacted to meet requirement of table No. 300-2)

cum

293.00

3.19

Compacting Original Ground


Compacting original ground supporting subgrade (Loosening of the ground upto a level of500 mm below the
subgrade level, watered, graded and compacted in layers to meet requirement of table 300-2 for subgrade construction.)

cum

60.00

:Compacting original ground supporting embankment

Case-I
Case-II

cum

29.00

3.20

Stripping and Storing Top Soil (Stripping, storing of top soil by road side at 15 m internal and re-application on
embankment slopes, cut slopes and other areas in localities where the available embankment material is not conducive to
plant growth)

cum

131.00

3.21

Stripping, storing and re-laying top soil from borrow areas in agriculture fields. (Stripping of top soil from borrow
areas located in agriculture fields, storing at a suitable place, spreading and re-laying after taking the borrow earth to
maintain fertility of the agricultural field, finishing it to the required levels and satisfaction of the farmer.)

cum

91.00

3.22

Turfing with Sods (Furnishing and laying of the live sods of perennial turf forming grass on embankment slope, verges or
other locations shown on the drawing or as directed by the engineer including preparation of ground, fetching of rods and
watering)

sqm

16.00

3.23

Seeding and Mulching (Preparation of seed bed on previously laid top soil, furnishing and placing of seeds, fertilizer,
mulching material, applying bituminous emulsion at the rate of0.23 litres per sqm and laying and fixing jute netting, including
watering for 3 months all as per clause 308)

sqm

129.00

3.24

Surface Drains in Soil (Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil to specified
lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be used in
embankment within a lead of50 metres (average lead 25 metres))
metre

56.00

metre

35.00

metre

114.00

metre
metre

52.00

A
B

Surface Drains in Ordinary Rock (Construction of unlined surface drain of average cross sectional area 0.4 sqm in
ordinary rock to specified lines, grades, levels and dimensions as per approved design and to the requirement of clause 301
to 309. Excavated material to be used in embankment at site.)

3.25
A
B
3.26

3.27

Mechanical means
Manual Means

Mechanical Means
Manual Means
Surface Drains in Hard Rock (Rate per metre may be worked out based on quantity of hard rock as per design.)
Sub Surface Drains with Perforated Pipe (Construction of subsurface drain with perforated pipe of 100 mm internal
diameter of metal/ asbestos cement/ cement concrete/PVC, closely jointed, perforations ranging from 3 mm to 6 mm
depending upon size of material surrounding the pipe, with 150 mm bedding below the pipe and 300 mm cushion above the
pipe, cross section of excavation 450 x 550 mm. Excavated material to be utilised in roadway at site )

587.00

3.28

Aggregate Sub- Surface Drains (Construction of aggregate sub surface drain 300 mm x 450 mm with aggregates
conforming to table 300-4, excavated material to be utilised in roadway )

metre

171.00

3.29

Underground Drain at Edge of Pavement (Construction of an underground drain 1 m x 1 m (inside dimensions) lined with
RCC-20 cm thick and covered with RCC slab10 cm in thickness on urban roads)

metre

2356.00

3.30

Preparation and Surface Treatment of formation. (Preparation and surface treatment of formation by removing mud and
slurry, watering to the extent needed to maintain the desired moisture content, trimming to the required line, grade, profile
and rolling with 8-10 tonne smooth wheeled roller, complete as per clause 310.)

sqm

1.00

3.31

Construction of Rock fill Embankment (Construction of rock fill embankment with broken hard rock fragments of size not
exceeding 300 mm laid in layers not exceeding 500 mm thick including filling of surface voids with stone spalls, blinding top
layer with granular material, rolled with vibratory road roller, all complete as per clause 313)

cum

50.00

3.32

Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by mechanical means including
cutting and trimming of side slopes and disposing of excavated earth with all lifts and lead upto 1000 metres)

cum

149.00

Page 14 of 264

Summary of Rate Analysis


Item No.

Descriptions

Unit

3.33

Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting. (Excavation in hilly area in
ordinary rock not requiring ballasting by mechanical means including cutting and trimming of slopes and disposal of cut
material with all lift and lead upto 1000 metres )

cum

224.00

cum

293.00

cum

314.00

3.34

Excavation in Hilly Areas in Hard Rock Requiring Blasting (Excavation in hilly areas in hard rock requiring blasting, by
mechanical means including trimming of slopes and disposal of cut material with all lifts and lead upto 1000 metres.)

3.35

Work in Urban Roads (The cost of earth work in urban roads inhabited area will be comparatively higher due to following
reasons:)

3.36

Embankment Construction with Fly ash/Pond ash available from coal or lignite burning Thermal Plants as waste
material. (Construction of embankment with fly ash conforming to table 1 of IRC: SP: 58 - 2001 obtained from coal or lignite
burning thermal power stations as waste material, spread and compacted in layer of 200mm thickness each at OMC, all as
specified in IRC: SP: 58-2001 and as per approved plans.)

Page 15 of 264

Rate

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
4.1

Granular Sub-base with Close Graded Material (Table:- 400-1)


Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant
at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and
compacting with vibratory power roller to achieve the desired density, complete as per clause 401 )

A
(i)

for grading- I Material

cum

1606.00

cum
cum

400.00
376.00

cum

561.00

cum

698.00

Lime Stabilisation for Improving Subgrade (Laying and spreading available soil in the subgrade on a prepared surface,
pulverising, mixing the spread soil in place with rotavator with 3 % slaked lime having minimum content of 70% of CaO,
grading with motor grader and compacting with the road roller at OMC to the desired density to form a layer of improved sub
grade)

4.3

A
B

By Mechanical Means
By Manual Means
Lime Treated Soil for Sub- Base (Providing, laying and spreading soil on a prepared sub grade, pulverising, mixing the
spread soil in place with rotavator with 3 % slaked lime with minimum content of 70% of CaO, grading with motor grader and
compacting with the road roller at OMC to achieve at least 98%of the max dry density to form a layer of sub base.)

4.4

4.5

Cement Treated Soil Sub Base/ Base (Providing, laying and spreading soil on a prepared sub grade, pulverising, adding
the designed quantity of cement to the spread soil, mixing in place with rotavator, grading with the motor grader and
compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of subbase/base.)

4.6

Cement Treated Crushed Rock or combination as per clause 403.2 and table 400.4in Sub base/ Base (Providing,
laying and spreading Material on a prepared sub grade, adding the designed quantity of cement to the spread Material,
mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the
desired unconfined compressive strength and to form a layer of sub-base/base.)

(i)

For Sub-Base course

cum

1953.00

(ii)

For Base course

cum

1953.00

sqm

404.00

cum

1266.00

cum

1714.00

cum

1927.03

cum
cum
cum

1727.00
1806.00
1899.00

cum

1741.00

cum

1914.00

cum
cum

1659.00
1872.24

cum
cum

1672.00
1752.00

cum

1844.00

cum

1686.00

cum

1859.00

Making 50 mm x 50 mm Furrows (Making 50 mm x 50 mm furrows, 25mm deep, 450 to the center line of the road and at
one metre interval in the existing thin bituminous wearing coarse including sweeping and disposal of excavated material
within 1000 metres lead)

4.7

Inverted Choke (Construction of inverted choke by providing, laying, spreading and compacting screening B type/ coarse
sand of specified grade in uniform layer on a prepared surface with motor grader and compacting with power roller etc)

4.8

Water Bound Macadam (Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound
macadam specification including spreading in uniform thickness, hand packing, rolling with vibratory roller 8-10 tonnes in
stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the
interstices of coarse aggregate, watering and compacting to the required density.)

4.9

A
(i)

By Manual Means
(a)
(b)

(ii)
(a)
(b)
(c)
(iii)
(a)
(b)
B
(i)
(a)
(b)
(ii)
(a)
(b)
(c)
(iii)
(a)
(b)

Grading- I (Using Screening Crushable type such as Moorum or Gravel)


Using Screening Crushable type such as Moorum or Gravel
Using Screening Type-A (13.2mm Agg.)
Grading- II (Using Screening Crushable type such as Moorum or Gravel)
Using Screening Crushable type such as Moorum or Gravel
Using Screening Type-A (13.2mm Agg.)
Using Screening Type-B (11.2mm Agg.)
Grading- III (Using Screening Crushable type such as Moorum or Gravel)
Using Screening Crushable type such as Moorum or Gravel
Using Screening Type-B (11.2mm Agg.)
By Mechanical Means:
Grading- I (Using Screening Crushable type such as Moorum or Gravel)
Using Screening Crushable type such as Moorum or Gravel
Using Screening Type-A (13.2mm Agg.)
Grading- II (Using Screening Crushable type such as Moorum or Gravel)
Using Screening Crushable type such as Moorum or Gravel
Using Screening Type-A (13.2mm Agg.)
Using Screening Type-B (11.2mm Agg.)
Grading- III (Using Screening Crushable type such as Moorum or Gravel)
Using Screening Crushable type such as Moorum or Gravel
Using Screening Type-B (11.2mm Agg.)

Page 16 of 264

Summary of Rate Analysis


Item No.

Descriptions

Unit

4.10

Crushed Cement Concrete Sub-base / Base (Breaking and crushing of material obtained by breaking damaged cement
concrete slabs to size range not exceeding 75 mm as specified in table 400.7 transporting the aggregates obtained from
breaking of cement concrete slabs at a lead of L km., laying and compacting the same as sub base/ base course,
constructed as WBM to clause 404 except the use of screening or binding Material.)

cum

163.00

sqm

24.00

4.12

Wet Mix Macadam (Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam
specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper
to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with
vibratory roller to achieve the desired density.)

cum

1861.26

4.13

Construction of Median and Island with Soil Taken from Roadway Cutting (Construction of Median and Island above
road level with approved material deposited at site from roadway cutting and excavation for drain and foundation of other
structures, spread, graded and compacted as per clause 407)

cum

99.00

4.14

Construction of Median and Island with Soil Taken from Borrow Areas (Construction of median and Island above road
level with approved material brought from borrow pits, spread, sloped and compacted as per clause 407)

cum

284.00

4.15

Construction of Shoulders (A. Earthen Shoulders)

4.16

Footpaths and Separators (Construction of footpath/separator by providing a 150 mm compacted granular sub base as
per clause 401 and 25 mm thick cement concrete grade M15, over laid with precast concrete tiles in cement mortar 1:3
including provision of all drainage arrangements but excluding kerb channel..)

sqm

586.00

4.17

Crusher Run Macadam Base (Providing crushed stone aggregate, depositing on a prepared surface by hauling vehicles,
spreading and mixing with a motor grader, watering and compacting with a vibratory roller to clause 410 to form a layer of
sub-base/Base)
cum

1710.00

cum

1741.00

cum

1868.00

cum

1188.00

cum

580.00

Penetration Coat Over Top Layer of Crushed Cement Concrete Base (Spraying of bitumen over cleaned dry surface of
crushed cement concrete base at the rate of 25 kg per 10 sqm by a bitumen pressure distributor, spreading of key
aggregates at the rate of 0.13 cum per 10 sqm by a mechanical gritter and rolling the surface as per clause 506.3.8)

4.11

(i)
(ii)
(i)
(ii)

4.18

By Mix in Place Method

For 53 mm maximum size


For 45 mm maximum size
B

Rate

By Mixing Plant :

For 53 mm maximum size


For 45 mm maximum size
Lime, Fly ash stabalised soil sub-base (Construction of Sub-base using lime - fly ash admixture with granular soil,
free from organic matter/ deleterious material or clayey silts and low plasticity clays having PI between 5 and 20
and liquid limit less than 25 and commercial dry lime, slaked at site or pre-slaked with CaO content not less than
50%, fly ash to conform to gradation as per clause 4.3 of IRC: 88-1984, lime + fly ash content ranging between 10 to
30%, the minimum un-confined compressive strength and CBR value after 28 days curing and 4 days soaking to be
7.5kg/sq, cm and 25% respectively, all as specified in IRC: 88-1984. )

Page 17 of 264

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
5.1

Prime coat (Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including
clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means.)

5.2

Tack coat
Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20
kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom.

sqm

51.40

sqm

16.76

cum
cum

7863.79
7871.54

Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH hot mix plant producing an average
output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder, transported to
site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per
clauses 501.6 and 501.7 to achieve the desired compaction)

5.3

(i)
(ii)

for Grading I ( 40 mm nominal size )


for GradingII(19 mm nominal size)
Bituminous Penetration Macadam (Construction of penetration macadam over prepared Base by providing a layer of
compacted crushed coarse aggregate using chips spreader with alternate applications of bituminous binder and key
aggregates and rolling with a smooth wheeled steel roller 8-10 tonne capacity to achieve the desired degree of compaction)

5.4

50 mm thick

sqm

432.00

75 mm thick

sqm

590.00

sqm

351.00

cum

10006.88

cum
cum

9943.00
10693.00

cum

11688.42

sqm

104.00

sqm

85.00

Built-Up-Spray Grout (Providing, laying and rolling of built-up-spray grout layer over prepared base consisting of a two
layer composite construction of compacted crushed coarse aggregates using motor grader for aggregates. key stone chips
spreader may be used with application of bituminous binder after each layer, and with key aggregates placed on top of the
second layer to serve as a Base conforming to the line, grades and cross-section specified, the compacted layer thickness
being 75 mm)

5.5

Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with 100-120 TPH batch type
HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler, transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 507 complete in all
respects.)

5.6

(i)

for Grading I ( 40 mm nominal size )


Semi - Dense Bituminous Concrete (Providing and laying semi dense bituminous concrete with 100-120 TPH batch type
HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.5 to 5 % of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher
with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MoRTH specification clause No. 508 complete in all respects)

5.7

(i)
(ii)

for Grading I ( 13 mm nominal size )


for GradingII(10 mm nominal size)
Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an
average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @
5.4 to 5.6 % of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control
to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 509 complete in all respects)

5.8

(i)

for Grading-I ( 13 mm nominal size )


Surface Dressing (Providing and laying surface dressing as wearing course in single coat using crushed stone aggregates
of specified size on a layer of bituminous binder laid on prepared surface and rolling with 8-10 tonne smooth wheeled steel
roller)

5.9
Case -1
Case - II

:-19 mm nominal chipping size


13 mm nominal size chipping
Open - Graded Premix Surfacing (Providing, laying and rolling of open - graded premix surfacing of 20 mm thickness
composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or cut-back or emulsion to required
line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying
and rolling with a smooth wheeled roller 8-10 tonne capacity, finished to required level and grades.)

5.10

(i)

Case - I: Mechanical method using Penetration grade Bitumen and HMP of appropriate capacity not less than 75
tonnes/hour .

sqm

152.00

(ii)

Case - II: Open-Graded Premix Surfacing using cationic Bitumen Emulsion

sqm

186.00

Page 18 of 264

Summary of Rate Analysis


Item No.

Unit

Descriptions
Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical means using HMP of appropriate capacity not
less than 75 tonnes/hour. Providing, laying and rolling of close-graded premix surfacing material of 20 mm
thickness composed of 11.2 mm to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b) aggregates using
penetration grade bitumen to the required line, grade and level to serve as wearing course on a previously
prepared base, including mixing in a suitable plant, laying and rolling with a Smooth wheeled roller 8-10 tonne
capacity, and finishing to required level and grade. )

5.11

Rate

sqm

200.00

Seal Coat (Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and
cross fall using Type A and B seal coats)

5.12
(i)

Case - I : Type A

sqm

80.00

(ii)

Case - II : Type B (Providing and laying of premix sand seal coat with HMP of appropriate capacity not less than 75
tonnes/ hours using crushed stone chipping 6.7 mm size and penetration bitumen of suitable grade.)

sqm

60.00

Supply of Stone Aggregates for Pavement Courses (Supply of stone aggregates from approved sources confirming to
the physical requirement, specified in the respective specified clauses, including royalties, fees rents, collection,
transportation, stacking and testing and measured in cum as per clause 514.5 Competitive market rates to be ascertained.
Alternatively, rates for stone crushing given in chapter 1may be adopted, if found economical. In case for supply of
aggregates at site are not available, nearest crusher site may be ascertained. Loading and un-loading charges and cost of
carriage may be added to these rates to arrive at the cost at site.)

5.13

Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt wearing course with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the
surface, including providing antiskid surface with bitumen precoated fine-grained hard stone chipping of 13.2 mm nominal
size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions,
pressed into surface when the temperature of surfaces not less than 1000C, protruding 1 mm to 4 mm over mastic surface,
all complete as per clause 515.)

5.14

cum

sqm

592.00

sqm
sqm
sqm

85.45
58.00
35.00

cum

7908.00

sqm

47.00

sqm

6.00

cum

12877.00

cum
cum
cum

12772.00
8695.00
8585.00

cum

9750.00

Slurry Seal Providing and laying slurry seal consisting of a mixture of fine aggregates, portland cement filler, bituminous
emulsion and water on a road surface including cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying
and compacting to provide even riding surface)

5.15
(i)
(ii)
(iii)

5 mm thickness
3 mm thickness
1.5 mm thickness
Recycling of Bituminous Pavement with Central Recycling Plant (Recycling pavement by cold milling of exiting
bituminous layers, planning the surface after cold milling, reclaiming excavated material to the extent of 30 % of the required
quantity, hauling and stock piling the reclaimed material near the central recycling plant after carrying out necessary checks
and evaluation, adding fresh material including rejuvenators as required, mixing in a hot mix plant, transporting and laying at
site and compacting to the required grade, level and thickness, all as specified in clause 517.)

5.16

5.17
added

Fog Spray
1.In case it is decided by the engineer to blind the fog spray, the following may be added
Bituminous Cold Mix ( Including Gravel Emulsion) (Providing, laying and rolling of bituminous cold mix on prepared base
consisting of a mixture of unheated mineral aggregate and emulsified or cutback bitumen, including mixing in a plant of
suitable type and capacity, transporting, laying, compacting and finishing to specified grades and levels.)

5.18
(i)
(ii)
(iii)
(iv)

Using bitumen emulsion and 9.5 mm or 13.2 mm nominal size aggregate


Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate
Using cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate
Using cutback bitumen and 19 mm or 26.5 mm nominal size aggregate
Sand Asphalt Base Course (Providing, laying and rolling sand-asphalt base course composed of sand, mineral filler and
bituminous binder on a prepared sub-grade or sub-base to the lines, levels, grades and cross sections as per the drawings
including mixing in a plant of suitable type and capacity, transporting, laying, compacting and finishing.)

5.19

Modified Binder (Supply of modified binder produced by mixing bitumen with modifier such as natural rubber or crumb
rubber or any other polymer found compatible with bitumen and which allows properties given in clause 521.3 and IRC: SP:
53 blending of modifier with bitumen to be done either at the refinery or at the site plant capable of producing the modified
binder to be delivered in drums which shall be agitated in melted condition using suitable device before use to ensure
uniform dispersion.)

5.20

5.21

tonne

Crack Prevention Courses

(i)

Stress Absorbing Membrane (SAM) crack width less than 6 mm (Providing and laying of a stress absorbing
membrane over a cracked road surface, with crack width below 6 mm after cleaning with a mechanical broom, using
modified binder complying with clause 521, sprayed at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed stone
aggregates @ 0.11 cum per 10 sqm with hydraulic chip spreader, sweeping the surface for uniform spread of aggregates
and surface finished to conform to clause 902.)

Page 19 of 264

sqm

57.00

Summary of Rate Analysis


Item No.

Unit

Descriptions

(ii)

(iii)

(iv)

Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm (Providing and laying of a stress absorbing
membrane over a cracked road surface, with crack width 6 to 9 mm after cleaning with a mechanical broom, using
modified binder complying with clause 521, sprayed at the rate of 11 kg per 10 sqm and spreading 11.2 mm crushed
stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of aggregates and surface finished
to conform to clause 902.)
Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 % (Providing and laying a
single coat of a stress absorbing membrane over a cracked road surface, with crack width above 9 mm and cracked area
above 50 % after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the
rate of 15 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the
surface for uniform spread of aggregates and surface finished to conform to clause 902.)
Case - IV : Bitumen Impregnated Geotextile (Providing and laying a bitumen impregnated geotextile layer after
cleaning the road surface, geotextile conforming to requirements of clause 704.3, laid over a tack coat with 1.05 kg per
sqm of paving grade bitumen 80 - 100 penetration and constructed to the requirement of clause 704.4.5)

Rate

sqm

67.00

sqm

88.00

sqm

124.00

Recipe Cold Mix (Providing and laying of premix of crushed stone aggregates and emulsion binder, mixed in a batch type
cold mixing plant, laid over prepared surface, by paver finisher, rolled with a pneumatic tyred roller initially and finished with
a smooth steel wheel roller, all as per clause 519.3)

5.22
(i)

75 mm thickness

cum

8688.00

(ii)

40 mm thickness

cum

12138.00

(iii)

25 mm thickness

cum

13930.00

Page 20 of 264

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with top and bottom width 115 and 165
mm respectively, 250 mm high in M 20 grade PCC on M-10 grade foundation 150 mm thick, foundation having 50 mm
projection beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all complete as
per clause 408)

8.1

Using Concrete Mixer

metre

226.00

Using Concrete Batching and Mixing Plant

metre

231.00

metre

439.00

Cast in Situ Cement Concrete M 20 Kerb with Channel (Construction of cement concrete kerb with channel with top and
bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M10 grade foundation 150 mm thick, kerb
channel 300 mm wide, 50 mm thick in PCC M20 grade, sloped towards the kerb, kerb stone with channel laid with kerb
laying machine, foundation concrete laid manually, all complete as per clause 408)

8.2

Using Concrete Batching and Mixing Plant


Printing new letter and figures of any shade (Printing new letter and figures of any shade with synthetic enamel paint
black or any other approved colour to give an even shade)

8.3
(i)
(ii)

Hindi ( Matras commas and the like not to be measured and paid for Half letter shall be counted as half )

cm height per
letter

0.60

English and Roman

cm height per
letter

0.30

Retro- reflectorised Traffic signs (Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign
as per IRC :67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5
mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved
drawing)

8.4

(i)
( ii )

90 cm equilateral triangle
60 cm equilateral triangle

each
each

4206.00
2783.00

( iii )
( iv )

60 cm circular
80 mm x 60 mm rectangular

each
each

3715.00
5160.00

(v)
(vi )
( vii )

60 cm x 45 cm rectangular

each
each
each

3619.00
4280.00
6569.00

sqm

9152.00

sqm

15825.00

tonne
tonne

83366.00
575.00

60 cm x 60 cm square
90 cm high octagon
Direction and Place Identification signs upto 0.9 sqm size board. (Providing and erecting direction and place
identification retro-reflectorised sign asper IRC:67 made of encapsulated lens type reflective sheeting vide clause 801.3,
fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm supported on a mild steel single angle iron post
75 x 75 x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 x
45 x 60 cm, 60 cm below ground level as per approved drawing)

8.5

Direction and Place Identification signs with size more than 0.9 sqm size board. (Providing and erecting direction and
place identification retro- reflectorised sign asper IRC :67 made of encapsulated lens type reflective sheeting vide clause
801.3, fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported on a mild steel angle iron post 75
mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly designed foundation with M 15 grade cement
concrete45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing)

8.6

Overhead Signs (Providing and erecting overhead signs with a corrosion resistant aluminium alloy sheet reflectorised with
high intensity retro-reflective sheeting of encapsulated lense type with vertical and lateral clearance given in clause 802.2
and 802.3 and installed as per clause 802.7 over a designed support system of aluminium alloy or galvanised steel trestles
and trusses of sections and type as per structural design requirements and approved plans)

8.7

A
B

Truss and Vertical Support


Aluminium alloy plate for over head sign

8.8

Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the surface with synthetic enamel paint in
all shades on new plastered concrete surfaces)

sqm

42.00

8.9

Painting on Steel Surfaces (Providing and applying two coats of ready mix paint of approved brand on steel surface after
through cleaning of surface to give an even shade)

sqm

49.00

8.10

Painting on Wood Surfaces (Providing and applying two coats of ready mix paint of approved brand on wood surface after
through cleaning of surface to give an even shade)

sqm

55.00

8.11

Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work (Painting lines, dashes, arrows etc on roads
in two coats on new work with ready mixed road marking paint conforming to IS:164 on bituminous surface, including
cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control )
sqm

63.00

sqm

54.00

(i)
(ii)

Over 10 cm in width
Up to 10 cm in width

Page 21 of 264

Summary of Rate Analysis


Item No.

Descriptions

8.12

Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old Work (Painting lines, dashes, arrows etc on roads in
two coats on old work with ready mixed road marking paint confirming to IS: 164 on bituminous surface, including cleaning
the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control )

Unit

Rate

(i)

Over 10 cm in width

sqm

43.00

(ii)

Up to 10 cm in width

sqm

46.00

sqm

607.78

5th kilometre stone (precast)

each

2632.00

Ordinary Kilometer stone (Precast)

each
each

1610.00
460.00

8.15

Road Delineators (Supplying and installation of delineators (road way indicators, hazard markers, object markers), 80-100
cm high above ground level, painted black and white in 15 cm wide stripes, fitted with 80 x 100 mm rectangular or 75 mm
dia circular reflectorised panels at the top, buried or pressed into the ground and confirming toIRC-79 and the drawings.)

each

1116.00

8.16

Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of standard design as per IRC:25-1967, fixed in
position including finishing and lettering but excluding painting)

each

535.00

metre

251.00

metre

415.00

8.19

Fencing with welded steel wire Fabric 75 mm x 50 mm (Suggestive) (Providing 1.20 metre high fencing with angle iron
posts 50 mm x 50 mm x 6 mm at 3 metre center to center with 0.40 metre embedded in M15 grade cement concrete,
corner, end and every 10th post to be strutted, provided with welded steel wire fabric of 75 mm x 50 mm mesh or 75 mm x
25 mm mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts etc. complete in all respects.)

metre

647.00

8.20

Tubular Steel Railing on Medium Weight steel channel ( ISMC series) 100 mm x 50 mm (Providing, fixing and erecting
50 mm dia steel pipe railing in 3 rows duly painted on medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2
metres high above ground, 2 m centre to centre, complete as per approved drawings)

metre

2270.00

8.21

Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level (Providing, fencing and erecting 50 mm dia
painted steel pipe railing in 3 rows on precast M20 grade RCC vertical posts1.8 metres high (1.2 m above GL) with 3 holes
50 mm dia for pipe, fixed 2 metres centre to, complete as per approved drawing)

metre

1820.00

metre

3469.00

metre

2721.00

metre

3525.00

8.13

Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface
(Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms
per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be
level, uniform and free from streaks and holes.)

8.14

Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in
position including painting and printing etc)
(i)
(ii)
(iii)

Hectometer stone (Precast)

G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2 metres high GI barbed wire fencing with 1.8 m angle iron
posts 40 mm x 40 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre
below ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on
one side only and provided with 9 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples,
turn buckles etc complete as per clause 807 )

8.17

G.I Barbed wire Fencing 1.8 metre high (Providing and fixing 1.8 metres high GI barbed wire fencing with 2.4 m angle iron
posts 50 mm x 50 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre
below ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on
one side only and provided with 12 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples,
turn buckles etc complete as per clause 807 )

8.18

Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash barrier at the edges of
the road, approaches to bridge structures and medians, constructed with M-20 grade concrete with HYSD reinforcement
conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler
board, keyed to the structure on which it is built and installed as per design given in the enclosure to MOST circular No.
RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at locations directed by the
Engineer, all as specified)

8.22

(i)
8.23

M 20 grade concrete
Metal Beam Crash Barrier
Type - A, "W" : Metal Beam Crash Barrier (Providing and erecting a "W" metal beam crash barrier comprising of 3 mm
thick corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x
75 x 5 mm spaced 2 m centre to centre, 1.8 m high, 1.1 m below ground/road level, all steel parts and fitments to be
galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical
post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per clause 810)

Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and erecting a "Thrie" metal beam crash barrier comprising
of 3 mm thick corrugated sheet metal beam rail, 85 cm above road/ground level, fixed on ISMC series channel vertical
post, 150 x 75 x 5 mm spaced 2 m centre to centre, 2 m high with 1.15 m below ground level, all steel parts and fitments
to be galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the
vertical post with a space of channel section 150 x 75 x 5 mm, 546 mm long complete as per clause 810)

Page 22 of 264

Summary of Rate Analysis


Item No.

Descriptions

8.24

Road Traffic Signals electrically operated (Since it is a ready made item commercially produced and erected by
specialised firm in the electrical and electronic field, rate may be taken based on market enquiry from firms specialised in
this field and ISI certified for the approved design and drawing.)

Unit

Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and erecting a wire rope safety barrier with vertical posts of
medium weight RS Joist (ISMB series) 100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85 m above ground and 0.65 m below
ground level, split at the bottom for better grip, embedded in M 15 grade cement concrete 450 x 450 x 450 mm, 1.50 m
center to center and with 4 horizontal steel wire rope 40 mm dia and anchored at terminal posts 15 m apart. Terminal post to
be embedded in M 15 gradecementconcretefoundation2400 x 450 x 900 mm (depth), strengthened by a strut of RS joist
100 x 75 mm, 2 m long at 450 inclination and a tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation
concrete as per approved design and drawing, rate excluding excavation and cement concrete.)

8.25

8.26

Rate

metre

2055.00

metre

4323.00

metre

807.00

each
each

4286.00
4235.00

each

3226.00

metre

2474.00

metre
metre

4566.00
6666.00

tonne

81484.00

Anti - Glare Devices in Median


Plantation (Plantation of shrubs and plants of approved species in the median. apart from cutting off glare from vehicle
coming from opposite direction, these plants provide a pleasant envoirenment and are eco-friendly. The rate for this item is
available in the chapter 11 on horticulture. )

Anti - Glare Screen with 25 mm steel pipe framework fixed with circular and rectangular vans (Providing and
erecting an anti - glare screen with 25 mm dia vertical pipes fabricated and framed in the form of panels of one metre
length and 1.75 mtr height fixed with circular vane 250 mm dia at top and rectangular vane 600 x 300 mm at the middle,
made out of steel sheet of 3 mm thickness, end vertical pipes of the panel made larger for embedding in foundation
concrete, applying 2 coats of paint on all exposed surfaces, all as per approved design and drawings.)
Anti - Glare Screen with Rectangular Vane of MS sheet (Providing and erecting anti - glare screen with rectangular
vanes of size 750 x 500 mm made from MS sheet, 3 mm thick and fixed on MS angle 50 x 50 x 6 mm at an angle of 450
to the direction of flow of traffic, 1.5 m center to center, top edge of the screen 1.75 m above ground level, vertical post
firmly embedded in cement concrete foundation 0.60 m below ground level, applying 2 coats of paint on exposed faces,
all complete as per approved design and drawings)
Street Lighting (Providing and erecting street light mounted on a steel circular hollow pole of standard specifications for
street lighting, 9 m high spaced 40 m apart, 1.8 m overhang on both sides if fixed in the median and on one side if fixed on
the footpath, fitted with sodium vapour lamp and fixed firmly in concrete foundation.)

8.27
(i)
(ii)

For Fixing in Median


For fixing in Footpath
Lighting on Bridges (Providing and fixing lighting on bridges, mounted on steel hollow circular poles of standard
specifications, 5 m high fixed on parapets with cement concrete, 20 m apart and fitted with sodium vapour lamp)

8.28

Cable Duct Across the Road (Providing and laying of a reinforced cement concrete pipe duct, 300 mm dia, across the
road (new construction), extending from drain to drain in cuts and toe of slope to toe of slope in fills, constructing head walls
at both ends, providing a minimum fill of granular material over top and sides of RCC pipe as per IRC:98-1997, bedded on a
0.3 m thick layer of granular material free of rock pieces, outer to outer distance of pipe at least half dia of pipe subject to
minimum 450 mm in case of double and triple row ducts, joints to be made leak proof, invert level of duct to be above higher
than ground level to prevent entry of water and dirt, all as per IRC: 98 - 1997 and approved drawings.)

8.29

(i)
(ii)
(iii)

Single Row for one utility service


Double Row for two utility services
Triple Row for three utility services
Highway Patrolling and Traffic Aid Post (It is proposed to locate one Traffic Aid Post every 50-60 km of the highway. )

8.30

Items related to under pass/ subway/ overhead bridge/ overhead foot bridge (The items involved for underpass/
subway/ overhead bridge/ overhead foot bridge are earthwork, plain cement concrete, plastering, painting, information sign
etc. The rates for these items are available in respective chapters which can be adopted for the quantities derived from the
approved designs and drawings)

8.31

Traffic Control System and Communication system (Providing a traffic control centre and communication system
including telecommunication facilities and related accessories, CCTV, radar, vehicle detection camera, central computer
system These are specialised item of telecommunication system and are the commercial products. The designer is required
to contact the manufacturers to ascertain market prices. In case of civil works required to be executed for these
installations, pricing may be done as per rates in relevant chapters for quantities derived approved design and drawing.)

8.32

Gantry Mounted Variable Message Sign board (Providing and erecting gantry mounted variable message sign board
electronically operated capable of flashing the desired message over a designed support system of aluminium alloy or
galvanised steel, erected as per approved design and drawings and with lateral clearance as per clause 802.3)

8.33
(i)

Gantry Support System

(ii)

Message Display (Message display board 6 sqm electronically operated with complete electronic fitments for flashing
the pre-determined messages.)

Page 23 of 264

Summary of Rate Analysis


Item No.

Descriptions

8.34

Traffic Impact Attenuators at Abutments and Piers

Unit

Rate

With Scrap Tyres (Provision and installation of traffic attenuators at abutment/pier of flyovers bridges using scrap tyres
of size 100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one above the other and tied with 20 mm wire rope as
per approved design and drawings.)

sqm

2389.00

Using Plastic/Steel Barrel, Filled with Sand (Provision and installation of traffic impact attenuator at abutment/pier of
flyovers bridges using plastic/steel barrels 0.60 m dia and 1.0 m in height, filled with sand in three rows and tied with20
mm steel wire rope as per approved design and drawings)

sqm

760.00

With HI - DRO cell Sandwich (Patented) ((In this patented HI - DRO cell system, water gets discharged from plastic
tubes on impact over a pre-determined time, thus absorbing the energy))

sqm

18533.00

8.35

Road Markers/Road Stud with Lense Reflector (Providing and fixing of road stud 100x 100 mm, die cast in aluminium,
resistant to corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or asphaltic surface by drilling
hole 30 mm upto a depth of 60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as per BS 873 part
4:1973)

each

730.00

8.36

Traffic Cone (Provision of red fluorescent with white reflective sleeve traffic cone made of low density polyethylene (LDPE)
material with a square base of 390 x 390 x 35 mm and a height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as
per BS 873)

each

296.00

8.37

Roadside Amenities

Rest Areas (Providing plainly furnished accommodation for rest rooms, dormitories, restaurants, stalls, shops, petrol pump,
telephone booth, first aid room, traffic aid post, police assistance booth, including electricity, toilet and sewerage system
Pricing may be done based on current plinth area rates approved by PWD/CPWD/MES for a particular zone. Area is
required to be assessed for specific location as per actual site conditions)

Parking areas and Bus Laybyes for Trucks, Buses and Light vehicles (Pricing of parking areas may be done for the
quantities of various items based on the approved dimensions and pavement design for a particular terrain and soil. Rates
for items may be from respective chapters.)

Lawn (Providing a lawn planted with grass and its maintenance )


Rumble Strips (Provision of 15 nos rumble strips covered with premix bituminous carpet, 15-20 mm high at center, 250 mm
wide placed at 1 m center to center at approved locations to control speed, marked with white strips of road marking paint.)

8.38

Policeman Umbrella (Provision of a 2 m high (floor to roof) umbrella for traffic policeman at road crossings, where
necessary, installed on a raised platform, built on a central support of a steel pipe 100 mm dia, roof made of 25 mm dia steel
pipe to provide covered area of 3 sqm, roofed with CGI sheets, all steel parts to be given 2 coats of paint)

8.39

sqm

each

High Mast Pole Lighting at Interchanges and Flyovers (Providing and erecting a high mast pole lighting with 30 m high
hot dip galvanised mast designed to withstand forces exerted with wind speeds of 180 km per hour with 3 seconds gust, as
per IS:875 (Part 3) - 1978, fitted with a base flange, door at the base of mast with heavy duty internal lock, lantern
carriage, suitable winching arrangement for safe working load of 750 kg and high powered electrically driven power tools
for raising and lowering of lantern carriage, flexible 8 core electric cable, lightening conductor, earthing terminal, and
fixing 2 nos aviation obstruction lights on top of the mast, all complete as per approved design and drawings This is a
specialised work and is generally done by firms who specialise in such jobs. The detailed designs and estimates are
submitted by the firms alongwith their tender for checks by the Department. The cost of this work is required to be worked
out based on approved design, drawings and estimate of the lowest tender. A separate contract for this work is concluded
as the contractors for road and bridge works generally donot undertake such jobs.)

8.40

Toll Plaza (The construction, operation and maintenance of Toll Plaza can be broken into separate items of work as under
based on the approved design and drawings:-)

8.41

Safety Devices and signs in Construction Zones (Provision and fixing of traffic signs for limited period at suitable
locations in construction zone comprising of warning zone, approach transition zone, working zone and terminal transition
zone with a minimum distance of 60 cm from the edge of the kerb in case of kerbed roads and 2 to 3 m from the edge of the
carriageway in case of un-kerbed roads, the bottom edge of the lowest sign plate to be not less than 2 m above the road
level, fixed on 60 mm x 60 mm x 6 mm angle iron post, founded and installed as per approved design and drawings,
removed and disposed of after completion of construction work, all as per IRC:SP:55-2001)

8.42

8.43

Portable Barricade in Construction Zone (Installation of a steel portable barricade with horizontal rail 300 mm wide, 2.5
m in length fitted on a 'A' frame made with 45 x 45 x 5 mm angle iron section, 1.5 m in height, horizontal rail painted (2
coats) with yellow and white stripes, 150 mm in width at an angle of 450, 'A' frame painted with 2 coats of yellow paint,
complete as per IRC:SP:55-2001 )

8.44

Permanent Type Barricade in Construction Zone

With Steel Components (Construction of a permanent type barricade made of steel components, 1.5 m high from road
level, fitted with 3 horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5 mm angle iron vertical support, painted with
yellow and white strips, 150 mm in width at an angle of450, complete as per IRC:SP:55-2001 )

Page 24 of 264

each

2598.00

each

4160.00

Summary of Rate Analysis


Item No.

Descriptions

Unit

Rate

With Wooden Components (Construction of a permanent type barricade made of wooden components, 1.5 m high
from road level, fitted with 3 horizontal planks 200 mm wide and 3.66 m long on 100 x 100mm wooden vertical post,
painted with yellow and white striups, 150 mm in width at an angle of450, complete as per IRC:SP:55-2001 )

each

5749.00

With Bricks (Construction of a permanent type barricade made with brick work in mud mortar, 1.5 m high, 4 m long,
600 mm thick, plastered with cement mortar 1:6, painted with yellow and white strips)

each

11476.00

8.45

Drum Delineator in Construction Zone (Provision of metal drum/empty bitumen drum delineator, 300 mm in diameter,
800 mm high, filled with earth for stability, painted in circumferential strips of alternate black and white 100 mm wide fitted
with reflectors 3 Nos of 7.5 cm dia, all as per IRC:SP:55-2001)

each

325.00

8.46

Flagman (Positioning of a smart flagman with a yellow vest and a yellow cap and a red flag 600 x 600 mm securely
fastened to a staff 1 m in length for guiding the traffic)

each

430.00

cum

66.00

cum
cum

85.00
113.00

Depth upto 3 m
Depth 3 m to 6 m

cum
cum

49.00
56.00

Depth above 6m

cum

68.00

cum
cum

94.00
64.00

cum

314.00

cum

347.00

cum
cum

288.00
67.00

cum

219.00

CHAPTER-12
FOUNDATIONS
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.)

12.1
I

Ordinary soil

Manual Means
(i)
(ii)
(iii)

B
(i)
(ii)
(iii)
II
A

upto 3 m depth
3 m to 6 m depth
Above 6 m depth
Mechanical Means

Ordinary rock (not requiring blasting)


(i)

Manual Means
Depth upto 3 m
Mechanical Means
Hard rock ( requiring blasting )

III
A
IV
A
V

Manual Means
Hard rock ( blasting prohibited )
Mechanical Means
Marshy soil
upto 3 m depth

(i)
A
B
VI

Manual means
Mechanical Means
Back Filling in Marshy Foundation Pits

12.2

Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6 nominal mix. Rate may be taken as per
items 13.4.)

12.3

Sand Filling in Foundation Trenches as per Drawing & Technical Specification

cum

811.00

12.4

PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm
nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)

cum

3626.00

12.5

Brick masonry work in cement mortar 1:3 in foundation complete excluding pointing and plastering, as per
drawing and technical specifications

cum

4545.00

cum
cum

3425.00
4150.00

cum
cum

2941.00
2519.00

cum
cum

6211.00
6020.00

cum

4228.00

cum

4653.00

cum

4726.00

cum

4650.00

cum
cum

5021.00
4949.00

cum

5098.00

12.6 A
B
C
D
12.7
(a)
(b)
12.8
A

Cement mortar1:3 (1cement :3 sand)


Cement mortar1:2 (1cement :2 sand)
Cement mortar1:4 (1cement :4 sand)
Cement mortar1:6 (1cement :6 sand)
Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical Specification
Square Rubble Coursed rubble masonry( first sort )
Random Rubble Masonry
Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications
PCC Grade M15
PCC Grade M20

B
C
Case I
Case II
D
Case I
Case II
E
Case I

RCC Grade M20


Using concrete mixer
With Batching Plant, Transit Mixer and Concrete Pump
PCC Grade M25
Using concrete Mixer
With Batching Plant, Transit Mixer and Concrete Pump
Page 25 of 264
RCC Grade M25
Using concrete Mixer

CHAPTER-1
CARRIAGE OF MATERIALS
Sr No

Ref. to
MoRTH
Spec.

1.1

Note
1.2

Note
1.3

Description

Unit

Loading and Unloading of Stone Boulder/Stone


aggregates/Sand/Kanker/Moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
ii) Loading by front end loader 1 cum bucket
capacity @ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for
return
iv) Waiting time, unforeseen contingencies etc
Total
a) Machinery
Tipper 5.5 tonnes capacity
Front end-loader 1 cum bucket capacity @ 25
cum/hour
b) Overhead charges @ 0.1 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 5.5 cum = a+b+c
Rate per cum = (a+b+c)/ 5.5
Unloading will be by tipping.
Loading and Unloading of Boulders by Manual Means

cum

Unit = cum
Taking output = 5.5 cum
a) Labour
Mate
Mazdoor for loading and unloading
b) Machinery
Tipper 5.5 tonne capacity
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for5.5 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.5
Unloading will be by tipping.
Loading and Unloading of Cement or Steel by Manual
Means and Stacking.
Unit = tonne
Taking output = 10 tonnes
a) Labour
Mate
Mazdoor for loading and unloading
b) Machinery
Truck 10 tonne capacity
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for10 tonnes = a+b+c+d
Rate per tonnes = (a+b+c+d)/10

Quantity

Rate Rs

Cost Rs

1 Min
13 Min
2 Min
4 Min
20 Min
hour
hour

0.330
0.330

339.00
806.00

111.87
265.98

say

37.79
41.56
457.20
83.13
83.00

P&M-048
P&M-017

day
day

0.110
0.750

151.44
136.69

16.66
102.52

L-12
L-13

hour

0.750

339.00

P&M-048

say

254.25
37.34
41.08
451.85
82.15
82.00

day
day

0.080
2.000

151.44
136.69

12.12
273.38

L-12
L-13

hour

2.000

315.27

630.54
91.60
100.76
1108.40
110.84
111.00

P&M-057

135.60
98.31
23.39
25.73

P&M-048
P&M-048

say
1.4

Remarks/
Input ref.

Cost of Haulage Excluding Loading and Unloading


Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
Unit = t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km
(i)

Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty :35 km / hour.
a) Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with load
Time taken for empty return trip.
b) Overhead charges @ 0.1 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Page 1 of 264

hour
hour

0.400
0.290

339.00
339.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

cost for 100 t km = a+b+c


Rate per t.km = (a+b+c)/100
1.4

(ii)

say

283.03
2.83
2.80

Remarks/
Input ref.

Unsurfaced Graveled Road


Speed with load: 20 km / hour
Speed for empty return trip :30 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load

hour

0.500

339.00

169.50

P&M-048

Time taken for empty return trip

hour

0.330

339.00

111.87

P&M-048

b)

Overhead charges @ 0.1 on (a)

28.14

c)

Contractor's profit @ 0.1 on (a+b)

30.95

Cost for 100 t .km = a+b+c

340.46

Rate per t.Km = (a+b+c)/100


1.4

(iii)

3.40
say

3.40

Katcha Track and Track in River Bed/Nallah Bed and


Choe Bed.
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a)

Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage

hour

1.000

339.00

339.00

P&M-048

Time taken for empty return trip

hour

0.670

339.00

227.13

P&M-048

b)

Overhead charges @ 0.1 on (a)

56.61

c)

Contractor's profit @ 0.1 on (a+b)

62.27

Cost for 100 t .km = a+b+c

685.02

Rate per t.Km = (a+b+c)/100

6.85
say

1.5

6.90

Hand Broken Stone Aggregates 63 mm Nominal Size


Supply of quarried stone, hand breaking into coarse
aggregate 63 mm nominal size (passing 80 mm and retained
on 50 mm sieve) and stacking as directed
Unit = cum
Taking output = 1 cum
a)

b)

Labour
Mate

day

0.060

151.44

9.09

L-12

Mazdoor

day

1.500

136.69

205.04

L-13

cum

1.100

494.68

544.15

M-002

Material
Supply of quarried stone 150 - 200 mm size

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

75.83
83.41

Rate per cum = a+b+c+d

917.51
say

1.6

918.00

Crushing of Stone Aggregates 13.2 mm Nominal Size.


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 13.2 mm nominal size.
Unit = cum
Taking Output = 600 cum at crusher location.
a) Labour

b)

Mate

day

0.760

151.44

115.09

L-12

Mazdoor Skilled

day

2.000

230.00

460.00

L-14

Mazdoor including breaking of any oversize boulder.

day

17.000

136.69

2323.73

L-13

cum

800.000

919.00

735200.00

Material
Stone Boulder of size 150 mm and below
Page 2 of 264

M-001

Sr No

Ref. to
MoRTH
Spec.
c)

Cost Rs

Remarks/
Input ref.

18228.00

109368.00

P&M-028

20.000

806.00

16120.00

P&M-017

20.000

339.00

6780.00

P&M-048

Description

Unit

Quantity

Integrated stone crusher of 200 TPH including belt


conveyor and vibrating screens
Front end loader 1 cum bucket capacity

Hour

6.000

Hour

Tipper 5.5 cum capacity

Hour

Rate Rs

Machinery

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

87036.68
95740.35

Cost for 600 cum = a+b+c+d+e

1053143.86

Rate per cum = (a+b+c+d+e)*0.95/600

1667.48
say

Note

1667.00

1. 800 cum of stone boulders are needed to get 600 cum of


stone chips of size 13.2 mm.
2. 95 per cent of above cost will be attributed to the
production of 600 cum of stone chips of 13.2 mm size and
balance 5 per cent to the production of stone dust which
comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.
Crushing of Stone Aggregates 20 mm Nominal Size

1.7

Crushing of stone boulders of 150 mm size in an integrated


stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 20 mm nominal size.
Unit = cum
Taking Output = 670 cum at crusher location.
a) Labour
Mate

day

0.760

151.44

115.09

L-12

Mazdoor Skilled

day

2.000

230.00

460.00

L-14

Mazdoor including breaking of any size boulder.

day

17.000

136.69

2323.73

L-13

cum

800.000

919.00

735200.00

M-001

Integrated stone crusher of 200 TPH including belt


conveyor and vibrating screens
Front end loader 1 cum bucket capacity

Hour

6.000

18228.00

109368.00

P&M-028

Hour

20.000

806.00

16120.00

P&M-017

Tipper 5.5 cum capacity

Hour

20.000

339.00

6780.00

P&M-048

b)

Material

c)

Machinery

Stone Boulder of size 150 mm and below

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

87036.68
95740.35

Cost for 670 cum = a+b+c+d+e

1053143.86

Rate per cum = (a+b+c+d+e)*0.90/670

1414.67
say

Note

1.8

1415.00

1. 800 cum of stone boulders are needed to get 600 cum of


stone chips of size 20 and 40 mm.
2. 90 per cent of above cost will be attributed to the
production of 670 cum of stone aggregates of 20mm size
and balance 10 per cent will be for smaller size aggregates
and stone dust which comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.
Crushing of Stone Aggregates 40 mm Nominal Size
Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 40 mm nominal size.
Unit = cum
Taking Output = 750 cum at crusher location.
a) Labour
Mate

day

0.760

151.44

115.09

L-12

Mazdoor Skilled

day

2.000

230.00

460.00

L-14

Page 3 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor

Quantity

Rate Rs

Cost Rs

day

17.000

136.69

2323.73

cum

800.000

919.00

735200.00

M-001

Integrated stone crusher of 200 TPH including belt


conveyor and vibrating screens
Front end loader 1 cum bucket capacity

Hour

6.000

18228.00

109368.00

P&M-028

Hour

20.000

806.00

16120.00

P&M-017

Tipper 5.5 cum capacity

Hour

20.000

339.00

6780.00

P&M-048

b)

Material

c)

Machinery

Stone Boulder of size 150 mm and below

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

87036.68
95740.35

Cost for 750 cum = (a+b+c+d+e)x0.85

895172.28

Rate per cum = (a+b+c+d+e)x0.85/750

1193.56
say

Note

Remarks/
Input ref.

1. 800 cum of stone boulders are needed to get 600 cum of


stone chips of size 13.2 mm.
2. 85 per cent of above cost will be attributed to the
production of 750 cum of stone aggregates of 40mm size
and balance 15 per cent will be for smaller size aggregates
and stone dust which comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.

Page 4 of 264

1194.00

L-13

CHAPTER-2
SITE CLEARANCE
Sr No

Ref. to
MoRTH
Spec.

2.1

201

Description

Unit

Quantity

Rate Rs

Cost Rs

Cutting of Trees, including cutting of Trunks, Branches


and Removal
Cutting of trees, including cutting of trunks, branches and
removal of stumps, roots, stacking of serviceable material
with all lifts and up to a lead of 1000 metres and earth filling
in the depression/pit.
(i)

Unit = Each
Girth from 300 mm to 600 mm
a)

Labour
Mate

day

0.020

151.44

3.03

L-12

day

0.600

136.69

82.01

L-13

b)

Mazdoors for cutting trees including cutting, refilling,


compaction of backfilling and stacking of serviceable
materials within 1000 metres lead by manual means.
Machinery

hour

0.100

282.50

28.25

P&M-053

Tractor-trolley
c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

11.33
12.46

Rate for each tree = a+b+c+d

137.08
say

2.1

(ii)

Mate

day

0.040

151.44

6.06

L-12

Mazdoors for cutting trees including cutting, refilling,


compaction of backfilling, and stacking of serviceable
materials within 1000 metres lead by manual means

day

0.900

136.69

123.02

L-13

hour

0.300

282.50

84.75

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

21.38
23.52

Rate for each tree = a+b+c+d

258.73
say

(iii)

Mate

day

0.080

151.44

12.12

L-12

Mazdoors for cutting trees including cutting, refilling,


compaction of backfilling and stacking of serviceable
materials within 1000 metres

day

2.000

136.69

273.38

L-13

hour

0.400

282.50

113.00

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

39.85
43.83

Rate for each tree = a+b+c+d


(iv)

259.00

Girth from 900 mm to 1800 mm


a) Labour

b)

2.1

137.00

Girth from 600 mm to 900 mm


a) Labour

b)

2.1

Remarks/
Input ref.

482.18

Girth above 1800 mm


a) Labour
Mate
Mazdoors for cutting trees including cutting, refilling,
compaction of backfilling and stacking of serviceable
materials within 1000 metres
Machinery
Tractor-trolley
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate for each tree = a+b+c+d

say

482.00

day
day

0.160
4.000

151.44
136.69

24.23
546.76

L-12
L-13

hour

0.600

282.50

169.50
74.05
81.45
895.99
896.00

P&M-053

b)

say
2.2

201

Clearing Grass and Removal of Rubbish


Clearing grass and removal of rubbish up to a distance of 50
metres outside the periphery of the area .
By Manual Means
Unit = Hectare
Taking output = 1 Hectare
Page 1 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Labour
Mate
Mazdoor
b) Overhead charges @ 0.1 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Rate per Hectare = a+b+c

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

a)

day
day

2.000
50.000

151.44
136.69

say
2.3

201

Unit = Hectare
Taking output = 1 Hectare
By Manual Means:In area of light jungle
a)

b)

Labour
Mate

day

6.000

151.44

908.64

L-12

Mazdoor

day

150.000

136.69

20503.50

L-13

hour

1.000

282.50

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2386.41

b)

Labour
Mate

day

8.000

151.44

1211.52

L-12

Mazdoor

day

200.000

136.69

27338.00

L-13

hour

2.000

282.50

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

By Mechanical Means

In area of light jungle


a)

b)

P&M-053

3202.60
35228.57
say

(ii)

565.00
2911.45

Rate per Hectare = a+b+c+d

35229.00

Labour
Mate

day

0.160

151.44

24.23

L-12

Mazdoor

day

4.000

136.69

546.76

L-13

hour

10.000

3720.00

37200.00

P&M-014

hour

1.000

282.50

282.50

P&M-053

Machinery
Dozer 80 HP with attachment for removal of trees &
stumps
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

3805.35

d)

Contractor's profit @ 0.1 on (a+b+c)

4185.88

Rate per Hectare = a+b+c+d

46044.72

Add 12% Premium

5525.37

Total =

51570.09
say

34411.00

In area of thorny jungle


a)

2.3 (ii)

P&M-053

26250.51
say

282.50
2169.46

Rate per Hectare = a+b+c+d

2.3

L-12
L-13

Clearing and Grubbing Road Land .


Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth
up to 300 mm, removal of stumps of trees cut earlier and
disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned, up to a lead of
1000 metres including removal and disposal of top organic
soil not exceeding 150 mm in thickness.

(i)

2.3 (i)

302.88
6834.50
713.74
785.11
8636.23
8636.00

49142.00

In area of thorny jungle


a)

b)

Labour
Mate

day

0.240

151.44

36.35

L-12

Mazdoor

day

6.000

136.69

820.14

L-13

hour

12.000

3720.00

44640.00

Machinery
Dozer 80 HP with attachment for removal of trees &
stumps
Page 2 of 264

P&M-014

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Tractor-trolley

Quantity

hour

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1.500

Rate Rs

Cost Rs

282.50

5051.23
55563.49
say

202

P&M-053

4592.02

Rate per Hectare = a+b+c+d


2.4

423.75

Remarks/
Input ref.

55563.00

Dismantling of Structures
Dismantling of existing structures like culverts, bridges,
retaining walls and other structure comprising of masonry,
cement concrete, wood work, steel work, including T&P and
scaffolding wherever necessary, sorting the dismantled
material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000 metres
Unit = cum
Taking output = 1.25 cum
(i)

Lime /Cement Concrete


I

By Manual Means

Lime Concrete, cement concrete grade M-10 and below


a)

b)

Labour
Mate

day

0.040

151.44

6.06

L-12

Mazdoor for dismantling and loading

day

1.000

136.69

136.69

L-13

hour

0.270

282.50

76.28

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

21.90
24.09

Cost for 1.25 cum = a+b+c+d

265.02

Rate per cum = (a+b+c+d)/ 1.25

212.01
say

2.4 (i)

a)

b)

Labour
Mate

day

0.050

151.44

7.57

L-12

Mazdoor for dismantling and loading

day

1.250

136.69

170.86

L-13

hour

0.270

282.50

76.28

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

25.47
28.02

Cost for 1.25 cum = a+b+c+d

308.20

Rate per cum = (a+b+c+d)/ 1.25


2.4 (i)

246.56
say

247.00

Prestressed / Reinforced cement concrete grade M-20 &


above
a) Labour

b)

Mate

day

0.150

151.44

22.72

L-12

Blacksmith

day

0.250

264.50

66.13

L-02

Mazdoor for dismantling, loading and unloading

day

3.500

136.69

478.42

L-13

hour

0.270

282.50

76.28

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

64.35
70.79

Cost for 1.25 cum = a+b+c+d

778.67

Rate per cum = (a+b+c+d)/ 1.25

622.94
say

2.4

212.00

Cement Concrete Grade M-15 & M-20

II

By Mechanical Means for items No. 202( b)& ( c)

Cement Concrete Grade M-15 & M-20


a)

623.00

Labour
Mate

day

0.020

151.44

3.03

L-12

Mazdoor for loading and unloading

day

0.250

136.69

34.17

L-13

Page 3 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor with Pneumatic breaker


b)

Quantity

Rate Rs

Cost Rs

day

0.250

230.00

57.50

L-14

hour

0.670

319.00

213.73

P&M-001

hour

0.270

282.50

76.28

P&M-053

Machinery
Air Compressor 250 cfm with 2 leads of pneumatic
breaker @ 1.5 cum per hour
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

38.47
42.32

Cost for 1.25 cum = a+b+c+d

465.49

Rate per cum = (a+b+c+d)/ 1.25

372.40
say

2.4 II

Mate

day

0.050

151.44

7.57

L-12

Mazdoor with Pneumatic breaker

day

0.660

230.00

151.80

L-14

Blacksmith

day

0.250

264.50

66.13

L-02

Mazdoor for loading and unloading

day

0.250

136.69

34.17

L-13

hour

1.000

319.00

319.00

P&M-001

hour

0.270

282.50

76.28

P&M-053

Machinery
Air Compressor 250 cfm with 2 leads of pneumatic
breaker @ 1.00 cum per hour
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

65.49
72.04

Cost for 1.25 cum = a+b+c+d

792.48

Rate per cum = (a+b+c+d)/ 1.25

633.99
say

(ii)

Dismantling Brick / Tile work

In lime mortar
a)

b)

Mate

day

0.020

151.44

3.03

L-12

Mazdoor for dismantling, loading and unloading

day

0.500

136.69

68.35

L-13

hour

0.270

282.50

76.28

P&M-053

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

14.76
16.24

Cost for 1.25 cum = a+b+c+d

178.66

Rate per cum = (a+b+c+d)/ 1.25

142.92
say

b)

Labour
Mate

day

0.030

151.44

4.54

L-12

Mazdoor for dismantling, loading and unloading

day

0.750

136.69

102.52

L-13

hour

0.270

282.50

76.28

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

18.33
20.17

Cost for 1.25 cum = a+b+c+d

221.84

Rate per cum = (a+b+c+d)/ 1.25

177.47
say

143.00

In cement mortar
a)

2.4 (ii)

634.00

Labour

Tractor-trolley

2.4 (ii)

372.00

Prestressed / reinforced cement concrete grade M-20 &


above
a) Labour

b)

2.4

Remarks/
Input ref.

177.00

In mud mortar
a)

b)

Labour
Mate

day

0.016

151.44

2.42

L-12

Mazdoor for dismantling and loading

day

0.400

136.69

54.68

L-13

hour

0.270

282.50

76.28

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

13.34

d)

Contractor's profit @ 0.1 on (a+b+c)

14.67

Page 4 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Cost for 1.25 cum = a+b+c+d

161.38

Rate per cum = (a+b+c+d)/ 1.25

129.11
say

2.4 (ii)

b)

Labour
Mate

day

0.014

151.44

2.12

L-12

Mazdoor for Dismantling, loading and unloading

day

0.350

136.69

47.84

L-13

hour

0.270

282.50

76.28

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

12.62
13.89

Cost for 1.25 cum = a+b+c+d

152.75

Rate per cum = (a+b+c+d)/ 1.25

122.20
say

(iii)
A

Rubble stone masonry in lime mortar

b)

Labour
Mate

day

0.024

151.44

3.63

L-12

Mazdoor for dismantling, loading and unloading.

day

0.600

136.69

82.01

L-13

hour

0.270

282.50

76.28

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

16.19
17.81

Cost for 1.25 cum = a+b+c+d

195.93

Rate per cum = (a+b+c+d)/ 1.25

156.74
say

b)

Labour
Mate

day

0.030

151.44

4.54

L-12

Mazdoor for dismantling, loading and unloading.

day

0.750

136.69

102.52

L-13

hour

0.270

282.50

76.28

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

18.33
20.17

Cost for 1.25 cum = a+b+c+d

221.84

Rate per cum = (a+b+c+d)/ 1.25

177.47
say

b)

Labour
Mate

day

0.020

151.44

3.03

L-12

Mazdoor for dismantling, loading and unloading.

day

0.500

136.69

68.35

L-13

hour

0.270

282.50

76.28

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

14.76
16.24

Cost for 1.25 cum = a+b+c+d

178.66

Rate per cum = (a+b+c+d)/ 1.25


D

177.00

Rubble Stone Masonry in mud mortar.


a)

2.4 (iii)

157.00

Rubble stone masonry in cement mortar.


a)

2.4 (iii)

122.00

Dismantling Stone Masonry


a)

2.4 (iii)

129.00

Dry brick pitching or brick soling


a)

2.4

Remarks/
Input ref.

142.92
say

143.00

Dry rubble masonry


a)

b)

Labour
Mate

day

0.018

151.44

2.73

L-12

Mazdoor for dismantling, loading and unloading.

day

0.450

136.69

61.51

L-13

hour

0.270

282.50

76.28

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

14.05

d)

Contractor's profit @ 0.1 on (a+b+c)

15.46

Page 5 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Cost for 1.25 cum = a+b+c+d

170.02

Rate per cum = (a+b+c+d)/ 1.25

136.02
say

2.4 (iii)

b)

Labour
Mate

day

0.016

151.44

2.42

L-12

Mazdoor for dismantling, loading and unloading.

day

0.400

136.69

54.68

L-13

hour

0.270

282.50

76.28

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

13.34
14.67

Cost for 1.25 cum = a+b+c+d

161.38

Rate per cum = (a+b+c+d)/ 1.25

129.11
say

b)

Labour
Mate

day

0.020

151.44

3.03

L-12

Mazdoor for dismantling, loading and unloading

day

0.500

136.69

68.35

L-13

hour

0.270

282.50

76.28

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

14.76
16.24

Cost for 1.25 cum = a+b+c+d

178.66

Rate per cum = (a+b+c+d)/ 1.25

142.92
say

(iv)

Mate

day

0.060

151.44

9.09

L-12

Carpenter

day

0.500

264.50

132.25

L-04

Mazdoor for dismantling, loading and unloading.

day

1.000

136.69

136.69

L-13

hour

0.270

282.50

76.28

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

35.43
38.97

Cost for 1.25 cum = a+b+c+d

428.70

Rate per cum = (a+b+c+d)/ 1.25

342.96
say

(v)

143.00

Wood Work wrought framed and fixed in frames of


trusses upto a height of 5 m above plinth level
a) Labour

b)

2.4

129.00

Dismantling boulders laid in wire crates including


opening of crates and stacking dismantled materials.
a)

2.4

136.00

Dismantling stone pitching/ dry stone spalls.


a)

2.4 (iii)

Remarks/
Input ref.

343.00

Steel Work in all types of sections upto a height of 5 m


above plinth level excluding cutting of rivet.
Unit = tonne
Taking output = 1 tonne

Including dismembering
a)

Labour
Mate

day

0.140

151.44

21.20

L-12

Blacksmith

day

1.000

264.50

264.50

L-02

Mazdoor for dismantling, loading and unloading

day

2.500

136.69

341.73

L-13

Add 2.5 per cent of cost of labour for gas cutting, ropes,
pulleys etc.
b) Machinery
Tractor-trolley

15.69

hour

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

0.170

282.50

69.11
76.03

Rate per tonne = a+b+c+d

836.28
say

2.4 (v)

48.03

Excluding dismembering.
Page 6 of 264

836.00

P&M-053

Sr No

Ref. to
MoRTH
Spec.

Description
a)

Unit

Quantity

Rate Rs

Cost Rs

Labour
Mate

day

0.220

151.44

33.32

L-12

Mazdoor for dismantling, loading and unloading

day

2.000

136.69

273.38

L-13

Blacksmith

day

0.500

264.50

132.25

L-02

Add 2.5 per cent of cost of labour for gas cutting, ropes,
pulleys etc.
b) Machinery
Tractor-trolley

10.97

hour

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

0.170

282.50

P&M-053

54.77
602.51
say

48.03
49.79

Rate per tonne = a+b+c+d


2.4 (v)

Remarks/
Input ref.

603.00

Extra over item No( v ) A and( v ) B for cutting rivets.


Unit = each
Taking output = 10 rivets
a)

Labour
Mate

day

0.010

151.44

1.51

L-12

Blacksmith

day

0.130

264.50

34.39

L-02

Mazdoor

day

0.130

136.69

17.77

L-13

b)

Overhead charges @ 0.1 on (a)

5.37

c)

Contractor's profit @ 0.1 on (a+b)

5.90

Cost for 10 rivets = a+b+c

64.94

Rate for each rivet = ( a+b+c)/10

6.49
say

2.4

(vi)

6.00

Scraping of Bricks Dismantled from Brick Work


including Stacking.
Unit = numbers
Taking output = 1000 numbers

In lime/Cement mortar
a)

Labour
Mate

day

0.140

151.44

21.20

L-12

Mazdoor

day

3.500

136.69

478.42

L-13

b)

Overhead charges @ 0.1 on (a)

49.96

c)

Contractor's profit @ 0.1 on (a+b)

54.96

Rate per1000 Nos = a+b+c

604.54
say

2.4 (iv)

a)

Labour
Mate

day

0.050

151.44

7.57

L-12

Mazdoor

day

1.250

136.69

170.86

L-13

b)

Overhead charges @ 0.1 on (a)

17.84

c)

Contractor's profit @ 0.1 on (a+b)

19.63

Rate per1000 Nos = a+b+c

215.91
say

2.4

(vii)

605.00

In mud mortar

216.00

Scraping of Stone from Dismantled Stone Masonry


Unit = cum
Taking output = 1 cum

In cement and lime mortar


a)

Labour
Mate

day

0.060

151.44

9.09

L-12

Mazdoor

day

1.400

136.69

191.37

L-13

b)

Overhead charges @ 0.1 on (a)

20.05

c)

Contractor's profit @ 0.1 on (a+b)

22.05

Rate per cum = a+b+c

242.55
say

2.4 (vii)

In Mud mortar

Page 7 of 264

243.00

Sr No

Ref. to
MoRTH
Spec.

Description
a)

Unit

Quantity

Rate Rs

Cost Rs

Labour
Mate

day

0.010

151.44

1.51

L-12

Mazdoor

day

0.300

136.69

41.01

L-13

b)

Overhead charges @ 0.1 on (a)

4.25

c)

Contractor's profit @ 0.1 on (a+b)

4.68

Rate per cum = a+b+c

51.45
say

2.4

(viii)

Remarks/
Input ref.

51.00

Scarping Plaster in Lime or Cement Mortar from Brick/


Stone Masonry
Unit = sqm
Taking output = 100 sqm
a)

b)

Labour
Mate

day

0.160

151.44

24.23

L-12

Mazdoor for scarping and loading

day

4.000

136.69

546.76

L-13

hour

0.320

282.50

90.40

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

66.14
72.75

Cost for 100 sqm = a+b+c+d

800.28

Rate per sqm = (a+b+c+d)/100

8.00
say

2.4

(ix)

8.00

Removing all type of Hume Pipes and Stacking within a


lead of 1000 metres including Earthwork and
Dismantling of Masonry Works.
Unit = metre
Taking output = 1 metre

Up to 600 mm dia
a)

Labour
Mate

day

0.020

151.44

3.03

L-12

Mazdoor

day

0.520

136.69

71.08

L-13

b)

Overhead charges @ 0.1 on (a)

7.41

c)

Contractor's profit @ 0.1 on (a+b)

8.15

Rate per metre = a+b+c

89.67
say

2.4 (ix)

a)

Labour
Mate

day

0.030

151.44

4.54

L-12

Mazdoor

day

0.700

136.69

95.68

L-13

b)

Overhead charges @ 0.1 on (a)

10.02

c)

Contractor's profit @ 0.1 on (a+b)

11.02

Rate per metre = a+b+c

121.27
say

2.4 (ix)

Labour
Mate

day

0.050

151.44

7.57

L-12

Mazdoor

day

1.200

136.69

164.03

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

17.16
18.88

Rate per metre = a+b+c

207.64
say

2.5

202

121.00

Above 900 mm
a)

Note

90.00

Above 600 mm to 900 mm dia

1. The excavation of earth, dismantling of stone masonry


work in head walls and protection works is not included
which is to be measured and paid separately.
2. Credit for retrieved stone from masonry work may be
taken as per actual availability.
Dismantling of Flexible Pavements
Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 metres, stacking
serviceable and unserviceable materials separately
Page 8 of 264

208.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit = cum
Taking output = 1 cum
I

By Manual Means

Bituminous courses
a)

b)

Labour
Mate

day

0.060

151.44

9.09

L-12

Mazdoor for dismantling, loading and unloading

day

1.500

136.69

205.04

L-13

hour

0.380

282.50

107.35

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

32.15
35.36

Rate per cum = a+b+c+d

388.98
say

2.5 I

a)

b)

Labour
Mate

day

0.040

151.44

6.06

L-12

Mazdoor for dismantling, loading and unloading.

day

1.000

136.69

136.69

L-13

hour

0.330

282.50

93.23

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

23.60
25.96

Rate per cum = a+b+c+d

285.53
say

2.5

II

By Mechanical Means

Bituminous course
a)

b)

Mate

day

0.010

151.44

1.51

L-12

Mazdoor

day

0.300

136.69

41.01

L-13

Tractor-trolley

hour

0.380

282.50

107.35

P&M-053

Farm tractor with ripper @ 60 cum per hour

hour

0.017

282.50

4.80

P&M-055

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

15.47
17.01
187.16
say

202

286.00

Labour

Rate per cum = a+b+c+d


2.6

389.00

Granular courses

187.00

Dismantling of Cement Concrete Pavement


Dismantling of cement concrete pavement by mechanical
means using pneumatic tools, breaking to pieces not
exceeding 0.02 cum in volume and stock piling at
designated locations and disposal of dismantled materials
up to a lead of 1000 metres, stacking serviceable and
unserviceable materials separately
Unit = cum
Taking output = 1 cum
a)

b)

Labour
Mate

day

0.030

151.44

4.54

L-12

Semi skilled mazdoor for operating pneumatic tools

day

0.500

230.00

115.00

L-14

Mazdoors as helpers including loading and unloading

day

0.500

136.69

68.35

L-13

Air compressor 250 cfm with two leads for pneumatic


cutters/ hammers @ 1 cum per hour
Tractor-trolley

hour

1.000

319.00

319.00

P&M-001

hour

0.400

282.50

113.00

P&M-053

Joint Cutting Machine with 2-3 blades

hour

1.000

200.00

200.00

P&M-083

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

81.99
90.19

Rate per cum = a+b+c+d

992.06
say
Page 9 of 264

992.00

Sr No

Ref. to
MoRTH
Spec.

Description
Note

2.7

202

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

The above analysis is for removal of complete pavement. In


case full depth repair work is required to be done after
dismantling, provision of a concrete cutting and sawing
machine may be added for 0.25 hours.
Dismantling of Guard Rails
Dismantling guard rails by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000
metres, stacking serviceable materials and unserviceable
materials separately.
Unit = running metre
Taking output = 1 metre
a)

b)

Labour
Mate

day

0.006

151.44

0.91

L-12

Mazdoor including loading and unloading

day

0.150

136.69

20.50

L-13

hour

0.050

282.50

14.13

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3.55
3.91

Rate per metre = a+b+c+d

43.00
say

2.8

202

43.00

Dismantling of Kerb Stone


Dismantling kerb stone by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000
metre
Unit = running metre
Taking output = 10 metre
a)

b)

Labour
Mate

day

0.010

151.44

1.51

L-12

Mazdoor including loading and unloading

day

0.150

136.69

20.50

L-13

hour

0.200

282.50

56.50

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

7.85
8.64

Cost for 10 m = a+b+c+d

95.01

Rate per metre = (a+b+c+d)/10

9.50
say

2.9

202

10.00

Dismantling of Kerb Stone Channel


Dismantling kerb stone channel by manual means and
disposal of dismantled material with all lifts and up to a lead
of 1000 metre
Unit = running metre
Taking output = 10 metre
a)

b)

Labour
Mate

day

0.015

151.44

2.27

L-12

Mazdoor including loading and unloading

day

0.225

136.69

30.76

L-13

hour

0.300

282.50

84.75

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

11.78
12.96

Cost for 10 m = a+b+c+d

142.51

Rate per metre = (a+b+c+d)/10

14.25
say

2.10

202

Dismantling of Kilometre Stone


Dismantling of kilometre stone including cutting of earth,
foundation and disposal of dismantled material with all lifts
and lead upto 1000 m and back filling of pit.
Unit = Each
Taking output = one KM stone

5th KM stone

Page 10 of 264

14.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Quantity of cement concrete = 0.392 cum


a)

b)

Labour
Mate

day

0.130

151.44

19.69

L-12

Mazdoor

day

0.750

136.69

102.52

L-13

hour

0.150

282.50

42.38

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

16.46
18.10

Rate for one 5th KM stone = a+b+c+d

199.14
say

199.00

Ordinary KM Stone
Quantity of cement concrete = 0.269 cum
a)

b)

Labour
Mate

day

0.020

151.44

3.03

L-12

Mazdoor

day

0.500

136.69

68.35

L-13

hour

0.100

282.50

28.25

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

9.96
10.96

Rate for one ordinary KM stone = a+b+c+d

120.54
say

121.00

Hectometre Stone
Quantity of cement concrete = 0.048 cum
a)

b)

Labour
Mate

day

0.004

151.44

0.61

L-12

Mazdoor

day

0.100

136.69

13.67

L-13

hour

0.020

282.50

5.65

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

1.99

d)

Contractor's profit @ 0.1 on (a+b+c)

2.19

Rate for one Hectometre stone = a+b+c+d

24.11
say

2.11

202

24.00

Dismantling of Fencing
Dismantling of barbed wire fencing/ wire mesh fencing
including posts, foundation concrete, back filling of pit by
manual means including disposal of dismantled material with
all lifts and up to a lead of 1000 metres, stacking serviceable
material and unserviceable material separately.
Unit = running metre
Taking output = 30 metres
a)

b)

Labour
Mate

day

0.150

151.44

22.72

L-12

Mazdoor including loading and unloading

day

3.000

136.69

410.07

L-13

Blacksmith

day

0.750

264.50

198.38

L-02

hour

0.150

282.50

42.38

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

67.35
74.09

Cost for 30 metres = a+b+c+d

814.98

Rate per metre = (a+b+c+d)/30

27.17
say

2.12

202

Dismantling of CI Water Pipe Line


Dismantling of CI water pipe line 600 mm dia including
disposal with all lifts and lead upto 1000 metres and stacking
of serviceable material and unserviceable material
separately under supervision of concerned department

Page 11 of 264

27.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit = running metre


Taking output = 10 metres
a)

b)

Labour
Mate

day

0.090

151.44

13.63

L-12

Mazdoor

day

2.000

136.69

273.38

L-13

Plumber

day

0.250

264.50

66.13

L-02

Truck 10 tonne capacity

hour

0.250

315.27

78.82

P&M-057

Light Crane 3 tonne capacity

hour

0.500

357.00

178.50

P&M-013

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

61.05
67.15

Cost for 10 metres = a+b+c+d

738.65

Rate per metre = (a+b+c+d)/10

73.86
say

Note

2.13

202

74.00

The rate analysis does not include any excavation in earth or


dismantling of masonry works which are to be measured and
paid separately.
Removal of Cement Concrete Pipe of Sewer Gutter
Removal of cement concrete pipe of sewer gutter 1500 mm
dia under the supervision of concerned department including
disposal with all lifts and up to a lead of 1000 metres and
stacking of serviceable and unserviceable material
separately but excluding earth excavation and dismantling of
masonry works.
Unit = running metre
Taking output = 10 metres
a)

b)

Labour
Mate

day

0.100

151.44

15.14

L-12

Mazdoor

day

2.500

136.69

341.73

L-13

Crane 5 tonne capacity

hour

0.300

116.53

34.96

P&M-070

Truck flat body 10 tonne

hour

1.000

315.27

315.27

P&M-057

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

70.71
77.78

Cost for 10 metres = a+b+c+d

855.59

Rate per metre = (a+b+c+d)/10

85.56
say

Note

2.14

202

86.00

The rate analysis does not include any excavation in earth or


dismantling of masonry works which are to be measured and
paid separately.
Removal of Telephone / Electric Poles and Lines
Removal of telephone / Electric poles including excavation
and dismantling of foundation concrete and lines under the
supervision of concerned department, disposal with all lifts
and up to a lead of 1000 metres and stacking the
serviceable and unserviceable material separately
Unit = each
Taking output = 30 Nos
a)

b)

Labour
Mate

day

0.480

151.44

72.69

L-12

Mazdoor

day

10.000

136.69

1366.90

L-13

Electrician/Lineman

day

2.000

264.50

529.00

L-02

hour

1.500

282.50

423.75

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Cost for 30 poles = a+b+c+d

239.23
263.16
2894.73

Rate per pole = (a+b+c+d)/30

96.49

Add 5% Premium

4.82

Page 12 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Total =

101.32
say

Page 13 of 264

101.00

Remarks/
Input ref.

CHAPTER - 3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Sr No

Ref. to
MoRTH
Spec.

3.1

301

Description

Unit

Note

301

Remarks/
Input ref.

day
day

1.800
45.000

151.44
136.69

272.59
6151.05

L-12
L-13

hour

10.000

315.27

P&M-057

say

3152.70
957.63
1053.40
11587.37
96.56
97.00

Excavation in Ordinary Rock by Manual Means


Excavation in ordinary rock using manual means including
loading in a truck and carrying of excavated material to
embankment site with in all lifts and leads upto 1000 metres

Note

301

Cost Rs

In case there is a situation where the cross-section is of cut


and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted.

Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor
b) Machinery
Truck 5.5 cum capacity
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120

3.3

Rate Rs

Excavation in Soil by Manual Means .


Excavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000 metres.
Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor
b) Machinery
Truck 5.5 cum capacity
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost of 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120

3.2

Quantity

day
day

2.800
70.000

151.44
136.69

424.03
9568.30

L-12
L-13

hour

10.000

315.27

P&M-057

say

3152.70
1314.50
1445.95
15905.49
132.55
133.00

In case there is a situation where the cross-section is of cut


and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted.
Excavation in Soil with Dozer with lead upto 100 metres
Excavation for road way in soil by mechanical means
including cutting and pushing the earth to site of
embankment upto a distance of 100 metres (average lead50
metres), including trimming bottom and side slopes in
accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 180 cum
a) Labour
Mate
Mazdoor
b) Machinery
Dozer, 80 HP @ 30 cum per hour
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 180 cum = a+b+c+d
Rate per cum = (a+b+c+d)/180

day
day

0.080
2.000

151.44
136.69

12.12
273.38

hour

6.000

3720.00

22320.00
2260.55
2486.60
27352.65
151.96
152.00

say

Page 1 of 264

L-12
L-13
P&M-014

Sr No

Ref. to
MoRTH
Spec.

3.4

301

Description

Unit

Quantity

Rate Rs

Cost Rs

Excavation in Ordinary Rock with Dozer with lead upto


100 metres
Excavation for roadway in ordinary rock by deploying a
dozer, 80 HP including cutting and pushing the cut earth to
site of embankment upto a distance of 100 metres ( average
lead 50 metres ), trimming bottom and side slopes in
accordance with the requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 108 cum
a) Labour
Mate
Mazdoor
b) Machinery
Dozer, 80 HP @ 20 cum per hour
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 108 cum = a+b+c+d
Rate per cum = (a+b+c+d)/108

day
day

0.120
3.000

151.44
136.69

18.17
410.07

hour

6.000

3720.00

22320.00
2274.82
2502.31
27525.37
254.86
255.00

say
3.5

Remarks/
Input ref.

L-12
L-13
P&M-014

Excavation in Hard Rock (requiring blasting)


with
disposal upto 1000 metres
Excavation for roadway in hard rock (requiring blasting)
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres

301

Unit = cum
Taking 0utput = 180 cum
a)

b)

c)

Labour
Mate

day

0.220

151.44

33.32

L-12

Mazdoor

day

3.000

136.69

410.07

L-13

Driller

day

2.000

264.50

529.00

L-06

Blaster

day

0.250

264.50

66.13

L-03

Dozer, 80 HP @ 30 cum per hour

hour

6.000

3720.00

22320.00

P&M-014

Air compressor, 250 cfm with 2 jack hammer

hour

6.000

319.00

1914.00

P&M-001

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

Tipper10 tonne capacity

hour

11.250

339.00

3813.75

P&M-048

9198.00

M-104

Machinery

Materials
Gelatin 80 per cent

d)

Electric Detonators @ 1 detonator for 2 gelatin sticks of


125 gms each
Credit for excavated rock found suitable for use @ 50
per cent quantity blasted
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

kg

63.000

146.00

each

252.000

14.56

cum

90.000

(37.00)

(3330.00)
4345.94
4780.53

Cost for 180 cum = a+b+c+d+e

52585.85

Rate per cum = (a+b+c+d+e)/180

292.14
say

Note

3669.12 M-094 /100

1. The quality and availability of rock shall be checked


before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced/restricted to that extent.

Page 2 of 264

292.00

M-089

Sr No

Ref. to
MoRTH
Spec.

3.6

301

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Excavation in Soil using Hydraulic Excavator CK 90 and


Tippers with Disposal upto 1000 metres.
Excavation for roadwork in soil with hydraulic excavator of
0.9 cum bucket capacity including cutting and loading in
tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts and
lead upto 1000m
Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

0.080

151.44

12.12

L-12

Mazdoor

day

2.000

136.69

273.38

L-13

hour

6.000

1302.00

7812.00

P&M-026

hour

16.000

339.00

5424.00

P&M-048

Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 60
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1352.15
1487.36

Cost for 360 cum = a+b+c+d

16361.01

Rate per cum = (a+b+c+d)/360

45.45
say

3.7

45.00

Excavation in Ordinary Rock using Hydraulic Excavator


CK-90 and Tippers with Disposal upto 1000 metres.

301

Excavation for roadway in ordinary rock with hydraulic


excavator of 0.9 cum bucket capacity including cutting and
loading in tippers, transporting to embankment site within all
lifts and lead upto 1000 m, trimming bottom and side slopes
in accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 240 cum
a)

b)

Labour
Mate

day

0.080

151.44

12.12

L-12

Mazdoor

day

2.000

136.69

273.38

L-13

hour

6.000

1302.00

7812.00

P&M-026

hour

11.000

339.00

3729.00

P&M-048

Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ 36
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1182.65
1300.91

Cost for 240 cum = a+b+c+d

14310.06

Rate per cum = (a+b+c+d)/240

59.63
say

3.8

301

60.00

Excavation in Hard Rock (blasting prohibited)


Excavation for roadway in hard rock (blasting prohibited)
with rock breakers including breaking rock, loading in tippers
and disposal within all lifts and lead upto 1000 metres,
trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.
A

Mechanised
Unit = cum
Taking output = 36 cum
a)

Labour
Mate

day

0.400

151.44

60.58

L-12

Mazdoor for trimming slopes including mannul loading


in truck
Machinery

day

10.000

136.69

1366.90

L-13

Hydraulic excavator with rock breaker attachment @ 6


cum per hour
Tipper 5.5 cum capacity, 1 trip per hour.

hour

6.000

1302.00

7812.00

P&M-026

hour

6.500

339.00

2203.50

P&M-048

cum

18.000

(37.00)

(666.00)

M-089

c)

Credit for excavated rock found suitable for use @ 50


per cent of excavated quantity
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

b)

1077.70
1185.47

Cost for 36 cum = a+b+c+d

13040.14

Rate per cum = (a+b+c+d)/36

362.23
say

Note

1. The quality and availability of rock shall be checked


before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be restricted/reduced to that extent.
3.Being small quantity, manual loading will be economical in
this case and has been provided accordingly.

Page 3 of 264

362.00

Sr No

Ref. to
MoRTH
Spec.

3.8

Description
B

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Manual Method
Unit = cum
Taking output = 16 cum
a)

Labour
Mate

day

1.640

151.44

248.36

L-12

Mazdoor including loading in truck

day

16.000

136.69

2187.04

L-13

Chiseller

day

24.000

264.50

6348.00

L-05

Blacksmith

day

1.000

264.50

264.50

L-02

Tipper 5.5 cum capacity, 1 trip per hour.

hour

2.900

339.00

983.10

P&M-048

cum

8.000

(37.00)

(296.00)

M-089

c)

Credit for excavated rock found suitable for use @ 50


per cent of excavated
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

b)

Machinery

973.50
1070.85

Cost for 16 cum = a+b+c+d

11779.35

Rate per cum = (a+b+c+d)/16

736.21
say

Note

736.00

1. Credit is considered for 50 per cent of quantity of work.


2. Loading for disposal will be done manually, being small
quantity.
3. In case some rock is issued to contractor at site, the item
of carriage shall be omitted to the extent of quantity issued
to the contractor.

3.9

301

Excavation in Hard Rock (controlled blasting) with


disposal upto 1000 metres
Excavation for roadway in hard rock with controlled blasting
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres
Unit = cum
Taking output = 180 cum
a)

b)

c)

Labour
Mate

day

0.220

151.44

33.32

L-12

Mazdoor

day

3.000

136.69

410.07

L-13

Driller

day

2.000

264.50

529.00

L-06

Blaster

day

0.500

264.50

132.25

L-03

Dozer 80 HP @ 30 cum per hour

hour

6.000

3720.00

22320.00

P&M-014

Air compressor, 250 cfm with 2 jack hammers

hour

6.000

319.00

1914.00

P&M-001

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

Tipper 5.5 cum capacity, 4 trips per hour.

hour

8.200

339.00

2779.80

P&M-048

9198.00

M-104

Machinery

Materials
Gelatin 80 per cent
Electric Detonators @ 1 detonator for1/2 gelatin stick
of 125 gms each
Credit for excavated rock found suitable for use @ 50
per cent quantity blasted
Add 5 per cent of cost of a+b+c towards muffling
arrangements to guard against any rock fly off during
blasting

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

kg

63.000

146.00

each

1008.000

14.56

cum

90.000

(37.00)

6197.44
68171.84
378.73
say

301

M-089

5634.04

Rate per cum = (a+b+c+d+e)/180

3.10

(3330.00)
2841.45

Cost for 180 cum = a+b+c+d+e

Note

14676.48 M-094 /100

379.00

1. Credit is considered for 50 per cent of quantity of


blastered rock, if found suitable for construction..
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced to that extent.
Excavation in Marshy Soil
Excavation for roadway in marshy soil with hydraulic
excavator 0.9 cum bucket capacity including cutting and
loading in tippers and disposal with in all lifts and lead upto
1000 metres, trimming of bottom and side slopes in
accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 300 cum
a)

b)

Labour
Mate

day

0.080

151.44

12.12

L-12

Mazdoor

day

2.000

136.69

273.38

L-13

hour

6.000

1302.00

7812.00

P&M-026

hour

13.640

339.00

4623.96

P&M-048

Machinery
Hydraulic excavator 0.90 cum bucket capacity @ 50
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1272.15
1399.36

Cost for 300 cum = a+b+c+d

15392.96

Rate per cum = (a+b+c+d)/300

51.31
say
Page 4 of 264

51.00

Sr No

Ref. to
MoRTH
Spec.

3.11

301

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Removal of Unserviceable Soil with Disposal upto 1000


metres
Removal of unserviceable soil including excavation, loading
and disposal upto 1000 metres lead but excluding
replacement by suitable soil which shall be paid separately
as per clause 305.
Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

0.080

151.44

12.12

L-12

Mazdoor

day

2.000

136.69

273.38

L-13

Excavator0.90 cum bucket capacity @ 60 cum per hour

hour

6.000

1302.00

7812.00

P&M-026

Tipper 5.5 cum capacity, 4 trips per hour.

hour

16.360

339.00

5546.04

P&M-048

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1364.35
1500.79

Cost for 360 cum = a+b+c+d

16508.68

Rate per cum = (a+b+c+d)/360

45.86
say

Note

3.12

303

46.00

This item does not include replacement of unsuitable soil by


suitable soil. Replacement, where required, is to be provided
and paid separately under clause 305.
Presplitting of Rock Excavation Slopes
Carrying out excavation in hard rock to achieve a specified
slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill
holes, collection of the excavated rock by a 80 HP dozer,
loading in tipper by a front end loader and disposing of the
material with all lifts and lead upto 1000 m, all as specified in
clause No. 303
Unit = sqm
Taking output = 400 sqm( 120 cum considering 300mm
average depth of excavation over the existing rock face)
a)

b)

c)

Labour
Mate

day

0.600

151.44

90.86

L-12

Mazdoor

day

15.000

136.69

2050.35

L-13

Air compressor 250 cfm with 2 leads @ 20 cum per


hour
Dozer, 80 HP

hour

6.000

319.00

1914.00

P&M-001

hour

6.000

3720.00

22320.00

P&M-014

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

kg

42.000

146.00

6132.00

M-104

each

672.000

14.56

Machinery

Materials
Gelatin 80 per cent

d)

Electric Detonators @ 1 detonator for 1/2 gelatin stick


of 125 gms each
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

4712.75
5184.03

Cost for 400 sqm = a+b+c+d+e

57024.32

Rate per sqm = (a+b+c+d+e)/400

142.56
say

Note

3.13

304

9784.32 M-094 /100

143.00

In case blasted rock is used to the contractor against


payment for constructed work, the cost of carriage shall be
reduced to that extent.
Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work.

(i)

Ordinary soil
Unit = cum
Taking output = 10 cum

Manual Means (Depth upto 3 m)


a)

Labour
Mate

day

0.320

151.44

48.46

L-12

Mazdoor

day

8.000

136.69

1093.52

L-13

b)

Overhead charges @ 0.1 on (a)

114.20

c)

Contractor's profit @ 0.1 on (a+b)

125.62

Cost for 10 cum = a+b+c

1381.80

Rate per cum = (a+b+c)/10


Note

3.13 (i)

138.18
say

138.00

151.44

48.46

Cost of dewatering may be added where required upto 10


per cent of labour cost Assessment for dewatering shall be
made as per site conditions..
Mechanical Means (Depth upto 3 m)
Unit = cum
Taking output = 300 cum
a)

Labour
Mate

day
Page 5 of 264

0.320

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor
b)

Quantity

Rate Rs

Cost Rs

day

8.000

136.69

1093.52

L-13

hour

6.000

1302.00

7812.00

P&M-026

Machinery
Hydraulic excavator 1.0 cum bucket capacity

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

895.40
984.94

Cost for 300 cum = a+b+c+d

10834.32

Rate per cum = (a+b+c+d)/300

36.11
say

Note

3.13

Remarks/
Input ref.

36.00

Cost of dewatering upto 5 per cent of (a+b)


may be
added, where required. Assessment for dewatering shall be
made as per site conditions..

(ii)

Ordinary Rock (not requiring blasting)

Manual Means (Depth upto 3 m)


Unit = cum
Taking output = 10 cum
a)

Labour
Mate

day

0.400

151.44

60.58

L-12

Mazdoor

day

10.000

136.69

1366.90

L-13

b)

Overhead charges @ 0.1 on (a)

142.75

c)

Contractor's profit @ 0.1 on (a+b)

157.02

Cost for 10 cum = a+b+c

1727.25

Rate per cum = (a+b+c)/10

172.72
say

Note

3.13 (ii)

173.00

Cost of dewatering upto 10 per cent of labour cost may be


added, where required. Assessment for dewatering shall be
made as per site conditions..
Mechanical Means
Unit = cum
Taking output = 216 cum
a)

b)

Labour
Mate

day

0.240

151.44

36.35

L-12

Mazdoor

day

6.000

136.69

820.14

L-13

hour

6.000

1302.00

7812.00

P&M-026

Machinery
Hydraulic excavator 1.0 cum bucket capacity

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

866.85
953.53

Cost for 216 cum = a+b+c+d

10488.87

Rate per cum = (a+b+c+d)/216

48.56
say

Note

3.13

(iii)
A

49.00

1.Cost of dewatering upto 5 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
Hard Rock ( requiring blasting )
Manual Means
Unit = cum
Taking output = 10 cum
a)

Labour
i) Mate

day

0.530

151.44

80.26

L-12

ii) Driller

day

0.840

264.50

222.18

L-06

iii) Blaster

day

0.400

264.50

105.80

L-03

iv) Mazdoor

day

12.000

136.69

1640.28

L-13

hour

0.667

319.00

212.67

P&M-001

kg

3.500

146.00

511.00

M-104

each

14.000

14.56

b)

Machinery

c)

Air Compressor 250 cfm with 2 jack hammer @ 15 cum


per hour
Material
Blasting Material
Detonator electric

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

297.60
327.36

Cost for 10 cum = a+b+c+d+e

3601.00

Rate per cum = (a+b+c+d+e)/10

360.10
say

Note

3.13

(iv)

203.84 M-094 /100

360.00

Cost of dewatering @ 10 per cent of labour cost may be


added, where required Assessment for dewatering shall be
made as per site conditions.
Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum

Mechanical Means
a)

b)

Labour
Mate

day

0.200

151.44

30.29

L-12

Mazdoor

day

5.000

136.69

683.45

L-13

hour

10.000

319.00

3190.00

P&M-001

Machinery
Air Compressor 250 cfm with 2 leads of pneumatic
breaker @ 1 cum per hour
Page 6 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Quantity

Rate Rs

Cost Rs
390.37
429.41

Cost for 10 cum = a+b+c+d

4723.52

Rate per cum = (a+b+c+d)/10

472.35
say

Note

3.13

(v)

Remarks/
Input ref.

472.00

1. Cost of dewatering upto 5 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug and
hence not included.
Marshy soil
Unit = cum
Taking output = 10 cum

Manual means ( upto 3 m depth)


a)

b)

Labour
Mate/Supervisor

day

0.400

151.44

60.58

L-12

Mazdoor

day

10.000

136.69

1366.90

L-13

hour

2.670

282.50

754.28

P&M-053

cum

5.000

43.00

215.00

M-163

Machinery
Tractor-trolley

c)

Material
Selected earth for refilling

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

239.68
263.64

Cost for 10 cum = a+b+c+d+e

2900.07

Rate per cum = ( a+b+c+d+e)/ 10

290.01
say

Note

290.00

1. Cost of dewatering @ 30 per cent of (a), may be added,


where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 20 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil

3.13 (v)

Mechanical Means
a)

b)

Labour
i) Mate

day

0.080

151.44

12.12

L-12

ii) Mazdoor for dressing sides, bottom and backfilling

day

2.000

136.69

273.38

L-13

hour

0.170

1302.00

221.34

P&M-026

hour

0.450

339.00

152.55

P&M-048

cum

5.000

43.00

215.00

M-163

Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Material
Selected earth for refilling

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

87.44
96.18

Cost for 10 cum = a+b+c+d+e

1058.01

Rate per cum = (a+b+c+d+e)/10

105.80
say

Note

3.14

106.00

1. Cost of dewatering @ 20 per cent of (a+b) may be


added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
Scarifying Existing Granular Surface to a Depth of 50
mm by Manual Means
Scarifying the existing granular road surface to a depth of 50
mm and disposal of scarified material within all lifts and
leads upto 1000 metres.

305.4.3

Unit = sqm
Taking output = 100 sqm
a)

b)

Labour
Mate

day

0.200

151.44

30.29

L-12

Mazdoor including loading and unloading

day

5.000

136.69

683.45

L-13

hour

1.670

282.50

471.78

P&M-053

Machinery
Tractor-trolley

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

118.55
130.41

Cost for 100 sqm = a+b+c+d

1434.47

Rate per sqm = (a+b+c+d)/100

14.34
say

Note
3.15

305.4.3

In case material is to be reused at site, transportation cost


catered above for disposal shall be deleted.
Scarifying Existing Bituminous Surface to a depth of 50
mm by Mechanical Means
Scarifying the existing bituminous road surface to a depth of
50 mm and disposal of scarified material with in all lifts and
lead upto 1000 metres.
Unit = sqm
Page 7 of 264

14.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 100 sqm


a)

b)

Labour
Mate

day

0.010

151.44

1.51

L-12

Mazdoor

day

0.250

136.69

34.17

L-13

Tractor with ripper attachment @ 60 cum per hour

hour

0.080

282.50

22.60

P&M-055

Front end loader 1 cum bucket capacity @ 25 cum per


hour
Tipper 5.5 cum capacity, 4 trips per hour.

hour

0.200

806.00

161.20

P&M-017

hour

0.230

339.00

77.97

P&M-048

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

29.75
32.72

Cost for 100 sqm = a+b+c+d

359.92

Rate per sqm = (a+b+c+d)/100

3.60
say

3.16

4.00

Construction of Embankment with Material obtained


from Borrowpits
Construction of embankment with approved material
obtained from borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and compacting
to meet requirement of table 300-2.

305

Unit = cum
Taking output = 100 cum
a)

b)

Labour
Mate

day

0.040

151.44

6.06

L-12

Mazdoor

day

1.000

136.69

136.69

L-13

hour

1.670

1302.00

2174.34

P&M-026

tonne.km

160 x L

2.46

7864.80

Lead =20
km & P&M058

Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum
per hour
Tipper 10 tonne capacity

c)

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour

786.48
hour

0.500

3720.00

1860.00

P&M-014

Motor grader for grading @ 100 cum per hour

hour

1.000

2395.00

2395.00

P&M-032

Water tanker6 KL capacity

hour

4.000

200.00

800.00

P&M-060

Vibratory roller 8 -10 tonnes @ 100 cum per hour

hour

1.000

1541.00

1541.00

P&M-059

KL

24.000

10.00

240.00

M-189

cum

100.000

28.00

2800.00

M-092

Material
Cost of water
Compensation for earth taken from private land

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2060.44
2266.48

Cost for 100 cum = a+b+c+d+e

24931.28

Rate per cum = (a+b+c+d+e)/100

249.31
say

Note

3.17

305

249.00

Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
Construction of Embankment with Material Deposited
from Roadway Cutting
Construction of embankment with approved materials
deposited at site from roadway cutting and excavation from
drain and foundation of other structures graded and
compacted to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a)

b)

c)

Labour
Mate

day

0.020

151.44

3.03

L-12

Mazdoor

day

0.500

136.69

68.35

L-13

Dozer 80 HP for spreading @ 200 cum per hour

hour

0.500

3720.00

1860.00

P&M-014

Motor grader for grading @ 100 cum per hour

hour

1.000

2395.00

2395.00

P&M-032

Water tanker6 KL capacity

hour

4.000

200.00

800.00

P&M-060

Vibratory roller 8-10 tonnes @ 100 cum per hour

hour

1.000

1541.00

1541.00

P&M-059

KL

24.000

10.00

240.00

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

690.74
759.81

Rate for 100 cum = a+b+c+d+e

8357.92

Rate per cum = (a+b+c+d+e)/100

83.58
say

Note

3.18

305

In case the earth cutting is done by dozer and pushed for


filling in the embankment, the input of dozer in the cost of
embankment shall be deleted as the same is already
provided in the cost of excavation. However, if the earth is
dumped by tippers from roadway cutting, the input of dozer
for spreading is required to be provided.
Construction of Subgrade and Earthen Shoulders

Page 8 of 264

84.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Construction of sub-grade and earthen shoulders with


approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No. 3002
Unit = cum
Taking output = 100 cum
a)

b)

Labour
Mate

day

0.040

151.44

6.06

L-12

Mazdoor

day

1.000

136.69

136.69

L-13

hour

1.670

1302.00

2174.34

P&M-026

tonne.km

175xL

2.46

8602.13

Lead =20
km & P&M058

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour

hour

0.500

3720.00

1860.00

P&M-014

Motor grader for grading @ 50 cum per hour

hour

2.000

2395.00

4790.00

P&M-032

Water tanker with 6 km lead

hour

4.000

200.00

800.00

P&M-060

Vibratory roller 8-10 tonnes @ 80 cum per hour

hour

1.250

1541.00

1926.25

P&M-059

KL

24.000

10.00

240.00

M-189

cum

100.000

28.00

2800.00

M-092

Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum
per hour
Tipper 10 tonne capacity

c)

860.21

Material
Cost of water
Compensation for earth taken from private land

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2419.57
2661.52

Cost for 100 cum = a+b+c+d+e

29276.77

Rate per cum = (a+b+c+d+e)/100

292.77
say

3.19

305.3.4

293.00

Compacting Original Ground


Case-I Compacting original ground supporting sub-grade
Loosening of the ground upto a level of 500 mm below the
sub-grade level, watered, graded and compacted in layers to
meet requirement of table 300-2 for sub-grade construction.
Unit = cum
Taking output = 600 cum
a)

b)

c)

Labour
Mate

day

0.120

151.44

18.17

L-12

Mazdoor

day

3.000

136.69

410.07

L-13

Tractor with ripper attachment

hour

9.000

282.50

2542.50

P&M-055

Motor grader for grading

hour

6.000

2395.00

14370.00

P&M-032

Water tanker 6 KL capacity

hour

4.000

200.00

800.00

P&M-060

Vibratory roller 8-10 tonne @ 80 cum/hour

hour

7.500

1541.00

11557.50

P&M-059

KL

24.000

10.00

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

M-189

3293.21

Cost for 600 cum = a+b+c+d+e

36225.27

Rate per cum = (a+b+c+d+e)/600

60.38
say

3.19

240.00
2993.82

60.00

Case-II :Compacting original ground supporting embankment


Loosening, leveling and Compacting original ground
supporting embankment to facilitate placement of first layer
of embankment, scarified to a depth of 150 mm, mixed with
water at OMC and then compacted by rolling so as to
achieve minimum dry density as given in Table 300-2 for
embankment construction.
Unit = cum
Taking output = 600 cum
a)

b)

c)

Labour
Mate

day

0.080

151.44

12.12

L-12

Mazdoor

day

2.000

136.69

273.38

L-13

Tractor with ripper attachment

hour

6.000

282.50

1695.00

P&M-055

Vibratory road roller 8-10 tonne capacity

hour

7.500

1541.00

11557.50

P&M-059

Water tanker6 KL capacity

hour

4.000

200.00

800.00

P&M-060

KL

24.000

10.00

240.00

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1457.80
1603.58

Cost for 600 cum = (a+b+c+d+e)

17639.37

Rate per sqm = (a+b+c+d+e)/600

29.40
say

3.20

305

Stripping and Storing Top Soil

Page 9 of 264

29.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Stripping, storing of top soil by road side at 15 m internal and


re-application on embankment slopes, cut slopes and other
areas in localities where the available embankment material
is not conducive to plant growth.
Unit = cum
Taking output = 10 cum
a)

b)

Labour
Mate

day

0.200

151.44

30.29

L-12

Mazdoor

day

5.000

136.69

683.45

L-13

hour

0.100

3720.00

372.00

P&M-014

Machinery
Dozer 80 HP @ 100 cum per hour

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

108.57
119.43

Cost for 10 cum = (a+b+c+d)

1313.74

Rate per cum = (a+b+c+d)/10

131.37
say

131.00

Stripping, Storing and Re-laying Top Soil from Borrow


Areas in Agriculture Fields.
Stripping of top soil from borrow areas located in agriculture
fields, storing at a suitable place, spreading and re-laying
after taking the borrow earth to maintain fertility of the
agricultural field, finishing it to the required levels and
satisfaction of the farmer.

3.21

Unit = cum
Taking output = 300 cum
a)

b)

Labour
Mate

day

0.080

151.44

12.12

L-12

Mazdoor

day

2.000

136.69

273.38

L-13

hour

6.000

3720.00

22320.00

Machinery
Dozer, 80 HP

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2486.60

Cost for 300 cum = (a+b+c+d)

27352.65

Rate per cum = (a+b+c+d)/300

91.18
say

3.22

307

P&M-014

2260.55

91.00

Turfing with Sods


Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of sods
and watering.
Unit = sqm
Taking output = 100 sqm
a)

b)

c)

Labour
Mate

day

0.120

151.44

18.17

L-12

Mazdoor for preparation of ground and fetching of sods

day

3.000

136.69

410.07

L-13

Water tanker including watering for 3 months

hour

2.000

200.00

400.00

P&M-060

Tractor-trolley

hour

1.000

282.50

282.50

P&M-053

cum

0.180

364.00

65.52

M-167

KL

12.000

10.00

120.00

M-189

Machinery

Material
Farm yard manure @ 0.18 cum per 100 sqm at site of
work
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

129.63
142.59

Cost for 100 sqm = a+b+c+d+e

1568.48

Rate per 100 sqm = (a+b+c+d+e)/100

15.68
say

3.23

308

16.00

Seeding and Mulching


Preparation of seed bed on previously laid top soil,
furnishing and placing of seeds, fertilizer, mulching material,
applying bituminous emulsion at the rate of 0.23 litres per
sqm and laying and fixing jute netting, including watering for
3 months all as per clause 308.
Unit = sqm
Taking output = 240 sqm
a)

b)

Labour
Mate

day

0.400

151.44

60.58

L-12

Mazdoor

day

10.000

136.69

1366.90

L-13

hour

14.000

200.00

2800.00

P&M-060

hour

2.400

282.50

678.00

P&M-053

Machinery
Water tanker 6 KL capacity including watering for 3
months
Tractor-trolley

c)

Material
Seeds

kg

3.600

243.00

874.80

M-162

Sludge/Farm yard manure @ 0.18 cum per 100 sqm

cum

0.430

364.00

156.52

M-167

Bitumen Emulsion

litre

55.200

49.92

2755.31

M-077

Jute netting, open weave, 2.5 cm square opening

sqm

264.000

61.00

16104.00

M-121

KL

84.000

10.00

840.00

M-189

Cost of water for 3 months


Page 10 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Quantity

Rate Rs

Cost Rs
2563.61
2819.97

Cost for 240 sqm = a+b+c+d+e

31019.69

Rate per sqm = (a+b+c+d+e)/240

129.25
say

3.24

309

Remarks/
Input ref.

129.00

Surface Drains in Soil


Construction of unlined surface drains of average cross
sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301 and
309. Excavated material to be used in embankment within a
lead of 50 metres (average lead 25 metres)
Unit = metre
Taking output = 10 metres
A

Mechanical means
a)

Labour
Mate

day

0.010

151.44

1.51

L-12

Mazdoor for dressing of bed and side of drain

day

0.250

136.69

34.17

L-13

hour

0.330

1302.00

429.66

P&M-026

b)

Machinery

c)

Hydraulic Excavator 0.3 cum bucket capacity @ 30


metres per hour
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

46.53
51.19

Cost for 10 metres = a+b+c+d

563.07

Rate per metre = (a+b+c+d)/10

56.31
say

3.24

a)

Labour
Mate

day

0.080

151.44

12.12

L-12

Mazdoor

day

2.000

136.69

273.38

L-13

b)

Overhead charges @ 0.1 on (a)

28.55

c)

Contractor's profit @ 0.1 on (a+b)

31.40

Cost for 10 metres = a+b+c

345.45

Rate per metre = (a+b+c)/10

34.54
say

Note

3.25

309

56.00

Manual Means

35.00

Where lining of drain is provided, quantity shall be worked


out based on approved design and drawing and priced on
rate of cement concrete of approved grade or stone/brick
masonry as the case may be.
Surface Drains in Ordinary Rock
Construction of unlined surface drain of average cross
sectional area 0.4 sqm in ordinary rock to specified lines,
grades, levels and dimensions as per approved design and
to the requirement of clause 301 to 309. Excavated material
to be used in embankment at site.
Unit = metre
Taking output = 10 metres

Mechanical Means
a)

Labour
Mate

day

0.020

151.44

3.03

L-12

Mazdoor for dressing of bed and side of drain

day

0.500

136.69

68.35

L-13

hour

0.670

1302.00

872.34

P&M-026

b)

Machinery

c)

Hydraulic Excavator 0.3 cum bucket capacity @ 15


metres per hour
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

94.37
103.81

Cost for 10 metres = a+b+c+d

1141.89

Rate per metre = (a+b+c+d)/10

114.19
say

3.25

a)

Labour
Mate

day

0.120

151.44

18.17

L-12

Mazdoor

day

3.000

136.69

410.07

L-13

b)

Overhead charges @ 0.1 on (a)

42.82

c)

Contractor's profit @ 0.1 on (a+b)

47.11

Cost for 10 metres = a+b+c

518.17

Rate per metre = (a+b+c)/10

51.82
say

3.26

3.27

114.00

Manual Means

309

Surface Drains in Hard Rock

309

Rate per metre may be worked out based on quantity of


hard rock as per design.
For rate of hard rock cutting, refer relevant item in this
chapter
Sub-Surface Drains with Perforated Pipe

Page 11 of 264

52.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Construction of subsurface drain with perforated pipe of 100


mm internal diameter of metal/ asbestos cement/ cement
concrete/PVC, closely jointed, perforations ranging from 3
mm to 6 mm depending upon size of material surrounding
the pipe, with 150 mm bedding below the pipe and 300 mm
cushion above the pipe, cross section of excavation 450 x
550 mm. Excavated material to be utilised in roadway at site.
Unit = metre
Taking output = 10 metres
a)

c)

Labour
Mate

day

0.040

151.44

6.06

L-12

Mazdoor for excavation and back filling

day

2.000

136.69

273.38

L-13

metre

10.000

243.00

2430.00

M-135

cum

2.400

894.00

2145.60

M-012

Material
Perforated pipe of cement concrete, internal dia 100
mm
Crushed stone as per table 300-3

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

485.50
534.05

Cost for 10 metres = a+b+c+d+e

5874.60

Rate per metre = (a+b+c+d+e)/10

587.46
say

Note
3.28

309

587.00

Type of pipe may be modified depending upon provision in


design.
Aggregate Sub-Surface Drains
Construction of aggregate sub surface drain 300 mm x 450
mm with aggregates conforming to table 300-4, excavated
material to be utilised in roadway.
Unit = metre
Taking output = 10 metres
a)

b)

Labour
Mate

day

0.020

151.44

3.03

L-12

Mazdoor for excavation and back filling with aggregates

day

1.500

136.69

205.04

L-13

cum

1.350

894.00

1206.90

M-012

Material
Crushed stone as per table 300-3

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

141.50
155.65

Cost for 10 metres = a+b+c+d

1712.11

Rate per metre = (a+b+c+d)/10

171.21
say

3.29

309

171.00

Underground Drain at Edge of Pavement


Construction of an underground drain 1 m x 1 m (inside
dimensions) lined with RCC-20 cm thick and covered with
RCC slab10 cm in thickness on urban roads.
Unit = Running metre
Taking output = one metre
a) Earthwork in soil

cum

1.500

36.00

b) RCC work M-20

cum

0.495

4650.00

Rate per metre = (a+b)


3.30

310

Rates for these items may be taken from chapters on earth


work and substructures respectively.
Preparation and Surface Treatment of Formation.

say

Item No.
3.13
2301.75 Item 12.8
(C) RCC
2355.75
54.00

2356.00

Preparation and surface treatment of formation by removing


mud and slurry, watering to the extent needed to maintain
the desired moisture content, trimming to the required line,
grade, profile and rolling with 8-10 tonne smooth wheeled
roller, complete as per clause 310.
Unit = sqm
Taking output = 3500sqm
a)

b)

c)

Labour
Mate

day

0.280

151.44

42.40

L-12

Mazdoor

day

6.000

136.69

820.14

L-13

Mazdoor skilled

day

1.000

164.69

164.69

L-15

Smooth 3 wheeled steel roller 8-10 tonnes

hour

3.000

460.00

1380.00

P&M-044

Water tanker 6 KL, one trip per hour

hour

3.000

200.00

600.00

P&M-060

KL

18.000

10.00

180.00

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

318.72
350.60

Cost for 3500 sqm = a+b+c+d+e

3856.55

Rate per sqm = (a+b+c+d+e)/3500

1.10
say

3.31

313

Construction of Rock fill Embankment

Page 12 of 264

1.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Construction of rock fill embankment with broken hard rock


fragments of size not exceeding 300 mm laid in layers not
exceeding 500 mm thick including filling of surface voids with
stone spalls, blinding top layer with granular material, rolled
with vibratory road roller, all complete as per clause 313.
Unit = cum
Taking output = 100 cum
a)

b)

c)

Labour
Mate

day

0.040

151.44

6.06

L-12

Mazdoor

day

1.500

136.69

205.04

L-13

Dozer 80 HP for spreading @ 200 cum per hour

hour

0.500

3720.00

1860.00

P&M-014

Vibratory road roller 8-10 tonnes @ 100 cum per hour

hour

1.000

1541.00

1541.00

P&M-059

Water tanker 6 KL, one trip per hour

hour

2.000

200.00

400.00

P&M-060

KL

12.000

10.00

120.00

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

413.21
454.53

Cost for 100 cum = a+b+c+d+e

4999.83

Rate per cum = (a+b+c+d+e)/100

50.00
say

Note

50.00

It is assumed that rock is available locally at site from


roadway cutting. In case, portion of the rock requires
breaking to acceptable size of 300 mm, breaking charges
will have to be added.
EARTH WORK ON HILL ROAD

3.32

301

Excavation in Hill Area in Soil by Mechanical Means


Excavation in soil in hilly area by mechanical means
including cutting and trimming of side slopes and disposing
of excavated earth with all lifts and lead upto 1000 metres.
Unit = cum
Taking output = 260 cum
a)

b)

Labour
Mate

day

0.240

151.44

36.35

L-12

Mazdoor for trimming slopes and helping in excavation


etc.
Machinery

day

6.000

136.69

820.14

L-13

Dozer 80 HP (D-80 A 12)@ 43.28 cum per hour

hour

6.000

3720.00

22320.00

P&M-014

Front end loader

hour

6.000

806.00

4836.00

P&M-017

Tipper 5.5cum capacity, 4 trips per hour.

hour

12.000

339.00

4068.00

P&M-048

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3208.05
3528.85

Cost for 260 cum = a+b+c+d

38817.39

Rate per cum = (a+b+c+d)/260

149.30
say

Note

3.33

149.00

In case the land on the valley side is barren and there is no


objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth shall be disposed off on the valley side.
Excavation in Hilly Area in Ordinary Rock by Mechanical
Means not Requiring Blasting.
Excavation in hilly area in ordinary rock not requiring blasting
by mechanical means including cutting and trimming of
slopes and disposal of cut material with all lift and lead upto
1000 metres.

301

Unit = cum
Taking output = 170 cum
a)

b)

Labour
Mate

day

0.320

151.44

48.46

L-12

Mazdoor

day

8.000

136.69

1093.52

L-13

Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour

hour

6.000

3720.00

22320.00

P&M-014

Front end loader

hour

7.000

806.00

5642.00

P&M-017

Tipper 5.5cum capacity, 4 trips per hour.

hour

7.000

339.00

2373.00

P&M-048

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3147.70
3462.47

Cost for 170 cum = a+b+c+d

38087.15

Rate per cum = (a+b+c+d)/170

224.04
say

Note

3.34

301

In case the land on the valley side is barren and there is no


objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.
Excavation in Hilly Areas in Hard Rock Requiring
Blasting

Page 13 of 264

224.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Excavation in hilly areas in hard rock requiring blasting, by


mechanical means including trimming of slopes and disposal
of cut material with all lifts and lead upto 1000 metres.
Unit = cum
Taking output = 170 cum
a)

b)

c)

Labour
Mate

day

0.490

151.44

74.21

L-12

Mazdoor

day

10.000

136.69

1366.90

L-13

Driller

day

2.000

264.50

529.00

L-06

Blaster

day

0.250

264.50

66.13

L-03

Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour

hour

6.000

3720.00

22320.00

P&M-014

Air compressor 250 cfm with two jack hammer @ 20


cum per hour
Front end loader

hour

5.000

319.00

1595.00

P&M-001

hour

7.000

806.00

5642.00

P&M-017

Tipper 5.5cum capacity, 4 trips per hour.

hour

7.000

339.00

2373.00

P&M-048

kg

35.000

146.00

5110.00

M-104

each

140.000

14.56

Machinery

Materials
Gelatine 80 per cent

d)

Electric Detonators @ 1 Detonator for 2 Gelatine sticks


of 125 gms each
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

4111.46
4522.61

Cost for 170 cum = a+b+c+d+e

49748.70

Rate per cum = (a+b+c+d+e)/170

292.64
say

Note

2038.40 M-094 /100

293.00

In case the land on the valley side is barren and there is no


objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.
In case of hill roads, the altitude effect comes into play. The
output of men and machines decreases progressively after
2100 m elevation leading to increase in cost . High altitude
effect has been explained in the basic approach.

3.35

Work in Urban Roads


The cost of earth work in urban roads inhabited area will be
comparatively higher due to following reasons:
a) There is mixed traffic on urban roads like slow moving
hand and animal driven carts, rickshaws, cycles, two/ three
wheeler apart from the usual vehicular traffic resulting into
traffic jams. This causes loss of working time which may be
in the range of 10 -15 per cent
b)
There is considerable disruption of traffic adversely
affecting the efficiency of the working parties including
machines due to congestion caused by pedestrian traffic,
local road side venders, parking of vehicles by the road side,
encroachments by the shopkeepers and local shops who
make use of the berms of the road in front of these shops
and unauthorised conversion of road berms into mini local
market The output of manpower and machines is
substantially reduced due to factors mentioned above.
c)
Cost of living in urban areas is comparatively more
resulting into higher wages.
d)
At times, work is executed during night time due to
heavy traffic during day time. This involves extra expenditure
by way of making arrangement for lighting and special
transport for working parties due to odd hour
In the light of above, the authorities engaged in preparing
the cost estimates may exercise their judgment and cater for
the additional cost to the extent of 2 to 3 per cent, keeping in
view the severity of factors mentioned above. Supporting
details for the extra cost based on the actual conditions in
specific cases will have to give in justification.

3.36

Suggest
ive

Embankment Construction with Flyash/Pond ash


available from coal or lignite burning Thermal Plants as
waste material.
Construction of embankment with Flyash conforming to table
1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning
thermal power stations as waste material, spread and
compacted in layer of 200mm thickness each at OMC, all as
specified in IRC: SP: 58-2001 and as per approved plans.
Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

0.160

151.44

24.23

L-12

Mazdoor

day

4.000

136.69

546.76

L-13

hour

6.000

1302.00

7812.00

P&M-026

tonne.km

432 x L

2.46

56272.64

Lead =53
km & P&M058

Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60
cum/hour
Tipper 10Tcapacity flyash 360 x 1.2 = 432 tonnes

Add 10 per cent of cost of carriagefor loading and


unloading
Page 14 of 264

5627.26

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Dozer 80 HP for spreading @ 200 cum/hour

hour

1.800

3720.00

6696.00

P&M-014

Motor Grader for grading @ 100 cum/hour

hour

3.600

2395.00

8622.00

P&M-032

Water tanker6 KL capacity

hour

12.000

200.00

2400.00

P&M-060

Vibratory Roller 8-10 tonne @ 100 cum/hour

hour

3.600

1541.00

5547.60

P&M-059

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

9354.85
10290.33

Cost for 360 cum = a+b+c+d

113193.68

Rate per cum = (a+b+c+d)/360

314.43
say

Note

Remarks/
Input ref.

1.As flyash is available free of cost as waste material from


Thermal Plants, cost of material has not been added.
2.The earth cover on sides and intermediate layers of earth
sandwiching the flyash have not been included in this
analysis. The same are required to be provided as per
approved design and priced separately as embankment
construction.

Page 15 of 264

314.00

CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Sr No

Ref. to
MoRTH
Spec.

4.1

401

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Granular Sub-Base with Close Graded Material (Table:400-1)


Plant Mix Method
Construction of granular sub-base by providing close graded
Material, mixing in a mechanical mix plant at OMC, carriage of
mixed Material to work site, spreading in uniform layers with
motor grader on prepared surface and compacting with
vibratory power roller to achieve the desired density, complete
as per clause 401
Unit = cum
Taking output = 225 cum (450 tonne)
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Machinery
Wet mix plant @ 75 tonne capacity per hour
Electric generator 125 KVA
Water tanker 6 KL capacity 5 km lead with one trip per
hour
Front end loader 1 cum bucket capacity
Tipper 10 tonne

Add 10 per cent of cost of carriage to cover loading and


unloading
Motor Grader 110 HP
Vibratory roller 8-10 t
c) Material
Close graded Granular sub-base Material as per table 400-1

4.1A

4.1A

4.1A

(i)

(ii)

(iii)

For Grading-I Material


53 mm to 9.5 mm @ 50 per cent
9.5 mm to 2.36 mm @ 20 per cent
2.36 mm below @ 30 per cent
Cost of water
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent
9.5 mm to 2.36 mm @ 25 per cent
2.36 mm below @ 40 per cent
Cost of water
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 35 per cent
4.75 mm to 2.36 mm @ 12.5 per cent
2.36 mm below @ 52.5 per cent
Cost of water
Rate per cum for grading-I Material
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 225 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/225

day
day
day

0.400
2.000
8.000

151.44
164.69
136.69

60.58
329.38
1093.52

L-12
L-15
L-13

hour
hour
hour

6.000
6.000
4.500

2195.03
652.00
200.00

13170.15
3912.00
900.00

P&M-093
P&M-018
P&M-060

hour
tonne.km

6.000
450 x L

806.00
2.46

4836.00
1105.99

P&M-017
Lead =1
km & P&M058

110.60
hour
hour

6.000
6.000

2395.00
1541.00

14370.00
9246.00

P&M-032
P&M-059

cum
cum
cum
KL

144.000
57.000
86.400
27.000

867.00
867.00
867.00
10.00

124848.00
49419.00
74908.80
270.00

M-013
M-017
M-020
M-189

cum
cum
cum
KL

100.800
72.000
115.200
27.000

867.00
867.00
867.00
10.00

87393.60
62424.00
99878.40
270.00

M-015
M-017
M-020
M-189

cum
cum
cum
KL

100.800
36.000
151.200
27.000

867.00
867.00
867.00
10.00

87393.60
31212.00
131090.40
270.00

M-016
M-018
M-020
M-189

say

29858.00
32843.80
361281.81
1605.70
1606.00

say

29910.02
32901.02
361911.26
1608.49
1608.00

say

29910.02
32901.02
361911.26
1608.49
1608.00

Rate per cum for grading-II Material


d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 225 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/225
Rate per cum for grading-III Material
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 225 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/225

Page 1 of 264

Sr No

Ref. to
MoRTH
Spec.

Description
Note

Unit

Any one of the grading for material may be adopted as per


design

Page 2 of 264

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Sr No
4.1

Ref. to
MoRTH
Spec.

Description
B

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

By Mix in Place Method


Construction of granular sub-base by providing close graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401
Unit = cum
Taking output = 300 cum
a)

b)

c)

Labour
Mate

day

0.480

151.44

72.69

L-12

Mazdoor skilled

day

2.000

164.69

329.38

L-15

Mazdoor unskilled

day

10.000

136.69

1366.90

L-13

Motor Grader 110 HP @ 50 cum

hour

6.000

2395.00

14370.00

P&M-032

Vibratory roller 8 -10 tonne

hour

6.000

1541.00

9246.00

P&M-059

Tractor - Rotavator

hour

12.000

0.00

0.00

P&M-054

Water tanker 6 KL capacity

hour

3.000

200.00

600.00

P&M-060

53 mm to 9.5 mm @ 50 per cent

cum

384.000

836.17

321089.28

M-013

9.5 mm to 2.36 mm @ 20 per cent

cum

0.000

836.17

0.00

M-017

2.36 mm below @ 30 per cent

cum

0.000

836.17

0.00

M-020

KL

18.000

10.00

180.00

M-189

Machinery

Material

Close graded Granular sub-base Material as per table 400-1


For Grading-I Material

Cost of water
OR
4.1B

(i)

Rate per cum for grading-I Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

34725.43
38197.97

Cost for 300 cum = a+b+c+d+e

420177.64

Rate per cum = (a+b+c+d+e)/300

1400.59

Add 1 % labour Cess

14.01
1414.60
say

4.1B

(ii)

1414.60

Rate per cum for grading-II Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

35139.78
38653.76

Cost for 300 cum = a+b+c+d+e

425191.34

Rate per cum = (a+b+c+d+e)/300

1417.30

Add 1 % labour Cess

14.17
1431.48
say

4.1B

(iii)

1431.48

Rate per cum for grading-III Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

35287.76
38816.54

Cost for 300 cum = a+b+c+d+e

426981.95

Rate per cum = (a+b+c+d+e)/300

1423.27

Add 1 % labour Cess

14.23
1437.51
say

Note

Any one of the grading for material may be adopted as per


design

Page 3 of 264

1437.51

Sr No

Ref. to
MoRTH
Spec.

4.2

401

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Granular Sub-Base with Coarse Graded Material (Table:400- 2)


Construction of granular sub-base by providing coarse graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401.
Unit = cum
Taking output = 300 cum
a)

b)

c)

Labour
Mate

day

0.400

151.44

60.58

L-12

Mazdoor skilled

day

2.000

164.69

329.38

L-15

Mazdoor

day

8.000

136.69

1093.52

L-13

Mortar Grader 110 HP @ 50 cum per hour

hour

6.000

2395.00

14370.00

P&M-032

Vibratory roller 8 -10 tonne

hour

6.000

1541.00

9246.00

P&M-059

Water tanker 6 KL capacity

hour

3.000

200.00

600.00

P&M-060

53 mm to 26.5 mm @ 35 per cent

cum

134.400

867.00

116524.80

M-029

26.5 mm to 4.75 mm @ 45 per cent

cum

172.800

867.00

149817.60

M-026

2.36 mm below @ 20 per cent (Coarse Sand)

cum

76.800

992.30

76208.64

M-022

KL

18.000

10.00

180.00

M-189

26.5 mm to 4.75 mm @ 75 per cent

cum

288.000

867.00

249696.00

M-026

2.36 mm below @ 25 per cent

cum

96.000

992.30

95260.80

M-022

KL

18.000

10.00

180.00

M-189

9.5 mm to 4.75 mm @ 66 per cent

cum

255.000

867.00

221085.00

M-025

2.36 mm below @ 34 per cent

cum

129.000

992.30

128006.70

M-022

KL

18.000

10.00

180.00

M-189

Machinery

Material

For coarse graded Granular sub-base Materials per table 4002


For grading-I Material

Cost of water
OR
For Grading-II Material

Cost of water
OR
For Grading-III Material

Cost of water
4.2

(i)

Rate per cum for grading-I Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

36843.05
40527.36

Cost for 300 cum = a+b+c+d+e

445800.92

Rate per cum = (a+b+c+d+e)/300

1486.00
say

4.2

(ii)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

37083.63
40791.99

Cost for 300 cum = a+b+c+d+e

448711.89

Rate per cum = (a+b+c+d+e)/300

1495.71
say

4.2

(iii)

1496.00

Rate per cum for grading-III Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

37497.12
41246.83

Cost for 300 cum = a+b+c+d+e

453715.12

Rate per cum = (a+b+c+d+e)/300

1512.38
say

Note

1486.00

Rate per cum for grading-II Material

Any one of the grading for material may be adopted as per


design

Page 4 of 264

1512.00

Sr No

Ref. to
MoRTH
Spec.

4.12

406

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Wet Mix Macadam


Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix
plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base course on well
prepared surface and compacting with vibratory roller to
achieve the desired density.
Unit = cum
Taking output = 225 cum (495 tonnes)
a)

b)

Labour
Mate

day

0.480

151.44

72.69

L-12

Mazdoor skilled

day

2.000

164.69

329.38

L-15

Mazdoor

day

10.000

136.69

1366.90

L-13

Wet mix plant of 75 tonne hourly capacity

hour

9.000

2195.03

19755.23

P&M-094

Electric generator 125 KVA

hour

6.000

652.00

3912.00

P&M-018

Front end loader 1 cum capacity

hour

6.000

806.00

4836.00

P&M-017

Paver finisher

hour

6.000

975.00

5850.00

P&M-035

Vibratory roller 8 - 10 tonne

hour

6x0.65

1541.00

6009.90

P&M-059

Smooth 3 wheeled steel roller @ 8-10 tonnes.

hour

12.000

Water tanker 6 KL capacity

hour

3.000

200.00

600.00

P&M-060

tonne.km

495 x L

2.46

1216.59

Lead =1
km & P&M058

Machinery

or

Tipper

c)

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Material ( Table 400-11)

121.66

45 mm to 22.4 mm@ 30 per cent

cum

89.100

1007.77

89792.31

M-034

22.4 mm to 2.36 mm @ 40 per cent

cum

118.800

1011.94

120218.47

M-031

2.36 mm to 75 micron@ 30 per cent

cum

89.100

992.30

88413.93

M-022

KL

18.000

10.00

180.00

M-189

Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

34267.51
37694.26

Cost for 225 cum = a+b+c+d+e

414636.81

Rate per cum = (a+b+c+d+e)/225

1842.83

Add 1 % labour Cess

18.43
1861.26
say

Note

1861.26

1. Though vibratory roller is required only for 3 hours as per


norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65
2. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative which can be
used if the thickness of individual layer does not exceed 100
mm..

4.13

407

Construction of Median and Island with Soil Taken from


Roadway Cutting
Construction of Median and Island above road level with
approved material deposited at site from roadway cutting and
excavation for drain and foundation of other structures,
spread, graded and compacted as per clause 407
Unit = cum
Taking output =21 cum
a)

b)

Labour
Mate

day

0.240

151.44

36.35

L-12

Mazdoor

day

6.000

136.69

820.14

L-13

hour

1.000

200.00

200.00

P&M-060

Machinery
Water tanker 6 KL with 5 km lead and 1 trip per hour
Page 5 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Plate compactor @ 3.5 cum per hour


c)

Quantity

Rate Rs

Cost Rs

hour

6.000

101.70

KL

6.000

10.00

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

60.00

M-189

189.94
2089.29

Rate per cum = (a+b+c+d+e)/21

99.49
say

407

P&M-086

172.67

Cost for 21 cum = a+b+c+d+e

4.14

610.20

Material
Cost of water

Note

Remarks/
Input ref.

99.00

This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case granular
fill is required to be paved, quantities of paving are required to
be calculated as per approved design and paid separately.
Construction of Median and Island with Soil Taken from
Borrow Areas
Construction of median and Island above road level with
approved material brought from borrow pits, spread, sloped
and compacted as per clause 407
Unit = cum
Taking output = 21 cum
a)

b)

Labour
Mate

day

0.160

151.44

24.23

L-12

Mazdoor

day

4.000

136.69

546.76

L-13

Water tanker with 5 km lead

hour

1.000

200.00

200.00

P&M-060

Plate Compactor @ 3.5 cum per hour

hour

6.000

101.70

610.20

P&M-086

Hydraulic Excavator1.0 cum bucket capacity @60 cum


per hour
Tipper 10 tonne capacity

hour

0.500

1302.00

651.00

P&M-026

tonne.km

52.5 x L

2.46

2580.64

Lead =20
km & P&M058

Machinery

Add 10 per cent of cost of transportation to cover cost


of loading and unloading
c) Material
Cost of water

258.06

KL

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

6.000

10.00

542.40

Cost for 21 cum = a+b+c+d+e

5966.38

Rate per cum = (a+b+c+d+e)/ 21

284.11
say

Note

4.15

This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case surface
finish is of hard type, the same may be provided separately as
per approved design.
Construction of Shoulders
A. Earthen Shoulders
The rate as applicable for sub-grade construction may be
adopted.
B. Hard Shoulders
Rate as applicable for sub-base and or base may be adopted
as per approved design.
C. Paved shoulders
The rate may be adopted as applicable for different layers of
pavement depending upon approved design of paved
shoulders.

4.16

409

60.00
493.09

Footpaths and Separators

Page 6 of 264

284.00

M-189

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Construction of footpath/separator by providing a 150 mm


compacted granular sub base as per clause 401 and 25 mm
thick cement concrete grade M15, over laid with pre-cast
concrete tiles in cement mortar 1:3 including provision of all
drainage arrangements but excluding kerb channel..
Unit = sqm
Taking output = 300 sqm
a)

b)

c)

Labour
Mate

day

1.360

151.44

205.96

Mason

day

4.000

223.36

893.44

L-12
L-11

Mazdoor

day

30.000

136.69

4100.70

L-13

Vibratory road roller 8 -10 tonnes @60 cum per hour

hour

0.750

1541.00

1155.75

P&M-059

Water tanker 6 KL capacity @ 1 trip per hour

hour

2.000

200.00

400.00

P&M-060

Concrete mixer 0.4/0.28 cum per hour

hour

6.000

233.00

1398.00

P&M-009

53 mm to 26.5 mm @ 35 per cent

cum

20.790

867.00

18024.93

M-029

26.5 mm to 4.75 mm @ 45 per cent

cum

26.730

867.00

23174.91

M-026

2.36 mm below @ 20 per cent

cum

11.880

867.00

10299.96

M-022

Aggregate 12 mm crushed @ 0.9 cum of concrete

cum

6.750

1028.00

6939.00

M-052

Sand @ 0.45 cum/cum of concrete

cum

3.380

710.46

2401.35

M-005

tonne

1.880

5000.00

9400.00

M-081

Machinery

Material

i) For Granular sub base material

ii) For cement concrete grade M157.5 cum

Cement
iii) For cement plaster 1:3
Sand
Cement

cum

3.840

710.46

2728.17

M-005

tonne

1.830

5000.00

9150.00

M-081

each

3300.000

15.00

49500.00

M-184

metre

22.500

243.00

5467.50

M-137

KL

12.000

10.00

120.00

M-189

iv) Pre-cast cement concrete tiles


Tiles size 300 x 300 mm and 25 mm thick
v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage
vi) Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

14535.97
15989.56

Cost for 300 sqm = a+b+c+d+e

175885.20

Rate per sqm = (a+b+c+d+e)/300

586.28
say

4.17

410

586.00

Crusher Run Macadam Base


Providing crushed stone aggregate, depositing on a prepared
surface by hauling vehicles, spreading and mixing with a motor
grader, watering and compacting with a vibratory roller to
clause 410 to form a layer of sub-base/Base
Unit = cum
Taking output = 360 cum
A

By Mix in Place Method


a)

b)

c)

Labour
Mate

day

0.480

151.44

72.69

L-12

Mazdoor skilled

day

2.000

164.69

329.38

L-15

Mazdoor

day

10.000

136.69

1366.90

L-13

Tractor attached with rotavator @ 25 cum per hour

hour

12.000

282.50

3390.00

P&M-054

Motor grader 110 HP

hour

6.000

2395.00

14370.00

P&M-032

Vibratory roller 8 -10 tonnes @ 60 cum per hour

hour

6.000

1541.00

9246.00

P&M-059

Water tanker 6 KL capacity

hour

6.000

200.00

1200.00

P&M-060

Machinery

Material

Aggregate at site
i) For 53 mm maximum size
Page 7 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

63 mm to 45 mm @ 33 per cent

cum

157.460

949.00

149429.54

M-038

22.5 mm to 5.6 mm@ 32 per cent

cum

151.060

1000.67

151160.71

M-032

Below 5.6 mm @ 35 per cent

cum

166.680

1066.89

177829.23

M-030

KL

36.000

10.00

360.00

M-189

Cost of water
Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent

cum

24.120

920.50

22202.46

M-034

22.4 mm to 5.6 mm@ 50 per cent

cum

237.600

1000.67

237758.40

M-032

Below 5.6 mm@ 45 per cent

cum

213.480

1066.89

227759.68

M-030

KL

36.000

10.00

360.00

M-189

Cost of water
4.17A

(i)

For 53 mm maximum size


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

50875.44
55962.99

Cost for 360.0cum = a+b+c+d+e

615592.88

Rate per cum = (a+b+c+d+e)/360

1709.98

or
4.17A

(ii)

say

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

51805.55
56986.11

Cost for 360.0cum = a+b+c+d+e

626847.17

Rate per cum = (a+b+c+d+e)/360

1741.24
say

Note
4.17

1710.00

For 45 mm maximum size

1741.00

Any one of the aggregate grading may be adopted


By Mixing Plant :
Unit = cum
Taking output = 225 cum (450 tonnes)
a)

b)

Labour
Mate

day

0.280

151.44

42.40

L-12

Mazdoor skilled

day

1.000

164.69

164.69

L-15

Mazdoor

day

6.000

136.69

820.14

L-13

Wet mix plant @ 75 tonne per hour

hour

6.000

2195.03

13170.15

P&M-093

Electric generator 125 KVA

hour

6.000

652.00

3912.00

P&M-018

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

Motor grader 110 HP

hour

6.000

2395.00

14370.00

P&M-032

Vibratory roller 8 - 10 tonne

hour

6.000

1541.00

9246.00

P&M-059

Water tanker 6 KL capacity

hour

3.000

200.00

600.00

P&M-060

tonne.km

450 x L

2.46

1105.99

Lead =1
km & P&M058

Machinery

Tipper 10 tonne capacity

c)

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Material

110.60

Aggregate at site
i) For 53 mm maximum size
63 mm to 45 mm @ 33 per cent

cum

98.400

949.00

22.5 mm to 5.6 mm@ 32 per cent


Below 5.6 mm @ 35 per cent

93381.60

M-038

cum

94.410

cum

104.180

1000.67

94472.94

M-032

1066.89

111148.60

M-030

Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent

cum

15.060

920.50

13862.73

M-034

22.4 mm to 5.6 mm@ 50 per cent

cum

148.500

1000.67

148599.00

M-032

Below 5.6 mm@ 45 per cent

cum

133.430

1066.89

142355.13

M-030

KL

18.000

10.00

180.00

M-189

Cost of water
4.17 B

(i)

For 53 mm maximum size


d)

Overhead charges @ 0.1 on (a+b+c)

34738.11

e)

Contractor's profit @ 0.1 on (a+b+c+d)

38211.92

Page 8 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Cost for 225cum = a+b+c+d+e

420331.14

Rate per cum = (a+b+c+d+e)/225

1868.14
say

4.17 B

(ii)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

35337.48
38871.23
427583.55

Rate per cum = (a+b+c+d+e)/360

1187.73
say

Suggest
ive

1868.00

For 45 mm maximum size

Cost for 360.0cum = a+b+c+d+e

4.18

Remarks/
Input ref.

1188.00

Lime, Flyash Stabilised Soil Sub-Base


Construction of Sub-base using lime - Flyash admixture with
granular soil, free from organic matter/ deleterious material or
clayey silts and low plasticity clays having PI between 5 and
20 and liquid limit less than 25 and commercial dry lime,
slaked at site or pre-slaked with CaO content not less than 50
per cent, Flyash to conform to gradation as per clause 4.3 of
IRC: 88-1984, lime + Flyash content ranging between 10 to 30
per cent, the minimum un-confined compressive strength and
CBR value after 28 days curing and 4 days soaking to be
7.5kg/sq, cm and 25 per cent respectively, all as specified in
IRC: 88-1984.
Unit = cum
Taking output = 480 cum (720 tonnes, density 1.50 t/cum)
Assumptions made
Total mass taken for analysis = 720 t
Lime + Flyash admixture @ 20 per cent = 0.2 x 720=144 t
Soil = 720 -144 = 576 t
576 /1.6 = 360 cum
Lime + Flyash = 144 t
Ratio Lime 4 : Flyash 16
Lime = 29 kg.
Flyash = 115 kg.
a)

b)

c)

Labour
Mate

day

0.240

151.44

36.35

L-12

Mazdoor

day

6.000

136.69

820.14

L-13

Mazdoor (Skilled)

day

1.000

164.69

164.69

L-15
P&M-026

Machinery
Hydraulic Excavator 0.90 cum bucket capacity @
60cum/hr. for 360 cum soil
Tipper 10T capacity for carriage of soil 576 tonnes

hour

6.000

1302.00

7812.00

tonne.km

576 x L

2.46

28411.59

Tipper 10T capacity for carriage of 115 tonnes Flyash

tonne.km

115 x L

2.46

Tipper 10T capacity for carriage of 29 tonnes of lime from


store to work site
Add 10 per cent of cost of carriage to cover cost of
loading and unloading
Tractor with disc harrows for pulverisation

hour

3.000

339.00

hour

6.000

282.50

1695.00

P&M-053

Motor Grader 110 HP @ 50 cum per hour for mixing inplace and grading
Vibratory roller 8 - 10 tonne

hour

9.600

2395.00

22992.00

P&M-032

hour

6.000

1541.00

9246.00

P&M-059

Water tanker 6 KL capacity

hour

12.000

200.00

2400.00

P&M-060

tonne

29.000

4500.00

130500.00

M-188

cum

360.000

28.00

10080.00

M-092

Lead =20
km & P&M058
14979.99 Lead =53
km & P&M058
1017.00

P&M-048

101.70

Material
Slaked Lime
Compensation for earth taken from private source

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Cost for 480 cum = a+b+c+d+e

23025.65
25328.21
278610.31

Page 9 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Rate per cum= (a+b+c+d+e)/480

580.44
say

Note

1.Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
2.Cost of Flyash has not been considered as same will be
available free of cost. Only carriage of Flyash has been
provided.
3.Lime + Flyash has been taken as 20 per cent of total mass
and ratio of lime and Flyash as 1:4 for estimating purposes.
Total quantities will be as per approved design.

Page 10 of 264

580.00

Remarks/
Input ref.

CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Sr No

Ref. to
MoRTH
Spec.

5.1

502

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Prime Coat
Providing and applying primer coat with bitumen
emulsion on prepared surface of granular Base
including clearing of road surface and spraying primer
at the rate of 0.85 kg/sqm using mechanical means.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate
Mazdoor
b) Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm
Bitumen pressure distributor @ 1750 sqm per hour
Water tanker 6 KL capacity @ 1 trip per hour
c) Material
Bitumen emulsion @ 0.85 kg per sqm
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500
Add 1 % labour Cess

day
day

0.080
2.000

151.44
136.69

12.12
273.38

L-12
L-13

hour
hour
hour
hour

2.800
2.800
2.000
1.000

357.00
319.00
1073.00
200.00

999.60
893.20
2146.00
200.00

P&M-031
P&M-001
P&M-004
P&M-060

tonne
KL

2.975
6.000

47937.00
10.00

142612.58
60.00
14719.69
16191.66
178108.21
50.89
0.51
51.40
51.40

say
Note

Bitumen primer has been provided @ 0.850 kg per sqm as


per clause 502.8. Payment shall be made with adjustment,
plus or minus, for the variation between this quantity and the
actual quantity approved by the Engineer after the
preliminary trials referred to in clause No. 502.4.3.

Page 1 of 264

M-077
M-189

Sr No
5.2

Ref. to
MoRTH
Spec.

Description

503

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Tack Coat
Providing and applying tack coat with bitumen emulsion
using emulsion pressure distributor at the rate of 0.20 kg per
sqm on the prepared bituminous/granular surface cleaned
with mechanical broom.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate
Mazdoor
b) Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm
Bitumen pressure distributor @ 1750 sqm per hour
c) Material
Bitumen emulsion @ 0.25 kg per sqm
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500
Add 1 % labour Cess

day
day

0.080
2.000

151.44
136.69

12.12
273.38

L-12
L-13

hour
hour
hour

2.800
2.800
2.000

357.00
319.00
1073.00

999.60
893.20
2146.00

P&M-031
P&M-001
P&M-004

tonne

0.875

49915.00

43675.63
4799.99
5279.99
58079.90
16.59
0.17
16.76
16.76

M-077

say
Note

1. Bitumen emulsion has been provided @ 0.20 kg per sqm


as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer after
preliminary trials referred to in clause No. 503.4.3
2. An output of 3500 sqm has been considered in case of
prime coat and tack coat which can be covered by
bituminous courses on the same day.

Page 2 of 264

Sr No
5.3

Ref. to
MoRTH
Spec.

Description

504

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Bituminous Macadam
Providing and laying bituminous macadam with 100-120
TPH hot mix plant producing an average output of 75 tonnes
per hour using crushed aggregates of specified grading
premixed with bituminous binder, transported to site, laid
over a previously prepared surface with paver finisher to the
required grade, level and alignment and rolled as per
clauses 501.6 and 501.7 to achieve the desired compaction
Unit = cum
Taking output = 205 cum (450 tonnes)
a) Labour

b)

Mate

day

0.840

151.44

127.21

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction

day

16.000

136.69

2187.04

L-13

Skilled mazdoor for checking line & levels

day

5.000

164.69

823.45

L-15

Batch mix HMP 100-120 TPH @ 75 tonne per hour


actual output
Mechanical broom hydraulic @ 1250 sqm per hour

hour

6.000

23405.00

140430.00

P&M-021

hour

2.200

357.00

785.40

P&M-031

Air compressor 250 cfm

hour

2.200

319.00

701.80

P&M-001

Paver finisher hydrostatic with sensor control @ 75


cum per hour
Generator 250 KVA

hour

6.000

2674.00

16044.00

P&M-034

hour

6.000

1906.88

11441.25

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

tonne.km

450 x L

2.46

1105.99

Lead =1
km & P&M058

Machinery

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Smooth wheeled roller 8-10 tonnes for initial break
down rolling.
Vibratory roller 8 tonnes for intermediate rolling.

c)

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller.
Material
i) Bitumen@ 3.3 per cent of mix

110.60
hour

6.00x0.65*

460.00

1794.00

P&M-044

hour

6.00x0.65*

1541.00

6009.90

P&M-059

hour

6.00x0.65*

1144.00

4461.60

P&M-045

tonne

14.850

55132.00

818710.20

M-074

weight of mix = 205 x 2.2 = 450 tonne


ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
*Grading I ( 40 mm nominal size )
37.5 - 25 mm 15 per cent

cum

43.510

1011.94

44029.51

M-049

25 - 10 mm 45 per cent

cum

130.550

1103.60

144074.98

M-046

10 - 5 mm 25 per cent

cum

72.530

1078.94

78255.52

M-040

5 mm and below15 per cent

cum

43.510

992.30

43174.97

M-030

25 - 10 mm 40 per cent

cum

116.040

1103.60

128061.74

M-046

10 - 5 mm 40 per cent

cum

116.040

1078.94

125200.20

M-040

5 mm and below 20 per cent

cum

58.020

992.30

57573.25

M-030

or
GradingII(19 mm nominal size)

(i)

* Any one of the alternative may be adopted as per


approved design
for Grading I ( 40 mm nominal size )
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

131910.34
145101.38

Cost for 205 cum = a+b+c+d+e

1596115.13

Rate per cum = (a+b+c+d+e)/205 (For Grading I)

7785.93

Add 1 % labour Cess

77.86
7863.79
say

(ii)

7863.79

for GradingII(19 mm nominal size)


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Cost for 205 cum = a+b+c+d+e

132040.36
145244.40
1597688.38

Page 3 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Rate per cum = (a+b+c+d+e)/205 (For Grading-II)

7793.60

Add 1 % labour Cess

77.94
7871.54
say

Page 4 of 264

7871.54

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description
Note

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

*1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65.
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case BM is laid over freshly laid tack coat, provision of
Mechanical broom and 2 mazdoors for the same shall be
deleted as the same has been included in the cost of tack
coat.

5.4

505

Bituminous Penetration Macadam


Construction of penetration macadam over prepared Base
by providing a layer of compacted crushed coarse aggregate
using chips spreader with alternate applications of
bituminous binder and key aggregates and rolling with a
smooth wheeled steel roller 8-10 tonne capacity to achieve
the desired degree of compaction
A

50 mm thick
Unit = sqm
Taking output = 4500 sqm (225 cum)
a) Labour

b)

c)

Mate

day

0.320

151.44

48.46

L-12

Mazdoor including for brooming of key aggregates

day

6.000

136.69

820.14

L-13

Mazdoor skilled

day

2.000

164.69

329.38

L-15

Hydraulic self propelled chip spreader both for


aggregates and key aggregates@ 1500 sqm per hour
for 4500 x 2 sqm = 9000 sqm

hour

6.000

2635.00

15810.00

P&M-025

Bitumen pressure distributor for @ 1750 sqm per hour

hour

2.570

1073.00

2757.61

P&M-004

Tipper 5.5 cum capacity for carriage of aggregates


from stockpile to chip spreader
Vibratory roller 8 tonnes

hour

10.000

339.00

3390.00

P&M-048

hour

6.000

1541.00

9246.00

P&M-059

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

tonne

22.500

55132.00

1240470.00

M-074

cum

270.000

968.60

261522.00

M-033

cum

67.500

1000.67

67545.00

M-031

Machinery

Material
Bitumen@ 5 kg per sqm

d)

Crushed stone coarse aggregate passing 45 mm and


retained on 2.8 mm sieve @ 0.06 cum per sqm
Key aggregates passing 22.4 mm and retained on 2.8
mm sieve @ 0.015 cum per sqm
Overhead charges @ 0.1 on (a+b+c)

Page 5 of 264

160677.46

Sr No

Ref. to
MoRTH
Spec.

Description
e)

Unit

Quantity

Rate Rs

Cost Rs

Contractor's profit @ 0.1 on (a+b+c+d)

176745.20

Cost for 4500 sqm = a+b+c+d+e

1944197.25

Rate per sqm = (a+b+c+d+e)/4500

432.04
say

Note
5.4

Remarks/
Input ref.

432.00

2 tippers will be needed to match the capacity of chip


spreader and front end loader.
75 mm thick
Unit = sqm
Taking output = 4500 sqm (337.5 cum compacted).
a) Labour

b)

c)

Mate

day

0.400

151.44

60.58

L-12

Mazdoor including for brooming of key aggregates

day

8.000

136.69

1093.52

L-13

Mazdoor skilled

day

2.000

164.69

329.38

L-15

Hydraulic self propelled chip spreader both for


aggregates and key aggregates@ 1500 sqm per hour
for 4500 x 2 sqm
Bitumen pressure distributor for@ 1750 sqm per hour

hour

6.000

2635.00

15810.00

P&M-025

hour

2.570

1073.00

2757.61

P&M-004

Tipper 5.5 cum capacity for carriage of aggregates


from stockpile to chip spreader
Vibratory roller 8 tonnes

hour

10.000

339.00

3390.00

P&M-048

hour

6.000

1541.00

9246.00

P&M-059

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

tonne

30.600

55132.00

1687039.20

M-074

cum

405.000

982.00

397710.00

M-037

cum

81.000

867.00

70227.00

M-026

Machinery

Material
Bitumen@ 6.8 kg per sqm

d)

Crushed stone coarse aggregate (loose passing 63


mm and retained on 2.8 mm sieve @ 0.09 cum per
sqm
Key aggregates passing 26.5 mm and retained on 2.8
mm sieve @ 0.018 cum per sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

219249.93
241174.92

Cost for 4500 sqm = a+b+c+d+e

2652924.14

Rate per sqm = (a+b+c+d+e)/4500

589.54
say

Note
5.5

506

590.00

2 tippers and 2 rollers will be needed to match the capacity


of chip spreader and front end loader.
Built-up-Spray Grout
Providing, laying and rolling of built-up-spray grout layer over
prepared base consisting of a two layer composite
construction of compacted crushed coarse aggregates using
motor grader for aggregates. key stone chips spreader may
be used with application of bituminous binder after each
layer, and with key aggregates placed on top of the second
layer to serve as a Base conforming to the line, grades and
cross-section specified, the compacted layer thickness being
75 mm
Unit = sqm
Taking output = 3000 sqm (225 cum)
a) Labour

b)

c)

d)

Mate

day

0.400

151.44

60.58

L-12

Mazdoor including for brooming of key aggregates

day

8.000

136.69

1093.52

L-13

Mazdoor skilled

day

2.000

164.69

329.38

L-15

Hydraulic self propelled chip spreader both for


aggregates and key aggregates@ 1500 sqm per hour
for 3000 x 3 sqm

hour

6.000

2635.00

15810.00

P&M-025

Bitumen pressure distributor for 3000 x 2 sqm @ 1750


sqm per hour
Tipper 5.5 cum capacity

hour

3.430

1073.00

3680.39

P&M-004

hour

10.000

339.00

3390.00

P&M-048

Vibratory roller 8 tonnes

hour

6.000

1541.00

9246.00

P&M-059

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

Bitumen30 kg per 10 sqm @ 15 kg per 10 sqm for


each layer
Crushed stone coarse aggregate passing 53 mm and
retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for
each layer

tonne

9.000

55132.00

496188.00

M-074

cum

300.000

990.25

297075.00

M-035

Key aggregates passing 22.4 mm and retained on 2.8


mm sieve @ 0.13 cum per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

cum

39.000

1000.67

39026.00

M-031

Machinery

Material

Page 6 of 264

87073.49

Sr No

Ref. to
MoRTH
Spec.

Description
e)

Unit

Quantity

Rate Rs

Cost Rs

Contractor's profit @ 0.1 on (a+b+c+d)

95780.84

Cost for 3000 sqm = a+b+c+d+e

1053589.19

Rate per sqm = (a+b+c+d+e)/3000

351.20
say

Note

2 tippers will be needed to match the capacity of hydraulic


chip spreader and front end loader.

Page 7 of 264

351.00

Remarks/
Input ref.

Sr No
5.6

Ref. to
MoRTH
Spec.

Description

505

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Dense Graded Bituminous Macadam


Providing and laying dense graded bituminous macadam
with 100-120 TPH batch type HMP producing an average
output of 75 tonnes per hour using crushed aggregates of
specified grading, premixed with bituminous binder @ 4.5
per cent by weight of total mix and filler, transporting the hot
mix to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MoRTH specification
clause No. 505 complete in all respects.
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour

b)

Mate

day

0.840

151.44

127.21

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction

day

16.000

136.69

2187.04

L-13

Skilled mazdoor for checking line & levels

day

5.000

164.69

823.45

L-15

Batch mix HMP @ 75 tonne per hour

hour

6.000

13842.00

83052.00

P&M-022

Paver finisher hydrostatic with sensor control @ 75


cum per hour
Generator 250 KVA

hour

6.000

2674.00

16044.00

P&M-034

hour

6.000

1906.88

11441.25

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

tonne.km

450 x L

2.46

1105.99

Lead =1
km & P&M058

Machinery

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
smooth wheeled roller 8-10 tonnes for initial break
down rolling.
Vibratory roller 8 tonnes for intermediate rolling.

c)

110.60
hour

6.00x0.65*

460.00

1794.00

P&M-044

hour

6.00x0.65*

1541.00

6009.90

P&M-059

hour

6.00x0.65*

1144.00

4461.60

P&M-045

tonne

20.250

56122.00

1136470.50

M-074

25 - 10 mm 30 per cent

cum

85.950

1103.60

94854.42

M-046

10 - 5 mm 28 per cent

cum

80.220

1078.94

86552.57

M-040

5 mm and below 40 per cent

cum

114.600

992.30

113717.58

M-030

tonne

8.595

4500.00

38677.50

M-188

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller.
Materials
Bitumen @ 4.50 per cent of weight of mix
Aggregate

Total weight of mix = 450 tonnes


Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450 -20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.50 cum
Grading - 2 26.5 mm (Nominal Size) 50-75 mm

Filler @ 2 per cent of weight of aggregates.

(i)

* Any one of the alternative may be adopted as per


approved design
For Grading 1 ( 37.5 mm nominal size ) 75-100 mm
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

159671.18
175638.30

Cost for 205 cum = a+b+c+d+e

1932021.27

Rate per cum = (a+b+c+d+e)/195 (For Grading I)

9907.80

Add 1 % labour Cess

99.08
10006.88
say

(ii)

10006.88

For Grading 2 ( 26.5 mm nominal size) 50-75 mm


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

160226.56
176249.22

Cost for 205 cum = a+b+c+d+e

1938741.38

Rate per cum = (a+b+c+d+e)/195 (For Grading-II)

9942.26

Add 1 % labour Cess

99.42
10041.69
say

Page 8 of 264

10041.69

Sr No

Ref. to
MoRTH
Spec.

Description
Note

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

*1. Although the roller are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65.
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case DBM is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be
used for construction I.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.
6. The individual percentage of aggregates should be
calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.

5.7

508

Semi-Dense Bituminous Concrete


Providing and laying semi dense bituminous concrete with
100-120 TPH batch type HMP producing an average output
of 75 tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 4.5 to 5 per
cent of mix and filler, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MoRTH specification clause No. 508
complete in all respects
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour

b)

Mate

day

0.840

151.44

127.21

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction

day

16.000

136.69

2187.04

L-13

Skilled mazdoor for checking line & levels

day

5.000

164.69

823.45

L-15

Batch mix HMP @ 75 tonne per hour

hour

6.000

17309.00

103854.00

P&M-022

Paver finisher hydrostatic with sensor control @ 75


cum per hour
Generator 250 KVA

hour

6.000

2674.00

16044.00

P&M-034

hour

6.000

1906.88

11441.25

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

tonne.km

450 x L

2.46

1105.99

Lead =1
km & P&M058

Machinery

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break
down rolling.
Vibratory roller 8 tonnes for intermediate rolling.

c)

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller
Material

110.60
hour

6.00x0.65*

460.00

1794.00

P&M-044

hour

6.00x0.65*

1541.00

6009.90

P&M-059

hour

6.00x0.65*

1144.00

4461.60

P&M-045

tonne

20.250

55132.00

1116423.00

M-074

* Grading I: 13 mm (Nominal Size)


i) Bitumen@ 4.5 per cent of weight of mix
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent

cum

57.300

1103.60

63236.28

M-044

10 - 5 mm 38 per cent

cum

108.870

1078.94

117464.20

M-040

Page 9 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

5 mm and below 40 per cent

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

cum

114.600

992.30

113717.58

M-030

tonne

8.620

4500.00

38790.00

M-188

tonne

22.500

55132.00

1240470.00

M-074

9.5 - 4.75 mm@ 57 per cent

cum

162.450

1078.94

175273.80

M-040

4.75 and below@ 41 per cent

cum

116.850

992.30

115950.26

M-030

tonne

8.620

4500.00

38790.00

M-188

Filler @ 2 per cent of weight of aggregates.


or
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of mix
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum

Filler @ 2 per cent of weight of aggregates.

(i)

*Any one of the alternative may be adopted as per


approved design
for Grading I ( 13 mm nominal size )
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

160242.61
176266.87

Cost for 205 cum = a+b+c+d+e

1938935.57

Rate per cum = (a+b+c+d+e)/195 (For Grading I)

9943.26
say

5.7

(ii)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

172327.91
189560.70

Cost for 205 cum = a+b+c+d+e

2085167.70

Rate per cum = (a+b+c+d+e)/195 (For Grading-II)

10693.17
say

Note

9943.00

for GradingII(10 mm nominal size)

*1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case SDBC is laid over freshly laid tack coat, provision
of broom and 2 mazdoor shall be deleted as the same has
been included in the cost of tack coat.
5. The quantity of Bitumen to be adjusted as per job mix
formula.

Page 10 of 264

10693.00

Sr No
5.8

Ref. to
MoRTH
Spec.

Description

509 / 507

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Bituminous Concrete
Providing and laying bituminous concrete with 100-120 TPH
batch type hot mix plant producing an average output of 75
tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 5.4 to 5.6 per
cent of mix and filler, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 507
complete in all respects
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour

b)

Mate

day

0.840

151.44

127.21

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels

day

16.000

136.69

2187.04

L-13

day

5.000

164.69

823.45

L-15

Batch mix HMP @ 75 tonne per hour

hour

6.000

13842.00

83052.00

P&M-022

Paver finisher hydrostatic with sensor control @ 75


cum per hour
Generator 250 KVA

hour

6.000

2674.00

16044.00

P&M-034

hour

6.000

1906.88

11441.25

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

tonne.km

450 x L

2.46

1105.99

Lead =1
km & P&M058

Machinery

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Smooth wheeled roller 8-10 tonnes for initial break
down rolling.
Vibratory roller 8 tonnes for intermediate rolling.

c)

110.60
hour

6.00x0.65*

460.00

1794.00

P&M-044

hour

6.00x0.65*

1541.00

6009.90

P&M-059

hour

6.00x0.65*

1144.00

4461.60

P&M-045

tonne

24.300

56122.00

1363764.60

M-074

20 - 10 mm 35 per cent

cum

99.330

1103.60

109620.59

M-045

10 - 5 mm 23 per cent

cum

65.274

1078.94

70426.73

M-040

5 mm and below 40 per cent

cum

113.520

992.30

112645.90

M-030

tonne

8.514

4500.00

38313.00

M-188

13.2 - 10 mm30 per cent

cum

85.500

1103.60

94357.80

M-044

10 - 5 mm 25 per cent

cum

71.250

1078.94

76874.48

M-040

5 mm and below43 per cent

cum

122.550

992.30

121606.37

M-030

tonne

8.620

4500.00

38790.00

M-188

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller.
Material
i) Bitumen@ 5.4 per cent of weight of mix

ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 24.30 tonnes
Weight of aggregate = 450 -24.30 = 425.70 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 283.80 cum
* Grading - 1-19 mm (Nominal Size) 50 mm

Filler @ 2 per cent of weight of aggregates.


or
Grading - 2-13.2 mm (Nominal Size) 30-40 mm

Filler @ 2 per cent of weight of aggregates.

(i)

*Any one of the alternative may be adopted as per


approved design
for Grading-I ( 13 mm nominal size )
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

182676.38
200944.02

Cost for 205 cum = a+b+c+d+e

2210384.26

Rate per cum = (a+b+c+d+e)/191

11572.69

Add 1 % labour Cess

115.73
11688.42
say

5.8

(ii)

11688.42

for Grading-II(10 mm nominal size)


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Cost for 205 cum = a+b+c+d+e

182738.63
201012.49
2211137.39

Page 11 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Rate per cum = (a+b+c+d+e)/191 (For Grading-II)

Remarks/
Input ref.

11576.64

Add 1 % labour Cess

115.77
11692.40
say

Note

11692.40

*1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case BC is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be
used for construction i.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.
6. The individual percentage of aggregates should be
calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.

5.9

510

Surface Dressing
Providing and laying surface dressing as wearing course in
single coat using crushed stone aggregates of specified size
on a layer of bituminous binder laid on prepared surface and
rolling with 8-10 tonne smooth wheeled steel roller
Unit = sqm
Taking output = 9000 sqm
Case -1 :-19 mm nominal chipping size
a) Labour

b)

c)

Mate

day

0.440

151.44

66.63

L-12

Mazdoor

day

9.000

136.69

1230.21

L-13

Mazdoor skilled

day

2.000

164.69

329.38

L-15

Mechanical broom @ 1250 sqm per hour

hour

7.200

357.00

2570.40

P&M-031

Air compressor 250 cfm

hour

7.200

319.00

2296.80

P&M-001

Hydraulic self propelled chip spreader @ 1500 sqm per


hour
Tipper 10 tonne capacity for carriage of stone chips
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity

hour

6.000

2635.00

15810.00

P&M-025

hour

6.000

339.00

2034.00

P&M-048

hour

6.000

806.00

4836.00

P&M-017

Bitumen pressure distributor

hour

6.000

1073.00

6438.00

P&M-004

Smooth wheeled roller 8-10 tonne weight

hour

6.000

460.00

2760.00

P&M-044

tonne

10.800

55132.00

595425.60

M-074

cum

135.000

1028.00

138780.00

M-053

Machinery

Material
Bitumen@ 1.20 kg per sqm

d)

Crushed stone chipping,19 mm nominal size @ 0.015


cum per sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

77257.70
84983.47

Cost for 9000 sqm = a+b+c+d+e

934818.20

Rate per sqm = (a+b+c+d+e)/9000

103.87
say

5.9

104.00

Case - II 13 mm nominal size chipping


a) Labour

b)

Mate

day

0.440

151.44

66.63

L-12

Mazdoor

day

9.000

136.69

1230.21

L-13

Mazdoor skilled

day

2.000

164.69

329.38

L-15

Mechanical broom @ 1250 sqm per hour

hour

7.200

357.00

2570.40

P&M-031

Air compressor 250 cfm

hour

7.200

319.00

2296.80

P&M-001

Machinery

Page 12 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Quantity

Rate Rs

Cost Rs

Hydraulic self propelled chip spreader @ 1500 sqm per


hour
Tipper 10 tonne capacity for carriage of stone chips
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity

hour

6.000

2635.00

15810.00

P&M-025

hour

6.000

339.00

2034.00

P&M-048

hour

6.000

806.00

4836.00

P&M-017

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

1073.00

6438.00

P&M-004

Vibratory roller 8-10 tonne weight

hour

6.000

1541.00

9246.00

P&M-059

tonne

9.000

55132.00

496188.00

M-074

cum

90.000

1028.00

92520.00

M-052

Material
Bitumen@ 1.00 kg per sqm

d)

Crushed stone chipping,13 mm nominal size @ 0.01


cum per sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

63356.54
69692.20

Cost for 9000 sqm = a+b+c+d+e

766614.16

Rate per sqm = (a+b+c+d+e)/9000

85.18
say

Note

5.10

Remarks/
Input ref.

85.00

1.Where the proposed aggregate fails to pass the stripping


test, an approved adhesion agent may be added to the
binder as per clause 510.2.4. Alternatively, chips may be
pre-coated as per clause 510.2.5
2.Input for the second coat, where required, will be the same
as per the Ist coat mentioned above
Open - Graded Premix Surfacing

511

Providing, laying and rolling of open - graded premix


surfacing of 20 mm thickness composed of 13.2 mm to 5.6
mm aggregates either using penetration grade bitumen or
cut-back or emulsion to required line, grade and level to
serve as wearing course on a previously prepared base,
including mixing in a suitable plant, laying and rolling with a
smooth wheeled roller 8-10 tonne capacity, finished to
required level and grades.
Unit = sqm
Taking output = 10250 sqm (205 cum)
(i)

Case - I: Mechanical method using Penetration grade


Bitumen and HMP of appropriate capacity not less than
75 tonnes/hour .
a) Labour

b)

Mate

day

0.840

151.44

127.21

L-12

Mazdoor working with HMP, road sweeper, paver and


roller
Skilled mazdoor for checking line & levels

day

16.000

136.69

2187.04

L-13

day

5.000

164.69

823.45

L-15

i) Batch type HMP 75 tonne per hour

hour

6.000

23405.00

140430.00

P&M-021

ii) Electric Generator Set 250 KVA

hour

6.000

1906.88

11441.25

P&M-081

iii) Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

tonne.km

450 x L

2.46

1105.99

Lead =1
km & P&M058

Machinery

iv) Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
v) Paver finisher hydrostatic with sensor attachment
iv) Smooth wheeled/tandom roller 8-10 tonnes weight
c)

110.60
hour

6.000

2674.00

16044.00

P&M-034

hour

6.000

1144.00

6864.00

P&M-045

tonne

14.970

55132.00

825326.04

M-074

cum

276.750

998.50

276334.88

M-043

Material
Bitumen@ 14.60 kg per 10 sqm

d)

Crushed stone chipping,13.2 mm to 5.6 mm @ 0.27


cum per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

128563.05
141419.35

Cost for 10250 sqm = a+b+c+d+e

1555612.85

Rate per sqm = (a+b+c+d+e)/10250

151.77
say

Page 13 of 264

152.00

Sr No

Ref. to
MoRTH
Spec.

5.10

Description

Unit

Note

If a premix sand seal coat of 'B' type is proposed, the same


is required to be provided over the open graded premix
carpet immediately on the same day. As the same HMP and
other machines will be used for laying of premix sand seal
coat, out of 6 effective working hours, 4.00 hours may be
utilised for laying of premix carpet and balance 2.00 hours
for the seal coat. The rate for the premix sand seal coat
under clause 513 (case II) has been worked out accordingly
by utilising the HMP for 2.00 hours for the purpose of seal
coat. In case type 'A' seal coat is proposed, HMP can be
worked for six hours for the premix carpet as type 'A' seal
coat does not require the use of HMP.

(ii)

Case - II: Open-Graded Premix Surfacing using cationic


Bitumen Emulsion
Unit = sqm

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 900 sqm (24.3 cum)


a) Labour

b)

c)

Mate

day

0.800

151.44

121.15

L-12

Mazdoor

day

18.000

136.69

2460.42

L-13

Mazdoor skilled

day

2.000

164.69

329.38

L-15

Concrete mixer 0.4/0.28 cum capacity

hour

6.000

233.00

1398.00

P&M-009

Smooth wheeled steel roller 8-10 tonne

hour

6.000

460.00

2760.00

P&M-044

tonne

1.940

55145.00

106981.30

M-073

cum

24.300

998.50

24263.55

M-043

Machinery

Material
Cationic Bitumen Emulsion @ 21.50 kg per 10 sqm

d)

Crushed stone aggregates 13.2 mm to 5.6 mm @ 0.27


cum per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

13831.38
15214.52

Cost for 900 sqm = a+b+c+d+e

167359.70

Rate per sqm = (a+b+c+d+e)/900

185.96
say

5.11

512

186.00

Close Graded Premix Surfacing/Mixed Seal Surfacing


Case I Mechanical means using HMP of appropriate capacity not
less than 75 tonnes/hour.
Providing, laying and rolling of close-graded premix
surfacing material of 20 mm thickness composed of 11.2 mm
to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b)
aggregates using penetration grade bitumen to the required
line, grade and level to serve as wearing course on a
previously prepared base, including mixing in a suitable
plant, laying and rolling with a Smooth wheeled roller 8-10
tonne capacity, and finishing to required level and grade.
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour

b)

Mate

day

0.840

151.44

127.21

L-12

Mazdoor working with HMP, road sweeper, paver and


roller
Skilled mazdoor for checking line & levels

day

16.000

136.69

2187.04

L-13

day

5.000

164.69

823.45

L-15

i) HMP of appropicate capacity.

hour

6.000

23405.00

140430.00

P&M-021

ii) Electric Generator Set 250 KVA

hour

6.000

1906.88

11441.25

P&M-081

iii) Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

tonne.km

450 x L

2.46

1105.99

Lead =1
km & P&M058

Machinery

iv) Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
v) Paver finisher hydrostatic with sensor attachment
iv) Smooth wheeled8-10 tonnes weight
c)

110.60
hour

6.000

2674.00

16044.00

P&M-034

hour

6.000

460.00

2760.00

P&M-044

tonne

22.500

55132.00

1240470.00

M-074

cum

276.750

987.00

273152.25

M-041

Material

Type - A
* Bitumen@ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 @ 0.27
cum per 10 sqm
or
Type - B
Page 14 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Bitumen @ 19 kg per 10 sqm

d)

Stone crushed aggregates 13.2 mm to 0.09 mm @


0.27 cum per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

tonne

19.480

55132.00

1073971.36

M-074

cum

276.750

1000.67

276934.50

M-042

169348.78
186283.66

Cost for 10250 sqm = a+b+c+d+e

2049120.22

Rate per sqm = (a+b+c+d+e)/10250

199.91
say

200.00

* Any one of the alternative may be adopted


5.12

513

Seal Coat
Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and
cross fall using Type A and B seal coats
Unit = sqm
Taking output = 10250 sqm (92.25 cum)
(i)

Case - I : Type A
a) Labour

b)

c)

Mate

day

0.240

151.44

36.35

L-12

Mazdoor

day

6.000

136.69

820.14

L-13

Hydraulic self propelled chip spreader

hour

6.000

2635.00

15810.00

P&M-025

Tipper 5.5 cum capacity

hour

6.000

339.00

2034.00

P&M-048

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

1073.00

6438.00

P&M-004

Smooth wheeled roller 8 -10 tonne weight

hour

6.000

460.00

2760.00

P&M-044

tonne

10.050

55132.00

554076.60

M-074

cum

92.250

969.00

89390.25

M-050

Machinery

Material
Bitumen@ 9.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size defined as 100
per cent passing 11.2 mm sieve and retained on 2.36
mm sieve applied @ 0.09 cum per 10 sqm

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

67620.13
74382.15

Cost for 10250 sqm = a+b+c+d+e

818203.62

Rate per sqm = (a+b+c+d+e)/10250

79.82
say

Note

5.12

(ii)

80.00

Since seal coat is provided immediately over the bituminous


layers, mechanical broom for clearing has not been catered.
Case - II : Type B
Providing and laying of premix sand seal coat with HMP of
appropriate capacity not less than 75 tonnes/ hours using
crushed stone chipping 6.7 mm size and penetration
bitumen of suitable grade.
Unit = sqm
Taking output = 7858 sqm (47.16 cum)
a) Labour

b)

Mate

day

0.160

151.44

24.23

L-12

Mazdoor

day

4.000

136.69

546.76

L-13

Machinery
HMP of 75 tonnes/hour.

hour

2.000

17309.00

34618.00

P&M-022

Electric Generator Set 250 KVA

hour

2.000

1906.88

3813.75

P&M-081

Front end loader 1 cum bucket capacity

hour

2.000

806.00

1612.00

P&M-017

tonne.km

104 x 'L'

2.46

255.61

Lead =1
km & P&M058

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Paver finisher hydrostatic with sensor attachment
Smooth wheeled 8-10 tonnes capacity
c)

25.56
hour

2.000

2674.00

5348.00

P&M-034

hour

2.000

460.00

920.00

P&M-044

tonne

5.340

55132.00

294404.88

M-074

cum

47.160

969.00

45698.04

M-050

Material
Bitumen@ 6.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size defined as
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.06 cum per 10 sqm

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Cost for 7858 sqm = a+b+c+d+e

38726.68
42599.35
468592.86

Rate per sqm = (a+b+c+d+e)/7858

59.63
Page 15 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs
say

Note

5.13

514

Remarks/
Input ref.

60.00

Since seal coat is required to be provided over the premix


carpet on the same day, out of the 6 working hours of the
HMP, 4.00 hours are proposed to be utilised for the premix
carpet and the balance 2.00 hours for the seal coat. Hence
2.00 hours have been considered for this case. This may be
linked to rate analysis worked out under clause 511.
Supply of Stone Aggregates for Pavement Courses
Supply of stone aggregates from approved sources
conforming to the physical requirement, specified in the
respective specified clauses, including royalties, fees rents,
collection, transportation, stacking and testing and measured
in cum as per clause 514.5
Competitive market rates to be as certained. Alternatively,
rates for stone crushing given in chapter 1may be adopted, if
found economical. In case for supply of aggregates at site
are not available, nearest crusher site may be as certained.
Loading and un-loading charges and cost of carriage may be
added to these rates to arrive at the cost at site.

5.14

515

Mastic Asphalt
Providing and laying 25 mm thick mastic asphalt wearing
course with paving grade bitumen meeting the requirements
given in table 500-29, prepared by using mastic cooker and
laid to required level and slope after cleaning the surface,
including providing antiskid surface with bitumen precoated
finegrained hard stone chipping of 13.2 mm nominal size at
the rate of 0.005cum per 10 sqm and at an approximate
spacing of 10 cm center to center in both directions, pressed
into surface when the temperature of surfaces is not less
than 1000C, protruding 1 mm to 4 mm over mastic surface,
all complete as per clause 515.

Unit = sqm
Taking output = 35.00 sqm (0.87 cum ) assuming a
density of 2.3 tonnes/cum.-2 tonnes
a) Labour

b)

c)

Mate

day

0.440

151.44

66.63

L-12

Mazdoor

day

10.000

136.69

1366.90

L-13

Mazdoor skilled

day

1.000

164.69

164.69

L-15

Mechanical broom @ 1250 sqm per hour

hour

0.060

357.00

21.42

P&M-031

Air compressor 250 cfm

hour

0.060

319.00

19.14

P&M-001

Mastic cooker 1 tonne capacity

hour

6.000

62.00

372.00

P&M-030

Bitumen boiler 1500 litres capacity

hour

6.000

198.00

1188.00

P&M-005

Tractor for towing and positioning of mastic cooker and


bitumen boiler
Material

hour

1.000

282.50

282.50

P&M-053

tonne

0.204

55132.00

11246.93

M-074

cum

0.390

476.80

185.95

M-021

tonne

0.360

4500.00

1620.00

M-188

cum

0.550

998.50

549.18

M-043

cum

0.018

1213.00

21.83

M-142

kg

0.500

55.00

27.50

M-074

Machinery

Base mastic (without coarse aggregates) = 60 per cent


Coarse aggregate (6.3mm to 13.2 mm) = 40 per cent .
Proportion of material required for mastic asphalt with coarse
aggregates (based on mix design done by CRRI for a
specific case)
I) Bitumen 85/25 or 30/40 @ 10.2 per cent by weight
of mix. 2 x 10.2/100 = 0.204
ii) Fine aggregate passing 2.36mm and retained on
0.075mm sieve @ 31.9 per cent by weight of mix = 2 x
31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium content not less
than 80 per cent by weight @ 17.92 per cent by
weight of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 6.3 mm to 13.2 mm @ 40 per
cent by weight of mix = 2 x 40/100 = 0.8 MT =
0.8/1.456 = 0.55
v) Pre-coated stone chips of 13.2 mm nominal size for
skid resistance = 35 x 0.005/10 = 0.018
vi) Bitumen for coating of chips @ 2 per cent by weight
= 0.018 x 1.456 x 2/100 = 0.0005 MT = 0.5kg
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1713.27
1884.59

Cost for 35.00 sqm = a+b+c+d+e

20730.53

Rate per sqm = (a+b+c+d+e)/35

592.30
Page 16 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs
say

Note

1.The rates for 50 mm & 40 mm thick layers may be worked


out on pro-rata basis.
2.Where tack coat is required to be provided before laying
mastic asphalt, the same is required to be measured and
paid separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix
design.
4.This rate analysis is based on design made by CRRI for a
specific case and is meant for estimating purposes only.
Actual design is required to be done for each case.

Page 17 of 264

592.00

Remarks/
Input ref.

Sr No
5.15

Ref. to
MoRTH
Spec.

Description

Unit

516

Slurry Seal

512

Providing and laying slurry seal consisting of a mixture of


fine aggregates, portland cement filler, bituminous emulsion
and water on a road surface including cleaning of surface,
mixing of slurry seal in a suitable mobile plant, laying and
compacting to provide even riding surface
(i)

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum
weight of mix = 176 tonnes
a) Labour

b)

c)

Mate

day

0.240

151.44

36.35

L-12

Mazdoor

day

6.000

136.69

820.14

L-13

Mechanical broom

hour

6.000

357.00

2142.00

P&M-031

Air compressor 250 cfm

hour

6.000

319.00

1914.00

P&M-001

Mobile slurry seal equipment

hour

6.000

1008.00

6048.00

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment, bitumen
emulsion and filler.

hour

6.000

339.00

2034.00

P&M-048

Pneumatic tyred roller with individual wheel load not


exceeding 1.5 tonnes
Water tanker6 KL capacity

hour

6.000

1243.00

7458.00

P&M-037

hour

2.000

200.00

400.00

P&M-060

tonne

19.360

49915.00

966354.40

M-077

cum

102.080

1066.89

108908.13

M-030

tonne

3.520

5000.00

17600.00

M-188

KL

12.000

10.00

120.00

M-189

Machinery

Material
Residual Binder @ 11 per cent of mix 80 x 2.2 x 0.11
Fine aggregate 4.75 mm and below 87 per cent of
total mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking
density1.5, = 153.12/1.5 = 102.08 cum
Filler (ordinary Portland Cement) @ 2 per cent of total
mix = 80 x 2.2 x 0.02
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

111867.10
123053.81

Cost for 16000 sqm = a+b+c+d+e

1353591.93

Rate per sqm = (a+b+c+d+e)/16000

84.60

Add 1 % labour Cess

0.85
85.45
say

Page 18 of 264

85.45

Sr No
5.15

Ref. to
MoRTH
Spec.

Description
(ii)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour

b)

c)

Mate

day

0.200

151.44

30.29

L-12

Mazdoor

day

5.000

136.69

683.45

L-13

Mechanical broom

hour

6.000

357.00

2142.00

P&M-031

Air compressor 250 cfm

hour

6.000

319.00

1914.00

P&M-001

Mobile slurry seal equipment

hour

6.000

1008.00

6048.00

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment, bitumen
emulsion and filler
Water tanker6 KL capacity

hour

6.000

339.00

2034.00

P&M-048

hour

2.000

200.00

400.00

P&M-060

Residual Binder @ 13 per cent of mix = 60 x 2.2 x


0.13
Fine aggregate 3 mm and below 85 per cent of total
mix, 60x 2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,

tonne

17.160

49915.00

856541.40

M-077

cum

74.800

867.00

64851.60

M-022

Filler @ 2 per cent of total mix = 60x 2.2 x 0.02

tonne

2.640

4500.00

11880.00

M-188

KL

12.000

10.00

120.00

M-189

Machinery

Material

Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

95148.07
104662.88

Cost for 30000 sqm = a+b+c+d+e

1151291.69

Rate per sqm = (a+b+c+d+e)/20000

57.56
say

5.15

(iii)

58.00

1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour

b)

c)

Mate

day

0.200

151.44

30.29

L-12

Mazdoor

day

5.000

136.69

683.45

L-13

Mechanical broom

hour

6.000

357.00

2142.00

P&M-031

Air compressor 250 cfm

hour

6.000

319.00

1914.00

P&M-001

Mobile slurry seal equipment

hour

6.000

1008.00

6048.00

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment, bitumen
emulsion and filler.

hour

6.000

339.00

2034.00

P&M-048

Water tanker6 KL capacity

hour

2.000

200.00

400.00

P&M-060

Residual Binder @ 16 per cent of mix, 36 x 2.2 x 0.16

tonne

12.670

49915.00

632423.05

M-077

Fine aggregate 2.36 mm and below,82 per cent of


total mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density
1.5

cum

43.300

867.00

37541.10

M-022

tonne

1.580

4500.00

7110.00

M-188

KL

12.000

10.00

120.00

M-189

Machinery

Material

Filler @ 2 per cent of total mix = 36x 2.2 x 0.02


Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

69528.19
76481.01

Cost for 24000 sqm = a+b+c+d+e

841291.08

Rate per sqm = (a+b+c+d+e)/24000

35.05
say

Note

1.Tack coat, if required to be provided, before laying slurry


seal may be measured and paid separately

Page 19 of 264

35.00

Sr No
5.16

Ref. to
MoRTH
Spec.

Description

517

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Recycling of Bituminous Pavement with Central


Recycling Plant
Recycling pavement by cold milling of existing bituminous
layers, planning the surface after cold milling, reclaiming
excavated material to the extent of 30 per cent of the
required quantity, hauling and stock piling the reclaimed
material near the central recycling plant after carrying out
necessary checks and evaluation, adding fresh material
including rejuvenators as required, mixing in a hot mix plant,
transporting and laying at site and compacting to the
required grade, level and thickness, all as specified in clause
517.
Unit = cum
Taking output = 120 cum (276 tonnes)
a) Labour

b)

c)

Mate

day

0.480

151.44

72.69

L-12

Mazdoor

day

10.000

136.69

1366.90

L-13

Mazdoor skilled

day

2.000

164.69

329.38

L-15

Cold milling machine @ 20 cum per hour

hour

6.000

300.00

1800.00

P&M-069

Mechanical broom @ 1250 sqm per hour

hour

1.280

357.00

456.96

P&M-031

Air compressor 250 cfm

hour

1.280

319.00

408.32

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

0.910

1073.00

976.43

P&M-004

Hot mix plant 100-120 TPH producing an average of 75


tonnes per hour
Electric generator set 250 KVA

hour

3.000

23405.00

70215.00

P&M-021

hour

3.000

1906.88

5720.63

P&M-081

Front end loader 1.00 cum bucket capacity

hour

3.000

806.00

2418.00

P&M-017

Tipper 5.5 cum capacity

hour

18.000

339.00

6102.00

P&M-048

Smooth wheeled roller 8-10 tonnes

hour

3.00x0.65*

460.00

897.00

P&M-044

Vibratory roller 8 tonnes

hour

3.00x0.65*

1541.00

3004.95

P&M-059

Smooth wheeled tandem roller 6-8 tonnes

hour

3.00x0.65*

1144.00

2230.80

P&M-045

tonne

1.987

55132.00

109558.31

M-074

tonne

7.728

55132.00

426060.10

M-074

37.5 - 25 mm @ 23 per cent

cum

28.440

1011.94

28779.57

M-049

25 - 10 mm @ 15 per cent

cum

18.550

1103.60

20471.78

M-046

10- 5 mm @ 20 per cent

cum

24.730

1078.94

26682.19

M-040

Below 5 mm @40 per cent

cum

49.460

992.30

49079.16

M-030

tonne

5.520

5000.00

27600.00

M-081

Machinery

Material

i) Bitumen
A bitumen content is 4.5 per cent bitumen weight of mix. For
reclaimed material, fresh bitumen will be required to the
extent of 60 per cent of normal requirement.
In a mix of 276 tonnes, 82.8 tonne is reclaimed and balance
193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne @ 60
per cent = 82.8 x 0.60 x0.04 = 1.99
Bitumen required for fresh mix of 193.2 tonnes = 193.2
x 0.04 = 7.73
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per cent
Weight of fresh mix = 276 x 0.70 = 193.2 tonne
Weight of fresh aggregate in the mix = 193.2 x 0.96 = 185.47
tonne
Taking average density of 1.5 tonnes/cum, total volume
of aggregate = 123.65 cum.
Size wise requirement of fresh aggregates

Filler (cement) @ 2 per cent = 5.52tonnes of 276 tonne


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

78423.02
86265.32

Cost for 120 cum of DBM = a+b+c+d+e

948918.49

Rate per cum = (a+b+c+d+e)/120

7907.65
say

Note

5.17

518

Although the total rolling time is only 4 hours as per norms,


all the three rollers have to be available at site for 3 hours
each to match with the output of re-cycling plant. To cater for
their idling time, these have been multiplied with a factor of
0.65.
Fog Spray
Providing and applying low viscosity bitumen emulsion for
sealing cracks less than 3 mm wide or incipient fretting or
disintegration in an existing bituminous surfacing.
Page 20 of 264

7908.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.120

151.44

18.17

L-12

Mazdoor

day

3.000

136.69

410.07

L-13

Mechanical broom @ 1250 sqm per hour

hour

6.000

357.00

2142.00

P&M-031

Air compressor 250 cfm

hour

6.000

319.00

1914.00

P&M-001

Bitumen emulsion pressure distributor @ 1750 sqm per


hour
Material

tonne

6.000

1073.00

6438.00

P&M-004

Bitumen emulsion @ 0.75 kg per sqm

tonne

7.880

49915.00

393330.20

Machinery

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

M-077

40425.24
44467.77

Cost for 10500 sqm = a+b+c+d+e

489145.46

Rate per sqm = (a+b+c+d+e)/10500

46.59
say

47.00

1.In case it is decided by the engineer to blind the fog spray,


the following may be added
a) Labour

b)

Mate

day

0.160

151.44

24.23

L-12

Mazdoor for precoating of grit

day

4.000

136.69

546.76

L-13

cum

26.250

867.00

22758.75

M-024

tonne

0.790

49915.00

39432.85

M-077

Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm
Bitumen emulsion for precoating grit @ 2 per cent of
grit,39.38 x 0.02

62762.59
5.98
say
5.18

519

6.00

Bituminous Cold Mix ( Including Gravel Emulsion)


Providing, laying and rolling of bituminous cold mix on
prepared base consisting of a mixture of unheated mineral
aggregate and emulsified or cutback bitumen, including
mixing in a plant of suitable type and capacity, transporting,
laying, compacting and finishing to specified grades and
levels.
Unit = cum
Taking output = 205 cum (450 tonne)
(i)

Using bitumen emulsion and 9.5 mm or 13.2 mm size


aggregate
Composition of mix (450 tonne) is assumed to be as
under:Bitumen Emulsion 8 per cent

By weight
of total mix

Filler2 per cent


Total aggregates 90 per cent
Proportion of aggregates
19 mm to 9.5 mm25 per cent
9.5 mm to 6 mm29 per cent
6 mm to 0.075 mm 36 per cent
a) Labour

b)

Mate

day

0.840

151.44

127.21

L-12

Mazdoor

day

16.000

136.69

2187.04

L-13

Mazdoor skilled

day

5.000

164.69

823.45

L-15

Drum mix plant for cold mixes of appropriate capacity


but not less than 75 tonnes/hour.
Electric generator 125 KVA

hour

6.000

3661.20

21967.20

P&M-077

hour

6.000

652.00

3912.00

P&M-018

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

tonne.km

450 x L

2.46

1105.99

Lead =1
km & P&M058

Machinery

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Paver finisher

c)

110.60
hour

6.000

2674.00

16044.00

P&M-034

Pneumatic tyred roller 12-15 tonnes

hour

6.00x0.65*

1243.00

4847.70

P&M-037

Smooth wheeled steel tandem roller 6-8 tonnes

hour

6.00x0.65*

1144.00

4461.60

P&M-045

tonne

36.000

49915.00

1796940.00

Material
Bitumen emulsion @ 8 per cent
Page 21 of 264

M-077

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Filler (lime)@ 2 per cent

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

tonne

9.000

4500.00

40500.00

M-188

Aggregates size 19 to 9.5 mm - 450 x 0.25 x 1/1.5

cum

75.000

1103.60

82770.00

M-045

Aggregates size 9.5 to 6 mm - 450 x 0.29 x 1/1.5

cum

87.000

1078.94

93867.78

M-040

Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5

cum

108.000

992.30

107168.40

M-030

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

218166.90
239983.59

Cost for 205 cum = a+b+c+d+e

2639819.45

Rate per cum = (a+b+c+d+e)/205

12877.17
say

12877.00

(Applicable to cases I to IV)


Note

1.Density of aggregates has been assumed 1.5 gms/cc


2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, their usage rates have been multiplied by a
factor of 0.65

5.18

(ii)

Using bitumen emulsion and 19 mm or 26.5 mm nominal


size aggregate
Composition of mix (450 tonne)
is assumed to be as
under:Bitumen Emulsion 8 per cent
Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 35 per cent
a) Labour

b)

Mate

day

0.840

151.44

127.21

L-12

Mazdoor

day

16.000

136.69

2187.04

L-13

Mazdoor skilled

day

5.000

164.69

823.45

L-15

Drum mix plant for cold mixes 60-90 tonne per hour
producing average output of 75 tonnes per hour
Electric generator 125 KVA

hour

6.000

3661.20

21967.20

P&M-077

hour

6.000

652.00

3912.00

P&M-018

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

tonne.km

450 x L

2.46

1105.99

Lead =1
km & P&M058

Machinery

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Paver finisher

c)

110.60
hour

6.000

2674.00

16044.00

P&M-034

Pneumatic tyred roller 12-15 tonnes

hour

6.00x0.65*

1243.00

4847.70

P&M-037

Smooth wheeled steel tandom roller 6-8 tonnes

hour

6.00x0.65*

1144.00

4461.60

P&M-045

Bitumen emulsion @ 8 per cent

tonne

36.000

49915.00

1796940.00

M-077

Filler (lime)@ 2 per cent

tonne

9.000

4500.00

40500.00

M-188

Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5

cum

75.000

956.33

71725.00

M-048

Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5

cum

90.000

1000.67

90060.00

M-047

Aggregates size 6 to 0.075 mm - 450 x 0.35 x 1/1.5

cum

105.000

992.30

104191.50

M-030

Material

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

216383.93
238022.32

Cost for 205 cum = a+b+c+d+e

2618245.54

Rate per cum = (a+b+c+d+e)/205

12771.93
say

Note

1.Density of aggregates has been assumed 1.5 gms/cc


2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, their usage rates have been multiplied by a
factor of 0.65

5.18

(iii)

Using cutback bitumen and 9.5 mm or 13.2 mm nominal


size aggregate
Page 22 of 264

12772.00

Sr No

Ref. to
MoRTH
Spec.

Description
Composition of mix (450 tonne)
under:Cutback bitumen 5 per cent
Filler (lime)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

is assumed to be as

2 per cent

Total aggregates 93 per cent


Proportion of aggregates
19 mm to 9.5 mm26 per cent
9.5 mm to 6 mm31 per cent
6 mm to 0.075 mm 36 per cent
a) Labour

b)

Mate

day

0.840

151.44

127.21

L-12

Mazdoor

day

16.000

136.69

2187.04

L-13

Mazdoor skilled

day

5.000

164.69

823.45

L-15

Drum mix plant for cold mixes 60-90 tonne per hour
producing average output of 75 tonnes per hour
Electric generator 125 KVA

hour

6.000

3661.20

21967.20

P&M-077

hour

6.000

652.00

3912.00

P&M-018

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

tonne.km

450 x L

2.46

1105.99

Lead =1
km & P&M058

Machinery

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Paver finisher

c)

110.60
hour

6.000

2674.00

16044.00

P&M-034

Pneumatic tyred roller 12-15 tonnes

hour

6.00x0.65*

1243.00

4847.70

P&M-037

Smooth wheeled steel tandem roller 6-8 tonnes

hour

6.00x0.65*

1144.00

4461.60

P&M-045

Cutback bitumen @ 5 per cent

tonne

22.500

47937.00

1078582.50

M-076

Filler (lime)@ 2 per cent

tonne

9.000

4500.00

40500.00

M-188

Aggregates size 19 to 9.5 mm - 450 x 0.26 x 1/1.5

cum

78.000

1103.60

86080.80

M-045

Aggregates size 9.5 to 6 mm - 450 x 0..31 x 1/1.5

cum

93.000

1078.94

100341.42

M-040

Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5

cum

108.000

992.30

107168.40

M-030

Material

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

147309.59
162040.55

Cost for 205 cum = a+b+c+d+e

1782446.05

Rate per cum = (a+b+c+d+e)/205

8694.86
say

Note

8695.00

1.Density of aggregates has been assumed 1.5 gms/cc


2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, their usage rates have been multiplied by a
factor of 0.65

5.18

(iv)

Using cutback bitumen and 19 mm or 26.5 mm nominal


size aggregate
Composition of mix (450 tonne)
is assumed to be as
under:Cutback bitumen 5 per cent
Filler2 per cent
Total aggregates 93 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 38 per cent
a) Labour

b)

Mate

day

0.840

151.44

127.21

L-12

Mazdoor

day

16.000

136.69

2187.04

L-13

Mazdoor skilled

day

5.000

164.69

823.45

L-15

Drum mix plant for cold mixes 60-90 tonne per hour
producing output of 75 tonnes per hour
Electric generator 125 KVA

hour

6.000

3661.20

21967.20

P&M-077

hour

6.000

652.00

3912.00

P&M-018

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

tonne.km

450 x L

2.46

1105.99

Lead =1
km & P&M058

Machinery

Tipper 10 tonne capacity

Page 23 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Paver finisher

c)

Quantity

Rate Rs

Cost Rs
110.60

hour

6.000

2674.00

16044.00

P&M-034

Pneumatic tyred roller 12-15 tonnes.

hour

6.00x0.65*

1243.00

4847.70

P&M-037

Smooth wheeled steel tandem roller 6-8 tonnes

hour

6.00x0.65*

1144.00

4461.60

P&M-045

Cutback bitumen on @ 5 per cent

tonne

22.500

47937.00

1078582.50

M-076

Filler (lime)@ 2 per cent

tonne

9.000

4500.00

40500.00

M-188

Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5

cum

75.000

956.33

71725.00

M-048

Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5

cum

90.000

1000.67

90060.00

M-047

Aggregates size 6 to 0.075 mm - 450 x0.38 x 1/1.5

cum

114.000

992.30

113122.20

M-030

Material

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

145441.25
159985.37

Cost for 205 cum = a+b+c+d+e

1759839.11

Rate per cum = (a+b+c+d+e)/205

8584.58
say

Note

Remarks/
Input ref.

8585.00

1.Density of aggregates has been assumed 1.5 gms/cc


2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, their usage rates have been multiplied by a
factor of 0.65

5.19

520

Sand Asphalt Base Course


Providing, laying and rolling sand-asphalt base course
composed of sand, mineral filler and bituminous binder on a
prepared sub-grade or sub-base to the lines, levels, grades
and cross sections as per the drawings including mixing in a
plant of suitable type and capacity, transporting, laying,
compacting and finishing.
Unit = cum
Taking output = 205 cum (450 tonne)
a) Labour

b)

Mate

day

0.840

151.44

127.21

L-12

Mazdoor

day

16.000

136.69

2187.04

L-13

Mazdoor skilled

day

5.000

164.69

823.45

L-15

Hot Mix Plant of appropriate capacity but not less than


75 tonnes/hour
Electric generator set 250 KVA

hour

6.000

13842.00

83052.00

P&M-023

hour

6.000

1906.88

11441.25

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

806.00

4836.00

P&M-017

tonne.km

450 x L

2.46

1105.99

Lead =1
km & P&M058

Machinery

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Paver finisher

c)

110.60
hour

6.000

2674.00

16044.00

P&M-034

smooth wheeled roller 8-10 tonnes for initial break


down rolling.
Vibratory roller 8 tonnes for intermediate rolling.

hour

6.00x0.65

460.00

1794.00

P&M-044

hour

6.00x0.65

1541.00

6009.90

P&M-059

Finish rolling with 6-8 tonnes smooth wheeled tandom


rollers.
Material

hour

6.00x0.65

1144.00

4461.60

P&M-045

Bitumen@ 5 per cent

tonne

22.500

55132.00

1240470.00

M-074

Filler (lime)@ 2 per cent

tonne

9.000

4500.00

40500.00

M-188

cum

288.620

828.00

238977.36

M-004

Composition of mix (450 tonne)


under:Density 2.20 tonne per cum

is assumed to be as

Weight450 tonne
Bitumen5 per cent
Filler2 per cent
Sand of size 4.75 to 0.075 mm 93 per cent

Sand of size 4.75 to 0.075 mm - 450 x 0.93 x 1/1.5


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Cost for 205 cum = a+b+c+d+e

165194.04
181713.44
1998847.88

Rate per cum = (a+b+c+d+e)/205

9750.48
Page 24 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs
say

Note

1. Tack coat will be measured and paid separately


2. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of this roller, their
usage rates has been multiplied by a factor of 0.65

5.20

521

Modified Binder
Supply of modified binder produced by mixing bitumen with
modifier such as natural rubber or crumb rubber or any other
polymer found compatible with bitumen and which allows
properties given in clause 521.3 and IRC:SP: 53 blending of
modifier with bitumen to be done either at the refinery or at
central unit with all facilities by proper industrial process, is
essential.
Unit = tonne
The use of modified binder is expected to result in an
extended service life of bituminous pavements subject to
heavy traffic loads in extreme climatic conditions, thus
justifying the entire cost of adding modifiers/fibres. Other
advantages include lower temperature susceptibility, higher
resistance to aging, higher fatigue life, higher resistance to
cracking and better adhesion between aggregates and
binder.
Detailed information and inductive dose level on the use of
polymer modified binder is available in IRC : SP-53 / 2002. A
number of proprietary products are now available in the
market. For such proprietary products, test reports and cost
effectiveness should be the basis for their selection in road
works.
The modifier, in the required quantity shall be blended at the
refinery or at central unit with all facilities by proper industrial
process, is essential. If supplied in drums it shall be agitated
in melted condition with suitable device for achieving
homogeneity
Proposals to use glass fibre, polypropylene fibres or any
other similar material in a bituminous mixture should be
substantiated, complete with all details including test results,
manufacturer's recommendations for addition or means of
incorporating the fibres, homogeneously, without
segregation, into the mixture.
Before agreeing to the use of a fibre, it should have been
proved to be satisfactory in use under circumstances, similar
to the work, elsewhere or it would have under gone
appropriate performance trials. Documented evidence of use
and trials of the fibre, in any country having conditions
similar to Indian will be acceptable.

Note

where information on use of trials is inadequate or lacking,


trials may be required to be under taken before agreeing to
the use of the fibre.
1. The modified binder is usually manufactured by
specialised firms as a proprietary product. The rate for this
product is required to be as certained from the market.
2.The specifications for various item of road works using
polymer/rubber modified bitumens are same as those for
penetration grade bitumen except those for any special
conditions which the manufacturer may indicate
3.The other controls during mixing, laying shall be same as
specified in IRC - 14, 29, 94 and 95 for open graded premix
carpet, bituminous concrete, DBM and SDBC respectively
4.The temperature of mixing and rolling will be slightly higher
than conventional bituminous mixes as indicated in Table 8
of IRC: SP: 53 - 2002

5.21

522

Crack Prevention Courses


(i)

Stress absorbing membrane (SAM) crack width less


than 6 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width below 6 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 9 kg per
10 sqm and spreading 5.6 mm crushed stone aggregates @
0.11 cum per 10 sqm with hydraulic chip spreader, sweeping
the surface for uniform spread of aggregates and surface
finished to conform to clause 902.
Page 25 of 264

9750.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.240

151.44

36.35

L-12

Mazdoor

day

6.000

136.69

820.14

L-13

Mechanical broom @ 1250 sqm per hour

hour

6.000

357.00

2142.00

P&M-031

Air compressor 250 cfm

hour

6.000

319.00

1914.00

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

1073.00

6438.00

P&M-004

Hydraulic Chip spreader

hour

6.000

2635.00

15810.00

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

460.00

2760.00

P&M-044

tonne

9.450

38740.00

366093.00

M-078

cum

105.000

969.00

101745.00

M-050

Machinery

Material
Modified binder
Crushed stone aggregates 5.6 mm size

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

49775.85
54753.43

Cost for 10500 sqm = a+b+c+d+e

602287.77

Rate per sqm = (a+b+c+d+e)/10500

57.36
say

5.21

(ii)

57.00

Stress absorbing membrane (SAM) with crack width 6


mm to 9 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 11 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.240

151.44

36.35

L-12

Mazdoor

day

6.000

136.69

820.14

L-13

Mechanical broom @ 1250 sqm per hour

hour

6.000

357.00

2142.00

P&M-031

Air compressor 250 cfm capacity

hour

6.000

319.00

1914.00

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

1073.00

6438.00

P&M-004

Hydraulic Chip spreader

hour

6.000

2635.00

15810.00

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

460.00

2760.00

P&M-044

tonne

11.550

38740.00

447447.00

M-078

cum

105.000

1005.00

105525.00

M-051

Machinery

Material
Modified binder
Crushed stone chipping 11.2 mm size

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

58289.25
64118.17

Cost for 10500 sqm = a+b+c+d+e

705299.91

Rate per sqm = (a+b+c+d+e)/10500

67.17
say

5.21

(iii)

67.00

Stress absorbing membrane (SAM) crack width above 9


mm and cracked area above 50 per cent
Providing and laying a single coat of a stress absorbing
membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 per cent after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 15 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

Mate

day

0.240

151.44

36.35

L-12

Mazdoor

day

6.000

136.69

820.14

L-13

Mazdoor skilled

day

2.000

164.69

329.38

L-15

Mechanical broom @ 1250 sqm per hour

hour

6.000

357.00

2142.00

P&M-031

Air compressor 250 cfm capacity

hour

6.000

319.00

1914.00

P&M-001

Machinery

Page 26 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Quantity

Rate Rs

Cost Rs

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

1073.00

6438.00

P&M-004

Hydraulic Chip spreader

hour

6.000

2635.00

15810.00

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

460.00

2760.00

P&M-044

tonne

15.750

38740.00

610155.00

M-078

cum

126.000

1005.00

126630.00

M-051

Material
Modified binder
Crushed stone aggregates 11.2 mm size

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

76703.49
84373.84

Cost for 10500 sqm = a+b+c+d+e

928112.19

Rate per sqm = (a+b+c+d+e)/10500

88.39
say

Note
5.21

(iv)

Remarks/
Input ref.

88.00

In case 2nd coat is also required to be provided, material


provided for the 2nd coat shall be as per table 500-47.
Case - IV : Bitumen impregnated geotextile
Providing and laying a bitumen impregnated geotextile layer
after cleaning the road surface, geotextile conforming to
requirements of clause 703.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration
and constructed to the requirement of clause 703.4.5
Unit = sqm
Taking output = 3500 sqm
a) Labour

b)

Mate

day

0.560

151.44

84.81

L-12

Mazdoor

day

12.000

136.69

1640.28

L-13

Mazdoor skilled

day

2.000

164.69

329.38

L-15

Mechanical broom @ 1250 sqm per hour

hour

2.800

357.00

999.60

P&M-031

Air compressor 250 cfm capacity

hour

2.800

319.00

893.20

P&M-001

tonne

2.000

1073.00

2146.00

P&M-004

hour

2.000

1243.00

2486.00

P&M-037

tonne

3.680

56122.00

206528.96

M-075

sqm

3850.000

37.25

143412.50

M-108

Machinery

Bitumen pressure distributor @ 1750 sqm per hour


Pneumatic roller
c)

Material
Paving grade bitumen of 80 - 100 penetration @ 1.05
kg per sqm
Geotextile including 10 per cent for overlaps

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

35852.07
39437.28

Cost for 10500 sqm = a+b+c+d+e

433810.08

Rate per sqm = (a+b+c+d+e)/3500

123.95
say

124.00

NOTE As bitumen overlay construction shall follow closely the


fabric placement on the same day, an output of 3500 sqm
only has been considered for the analysis which will cover a
length of 500 m, of 7 m wide carriagway. This can be
conveniently overlaid by a bitumenious course in a day
5.22

519.3

Recipe Cold Mix


Providing and laying of premix of crushed stone aggregates
and emulsion binder, mixed in a batch type cold mixing
plant, laid over prepared surface, by paver finisher, rolled
with a pneumatic tyred roller initially and finished with a
smooth steel wheel roller, all as per clause 519.3
Unit = cum
Taking output = 205 cum (450 tonnes)
(i)

75 mm thickness
a) Labour

b)

Mate

day

1.000

151.44

151.44

L-12

Mazdoor

day

12.000

136.69

1640.28

L-13

Mazdoor skilled

day

5.000

164.69

823.45

L-15

Batch type cold mixing plant 100-120 TPH capacity


producing an average output of 75 tonne per hour
Electric generator 125 KVA

hour

6.000

25594.50

153567.00

P&M-064

hour

6.000

652.00

3912.00

P&M-018

Front end loader 1 cum capacity

hour

6.000

806.00

4836.00

P&M-017

Paver finisher hydrostatic with sensor control @ 75


cum per hour

hour

6.000

2674.00

16044.00

P&M-034

Machinery

Page 27 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Tipper 10 tonne capacity

tonne.km

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Pneumatic tyred roller12-15 tonnes.

c)

Quantity
450 x L

Rate Rs

Cost Rs

2.46

Lead =1
km & P&M058

110.60
hour

6.00x0.65*

1243.00

4847.70

P&M-037

Smooth wheeled steel roller6-8 tonnes.

hour

6.00x0.65*

460.00

1794.00

P&M-044

Water tanker6 KL capacity

hour

1.000

200.00

200.00

P&M-060

tonne

20.250

49915.00

1010778.75

M-077

cum

297.000

916.00

272052.00

M-055

KL

6.000

10.00

60.00

M-189

Material
Bitumen emulsion @ 45 litres per tonne
Crushed stone aggregates 40 mm nominal size
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

147192.32
161911.55

Cost for 10500 sqm = a+b+c+d+e

1781027.08

Rate per sqm = (a+b+c+d+e)/205

8687.94
say

Note

1105.99

Remarks/
Input ref.

8688.00

(Case I to III)
1. These mixes are considered suitable for minor repair work
and temporary road surface improvement.
2. In case concrete mixtures are required to be used for
mixing, a number of these will be needed to match the
capacity of road rollers.
3. Tack coat, where provided, will be measured and paid
separately.
*4.Both the rollers have to be available at site to match with
the output of batch mixing plant and paver finisher. A
multiplying factor of 0.65 has been adopted to cater for the
idling period of road rollers.

5.22

(ii)

40 mm thickness
a) Labour

b)

Mate

day

1.000

151.44

151.44

L-12

Mazdoor

day

12.000

136.69

1640.28

L-13

Mazdoor skilled

day

5.000

164.69

823.45

L-15

Batch type cold mixing plant100-120 TPH capacity


producing an average output of 75 tonne per hour
Electric generator 125 KVA

hour

6.000

25594.50

153567.00

P&M-064

hour

6.000

652.00

3912.00

P&M-018

Front end loader 1 cum capacity

hour

6.000

806.00

4836.00

P&M-017

Paver finisher hydrostatic with sensor control @ 75


cum per hour
Tipper 10 tonne capacity

hour

6.000

2674.00

16044.00

P&M-034

tonne.km

450 x L

2.46

1105.99

Lead =1
km & P&M058

Machinery

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Pneumatic tyred roller 12-15 tonnes.

c)

110.60
hour

6.00x0.65*

1243.00

4847.70

P&M-037

Smooth wheeled steel roller 6-8 tonnes.

hour

6.00x0.65*

460.00

1794.00

P&M-044

Water tanker6 KL capacity

hour

1.000

200.00

200.00

P&M-060

tonne

31.500

49915.00

1572322.50

M-077

cum

287.000

1028.00

295036.00

M-052

KL

6.000

10.00

60.00

M-189

Material
Bitumen emulsion @ 70 litres per tonne
Crushed stone aggregates 14 mm nominal size
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

205645.10
226209.61

Cost for 10500 sqm = a+b+c+d+e

2488305.66

Rate per sqm = (a+b+c+d+e)/205

12138.08
say

5.22

(iii)

12138.00

25 mm thickness
a) Labour

b)

Mate

day

1.000

151.44

151.44

L-12

Mazdoor

day

12.000

136.69

1640.28

L-13

Mazdoor skilled

day

5.000

164.69

823.45

L-15

Batch type cold mixing plant 100-120 TPH capacity


producing an average output of 75 tonne per hour
Electric generator 125 KVA

hour

6.000

25594.50

153567.00

P&M-064

hour

6.000

652.00

3912.00

P&M-018

Front end loader 1 cum capacity

hour

6.000

806.00

4836.00

P&M-017

Machinery

Page 28 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Paver finisher hydrostatic with sensor control @ 75


cum per hour
Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Pneumatic tyred roller

c)

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

hour

6.000

2674.00

16044.00

P&M-034

tonne.km

450 x L

2.46

1105.99

Lead =1
km & P&M058

110.60
hour

6.00x0.65*

1243.00

4847.70

P&M-037

Smooth wheeled steel roller

hour

6.00x0.65*

460.00

1794.00

P&M-044

Water tanker6 KL capacity

hour

1.000

200.00

200.00

P&M-060

tonne

38.250

49915.00

1909248.75

M-077

cum

270.000

969.00

261630.00

M-050

KL

6.000

10.00

60.00

M-189

Material
Bitumen emulsion @ 85 litres per tonne
Crushed stone aggregates 6 mm nominal size
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

235997.12
259596.83

Cost for 10500 sqm = a+b+c+d+e

2855565.16

Rate per sqm = (a+b+c+d+e)/205

13929.59
say

Page 29 of 264

13930.00

CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Sr No

Ref. to
MoRTH
Spec.

7.1

702

Description

Unit

Rate Rs

Cost Rs

Remarks/
Input ref.

Sub-Surface Drain with Geotextiles


Construction of sub surface drain 200 mm dia using
geotextiles treated with carbon black with physical properties
as given in clause 702.2.3 formed in to a stable network and
a planar geocomposite structure, joints wrapped with
geotextile to prevent ingress of soil, all as per clause 702
and approved drawings including excavation and backfilling
Unit = Running metre
Taking output = one metre
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Material
Geonets, geomembrane and geotextile to make planar
geocomposite stable network for sub surface drain including
wrapping of joints with 160 mm over lapping with geotextile .
Geonets
Geomembrane
Geotextile
Add 2 per cent cost of material for miscellaneous items like
synthetic cord
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per metre = a+b+c+d
Note

7.2

Quantity

702.4

day
day
day

0.040
0.250
0.500

151.44
164.69
136.69

6.06
41.17
68.35

L-12
L-15
L-13

sqm
sqm
sqm

1.000
1.000
2.000

607.00
607.00
37.25

607.00
607.00
74.50
25.77

M-107
M-106
M-108

say

142.98
157.28
1730.11
1730.00

Surplus excavated material to be used at site. Hence


seprate cost for disposal not added.
Narrow Filter Sub-Surface Drain
Construction of a narrow filter sub- surface drain consisting
of porous or perforated pipe laid in narrow trench
surrounded by a geotextile filter fabric, with a minimum of
450 mm overlap of fabric and installed as per clause 702.3
and 309.3.5 including excavation and backfilling
Unit = Running metre length
Taking output = one metre
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Material
Perforated geosynthetic pipe 150 mm dia
Geotextile filter fabric
Add 2 per cent cost of material for miscellaneous item like
synthetic cord
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per metre = a+b+c+d

day
day
day

0.040
0.250
0.500

151.44
164.69
136.69

6.06
41.17
68.35

L-12
L-15
L-13

metre
sqm

1.000
1.250

182.00
37.25

182.00
46.56
4.57

M-134
M-109

say
Note

Surplus excavated material to be used at site. Hence


Separate cost for disposal not added.

Page 1 of 264

34.87
38.36
421.94
422.00

Sr No

Ref. to
MoRTH
Spec.

7.3

703

Description

Unit

Quantity

Rate Rs

Cost Rs

Laying Paving Fabric Beneath a Pavement Overlay


Providing and laying paving fabric with physical
requirements as per table 704-2 over a tack coat of paving
grade Bitumen 80-100 penetration, laid at the rate of 1 kg
per sqm over thoroughly cleaned and repaired surface to
provide a water resistant membrane and crack retarding
layer. Paving fabric to be free of wrinkling and folding and to
be laid before cooling of tack coat, brooming and rolling of
surface with pneumatic roller to maximise paving fabric
contact with pavement surface
Unit = sqm
Taking output = 2800 sqm
a) Labour
Mate
Mazdoor
b) Machinery
Road sweeper 1250 sqm per hour
Pneumatic roller 14 tonnes 2000 sqm per hour
Bitumen pressure distributor 1750 sqm per hour
c) Material
Paving Fabric
Paving Bitumen 80-100
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 2800 sqm = a+b+c+d+e
Rate per sqm =(a+b+c+d+e)/2800

day
day

0.800
20.000

151.44
136.69

121.15
2733.80

L-12
L-13

hour
hour
hour

2.240
1.400
1.680

357.00
1243.00
1073.00

799.68
1740.20
1802.64

P&M-031
P&M-037
P&M-004

sqm
tonne

2940.000
2.800

225.00
56122.00

661500.00
157141.60
82583.91
90842.30
999265.28
356.88
356.88

say
7.4

704

Remarks/
Input ref.

M-133
M-075

Laying Boulder Apron in Crates of Synthetic Geogrids


Providing, preparing and laying of geogrid crated apron 1 m
x 5 m, 600 mm thick including excavation and backfilling with
baffles at 1 metre interval, made with geogrids having
characteristics as per clause 704.2, joining sides with
connectors/ring staples, top corners to be tie tensioned,
placing of suitable cross interval ties in layers of 300 mm
connecting opposite side with lateral braces and tied with
polymer braids to avoid bulging, constructed as per clause
704.3. filled with stone with minimum size of 200 mm and
specific gravity not less than 2.65, packed with stone spalls,
keyed to the foundation recess in case of sloping ground
and laid over a layer of geotextile to prevent migration of
fines, all as per clause 704 and laid as per clause 2503.3
and approved design.
Unit = cum
Taking output = 3.00 cum
a) Labour

b)

Mate

day

0.060

151.44

9.09

L-12

Mazdoor skilled

day

0.500

164.69

82.35

L-15

Mazdoor

day

1.500

136.69

205.04

L-13

Geo grids

sqm

21.000

607.00

12747.00

M-105

Connectors/ Staples

each

50.000

61.00

3050.00

M-085

metre

20.000

364.00

7280.00

M-140

Stones with minimum size of 200 mm

cum

3.450

494.68

1706.65

M-003

Stones spall for filling voids

cum

0.450

921.00

414.45

M-008

Material

Polymer braids

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2549.46
2804.40

Cost for 3 cum = a+b+c+d

30848.42

Rate per cum = (a+b+c+d)/ 3

2372.96
say

7.5

3100

Reinforced Earth Structures


Reinforced earth Structures have four main components as
under:
a)
Excavation for foundation, foundation concrete and
cement concrete grooved seating in the foundation for facing
elements (facia material).
Page 2 of 264

2373.00

Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Facia material and its placement.

c)
Assembling, joining with facing elements and laying of
the reinforcing elements.
d)
Earth fill with granular material which is to be retained
by the wall.
Each component is analysed separately as under:
considering Average height of wall = 8 m.
7.5

3102

(i)

Assembling, joining and laying of reinforcing elements.

With reinforcing element of steel / Aluminium strips /


polymeric strips.
Unit = Running Metre
Taking Output = 450 m
a)

b)

Labour
Mate

day

0.360

151.44

54.52

L-12

Mazdoor

day

6.000

136.69

820.14

L-13

Mazdoor skilled

day

3.000

164.69

494.07

L-15

metre

450*1.1

364.00

180180.00

M-154

metre

450*1.1

364.00

180180.00

M-153

metre

450*1.1

364.00

180180.00

M-157

metre

450*1.1

364.00

180180.00

M-156

metre

450*1.1

364.00

180180.00

M-155

Material

@ Reinforcement strips 60 mm wide 5 mm thick as per


clause 3102.
1.Galvanised carbon steel strips
or
2.Copper Strips
or
3.Aluminium Strips
or
4.Stainless steel strips
or
5.Glass reinforced polymer/fibre reinforced
polymer/polymeric strips
@ Any one of the above alternative may be adopted as per
approved design.
Add 10 per cent of the cost of reinforcing strip towards
accessories like tie-strips, nuts and bolts and loops/lugs for
joining reinforcing elements with the facia pannels, overlaps,
heat bonding or extension.
Type 1

1.Galvanised carbon steel strips


c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

18154.87
18154.87

Cost of 450 m = a+b+c+d

217858.47

Rate per metre =(a+b+c+d)/450

484.13
say

Type 2

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

18154.87
18154.87

Cost of 450 m = a+b+c+d

217858.47

Rate per metre =(a+b+c+d)/450

484.13
say

Type 3

484.00

3.Aluminium Strips
c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

18154.87
18154.87

Cost of 450 m = a+b+c+d

217858.47

Rate per metre =(a+b+c+d)/450

484.13
say

Type 4

484.00

2.Copper Strips

484.00

4.Stainless steel strips


c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

18154.87
18154.87

Cost of 450 m = a+b+c+d

217858.47

Rate per metre =(a+b+c+d)/450

484.13
say
Page 3 of 264

484.00

Sr No

Ref. to
MoRTH
Spec.

Description
Type 5

Unit

Quantity

Rate Rs

Cost Rs

5.Glass reinforced polymer/fibre reinforced


polymer/polymeric strips
c) Overhead charges @ 0.1 on (a+b)
d)

18154.87

Contractor's profit @ 0.1 on (a+b+c)

18154.87

Cost of 450 m = a+b+c+d

217858.47

Rate per metre =(a+b+c+d)/450

484.13
say

7.5(i)

Remarks/
Input ref.

484.00

With reinforcing elements of synthetic geogrids


Unit = sqm
Taking output = 300 sqm
a)

b)

Labour
Mate

day

0.360

151.44

54.52

L-12

Mazdoor

day

6.000

136.69

820.14

L-13

Mazdoor skilled

day

3.000

164.69

494.07

L-15

sqm

300.000

607.00

182100.00

Material
Synthetic Geogrids as per clause 3102.8 and approved
design and specifications.
Add 10 per cent of the cost of reinforcing elements
(synthetic geogrids) for accessories like tie-strips, nuts
and bolts and loops/lugs for joining reinforcing
elements with the facia pannels, overlaps and other
protective elements for synthetic geogrids.

18210.00

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

20167.87
22184.66

Cost of 300 sqm of Synthetic geogrids = a+b+c+d

244031.26

Rate per sqm = (a+b+c+d)/ 300

813.44
say

7.5

3104

(ii)

M-181

813.00

Facing elements of RCC


Unit = sqm
Taking output = 75 sqm
a)

b)

Labour
Mate

day

0.180

151.44

27.26

L-12

Mazdoor

day

3.000

136.69

410.07

L-13

Mazdoor skilled

day

1.500

164.69

247.04

L-15

hour

6.000

357.00

2142.00

P&M-013

cu.m

13.500

3952.00

53352.00

Item 12.8
(H)

tonnes

0.380

65101.00

Machinery
Light crane with lifting capacity upto 3 tonne

c)

Material
Pre-cast RCC M-35 facing elements of size as per
design and 18 cm thick for 75 sqm. (Refer Item 12.8
(H))
HYSD steel @ 5 kg / sqm (Refer Item 12.6)

Add 2 per cent of cost of facia pannels, for all necessary


temporary form work, scaffolding and provision of loops/lugs
for lifting of pannels and joining the reinforcing elements.
d)

Overhead charges @ 0.1 on (a+b)

e)

Contractor's profit @ 0.1 on (a+b+d)

1561.81

282.64
310.90

Cost for 75 sqm = a+b+c+d+e

83072.09

Rate per sqm = (a+b+c+d+e)/ 75

1107.63
say

Note

24738.38 Item 13.6

1.The specification and construction details to be adopted


shall be as per section 3100 of MoRTH Specification.
2.Drainage arrangement shall be made as per approved
design and drawings.
3.The quantity of filler media shall be calculated as per
approved design and specifications and shall be priced
separately.The rate for same to be adopted from chapter 15.

Page 4 of 264

1108.00

Ref. to
MoRTH
Spec.

Sr No

Description

Unit

4.Excavation for foundation including foundation concrete


and groove in the foundation for seating of bottom most
facia panel and capping beam to be calculated as per
design and priced separately. The rates for excavation and
foundation concrete shall be taken from the chapter 12 & 13
in bridge section.
5.The earth fill to be retained is not included in this analysis.
The same is to be worked out and provided separately
complete as per clause 305.
,

6.For compaction of Earthwork, attention is invited to clause


3105.5 of MoRTH Specification.
7.Length of reinforcing strips will vary with the height of wall
and will be as per approved design and drawings.
8.The type of reinforcing elements to be adopted shall be as
per approved design and specifications.
9.The market rate for supply of reinforcing elements and
their accessories are to be ascertained from reputed firms in
the field of earth reinforcement.
10.The earth fill material shall be clean, free draining,
granular with high friction and low cohesion, non-corrosive,
coarse grained with not 10 per cent of particles passing 75
micron sieve, free of any deleterious matter, chlorides, salts,
acids, alkalies, mineral oil, fungus and microbes and shall be
of specified PH value.
11.Capping beam is to be priced separately as per approved
design. The rate for cement concrete shall be taken from the
chapter of sub-structure in bridge section.
12.The cost of reinforced earth retaining wall shall include
following:
(I) Excavation for foundation including backfilling.
(ii) Foundation concrete as per approved design.
(iii) Cost of facial pannels and their erection .
(iv) Cost of reinforcing elements including their fixing and
joining with the facial pannels.
(v) Drainage arrangement including filter media as per
approved design and drawings.
13. The compacted earth filling to be retained shall form part
of embankment.

Page 5 of 264

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Sr No
8.1

Ref. to
MoRTH
Spec.
408

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Cast in Situ Cement Concrete M20 Kerb


Construction of cement concrete kerb with top and bottom
width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M-10 grade foundation 150 mm thick,
foundation having 50 mm projection beyond kerb stone, kerb
stone laid with kerb laying machine, foundation concrete laid
manually, all complete as per clause 408

A.

Unit = Running metre


Taking output = 360 metre
Using Concrete Mixer
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base= 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate
Mason
Mazdoor
b) Machinery
Kerb casting machine @ 60 metres/hour
Concrete mixer 0.48/0.28 cum capacity
Water tanker6 KL capacity
c) Material
Crushed stone aggregate 20 mm nominal size 59 per
cent
Coarse sand 30 per cent
Cement 11 per cent
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 360 meter = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/360
Using Concrete Batching and Mixing Plant
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base = 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate
Mason
Mazdoor
b) Machinery
Kerb casting machine @ 60 metres/hour
Concrete batching and mixing plant @ 15 cum/hr.
Water tanker6 KL capacity
Tipper 5.5 cum capacity
c) Material
Crushed stone aggregate 20 mm nominal size 59 per
cent
Coarse sand 30 per cent
Cement 11 per cent
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 360 meter = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/360

day
day
day

0.720
2.000
16.000

151.44
223.36
136.69

109.04
446.72
2187.04

L-12
L-11
L-13

hour
hour
hour

6.000
12.000
5.000

310.00
233.00
200.00

1860.00
2796.00
1000.00

P&M-029
P&M-009
P&M-060

cum

21.790

1028.00

22400.12

M-053

cum
tonne
KL

10.900
5.700
30.000

710.46
5000.00
10.00

M-005
M-081
M-189

say

7744.01
28500.00
300.00
6734.29
7407.72
81484.95
226.35
226.00

day
day
day

0.120
1.000
2.000

151.44
223.36
136.69

18.17
223.36
273.38

L-12
L-11
L-13

hour
hour
hour
hour

6.000
1.600
5.000
6.000

310.00
1860.00
200.00
339.00

1860.00
2976.00
1000.00
2034.00

P&M-029
P&M-003
P&M-060
P&M-048

cum

21.790

1028.00

22400.12

M-053

cum
tonne
KL

10.900
5.700
30.000

828.00
5000.00
10.00

9025.20
28500.00
300.00
6861.02
7547.13
83018.38
230.61
231.00

M-004
M-081
M-189

say
8.2

408

Cast in Situ Cement Concrete M 20 Kerb with Channel


Construction of cement concrete kerb with channel with top
and bottom width 115 and 165 mm respectively, 250 mm
high in M 20 grade PCC on M10 grade foundation 150 mm
thick, kerb channel 300 mm wide, 50 mm thick in PCCM20
grade, sloped towards the kerb, kerb stone with channel laid
with kerb laying machine, foundation concrete laid manually,
all complete as per clause 408
A

Using Concrete Mixer


Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Page 1 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Cement concrete of grade M20= 17.48 cum


Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a)

b)

c)

Labour
Mate

day

0.720

151.44

109.04

Mason

day

2.000

223.36

446.72

L-11

Mazdoor

day

16.000

136.69

2187.04

L-13

Machinery
Kerb casting machine @ 50 metres/hour for laying kerb
and channel
Concrete mixer 0.48/0.28

hour

6.000

310.00

1860.00

P&M-029

hour

16.000

233.00

3728.00

P&M-009

Water tanker6 KL capacity

hour

6.000

200.00

1200.00

P&M-060

Material
Crushed stone aggregate 20 mm nominal size 60 per
cent
Coarse sand 30 per cent

cum

36.590

1028.00

37614.52

M-053

cum

18.300

710.46

13001.42

M-005

Cement 10 per cent

tonne

9.010

5000.00

45050.00

M-081

KL

36.000

10.00

360.00

M-189

Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

L-12

10555.67
11611.24

Cost for 360 meter = a+b+c+d+e

127723.65

Rate per metre = (a+b+c+d+e)/300

425.75

Add 1 % labour Cess

4.26
430.00
say

8.2

430.00

Using Concrete Batching and Mixing Plant


Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a)

b)

c)

Labour
Mate

day

0.120

151.44

18.17

Mason

day

1.000

223.36

223.36

L-11

Mazdoor

day

2.000

136.69

273.38

L-13

Machinery
Kerb casting machine @ 50 metres/hour for laying kerb
and channel
Concrete batching and mixing plant @ 15 cum/hr.

hour

6.000

310.00

1860.00

P&M-029

hour

2.700

1860.00

5022.00

P&M-003

Water tanker6 KL capacity

hour

6.000

200.00

1200.00

P&M-060

Tipper of 5.5 cum capacity

hour

6.000

339.00

2034.00

P&M-048

Material
Crushed stone aggregate 20 mm nominal size 60 per
cent
Coarse sand 30 per cent

cum

36.590

1028.00

37614.52

M-053

cum

18.300

828.00

15152.40

M-004

Cement 10 per cent

tonne

9.010

5000.00

45050.00

M-081

KL

36.000

10.00

360.00

M-189

Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

10880.78
11968.86

Cost for 300 meter = a+b+c+d+e

131657.48

Rate per metre = (a+b+c+d+e)/300

438.86
say

8.3

801

Printing New Letter and Figures of any Shade


Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade
(i)

Hindi ( Matras commas and the like not to be measured


and paid for Half letter shall be counted as half )
Details for 100 letters of 16 cm height i.e. 1600 cm
Unit = per cm height per letter
a)

Labour
Page 2 of 264

439.00

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

Cost Rs

Mate

day

0.120

151.44

18.17

L-12

Painter

day

2.000

223.36

446.72

L-18

Mazdoor

day

1.000

136.69

136.69

L-13

Litre

0.700

192.81

134.97

M-131

Material
Paint

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

73.65
81.02

Cost for 1600 cm = a+b+c+d

891.23

Rate per cm height per letter = (a+b+c+ d)/1600

0.56
say

8.3

(ii)

Remarks/
Input ref.

0.60

English and Roman


Hyphens and the like not to be measured and paid for
Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
a)

b)

Labour
Mate

day

0.070

151.44

10.60

L-12

Painter Ist class

day

1.250

223.36

279.20

L-18

Mazdoor

day

0.500

136.69

68.35

L-13

Litre

0.500

192.81

96.41

M-131

Material
Paint

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

45.46
50.00

Cost for 1600 cm = a+b+c+d

550.01

Rate per cm height per letter = (a+b+c +d)/1600


8.4

801

0.34
say

0.30

Retro-Reflectorised Traffic Signs


Providing and fixing of retro- reflectorised cautionary,
mandatory and informatory sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 1.5 mm thick supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the
ground by means of properly designed foundation with M15
grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm
below ground level as per approved drawing
Unit = Each
Taking output = one traffic sign

a)

b)

i)

Excavation for foundation

cum

0.216

138.00

29.81

ii)

Cement concrete M15 grade

cum

0.120

4228.00

507.36

iii)

Painting angle iron post two coats

sqm

0.430

46.00

19.78

Item No.
3.13
Item 12.8
(A)
Item 8.9

Mate

day

0.010

151.44

1.51

L-12

Mazdoor

day

0.250

136.69

34.17

L-13

kg

19.000

45.00

855.00

M-179 /
1000

sqm

0.350

6064.00

2122.40

M-061

sqm

0.156

6064.00

945.98

M-061

sqm

0.283

6064.00

1716.11

M-061

sqm

0.480

6064.00

2910.72

M-061

sqm

0.270

6064.00

1637.28

M-061

sqm

0.360

6064.00

2183.04

M-061

Labour (For fixing at site)

Material
Mild steel angle iron 75 x 75 x 6 mm

(i)

Aluminium sheeting fixed with encapsulated lens type


reflective sheeting of size including lettering and signs as
applicable
Add 2 per cent of cost of angle iron towards cost of drilling
holes, nuts, bolts etc.
90 cm equilateral triangle
or

( ii )

60 cm equilateral triangle
or

( iii )

60 cm circular
or

( iv )

80 mm x 60 mm rectangular
or

(v)

60 cm x 45 cm rectangular
or

(vi )

60 cm x 60 cm square
Page 3 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

or
( vii )

90 cm high octagon
c)

Tractor-trolley
(i)

sqm

0.672

6064.00

4075.01

hour

0.010

282.50

2.83

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

301.59
331.75
4206.20
say

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

183.95
202.34
2782.74
say

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

260.96
287.06
3714.59
say

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

380.42
418.47
5160.07
say

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

253.08
278.39
3619.21
say

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

307.66
338.42
4279.58
say

4280.00

90 cm high octagon
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

496.85
546.54

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

Note

3619.00

60 cm x 60 cm square

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


( vii )

5160.00

60 cm x 45 cm rectangular

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


(vi )

3715.00

80 mm x 60 mm rectangular

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


(v)

2783.00

60 cm circular

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


( iv )

4206.00

60 cm equilateral triangle

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


( iii )

P&M-053

90 cm equilateral triangle

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


( ii )

M-061

Machinery

6568.86
say

6569.00

138.00

29.81

1.Any one area of aluminium sheeting given at (i) to (vii) may


be adopted as per site requirement and in accordance with
IRC : 67
2.Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
3. The depth of foundation and quantity of cement concrete
in the foundation are indicative. These may be increased for
areas having higher wind velocities like in coastal areas.
This is applicable to all road signs and directions boards.

8.5

801

Direction and Place Identification Signs upto 0.9 sqm


Size Board.
Providing and erecting direction and place identification
retro-reflectorised sign as per IRC:67 made of high intensity
grade sheeting vide clause 801.3, fixed over aluminium
sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on a mild steel single angle iron post 75 x 75 x 6
mm firmly fixed to the ground by means of properly designed
foundation with M15 grade cement concrete 45 x 45 x 60
cm, 60 cm below ground level as per approved drawing
Unit = sqm
Taking output = 0.9 sqm
i) Excavation for foundation

cum
Page 4 of 264

0.216

Item No.
3.13

Sr No

Ref. to
MoRTH
Spec.

Description

a)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

ii) Cement concrete M15 grade

cum

0.120

4228.00

507.36

iii) Painting angle iron post two coats

sqm

0.430

46.00

19.78

Item 12.8
(A)
Item 8.9

Mate

day

0.010

151.44

1.51

L-12

Mazdoor

day

0.200

136.69

27.34

L-13

kg

19.000

45.00

855.00

sqm

0.900

6064.00

5457.60

M-179 /
1000
M-061

hour

0.020

282.50

5.65

P&M-053

Labour (For fixing at site)

b)

Material
Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85
metres long
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

634.71
698.18

Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e


Rate per sqm (for sign having area upto 0.9 sqm) =
(I+ii+iii+a+b+c+d+e)/0.90

Note

8.6

801

8236.94
9152.16
say

9152.00

I) Lettering and arrow marks on sign board to be provided


separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
Direction and Place Identification Signs with size more
than 0.9 sqm size Board.
Providing and erecting direction and place identification
retro- reflectorised sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick with area exceeding 0.9
sqm supported on a mild steel angle iron post 75 mm x 75
mm x 6 mm, 2 Nos. firmly fixed to the ground by means of
properly designed foundation with M 15 grade cement
concrete45 cm x 45 cm x 60 cm, 60 cm below ground level
as per approved drawing
Unit = sqm
Taking output = 1.50 sqm

a)

i)

Excavation for foundation

cum

0.430

138.00

59.34

ii)

Cement concrete M15 grade

cum

0.240

4228.00

1014.72

iii)

Painting angle iron post 2 coats

sqm

0.860

46.00

39.56

Item No.
3.13
Item 12.8
(A)
Item 8.9

Mate

day

0.010

151.44

1.51

L-12

Mazdoor

day

0.300

136.69

41.01

L-13

kg

38.000

45.00

1710.00

sqm

1.500

6064.00

9096.00

Labour (For fixing at site)

b)

Material
Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85
metres long, 2 nos
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.

Page 5 of 264

M-179 /
1000
M-061

Sr No

Ref. to
MoRTH
Spec.

Description
c)

Unit

Quantity

Rate Rs

Cost Rs

Machinery
Tractor-trolley

hour

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

0.020

282.50

802

P&M-053

1193.53
14242.49
15824.99
say

8.7

5.65
1081.17

Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e


Rate per sqm ( for sign having area more than 0.9 sqm)
= ( i+ii+iii+a+b+c+d+e)/1.50

Note

Remarks/
Input ref.

15825.00

i) Lettering and arrow marks on sign board to be provided


separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
Overhead Signs
Providing and erecting overhead signs with a corrosion
resistant 2mm thick aluminium alloy sheet reflectorised with
high intensity retro-reflective sheeting of encapsulated lense
type with vertical and lateral clearance given in clause 802.2
and 802.3 and installed as per clause 802.7 over a designed
support system of aluminium alloy or galvanised steel
trestles and trusses of sections and type as per structural
design requirements and approved plans

Truss and Vertical Support


Unit = tonne
Taking output = 1 tonne
a)

Labour
Mate

day

0.240

151.44

36.35

L-12

Blacksmith

day

2.000

264.50

529.00

L-02

Mazdoor including for handling & fixing at site.

day

4.000

136.69

546.76

L-13

tonne

1.050

54574.00

57302.70

b)

Material
Aluminium alloy/galvanised steel including 5 per cent
wastage
Add 1 per cent on cost of material for nuts, bolts and drilling
and welding consumables
Add 15 per cent on cost of material for fabrication of trusses
as per approved design
c) Machinery

573.03
8681.36

Crane 3 tonne capacity

hour

3.000

357.00

1071.00

P&M-013

Truck

hour

0.500

315.27

157.64

P&M-057

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

6889.78
7578.76

Rate per tonne = (a+b+c+d+e)

83366.37
say

8.7

M-060

83366.00

Aluminium Alloy Plate for Over Head Sign


Unit = sqm
Taking output = 1 sqm
a)

Labour
Mate

day

0.020

151.44

3.03

L-12

Blacksmith

day

0.100

264.50

26.45

L-02

Mazdoor

day

0.150

136.69

20.50

L-13

sqm

1.000

425.00

425.00

M-059

b)

Material
Aluminium alloy plate,2 mm thick, fixed with high
intensity grade sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement, like
ladders, pulleys, ropes etc
c) Overhead charges @ 0.1 on (a+b)
d)

0.50
47.55

Contractor's profit @ 0.1 on (a+b+c)

52.30

Rate per sqm = (a+b+c+d)

575.33
say

Note

1. The cost of excavation and foundation concrete for fixing


of vertical support system to be worked out separately as
per the approved drawing/design and to be included in the
estimate.

Page 6 of 264

575.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

2. Lettering and arrow marks on sign board to be provided


separately as per actual requirement. Rates for these items
have been included separately in this chapter.

Page 7 of 264

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

8.8

803

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Painting Two Coats on New Concrete Surfaces


Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a)

b)

Labour
Mate

day

0.120

151.44

18.17

L-12

Painter

day

2.000

223.36

446.72

L-18

Mazdoor

day

1.000

136.69

136.69

L-13

Litre

6.000

117.16

702.96

M-132

Material
Paint conforming to requirement of clause 803.3.
Add for scaffolding @ 1 per cent of labour cost where
required
Add @ 5 per cent cost of labour and materials to
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

7.03
65.23

137.68
151.45

Cost for 40 sqm = a+b+c+d

1665.93

Rate per sqm = (a+b+c+d)/40

41.65

say
8.9

803

42.00

Painting on Steel Surfaces


Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.030

151.44

4.54

L-12

Painter

day

0.450

223.36

100.51

L-18

Mazdoor

day

0.250

136.69

34.17

L-13

Litre

1.250

192.81

241.01

M-131

Material
Paint ready mixed approved brand.
Add @ 1 per cent on cost of material for scaffolding

2.41

Add @ 5 per cent cost of labour and materials to


prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.

19.01

c)

Overhead charges @ 0.1 on (a+b)

40.17

d)

Contractor's profit @ 0.1 on (a+b+c)

44.18

Cost for 10 sqm = a+b+c+d

486.01

Rate per sqm= (a+b+c+d)/10

48.60
say

8.10

803

49.00

Painting on Wood Surfaces


Providing and applying two coats of ready mix paint of
approved brand on wood surface after thorough cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.030

151.44

4.54

L-12

Painter

day

0.500

223.36

111.68

L-18

Mazdoor

day

0.200

136.69

27.34

L-13

Litre

1.500

192.81

289.22

M-131

Material
Paint ready mixed of approved brand.
Add @ 1 per cent on cost of material for scaffolding
Add @ 5 per cent cost of labour and materials to
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.
Page 8 of 264

2.89
21.64

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Quantity

Rate Rs

Cost Rs
45.73
50.30

Cost for 10 sqm = a+b+c+d

553.34

Rate per sqm = (a+b+c+d)/10

55.33
say

8.11

Remarks/
Input ref.

55.00

Painting Lines, Dashes, Arrows etc on Roads in Two


Coats on New Work

803

Painting lines, dashes, arrows etc on roads in two coats on


new work with ready mixed road marking paint conforming to
IS:164 on bituminous surface, including cleaning the surface
of all dirt, dust and other foreign matter, demarcation at site
and traffic control
(i)

Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.090

151.44

13.63

L-12

Painter

day

0.550

223.36

122.85

L-18

Mazdoor

day

1.550

136.69

211.87

L-13

Litre

1.480

117.16

173.40

M-132

Material
Road marking Paint as per IS :164

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

52.17
57.39

Cost for 10 sqm = a+b+c+d

631.31

Rate per sqm= (a+b+c+d)/10


8.11

(ii)

63.13
say

63.00

Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.070

151.44

10.60

L-12

Painter

day

0.350

223.36

78.18

L-18

Mazdoor

day

1.350

136.69

184.53

L-13

Litre

1.480

117.16

173.40

M-132

Material
Road marking paint

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

44.67
49.14

Cost for 10 sqm = a+b+c+d

540.51

Rate per sqm = (a+b+c+d)/10

54.05
say

8.12

54.00

Painting Lines, Dashes, Arrows etc on Roads in Two


Coats on Old Work

803

Painting lines, dashes, arrows etc on roads in two coats on


old work with ready mixed road marking paint conforming to
IS: 164 on bituminous surface, including cleaning the
surface of all dirt, dust and other foreign matter, demarcation
at site and traffic control
(i)

Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.060

151.44

9.09

L-12

Painter Ist class

day

0.300

223.36

67.01

L-18

Mazdoor

day

1.250

136.69

170.86

L-13

Litre

0.900

117.16

105.44

M-132

Material
Road marking paint

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

35.24
38.76

Cost for 10 sqm = a+b+c+d

426.41

Rate per sqm = (a+b+c+d)/10

42.64
say

8.12

(ii)

Up to 10 cm in width
Page 9 of 264

43.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.070

151.44

10.60

L-12

Painter Ist class

day

0.350

223.36

78.18

L-18

Mazdoor

day

1.350

136.69

184.53

L-13

Litre

0.900

117.16

105.44

M-132

Material
Road marking Paint

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

37.88
41.66

Cost for 10 sqm= a+b+c+d

458.29

Rate per sqm = (a+b+c+d)/10

45.83
say

8.13

46.00

Road Marking with Hot Applied Thermoplastic


Compound with Reflectorising Glass Beads on
Bituminous Surface

803

Providing and laying of hot applied thermoplastic compound


2.5 mm thick including reflectorising glass beads @ 250 gms
per sqm area, thickness of 2.5 mm is exclusive of surface
applied glass beads as per IRC:35 .The finished surface to
be level, uniform and free from streaks and holes.
Unit = sqm
Taking output = 640 sqm
a)

b)

c)

Labour
Mate

day

0.050

151.44

7.57

L-12

Mazdoor

day

2.000

136.69

273.38

L-13

Road marking machine @ 80 sqm per hour

hour

8.000

93.00

744.00

P&M-043

Tractor-trolley

hour

8.000

282.50

2260.00

P&M-053

Litre

2000.000

150.00

300000.00

M-118

kg

200.000

75.00

15000.00

M-152

Machinery

Material
Hot applied thermoplastic compound
Reflectorising glass beads

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

31828.50
35011.34

Cost for 640 sqm = a+b+c+d+e

385124.79

Rate per sqm = a+b+c+d+e)/640

601.76

Add 1 % labour Cess

6.02
607.78

Note

8.14

say

607.78

9935.80

1. A sealing primer may be applied in advance on cement


concrete pavement to ensure proper bonding. Any laitance
and/or curing compound to be removed where paint is
required to be applied on concrete surface.
2.Cost of painter is already included in hire charges of road
marking machine.
Kilometre Stone

804

Reinforced cement concrete M15grade kilometre stone of


standard design as per IRC:8-1980, fixing in position
including painting and printing etc
(i)

5th kilometre stone (precast)


Unit = Nos.
Taking output = 6 Nos.
a)

M-15 grade of concrete

b)

Steel reinforcement @ 5 kg per sqm

c)

Excavation in soil for foundation

d) Painting two coats on concrete surface


e) Lettering on km post (average 30 letters of 10
cm height each)
Transportation and fixing
f)

Item 12.8
(A)
1437.43 Item 13.6 /
1000
231.84 Item No.
3.13
394.00 Item 8.8

cum

2.350

4228.00

kg

22.080

65.10

cum

1.680

138.00

sqm
per cm per
letter

9.850

40.00

1800.000

0.30

540.00

Item 8.3

0.260

151.44

39.37

L-12

Labour
Mate

day
Page 10 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

g)

Unit

Cost Rs

Remarks/
Input ref.

day

0.600

223.36

134.02

L-11

Mazdoor including loading/unloading

day

6.000

136.69

820.14

L-13

hour

6.000

282.50

1695.00

P&M-053

Machinery

h)

Overhead charges @ 0.1 on (f+g)

i)

Contractor's profit @ 0.1 on (f+g+h)

Cost for 6 Nos. 5th km stone = a+b+c+ d+e +f+g+h +i


Rate for each 5th km stone = (a+b+c+ d+e +f+g+h +i )
6
(ii)

Rate Rs

Mason

Tractor-trolley

8.14

Quantity

268.85
295.74
15792.19
/

2632.03
say

2632.00

15939.56

Ordinary kilometer stone (precast)


Unit = Nos.
Taking output = 14 Nos.
a)

M-15 grade of concrete

b)

Steel reinforcement @ 5 kg per sqm

c)

Excavation in soil for foundation

d) Painting two coats on concrete surface


e) Lettering on km post ( average 12 letters of 10
cm height each)
Transportation and fixing
f)

g)

3.770

4228.00

kg

26.320

65.10

cum

2.770

138.00

sqm
per cm per
letter

11.410

40.00

1680.000

0.30

Item 8.3

L-12

day

0.320

151.44

48.46

Mason

day

1.000

223.36

223.36

L-11

Mazdoor

day

7.000

136.69

956.83

L-13

hour

6.000

282.50

1695.00

P&M-053

Machinery
Overhead charges @ 0.1 on (f+g)

292.37
321.60
22533.30

Rate for each ordinary km stone = (a+b+ c


+d+e+f+g+h+j) /14
(iii)

504.00

Mate

i) Contractor's profit @ 0.1 on (f+g+h)


Cost for 14 Nos. ordinary km stone = (a+b+ c +d+e+f+g+h+i)

8.14

Item 12.8
(A)
1713.46 Item 13.6 /
1000
382.26 Item No.
3.13
456.40 Item 8.8

Labour

Tractor-trolley
h)

cum

1609.52
say

1610.00

6680.24

Hectometer stone (precast)


Unit = Nos.
Taking output = 33 Nos.
a)

M-15 grade of concrete

b)

Steel reinforcement @ 5 kg per sqm

c)

Excavation in soil for foundation

cum

1.580

4228.00

kg

66.000

65.10

cum

1.390

138.00

6.270

40.00

330.000

0.30

d) Painting two coats on concrete surface


sqm
e) Lettering on km post (average 1 letter of 10 cm per cm per
height each)
letter
Transportation and fixing
f)

g)

Item 8.3

L-12

Mate

day

0.340

151.44

51.49

Mason

day

1.500

223.36

335.04

L-11

Mazdoor

day

7.000

136.69

956.83

L-13

hour

6.000

282.50

1695.00

P&M-053

Machinery
Overhead charges @ 0.1 on (f+g)

303.84

i) Contractor's profit @ 0.1 on (f+g+h)


Cost for 33 Nos. Hectometer stone = (a+b +c +d+e+f+
g+h+i)
Rate for each Hectometer stone = (a+b +c +d+e+f+
g+h+i) 33

334.22
15194.94
460.45
say

Note

99.00

Labour

Tractor-trolley
h)

Item 12.8
(A)
4296.67 Item 13.6 /
1000
191.82 Item No.
3.13
250.80 Item 8.8

The rate for excavation, cement concrete, steel


reinforcement, painting and lettering may be taken from
respective chapters.
Page 11 of 264

460.00

Sr No

Ref. to
MoRTH
Spec.

8.15

805

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Road Delineators
Supplying and installation of delineators (road way
indicators, hazard markers, object markers), 80-100 cm high
above ground level, painted black and white in 15 cm wide
strips, fitted with 80 x 100 mm rectangular or 75 mm dia
circular reflectorised panels at the top, buried or pressed into
the ground and conforming toIRC-79 and the drawings.
Unit = Each
Taking output= 30 Nos.
a)

Labour
Mate

day

0.040

151.44

6.06

L-12

Mazdoor for fixing

day

1.000

136.69

136.69

L-13

each

30.000

834.40

25032.00

b)

Material
Cost of approved type of delineators from ISI certified
firm as per the standard drawing given in IRC - 79
Add 10 per cent cost of material for installation
c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2503.20
2767.79
3044.57

Cost for 30 Nos. delineators = (a+b+ c+d)

33490.32

Rate per delineators = (a+b+c+d) /30

Note

8.16

806

M-091

1116.34
say

1116.00

5285.00

In case of soft ground, a proper foundation may be provided


as per approved design. In case foundation is required to be
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.
Boundary pillar
Reinforced cement concrete M15 grade boundary pillars of
standard design as per IRC:25-1967, fixed in position
including finishing and lettering but excluding painting
Unit = Each
Taking output = 57 Nos.
a)

M-15 grade of the boundary stone

b)

Steel reinforcement

c)

Excavation in soil

d)

Lettering, each 10 cm high

cum

1.250

4228.00

kg

79.800

65.10

cum

10.720

138.00

per letter
per cm high

2280.000

0.30

Item 12.8
(A)
5195.06 Item 13.6 /
1000
1479.36 Item No.
3.13
684.00 Item 8.3

Transportation and fixing


e)

f)

Labour
Mate

day

0.570

151.44

86.32

L-12

Mazdoor

day

14.250

136.69

1947.83

L-13

hour

6.000

282.50

1695.00

P&M-053

cum

11.970

921.00

11024.37

M-008

Machinery
Tractor-trolley

g)

Material
Stone spall

h)

Overhead charges @ 0.1 on (e+f+g)

1475.35

i) Contractor's profit @ 0.1 on (e+f+g+h)


Cost for 57 Nos. boundary pillar = (a+b +c+d +e+ f+g+h+i )

1622.89
30495.18

Rate for each boundary pillar = (a+b+c+d+e+ f+g+h+i)/57

535.00
say

Note

8.17

807

In case of soft ground, a proper foundation may be provided


as per approved design. In case foundation is required to be
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.
G.I Barbed Wire Fencing 1.2 Metre High

Page 12 of 264

535.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Providing and fixing 1.2 metres high GI barbed wire fencing


with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 9 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807
Unit = per running metre
Taking output = 30 metres
a)

Labour
Mate

day

0.090

151.44

13.63

L-12

Blacksmith

day

0.250

264.50

66.13

L-02

Mazdoor

day

2.000

136.69

273.38

L-13

kg

31.420

65.56

2059.90

M-063

kg

80.500

45.00

3622.50

M-179 /
1000

b)

Material
Barbed wire 335 metres length @ 9.38 kg per 100
metres
MS angle iron 40 mm x 40mm x 6 mm, 23 metres in
length @ 3.5 kg per metre
Add for GI staple binding wire, drilling holes etc. @ 2 per
cent of the cost of material
c) Painting
Applying two coats of painting on exposed surface of
angle iron posts ( Rate as per item no. 8.9)
d) Overhead charges @ 0.1 on (a+b)
e)

113.65

sqm

2.110

46.00

676.41
7537.57

Rate per metre = (a+b+c+d+e)/30

251.25
say

8.18

807

Item 8.9

614.92

Contractor's profit @ 0.1 on (a+b+d)

Cost for 30 metres fencing = a+b+c+d+e

Note

97.06

251.00

Cost of excavation for foundation and foundation concrete to


be added separately in the cost estimate as per approved
design. The rate for these items may be taken from
respective chapters.
G.I Barbed Wire Fencing 1.8 Metre High
Providing and fixing 1.8 metres high GI barbed wire fencing
with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 12 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807
Unit = per running metre
Taking output = 30 metres
a)

b)

Labour
Mate

day

0.120

151.44

18.17

L-12

Blacksmith

day

0.400

264.50

105.80

L-02

Mazdoor

day

2.500

136.69

341.73

L-13

kg

40.150

65.56

2632.23

M-063

kg

152.000

45.00

6840.00

M-179 /
1000

d)

Material
Barbed wire 428 metres length @ 9.38 kg per 100
metres
MS angle iron 50 mm x 50 mm x 6 mm,33.8 metres in
length @ 4.5 kg per metre
Add for GI staple, binding wire, drilling holes etc. @ 2
per cent of the cost of material
Painting
Applying two coats of painting on exposed surface of
angle iron posts
Overhead charges @ 0.1 on (a+b)

e)

Contractor's profit @ 0.1 on (a+b+d)

c)

189.44

sqm

3.960

46.00

1012.74
1114.01

Cost for 30 metres fencing = a+b+c+d+e

12436.29

Rate per metre fencing = (a+b+c +d+e)/30

414.54
say

Page 13 of 264

182.16

415.00

Item 8.9

Sr No

Ref. to
MoRTH
Spec.

Description

Note

8.19

Suggest
ive

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Cost of excavation for foundation and foundation concrete to


be added separately in the cost estimate as per approved
design. The rate for these items may be taken from
respective chapters.
Fencing With Welded Steel Wire Fabric 75 mm x 50 mm
Providing 1.20 metre high fencing with angle iron posts 50
mm x 50 mm x 6 mm at 3 metre center to center with 0.40
metre embedded in M15 grade cement concrete, corner, end
and every 10th post to be strutted, provided with welded
steel wire fabric of 75 mm x 50 mm mesh or 75 mm x 25 mm
mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts
etc. complete in all respects.
Unit = Running metre
Taking output = 30 m
a)

b)

Labour
Mate

day

0.120

151.44

18.17

L-12

Welder

day

1.000

264.50

264.50

L-02

Mazdoor

day

2.000

136.69

273.38

L-13

i) Angle iron for posts 50 x 50 x 6 mm

kg

106.000

45.00

4770.00

ii) Runner flat 50 x 5 mm

kg

26.000

45.00

1170.00

kg

151.000

61.00

9211.00

M-179 /
1000
M-179 /
1000
M-191

kg

293.000

28.25

P&M-053

368.00

Item 8.9

Material

iii) Welded steel wire fabric 75x50 mm mesh @ 4


kg/sqm,4 x 30 x 1.2 + 5 per cent wastage
OR
Welded steel wire fabric 75 x 25 mm mesh @ 7.75
kg/sqm, 7.75 x 30 x 1.2 + 5 per cent wastage
Add 2.5 per cent of cost of material for drilling holes in
angles, flats, splitting angle at bottom, nuts and bolts and
welded consumables
c)

Machinery
Tractor-trolley

d)

hour

0.100

282.50

sqm

8.000

46.00

Painting
Painting two coats including priming

e)

Overhead charges @ 0.1 on (a+b+c)

f)

Contractor's profit @ 0.1 on (a+b+c+e)

1573.53
1730.88

Cost for 30 metre = a+b+c+d+e+f

19407.72

Rate per metre = (a+b+c+d+e+f)/30

Note

8.20

808

646.92
say

647.00

i) Adopt any one type of welded steel wire fabric 75 x 50 mm


or 75 x 25 mm as per approved design.
ii) The item of excavation and cement concrete in foundation
shall be measured and paid separately
Tubular Steel Railing on Medium Weight Steel Channel
( ISMC series) 100 mm x 50 mm
Providing, fixing and erecting 50 mm dia steel pipe railing in
3 rows duly painted on medium weight steel channels (ISMC
series) 100 mm x 50 mm, 1.2 metres high above ground, 2
m centre to centre, complete as per approved drawings
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x
0.6
ii) Foundation concrete M-15 grade PCC 6 x 0.6 x
0.6 x 0.3
iii) Painting of pipe
iv) Painting of channel section 6 nos,1.8 metres
each 0.2 x 1.8 x 6 = 2.16
a) Labour (For fixing at site)

b)

cum

1.296

138.00

178.85

cum

0.648

4228.00

2739.74

sqm

4.710

46.00

216.66

Item No.
3.13
Item 12.8
(A)
Item 8.9

sqm

2.160

46.00

99.36

Item 8.9

Mate

day

0.010

151.44

1.51

L-12

Mazdoor

day

0.250

136.69

34.17

L-13

Plumber

day

0.010

264.50

2.65

L-02

metre

30.000

364.00

10920.00

Material
Steel pipe 50 mm external dia as per IS:1239
Page 14 of 264

M-175

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Medium weight steel channel (ISMC series) 100 mm x


50 mm,10.8 metres length @ 9.2 kg per metre
Add for drilling holes @ 2 per cent of cost of channels
c)

kg

Quantity
99.360

Rate Rs

Cost Rs

45.00

M-179 /
1000

89.42

Machinery
Tractor-trolley

hour

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

0.040

282.50

11.30

P&M-053

1875.36
2062.89

Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e

22703.12

Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10


8.21

4471.20

Remarks/
Input ref.

2270.31
say

2270.00

Tubular Steel Railing on Precast RCC Posts, 1.2 m High


Above Ground Level

808

Providing, fencing and erecting 50 mm dia painted steel pipe


railing in 3 rows on precast M20 grade RCC vertical posts1.8
metres high (1.2 m above GL) with 3 holes 50 mm dia for
pipe, fixed 2 metres centre to, complete as per approved
drawing
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x
0.6
ii) Foundation concrete M - 15 grade PCC 6 x 0.6 x
0.6 x 0.3
iii) RCC M - 20 for pre cast posts 6 nos of 1.8
metres each
iv) Painting of pipe
a)

b)

cum

1.296

138.00

178.85

cum

0.648

4228.00

2739.74

cum

0.320

5317.00

1701.44

sqm

4.710

46.00

216.66

Mate

day

0.014

151.44

2.12

L-12

Mazdoor

day

0.350

136.69

47.84

L-13

Plumber

day

0.010

264.50

2.65

L-02

metre

30.000

364.00

10920.00

hour

0.250

282.50

Labour

Material
Steel pipe 50 mm dia as per IS:1239

c)
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

70.63

P&M-053

1104.32
1214.76

Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e

18199.00

Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10


809

M-175

Machinery
Tractor-trolley

8.22

Item No.
3.13
Item 12.8
(A)
Item
14.1(A)
Item 8.9

1819.90
say

1820.00

15951.00

Reinforced Cement Concrete Crash Barrier


Provision of an Reinforced cement concrete crash barrier at
the edges of the road, approaches to bridge structures and
medians, constructed with M-20 grade concrete with HYSD
reinforcement conforming to IRC:21 and dowel bars 25 mm
dia, 450 mm long at expansion joints filled with pre-moulded
asphalt filler board, keyed to the structure on which it is built
and installed as per design given in the enclosure to MOST
circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994
as per dimensions in the approved drawing and at locations
directed by the Engineer, all as specified
Unit = Linear metre
Taking output = 10 m
(i)

a)

M 20 grade concrete
cum

3.000

5317.00

Mate

day

0.040

151.44

6.06

L-12

Mazdoor

day

1.000

136.69

136.69

L-13

HYSD steel reinforcement including dowel bars

tonne

0.280

45000.00

12600.00

M-082

Pre-moulded asphalt filler board

sqm

0.320

425.00

136.00

M-144

M 20 grade concrete
b)

c)

Item
14.1(A)

Labour

Material

d)

Overhead charges @ 0.1 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

Cost for 10 metre = a+b+c+d+e

1287.87
1416.66
34687.71

Page 15 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Rate per metre = (a+b+c+d+e)/10

3468.77
say

Note

8.23

810
A

Remarks/
Input ref.

3469.00

i) Excavation and backfilling are incidental to work and not to


be measured separately.
ii) Rate for RCC M 20 may be taken from chapter on super
structure.
Metal Beam Crash Barrier
Type - A, "W" : Metal Beam Crash Barrier
Providing and erecting a "W" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail,
70 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 1.8 m high, 1.1 m below ground/road level, all steel
parts and fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a spacer of channel section
150 x 75 x 5 mm, 330 mm long complete as per clause 810
Unit = Running metre
Taking output = 4.5 metre length
a)

b)

Labour
Mate

day

0.060

151.44

9.09

L-12

Blacksmith

day

0.500

264.50

132.25

L-02

Mazdoor

day

1.000

136.69

136.69

L-13

hour

0.100

282.50

28.25

P&M-053

kg

41.210

45.00

1854.45

kg

88.560

45.00

3985.20

kg

16.240

45.00

730.80

kg

20.000

64.07

1281.40

M-179 /
1000
M-179 /
1000
M-179 /
1000
M-130

Machinery
Tractor-trolley

c)

Material
Corrugated sheet,3 mm thick, "W" beam section
railing,4.5 m in length
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @
16.4 kg per metre
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @
16.4 kg per metre
Nuts and bolts
Add 25 per cent of the cost of material for fabrication, nuts,
bolts and washers etc.)
d) Overhead charges @ 0.1 on (a+b+c)
e)

1962.96
1012.11

Contractor's profit @ 0.1 on (a+b+c+d)

1113.32

Cost for 4.5 metre = a+b+c+d+e

12246.52

Rate per metre = (a+b+c+d+e)/4.5

2721.45
say

8.23

2721.00

Type - B, "THRIE" : Metal Beam Crash Barrier


Providing and erecting a "Thrie" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail,
85 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 2 m high with 1.15 m below ground level, all steel
parts and fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a space of channel section
150 x 75 x 5 mm, 546 mm long complete as per clause 810
Unit = Running metre
Taking output = 4.5 metre length
a)

b)

Labour
Mate

day

0.060

151.44

9.09

L-12

Blacksmith

day

0.500

264.50

132.25

L-02

Mazdoor

day

1.000

136.69

136.69

L-13

hour

0.100

282.50

28.25

P&M-053

kg

72.940

49.00

3574.06

M-088

kg

98.400

45.00

4428.00

kg

26.860

45.00

1208.70

M-179 /
1000
M-179 /
1000

Machinery
Tractor-trolley

c)

Material
Corrugated sheet,3 mm thick, "Thrie" beam section
railing,4.5 m in length
Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @ 16.4
kg per metre
Spacer 150 x 75 x 5 mm channel 0.546 m long,3 Nos
Page 16 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Nuts and bolts


Add 15 per cent of the cost of material for fabrication, nuts,
bolts and washers etc.)
d) Overhead charges @ 0.1 on (a+b+c)

kg

e)

Quantity
30.000

Rate Rs

Cost Rs

64.07

1310.91

Contractor's profit @ 0.1 on (a+b+c+d)

1442.00
15861.97

Rate per metre= (a+b+c+d+e)/4.5

3524.88
say

8.24

811

3525.00

In the case of median crash barrier, 'W' metal beam or thrie


beam section should be provided on both sides of the
vertical posts fixed in the median. Extra provision for metal
beam railing and spacer is required to be made when fixed
in the median depending on approved design.
Road Traffic Signals electrically operated

Note

8.25

M-130

1669.93

Cost for 4.5 metre = a+b+c+d+e

Note

1922.10

Remarks/
Input ref.

Suggest
ive

Since it is a ready made item commercially produced and


erected by specialised firm in the electrical and electronic
field, rate may be taken based on market enquiry from firms
specialised in this field and ISI certified for the approved
design and drawing.
Flexible Crash Barrier, Wire Rope Safety Barrier
Providing and erecting a wire rope safety barrier with vertical
posts of medium weight RS Joist (ISMB series) 100 mm x 75
mm (11.50 kg/m), 1.50 m long 0.85 m above ground and
0.65 m below ground level, split at the bottom for better grip,
embedded in M 15 grade cement concrete 450 x 450 x 450
mm, 1.50 m center to center and with 4 horizontal steel wire
rope 40 mm dia and anchored at terminal posts 15 m apart.
Terminal post to be embedded in M 15 grade cement
concrete foundation 2400 x 450 x 900 mm (depth),
strengthened by a strut of RS joist 100 x 75 mm, 2 m long
at 450 inclination and a tie 100 x 8 mm, 1.50 m long at the
bottom, all embedded in foundation concrete as per
approved design and drawing, rate excluding excavation and
cement concrete.
Unit = Running metre
Taking output = 15 metre
a) Labour

b)

Mate

day

0.120

151.44

18.17

L-12

Mazdoor

day

2.000

136.69

273.38

L-13

Blacksmith

day

1.000

264.50

264.50

L-02

kg

190.000

45.00

8550.00

kg

46.000

45.00

2070.00

kg

188.400

45.00

8478.00

kg

65.000

61.00

3965.00

M-179 /
1000
M-179 /
1000
M-179 /
1000
M-177

Material
i) RS Joist 100 x 75 mm - 16.5 m @ 11.5 kg per metre

ii) Struts - 2 Nos. for terminal posts,2 m long each 2 x 2


x 11.50
iii) Tie 2 Nos. of 8 mm steel plate,1.5 sqm each for
terminal posts @ 62.80 kg/sqm (2 x 1.5)
iv) Steel wire rope 40 mm, including 7.50 per cent
extra for fixing at ends 15 x 4 x 1.075 @ 1 kg per m
Add 5 per cent of cost of material for drilling, gripping, fixing,
fabrication and welding consumables
c) Painting
Applying 2 coats of painting on exposed surface
d)

1153.15
sqm

16.500

46.00

hour

0.250

282.50

Tractor-trolley
e)

Overhead charges @ 0.1 on (a+b+d)

f)

Contractor's profit @ 0.1 on (a+b+d+e)

2054.59

The items of excavations and cement concrete works will be


measured and included separately as per the approved
designs and drawings.
Anti-Glare Devices in Median

P&M-053

2732.71

say

Suggest
ive

70.63

30818.82

Rate per m = (a+b+c+d+e+f)/15

8.26

Item 8.9

2484.28

Cost for 15 m = a+b+c+d+e+f

Note

759.00

Machinery

Plantation

Page 17 of 264

2055.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Plantation of shrubs and plants of approved species in the


median. apart from cutting off glare from vehicle coming from
opposite direction, these plants provide a pleasant
envoirenment and are eco-friendly. The rate for this item is
available in the chapter 11 on horticulture.
B

Anti-glare screen with 25 mm steel pipe framework fixed


with circular and rectangular vans
Providing and erecting an anti - glare screen with 25 mm dia
vertical pipes fabricated and framed in the form of panels of
one metre length and 1.75 metre height fixed with circular
vane 250 mm dia at top and rectangular vane 600 x 300 mm
at the middle, made out of steel sheet of 3 mm thickness,
end vertical pipes of the panel made larger for embedding in
foundation concrete, applying 2 coats of paint on all exposed
surfaces, all as per approved design and drawings.
Unit = Running metre
Taking output = one metre
a)

b)

Labour
Mate

day

0.004

151.44

0.61

L-12

Mazdoor

day

0.100

136.69

13.67

L-13

metre

16.000

182.00

2912.00

M-174

kg

4.320

45.00

194.40

kg

4.800

45.00

216.00

M-179 /
1000
M-179 /
1000

Material

i) 25 mm steel pipe
ii) MS sheet for 600 x 300 x 3 mm rectangular vane,
one number @ 24kg/sqm
iii) MS sheet for 250 mm dia circular vane 3 mm thick,4
numbers @ 24 kg/sqm
Add 5 per cent cost of material for fabrication, welding,
bending, nuts, bolts etc
c) Painting
Applying 2 coats of painting on exposed surface
d)

Overhead charges @ 0.1 on (a+b)

e)

Contractor's profit @ 0.1 on (a+b+d)

166.12
sqm

1.830

46.00

4322.56
say

8.26

Item 8.9

385.31

Rate per metre = a+b+c+d+e


Note

84.18
350.28

4323.00

The items of excavation and cement concrete as per


approved design to be measured and paid separately
Anti-glare screen with rectangular vane of MS sheet
Providing and erecting anti - glare screen with rectangular
vanes of size 750 x 500 mm made from MS sheet, 3 mm
thick and fixed on MS angle 50 x 50 x 6 mm at an angle of
450 to the direction of flow of traffic, 1.5 m center to center,
top edge of the screen 1.75 m above ground level, vertical
post firmly embedded in M-15 cement concrete foundation
0.60 m below ground level, applying 2 coats of paint on
exposed faces, all complete as per approved design and
drawings
Unit = Running metre
Taking output = 1.50 metre
a)

b)

Labour
Mate

day

0.004

151.44

0.61

L-12

Mazdoor

day

0.100

136.69

13.67

L-13

i) Angle iron post,50 x 50 x 6 mm, length 2.35 m

kg

10.580

45.00

476.10

ii) MS sheet 3 mm thick @ 24 kg/sqm

kg

9.000

45.00

405.00

M-179 /
1000
M-179 /
1000

Material

Add 5 per cent of cost of material for fabrication, nuts, bolts


etc
c) Machinery
Tractor-trolley
d)

44.06
hour

0.100

282.50

28.25

P&M-053

sqm

0.850

46.00

39.10

Item 8.9

Painting
Applying 2 coats of painting

e)

Overhead charges @ 0.1 on (a+b+c)

f)

Contractor's profit @ 0.1 on (a+b+c+e)

Cost for 1.5 m = a+b+c+d+e+f

96.77
106.44
1209.99

Page 18 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Rate per metre = (a+b+c+d+e+f)/1.50

806.66
say

Note

8.27

Suggest
ive

Remarks/
Input ref.

807.00

The items of excavation and cement concrete as per


approved design to be measured and paid separately. Rate
of painting has been analaysed separately in this chapter.
Street Lighting
Providing and erecting street light mounted on a steel
circular hollow pole of standard specifications for street
lighting, 9 m high spaced 40 m apart, 1.8 m overhang on
both sides if fixed in the median and on one side if fixed on
the footpath, fitted with sodium vapour lamp and fixed firmly
in concrete foundation.
Unit = Each
Taking output = one light
a)

b)

Labour
Mate

day

0.030

151.44

4.54

L-12

Mazdoor

day

0.500

136.69

68.35

L-13

Electrician

day

0.250

264.50

66.13

L-02

1820.00

1820.00

M-171

each

1.000

each

1.000

1213.00

1213.00

M-168

Material
i) Steel circular hollow pole of standard specification for
street lighting to mount light at 9 m height above road
level

ii) Sodium vapour lamp


Add 5 per cent of cost of material for holder, electric cable,
insulation, ladder, scaffolding etc
c) Painting

(i)

For Fixing in Median


Providing two coats of alluminium paint over steel
circular hollow pipe with overhang on both sides
For fixing in Footpath
Providing two coats of alluminium paint over steel
circular hollow pipe with overhang on one side
For Fixing in Median

151.65

sqm

5.750

46.00

264.50

Item 8.9

sqm

4.630

46.00

212.98

Item 8.9

d)

Overhead charges @ 0.1 on (a+b)

e)

Contractor's profit @ 0.1 on (a+b+d)

332.37
365.60

Rate per light for fixing in Median= a+b+c+d+e

4286.13
say

(ii)

Rate per light for Fixing in Footpath = a+b+c+d+e

4234.61
say

Note

8.28

Suggest
ive

4286.00

For fixing in Footpath


4235.00

The items of excavation and cement concrete foundation will


be measured and included separately in the estimate as per
approved design and drawing. The rate for painting has
been analysed in this chapter.
Lighting on Bridges
Providing and fixing lighting on bridges, mounted on steel
hollow circular poles of standard specifications, 5 m high
fixed on parapets with cement concrete, 20 m apart and
fitted with sodium vapour lamp
Unit = Each
Taking output = one light
a)

b)

Labour
Mate

day

0.020

151.44

3.03

L-12

Mazdoor

day

0.400

136.69

54.68

L-13

Electrician

day

0.200

264.50

52.90

L-02

1213.00

1213.00

M-170

each

1.000

each

1.000

1213.00

1213.00

M-168

Material
i) Steel circular hollow pole of standard specification for
street lighting to mount light at 5 m above deck level

ii) Sodium vapour lamp 70 watt


Add 1 per cent of cost of material for holder, electric cable,
insulation, ladder, scaffolding etc
c) Painting

Page 19 of 264

24.26

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

d)

Providing two coats of alluminium paint over steel


circular hollow pipe
Overhead charges @ 0.1 on (a+b)

e)

Contractor's profit @ 0.1 on (a+b+d)

sqm

Quantity
2.760

Rate Rs

Cost Rs

46.00

8.29

Suggest
ive

Item 8.9

256.09
281.70

Rate per light = a+b+c+d+e

Note

126.96

Remarks/
Input ref.

3225.61
say

3226.00

13239.60

The items of cement concrete to be measured and paid


separately as per approved design. The rate for painting has
already been analysed in this chapter.
Cable Duct Across the Road
Providing and laying of a reinforced cement concrete pipe
duct, 300 mm dia, across the road (new construction),
extending from drain to drain in cuts and toe of slope to toe
of slope in fills, constructing head walls at both ends,
providing a minimum fill of granular material over top and
sides of RCC pipe as per IRC:98-1997, bedded on a 0.3 m
thick layer of granular material free of rock pieces, outer to
outer distance of pipe at least half dia of pipe subject to
minimum 450 mm in case of double and triple row ducts,
joints to be made leak proof, invert level of duct to be above
higher than ground level to prevent entry of water and dirt,
all as per IRC: 98 - 1997 and approved drawings.

(i)

Single row for one utility service


Unit = Running metre
Taking output = 20metres
a) Random Rubble masonry/Brick masonry in
cement mortar 1:6 for head wall both side
b) Labour

c)

d)

cum

2.360

5610.00

Mate

day

0.050

151.44

7.57

L-12

Mazdoor

day

1.000

136.69

136.69

L-13

Mazdoor skilled

day

0.250

164.69

41.17

L-15

Reinforced Cement Concrete pipe 300 mm dia


Granular soil with PI less than 6 for bedding and sides
of pipe (0.6 x 0.6 x 20 m)
Collar for joints 300 mm dia

metre

20.000

1149.00

22980.00

M-151

cum

7.200

727.79

5240.09

M-009

each

9.000

146.00

1314.00

Cement mortar 1:2 for joints

cum

0.020

4152.00

83.04

Item 12.6
(B)

hour

0.500

282.50

141.25

P&M-053

Material

e)

Overhead charges @ 0.1 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

2994.38
3293.82

Cost for 20 metre = a+b+c+d+e+f

49471.61

Rate per metre = (a+b+c+d+e+f)/20


(ii)

M-083

Machinery
Tractor-trolley

8.29

Item 12.7
(Addl) B)

2473.58
say

2474.00

18905.70

Double row for two utility services


Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement
mortar 1:6 for head wall both sides.
b) Labour

c)

3.370

5610.00

Mate

day

0.050

151.44

7.57

L-12

Mazdoor

day

2.000

136.69

273.38

L-13

Mazdoor skilled

day

0.250

164.69

41.17

L-15

metre

40.000

1149.00

45960.00

M-151

cum

14.400

727.79

10480.18

M-009

each

18.000

146.00

2628.00

M-083

cum

0.040

4152.00

166.08

Item 12.6
(B)

hour

1.000

282.50

282.50

P&M-053

Material
Reinforced Cement Concrete pipe 300 mm dia
Granular soil with PI less than 6 for bedding and sides
of pipe (0.6 x 0.6 x 40 m)
Collar for joints 300 mm dia
Cement mortar 1:2 for joints

d)

Machinery
Tractor-trolley

e)

Item 12.7
(Addl) B)

cum

Overhead charges @ 0.1 on (b+c+d)


Page 20 of 264

5983.89

Sr No

Ref. to
MoRTH
Spec.

Description
f)

Unit

Quantity

Rate Rs

Cost Rs

Contractor's profit @ 0.1 on (b+c+d+e)

6582.28

Cost for 20 metre = a+b+c+d+e+f

91310.75

Rate per metre = (a+b+c+d+e+f)/20


8.29

(iii)

Remarks/
Input ref.

4565.54
say

4566.00

24571.80

Triple rRow for three utility services


Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement
mortar 1:6 for head wall both sides.
b) Labour

c)

cum

4.380

5610.00

Mate

day

0.160

151.44

24.23

L-12

Mazdoor

day

3.000

136.69

410.07

L-13

Mazdoor skilled

day

1.000

164.69

164.69

L-15

metre

60.000

1149.00

68940.00

M-151

cum

21.600

727.79

15720.26

M-009

each

27.000

146.00

3942.00

M-083

cum

0.060

4152.00

249.12

Item 12.6
(B)

hour

1.500

282.50

423.75

P&M-053

Material
Reinforced Cement Concrete pipe 300 mm dia
Granular soil with PI less than 6 for bedding and sides
of pipe (0.6 x 0.6 x 60 m)
Collar for joints 300 mm dia
Cement mortar 1:2 for joints

d)

Machinery
Tractor-trolley

e)

Overhead charges @ 0.1 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

8987.41
9886.15

Cost for 20 metre = a+b+c+d+e+f

133319.49

Rate per metre = (a+b+c+d+e+f)/20

6665.97
say

Note

8.30

8.31

Suggest
ive

Suggest
ive

1.Inspection chamber at both ends is the responsibility of the


agency who is laying the duct. Hence not included.
2.The rates for stone masonry / brick masonry and cement
mortar to be adopted from respective clauses.
Highway Patrolling and Traffic Aid Post
It is proposed to locate one Traffic Aid Post every 50-60 km
of the highway.
The organisation and financial aspect are required to be
finalised in consultation with administrative and traffic
authorities .
Items Related to Underpass/ Subway/ Overhead Bridge/
Overhead Foot Bridge
The items involved for underpass/ subway/ overhead bridge/
overhead foot bridge are earthwork, plain cement concrete,
plastering, painting, information sign etc. The rates for these
items are available in respective chapters which can be
adopted for the quantities derived from the approved
designs and drawings

8.32

Suggest
ive

Traffic Control System and Communication System


Providing a traffic control centre and communication system
including telecommunication facilities and related
accessories, CCTV, radar, vehicle detection camera, central
computer system
These are specialised item of telecommunication system
and are the commercial products. The designer is required
to contact the manufacturers to ascertain market prices. In
case of civil works required to be executed for these
installations, pricing may be done as per rates in relevant
chapters for quantities derived as per approved design and
drawing.
As regards the locations where such devices are required to
be installed, the traffic control authority should be consulted
to finalise the location

8.33

Suggest
ive

Item 12.7
(Addl) B)

Gantry Mounted Variable Message Sign Board

Page 21 of 264

6666.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Providing and erecting gantry mounted variable message


sign board electronically operated capable of flashing the
desired message over a designed support system of
aluminium alloy or galvanised steel, erected as per approved
design and drawings and with lateral clearance as per
clause 802.3
(i)

Gantry Support System


Unit = tonne
Taking output=1 tonne
a)

b)

c)

Labour
Mate

day

0.120

151.44

18.17

L-12

Mazdoor

day

2.000

136.69

273.38

L-13

Blacksmith

day

1.000

264.50

264.50

L-02

tonne

1.050

54574.00

57302.70

Material
Alluminium alloy/galvanised steel including 5 per cent
wastage
Add 15 per cent of cost of material for fabrication and
erection.
Add 1 per cent of cost of material for nuts, bolts and
welding
Machinery
Truck 10 tonne

8595.41
573.03

hour

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1.000

315.27

P&M-057

7407.67
81484.37
say

(ii)

315.27
6734.25

Rate per tonne = a+b+c+d+e


8.33

M-060

81484.00

Message Display
Message display board 6 sqm electronically operated with
complete electronic fitments for flashing the pre-determined
messages.
This is a specilised commercial product and the lumpsum
rate including erection at site is required to be as certained
from the market and including in the rate analysis. The size
of the board will vary depending upon specific location.
The rate for the gantry mounted variable sign would be the
addition of cost of gantry support system as per approved
design determined at (i) above and the cost of message
display board as certained from the market at (ii) above

8.34

Suggest
ive

Traffic Impact Attenuators at Abutments and Piers


A

With Scrap Tyres


Provision and installation of traffic attenuators at
abutment/pier of flyovers bridges using scrap tyres of size
100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one
above the other and tied with 20 mm wire rope as per
approved design and drawings.
Unit = sqm
Taking output = 20sqm
a)

b)

Labour
Mate

day

0.080

151.44

12.12

L-12

Mazdoor

day

1.500

136.69

205.04

L-13

Blacksmith

day

0.250

264.50

66.13

L-02

each

80.000

364.00

29120.00

M-161

kg

150.000

61.00

9150.00

M-176

Material
Scrap tyres of size 900 x 20
20 mm steel wire rope

Add 1 per cent of cost of wire rope for clamps etc.


c)

91.50

Machinery
Tractor-trolley

hour

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3.000

282.50

4344.15

Cost for 20 sqm = a+b+c+d+e

47785.65

Rate per sqm = (a+b+c+d+e)/20

2389.28
say

8.34

847.50
3949.23

Using Plastic/Steel Barrel, Filled with Sand


Page 22 of 264

2389.00

P&M-053

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Provision and installation of traffic impact attenuator at


abutment/pier of flyovers bridges using plastic/steel barrels
0.60 m dia and 1.0 m in height, filled with sand in three rows
and tied with20 mm steel wire rope as per approved design
and drawings
Unit = sqm
Taking output = 20sqm
a)

b)

Labour
Mate

day

0.130

151.44

19.69

L-12

Mazdoor

day

3.000

136.69

410.07

L-13

Blacksmith

day

0.250

264.50

66.13

L-02

each

50.000

Steel barrels

each

50.000

79.00

3950.00

M-172

Sand

cum

8.000

828.00

6624.00

M-004

kg

15.000

61.00

915.00

M-176

Material
Plastic barrels
or

20 mm steel wire rope


Add 1 per cent of cost of wire rope for clamps etc.
c)

9.15

Machinery
Tractor-trolley

hour

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2.000

282.50

15196.43

Rate per sqm = (a+b+c+d+e)/20

759.82
say

P&M-053

1381.49

Cost for 20 sqm = a+b+c+d+e

8.34

565.00
1255.90

760.00

With HI - DRO cell Sandwich (Patented)


(In this patented HI - DRO cell system, water gets
discharged from plastic tubes on impact over a predetermined time, thus absorbing the energy)
Providing and installing a patentend HI - DRO cell system as
a traffic impact attenuators, using plastic tubes 50 cm dia,
1.2 m in height, 25 mm opening at the top, placed in three
rows, filled with water and tied with a 20 mm steel wire rope
Unit = sqm
Taking output = 10sqm
a)

b)

Labour
Mate

day

0.100

151.44

15.14

L-12

Mazdoor

day

2.500

136.69

341.73

L-13

Material
Plastic tubes 50 cm dia,1.2 m high

each

40.000

3639.00

145560.00

M-139

Cost of water

KL

12.000

10.00

120.00

M-189

20 mm steel wire rope

kg

100.000

61.00

6100.00

M-176

Add 1 per cent of cost of wire rope for clamps etc.


c)

61.00

Machinery
Tractor-trolley

hour

2.000

282.50

565.00

P&M-053

Water tanker6 KL capacity

hour

2.000

200.00

400.00

P&M-060

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

15316.29
16847.92

Cost for 10 sqm = a+b+c+d+e

185327.07

Rate per sqm = (a+b+c+d+e)/10

8.35

Suggest
ive

18532.71
say

18533.00

151.44

6.06

Road Markers/Road Stud with Lense Reflector


Providing and fixing of road stud 100x 100 mm, die-cast in
aluminium, resistant to corrosive effect of salt and grit, fitted
with lense reflectors, installed in concrete or asphaltic
surface by drilling hole 30 mm upto a depth of 60 mm and
bedded in a suitable bituminous grout or epoxy mortar, all as
per BS 873 part 4:1973
Unit = Nos
Taking output = 50Nos
a)

Labour
Mate

day
Page 23 of 264

0.040

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor
b)

Material
Aluminium studs 100 x 100 mm fitted with lense
reflectors

Quantity

Rate Rs

Cost Rs

day

1.000

136.69

136.69

each

50.000

546.00

27300.00

Add 10 per cent of cost of material for fixing and installation

2730.00

c)

Overhead charges @ 0.1 on (a+b)

3017.27

d)

Contractor's profit @ 0.1 on (a+b+c)

M-062

36509.02

Rate per studs = (a+b+c+d)/50

730.18
say

8.36

L-13

3319.00

Cost for 50 studs = a+b+c+d

Suggest
ive

Remarks/
Input ref.

730.00

Traffic Cone
Provision of red fluorescent with white reflective sleeve traffic
cone made of low density polyethylene (LDPE)
material
with a square base of 390 x 390 x 35 mm and a height of
770 mm, 4 kg in weight, placed at 1.5 m interval, all as per
BS 873
Unit = Running metre
Taking output = 68 Nos.
a)

Labour
Mate

day

0.020

151.44

3.03

L-12

Mazdoor

day

0.500

136.69

68.35

L-13

each

68.000

243.00

16524.00

hour

0.100

282.50

b)

Material
Traffic cones with 150 mm reflective sleeve

c)

Tractor-trolley
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1828.60
20114.58

Rate per metre = (a+b+c+d+e)/68

295.80
say

Suggest
ive

Roadside Amenities
A

Rest areas
Providing plainly furnished accommodation for rest rooms,
dormitories, restaurants, stalls, shops, petrol pump,
telephone booth, first aid room, traffic aid post, police
assistance booth, including electricity, toilet and sewerage
system
Pricing may be done based on current plinth area rates
approved by PWD/CPWD/MES for a particular zone. Area is
required to be assessed for specific location as per actual
site conditions

Parking areas and bus laybyes for trucks, buses and


light vehicles
Pricing of parking areas may be done for the quantities of
various items based on the approved dimensions and
pavement design for a particular terrain and soil. Rates for
items may be from respective chapters.
Lawn
Providing a lawn planted with grass and its maintenance
Pricing of lawn may be done as per rates given in the
chapter on horticulture for the quantities as per approved
dimensions in the drawings

8.38

Suggest
ive

28.25
1662.36

Cost for 68 Nos. = a+b+c+d+e

8.37

M-186

Machinery

Rumble Strips
Provision of 15 nos rumble strips covered with premix
bituminous carpet, 15-20 mm high at center, 250 mm wide
placed at 1 m center to center at approved locations to
control speed, marked with white strips of road marking
paint.
Unit = sqm
Taking output = 100 sqm (including gaps)
The rate per sqm of premix carpet and road marking may be
adopted from chapter 5 & 8 respectively for the quantities
calculated from approved drawings

Page 24 of 264

296.00

P&M-053

Sr No
8.39

Ref. to
MoRTH
Spec.
Suggest
ive

Description

Unit

Quantity

Policeman Umbrella
Provision of a 2 m high (floor to roof) umbrella for traffic
policeman at road crossings, where necessary, installed on a
raised platform, built on a central support of a steel pipe 100
mm dia, roof made of 25 mm dia steel pipe to provide
covered area of 3 sqm, roofed with CGI sheets, all steel
parts to be given 2 coats of paint
Unit = each
Taking output = one number
Earthwork
Cement Concrete
brick masonry or

Quantities of these items to be


calculated as per approved design and
cost added as per rates of these items
given in chapter 3 and 13

stone masonry

b)

cum
cum
cum

Painting
a)

cum

sqm

2.500

Mate

day

0.090

Mazdoor

day

1.000

Blacksmith

day

1.000

Welder

day

0.250

Labour

Material
Steel pipe 100 mm dia

metre

3.500

Steel pipe 25 mm dia

metre

10.000

kg

8.000

hour

0.500

CGI sheets
Add 25 per cent of cost of material for fabrication
Add 2 per cent of cost of material for welding consumables,
J-hooks, washers etc.
c) Machinery
Tractor-trolley
d)

Overheads @ per cent on (a+b+c)

e)

Contractors Profit@ per cent on (a+b+c+d)

Rate per policeman umbrella = a+b+c+d+e


8.40

suggesti
ve

High Mast Pole Lighting at Interchanges and Flyovers


Providing and erecting a high mast pole lighting with 30 m
high hot dip galvanised mast designed to withstand forces
exerted with wind speeds of 180 km per hour with 3 seconds
gust, as per IS:875 (Part 3) - 1978, fitted with a base flange,
door at the base of mast with heavy duty internal lock,
lantern carriage, suitable winching arrangement for safe
working load of 750 kg and high powered electrically driven
power tools for raising and lowering of lantern carriage,
flexible 8 core electric cable, lightening conductor, earthing
terminal, and fixing 2 nos aviation obstruction lights on top of
the mast, all complete as per approved design and drawings
This is a specialised work and is generally done by firms
who specialise in such jobs. The detailed designs and
estimates are submitted by the firms along with their tender
for checks by the Department. The cost of this work is
required to be worked out based on approved design,
drawings and estimate of the lowest tender. A separate
contract for this work is concluded as the contractors for
road and bridge works generally donot undertake such jobs.

8.41

Toll Plaza
The construction, operation and maintenance of Toll Plaza
can be broken into separate items of work as under based
on the approved design and drawings:a)
Provision of toll collection service lane to separate
different categories of vehicles for purpose of toll collection.
This involves considerable increase in carriage way width
b)
Provision of 2.5 m wide separators for different toll
collection service lanes for safety
c) Toll booths with integrated roof cover
d) Barrier gates for individual lanes
e)
Provision of building to provide facility to toll plaza
personnel
Page 25 of 264

Rate Rs

Cost Rs

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

f) Toll plaza office equipment and furniture


g)
Water supply, electricity, sanitation, septic-tank system
and drainage
h)
Telephone, intercomes, wireless communication
system
i) High mast lighting
j) Pavement marking
k) Overhead signs
l) Fixed message signs (Advance)
m) Variable message signs
n) Traffic cones and pylons
o) First aid post
p) Traffic aid post and security
The quantities for the above mentioned items may be
calculated from the approved design and drawings and their
rates adopted from respective chapters of the Standard Data
Book
8.42

Safety Devices and Signs in Construction Zones


Provision and fixing of traffic signs for limited period at
suitable locations in construction zone comprising of warning
zone, approach transition zone, working zone and terminal
transition zone with a minimum distance of 60 cm from the
edge of the kerb in case of kerbed roads and 2 to 3 m from
the edge of the carriageway in case of un-kerbed roads, the
bottom edge of the lowest sign plate to be not less than 2 m
above the road level, fixed on 60 mm x 60 mm x 6 mm angle
iron post, founded and installed as per approved design and
drawings, removed and disposed of after completion of
construction work, all as per IRC:SP:55-2001
Unit = each
Taking output = one sign post
Following types of signs are required to be fixed in
construction zones for safety of traffic
a) Diversion one km ahead
b)

Traffic sign ahead

c)

Road ahead closed

d)

Men at work

e)

Road narrow

f)

Single file traffic

g)

Right lane diverted

h)

Left lane diverted

i)

Right lane closed

j) Left lane closed


k) Median closed
l) Diversion to other carriageway
m) Traffic signal ahead
n) Two way traffic
o) Un - even road
p) Slippery road
q) Loose chippings
r) Dual carriageway ends
s) Diversion
t) Do not enter
u) Road closed
v) Stop
w) Slow
x) One way
y) Give way
z)
aa)

Overtaking prohibited
Speed limit

bb)

Weight limit

cc)

Height and length limit

dd)

No stopping or standing
Page 26 of 264

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

ee)
Any other warning or regulatory safety sign as per
site requirement and consistent with IRC:SP:55-2001 and
IRC:67
The rate for traffic signs are already worked out and given
elsewhere in this chapter. The same may be adopted.
8.43

suggesti
ve

Portable Barricade in Construction Zone


Installation of a steel portable barricade with horizontal rail
300 mm wide, 2.5 m in length fitted on a 'A' frame made with
45 x 45 x 5 mm angle iron section, 1.5 m in height,
horizontal rail painted (2 coats) with yellow and white stripes,
150 mm in width at an angle of 450, 'A' frame painted with 2
coats of yellow paint, complete as per IRC:SP:55-2001
Unit = each
Taking output = one steel portable barricade
a)

b)

Labour
Mate

day

0.020

151.44

3.03

L-12

Mazdoor

day

0.250

136.69

34.17

L-13

Painter

day

0.500

223.36

111.68

L-18

Welder

day

0.250

264.50

66.13

L-02

Angle iron 45 x 45 x 5 mm

kg

25.000

45.00

1125.00

MS sheet 300 mm wide,2.5 m long and 2.6 mm thick

kg

15.000

45.00

675.00

litre

0.500

192.81

96.41

Material

Paint
Add 2 per cent of cost of steel for welding consumables,
nuts & bolts and drilling holes
c) Overhead charges @ 0.1 on (a+b)
d)

36.00
214.74

Contractor's profit @ 0.1 on (a+b+c)

236.22

Rate per barricade = a+b+c+d

2598.37
say

8.44

suggesti
ve

M-179 /
1000
M-179 /
1000
M-131

2598.00

Permanent Type Barricade in Construction Zone


A

With steel components


Construction of a permanent type barricade made of steel
components, 1.5 m high from road level, fitted with 3
horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5
mm angle iron vertical support, painted with yellow and white
strips, 150 mm in width at an angle of450, complete as per
IRC:SP:55-2001
Unit = each
Taking output = one barricade
a)

b)

Labour
Mate

day

0.050

151.44

7.57

L-12

Mazdoor

day

0.300

136.69

41.01

L-13

Painter

day

0.600

223.36

134.02

L-18

Welder

day

0.300

264.50

79.35

L-02

kg

15.000

45.00

675.00

kg

50.000

45.00

2250.00

litre

1.000

192.81

192.81

M-179 /
1000
M-179 /
1000
M-131

Material
Angle iron 50 x 50 x 5 mm,2 m long,2 Nos.

MS sheet of 12 SWG,3 Nos of 200 mm width and 4 m


length
Paint
Add 1 per cent of cost of steel for welding consumables,
nuts & bolts and drilling holes
c) Overhead charges @ 0.1 on (a+b)
d)

58.50
343.83

Contractor's profit @ 0.1 on (a+b+c)

378.21

Rate per barricade = a+b+c+d

4160.29
say

8.44

With wooden components

Page 27 of 264

4160.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Construction of a permanent type barricade made of wooden


components, 1.5 m high from road level, fitted with 3
horizontal planks 200 mm wide and 3.66 m long on 100 x
100mm wooden vertical post, painted with yellow and white
strips, 150 mm in width at an angle of450, complete as per
IRC:SP:55-2001
Unit = each
Taking output = one barricade
a)

b)

Labour
Mate

day

0.050

151.44

7.57

L-12

Mazdoor

day

0.300

136.69

41.01

L-13

Painter

day

0.600

223.36

134.02

L-18

Carpenter

day

0.600

264.50

158.70

L-04

cum

0.180

24255.00

4365.90

M-185

Material
Timber

Add 1 per cent of cost of timber for nuts & bolts, nails, etc.
c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

43.66
475.09
522.59

Rate per barricade = a+b+c+d

5748.53
say

8.44

5749.00

With bricks
Construction of a permanent type barricade made with brick
work in mud mortar, 1.5 m high, 4 m long, 600 mm thick,
plastered with cement mortar 1:6, painted with yellow and
white strips
Unit = each
Taking output = one barricade
a)

b)

Labour
Mate

day

0.240

151.44

36.35

L-12

Mazdoor

day

3.000

136.69

410.07

L-13

Painter

day

1.000

223.36

223.36

L-18

Mason

day

2.000

223.36

446.72

L-11

each

1800.000

4.42

7952.72

M-079

110.00

Material
Brick

kg

22.000

5.00

Sand

cum

0.090

710.46

63.94

M-081 /
1000
M-005

Paint

litre

1.250

192.81

241.01

M-131

Cement

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

948.42
1043.26

Rate per barricade = a+b+c+d

11475.85
say

8.45

suggesti
ve

11476.00

Drum Delineator in Construction Zone


Provision of metal drum/empty bitumen drum delineator, 300
mm in diameter, 800 mm high, filled with earth for stability,
painted in circumferential strips of alternate black and white
100 mm wide fitted with reflectors 3 Nos of 7.5 cm dia, all as
per IRC:SP:55-2001
Unit = each
Taking output = one drum delineator
a)

b)

Labour
Mate

day

0.020

151.44

3.03

L-12

Mazdoor

day

0.250

136.69

34.17

L-13

Painter

day

0.250

223.36

55.84

L-18

Material
Steel drum 300 mm dia 1.2 m high/empty bitumen
drum
Paint

each

1.000

79.00

79.00

M-172

litre

0.500

192.81

96.41

M-131

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

26.84
29.53

Rate per drum delineator = a+b+c+d

324.82
say

Page 28 of 264

325.00

Sr No
8.46

Ref. to
MoRTH
Spec.
suggesti
ve

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Flagman
Positioning of a smart flagman with a yellow vest and a
yellow cap and a red flag 600 x 600 mm securely fastened to
a staff 1 m in length for guiding the traffic
Unit = each
Taking output = one flagman
a)

Labour
Mate

day

0.040

151.44

6.06

L-12

Mazdoor

day

1.000

136.69

136.69

L-13

each

1.000

91.00

91.00

M-099

1.000

122.00

122.00

M-196

b)

Material

c)

Flag of red color cloth 600 x 600 mm


Wooden staff for fastening of flag 25 mm dia, one m
long
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

each

35.57
39.13

Rate per flagman = a+b+c+d

430.45
say

Page 29 of 264

430.00

CHAPTER-9
PIPE CULVERTS
Sr No

Ref. to
MoRTH
Spec.

9.1

408

Description

Unit

Rate Rs

Cost Rs

Remarks/
Input ref.

PCC 1:3:6 in Foundation


Plain cement concrete 1:3:6 mix with crushed stone
aggregate 40 mm nominal size mechanically mixed, placed
in foundation and compacted by vibration including curing for
14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate
Mason
Mazdoor
b) Material
40mm Aggregate at site
Sand at site
Cement at site
Cost of water
c) Machinery
Concrete mixer0.4/ 0.28 cum
Generator set 33 KVA
Water tanker6 KL capacity
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Note

9.2

Quantity

2900

day
day
day

0.640
1.000
15.000

151.44
223.36
136.69

96.92
223.36
2050.35

L-12
L-11
L-13

cum
cum
tonne
KL

13.800
6.900
3.300
18.000

916.00
710.46
5000.00
10.00

12640.80
4902.17
16500.00
180.00

M-055
M-005
M-081
M-189

hour
hour
hour

6.000
6.000
3.000

233.00
406.80
200.00

P&M-009
P&M-079
P&M-060

say

1398.00
2440.80
600.00
4103.24
4513.56
49649.21
3309.95
3310.00

Vibrator is a part of minor T & P which is already included in


overhead charges of the contractor.
Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Single Row .
Laying Reinforced cement concrete pipe NP4/prestressed
concrete pipe for culverts on first class bedding of granular
material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .

Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length
each )
1000 mm dia
a)

Labour
Mate
Mason
Mazdoor
b) Material
Sand at site
Cement at site
RCC pipe NP-4 /prestressed concrete pipe including
collar at site
Granular material passing 5.6 mm sieve for bedding
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 12.5 metres = a+b+c+d
Rate per metre = (a+b+c+d)/12.5
Note

day
day
day

0.180
0.500
4.000

151.44
223.36
136.69

27.26
111.68
546.76

L-12
L-11
L-13

cum
tonne
metre

0.070
0.050
12.500

710.46
5000.00
5000.00

49.73
250.00
62500.00

M-005
M-081
M-149

cum

4.500

727.79

M-009

say

3275.06
6676.05
7343.65
80780.19
6462.42
6462.42

151.44
223.36

42.40
223.36

1. In case of cement craddle bedding, quantity of PCC M15


is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

9.2

1200 mm dia
a) Labour
Mate
Mason

day
day
Page 1 of 264

0.280
1.000

L-12
L-11

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor
Material
Sand at site
Cement at site
RCC pipe NP-4/prestressed concrete pipe including
collar at site
Granular material passing 5-6 mm sieve for class
bedding
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 12.5 metres = a+b+c+d
Rate per metre= (a+b+c+d)/12.5

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

day

6.000

136.69

820.14

L-13

cum
tonne
metre

0.090
0.070
12.500

710.46
5000.00
4452.00

63.94
350.00
55650.00

M-005
M-081
M-150

cum

5.000

727.79

3638.95

M-009

say

6078.88
6686.77
73554.44
5884.36
5884.00

b)

Note

9.3

2900

1. In case of cement craddle bedding, quantity of PCC M15


is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Double Row .
Laying Reinforced cement concrete pipe NP4 / prestressed
concrete pipe for culverts on first class bedding of granular
material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre

Taking output = 12.5 metres ( 10 pipes of 2.5 m length


each in two rows.)
1000 mm dia
a)

b)

Labour
Mate

day

0.360

151.44

54.52

Mason

day

1.000

223.36

223.36

L-11

Mazdoor

day

8.000

136.69

1093.52

L-13

Material
Sand at site

cum

0.140

710.46

99.46

M-005

Cement at site

tonne

0.100

5000.00

500.00

M-081

RCC pipe NP-4/prestressed concrete pipe including


collar at site
Granular material passing 5.6 mm sieve for bedding

metre

25.000

5000.00

125000.00

M-149

cum

12.500

727.79

9097.38

M-009

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

13606.82
14967.51

Cost for 12.5 metres = a+b+c+d

164642.57

Rate per metre = (a+b+c+d)/12.5


Note

9.3

L-12

13171.41

1. In case of cement craddle bedding, quantity of PCC M15


is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

say

13171.00

1200 mm dia
a)

b)

Labour
Mate

day

0.560

151.44

84.81

Mason

day

2.000

223.36

446.72

L-12
L-11

Mazdoor

day

12.000

136.69

1640.28

L-13

cum

0.180

710.46

127.88

M-005

tonne

0.140

5000.00

700.00

M-081

Material
Sand at site
Cement at site
Page 2 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

c)

RCC pipe NP-4 /prestressed concrete pipe including


collar at site
Granular material passing 5-6 mm sieve for class
bedding
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Quantity

Rate Rs

Cost Rs

metre

25.000

4452.00

111300.00

M-150

cum

13.750

727.79

10007.11

M-009

12430.68
13673.75

Cost for 12.5 metres = a+b+c+d

150411.23

Rate per metre= (a+b+c+d)/12.5


Note

12032.90

1. In case of cement craddle bedding, quantity of PCC M15


is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

Page 3 of 264

Remarks/
Input ref.

say

12033.00

CHAPTER-12
FOUNDATIONS
Sr No

Ref. to
MoRTH
Spec.

12.1

304

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Excavation for Structures


Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with approved material.
I

Ordinary soil
Unit = cum
Taking output = 10 cum

A
(i)

Manual Means
Depth upto 3 m
a) Labour
Mate
Mazdoor
b) Overhead charges @ 0.2 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

day
day

0.14
3.50

151.44
136.69

21.20
478.42
99.92
59.95
659.49
65.95
66.00

L-12
L-13

27.26
615.11
128.47
77.08
847.92
84.79
85.00

L-12
L-13

L-12
L-13

say

36.35
820.14
171.30
102.78
1130.56
113.06
113.00

say
Note

12.1 (I) A

(ii)

1. Cost of dewatering may be added where required upto, 10


per cent of labour cost Assessment for dewatering shall be
made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy
soil. Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding marshy soil.
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
Depth 3 m to 6 m
a) Labour
Mate/Supervisor
Mazdoor
b) Overhead charges @ 0.2 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

day
day

0.18
4.50

151.44
136.69

say

12.1 (I) A

Note

Cost of dewatering may be added where required upto 15


per cent of labour cost. Assessment for dewatering shall be
done as per actual ground conditions.

(iii)

Depth above 6 m
a) Labour
Mate/Supervisor
Mazdoor
b) Overhead charges @ 0.2 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

Note

12.1 (I)

B
(i)

1. Cost of dewatering may be added where required upto 20


per cent of labour cost. Assessment for dewatering shall be
made as per site conditions..
Mechanical Means
Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity
c) Overhead charges @ 0.2 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240
Page 1 of 264

day
day

0.24
6.00

151.44
136.69

day
day

0.32
8.00

151.44
136.69

48.46
1093.52

L-12
L-13

hour

6.00

1302.00

7812.00
1790.80
1074.48
11819.25
49.25

P&M-026

Sr No

Ref. to
MoRTH
Spec.

Description

Note

12.1 (I) B

(ii)

Unit

Quantity

Rate Rs
say

49.00

Remarks/
Input ref.

Cost of dewatering upto 5 per cent of (a+b) may be added,


where required. Assessment for dewatering shall be made
as per site conditions..
Depth 3 m to 6 m
Unit = cum
Taking output = 210 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity
c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

day
day

0.32
8.00

151.44
136.69

48.46
1093.52

L-12
L-13

hour

6.00

1302.00

7812.00

P&M-026

1790.80
1074.48

Cost for 210 cum = a+b+c+d

11819.25

Rate per cum = (a+b+c+d)/210

56.28
say

12.1 (I) B

Cost Rs

Note

Cost of dewatering upto 7.5 per cent of (a+b)


may be
added, where required. Assessment for dewatering shall be
made as per site conditions..

(iii)

Depth above 6m

56.00

Unit = cum
Taking output = 180 cum
a)

b)

Labour
Mate

day

0.40

151.44

60.58

L-12

Mazdoor

day

10.00

136.69

1366.90

L-13

hour

6.00

1302.00

7812.00

P&M-026

Machinery
Hydraulic excavator 1.0 cum bucket capacity

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1847.90
1108.74

Cost for 180 cum = a+b+c+d

12196.11

Rate per cum = (a+b+c+d)/180

67.76
say

Note

12.1

68.00

1. Cost of dewatering upto 10 per cent of (a+b)


may be
added, where required. Assessment for dewatering shall be
made as per site conditions..

II

2.Labour provided for excavation by mechanical means


includes that required for trimming of bottom and side
slopes.
Ordinary Rock (not requiring blasting)

Manual Means

(i)

Depth upto 3 m
Unit = cum
Taking output = 10 cum
a)

Labour
Mate

day

0.20

151.44

30.29

L-12

Mazdoor

day

5.00

136.69

683.45

L-13

b)

Overhead charges @ 0.2 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

142.75
85.65

Cost for 10 cum = a+b+c

942.13

Rate per cum = (a+b+c)/10

94.21
say

Note

12.1(II)

Cost of dewatering upto 10 per cent of labour cost may be


added, where required. Assessment for dewatering shall be
made as per site conditions..
Mechanical Means
Unit = cum
Taking output = 180 cum
a)

Labour
Page 2 of 264

94.00

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

day

0.24

151.44

36.35

L-12

Mazdoor

day

6.00

136.69

820.14

L-13

hour

6.00

1302.00

7812.00

P&M-026

Machinery

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1733.70
1040.22

Cost for 180 cum = a+b+c+d

11442.40

Rate per cum = (a+b+c+d)/180

63.57
say

12.1

Remarks/
Input ref.

Mate

Hydraulic excavator 1.0 cum bucket capacity

Note

Cost Rs

III

1.Cost of dewatering upto 10 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
Hard Rock ( requiring blasting )

Manual Means

64.00

Unit = cum
Taking output = 10 cum
a)

b)

Labour
Mate

day

0.35

151.44

53.00

L-12

Driller

day

0.50

264.50

132.25

L-06

Blaster

day

0.25

264.50

66.13

L-03

Mazdoor

day

8.00

136.69

1093.52

L-13

hour

1.00

319.00

319.00

P&M-001

511.00

M-104

Machinery
Air Compressor 250 cfm with 2 jack hammer for drilling.

c)

Material
Blasting Material

kg

3.50

146.00

Detonator electric

each

14.00

14.56

d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

475.75
285.45

Cost for 10 cum = a+b+c+d+e

3139.94

Rate per cum = (a+b+c+d+e)/10

313.99
say

Note

12.1

IV

203.84 M-094/100

314.00

Cost of dewatering @ 10 per cent of (a+b)


may be
added, where required Assessment for dewatering shall be
made as per site conditions.
Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum

Mechanical Means
a)

Labour
Mate

day

0.20

151.44

30.29

L-12

Mazdoor

day

5.00

136.69

683.45

L-13

hour

6.00

319.00

1914.00

P&M-001

b)

Machinery

c)

Air Compressor 250 cfm with 2 leads of pneumatic


breaker
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

525.55
315.33

Cost for 10 cum = a+b+c+d

3468.61

Rate per cum = (a+b+c+d)/10

346.86
say

Note

12.1

1. Cost of dewatering upto10 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
Marshy Soil
Unit = cum

Page 3 of 264

347.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 10 cum


Depth upto 3 m
A

Manual means
a)

b)

Labour
Mate/Supervisor

day

0.40

151.44

60.58

L-12

Mazdoor

day

10.00

136.69

1366.90

L-13

hour

2.67

282.50

754.28

P&M-053

Machinery
Tractor-trolley for removal.

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

436.35
261.81

Cost for 10 cum = a+b+c+d

2879.91

Rate per cum = ( a+b+c+d)/ 10

287.99
say

Note

12.1 (V)

2. Shoring & strutting 15 per cent of (a), where required may


be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item12.1 (i) to (iv) for ordinary soil
Mechanical Means
a)

b)

Labour
Mate

day

0.08

151.44

12.12

L-12

Mazdoor for dressing sides, bottom and backfilling

day

2.00

136.69

273.38

L-13

hour

0.17

1302.00

221.34

P&M-026

hour

0.45

0.00

P&M-048

Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

101.37
60.82

Cost for 10 cum = a+b+c+d

669.02

Rate per cum = (a+b+c+d)/10

66.90
say

Note

VI

288.00

1. Cost of dewatering @ 30 per cent of (a), may be added,


where required Assessment for dewatering shall be made as
per site conditions.

67.00

1. Cost of dewatering @ 20 per cent of (a+b)


may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item 12.1 (i) to (iv) for ordinary soil
Back Filling in Marshy Foundation Pits
Unit : Cum
Taking Output : 6 cum
a)

b)

Labour
Mate

day

0.12

151.44

18.17

L-12

Mazdoor for dressing sides, bottom and backfilling

day

3.00

136.69

410.07

L-13

hour

2.00

282.50

565.00

P&M-053

Machinery
Tractor-trolley for transportation

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

198.65
119.19

Cost for 6 cum = a+b+c+d

1311.08

Rate per cum = (a+b+c+d)/6

218.51
say

12.2

304

Filling Annular Space Around Footing in Rock


Unit = cum
Taking out put = 1 cum
Lean cement concrete 1:3:6 nominal mix. Rate may be
taken as per item 12.4.

Page 4 of 264

219.00

Sr No
12.3

Ref. to
MoRTH
Spec.

Description

304

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Sand Filling in Foundation Trenches as per Drawing &


Technical Specification
Unit = cum
Taking output = 1 cum
a)

b)

Labour
Mate

day

0.01

151.44

1.51

L-12

Mazdoor

day

0.30

136.69

41.01

L-13

cum

1.20

476.80

572.16

M-006

Material
Sand (assuming 20 per cent voids)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

122.94
73.76

Rate per cum = a+b+c+d

811.38
say

12.4

2100

811.00

PCC 1:3:6 in Foundation


Plain cement concrete 1:3:6 nominal mix in foundation with
crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum
a)

b)

255.94

Labour
Mate

day

0.64

151.44

96.92

Mason

day

1.00

223.36

223.36

L-11

Mazdoor

day

15.00

136.69

2050.35

L-13

40 mm Aggregate

cum

13.50

916.00

12366.00

M-055

coarse Sand

cum

6.75

710.46

4795.61

M-005

cement

tonne

3.45

5000.00

17250.00

M-081

KL

18.00

10.00

180.00

M-189

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

Water tanker 6 KL capacity

hour

2.00

200.00

400.00

P&M-060

Material

Cost of water
c)

Machinery

d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

8240.21
4944.12

Cost for 15 cum = a+b+c+d+e

54385.37

Rate per cum = (a+b+c+d+e)/15


Note
12.5

1300

L-12

3625.69
say

3626.00

Vibrator is a part of minor T & P which is already included in


overhead charges of the contractor.
Brick Masonry Work in Cement Mortar 1:3 in Foundation
complete excluding Pointing and Plastering, as per
Drawing and Technical Specifications.
Unit = cum
Taking output = 5 cum
a)

b)

Material
Bricks Ist class

each

2500.00

4.42

11045.45

M-079

Cement mortar 1:3 (Rate as in Item 12.6 A subanalysis)


Labour

cum

1.20

3425.00

4110.00

Item 12.6
(A)

Mate

day

0.48

151.44

72.69

Mason

day

4.00

223.36

893.44

L-11

Mazdoor

day

8.00

136.69

1093.52

L-13

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3443.02
2065.81

Cost for 5 cum = a+b+c+d

22723.93

Rate per cum (a+b+c+d)/5

4544.79
say
Page 5 of 264

4545.00

L-12

Sr No
12.6

Ref. to
MoRTH
Spec.
Subanalysis

Description
(A)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Cement Mortar 1:3 (1 cement : 3 sand)

Unit = 1 cum
Taking output = 1 cum
a)

b)

Materials
Cement

tonne

0.51

5000.00

2550.00

M-081

Sand

cum

1.05

710.46

745.98

M-005

Mate

day

0.04

151.44

6.06

L-12

Mazdoor

day

0.90

136.69

123.02

L-13

say

3425.00

Labour

Total Material and Labour = (a+b)


Subanalysis
(Addl.)

(B)

Cement Mortar1:2 (1cement :2 sand)

Unit = 1 cum
Taking output = 1 cum
a)

b)

Materials
Cement

tonne

0.67

5000.00

3360.00

M-081

Sand

cum

0.93

710.46

660.73

M-005

Mate

day

0.04

151.44

6.06

L-12

Mazdoor

day

0.90

136.69

123.02

L-13

say

4150.00

Labour

Total Material and Labour = (a+b)


Subanalysis
(Addl.)

(C)

Cement Mortar1:4 (1cement :4 sand)

Unit = 1 cum
Taking output = 1 cum
a)

b)

Materials
Cement

tonne

0.40

5000.00

2016.00

M-081

Sand

cum

1.12

710.46

795.72

M-005

Mate

day

0.04

151.44

6.06

L-12

Mazdoor

day

0.90

136.69

123.02

L-13

say

2941.00

Labour

Total Material and Labour = (a+b)


Subanalysis
(Addl.)

(D)

Cement Mortar1:6 (1cement :6 sand)

Unit = 1 cum
Taking output = 1 cum
a)

b)

Materials
Cement

tonne

0.29

5000.00

1440.00

M-081

Sand

cum

1.34

710.46

949.99

M-005

Mate

day

0.04

151.44

6.06

L-12

Mazdoor

day

0.90

136.69

123.02

L-13

say

2519.00

2705.04

14877.72

Labour

Total Material and Labour = (a+b)


12.7

1400

Stone Masonry Work in Cement Mortar 1:3 in


Foundation complete as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum

1405.4

(A)

Square Rubble Coursed Rubble Masonry (first sort)


a)

Material
Stone

cum
Page 6 of 264

5.50

M-169

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Through and bond stone

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

each

35.00

14.45

505.86

M-182

Cement mortar 1:3 (Rate as in Item 12.6 A subanalysis)


Labour

cum

1.50

3425.00

5137.50

Item 12.6
(A)

Mate

day

0.66

151.44

99.95

Mason

day

7.50

223.36

1675.20

L-11

Mazdoor

day

9.00

136.69

1230.21

L-13

(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)

b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

4705.29
2823.17

Cost for 5 cum = a+b+c+d

31054.89

Rate per cum (a+b+c+d)/5


1405.3

(B)

L-12

6210.98
say

6211.00

Random Rubble Masonry


( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a)

Material
Stone

cum

5.50

2604.51

14324.81

M-148

Through and bond stone

each

35.00

14.45

505.86

M-182

Cement mortar 1:3 (Rate as in Item 12.6 A subanalysis)


Labour

cum

1.55

3425.00

5308.75

Item 12.6
(A)

Mate

day

0.62

151.44

93.89

L-12

Mason

day

6.00

223.36

1340.16

L-11

Mazdoor

day

9.00

136.69

1230.21

L-13

(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)

b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

4560.73
2736.44

Cost for 5 cum = a+b+c+d

30100.85

Rate per cum (a+b+c+d)/5


Note

12.8

1500,
1700 &
2100
A

6020.17
say

6020.00

The labour already considered in cement mortar has been


taken into account while proposing labour for masonry
works.
Plain/Reinforced Cement Concrete in Open Foundation
complete as per Drawing and Technical Specifications.
PCC Grade M15
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

4.13

5000.00

20650.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

40 mm Aggregate

cum

8.10

916.00

7419.60

M-055

20 mm Aggregate

cum

4.05

1028.00

4163.40

M-053

10 mm Aggregate

cum

1.35

1005.00

1356.75

M-051

Mate

day

0.86

151.44

130.24

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 63 KVA

hour

6.00

535.00

3210.00

P&M-019

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost
of material, labour and machinery

Page 7 of 264

3080.00
1847.70

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

5764.82
63412.97

Rate per cum = (a+b+c+d+e+f)/15

12.8

Remarks/
Input ref.

9608.03

Cost for 15 cum = a+b+c+d+e+f

Note

Cost Rs

4227.53
say

4228.00

Needle Vibrator is an item of minor T & P which is already


included in overhead charges. Hence not added in rate
analysis of cement concrete works.
PCC Grade M20
Unit : cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

5.16

5000.00

25800.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

40 mm Aggregate

cum

5.40

916.00

4946.40

M-055

20 mm Aggregate

cum

5.40

1028.00

5551.20

M-053

10 mm Aggregate

cum

2.70

1005.00

2713.50

M-051

Mate

day

0.86

151.44

130.24

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d)
Formwork @ 4 per cent on cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)
f)

3390.00
2033.78
10575.67

Contractor's profit @ 0.1 on (a+b+c+d+e)

6345.40

Cost for 15 cum = a+b+c+d+e+f

69799.44

Rate per cum = (a+b+c+d+e+f)/15


12.8

C
Case I

4653.30
say

4653.00

RCC Grade M20


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

5.21

5000.00

26050.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.86

151.44

130.24

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 4 per cent on (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3443.00
2065.49
10740.55
6444.33

Cost for 15 cum = a+b+c+d+e+f

70887.66

Rate per cum = ( a+b+c+d+e+f )/15

4725.84
say

Page 8 of 264

4726.00

Sr No
12.8 C

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Case II With Batching Plant, Transit Mixer and Concrete Pump


Unit : cum
Taking Output = 120 cum
a) Material

b)

c)

Cement

tonne

41.66

5000.00

208300.00

M-081

Coarse Sand

cum

54.00

828.00

44712.00

M-004

20 mm Aggregate

cum

64.80

1028.00

66614.40

M-053

10 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

Mate

day

0.84

151.44

127.21

Mason

day

3.00

223.36

670.08

L-11

Mazdoor

day

18.00

136.69

2460.42

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader 1 cum capacity

hour

6.00

806.00

4836.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

256.00

1536.00

P&M-050
Lead= 1
km
P&M-007

Labour

Machinery

Lead beyond 1 km, L-lead in km

Concrete Pump

hour

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)
f)

3388.00
16260.23
84553.21

Contractor's profit @ 0.1 on (a+b+c+d+e)

50731.93

Cost for 120 cum = a+b+c+d+e+f

558051.18

Rate per cum = ( a+b+c+d+e+f )/120


12.8

D
Case I

L-12

4650.43
say

4650.00

PCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

5.99

5000.00

29950.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

40 mm Aggregate

cum

5.40

916.00

4946.40

M-055

20 mm Aggregate

cum

5.40

1028.00

5551.20

M-053

10 mm Aggregate

cum

2.70

1005.00

2713.50

M-051

Mate

day

0.86

151.44

130.24

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.75 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3667.00
2062.30
11411.38
6846.83

Cost for 15 cum = a+b+c+d+e+f

75315.08

Rate per cum = ( a+b+c+d+e+f )/15

5021.01
say

12.8 D

Case II With Batching Plant, Transit Mixer and Concrete Pump


Unit : cum
Page 9 of 264

5021.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking Output = 120 cum


a)

b)

c)

Material
Cement

tonne

47.95

5000.00

239750.00

M-081

Coarse sand

cum

54.00

828.00

44712.00

M-004

40 mm Aggregate

cum

43.20

916.00

39571.20

M-055

20 mm Aggregate

cum

43.20

1028.00

44409.60

M-053

10 mm Aggregate

cum

21.60

1005.00

21708.00

M-051

Mate

day

0.84

151.44

127.21

Mason

day

3.00

223.36

670.08

L-11

Mazdoor

day

18.00

136.69

2460.42

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader 1 cum capacity

hour

6.00

806.00

4836.00

P&M-017

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

256.00

1536.00

P&M-050
Lead= 1
km
P&M-007

Labour

Machinery

Transit Mixer 4 cum capacity for lead upto 1 km.


Transit Mixer 4 cum capacity lead beyond 1 Km, L lead in Kilometer
Concrete Pump

hour

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d)
Formwork @ 3.75 per cent of cost of concrete i.e.
cost of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)
f)

3614.00
16260.53
89974.95

Contractor's profit @ 0.1 on (a+b+c+d+e)

53984.97

cost of 120 cum = a+b+c+d+e+f

593834.66

Rate per cum = (a+b+c+d+e+f)/120


12.8

E
Case I

L-12

4948.62
say

4949.00

RCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.05

5000.00

30250.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.86

151.44

130.24

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.75 per cent of a+b+c.
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3723.00
2093.90
11586.24
6951.74

cost of 15 cum = a+b+c+d+e+f

76469.16

Rate per cum (a+b+c+d+e+f )/15

5097.94
say

12.8 E

Case II With Batching Plant, Transit Mixer and Concrete Pump


Unit: cum
Taking Output = 120 cum
a)

Material

Page 10 of 264

5098.00

Sr No

Ref. to
MoRTH
Spec.

Description

b)

c)

Unit

Rate Rs

tonne

48.38

5000.00

241900.00

M-081

cum

54.00

828.00

44712.00

M-004

20 mm Aggregate

cum

64.80

1028.00

66614.40

M-053

10 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

Mate

day

0.84

151.44

127.21

Mason

day

3.00

223.36

670.08

L-11

Mazdoor

day

18.00

136.69

2460.42

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader 1 cum capacity 1 cum

hour

6.00

806.00

4836.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

P&M-050
Lead= 1
km

6.00

256.00

1536.00

P&M-007

Labour

hour

3668.00
16503.97
91321.96

Contractor's profit @ 0.1 on (a+b+c+d+e)

54793.17

cost of 120 cum = a+b+c+d+e+f

602724.91

Rate per cum (a+b+c+d+e+f )/120

Case I

L-12

Machinery

Concrete Pump

Remarks/
Input ref.

Coarse sand

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d)
Formwork @ 3.75 per cent on cost of concrete i.e.
cost of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)

12.8

Cost Rs

Cement

Transit Mixer 4 cum capacity lead beyond 1 Km, L lead in Kilometer

f)

Quantity

5022.71
say

5023.00

PCC Grade M30


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.08

5000.00

30400.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

40 mm Aggregate

cum

5.40

916.00

4946.40

M-055

20 mm Aggregate

cum

5.40

1028.00

5551.20

M-053

10 mm Aggregate

cum

2.70

1005.00

2713.50

M-051

Mate

day

0.86

151.44

130.24

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e.
cost of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)
f)

3697.00
1940.56
11477.03

Contractor's profit @ 0.1 on (a+b+c+d+e)

6886.22

cost of 15 cum = a+b+c+d+e+f

75748.39

Rate per cum (a+b+c+d+e+f )/15


12.8 F

5049.89
say

5050.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit : cum
Taking Output = 120 cum
a)

Material
Cement

tonne

48.60

5000.00

243000.00

M-081

Coarse sand

cum

54.00

828.00

44712.00

M-004

Page 11 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

b)

c)

Unit

Rate Rs

cum

43.20

916.00

39571.20

M-055

cum

43.20

1028.00

44409.60

M-053

10 mm Aggregate

cum

21.60

1005.00

21708.00

M-051

Mate

day

0.84

151.44

127.21

Mason

day

3.00

223.36

670.08

L-11

Mazdoor

day

18.00

136.69

2460.42

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader 1 cum capacity

hour

6.00

806.00

4836.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

P&M-050
Lead= 1
km

6.00

256.00

1536.00

P&M-007

Labour

hour

3641.00
15290.25
90430.89

Contractor's profit @ 0.1 on (a+b+c+d+e)

54258.53

cost of 120 cum = a+b+c+d+e+f

596843.88

Rate per cum (a+b+c+d+e+f )/120

Case I

L-12

Machinery

Concrete Pump

Remarks/
Input ref.

20 mm Aggregate

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e.
cost of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)

12.8

Cost Rs

40 mm Aggregate

Transit Mixer 4 cum capacity lead beyond 1 Km, L lead in Kilometer

f)

Quantity

4973.70
say

4974.00

RCC Grade M30


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.10

5000.00

30500.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.86

151.44

130.24

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e.
cost of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)
f)

3740.00
1963.05
11610.07

Contractor's profit @ 0.1 on (a+b+c+d+e)

6966.04

cost of 15 cum = a+b+c+d+e+f

76626.45

Rate per cum = (a+b+c+d+e+f)/15


12.8 G

Case II

5108.43
say

5108.00

Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
Cement

tonne

48.80

5000.00

244000.00

M-081

Coarse sand

cum

54.00

828.00

44712.00

M-004

20 mm Aggregate

cum

64.80

1028.00

66614.40

M-053

10 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

Page 12 of 264

Sr No

Ref. to
MoRTH
Spec.

Description
b)

c)

Unit

Rate Rs

day

0.84

151.44

127.21

Mason

day

3.00

223.36

670.08

L-11

Mazdoor

day

18.00

136.69

2460.42

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader 1 cum capacity

hour

6.00

806.00

4836.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

6.00

256.00

1536.00

P&M-050
Lead= 1
km
P&M-007

hour

3686.00
15477.20
91536.60

Contractor's profit @ 0.1 on (a+b+c+d+e)

54921.96

cost of 120 cum = a+b+c+d+e+f

604141.58

Rate per cum (a+b+c+d+e+f )/120

Case I

L-12

Machinery

Concrete Pump

Remarks/
Input ref.

Labour

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)

12.8

Cost Rs

Mate

Transit Mixer 4 cum capacity lead beyond 1 Km, L lead in Kilometer

f)

Quantity

5034.51
say

5035.00

RCC Grade M35


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.33

5000.00

31650.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.86

151.44

130.24

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3 per cent on a+b+c
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3816.00
1717.12
11790.88
7074.53

cost of 15 cum = a+b+c+d+e+f

77819.81

Rate per cum = (a+b+c+d+e+f)/15


12.8 H

5187.99
say

5188.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit ; cum
Taking Output = 120 cum
a)

b)

Material
Cement

tonne

50.64

5000.00

253200.00

M-081

Coarse sand

cum

54.00

828.00

44712.00

M-004

20 mm Aggregate

cum

64.80

1028.00

66614.40

M-053

10 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

Mate

day

0.84

151.44

127.21

L-12

Mason

day

3.00

223.36

670.08

L-11

Labour

Page 13 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor
c)

Rate Rs

Remarks/
Input ref.

day

18.00

136.69

2460.42

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader1 cum capacity

hour

6.00

806.00

4836.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

P&M-050
Lead= 1
km

6.00

256.00

1536.00

P&M-007

Concrete Pump

hour

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d)
Formwork @ 3 per cent on cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)

3762.00
13542.17
92989.60

Contractor's profit @ 0.1 on (a+b+c+d+e)

55793.76

cost of 120 cum = a+b+c+d+e+f

613731.34

Rate per cum = (a+b+c+d+e+f)/120


Note:

Cost Rs

Machinery

Transit Mixer 4 cum capacity lead beyond 1 Km, L lead in Kilometer

f)

Quantity

5114.43
say

5114.00

Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.

WELL FOUNDATION
12.9

1200

Providing and Constructing Temporary Island 16 m


diameter for Construction of Well Foundation for 8m dia.
Well.
Assuming depth of water 1.0 m and height of island to
be 1.25 m.
Unit = 1 No
Taking output = 1 No.
a)

b)

c)

Material
Earth (compacted)

cum

251.20

28.0

7033.60

M-092

Sand bags

each

750.00

7.00

5250.00

M-159

Labour
Mate

day

0.40

151.44

60.58

L-12

Mazdoor for filling sand bags, stitching and placing

day

15.00

136.69

2050.35

L-13

hour

20.00

853.00

17060.00

P&M-012

Machinery
Crane with grab 1 cum capacity

Consumables @ 2.5 per cent of (c) above


d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

426.50
6376.21
3825.72

Rate per No. (a+b+c+d+e)


Note
12.9

42082.95
say

42083.00

It is assumed that earth will be available within the working


space of crane with grab bucket.
Assuming depth of water 4.0 m and height of island 4.5
m.
Unit = 1No
Taking output = 1 No
a)

b)

Material
Earth (compacted)

cum

904.32

28.00

25320.96

M-092

Sand bags

each

6000.00

7.00

42000.00

M-159

Wooden ballies 8" Dia and 9 m long

each

95.00

91.00

8645.00

M-194

Wooden ballies 2" Dia for bracing

metre

190.00

61.00

11590.00

M-193

Labour
Mate

day

5.60

151.44

848.06

L-12

Mazdoor for piling 8" dia ballies for piling 8" dia ballies

day

18.00

136.69

2460.42

L-13

Mazdoor for bracing with 2" dia ballies

day

12.00

136.69

1640.28

L-13

Page 14 of 264

Sr No

Ref. to
MoRTH
Spec.
c)

Quantity

Rate Rs

Unit

Mazdoor for filling sand bags, stitching and placing

day

110.00

136.69

15035.90

L-13

hour

50.00

853.00

42650.00

P&M-012

Machinery
Crane with grab 1 cum capacity

Consumables and other arrangements for piling ballies @


2.5 per cent of (a+b+c).
d) Overhead charges @ 0.2 on (a+b+c)
e)

3754.77
30789.08

Contractor's profit @ 0.1 on (a+b+c+d)

18473.45

Rate per No. (a+b+c+d+e)


Note

12.9

Cost Rs

Remarks/
Input ref.

Description

203207.91
say

203208.00

For other well diameters rate can be worked out on the basis
of cross-sectional area of well. The diameter of the island
shall be in the conformity with clause 1203.2 of MoRTH
specifications.
Providing and constructing one span service road to
reach island location from one pier location to another
pier location
Assuming span length 30 m, width of service road 10m and
depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a)

b)

c)

Material
Earth

cum

450.00

28.00

12600.00

M-092

Sand bags

each

300.00

7.00

2100.00

M-159

Mate

day

0.24

151.44

36.35

L-12

Mazdoor for filling sand bags, stitching and placing

day

6.00

136.69

820.14

L-13

Front end Loader 1 cum capacity

hour

27.00

806.00

21762.00

P&M-017

Tipper 5.5 cum capacity

hour

28.00

339.00

9492.00

P&M-048

Labour

Machinery

d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

9362.10
5617.26

Cost for 30 m (a+b+c+d+e)

61789.84

Rate per m (a+b+c+d+e)/30


12.10

1200 &
1900

2059.66
say

2060.00

Providing and Laying Cutting Edge of Mild Steel


weighing 40 kg per metre for Well Foundation complete
as per Drawing and Technical Specification.
Unit = 1 MT
Taking output = 1 MT
a)

Material
Structural steel in plates, angles, etc including 5 per
cent wastage
Nuts & bolts

b)

tonne

1.05

45000.00

47250.00

M-179

Kg

20.00

64.07

1281.40

M-130

day

1.32

151.44

199.90

L-12

Fitter

day

5.50

230.00

1265.00

L-08

Blacksmith

day

5.50

264.50

1454.75

L-02

Welder

day

5.50

264.50

1454.75

L-02

Mazdoor

day

16.50

136.69

2255.39

L-13

Labour

(for cutting, bending, making holes, joining, welding and


erecting in position)
Mate

Electrodes, cutting gas and other consumables @ 10 per


cent of cost of (a) above
c) Overhead charges @ 0.2 on (a+b)
d)

4853.14
12002.87

Contractor's profit @ 0.1 on (a+b+c)

7201.72

Rate per MT (a+b+c+d)

79218.91
say

12.11

1200,
1500 &
1700

Plain/Reinforced Cement Concrete, in Well Foundation


complete as per Drawing and Technical Specification.

Page 15 of 264

79219.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Unit = 1 cum
Taking output = 1 cum
A

Well curb

(i)

RCC M20 Grade


Same as for 12.8 (C) except for formwork which shall be@
20 per cent of the cost of concrete instead of 4 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3443.00
688.60
826.32
495.79

Rate perm (a+b+c+d+e+f)

5453.71
say

12.11 A (i)

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete

3388.00
677.60

e)

Overhead charges @ 0.2 on (a+b+c+d)

813.12

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

487.87

Rate perm (a+b+c+d+e+f)

5366.59
say

12.11 A

5454.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

(ii)

5367.00

RCC M25 Grade


Same as for 12.8 (E) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.75 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3723.00
744.60
893.52
536.11

Rate perm (a+b+c+d+e+f)

5897.23
say

12.11 A
(ii)

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3740.00
748.00
897.60
538.56

Rate perm (a+b+c+d+e+f)

5924.16
say

12.11 A

5897.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

(iii)

5924.00

RCC M35 Grade


Same as for 12.8 (H) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.0 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3816.00
763.20
915.84
549.50

Rate perm (a+b+c+d+e+f)

6044.54
say

12.11 A
(iii)

6045.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Page 16 of 264

3838.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

d)

formwork @ 20 per cent of the cost of concrete

767.60

e)

Overhead charges @ 0.2 on (a+b+c+d)

921.12

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

552.67

Rate perm (a+b+c+d+e+f)

6079.39
say

Note.

12.11

Cost Rs

6079.00

If curb concrete is carried out within steel liner, cost of


formwork shall be excluded.

Well steining

(I)

PCC M15 Grade


Same as for 12.8 (A) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3080.00
308.00
677.60
406.56

Rate perm (a+b+c+d+e+f)

4472.16
say

12.11 B

(ii)

4472.00

PCC M20 Grade


Same as for 12.8 (B) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3390.00
339.00
745.80
447.48

Rate perm (a+b+c+d+e+f)

4922.28
say

12.11 B

(iii)

4922.00

RCC M20 Grade


Same as for 12.8 (C) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete

3443.00
344.30

e)

Overhead charges @ 0.2 on (a+b+c+d)

757.46

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

454.48

Rate perm (a+b+c+d+e+f)

4999.24
say

12.11 B
(iii)

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3388.00
338.80
745.36
447.22

Rate perm (a+b+c+d+e+f)

4919.38
say

12.11 B

4999.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

(iv)

4919.00

PCC M25 Grade


Same as for 12.8 (D) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Page 17 of 264

3667.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

d)

formwork @ 10 per cent of the cost of concrete

366.70

e)

Overhead charges @ 0.2 on (a+b+c+d)

806.74

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

484.04

Rate perm (a+b+c+d+e+f)

5324.48
say

12.11 B
(iv)

5324.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3614.00
361.40
795.08
477.05

Rate perm (a+b+c+d+e+f)

5247.53
say

'12.11 B

Cost Rs

(v)

5248.00

RCC M25 Grade


Same as for 12.8 (E) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3723.00
372.30
819.06
491.44

Rate perm (a+b+c+d+e+f)

5405.80
say

12.11 B
(v)

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3740.00
374.00
822.80
493.68

Rate perm (a+b+c+d+e+f)

5430.48
say

'12.11 B

5406.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

(vi)

5430.00

PCC M30 Grade


Same as for 12.8 (F) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3697.00
369.70
813.34
488.00

Rate perm (a+b+c+d+e+f)

5368.04
say

12.11 B
(vi)

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3641.00
364.10
801.02
480.61

Rate perm (a+b+c+d+e+f)

5286.73
say

'12.11 B

5368.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

(vii)

RCC M30 Grade


Same as for 12.8 (G) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I

Using Concrete Mixer


Page 18 of 264

5287.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

374.00
822.80
493.68
5430.48
say

5430.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3686.00
368.60
810.92
486.55

Rate perm (a+b+c+d+e+f)

5352.07
say

'12.11 B

Remarks/
Input ref.

3740.00

Rate perm (a+b+c+d+e+f)


12.11 B
(vii)

Cost Rs

(viii)

5352.00

RCC M35 Grade


Same as for 12.8 (H) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3816.00
381.60
839.52
503.71

Rate perm (a+b+c+d+e+f)

5540.83
say

12.11 B
(viii)

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3838.00
383.80
844.36
506.62

Rate perm (a+b+c+d+e+f)


'12.11 B

5541.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

(ix)

5572.78
say

5573.00

RCC M40 Grade


Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a)

Material
Cement

tonne

51.60

5000.00

258000.00

M-081

Coarse Sand

cum

54.00

828.00

44712.00

M-004

20 mm Aggregate

cum

64.80

1028.00

66614.40

M-053

10 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

kg

206.00

44.70

9208.20

M-180

Mate

day

0.84

151.44

127.21

L-12

Meson

day

3.00

223.36

670.08

L-11

Mazdoor

day

18.00

136.69

2460.42

L-13

Admixture
b)

c)

Labour

Machinery
Batching Plant

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader 1 cum capacity

hour

6.00

806.00

4836.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300xL

2.03

610.20

hour

6.00

256.00

1536.00

Lead= 1 ,
P&M-050
P&M-007

Transit Mixer 4 cum capacity for lead beyond 1 km.


Concrete Pump
Page 19 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 10 per cent on cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)
f)

Quantity

Rate Rs

46541.40
102391.08

Contractor's profit @ 0.1 on (a+b+c+d+e)

61434.65
675781.14

Rate per cum = (a+b+c+d+e+f)/120


C

Remarks/
Input ref.

31028.00

cost of 120 cum = a+b+c+d+e+f

12.11 C

Cost Rs

5631.51
say

5632.00

Bottom Plug
Concrete to be placed using tremie pipe

(i)
Case I

Note: 10% extra cement to be added where under water


concreting is involved
PCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

5.55

5000.00

27750.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

40 mm Aggregate

cum

5.40

916.00

4946.40

M-055

20 mm Aggregate

cum

5.40

1028.00

5551.20

M-053

10 mm Aggregate

cum

2.70

1005.00

2713.50

M-051

Admixture

Kg

18.60

44.70

831.42

M-180

Mate

day

0.90

151.44

136.30

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

Light Crane 3 tonnes capacity for handling tremie pipe

hour

6.00

357.00

2142.00

P&M-013

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..
d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3719.00
2489.66

11652.74
6991.65

cost of 15 cum = a+b+c+d+e

76908.12

Rate per cum = (a+b+c+d+e)/15


12.11 C
(i)

5127.21
say

5127.00

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit ; cum
Taking Output = 120 cum
a)

b)

c)

Material
Cement

tonne

44.40

5000.00

222000.00

M-081

Coarse sand

cum

54.00

828.00

44712.00

M-004

20 mm Aggregate

cum

64.80

1028.00

66614.40

M-053

10 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

Admixture

Kg

148.80

44.70

6651.36

M-180

Mate

day

0.88

151.44

133.27

L-12

Mason

day

3.00

223.36

670.08

L-11

Mazdoor

day

18.00

136.69

2460.42

L-13

Labour

Machinery
Page 20 of 264

Sr No

Ref. to
MoRTH
Spec.

Unit

Batching Plant @ 20 cum/hour

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader 1 cum capacity

hour

6.00

806.00

4836.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

6.00

256.00

1536.00

P&M-050
Lead= 1
km
P&M-007

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer


Concrete Pump

hour

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..
d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Quantity

Rate Rs

3558.00
19332.88

89239.22
53543.53

cost of 120 cum = a+b+c+d+e

588978.86

Rate per cum = (a+b+c+d+e)/120


'12.11 C

(ii)
Case I

Cost Rs

Remarks/
Input ref.

Description

4908.16
say

4908.00

PCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

5.99

5000.00

29950.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

40 mm Aggregate

cum

5.40

916.00

4946.40

M-055

20 mm Aggregate

cum

5.40

1028.00

5551.20

M-053

10 mm Aggregate

cum

2.70

1005.00

2713.50

M-051

Admixture

Kg

21.60

44.70

965.52

M-180

Mate

day

0.90

151.44

136.30

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

hour

6.00

357.00

2142.00

P&M-013

Labour

Machinery

Light Crane of 3 tonnes capacity for handling tremie


pipe
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Add 5 per cent of cost of material and labour towards cost
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..
d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3874.00
2606.37

12142.91
7285.74

cost of 15 cum = a+b+c+d+e

80143.18

Rate per cum = (a+b+c+d+e)/15


12.11 C
(ii)

5342.88
say

5343.00

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit = cum
Taking output = 120 cum
a)

Material
Cement

tonne

47.88

5000.00

239400.00

M-081

Coarse sand

cum

54.00

828.00

44712.00

M-004

20 mm Aggregate

cum

64.80

1028.00

66614.40

M-053

10 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

Admixture

Kg

172.80

44.70

7724.16

M-180

Page 21 of 264

Sr No

Ref. to
MoRTH
Spec.

Description
b)

c)

Unit

Quantity

Rate Rs

Labour
day

0.88

151.44

133.27

Mason

day

3.00

223.36

670.08

L-11

Mazdoor

day

18.00

136.69

2460.42

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader 1 cum capacity

hour

6.00

806.00

4836.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

6.00

256.00

1536.00

P&M-050
Lead= 1
km
P&M-007

Concrete Pump

hour

d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3712.00
20256.52

93118.51
55871.11

cost of 120 cum = a+b+c+d+e

614582.16

Rate per cum = (a+b+c+d+e)/120

Case I

L-12

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

(iii)

Remarks/
Input ref.

Mate

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer

'12.11 C

Cost Rs

5121.52
say

5122.00

PCC Grade M30


Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.08

5000.00

30400.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

40 mm Aggregate

cum

5.40

916.00

4946.40

M-055

20 mm Aggregate

cum

5.40

1028.00

5551.20

M-053

10 mm Aggregate

cum

2.70

1005.00

2713.50

M-051

Admixture

Kg

21.60

44.70

965.52

M-180

Mate

day

0.90

151.44

136.30

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

hour

6.00

357.00

2142.00

P&M-013

Labour

Machinery

Light Crane of 3 tonnes capacity for handling tremie


pipe
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Add 5 per cent of cost of material and labour towards cost
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..
d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3904.00
2628.87

12237.41
7342.44

cost of 15 cum = a+b+c+d+e

80766.88

Rate per cum = (a+b+c+d+e)/15

5384.46
say

12.11 C
(iii)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit = cum
Taking output = 120 cum
a)

Material
Page 22 of 264

5384.00

Sr No

Ref. to
MoRTH
Spec.

Description

b)

c)

Unit

Quantity

Rate Rs

tonne

48.64

5000.00

243200.00

M-081

Coarse sand

cum

54.00

828.00

44712.00

M-004

20 mm Aggregate

cum

64.80

1028.00

66614.40

M-053

10 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

Admixture

Kg

172.80

44.70

7724.16

M-180

Mate

day

0.88

151.44

133.27

L-12

Mason

day

3.00

223.36

670.08

L-11

Mazdoor

day

18.00

136.69

2460.42

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader 1 cum capacity

hour

6.00

806.00

4836.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

P&M-050
Lead= 1
km

6.00

256.00

1536.00

P&M-007

Labour

Machinery

Concrete Pump

hour

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..
d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3743.00
20446.52

93916.51
56349.91

cost of 120 cum = a+b+c+d+e

619848.96

Rate per cum = (a+b+c+d+e)/120


(iv)
Case I

Remarks/
Input ref.

Cement

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer

'12.11 C

Cost Rs

5165.41
say

5165.00

PCC Grade M35


Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.29

5000.00

31450.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

40 mm Aggregate

cum

5.40

916.00

4946.40

M-055

20 mm Aggregate

cum

5.40

1028.00

5551.20

M-053

10 mm Aggregate

cum

2.70

1005.00

2713.50

M-051

Admixture

Kg

21.60

44.70

965.52

M-180

Mate

day

0.90

151.44

136.30

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

hour

6.00

357.00

2142.00

P&M-013

Labour

Machinery

Light Crane of 3 tonnes capacity for handling tremie


pipe
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Add 5 per cent of cost of material and labour towards cost
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..
d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

cost of 15 cum = a+b+c+d+e

3974.00
2681.37

12457.91
7474.74
82222.18

Rate per cum = (a+b+c+d+e)/15

5481.48

Page 23 of 264

Sr No

12.11 C
(iv)

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

say

5481.00

Remarks/
Input ref.

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

50.28

5000.00

251400.00

M-081

Coarse sand

cum

54.00

828.00

44712.00

M-004

20 mm Aggregate

cum

64.80

1028.00

66614.40

M-053

10 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

Admixture

Kg

172.80

44.70

7724.16

M-180

Mate

day

0.88

151.44

133.27

L-12

Mason

day

3.00

223.36

670.08

L-11

Mazdoor

day

18.00

136.69

2460.42

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader 1 cum capacity

hour

6.00

806.00

4836.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

P&M-050
Lead= 1
km

6.00

256.00

1536.00

P&M-007

Labour

Machinery

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer


Concrete Pump

hour

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..
d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3812.00
20856.52

95638.51
57383.11

cost of 120 cum = a+b+c+d+e

631214.16

Rate per cum = (a+b+c+d+e)/120

5260.12
say

12.11

Intermediate plug

(i)

Grade M20 PCC

Case I

Same as in bottom plug concrete, excluding cost of forming


sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

3719.00
743.80

Contractor's profit @ 0.1 on (a+b+c+d)

446.28

Rate per cum = (a+b+c+d+e)

4909.08
say

12.11 D
(i)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

711.60

Contractor's profit @ 0.1 on (a+b+c+d)

426.96
4696.56
say

(ii)

Case I

4909.00

3558.00

Rate per cum = (a+b+c+d+e)


'12.11 D

5260.00

4697.00

Grade M25 PCC


Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
Page 24 of 264

3874.00
774.80

Sr No

Ref. to
MoRTH
Spec.

Description
e)

Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c+d)

464.88

Rate per cum = (a+b+c+d+e)

5113.68
say

12.11 D
(ii)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

742.40

Contractor's profit @ 0.1 on (a+b+c+d)

445.44
4899.84
say

(iii)

Case I

Same as in bottom plug concrete, excluding cost of forming


sump, protective bunds, chiseling etc.
Using Concrete Mixer

e)

3904.00
780.80

Contractor's profit @ 0.1 on (a+b+c+d)

468.48

Rate per cum = (a+b+c+d+e)

5153.28
say

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

748.60

Contractor's profit @ 0.1 on (a+b+c+d)

449.16
4940.76
say

Top plug

(i)

Grade M15 PCC

5153.00

3743.00

Rate per cum = (a+b+c+d+e)


12.11

4900.00

Grade M30 PCC

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)

12.11 D
(iii)

5114.00

3712.00

Rate per cum = (a+b+c+d+e)


'12.11 D

Cost Rs

4941.00

Same as Item 12.8(a) excluding formwork


Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

3080.00
616.00

Contractor's profit @ 0.1 on (a+b+c+d)

369.60

Rate per cum = (a+b+c+d+e)

4065.60
say

'12.11 E

(ii)

4066.00

Grade M20 PCC


Same as Item 12.8(b) excluding formwork

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

3390.00
678.00

Contractor's profit @ 0.1 on (a+b+c+d)

406.80

Rate per cum = (a+b+c+d+e)

4474.80
say

'12.11 E

(iii)

Same as Item 12.8 (d)


Case I

excluding formwork

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

3667.00
733.40

Contractor's profit @ 0.1 on (a+b+c+d)

440.04

Rate per cum = (a+b+c+d+e)

4840.44
say

12.11 E
(iii)

4475.00

Grade M25 PCC

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump

Page 25 of 264

4840.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

722.80

Contractor's profit @ 0.1 on (a+b+c+d)

433.68
4770.48
say

(iv)

Remarks/
Input ref.

3614.00

Rate per cum = (a+b+c+d+e)


'12.11 E

Cost Rs

4770.00

Grade M30 PCC


Same as Item 12.8(f) excluding formwork

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

3697.00
739.40

Contractor's profit @ 0.1 on (a+b+c+d)

443.64

Rate per cum = (a+b+c+d+e)

4880.04
say

12.11 E
(iv)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

3641.00
728.20

Contractor's profit @ 0.1 on (a+b+c+d)

436.92

Rate per cum = (a+b+c+d+e)


12.11

F
(i)
Case I

4880.00

4806.12
say

4806.00

Well cap
RCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

5.12

5000.00

25600.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.86

151.44

130.24

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

Labour

Machinery

Form Work @ 4 per cent of a+b+c


d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2047.49
10646.95
6388.17

cost of 15 cum = a+b+c+d+e

70269.90

Rate per cum = (a+b+c+d+e)/15


12.11 F (i)

4684.66
say

4685.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

Material
Cement

tonne

40.92

5000.00

204600.00

M-081

Coarse sand

cum

54.00

828.00

44712.00

M-004

20 mm Aggregate

cum

64.80

1028.00

66614.40

M-053

10 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

Mate

day

0.84

151.44

127.21

L-12

Mason

day

3.00

223.36

670.08

L-11

Labour

Page 26 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor
c)

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

day

18.00

136.69

2460.42

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader (capacity 1 cum)

hour

6.00

806.00

4836.00

P&M-017

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

P&M-050
Lead= 1
km

hour

6.00

256.00

1536.00

P&M-007

Formwork @ 4 per cent of (a+b+c)

16112.23

d)

Overhead charges @ 0.2 on (a+b+c)

83783.61

e)

Contractor's profit @ 0.1 on (a+b+c+d)

50270.17

cost of 120 cum = a+b+c+d+e

552971.82

Rate per cum = (a+b+c+d+e)/120


12.11 F

(ii)
Case I

4608.10
say

4608.00

RCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.05

5000.00

30250.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.86

151.44

130.24

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

Labour

Machinery

Form Work @ 3.75 per cent of a+b+c

2093.90

d)

Overhead charges @ 0.2 on (a+b+c)

11586.24

e)

Contractor's profit @ 0.1 on (a+b+c+d)

6951.74

cost of 15 cum = a+b+c+d+e

76469.16

Rate per cum = (a+b+c+d+e)/15


12.11 F
(ii)

5097.94
say

5098.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

48.40

5000.00

242000.00

M-081

Coarse sand

cum

54.00

828.00

44712.00

M-004

20 mm Aggregate

cum

64.80

1028.00

66614.40

M-053

10 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

Mate

day

0.84

151.44

127.21

Mason

day

3.00

223.36

670.08

L-11

Mazdoor

day

18.00

136.69

2460.42

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader (capacity 1 cum)

hour

6.00

806.00

4836.00

P&M-017

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Page 27 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Transit Mixer 4 cum capacity for lead upto 1 km.


Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

Quantity

Rate Rs

hour

15.00

1017.00

15255.00

P&M-049

300L

2.03

610.20

P&M-050
Lead= 1
km

hour

6.00

256.00

1536.00

P&M-007

Formwork @ 3.75 per cent of ( a+b+c)

16507.72

d)

Overhead charges @ 0.2 on (a+b+c)

91342.71

e)

Contractor's profit @ 0.1 on (a+b+c+d)

54805.62
602861.86

Rate per cum = (a+b+c+d+e)/120


(iii)
Case I

Remarks/
Input ref.

tonne.km

cost of 120 cum = a+b+c+d+e

12.11 F

Cost Rs

5023.85
say

5024.00

RCC Grade M30


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.10

5000.00

30500.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.86

151.44

130.24

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

Labour

Machinery

Formwork @ 3.5 per cent of (a+b+c)

1963.05

d)

Overhead charges @ 0.2 on (a+b+c)

11610.07

e)

Contractor's profit @ 0.1 on (a+b+c+d)

6966.04

cost of 15 cum = a+b+c+d+e

76626.45

Rate per cum = (a+b+c+d+e)/15


12.11 F
(iii)

5108.43
say

5108.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

48.79

5000.00

243950.00

M-081

Coarse sand

cum

54.00

828.00

44712.00

M-004

20 mm Aggregate

cum

64.80

1028.00

66614.40

M-053

10 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

Mate

day

0.84

151.44

127.21

Mason

day

3.00

223.36

670.08

L-11

Mazdoor

day

18.00

136.69

2460.42

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader (capacity 1 cum)

hour

6.00

806.00

4836.00

P&M-017

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump
d)

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

P&M-050
Lead= 1
km

hour

6.00

256.00

1536.00

P&M-007

Formwork @ 3.5 per cent of (a+b+c)

15475.45

Overhead charges @ 0.2 on (a+b+c)

91526.25

Page 28 of 264

Sr No

Ref. to
MoRTH
Spec.

Description
e)

Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c+d)

604073.27

Rate per cum = (a+b+c+d+e)/120


(iv)
Case I

Remarks/
Input ref.

54915.75

cost of 120 cum = a+b+c+d+e

12.11 F

Cost Rs

5033.94
say

5034.00

RCC Grade M35


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.33

5000.00

31650.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.86

151.44

130.24

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

Labour

Machinery

Formwork @ 3 per cent of (a+b+c)


d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1717.12
11790.88
7074.53

cost of 15 cum = a+b+c+d+e

77819.81

Rate per cum = (a+b+c+d+e)/15


12.11 F
(iv)

5187.99
say

5188.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

50.64

5000.00

253200.00

M-081

Coarse sand

cum

54.00

828.00

44712.00

M-004

20 mm Aggregate

cum

64.80

1028.00

66614.40

M-053

10 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

Mate

day

0.84

151.44

127.21

Mason

day

3.00

223.36

670.08

L-11

Mazdoor

day

18.00

136.69

2460.42

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader (capacity 1 cum)

hour

6.00

806.00

4836.00

P&M-017

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

P&M-050
Lead= 1
km

hour

6.00

256.00

1536.00

P&M-007

Formwork @ 3 per cent of (a+b+c)

13542.17

d)

Overhead charges @ 0.2 on (a+b+c)

92989.60

e)

Contractor's profit @ 0.1 on (a+b+c+d)

55793.76

cost of 120 cum = a+b+c+d+e

613731.34

Rate per cum = (a+b+c+d+e)/120

5114.43
say

Page 29 of 264

5114.00

Sr No

Ref. to
MoRTH
Spec.

Description
Note

'12.11 F

(v)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a)

Material
Cement

tonne

52.20

5000.00

261000.00

M-081

Coarse Sand

cum

54.00

828.00

44712.00

M-004

20 mm Aggregate

cum

64.80

1028.00

66614.40

M-053

10 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

kg

206.00

44.70

9208.20

M-180

Mate

day

0.84

151.44

127.21

L-12

Mason

day

3.00

223.36

670.08

L-11

Mazdoor

day

18.00

136.69

2460.42

L-13

Admixture
b)

c)

Labour

Machinery
Batching Plant

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader 1 cum capacity

hour

6.00

806.00

4836.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300.L

2.03

610.20

hour

6.00

256.00

P&M-050
Lead= 1
km
P&M-007

Transit Mixer 4 cum capacity for lead beyond 1 km.

Concrete Pump

d)

Formwork @ 3 per cent on cost of concrete i.e. cost of


material, labour and machinery
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

96493.29
57895.97

cost of 120 cum = a+b+c+d+e

636855.69

Rate per cum = (a+b+c+d+e)/120

5307.13
say

12.12

Section
1200

1536.00
14052.42

5307.00

Sinking of 6 m external diameter well (other than


pneumatic method of sinking) through all types of strata
namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 6 m.
A
(i)

Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking = 0.50 m per hour.
a)

b)

Labour
Mate

day

0.12

151.44

18.17

L-12

Sinker ( skilled )

day

1.00

164.69

164.69

L-15

Sinking helper ( semi-skilled )

day

2.00

230.00

460.00

L-14

hour

2.00

1073.50

2147.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

214.70
600.91
360.55

Rate per metre = (a+b+c+d)

3966.02
say

12.12 A

(ii)

Beyond 3m upto 10m depth


Page 30 of 264

3966.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Rate of sinking = 0.33 m per hour.


a)

b)

Labour
Mate

day

0.15

151.44

22.72

L-12

Sinker

day

1.25

164.69

205.86

L-15

Sinking helper ( semi-skilled )

day

2.50

230.00

575.00

L-14

hour

3.00

1073.50

3220.50

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

322.05
869.23
521.54

Rate per metre = (a+b+c+d)

5736.89
say

12.12 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

6024.00

12th m

5%

6325.00

13th m

5%

6641.00

14th m

5%

6973.00

15th m

5%

7322.00

16th m

5%

7688.00

17th m

5%

8072.00

18th m

5%

8476.00

19th m

5%

8900.00

20th m

5%

9345.00

Total Cost from 10m upto 20m

75766.00

Avg Rate per metre


12.12 A

(iv)
a
b

7577.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
21st m

7.5%

10046.00

Including 20%
for Kentledge
12055.00

22nd m

7.5%

10799.00

12959.00

23rd m

7.5%

11609.00

13931.00

24th m

7.5%

12480.00

14976.00

25th m

7.5%

13416.00

16099.00

26th m

7.5%

14422.00

17306.00

27th m

7.5%

15504.00

18605.00

28th m

7.5%

16667.00

20000.00

29th m

7.5%

17917.00

21500.00

30th m

7.5%

19261.00

23113.00

142121.00

170544.00

14212.00

17054.00

Total Cost from 20m upto 30m


Avg Rate per metre
12.12 A

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
31st m

10%

21187.00

Including 20%
for Kentledge
25424.00

32nd

10%

23306.00

27967.00

33rd m

10%

25637.00

30764.00

34th m

10%

28201.00

33841.00

35th m

10%

31021.00

37225.00

36th m

10%

34123.00

40948.00

37th m

10%

37535.00

45042.00

38th m

10%

41289.00

49547.00

39th m

10%

45418.00

54502.00

Page 31 of 264

5737.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

40th m

10%

Total Cost from 30m upto 40m


Avg Rate per metre
12.12

Quantity

Rate Rs

49960.00

59952.00

337677.00

405212.00

33768.00

40521.00

Cost Rs

Remarks/
Input ref.

Clayey Soil ( 6m dia. Well )


Unit = Running Meter.
Taking output = 1 meter

(i)

Depth below bed level upto 3.0 M


Rate of sinking = 0.33 m per hour.
a)

b)

Labour
Mate

day

0.15

151.44

22.72

L-12

Sinker ( skilled )

day

1.50

164.69

247.04

L-15

Sinking helper ( semi-skilled )

day

2.25

230.00

517.50

L-14

hour

3.00

1073.50

3220.50

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

322.05
865.96
519.58

Rate per metre = (a+b+c+d)

5715.34
say

12.12 B

(ii)

5715.00

Beyond 3m upto 10m depth


Rate of sinking = 0.17 m per hour.
a)

b)

Labour
Mate

day

0.30

151.44

45.43

L-12

Sinker

day

3.00

164.69

494.07

L-15

Sinking helper ( semi-skilled )

day

4.50

230.00

1035.00

L-14

hour

6.00

1073.50

6441.00

P&M-075

hour

2.00

740.15

1480.30

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

792.13
2057.59
1234.55

Rate per metre = (a+b+c+d)

13580.07
say

12.12 B

(iii)
a
b

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

11th m

5%

14259.00

14972.00

12th m

5%

14972.00

15721.00

13th m

5%

15721.00

16507.00

14th m

5%

16507.00

17332.00

15th m

5%

17332.00

18199.00

16th m

5%

18199.00

19109.00

17th m

5%

19109.00

20064.00

18th m

5%

20064.00

21067.00

19th m

5%

21067.00

22120.00

20th m

5%

22120.00

23226.00

179350.00

188317.00

17935.00

18832.00

Total Cost from 10m upto 20m


Avg Rate per metre
12.12 B

(iv)
a

Including for
dewatering @
5% of cost, if
required

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Page 32 of 264

13580.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Add 5 per cent of cost for dewatering of the cost, if required

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

7.5%

23779.00

29724.00

31210.00

22nd m

7.5%

25562.00

31953.00

33551.00

23rd m

7.5%

27479.00

34349.00

36066.00

24th m

7.5%

29540.00

36925.00

38771.00

25th m

7.5%

31756.00

39695.00

41680.00

26th m

7.5%

34138.00

42673.00

44807.00

27th m

7.5%

36698.00

45873.00

48167.00

28th m

7.5%

39450.00

49313.00

51779.00

29th m

7.5%

42409.00

53011.00

55662.00

30th m

7.5%

45590.00

56988.00

59837.00

336401.00

420504.00

441530.00

33640.00

42050.00

44153.00

Avg Rate per metre


Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

31st m

10%

50149.00

60179.00

63188.00

32nd

10%

55164.00

66197.00

69507.00

33rd m

10%

60680.00

72816.00

76457.00

34th m

10%

66748.00

80098.00

84103.00

35th m

10%

73423.00

88108.00

92513.00

36th m

10%

80765.00

96918.00

101764.00

37th m

10%

88842.00

106610.00

111941.00

38th m

10%

97726.00

117271.00

123135.00

39th m

10%

107499.00

128999.00

135449.00

40th m

10%

118249.00

141899.00

148994.00

799245.00

959095.00

1007051.00

79925.00

95910.00

100705.00

Avg Rate per metre


C

Remarks/
Input ref.

Including 20% Including 5%


for Kentledge
for
dewatering, if
required

Total Cost from 30m upto 40m


12.12

Cost Rs

21st m

(v)

Rate Rs

Including 25% Including 5%


for Kentledge
for
dewatering, if
required

Total Cost from 20m upto 30m


12.12 B

Quantity

Soft Rock (6m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
a)

b)

Labour
Mate

day

0.92

151.44

139.32

L-12

Sinker ( skilled )

day

3.00

164.69

494.07

L-15

Sinking helper ( semi-skilled )

day

20.00

230.00

4600.00

L-14

Diver

day

0.50

264.50

132.25

L-07

hour

4.00

1073.50

4294.00

P&M-075

hour

3.50

740.15

2590.53

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)

688.45
646.93

c)

Add for dewatering @ of 5 per cent of (a+b), if


required
Overhead charges @ 0.2 on (a+b)

2717.11

d)

Contractor's profit @ 0.1 on (a+b+c)

1630.27

Rate per metre = (a+b+c+d)

17932.93
say
Page 33 of 264

17933.00

Sr No

Ref. to
MoRTH
Spec.

12.12

Description
D

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Hard Rock (6m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a)

b)

c)

Material
Gelatine 80 per cent

Kg

4.00

146.00

Electric Detonators

each

18.00

14.56

Mate

day

1.56

151.44

236.25

L-12

Driller

day

2.00

264.50

529.00

L-06

Blaster

day

0.25

264.50

66.13

L-03

Mazdoor

day

12.00

136.69

1640.28

L-13

Mazdoor (Skilled)

day

4.00

164.69

658.76

L-15

hour

6.00

1073.50

6441.00

P&M-075

hour

2.00

740.15

1480.30

P&M-063

Machinery

552.59

Consumables in sinking @ 10 per cent of cost of (b).


d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

792.13
2648.50
1589.10

Rate per metre = (a+b+c+d+e)

17480.11
say

Section
1200

M-104

262.08 M-094/100

Labour

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.

12.13

584.00

17480.00

Sinking of 7 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 7 m.
A
(i)

Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking = 0.30 m per hour.
a)

b)

Labour
Mate

day

0.15

151.44

22.72

L-12

Sinker ( skilled )

day

1.25

164.69

205.86

L-15

Sinking helper ( semi-skilled )

day

2.50

230.00

575.00

L-14

hour

3.25

1073.50

3488.88

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

348.89

c)

Overhead charges @ 0.2 on (a+b)

928.27

d)

Contractor's profit @ 0.1 on (a+b+c)

464.13

Rate per metre = (a+b+c+d)


12.13 A

(ii)

6033.74

Beyond 3m upto 10m depth

12067.49

Rate of sinking = 0.22 m per hour.


a)

b)

say

Mate

day

0.18

151.44

27.26

L-12

Sinker

day

1.50

164.69

247.04

L-15

Sinking helper ( semi-skilled )

day

3.00

230.00

690.00

L-14

hour

4.50

1073.50

4830.75

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

12067.00

Labour

Overhead charges @ 0.2 on (a+b)


Page 34 of 264

483.08
1255.62

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c)

753.37

Rate per metre = (a+b+c+d)

8287.12
say

12.13 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

0.165

5%

8701.00

12th m

5%

9136.00

13th m

5%

9593.00

14th m

5%

10073.00

15th m

5%

10577.00

16th m

5%

11106.00

17th m

5%

11661.00

18th m

5%

12244.00

19th m

5%

12856.00

20th m

5%

Total Cost from 10m upto 20m


(iv)
a
b

10945.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).
21st m

7.5%

14511.00

Including 20%
for Kentledge
17413.00

22nd m

7.5%

15599.00

18719.00

23rd m

7.5%

16769.00

20123.00

24th m

7.5%

18027.00

21632.00

25th m

7.5%

19379.00

23255.00

26th m

7.5%

20832.00

24998.00

27th m

7.5%

22394.00

26873.00

28th m

7.5%

24074.00

28889.00

29th m

7.5%

25880.00

31056.00

30th m

7.5%

27821.00

33385.00

205286.00

246343.00

20529.00

24634.00

Total Cost from 20m upto 30m


Avg Rate per metre
12.13 A

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
31st m

10%

30603.00

Including 20%
for Kentledge
36724.00

32nd

10%

33663.00

40396.00

33rd m

10%

37029.00

44435.00

34th m

10%

40732.00

48878.00

35th m

10%

44805.00

53766.00

36th m

10%

49286.00

59143.00

37th m

10%

54215.00

65058.00

38th m

10%

59637.00

71564.00

39th m

10%

65601.00

78721.00

40th m

10%

72161.00

86593.00

487732.00

585278.00

48773.00

58528.00

Total Cost from 30m upto 40m


Avg Rate per metre
12.13

Clayey Soil ( 7m dia. Well )


Unit = Running Meter.
Taking output = 1 cum

(I)

13499.00
109446.00

Avg Rate per metre


12.13 A

Depth below bed level upto 3.0 M


Rate of sinking = 0.22 m per hour.
a)

Cost Rs

Labour
Page 35 of 264

8287.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

day

0.18

151.44

27.26

L-12

Sinker ( skilled )

day

1.50

164.69

247.04

L-15

Sinking helper ( semi-skilled )

day

3.00

230.00

690.00

L-14

hour

4.50

1073.50

4830.75

P&M-075

Machinery

d)

Overhead charges @ 0.2 on (a+b)

e)

Contractor's profit @ 0.1 on (a+b+c)

483.08
1255.62
753.37

Rate per metre = (a+b+c+d)

8287.12
say

(ii)

Remarks/
Input ref.

Mate

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

12.13 B

Cost Rs

8287.00

Beyond 3m upto 10m depth


Rate of sinking = 0.17 m per hour.
a)

b)

Labour
Mate

day

0.26

151.44

39.37

L-12

Sinker

day

2.00

164.69

329.38

L-15

Sinking helper ( semi-skilled )

day

4.00

230.00

920.00

L-14

hour

6.00

1073.50

6441.00

P&M-075

hour

3.25

740.15

644.10

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

708.51
1816.47
1089.88

Rate per metre = (a+b+c+d)

11988.72
say

12.13 B

(iii)
a
b

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

Including for
dewatering @
5% of cost, if
required

11th m

5%

12588.00

13217.00

12th m

5%

13217.00

13878.00

13th m

5%

13878.00

14572.00

14th m

5%

14572.00

15301.00

15th m

5%

15301.00

16066.00

16th m

5%

16066.00

16869.00

17th m

5%

16869.00

17712.00

18th m

5%

17712.00

18598.00

19th m

5%

18598.00

19528.00

20th m

5%

19528.00

20504.00

158329.00

166245.00

15833.00

16625.00

Total Cost from 10m upto 20m


Avg Rate per metre
12.13 B

(iv)
a
b
c

11989.00

Beyond 10 m upto 20 m

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).

Including 25% Including 5%


for Kentledge
for
dewatering, if
required

31st m

7.5%

20993.00

26241.00

27553.00

32nd

7.5%

22567.00

28209.00

29619.00

33rd m

7.5%

24260.00

30325.00

31841.00

34th m

7.5%

26080.00

32600.00

34230.00

35th m

7.5%

28036.00

35045.00

36797.00

Page 36 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
7.5%

30139.00

37674.00

39558.00

7.5%

32399.00

40499.00

42524.00

38th m

7.5%

34829.00

43536.00

45713.00

39th m

7.5%

37441.00

46801.00

49141.00

40th m

7.5%

40249.00

50311.00

52827.00

296993.00

371241.00

389803.00

29699.00

37124.00

38980.00

Avg Rate per metre


Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

31st m

10%

44274.00

53129.00

55785.00

32nd

10%

48701.00

58441.00

61363.00

33rd m

10%

53571.00

64285.00

67499.00

34th m

10%

58928.00

70714.00

74250.00

35th m

10%

64821.00

77785.00

81674.00

36th m

10%

71303.00

85564.00

89842.00

37th m

10%

78433.00

94120.00

98826.00

38th m

10%

86276.00

103531.00

108708.00

39th m

10%

94904.00

113885.00

119579.00

40th m

10%

104394.00

125273.00

131537.00

705605.00

846727.00

889063.00

70561.00

84673.00

88906.00

Avg Rate per metre


C

Remarks/
Input ref.

Including 20% Including 5%


for Kentledge
for
dewatering, if
required

Total Cost from 30m upto 40m


12.13

Cost Rs

37th m

(v)

Rate Rs

36th m

Total Cost from 30m upto 40m


12.13 B

Quantity

Soft Rock ( 7m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a)

b)

Labour
Mate

day

0.58

151.44

87.84

L-12

Sinker ( skilled )

day

4.00

164.69

658.76

L-15

Sinking helper ( semi-skilled )

day

10.00

230.00

2300.00

L-14

Diver

day

0.75

264.50

198.38

L-07

hour

4.50

1073.50

4830.75

P&M-075

hour

3.75

740.15

2775.56

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)

760.63
542.56

c)

Add for dewatering @ of 5 per cent of (a+b), if


required
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2430.90
1458.54

Rate per metre = (a+b+c+d)


12.13

16043.91
say

16044.00

1022.00

Hard Rock ( 7m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a)

b)

Material
Gelatine 80 per cent

Kg

7.00

146.00

Electric Detonators

each

30.00

14.56

day

1.60

151.44

M-104

436.80 M-094/100

Labour
Mate
Page 37 of 264

242.30

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Quantity

Rate Rs

day

2.00

264.50

529.00

L-06

Blaster

day

0.25

264.50

66.13

L-03

Mazdoor

day

18.00

136.69

2460.42

L-13

Mazdoor (Skilled)

day

4.00

164.69

658.76

L-15

Diver

day

0.50

264.50

132.25

L-07

hour

6.00

1073.50

6441.00

P&M-075

hour

2.00

740.15

1480.30

P&M-063

Machinery

600.51

Consumables in sinking @ 10 per cent of cost of (b).


d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

852.18
2984.33
1790.60

Rate per metre = (a+b+c+d+e)

19696.58
say

Section
1200

Remarks/
Input ref.

Driller

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.

12.14

Cost Rs

19697.00

Sinking of 8 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 8 m.
A
(i)

Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a)

b)

Labour
Mate

day

0.18

151.44

27.26

L-12

Sinker ( skilled )

day

1.50

164.69

247.04

L-15

Sinking helper ( semi-skilled )

day

3.00

230.00

690.00

L-14

hour

4.00

1073.50

4294.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

429.40
1137.54
682.52

Rate per metre = (a+b+c+d)

7507.76
say

12.14 A

(ii)

7508.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.20 m/hour
a)

b)

Labour
Mate

day

0.25

151.44

37.86

L-12

Sinker

day

1.75

164.69

288.21

L-15

Sinking helper ( semi-skilled )

day

3.50

230.00

805.00

L-14

hour

5.00

1073.50

5367.50

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

536.75
1407.06
844.24

Rate per metre = (a+b+c+d)

9286.62
say

12.14 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m
12th m
Page 38 of 264

5%

9751.00

5%

10239.00

9287.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

13th m

5%

10751.00

14th m

5%

11289.00

15th m

5%

11853.00

16th m

5%

12446.00

17th m

5%

13068.00

18th m

5%

13721.00

19th m

5%

14407.00

20th m

5%

Total Cost from 10m upto 20m


(iv)
a
b

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
21st m

7.5%

16262.00

22nd m

7.5%

17482.00

20978.00

23rd m

7.5%

18793.00

22552.00

24th m

7.5%

20202.00

24242.00

25th m

7.5%

21717.00

26060.00

26th m

7.5%

23346.00

28015.00

27th m

7.5%

25097.00

30116.00

28th m

7.5%

26979.00

32375.00

29th m

7.5%

29002.00

34802.00

30th m

7.5%

31177.00

37412.00

230057.00

276066.00

23006.00

27607.00

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
31st m

10%

34295.00

Including 20%
for Kentledge
41154.00

32nd

10%

37725.00

45270.00

33rd m

10%

41498.00

49798.00

34th m

10%

45648.00

54778.00

35th m

10%

50213.00

60256.00

36th m

10%

55234.00

66281.00

37th m

10%

60757.00

72908.00

38th m

10%

66833.00

80200.00

39th m

10%

73516.00

88219.00

40th m

10%

80868.00

97042.00

80868.00

97042.00

8087.00

9704.00

Total Cost from 30m upto 40m


Avg Rate per metre
B

15127.00

Including 20%
for Kentledge
19514.00

Avg Rate per metre

12.14

Remarks/
Input ref.

12265.00

(v)

Cost Rs

Beyond 20m upto 30 m

Total Cost from 20m upto 30m


12.14 A

Rate Rs

122652.00

Avg Rate per metre


12.14 A

Quantity

Clayey Soil ( 8m dia. Well )


Unit = Running Meter.
Taking output = 1 meter

(i)

Depth from bed level upto 3.0 M


Rate of sinking @ 0.18 m/hour
a)

b)

Labour
Mate

day

0.22

151.44

33.32

L-12

Sinker ( skilled )

day

2.00

164.69

329.38

L-15

Sinking helper ( semi-skilled )

hour

3.50

230.00

805.00

L-14

5.50

1073.50

5904.25

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)


Page 39 of 264

590.43
1532.47

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c)

10114.33
say

(ii)

Remarks/
Input ref.

919.48

Rate per metre = (a+b+c+d)


12.14 B

Cost Rs

10114.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.17 m/hour
a)

b)

Labour
Mate

day

0.32

151.44

48.46

L-12

Sinker

day

2.50

164.69

411.73

L-15

Sinking helper ( semi-skilled )

day

4.50

230.00

1035.00

L-14

hour

6.00

1073.50

6441.00

P&M-075

hour

3.50

740.15

2590.53

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

903.15
2285.97
1371.58

Rate per metre = (a+b+c+d)

15087.42
say

12.14 B

(iii)
a
b

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

Including for
dewatering @
5% of cost, if
required

11th m

5%

15842.00

16634.00

12th m

5%

16634.00

17466.00

13th m

5%

17466.00

18339.00

14th m

5%

18339.00

19256.00

15th m

5%

19256.00

20219.00

16th m

5%

20219.00

21230.00

17th m

5%

21230.00

22292.00

18th m

5%

22292.00

23407.00

19th m

5%

23407.00

24577.00

20th m

5%

24577.00

25806.00

199262.00

209226.00

19926.00

20923.00

Total Cost from 10m upto 20m


Avg Rate per metre
12.14 B

(iv)
a
b
c

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).

7.5%

26420.00

33025.00

34676.00

32nd

7.5%

28402.00

35503.00

37278.00

33rd m

7.5%

30532.00

38165.00

40073.00

34th m

7.5%

32822.00

41028.00

43079.00

35th m

7.5%

35284.00

44105.00

46310.00

36th m

7.5%

37930.00

47413.00

49784.00

37th m

7.5%

40775.00

50969.00

53517.00

38th m

7.5%

43833.00

54791.00

57531.00

39th m

7.5%

47120.00

58900.00

61845.00

40th m

7.5%

50654.00

63318.00

66484.00

373772.00

467217.00

490577.00

37377.00

46722.00

49058.00

Avg Rate per metre


(v)

Including 25% Including 5%


for Kentledge
for
dewatering, if
required

31st m

Total Cost from 30m upto 40m


12.14 B

15087.00

Beyond 10 m upto 20 m

Beyond 30m upto 40 m


Page 40 of 264

Sr No

Ref. to
MoRTH
Spec.

Description
a
b
c

Unit

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

Cost Rs

Remarks/
Input ref.

Including 20% Including 5%


for Kentledge
for
dewatering, if
required

31st m

10%

55719.00

66863.00

70206.00

32nd

10%

61291.00

73549.00

77226.00

33rd m

10%

67420.00

80904.00

84949.00

34th m

10%

74162.00

88994.00

93444.00

35th m

10%

81578.00

97894.00

102789.00

36th m

10%

89736.00

107683.00

113067.00

37th m

10%

98710.00

118452.00

124375.00

38th m

10%

108581.00

130297.00

136812.00

39th m

10%

119439.00

143327.00

150493.00

40th m

10%

131383.00

157660.00

165543.00

888019.00

1065623.00

1118904.00

88802.00

106562.00

111890.00

Avg Rate per metre


C

Rate Rs

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

Total Cost from 30m upto 40m


12.14

Quantity

Soft Rock ( 8m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a)

b)

Labour
Mate

day

0.68

151.44

102.98

L-12

Sinker ( skilled )

day

4.00

164.69

658.76

L-15

Sinking helper ( semi-skilled )

day

12.00

230.00

2760.00

L-14

Diver

day

1.00

264.50

264.50

L-07

hour

5.00

1073.50

5367.50

P&M-075

hour

3.75

740.15

2775.56

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)

814.31
637.18

c)

Add for dewatering @ of 5 per cent of (a+b), if


required
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2676.16
1605.69

Rate per metre = (a+b+c+d)


12.14

17662.64
say

17663.00

1168.00

Hard Rock ( 8m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a)

b)

c)

Material
Gelatine 80 per cent

Kg

8.00

146.00

Electric Detonators

each

32.00

14.56

M-104

Mate

day

1.09

151.44

165.07

L-12

Driller

day

2.00

264.50

529.00

L-06

Blaster

day

0.25

264.50

66.13

L-03

Mazdoor

day

20.00

136.69

2733.80

L-13

Mazdoor (Skilled)

day

4.00

164.69

658.76

L-15

hour

6.00

1073.50

6441.00

P&M-075

hour

2.00

740.15

1480.30

P&M-063

465.92 M-094/100

Labour

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Page 41 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Dewatering @ 5 per cent of cost of (b+c), if required.


Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

415.28
2945.39
1767.23

Rate per metre = (a+b+c+d+e)

19439.58
say

12.15

Section
1200

Remarks/
Input ref.

603.70

Consumables in sinking @ 10 per cent of cost of (b).


d)

Cost Rs

19440.00

Sinking of 9 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 9 m.
A
(i)

Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a)

b)

Labour
Mate

day

0.19

151.44

28.77

L-12

Sinker ( skilled )

day

1.50

164.69

247.04

L-15

Sinking helper ( semi-skilled )

day

3.25

230.00

747.50

L-14

hour

4.00

1073.50

4294.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

429.40
1149.34
689.61

Rate per metre = (a+b+c+d)

7585.66
say

12.15 A

(ii)

7586.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.18 m/hour
a)

b)

Labour
Mate

day

0.27

151.44

40.89

L-12

Sinker

day

1.75

164.69

288.21

L-15

Sinking helper ( semi-skilled )

day

4.00

230.00

920.00

L-14

hour

5.50

1073.50

5904.25

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

590.43
1548.75
929.25

Rate per metre = (a+b+c+d)

10221.78
say

12.15 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

10733.00

12th m

5%

11270.00

13th m

5%

11834.00

14th m

5%

12426.00

15th m

5%

13047.00

16th m

5%

13699.00

17th m

5%

14384.00

18th m

5%

15103.00

19th m

5%

15858.00

20th m

5%

Total Cost from 10m upto 20m

16651.00
135005.00

Avg Rate per metre

13501.00
Page 42 of 264

10222.00

Sr No
12.15 A

Ref. to
MoRTH
Spec.

Description
(iv)
a
b

Unit

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
21st m

7.5%

17899.83

Including 20%
for Kentledge
21480.00

22nd m

7.5%

19242.00

23090.00

23rd m

7.5%

20685.00

24822.00

24th m

7.5%

22236.00

26683.00

25th m

7.5%

23904.00

28685.00

26th m

7.5%

25697.00

30836.00

27th m

7.5%

27624.00

33149.00

28th m

7.5%

29696.00

35635.00

29th m

7.5%

31923.00

38308.00

30th m

7.5%

34317.00

41180.00

253223.83

303868.00

25322.00

30387.00

Avg Rate per metre


(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
31st m

10%

37748.70

Including 20%
for Kentledge
45298.00

32nd

10%

41524.00

49829.00

33rd m

10%

45676.00

54811.00

34th m

10%

50244.00

60293.00

35th m

10%

55268.00

66322.00

36th m

10%

60795.00

72954.00

37th m

10%

66875.00

80250.00

38th m

10%

73563.00

88276.00

39th m

10%

80919.00

97103.00

40th m

10%

89011.00

106813.00

601623.70

721949.00

60162.00

72195.00

Total Cost from 30m upto 40m


Avg Rate per metre
12.15

Rate Rs

Cost Rs

Remarks/
Input ref.

Beyond 20m upto 30 m

Total Cost from 20m upto 30m


12.15 A

Quantity

Clayey Soil ( 9m dia. Well )


Unit = Running Meter.
Taking output = 1 cum

(i)

Depth below bed level upto 3.0 M


Rate of sinking 0.17 m / hour
a)

b)

Labour
Mate

day

0.24

151.44

36.35

L-12

Sinker ( skilled )

day

2.25

164.69

370.55

L-15

Sinking helper ( semi-skilled )

day

3.75

230.00

862.50

L-14

hour

5.75

1073.50

6172.63

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

617.26
1611.86
967.11

Rate per metre = (a+b+c+d)

10638.26
say

12.15 B

(ii)

10638.00

Beyond 3m upto 10m depth


Rate of sinking 0.15 m / hour
a)

b)

Labour
Mate

day

0.34

151.44

51.49

L-12

Sinker

day

2.50

164.69

411.73

L-15

Sinking helper ( semi-skilled )

day

5.00

230.00

1150.00

L-14

Machinery
Page 43 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)
c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Quantity

Rate Rs

6.50

1073.50

6977.75

P&M-075

hour

3.75

740.15

2775.56

P&M-063

975.33
2468.37
1481.02
16291.25
say

(iii)
a
b

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

Including for
dewatering @
5% of cost, if
required

11th m

5%

17106.00

17961.00

12th m

5%

17961.00

18859.00

13th m

5%

18859.00

19802.00

14th m

5%

19802.00

20792.00

15th m

5%

20792.00

21832.00

16th m

5%

21832.00

22924.00

17th m

5%

22924.00

24070.00

18th m

5%

24070.00

25274.00

19th m

5%

25274.00

26538.00

20th m

5%

26538.00

27865.00

215158.00

225917.00

21516.00

22592.00

Avg Rate per metre


(iv)
a
b
c

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).

Including 25% Including 5%


for Kentledge
for
dewatering, if
required

31st m

7.5%

28528.00

35660.00

37443.00

32nd

7.5%

30668.00

38335.00

40252.00

33rd m

7.5%

32968.00

41210.00

43271.00

34th m

7.5%

35441.00

44301.00

46516.00

35th m

7.5%

38099.00

47624.00

50005.00

36th m

7.5%

40956.00

51195.00

53755.00

37th m

7.5%

44028.00

55035.00

57787.00

38th m

7.5%

47330.00

59163.00

62121.00

39th m

7.5%

50880.00

63600.00

66780.00

40th m

7.5%

54696.00

68370.00

71789.00

403594.00

504493.00

529719.00

40359.00

50449.00

52972.00

Total Cost from 30m upto 40m


Avg Rate per metre
12.15 B

(v)
a
b
c

16291.00

Beyond 10 m upto 20 m

Total Cost from 10m upto 20m


12.15 B

Beyond 30m upto 40 m


Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).

Including 20% Including 5%


for Kentledge
for
dewatering, if
required

31st m

10%

60166.00

72199.00

75809.00

32nd

10%

66183.00

79420.00

83391.00

33rd m

10%

72801.00

87361.00

91729.00

34th m

10%

80081.00

96097.00

100902.00

Page 44 of 264

Remarks/
Input ref.

hour

Rate per metre = (a+b+c+d)


12.15 B

Cost Rs

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Cost Rs

Remarks/
Input ref.

10%

88089.00

105707.00

110992.00

36th m

10%

96898.00

116278.00

122092.00

37th m

10%

106588.00

127906.00

134301.00

38th m

10%

117247.00

140696.00

147731.00

39th m

10%

128972.00

154766.00

162504.00

40th m

10%

141869.00

170243.00

178755.00

958894.00

1150673.00

1208206.00

95889.00

115067.00

120821.00

0.76

151.44

115.09

L-12

Avg Rate per metre


C

Rate Rs

35th m

Total Cost from 30m upto 40m


12.15

Quantity

Soft Rock ( 9m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a)

b)

Labour
Mate

day

Sinker ( skilled )

day

4.00

164.69

658.76

L-15

Sinking helper ( semi-skilled )

day

14.00

230.00

3220.00

L-14

Diver

day

1.20

264.50

317.40

L-07

hour

6.50

1073.50

6977.75

P&M-075

hour

4.00

740.15

2960.60

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)

993.84
1524.34

c)

Add for dewatering @ of 5 per cent of (a+b), if


required
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3353.56
2012.13

Rate per metre = (a+b+c+d)


12.15

22133.47
say

22133.00

1460.00

Hard Rock ( 9m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a)

b)

c)

Material
Gelatine 80 per cent

Kg

10.00

146.00

Electric Detonators

each

40.00

14.56

M-104

Mate

day

1.17

151.44

177.18

L-12

Driller

day

2.00

264.50

529.00

L-06

Blaster

day

0.25

264.50

66.13

L-03

Mazdoor

day

22.00

136.69

3007.18

L-13

Mazdoor (Skilled)

day

4.00

164.69

658.76

L-15

Diver

day

1.00

264.50

264.50

L-07

hour

7.00

1073.50

7514.50

P&M-075

hour

2.50

740.15

1850.38

P&M-063

582.40 M-094/100

Labour

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.

703.38

Consumables in sinking @ 10 per cent of cost of (b).


d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

470.27
3456.74
2074.04

Rate per metre = (a+b+c+d+e)

22814.46
say

Page 45 of 264

22814.00

Sr No

Ref. to
MoRTH
Spec.

12.16

1200

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Sinking of 10 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter
Taking output = 1 m
Diameter of well - 10 m.
A

Sandy Soil

(i)

Depth below bed level upto 3.0 M


Rate of sinking 0.20 m / hour
a)

b)

Labour
Mate

day

0.20

151.44

30.29

L-12

Sinker ( skilled )

day

1.50

164.69

247.04

L-15

Sinking helper ( semi-skilled )

day

3.50

230.00

805.00

L-14

hour

5.00

1073.50

5367.50

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

536.75
1397.31
838.39

Rate per metre = (a+b+c+d)

9222.28
say

12.16 A

(ii)

9222.00

Beyond 3m upto 10m depth


Rate of sinking 0.17 m / hour
a)

b)

Labour
Mate

day

0.31

151.44

46.95

L-12

Sinker

day

2.00

164.69

329.38

L-15

Sinking helper ( semi-skilled )

day

4.25

230.00

977.50

L-14

hour

5.75

1073.50

6172.63

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

617.26
1628.74
977.25

Rate per metre = (a+b+c+d)

10749.70
say

12.16 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%
5%

11851.00

13th m

5%

12444.00

14th m

5%

13066.00

15th m

5%

13719.00

16th m

5%

14405.00

17th m

5%

15125.00

18th m

5%

15881.00

19th m

5%

16675.00

20th m

5%

Total Cost from 10m upto 20m


(iv)
a
b

17509.00
141962.00

Avg Rate per metre


12.16 A

11287.00

12th m

14196.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
21st m
Page 46 of 264

7.5%

18822.00

Including 20%
for Kentledge
22586.00

10750.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
7.5%

20234.00

24281.00

23rd m

7.5%

21752.00

26102.00

24th m

7.5%

23383.00

28060.00

25th m

7.5%

25137.00

30164.00

26th m

7.5%

27022.00

32426.00

27th m

7.5%

29049.00

34859.00

28th m

7.5%

31228.00

37474.00

29th m

7.5%

33570.00

40284.00

30th m

7.5%

36088.00

43306.00

266285.00

319542.00

26629.00

31954.00

Avg Rate per metre


(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
31st m

10%

39697.00

Including 20%
for Kentledge
47636.00

32nd

10%

43667.00

52400.00

33rd m

10%

48034.00

57641.00

34th m

10%

52837.00

63404.00

35th m

10%

58121.00

69745.00

36th m

10%

63933.00

76720.00

37th m

10%

70326.00

84391.00

38th m

10%

77359.00

92831.00

39th m

10%

85095.00

102114.00

40th m

10%

93605.00

112326.00

632674.00

759208.00

63267.00

75921.00

Total Cost from 30m upto 40m


Avg Rate per metre
12.16

Rate Rs

22nd m

Total Cost from 20m upto 30m


12.16 A

Quantity

Cost Rs

Remarks/
Input ref.

Clayey Soil (10m dia. Well )


Unit = Running Meter
Taking output = 1 cum

(i)

Depth below bed level upto 3.0 M


Rate of sinking 0.18m/hour.
a)

b)

Labour
Mate

day

0.25

151.44

37.86

L-12

Sinker ( skilled )

day

2.50

164.69

411.73

L-15

Sinking helper ( semi-skilled )

day

5.50

230.00

1265.00

L-14

hour

6.00

1073.50

6441.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

644.10
1759.94
1055.96

Rate per metre = (a+b+c+d)

11615.58
say

12.16 B

(ii)

11616.00

Beyond 3m upto 10m depth


Rate of sinking 0.15m/hour.
a)

b)

Labour
Mate

day

0.40

151.44

60.58

L-12

Sinker

day

3.00

164.69

494.07

L-15

Sinking helper ( semi-skilled )

day

5.50

230.00

1265.00

L-14

hour

6.00

1073.50

6441.00

P&M-075

hour

4.00

740.15

2960.60

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)


Page 47 of 264

940.16
2432.28

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c)

1459.37

Rate per metre = (a+b+c+d)

16053.06
say

12.16 B

(iii)
a
b

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

Including for
dewatering @
5% of cost, if
required

11th m

5%

16856.00

17699.00

12th m

5%

17699.00

18584.00

13th m

5%

18584.00

19513.00

14th m

5%

19513.00

20489.00

15th m

5%

20489.00

21513.00

16th m

5%

21513.00

22589.00

17th m

5%

22589.00

23718.00

18th m

5%

23718.00

24904.00

19th m

5%

24904.00

26149.00

20th m

5%

26149.00

27456.00

212014.00

222614.00

21201.00

22261.00

Avg Rate per metre


(iv)
a
b
c

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).

Including 25% Including 5%


for Kentledge
for
dewatering, if
required

31st m

7.5%

28110.00

35138.00

36895.00

32nd

7.5%

30218.00

37773.00

39662.00

33rd m

7.5%

32484.00

40605.00

42635.00

34th m

7.5%

34920.00

43650.00

45833.00

35th m

7.5%

37539.00

46924.00

49270.00

36th m

7.5%

40354.00

50443.00

52965.00

37th m

7.5%

43381.00

54226.00

56937.00

38th m

7.5%

46635.00

58294.00

61209.00

39th m

7.5%

50133.00

62666.00

65799.00

40th m

7.5%

53893.00

67366.00

70734.00

397667.00

497085.00

521939.00

39767.00

49709.00

52194.00

Total Cost from 30m upto 40m


Avg Rate per metre
12.16 B

(v)
a
b
c

16053.00

Beyond 10 m upto 20 m

Total Cost from 10m upto 20m


12.16 B

Cost Rs

Beyond 30m upto 40 m


Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).

Including 20% Including 5%


for Kentledge
for
dewatering, if
required

31st m

10%

59282.00

71138.00

74695.00

32nd

10%

65210.00

78252.00

82165.00

33rd m

10%

71731.00

86077.00

90380.85

34th m

10%

78904.00

94685.00

99419.25

35th m

10%

86794.00

104153.00

109360.65

36th m

10%

95473.00

114568.00

120296.40

37th m

10%

105020.00

126024.00

132325.20

38th m

10%

115522.00

138626.00

145557.30

39th m

10%

127074.00

152489.00

160113.45

Page 48 of 264

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description
40th m

Unit

Quantity

10%

139781.00

167737.00

176123.85

944791.00

1133749.00

1190436.95

94479.00

113375.00

119044.00

Total Cost from 30m upto 40m


Avg Rate per metre
12.16

Rate Rs

Cost Rs

Remarks/
Input ref.

Soft Rock (10m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a)

b)

Labour
Mate

day

0.86

151.44

130.24

L-12

Sinker ( skilled )

day

4.00

164.69

658.76

L-15

Sinking helper ( semi-skilled )

day

16.00

230.00

3680.00

L-14

Diver

day

1.40

264.50

370.30

L-07

hour

7.00

1073.50

7514.50

P&M-075

hour

4.25

740.15

3145.64

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)

1066.01

Add for dewatering @ 5 per cent of cost, if required

586.31

c)

Overhead charges @ 0.2 on (a+b)

3430.35

d)

Contractor's profit @ 0.1 on (a+b+c)

2058.21

Rate per metre = (a+b+c+d)


12.16

22640.32
say

22640.00

1606.00

Hard Rock (10m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a)

b)

c)

Material
Gelatine 80 per cent

Kg

11.00

146.00

Electric Detonators

each.

44.00

14.56

Mate

day

1.27

151.44

192.33

L-12

Driller

day

2.00

264.50

529.00

L-06

Blaster

day

0.25

264.50

66.13

L-03

Mazdoor

day

24.00

136.69

3280.56

L-13

Mazdoor (Skilled)

day

4.00

164.69

658.76

L-15

hour

8.50

1073.50

9124.75

P&M-075

hour

3.00

740.15

2220.45

P&M-063

Labour

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required.

d)

Consumables in sinking @ 10 per cent of cost of


(b+c).
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

567.26
1663.92
4109.96
2465.98

Rate per metre = (a+b+c+d+e)

27125.73
say

12.17

1200

Sinking of 11 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter
Taking output = 0.50 m
Diameter of well - 11 m.
A

M-104

640.64 M-094/100

Sandy Soil
Page 49 of 264

27126.00

Sr No

Ref. to
MoRTH
Spec.

Description
(i)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Depth from bed level upto 3.0 M


Rate of sinking @ 0.15 m/hour
a)

b)

Labour
Mate

day

0.21

151.44

31.80

L-12

Sinker ( skilled )

day

1.50

164.69

247.04

L-15

Sinking helper (semi-skilled)

day

3.30

230.00

759.00

L-14

hour

6.00

1073.50

6441.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

644.10
1624.59
974.75

Cost for 0.5m = a+b+c+d

10722.28

Rate per metre = (a+b+c+d)/0.50

21444.55
say

12.17 A

(ii)

21445.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.13 m/hour
a)

b)

Labour
Mate

day

0.32

151.44

48.46

L-12

Sinker

day

2.00

164.69

329.38

L-15

Sinking helper (semi-skilled)

day

4.50

230.00

1035.00

L-14

hour

4.00

1073.50

4294.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b+c)

d)

Contractor's profit @ 0.1 on (a+b+c+d)

429.40
1227.25
736.35

Cost for 0.5m = a+b+c+d

8099.84

Rate per metre = (a+b+c+d)/0.50

16199.68
say

12.17 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

17010.00

12th m

5%

17861.00

13th m

5%

18754.00

14th m

5%

19692.00

15th m

5%

20677.00

16th m

5%

21711.00

17th m

5%

22797.00

18th m

5%

23937.00

19th m

5%

25134.00

20th m

5%

Total Cost from 10m upto 20m


Avg Rate per metre
12.17 A

(iv)
a
b

26391.00
213964.00
21396.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
21st m

7.5%

28370.00

Including 20%
for Kentledge
34044.00

22nd m

7.5%

30498.00

36598.00

23rd m

7.5%

32785.00

39342.00

24th m

7.5%

35244.00

42293.00

25th m

7.5%

37887.00

45464.00

26th m

7.5%

40729.00

48875.00

27th m

7.5%

43784.00

52541.00

28th m

7.5%

47068.00

56482.00

Page 50 of 264

16200.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
7.5%

50598.00

30th m

7.5%

54393.00

65272.00

401356.00

481629.00

40136.00

48163.00

Avg Rate per metre


(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
31st m

10%

59832.00

32nd

10%

65815.00

78978.00

33rd m

10%

72397.00

86876.00

34th m

10%

79637.00

95564.00

35th m

10%

87601.00

105121.00

36th m

10%

96361.00

115633.00

37th m

10%

105997.00

127196.00

38th m

10%

116597.00

139916.00

39th m

10%

128257.00

153908.00

40th m

10%

141083.00

169300.00

953577.00

1144290.00

95358.00

114429.00

Avg Rate per metre


B

Cost Rs

Remarks/
Input ref.

60718.00

Including 20%
for Kentledge
71798.00

Total Cost from 30m upto 40m


12.17

Rate Rs

29th m
Total Cost from 20m upto 30m
12.17 A

Quantity

Clayey Soil (11 m dia. Well )


Unit = Running Meter
Taking output = 0.50 meter

(i)

Depth from bed level upto 3.0 M


Rate of sinking @ 0.10 m/hour
a)

b)

Labour
Mate

day

0.26

151.44

39.37

L-12

Sinker ( skilled )

day

2.50

164.69

411.73

L-15

Sinking helper (semi-skilled)

day

4.00

230.00

920.00

L-14

hour

5.00

1073.50

5367.50

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

536.75
1455.07
873.04

Cost for 0.5m = a+b+c+d

9603.46

Rate per metre = (a+b+c+d)/0.50

19206.92
say

12.17 B

(ii)

19207.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.08 m/hour
a)

b)

Labour
Mate

day

0.43

151.44

65.12

L-12

Sinker

day

3.50

164.69

576.42

L-15

Sinking helper (semi-skilled)

day

5.75

230.00

1322.50

L-14

hour

6.00

1073.50

6441.00

P&M-075

hour

4.25

740.15

3145.64

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

958.66
2501.87
1501.12

Cost for 0.5m = a+b+c+d

16512.32

Rate per metre = (a+b+c+d)/0.50

33024.65
say

12.17 B

(iii)
a

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Page 51 of 264

33025.00

Sr No

Ref. to
MoRTH
Spec.

Description
b

Unit

Add for dewatering @ 5 per cent of cost, if required.

11th m

5%

34676.00

36410.00

12th m

5%

36410.00

38231.00

13th m

5%

38231.00

40143.00

14th m

5%

40143.00

42150.00

15th m

5%

42150.00

44258.00

16th m

5%

44258.00

46471.00

17th m

5%

46471.00

48795.00

18th m

5%

48795.00

51235.00

19th m

5%

51235.00

53797.00

20th m

5%

53797.00

56487.00

436166.00

457974.00

43617.00

45797.00

Avg Rate per metre


(iv)
a
b
c

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).

Including 25% Including 5%


for Kentledge
for
dewatering, if
required

31st m

7.5%

57832.00

72290.00

75905.00

32nd

7.5%

62169.00

77711.00

81597.00

33rd m

7.5%

66832.00

83540.00

87717.00

34th m

7.5%

71844.00

89805.00

94295.00

35th m

7.5%

77232.00

96540.00

101367.00

36th m

7.5%

83024.00

103780.00

108969.00

37th m

7.5%

89251.00

111564.00

117142.00

38th m

7.5%

95945.00

119931.00

125928.00

39th m

7.5%

103141.00

128926.00

135372.00

40th m

7.5%

110877.00

138596.00

145526.00

818147.00

1022683.00

1073817.00

81815.00

102268.00

107382.00

Avg Rate per metre


(v)
a
b
c

Beyond 30m upto 40 m


Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).

10%

121965.00

146358.00

153676.00

32nd

10%

134162.00

160994.00

169044.00

33rd m

10%

147578.00

177094.00

185949.00

34th m

10%

162336.00

194803.00

204543.00

35th m

10%

178570.00

214284.00

224998.00

36th m

10%

196427.00

235712.00

247498.00

37th m

10%

216070.00

259284.00

272248.00

38th m

10%

237677.00

285212.00

299473.00

39th m

10%

261445.00

313734.00

329421.00

40th m

10%

287590.00

345108.00

362363.00

1943820

2332583

2449213

194382.00

233258.00

244921.00

Avg Rate per metre


C

Including 20% Including 5%


for Kentledge
for
dewatering, if
required

31st m

Total Cost from 30m upto 40m


12.17

Cost Rs

Beyond 20m upto 30 m

Total Cost from 30m upto 40m


12.17 B

Rate Rs
Including for
dewatering @
5% of cost, if
required

Total Cost from 10m upto 20m


12.17 B

Quantity

Soft Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Page 52 of 264

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Depth in soft rock strata upto 3m


Rate of sinking @ 0.06 m/hour
a)

b)

Labour
Mate

day

0.95

151.44

143.87

L-12

Sinker ( skilled )

day

4.25

164.69

699.93

L-15

Sinking helper (semi-skilled)

day

18.00

230.00

4140.00

L-14

Diver

day

1.50

264.50

396.75

L-07

hour

8.00

1073.50

8588.00

P&M-075

hour

4.50

740.15

3330.68

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)

1191.87

Add for dewatering @ 5 per cent of cost, if required


c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

655.53
3829.32
2297.59

Cost for 0.5m = a+b+c+d

25273.54

Rate per metre = (a+b+c+d)/0.50


12.17

50547.08
say

50547.00

1752.00

Hard Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a)

b)

c)

Material
Gelatine 80 per cent

Kg

12.00

146.00

Electric Detonators

each.

48.00

14.56

Mate

day

1.35

151.44

204.44

L-12

Driller

day

2.00

264.50

529.00

L-06

Blaster

day

0.25

264.50

66.13

L-03

Mazdoor

day

26.00

136.69

3553.94

L-13

Mazdoor (Skilled)

day

4.00

164.69

658.76

L-15

hour

10.00

1073.50

10735.00

P&M-075

hour

3.50

740.15

2590.53

P&M-063

Labour

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required.

d)

Consumables in sinking @ 10 per cent of cost of


(b+c).
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

666.28
1833.78
4657.75
2794.65

Cost for 0.5m = a+b+c+d

30741.12

Rate per metre = (a+b+c+d)/0.50


12.18

1200

M-104

698.88 M-094/100

61482.25
say

61482.00

151.44

33.32

Sinking of 12 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter
Taking output = 0.25 m
Diameter of well - 12 m.
A

Sandy Soil

(i)

I) Depth below bed level upto 3.0 M


Rate of sinking @ 0.05 m/hour
a)

Labour
Mate

day
Page 53 of 264

0.22

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

day

1.75

164.69

288.21

L-15

Sinking helper (semi-skilled)

day

4.00

230.00

920.00

L-14

hour

6.00

1073.50

6441.00

P&M-075

Machinery

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

644.10
1665.32
999.19

Cost for 0.25m = a+b+c+d

10991.14

Rate per metre = (a+b+c+d)/0.25

43964.58
say

(ii)

Remarks/
Input ref.

Sinker ( skilled )

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

12.18 A

Cost Rs

43965.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.038 m/hour
a)

b)

Labour
Mate

day

0.37

151.44

56.03

L-12

Sinker

day

2.50

164.69

411.73

L-15

Sinking helper (semi-skilled)

day

4.75

230.00

1092.50

L-14

hour

6.50

1073.50

6977.75

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

697.78
1847.16
1108.29

Cost for 0.25m = a+b+c+d

12191.23

Rate per metre = (a+b+c+d)/0.25

48764.93
say

12.18 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

51203.00

12th m

5%

53763.00

13th m

5%

56451.15

14th m

5%

59273.71

15th m

5%

62237.39

16th m

5%

65349.26

17th m

5%

68616.73

18th m

5%

72047.56

19th m

5%

75649.94

20th m

5%

Total Cost from 10m upto 20m


Avg Rate per metre
12.18 A

(iv)
a
b

79432.44
644024.18
64402.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
21st m

7.5%

85390.00

Including 20%
for Kentledge
102468.00

22nd m

7.5%

91794.00

110153.00

23rd m

7.5%

98679.00

118415.00

24th m

7.5%

106080.00

127296.00

25th m

7.5%

114036.00

136843.00

26th m

7.5%

122589.00

147107.00

27th m

7.5%

131783.00

158140.00

28th m

7.5%

141667.00

170000.00

29th m

7.5%

152292.00

182750.00

30th m

7.5%

163714.00

196457.00

1208024.00

1449629.00

120802.00

144963.00

Total Cost from 20m upto 30m


Avg Rate per metre
Page 54 of 264

48765.00

Sr No
12.18 A

Ref. to
MoRTH
Spec.

Description

Unit

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
31st m

10%

180085.00

32nd

10%

198094.00

237713.00

33rd m

10%

217903.00

261484.00

34th m

10%

239693.00

287632.00

35th m

10%

263662.00

316394.00

36th m

10%

290028.00

348034.00

37th m

10%

319031.00

382837.00

38th m

10%

350934.00

421121.00

39th m

10%

386027.00

463232.00

40th m

10%

424630.00

509556.00

Avg Rate per metre


B

Rate Rs

Including 20%
for Kentledge
216102.00

Total Cost from 30m upto 40m


12.18

Quantity

2870087

3444105

287009.00

344411.00

Cost Rs

Remarks/
Input ref.

Clayey Soil (12 m dia. Well )


Unit = Running Meter.
Taking output = 0.25 meter.

(i)

Depth below bed level upto 3.0 M


Rate of sinking @ 0.04 m/hour
a)

b)

Labour
Mate

day

0.30

151.44

45.43

L-12

Sinker ( skilled )

day

3.00

164.69

494.07

L-15

Sinking helper (semi-skilled)

day

4.50

230.00

1035.00

L-14

hour

6.25

1073.50

6709.38

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

670.94
1790.96
1074.58

Cost for 0.25m = a+b+c+d

11820.36

Rate per metre = (a+b+c+d)/0.25

47281.42
say

12.18 B

(ii)

47281.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.03 m/hour
a)

b)

Labour
Mate

day

0.48

151.44

72.69

L-12

Sinker

day

3.75

164.69

617.59

L-15

Sinking helper (semi-skilled)

day

6.00

230.00

1380.00

L-14

hour

8.33

1073.50

8942.26

P&M-075

hour

4.50

740.15

3330.68

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

1227.29

c)

Overhead charges @ 0.2 on (a+b)

3114.10

d)

Contractor's profit @ 0.1 on (a+b+c)

1868.46

Cost for 0.25m = a+b+c+d

20553.06

Rate per metre = (a+b+c+d)/0.25

82212.25
say

12.18 B

(iii)
a
b

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

Page 55 of 264

Including for
dewatering @
5% of cost, if
required

82212.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
5%

86323.00

90639.00

12th m

5%

90639.00

95171.00

13th m

5%

95171.00

99930.00

14th m

5%

99930.00

104927.00

15th m

5%

104927.00

110173.00

16th m

5%

110173.00

115682.00

17th m

5%

115682.00

121466.00

18th m

5%

121466.00

127539.00

19th m

5%

127539.00

133916.00

20th m

5%

133916.00

140612.00

1085766.00

1140055.00

108577.00

114006.00

Avg Rate per metre


(iv)
a
b
c

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).

Including 25% Including 5%


for Kentledge
for
dewatering, if
required

31st m

7.5%

143960.00

179950.00

32nd

7.5%

154757.00

193446.00

203118.00

33rd m

7.5%

166364.00

207955.00

218353.00

34th m

7.5%

178841.00

223551.00

234729.00

35th m

7.5%

192254.00

240318.00

252334.00

36th m

7.5%

206673.00

258341.00

271258.00

37th m

7.5%

222173.00

277716.00

291602.00

38th m

7.5%

238836.00

298545.00

313472.00

39th m

7.5%

256749.00

320936.00

336983.00

40th m

7.5%

276005.00

345006.00

362256.00

2036612

2545764

2673053

203661.00

254576.00

267305.00

Avg Rate per metre


(v)
a
b
c

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).

10%

303606.00

364327.00

382543.00

32nd

10%

333967.00

400760.00

420798.00

33rd m

10%

367364.00

440837.00

462879.00

34th m

10%

404100.00

484920.00

509166.00

35th m

10%

444510.00

533412.00

560083.00

36th m

10%

488961.00

586753.00

616091.00

37th m

10%

537857.00

645428.00

677699.00

38th m

10%

591643.00

709972.00

745471.00

39th m

10%

650807.00

780968.00

820016.00

40th m

10%

715888.00

859066.00

902019.00

4838703

5806443

6096765

483870.00

580644.00

609677.00

Soft Rock (12m dia well )


Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a)

Including 20% Including 5%


for Kentledge
for
dewatering, if
required

31st m

Avg Rate per metre


C

188948.00

Beyond 30m upto 40 m

Total Cost from 30m upto 40m


12.18

Cost Rs

Beyond 20m upto 30 m

Total Cost from 30m upto 40m


12.18 B

Rate Rs

11th m

Total Cost from 10m upto 20m


12.18 B

Quantity

Labour
Page 56 of 264

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

day

1.06

151.44

160.53

L-12

Sinker ( skilled )

day

4.50

164.69

741.11

L-15

Sinking helper (semi-skilled)

day

20.00

230.00

4600.00

L-14

Diver

day

1.75

264.50

462.88

L-07

hour

10.00

1073.50

10735.00

P&M-075

hour

4.75

740.15

3515.71

P&M-063

Machinery

1425.07

Add for dewatering @ 5 per cent, if required


c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

783.79
4484.82
2690.89

Cost for 0.25m = a+b+c+d

29599.78

Rate per metre = (a+b+c+d)/0.25


D

Remarks/
Input ref.

Mate

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

12.18

Cost Rs

118399.14
say

118399.00

2044.00

Hard Rock (12m dia well )


Unit = Running Meter
Taking output = 0.25 m

(i)

Depth in hard rock strata upto 3 m


Rate of sinking @ 0.020 m/hour
a)

Material
Gelatine80 per cent

Kg

14.00

146.00

each.

56.00

14.56

Mate

day

1.44

151.44

218.07

L-12

Driller

day

2.00

264.50

529.00

L-06

Blaster

day

0.25

264.50

66.13

L-03

Mazdoor

day

28.00

136.69

3827.32

L-13

Mazdoor (Skilled)

day

4.50

164.69

741.11

L-15

hour

12.50

1073.50

13418.75

P&M-075

hour

4.00

740.15

2960.60

P&M-063

Electric detonator
b)

c)

Labour

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent, if required.

818.97

Consumables in sinking @ 10 per cent of (c).

1719.83

d)

Overhead charges @ 0.2 on (a+b+c)

5431.83

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3259.10

Cost for 0.25m = a+b+c+d+e

35850.06

Rate per metre = (a+b+c+d+e)/0.25

143400.22
say

12.19

1200

M-104

815.36 M-094/100

143400.00

Sinking of Twin D Type well (other than pneumatic


method of sinking) through all types of strata namely
sandy soil, clayey soil and rock as shown against each
case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
A

Sandy Soil

(i)

Depth from bed level upto 3.0 M


Rate of sinking @ 0.18 m/hour
a)

Labour
Mate

day

0.20

151.44

30.29

L-12

Sinker ( skilled )

day

1.25

164.69

205.86

L-15

Page 57 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Sinking helper (semi-skilled)


b)

Quantity

Rate Rs

day

3.75

230.00

862.50

L-14

hour

5.50

1073.50

5904.25

P&M-075

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

590.43
1518.67
911.20

Rate per metre = (a+b+c+d)

10023.19
say

(ii)

Remarks/
Input ref.

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

12.19 A

Cost Rs

10023.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.17 m/hour
a)

b)

Labour
Mate

day

0.30

151.44

45.43

L-12

Sinker

day

1.50

164.69

247.04

L-15

Sinking helper (semi-skilled)

day

4.00

230.00

920.00

L-14

hour

5.88

1073.50

6312.18

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

631.22
1631.17
978.70

Rate per metre = (a+b+c+d)

10765.74
say

12.19 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%
5%

11869.00

13th m

5%

12462.00

14th m

5%

13085.00

15th m

5%

13739.00

16th m

5%

14426.00

17th m

5%

15147.00

18th m

5%

15904.00

19th m

5%

16699.00

20th m

5%

Total Cost from 10m upto 20m


(iv)
a
b

14217.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
21st m

7.5%

18849.00

Including 20%
for Kentledge
22619.00

22nd m

7.5%

20263.00

24316.00

23rd m

7.5%

21783.00

26140.00

24th m

7.5%

23417.00

28100.00

25th m

7.5%

25173.00

30208.00

26th m

7.5%

27061.00

32473.00

27th m

7.5%

29091.00

34909.00

28th m

7.5%

31273.00

37528.00

29th m

7.5%

33618.00

40342.00

30th m

7.5%

36139.00

43367.00

266667.00

320002.00

26667.00

32000.00

Total Cost from 20m upto 30m


Avg Rate per metre
12.19 A

17534.00
142169.00

Avg Rate per metre


12.19 A

11304.00

12th m

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Page 58 of 264

10766.00

Sr No

Ref. to
MoRTH
Spec.

Description
b

Unit

Add 20 per cent of cost for Kentledge including supports,


loading arrangement, and Labour etc.
31st m

10%

39753.00

32nd

10%

43728.00

52474.00

33rd m

10%

48101.00

57721.00

34th m

10%

52911.00

63493.00

35th m

10%

58202.00

69842.00

36th m

10%

64022.00

76826.00

37th m

10%

70424.00

84509.00

38th m

10%

77466.00

92959.00

39th m

10%

85213.00

102256.00

40th m

10%

Avg Rate per metre


B

Rate Rs
Including 20%
for Kentledge
47704.00

Total Cost from 30m upto 40m


12.19

Quantity

93734.00

112481.00

633554.00

760265.00

63355.00

76027.00

Cost Rs

Remarks/
Input ref.

Clayey Soil (Twin D Type Well )


Unit = Running Meter
Taking output = 1 meter

(i)

Depth below bed level upto 3.0 M


Rate of sinking @ 0.16 m/hour
a)

b)

Labour
Mate

day

0.26

151.44

39.37

L-12

Sinker ( skilled )

day

2.50

Sinking helper (semi-skilled)

day

4.00

164.69

411.73

L-15

230.00

920.00

L-14

hour

6.25

1073.50

6709.38

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

670.94
1750.28
1050.17

Rate per metre = (a+b+c+d)

11551.86
say

12.19 B

(ii)

11552.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.15 m/hour
a)

b)

Labour
Mate

day

0.45

151.44

68.15

L-12

Sinker

day

3.25

164.69

535.24

L-15

Sinking helper (semi-skilled)

day

6.00

230.00

1380.00

L-14

hour

6.67

1073.50

7160.25

P&M-075

hour

4.50

740.15

3330.68

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1049.09
2704.68
1622.81

Rate per metre = (a+b+c+d)

17850.89
say

12.19 B

(iii)
a
b

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

Including for
dewatering @
5% of cost, if
required

11th m

5%

18743.00

19680.00

12th m

5%

19680.00

20664.00

13th m

5%

20664.00

21697.00

14th m

5%

21697.00

22782.00

15th m

5%

22782.00

23921.00

Page 59 of 264

17851.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
5%

23921.00

25117.00

17th m

5%

25117.00

26373.00

18th m

5%

26373.00

27692.00

19th m

5%

27692.00

29077.00

20th m

5%

29077.00

30531.00

235746.00

247534.00

23575.00

24753.00

Avg Rate per metre


(iv)
a
b
c

a
b
c

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

Including 25% Including 5%


for Kentledge
for
dewatering, if
required

31st m

7.5%

31258.00

39073.00

41027.00

32nd

7.5%

33602.00

42003.00

44103.00

33rd m

7.5%

36122.00

45153.00

47411.00

34th m

7.5%

38831.00

48539.00

50966.00

35th m

7.5%

41743.00

52179.00

54788.00

36th m

7.5%

44874.00

56093.00

58898.00

37th m

7.5%

48240.00

60300.00

63315.00

38th m

7.5%

51858.00

64823.00

68064.00

39th m

7.5%

55747.00

69684.00

73168.00

40th m

7.5%

59928.00

74910.00

78656.00

442203.00

552757.00

580396.00

44220.00

55276.00

58040.00

Beyond 30m upto 40 m


Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).

Including 20% Including 5%


for Kentledge
for
dewatering, if
required

31st m

10%

65921.00

79105.00

32nd

10%

72513.00

87016.00

91367.00

33rd m

10%

79764.00

95717.00

100503.00

34th m

10%

87740.00

105288.00

110552.00

35th m

10%

96514.00

115817.00

121608.00

36th m

10%

106165.00

127398.00

133768.00

37th m

10%

116782.00

140138.00

147145.00

38th m

10%

128460.00

154152.00

161860.00

39th m

10%

141306.00

169567.00

178045.00

40th m

10%

155437.00

186524.00

195850.00

1050602.00

1260722.00

1323758.00

105060.00

126072.00

132376.00

Total Cost from 30m upto 40m


Avg Rate per metre
12.19

Remarks/
Input ref.

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Avg Rate per metre


(v)

Cost Rs

Beyond 20m upto 30 m

Total Cost from 30m upto 40m


12.19 B

Rate Rs

16th m

Total Cost from 10m upto 20m


12.19 B

Quantity

83060.00

Soft Rock (Twin D Type Well )


Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a)

b)

Labour
Mate

day

0.86

151.44

130.24

L-12

Sinker ( skilled )

day

4.50

164.69

741.11

L-15

Sinking helper (semi-skilled)

day

15.00

230.00

3450.00

L-14

Diver

day

1.50

264.50

396.75

L-07

Machinery
Page 60 of 264

Sr No

Ref. to
MoRTH
Spec.

Quantity

Rate Rs

Unit

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Air compressor with pneumatic breakers

hour

8.33

1073.50

8942.26

P&M-075

hour

6.00

740.15

4440.90

P&M-063

Consumables in sinking @ 10 per cent of (b)

1338.32

Add for dewatering @ 5 per cent, if required


c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

736.07
4035.13
2421.08

Rate per metre = (a+b+c+d)


12.19

Cost Rs

Remarks/
Input ref.

Description

26631.84
say

26632.00

1460.00

Hard Rock (Twin D Type Well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a)

b)

c)

Material
Geletine80 per cent

Kg

10.00

146.00

Electric detonators

each.

40.00

14.56

Mate

day

1.34

151.44

202.93

L-12

Driller

day

2.00

264.50

529.00

L-06

Blaster

day

0.25

264.50

66.13

L-03

Mazdoor

day

25.00

136.69

3417.25

L-13

Mazdoor (Skilled)

day

4.25

164.69

699.93

L-15

hour

10.00

1073.50

10735.00

P&M-075

hour

3.00

740.15

2220.45

P&M-063

Labour

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if required.

893.53

Consumables in sinking @ 10 per cent of (b).

1384.90

d)

Overhead charges @ 0.2 on (a+b+c)

4438.30

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2662.98

Rate per metre = (a+b+c+d+e)


12.20

1200

M-104

582.40 M-094/100

29292.81
say

29293.00

Pneumatic sinking of wells with equipment of approved


design, drawing and specifications worked by
competent and trained personnel and comprising of
compression and decompression chambers, reducers,
two air locks separately for men and plant & materials,
arrangement for supply of fresh air to working
chambers, check valves, exhaust valves, shafts made
from steel plates of riveted construction not less than 6
mm thick to withstand an air pressure of 0.50 MPa,
controlled blasting of hard rock where required,
staircases and 1 m wide landing plateforms with railing,
arrangement for compression and decompression,
electric lighting of 50 V maximum, proper rooms for rest
and medical examinations and compliance with safety
precautions as per IS:4138, all as per clause1207.6 of
MoRTH Specifications.

Unit - 1 cum
Taking output = 5 cum
a)

Material
M35 grade RCC corbel provided for supporting of
equipment (Dimensions as per ground conditions).
Rate may be adopted vide Item 12.8 (H)

Cum

8.00

5217.00

41736.00

Item 12.8
(H)

HYSD bar reinforcement in corbel

tonne

0.48

45000.00

21600.00

M-082

Gelatine 80 per cent

Kg

1.50

146.00

219.00

M-104

Electric detonators

each

6.00

14.56

Blasting material

Page 61 of 264

87.36 M-094/100

Sr No

Ref. to
MoRTH
Spec.

Description
b)

c)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Labour
Medical Officer

day

0.50

304.20

152.10

L-16

Para medical personnel

day

1.00

264.50

264.50

L-19

Mate

day

1.86

151.44

281.68

L-12

Driller

day

1.00

264.50

264.50

L-06

Blaster

day

0.50

264.50

132.25

L-03

Mazdoor (for cutting, blasting, cleaning, removal of


Material etc.)
Mazdoor (Skilled) (for fixation and removal of adopter
for air lock, carrying out mechanical and electrical
operations and repairs and other skilled jobs.)

day

30.00

136.69

4100.70

L-13

day

10.00

164.69

1646.90

L-15

Diver

day

4.00

264.50

1058.00

L-07

(i) Induction, deinduction and erection of plant and


equipment including all components and
accessories for pneumatic method of well sinking.

hour

6.00

1000.00

6000.00

P&M-082

Induction and deinduction

L.S

Erection at site and commissioning

L.S

Usage of plant and equipment for pneumatic method of


well sinking
Air compressor 250 cfm, 2 nos.

hour

Hire and running charges of crane of 15 tonne capacity

Machinery

100000.00
150000.00
6.00

4170.00

25020.00

P&M-038

hour

2x6

319.00

3828.00

P&M-001

hour

6.00

349.59

2097.56

P&M-072

Motorised barge of 20 tonne capacity

hour

6.00

100.00

600.00

P&M-066

Boat to carry atleast 20 persons

hour

6.00

100.00

600.00

P&M-066

Electric generating set 33 KVA

hour

6.00

406.80

2440.80

P&M-079

Tipper 10 tonne capacity

hour

6.00

339.00

2034.00

P&M-048

d)

Overhead charges @ 0.2 on (a+b+c)

64485.47

e)

Contractor's profit @ 0.1 on (a+b+c+d)

38691.28

Cost for 5 cum = a+b+c+d+e (see notes below)


Rate per cum = (a+b+c+d+e)/5
Note

1.The cost of induction, deinduction and erection of


equipment shall be divided by the total quantity of pneumatic
sinking for all the wells of a particular bridge to arrive at the
per cum rate on account of this item.
2.Cost of pneumatic sinking per cum of individual wells will
be added to the cost indicated at (1) above to arrive at the
final rate of pneumatic sinking per cum.
3.The cost of induction and deinduction will depend upon the
distance involved for shifting of equipment which may be
assessed in individual cases as per actual ground conditions
at the time of making of cost estimates.
4.In case pneumatic sinking is involved on a dry bed, the
provision of barge and boat may be omitted.
5.The necessity and dimensions of the corbel will be as per
actual ground conditions.
6.Small equipments like welding sets, pumps, vibrators,
pneumatic tools, portable lamps, fire extinguishers, hose
pipes etc., have not been included as the same are covered
as items of minor T&P under overhead charges.
7.Depth of sinking shall be restricted to 30 m.

12.21

1207

Sand Filling in Wells complete as per Drawing and


Technical Specifications.
Unit = 1 cum
Taking output = 1 cum
a)

Material
Sand (assuming 20 per cent voids )

b)

c)

cum

1.20

476.80

572.16

M-006

Mate

day

0.01

151.44

1.51

L-12

Mazdoor

day

0.30

136.69

41.01

L-13

Labour

Overhead charges @ 0.2 on (a+b)


Page 62 of 264

122.94

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c)

1200 &
1900

Remarks/
Input ref.

73.76

Rate per cum (a+b+c+d)


12.22

Cost Rs

811.38
say

811.00

47250.00

Providing Steel Liner 10 mm thick for Curbs and 6 mm


thick for Steining of Wells including Fabricating and
Setting out as per Detailed Drawing.
Unit = 1 MT
Taking output = 1 MT
a)

Material
i) Structural steel including 5 per cent wastage

b)

tonne

1.05

45000.00

Mate

day

1.24

151.44

187.79

L-12

Fitter

day

6.00

230.00

1380.00

L-08

Blacksmith

day

5.00

230.00

1150.00

L-01

Welder

day

5.00

264.50

1322.50

L-02

Mazdoor

day

10.00

136.69

1366.90

L-13

c)

Electrodes, cutting gas and other consumables @ 5


per cent on cost a (a) above.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2362.50
11003.94
6602.36

Rate for per MT (a+b+c+d)

72625.98
say

12.23

1100 &
1700

M-179

Labour

72626.00

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a)

Materials
PCC Grade M35

cum

6.62

5260.00

34821.20 Item 12.11


(C) iv

Hire and running charges of hydraulic piling rig with


power unit and complete accessories including shifting
from one bore location to another.

hour

6.00

5464.00

32784.00

P&M-036

Hire and running charges of light crane for lowering


reinforcement cage
Hire and running charges of Bentonite pump

hour

0.50

357.00

178.50

P&M-013

hour

Loader I cum bucket capacity.

hour

6.00 Rate included in


piling rig
0.30
806.00

241.80

P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile


bore hole
Bentonite

hour

0.30

339.00

101.70

P&M-048

kg

300.00

4.10

1230.00

M-071

Mate/Supervisor

day

0.14

151.44

21.20

L-12

Mazdoor

day

3.50

136.69

478.42

L-13

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)

c)

Machinery( for boring and construction )

Labour

d)

Overhead charges @ 0.2 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

7007.12
4204.27

Cost for 15 m = a+b+c+d+d+e

81068.21

Rate per metre (a+b+c+d+e)/15

5404.55
say

12.24
1100,160
0 & 1700

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1000 mm

Page 63 of 264

5405.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit = meter
Taking output = 10 m
a)

Materials
PCC Grade M35

cum

7.85

5260.00

41291.00 Item 12.11


(C) iv

Hire and running charges of hydraulic piling rig with


power unit and complete accessories including shifting
from one bore location to another.

hour

6.00

5464.00

32784.00

P&M-036

Hire and running charges of light crane for lowering


reinforcement cage
Hire and running charges of Bentonite pump

hour

0.50

357.00

178.50

P&M-013

hour

Loader I cum bucket capacity.

hour

6.00 Rate included in


piling rig
0.40
806.00

322.40

P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile


bore hole
Bentonite

hour

0.40

339.00

135.60

P&M-048

kg

350.00

4.10

1435.00

M-071

Mate/Supervisor

day

0.16

151.44

24.23

L-12

Mazdoor

day

4.00

136.69

546.76

L-13

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)

c)

Machinery( for boring and construction )

Labour

d)

Overhead charges @ 0.2 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

7085.30
4251.18

Cost for 10 m = a+b+c+d+d+e

88053.97

Rate per metre (a+b+c+d+e)/10

8805.40
say

12.25

1100 &
1700

8805.00

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a)

Materials
PCC Grade M35

cum

10.17

5260.00

53494.20 Item 12.11


(C) iv

Hire and running charges of hydraulic piling rig with


power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering
reinforcement cage
Hire and running charges of Bentonite pump

hour

6.00

5464.00

32784.00

P&M-036

hour

0.50

357.00

178.50

P&M-013

hour

Loader I cum bucket capacity.

hour

6.00 Rate included in


piling rig
0.50
806.00

403.00

P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile


bore hole
Bentonite

hour

0.50

339.00

169.50

P&M-048

kg

385.00

4.10

1578.50

M-071

Mate/Supervisor

day

0.18

151.44

27.26

L-12

Mazdoor

day

4.50

136.69

615.11

L-13

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)

c)

Machinery( for boring and construction )

Labour

d)

Overhead charges @ 0.2 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

7151.17
4290.70

Cost for 9 m = a+b+c+d+d+e

100691.94

Rate per metre (a+b+c+d+e)/9

11187.99
say

Page 64 of 264

11188.00

Sr No
12.26

Ref. to
MoRTH
Spec.

Description

1100 &
1700

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Driven cast-in-place vertical M35 grade R.C.C. Pile


excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 750 mm
Unit = Running meter
Taking output = 40 metre
a)

Materials
PCC Grade M35

cum

17.66

5260.00

92891.60 Item 12.11


(C) iv

i) C.I. shoes for the pile

Kg

160.00

59.60

9536.00

M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m

Kg

70.00

52.15

3650.50

M-124

iii) Steel helmet and cushion block on top of casing


head during driving
Machinery

Kg

50.00

61.00

3050.00

M-173

hour

6.00

5974.88

35849.25

P&M-085

hour

0.50

825.00

412.50

P&M-070

Mate/Supervisor

day

0.12

151.44

18.17

L-12

Mazdoor

day

3.00

136.69

410.07

L-13

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
b) Materials Pile shoes

c)

Hire and running charges of piling rig Including double


acting pile driving hammer complete with power unit
and accessories..
Hiring and running charges for light crane 5 tonnes
lifting capacity for lowering reinforcement and handling
steel casing.
d)

Labour

e)

Overhead charges @ 0.2 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

10585.30
6351.18

Cost for 40 m = a+b+c+d+e

162754.57

Rate per metre (a+b+c+d+e)/40

4068.86
say

Note

12.27

1100 &
1700

4069.00

1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven castin-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
a)

Materials
PCC Grade M35

cum

23.55

5260.00

123873.00 Item 12.11


(C) iv

i) C.I. shoes for the pile

Kg

160.00

59.60

9536.00

M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m

Kg

70.00

52.15

3650.50

M-124

iii) Steel helmet and cushion block on top of casing


head during driving
Machinery

Kg

50.00

61.00

3050.00

M-173

hour

6.00

5974.88

35849.25

P&M-085

hour

0.50

116.53

58.27

P&M-070

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes

c)

Hire and running charges of piling rig Including double


acting pile driving hammer complete with power unit
and accessories.
Hiring and running charges for light crane 5 tonnes
lifting capacity for lowering reinforcement and handling
steel casing.

Page 65 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

d)

Unit

Quantity

Rate Rs

Hire and running charges for light crane for lowering


reinforcement cage.
Labour

hour

0.50

357.00

Mate/Supervisor

day

0.16

Mazdoor

day

4.00

e)

Overhead charges @ 0.2 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

P&M-013

151.44

24.23

L-12

136.69

546.76

L-13

10578.70
6347.22
193692.43

Rate per metre (a+b+c+d+e)/30

6456.41
say

12.28

1100 &
1700

Remarks/
Input ref.

178.50

Cost for 30 m = a+b+c+d+e

Note

Cost Rs

6456.00

1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven castin-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1200 mm
Unit = Running meter
Taking output = 20 metre
a)

Materials
PCC Grade M35

cum

22.61

5260.00

118928.60 Item 12.11


(C) iv

i) C.I. shoes for the pile

Kg

160.00

59.60

9536.00

M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m

Kg

70.00

52.15

3650.50

M-124

iii) Steel helmet on top of casing head during driving

Kg

50.00

61.00

3050.00

M-173

Hire and running charges of piling rig Including double


acting pile driving hammer complete with power unit
and accessories.

hour

6.00

5974.88

35849.25

P&M-085

Hiring and running charges for light crane 5 tonnes


lifting capacity for lowering reinforcement and handling
steel casing.
Labour

hour

0.50

116.53

58.27

P&M-070

Mate/Supervisor

day

0.18

151.44

27.26

L-12

Mazdoor

day

4.50

136.69

615.11

L-13

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes

c)

d)

Machinery

e)

Overhead charges @ 0.2 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

10557.28
6334.37

Cost for 20 m = a+b+c+d+e

188606.62

Rate per metre (a+b+c+d+e)/20

9430.33
say

Note

12.29

1100 &
1700

1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven castin-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and &
Technical Specification
Pile Diameter = 500 mm
Unit = Running Meter
Page 66 of 264

9430.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 60 m
a)

Materials
RCC Grade M35

cum

11.78

5114.00

60242.92 Item 12.11


(F) iv

a) C.I Shoes

Kg

240.00

59.60

14304.00

M-080

b) M.S. shoes

Kg

105.00

37.00

3885.00

M-125

Kg

30.00

61.00

1830.00

M-173

c)

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery
Crane20 t capacity

hour

6.00

466.13

2796.75

P&M-073

hour

6.00

1000.00

6000.00

P&M-092

d)

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour
Mate/Supervisor

day

0.12

151.44

18.17

L-12

Mazdoor

day

3.00

136.69

410.07

L-13

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.2 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

894.87

6027.77
3616.66

Cost for 60 m = a+b+c+d+e+f

100026.22

Rate per metre (a+b+c+d+e+f)/60

1667.10
say

Note

12.30

1100 &
1700

1667.00

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and &
Technical Specification
Pile Diameter = 750 mm
Unit = Running Meter
Taking output = 50 m
a)

Materials
RCC Grade M35

cum

22.08

5114.00

112917.12 Item 12.11


(F) iv

a) C.I. shoes

Kg

160.00

59.60

9536.00

M-080

b) M.S. shoes

Kg

70.00

37.00

2590.00

M-125

Kg

40.00

61.00

2440.00

M-173

c)

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery
Crane 40 T capacity

hour

6.00

932.25

5593.50

P&M-074

hour

6.00

1000.00

6000.00

P&M-092

d)

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour
Mate/Supervisor

day

0.16

151.44

24.23

L-12

Mazdoor

day

4.00

136.69

546.76

L-13

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.

1396.48

e)

Overhead charges @ 0.2 on (b+c+d)

5625.39

f)

Contractor's profit @ 0.1 on (b+c+d+e)

3375.24

Cost for 50 m = a+b+c+d+e+f

150044.72

Rate per metre (a+b+c+d+e+f)/50

3000.89
say

Page 67 of 264

3001.00

Sr No

Ref. to
MoRTH
Spec.

Description
Note

12.31

1100 &
1700

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and &
Technical Specification
Pile Diameter = 1000 mm
Unit = Running Meter
Taking output = 40 m
a)

Materials
RCC Grade M35

cum

31.40

5114.00

160579.60 Item 12.11


(F) iv

a) C.I. shoes for the pile

Kg

160.00

59.60

9536.00

M-080

b) M.S. shoes @ 35 Kg per pile of 15 m

Kg

70.00

37.00

2590.00

M-125

Kg

50.00

61.00

3050.00

M-173

c)

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery
Crane 50 t capacity.

hour

6.00

1279.00

7674.00

P&M-011

hour

6.00

1000.00

6000.00

P&M-092

d)

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour
Mate/Supervisor

day

0.20

151.44

30.29

L-12

Mazdoor

day

5.00

136.69

683.45

L-13

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.2 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

1901.43

6293.03
3775.82

Cost for 40 m = a+b+c+d+e+f

202113.63

Rate per metre (a+b+c+d+e+f)/40

5052.84
say

Note

12.32

1100&17
00

5053.00

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and &
Technical Specification
Size of pile - 300 mm x 300 mm
Unit = Running Meter
Taking output = 60 m
a)

Materials

RCC Grade M-35


Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes

c)

cum

5.40

5114.00

27615.60 Item 12.11


(F) iv

a) C I shoes

kg

240.00

59.60

14304.00

M-080

b) M. S shoes

kg

105.00

37.00

3885.00

M-125

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

30.00

61.00

1830.00

M-173

hour

6.00

1237.50

7425.00

P&M-071

hour

6.00

1000.00

6000.00

P&M-092

Mate/Supervisor

day

0.12

151.44

18.17

L-12

Mazdoor

day

3.00

136.69

410.07

L-13

Crane 10 tonne capacity


Vibrating Pile driving hammer complete with power unit
and accessories.
d ) Labour

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Page 68 of 264

614.88

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

e)

Overhead charges @ 0.2 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

Quantity

Rate Rs

4138.45
73138.60

Rate per metre (a+b+c+d+e+f)/60

1218.98
say

12.33

1100
&1700

Remarks/
Input ref.

6897.42

Cost for 60 m = a+b+c+d+e+f

Note

Cost Rs

1219.00

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and &
Technical Specification
Size of pile - 500 mm x 500 mm
Unit = Running Meter
Taking output = 50 m
a)

Materials

RCC Grade M-35


Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes

c)

cum

12.50

5114.00

a) C I shoes

kg

160.00

59.60

9536.00

M-080

b) M. S shoes

kg

70.00

37.00

2590.00

M-125

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

30.00

61.00

1830.00

M-173

hour

6.00

466.13

2796.75

P&M-073

hour

6.00

1000.00

6000.00

P&M-092

Mate/Supervisor

day

0.16

151.44

24.23

L-12

Mazdoor

day

4.00

136.69

546.76

L-13

Crane 20 tonne capacity


Vibrating Pile driving hammer complete with power unit
and accessories.
d ) Labour

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
e)

Overhead charges @ 0.2 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

872.49

4839.25
2903.55

Cost for 50 m = a+b+c+d+e+f

95864.02

Rate per metre (a+b+c+d+e+f)/50

1917.28
say

Note

12.34

1100
&1700

63925.00 Item 12.11


(F) iv

1917.00

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and &
Technical Specification
Size of pile - 750 mm x 750 mm
Unit = Running Meter
Taking output = 40 m
a)

Materials

RCC Grade M-35


Rate for concrete may be adopted same as for bottom
plug vide item no. 13.11( F ) (IV)
b ) Material

cum

22.50

5114.00

115065.00 Item 12.11


(F) iv

a) C I shoes

kg

160.00

59.60

9536.00

M-080

b) M. S shoes

kg

70.00

37.00

2590.00

M-125

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

30.00

61.00

1830.00

M-173

Crane 20 tonne capacity

hour

6.00

466.13

2796.75

P&M-073

Vibrating Pile driving hammer complete with power unit


and accessories.

hour

6.00

1000.00

6000.00

P&M-092

Pile shoes

c)

Page 69 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

d ) Labour
Mate/Supervisor

day

0.18

151.44

27.26

L-12

Mazdoor

day

4.50

136.69

615.11

L-13

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.2 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

1384.60

4955.94
2973.57

Cost for 40 m = a+b+c+d+e+f

147774.22

Rate per metre (a+b+c+d+e+f)/40


Note

12.35

1100,
1900

3694.36
say

3694.00

45000.00

271800.00

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven Vertical Steel Piles complete as per Drawing and
& Technical Specification
Section of the pile - H Section steel column 400 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 70 m
a)

Materials

b)

Structural steel including 5 per cent wastage @ 82.20


kg/m
Machinery

c)

tonnes

6.04

Crane 10 T capacity

hour

6.00

233.06

1398.38

P&M-071

Vibrating Pile driving hammer complete with power unit


and other accessories.
Labour

hour

6.00

1000.00

6000.00

P&M-092

Mate/Supervisor

day

0.12

151.44

18.17

L-12

Mazdoor

day

3.00

136.69

410.07

L-13

Add 0.5 per cent of (a+b+c) for providing steel


helmet on top of pile head during driving, stacking of
piles at site, providing anti-corrosion treatment and
other imponderables during installation.
d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1398.13

56204.95
33722.97

Cost for 70 m = a+b+c+d+e

370952.67

Rate per metre (a+b+c+d+e)/70


12.36

1100
&1900

M-179

5299.32
say

5299.00

45000.00

262350.00

Driven Vertical Steel Piles complete as per Drawing and


& Technical Specification
Section of the pile - H Section steel column 450 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 60 m
a)

Materials

b)

Structural steel including 5 per cent wastage @92.50


kg/m
Machinery

c)

tonnes

5.83

Crane 10 T capacity

hour

6.00

233.06

1398.38

P&M-071

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour

hour

6.00

1000.00

6000.00

P&M-092

Mate/Supervisor

day

0.14

151.44

21.20

L-12

Mazdoor

day

3.50

136.69

478.42

L-13

Add 0.5 per cent of (a+b+c) for providing steel


helmet and cushion block on top of pile head during
driving, stacking of piles at site, providing anti-corrosive
treatment and other imponderables during installation.

1351.24

d)

Overhead charges @ 0.2 on (a+b+c)

54319.85

e)

Contractor's profit @ 0.1 on (a+b+c+d)

32591.91

Page 70 of 264

M-179

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost for 60 m = a+b+c+d+e

5975.18
say

1100

Remarks/
Input ref.

358510.99

Rate per metre (a+b+c+d+e)/60


12.37

Cost Rs

5975.00

Pile Load Test on single Vertical Pile in accordance with


IS:2911(Part-IV)
Unit = 1 MT
Taking output = 1 MT

Note

12.38

1100,
1500
&1700

a) Initial and routine load test

tonne

1.00

300.00

b) Lateral load test

tonne

1.00

5000.00

Cement

tonne

5.12

5000.00

25600.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.90

151.44

136.30

L-12

Mason

day

1.50

230.00

345.00

L-10

Mazdoor for concreting

day

20.00

136.69

2733.80

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

136.69

136.69

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator (capacity 33 KVA)

hour

6.00

406.80

2440.80

P&M-079

Although, this item is incidental to work and is not required to


be included in BOQ of contract, the same is required to be
added in the estimate to assess cost of work.
Cement Concrete for Reinforced Concrete in Pile Cap
complete as per Drawing and Technical Specification

RCC Grade M20


Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

b)

c)

Material

Labour

d)

Formwork @ 4 per cent on cost of concrete i.e. cost


of a) Material, b) Labour and c) Machinery
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2053.60
10678.72
6407.23

Cost for 15 cum = a+b+c+d+e

70479.54

Rate per metre (a+b+c+d+e)/15


12.38A

(ii)

4698.64
say

4699.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

b)

c)

Material
Cement

tonne

5.12

5000.00

25600.00

M-081

Coarse sand

cum

6.75

828.00

5589.00

M-004

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.16

151.44

24.23

L-12

Mason

day

0.38

230.00

87.40

L-10

Mazdoor for concreting

day

2.50

136.69

341.73

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

136.69

136.69

L-13

Batching Plant @ 20 cum/hour

hour

0.75

2232.00

1674.00

P&M-002

Generator 100 KVA

hour

0.75

762.75

572.06

P&M-080

Loader (capacity 1 cum)

hour

0.75

806.00

604.50

P&M-017

hour

2.00

1017.00

2034.00

P&M-049

Labour

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Page 71 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

d)

Formwork @ 4 per cent on cost of concrete i.e. cost


of a) Material, b) Labour and c) Machinery
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Quantity

Rate Rs

tonne.km

37.5L

2.03

hour

0.75

256.00

76.28

Lead =1
km & P&M050

192.00

P&M-007

10542.62
6325.57
69581.31

Rate per metre (a+b+c+d+e)/15

12.38

Remarks/
Input ref.

2027.43

Cost for 15 cum = a+b+c+d+e

Note

Cost Rs

4638.75
say

4639.00

The value of a, b and c may be taken as applicable i.e.


either using concrete mixer or batching plant.
RCC Grade M25
Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

b)

c)

Material
Cement

tonne

5.99

5000.00

29950.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.90

151.44

136.30

L-12

Mason

day

1.50

230.00

345.00

L-10

Mazdoor for concreting

day

20.00

136.69

2733.80

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

136.69

136.69

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator (capacity 33 KVA)

hour

6.00

406.80

2440.80

P&M-079

Labour

d)

Formwork @ 4 per cent on cost of concrete i.e. cost


of a) Material, b) Labour and c) Machinery
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2227.60
11583.52
6950.11

Cost for 15 cum = a+b+c+d+e

76451.22

Rate per metre (a+b+c+d+e)/15


12.38B

(ii)

5096.75
say

5097.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

b)

c)

Material
Cement

tonne

5.99

5000.00

29950.00

M-081

Coarse sand

cum

6.75

828.00

5589.00

M-004

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.16

151.44

24.23

L-12

Mason

day

0.38

230.00

87.40

L-10

Mazdoor for concreting

day

2.50

136.69

341.73

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

136.69

136.69

L-13

Batching Plant @ 20 cum/hour

hour

0.75

2232.00

1674.00

P&M-002

Generator 125 KVA

hour

0.75

652.00

489.00

P&M-018

Loader (capacity 1 cum)

hour

0.75

806.00

604.50

P&M-017

hour

2.00

1017.00

2034.00

P&M-049

tonne.km

37.5L

2.03

76.28

Labour

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer

Page 72 of 264

Lead =1
km & P&M050

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Concrete Pump

hour

d)

Formwork @ 4 per cent on cost of concrete i.e. cost


of a) Material, b) Labour and c) Machinery
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Quantity
0.75

Rate Rs
256.00

P&M-007

11430.15
6858.09
75438.96

Rate per metre (a+b+c+d+e)/15

12.38

192.00

Remarks/
Input ref.

2198.10

Cost for 15 cum = a+b+c+d+e

Note

Cost Rs

5029.26
say

5029.00

The value of a, b and c may be taken as applicable i.e.


either using concrete mixer or batching plant.
RCC Grade M30
Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

b)

c)

Material
Cement

tonne

6.10

5000.00

30500.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.90

151.44

136.30

L-12

Mason

day

1.50

230.00

345.00

L-10

Mazdoor for concreting

day

20.00

136.69

2733.80

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

136.69

136.69

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator (capacity 33 KVA)

hour

6.00

406.80

2440.80

P&M-079

Labour

d)

Formwork @ 4 per cent on cost of concrete i.e. cost


of a) Material, b) Labour and c) Machinery
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2249.60
11697.92
7018.75

Cost for 15 cum = a+b+c+d+e

77206.26

Rate per metre (a+b+c+d+e)/15


'12.38C

(ii)

5147.08
say

5147.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

b)

c)

Material
Cement

tonne

6.10

5000.00

30500.00

M-081

Coarse sand

cum

6.75

828.00

5589.00

M-004

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.16

151.44

24.23

L-12

Mason

day

0.38

230.00

87.40

L-10

Mazdoor for concreting

day

2.50

136.69

341.73

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

136.69

136.69

L-13

Batching Plant @ 20 cum/hour

hour

0.75

2232.00

1674.00

P&M-002

Generator 100 KVA

hour

0.75

762.75

572.06

P&M-080

Loader (capacity 1 cum)

hour

0.75

806.00

604.50

P&M-017
P&M-049

Labour

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

Page 73 of 264

hour

2.00

1017.00

2034.00

tonne.km

37.5L

2.03

76.28

Lead =1
km & P&M050

hour

0.75

256.00

192.00

P&M-007

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

d)

Formwork @ 4 per cent on cost of concrete i.e. cost


of a) Material, b) Labour and c) Machinery
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Quantity

Rate Rs

11561.82
6937.09
76308.03

Rate per metre (a+b+c+d+e)/15

12.38

Remarks/
Input ref.

2223.43

Cost for 15 cum = a+b+c+d+e

Note

Cost Rs

5087.20
say

5087.00

The value of a, b and c may be taken as applicable i.e.


either using concrete mixer or batching plant.
RCC Grade M35
Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

b)

c)

Material
Cement

tonne

6.33

5000.00

31650.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.90

151.44

136.30

L-12

Mason

day

1.50

230.00

345.00

L-10

Mazdoor

day

20.00

136.69

2733.80

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

136.69

136.69

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator (capacity 33 KVA)

hour

6.00

406.80

2440.80

P&M-079

Labour

d)

Formwork @ 4 per cent on cost of concrete i.e. cost


of a) Material, b) Labour and c) Machinery
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2295.60
11937.12
7162.27

Cost for 15 cum = a+b+c+d+e

78784.98

Rate per metre (a+b+c+d+e)/15


'12.38D

(ii)

5252.33
say

5252.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

b)

c)

Material
Cement

tonne

6.33

5000.00

31650.00

M-081

Coarse sand

cum

6.75

828.00

5589.00

M-004

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.16

151.44

24.23

L-12

Mason

day

0.38

230.00

87.40

L-10

Mazdoor for concreting

day

2.50

136.69

341.73

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

136.69

136.69

L-13

Batching Plant @ 20 cum/hour

hour

0.75

2232.00

1674.00

P&M-002

Generator 125 KVA

hour

0.75

652.00

489.00

P&M-018

Loader (capacity 1 cum)

hour

0.75

806.00

604.50

P&M-017
P&M-049

Labour

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump
Formwork @ 4 per cent on cost of concrete i.e. cost
of a) Material, b) Labour and c) Machinery

Page 74 of 264

hour

2.00

1017.00

2034.00

tonne.km

37.5L

2.03

76.28

Lead =1
km & P&M050

hour

0.75

256.00

192.00

P&M-007

2266.10

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Quantity

Rate Rs

7070.25
77772.72

Rate per metre (a+b+c+d+e)/15


1100&17
00

Remarks/
Input ref.

11783.75

Cost for 15 cum = a+b+c+d+e

12.39

Cost Rs

5184.85
say

5185.00

Levelling Course for Pile cap


Providing and laying of PCC M15 levelling course
100mm thick below the pile cap.
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

4.13

5000.00

20650.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

40 mm aggregate

cum

8.10

916.00

7419.60

M-055

20 mm Aggregate

cum

4.05

1028.00

4163.40

M-053

10 mm Aggregate

cum

1.35

1005.00

1356.75

M-051

Mate

day

0.86

151.44

130.24

L-12

Mason

day

1.50

230.00

345.00

L-10

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

Labour

Machinery

d)

Overhead charges @ 0.2 on (a+b+c)

9086.64

e)

Contractor's profit @ 0.1 on (a+b+c+d)

5451.98

Cost for 15 cum = a+b+c+d+e

59971.82

Rate per metre (a+b+c+d+e)/15


12.40

1600

3998.12
say

3998.00

Supplying, Fitting and Placing un-coated HYSD bar


Reinforcement in Foundation complete as per Drawing
and Technical Specifications.
Unit = 1 MT
Taking output = 1 MT
a)

Material
HYSD bars including5 per cent overlaps and wastage
Binding wire

b)
Labour for cutting, bending, shifting to site, tying
and placing in position
Mate

tonne

1.05

45000.00

47250.00

M-082

Kg

6.00

100.00

600.00

M-072

day

0.40

151.44

60.58

L-12

Blacksmith

day

2.00

264.50

529.00

L-02

Mazdoor

day

6.00

136.69

820.14

L-13

9851.94
5911.17
65022.83
12.41

1600

say

65023.00

Supplying, fitting and placing un-coated Mild steel


reinforcement complete in foundation as per drawing
and technical specification
Unit = 1 MT
Taking output = 1 MT
a)

Material
MS bars including 5 per cent overlaps and wastage
Binding wire

b)
Labour for straightening, cutting, bending, shifting
to site, tying and placing in position
Mate
Blacksmith
Page 75 of 264

tonne

1.05

47307.50

49672.88

M-126

Kg

6.00

100.00

600.00

M-072

day

0.43

151.44

65.12

L-12

day

2.25

264.50

595.13

L-02

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor

day

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Quantity
6.50

Rate Rs
136.69

Cost Rs
888.49
10364.32
6218.59

Rate for per MT (a+b+c+d)

68404.52
say

Page 76 of 264

68405.00

Remarks/
Input ref.
L-13

CHAPTER-13
SUB-STRUCTURE
Sr No
13.1

13.2

Ref. to
MoRTH
Spec.

Description

1300 &
2200

Unit

Brick masonry work in 1:3 in sub-structure complete


excluding pointing and plastering, as per drawing and
Technical Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class
Cement mortar 1:3 (Rate as in Item 12.6 A subanalysis)
b) Labour
Mate
Mason
Mazdoor
Add for scaffolding @ 5 per cent of cost of material
and labour
c) Overhead charges @ 0.2 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per cum (a+b+c+d)

1300 &
2200

Pointing with cement mortar (1:3 ) on brick work in


substructure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6 )
Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.2 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per 10 sqm (a+b+c+d)

each
cum

day
day
day

Quantity

Rate Rs

Cost Rs

500.00
0.24

4.42
3425.00

2209.09
822.00

M-079
Item 12.6
(A)

0.06
0.80
0.80

151.44

9.09
0.00
109.35
157.48

L-12
L-11
L-13

136.69

say

661.40
396.84
4365.25
4365.00

cum

0.03

3425.00

102.75

Item 12.6
(A)

day
day
day

0.04
0.50
0.50

151.44
223.36
136.69

L-12
L-11
L-13

say

6.06
111.68
68.35
57.77
34.66
381.26
381.00

b)

13.3

Note
1300 &
2200

Scaffolding is already included in item 13.1


Plastering with cement mortar (1:3 ) on brick work in
sub-structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6)
Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.2 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per 10 sqm (a+b+c+d)

Remarks/
Input ref.

cum

0.144

3425.00

493.20

Item 12.6
(A)

day
day
day

0.04
0.50
0.50

151.44
223.36
136.69

L-12
L-11
L-13

say

6.06
111.68
68.35
135.86
81.51
896.65
897.00

b)

13.4

Note

1.Scaffolding is already included in item no. 13.1


2.The number of masons and Mazdoors already catered in
the cement mortar have been taken into account while
providing these categories in brick masonry, pointing and
plastering.

1400 &
2200

Stone masonry work in cement mortar 1:3 for


substructure complete as per drawing and Technical
Specifications
A

Random Rubble Masonry


( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone
Through and bond stone
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6)

Page 1 of 264

cum
No

1.00
7.00

2604.51
14.45

2604.51
101.17

M-148
M-182

cum

0.33

3425.00

1130.25

Item 12.6
(A)

Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit

c)

Labour
Mate
Mason
Mazdoor
Add for scaffolding @ 5 per cent of cost of a)
Material and b) Labour
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

day
day
day

Quantity

0.10
1.20
1.20

Rate Rs

Cost Rs

151.44
223.36
136.69

L-12
L-11
L-13

899.46
539.68

Rate per cum (a+b+c+d)


13.4

15.14
268.03
164.03
214.16

Remarks/
Input ref.

5936.43
say

5936.00

Coursed rubble masonry (first sort )


Unit = cum
Taking output = 1 cum
a) Material
Stone

cum

1.10

2604.51

2864.96

M-148

Through and bond stone

each

7.00

14.45

101.17

M-182

cum

0.30

3425.00

1027.50

Item 12.6
(A)

Mate

day

0.12

151.44

18.17

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

1.50

136.69

205.04

L-13

(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6)
b)

Labour

c)

Add for scaffolding @ 5 per cent of cost of material


and labour
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

227.59
955.89
573.54

Rate per cum (a+b+c+d)


13.4

L-12

6308.91
say

6309.00

Ashlar masonry ( first sort )


Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone

cum

1.11

2705.04

3002.59

M-169

Through and bond stone

each

7.00

14.45

101.17

M-182

cum

0.33

3425.00

1130.25

Item 12.6
(A)

Mate

day

0.20

151.44

30.29

Mason

day

2.50

223.36

558.40

L-11

Mazdoor

day

2.50

136.69

341.73

L-13

(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6)
b)

Labour for masonry work

c)

Add for scaffolding @ 5 per cent of cost of a)


Material and b) Labour
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

258.22
1084.53
650.72

Rate per cum (a+b+c+d)

7157.90
say

Note

13.5

The labour already considered in the cement mortar have


been taken into account while providing these categories in
the stone masonry works.
Plain/Reinforced cement concrete in sub-structure
complete as per drawing and Technical Specifications

1500,
1700 &
2200

Unit = cum
Taking output = 1 cum
A

PCC Grade M15

(p) Height upto 5m

Page 2 of 264

7158.00

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Same as Item 12.8 (A) upto 5 m height, except for formwork


which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (A)
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3080.00 Item 12.8 (A)

10.00

308.00
677.60
406.56

Rate perm (a+b+c+d+e+f)

4472.16
say

13.5

4472.00

PCC Grade M20

(p) Height upto 5m


Same as Item 12.8 (B) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (B)
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3390.00 Item 12.8 (B) PCC

10.00

339.00
745.80
447.48

Rate perm (a+b+c+d+e+f)

4922.28
say

13.5

4922.00

PCC Grade M25

(p) Height upto 5m


Same as Item 12.8 (D) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.75 per cent of cost of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3667.00 Item 12.8 (D)

10.00

366.70
806.74
484.04

Rate perm (a+b+c+d+e+f)

5324.48
say

13.5 C
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3614.00 Item 12.8 (D)

10.00

361.40
795.08
477.05

Rate perm (a+b+c+d+e+f)

5247.53
say

13.5 C

5324.00

5248.00

(q) Height 5m to 10m


Same as Item 12.8 (D) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.75 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case I
Page 3 of 264

3667.00 Item 12.8 (D)

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

12.00

440.04

2.00

73.34
836.08
501.65

Rate perm (a+b+c+d+e+f)

5518.10
say

13.5 C
(q)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case II
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3614.00

12.00

433.68

2.00

72.28
823.99
494.40

Rate perm (a+b+c+d+e+f)

5438.35
say

13.5 C

(r)

5518.00

5438.00

Height above 10m


Same as Item 12.8 (D) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.75 per cent of cost of
material, labour and machinery.

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case I
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3667.00 Item 12.8 (D)

15.00

550.05

4.00

146.68
872.75
523.65

Rate perm (a+b+c+d+e+f)

5760.12
say

13.5 C
(r)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case II
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3614.00 Item 12.8 (D)

15.00

542.10

4.00

144.56
860.13
516.08

Rate perm (a+b+c+d+e+f)

5676.87
say

13.5

5760.00

5677.00

PCC Grade M30

(p) Height upto 5m


Same as Item 12.8 (F) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.50 per cent of cost of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case I
Page 4 of 264

3697.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

10.00

369.70
813.34
488.00

Rate perm (a+b+c+d+e+f)

5368.04
say

13.5 D
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3641.00

10.00

364.10
801.02
480.61

Rate perm (a+b+c+d+e+f)

5286.73
say

13.5 D

5368.00

5287.00

(q) Height 5m to 10m


Same as Item 12.8 (F) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.50 per cent of
cost of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case I
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3697.00

12.00

443.64

2.00

73.94
842.92
505.75

Rate perm (a+b+c+d+e+f)

5563.25
say

13.5 D
(q)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case II
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3641.00

12.00

436.92

2.00

72.82
830.15
498.09

Rate perm (a+b+c+d+e+f)

5478.98
say

13.5 D

(r)

5563.00

5479.00

Height above 10m


Same as Item 12.8 (F) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.50 per cent of cost of
material, labour and machinery

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case I
d) formwork
Add 15 per cent of cost of material, labour and
machinery (a+b+c) for Formwork

Page 5 of 264

3697.00

15.00

554.55

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

e)

Add 4 per cent of cost of material, Labour and


machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

Cost Rs

4.00

147.88
879.89
527.93

Rate perm (a+b+c+d+e+f)

5807.25
say

13.5 D
(r)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case II
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3641.00

15.00

546.15

4.00

145.64
866.56
519.93

Rate perm (a+b+c+d+e+f)

5719.28
say

13.5

5807.00

5719.00

RCC Grade M20

(p) Height upto 5m


Same as Item 12.8 (C) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3443.00

10.00

344.30
757.46
454.48

Rate perm (a+b+c+d+e+f)

4999.24
say

13.5 E
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3388.00

10.00

338.80
745.36
447.22

Rate perm (a+b+c+d+e+f)

4919.38
say

13.5 E

4999.00

4919.00

(q) Height 5m to 10m


For height, upto 10m, add 2 per cent of cost as above
excluding formwork. For cost of formwork add 12 per cent of
cost of material, labour and machinery instead of 4 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case I
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Rate perm (a+b+c+d+e+f)

3443.00

12.00

413.16

2.00

68.86
785.00
471.00
5181.03

Page 6 of 264

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs
say

13.5 E
(q)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case II
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3388.00

12.00

406.56

2.00

67.76
772.46
463.48

Rate perm (a+b+c+d+e+f)

5098.26
say

13.5 E

(r)

5181.00

5098.00

Height above 10m


Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 4 per cent of cost of
material, labour and machinery.

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case I
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3443.00

15.00

516.45

4.00

137.72
819.43
491.66

Rate perm (a+b+c+d+e+f)

5408.26
say

13.5 E
(r)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case II
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3388.00

15.00

508.20

4.00

135.52
806.34
483.81

Rate perm (a+b+c+d+e+f)

5321.87
say

13.5

5408.00

5322.00

RCC Grade M25

(p) Height upto 5m


Same as Item 12.8 (E) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.75 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3723.00

10.00

372.30
819.06
491.44

Rate perm (a+b+c+d+e+f)

5405.80
say

13.5 F
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Page 7 of 264

5406.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c) of Item 12.8 (E) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3740.00

10.00

374.00
822.80
493.68

Rate perm (a+b+c+d+e+f)

5430.48
say

13.5 F

For height, upto 10m, add 1.8 per cent of cost as above
excluding formwork. For cost of formwork add 11.8 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case I
d) formwork

e)

Add 11.8 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3723.00

11.80

439.31

1.80

67.01
845.87
507.52

Rate perm (a+b+c+d+e+f)

5582.71
say

13.5 F
(q)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case II
d) formwork

e)

Add 11.8 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

11.80

441.32

1.80

67.32
849.73
509.84
5608.20
say

(r)

5583.00

3740.00

Rate perm (a+b+c+d+e+f)


13.5 F

5430.00

(q) Height 5m to 10m

5608.00

Height above 10m


For height, above 10m, add 4 per cent of cost as above
excluding formwork. For cost of formwork add 15 per cent of
cost of material, labour and machinery

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case I
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3723.00

15.00

558.45

4.00

148.92
886.07
531.64

Rate perm (a+b+c+d+e+f)

5848.09
say

13.5 F
(r)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case II
d) formwork
Add 15 per cent of cost of material, labour and
machinery (a+b+c) for Formwork

Page 8 of 264

5848.00

3740.00

15.00

561.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

e)

Add 4 per cent of cost of material, Labour and


machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

Cost Rs

4.00

149.60
890.12
534.07

Rate perm (a+b+c+d+e+f)

5874.79
say

13.5

5875.00

RCC Grade M30

(p) Height upto 5m


Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3740.00

10.00

374.00
822.80
493.68

Rate perm (a+b+c+d+e+f)

5430.48
say

13.5 G
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3686.00

10.00

368.60
810.92
486.55

Rate perm (a+b+c+d+e+f)

5352.07
say

13.5 G

5352.00

(q) Height 5m to 10m


For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case I
d) formwork

e)

Add 11.5 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3740.00

11.50

430.10

1.60

59.84
845.99
507.59

Rate perm (a+b+c+d+e+f)

5583.52
say

13.5 G
(q)

5430.00

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case II
d) formwork

e)

Add 11.5 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5584.00

3686.00

11.50

423.89

1.60

58.98
833.77
500.26

Rate perm (a+b+c+d+e+f)

5502.90
say
Page 9 of 264

5503.00

Remarks/
Input ref.

Sr No
13.5 G

Ref. to
MoRTH
Spec.

Description
(r)

Unit

Quantity

Rate Rs

Cost Rs

Height above 10m


For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent of
cost of material, labour and machinery

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case I
d) formwork

e)

Add 14 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3740.00

14.00

523.60

3.50

130.90
878.90
527.34

Rate perm (a+b+c+d+e+f)

5800.74
say

13.5 G
(r)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case II
d) formwork

e)

Add 14 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3686.00

14.00

516.04

3.50

129.01
866.21
519.73

Rate perm (a+b+c+d+e+f)

5716.99
say

13.5

5801.00

5717.00

RCC Grade M35

(p) Height upto 5m


Same as Item 12.8 (H) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3816.00

10.00

381.60
839.52
503.71

Rate perm (a+b+c+d+e+f)

5540.83
say

13.5 H
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3838.00

10.00

383.80
844.36
506.62

Rate perm (a+b+c+d+e+f)

5572.78
say

13.5 H

5541.00

(q) Height 5m to 10m


For height, upto 10m, add 1.4 per cent of cost as above
excluding formwork. For cost of formwork add 11 per cent of
cost of material, labour and machinery .
Case Using concrete Mixer
I

Page 10 of 264

5573.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c) of Item 12.8 (H) Case I
d) formwork

e)

Add 11 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3816.00

11.00

419.76

1.40

53.42
857.84
514.70

Rate perm (a+b+c+d+e+f)

5661.72
say

13.5 H
(q)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case II
d) formwork

e)

Add 11 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3838.00

11.00

422.18

1.40

53.73
862.78
517.67

Rate perm (a+b+c+d+e+f)

5694.36
say

13.5 H

(r)

5662.00

5694.00

Height above 10m


For height, above 10m, add 3 per cent of cost as above
excluding formwork. For cost of formwork add 13 per cent of
cost of material, labour and machinery

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case I
d) formwork

e)

Add 13 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3816.00

13.00

496.08

3.00

114.48
885.31
531.19

Rate perm (a+b+c+d+e+f)

5843.06
say

13.5 H
(r)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case II
d) formwork

e)

Add 13 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3838.00

13.00

498.94

3.00

115.14
890.42
534.25

Rate perm (a+b+c+d+e+f)

5876.75
say

Note

5843.00

The basic components of this analysis are the same as


those of items 13.8 (A to H). The only changes are as under:
a)
Ramps/Stairs: Extra expenditure on structures which
are more than 5 m high @ 2 per cent of cost for height upto
10 m and 4 per cent for heights above 10 m will be involved
for approaching the work spot by providing higher ramp/stair
case for use by the working parties.

Page 11 of 264

5877.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

b) The above mentioned percentages have been suitably


modified for different categories as cost for various
categories varies, whereas effort for access for same height
will be similar. As the cost of richer concrete is comparatively
more, the percentage to be added has been reduced to
maintain the same cost for extra efforts.
13.6

Section
1600 &
2200

Supplying, fitting and placing HYSD bar reinforcement in


sub-structure complete as per drawing and Technical
Specifications
Output: MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent overlaps and wastage
Binding wire
b)
Labour for cutting, bending, shifting to site, tying
and placing in position
Mate

tonne

1.05

45000.00

47250.00

M-082

kg

6.00

100.00

600.00

M-072

day

0.34

151.44

51.49

L-12

Blacksmith

day

2.00

264.50

529.00

L-02

Mazdoor

day

6.50

136.69

888.49

L-13

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

9863.79
5918.28

Rate for per MT (a+b+c+d)


13.7

1600 &
2200

65101.05
say

65101.00

Supplying, fitting and placing Mild steel reinforcement


complete in sub-structure as per drawing and Technical
Specification
Unit = MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage
Binding wire
b) Labour for straightening, cutting, bending, shifting
to site, tying and placing in position
Mate

tonne

1.05

47307.50

49672.88

M-126

kg

6.00

100.00

600.00

M-072

day

0.28

151.44

42.40

L-12

Blacksmith

day

1.50

264.50

396.75

L-02

Mazdoor

day

5.50

136.69

751.80

L-13

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

10292.76
6175.66

Rate for per MT (a+b+c+d)


13.8

2706 &
2200

67932.25
say

67932.00

Providing weep holes in Brick masonry/Plain/


Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full
width of the structure with slope of 1V :20H towards
drawing foce. Complete as per drawing and Technical
Specifications
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per cent )

metre

31.50

65.00

2047.50

Average length of weep hole is taken as one metre for the


purpose of estimating.
MS clamp

each.

30.00

13.00

390.00

M-123

each.

10.00

6.50

65.00

M-056/10

cum

0.05

3425.00

171.25

Item 12.6
(A)

Mate

day

0.03

151.44

4.54

L-12

Mason

day

0.50

223.36

111.68

L-11

collar for AC pipe (average) taking 10% of above pipe


rate
Cement mortar 1:3 (Rate as in Item 12.6)
b)

M-056

Labour

Page 12 of 264

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor

day

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Quantity
0.25

Rate Rs

Cost Rs

136.69

338.90
3727.87

Rate per m (a+b+c+d)/30

124.26
say

13.9

L-13

564.83

Cost for 30 m = a+b+c+d

Note

34.17

Remarks/
Input ref.

124.00

1. In case of stone masonry, the size of the weep hole shall


be 150 mm x 80 mm or circular with 150 mm diameter.
2. For structure in stone masonry, the weep holes shall be
deemed to be included in the item of stone masonry work
and shall not be paid separately.
Back filling behind abutment, wing wall and return wall
complete as per drawing and Technical Specification

710.1.4.
of
IRC:78
& 2200

Unit = cum
Taking output = 10 cum
A

Granular material
a)

b)

Labour
Mate

day

0.28

151.44

42.40

L-12

Mazdoor

day

7.00

136.69

956.83

L-13

cum

12.00

727.79

8733.48

M-009

Plate compactor/power rammer

hour

2.50

101.70

254.25

P&M-086

Water Tanker

hour

0.05

200.00

10.00

P&M-060

Material
Granular material

c)

Machinery

d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1999.39
1199.64

Cost for 10 cum of granular backfill = a+b+c+d+e

13195.99

Rate per cum = (a+b+c+d+e)/10

1319.60
say

13.9

a)

b)

Labour
Mate

day

0.28

151.44

42.40

L-12

Mazdoor for filling, watering, ramming etc.

day

7.00

136.69

956.83

L-13

cum

12.00

476.80

5721.60

M-006

Plate compactor/power rammer

hour

2.50

101.70

254.25

P&M-086

Water Tanker

hour

0.06

200.00

12.00

P&M-060

Material
Sand

c)

Machinery

d)

Overhead charges @ 0.2 on (a+b+c)

1397.42

e)

Contractor's profit @ 0.1 on (a+b+c+d)

838.45

Cost for 10 cum of sandy backfill = a+b+c+d+e

9222.95

Rate per cum = (a+b+c+d+e)/10


13.10

710.1.4.
of
IRC:78
and
2200

1320.00

Sandy material

922.29
say

922.00

151.44

48.46

Providing and laying of Filter media with granular


materials/stone crushed aggregates satisfying the
requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm
with smaller size towards the soil and bigger size
towards the wall and provided over the entire surface
behind abutment, wing wall and return wall to the full
height compacted to a firm condition complete as per
drawing and Technical Specification.
Unit = cum
Taking output = 10 cum.
a) Labour
Mate

day
Page 13 of 264

0.32

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Mazdoor for filling, watering, ramming etc.

day

7.00

136.69

956.83

L-13

Mazdoor (Skilled)

day

1.00

164.69

164.69

L-15

10728.00

b)

Material
cum

12.00

894.00

c)

Filter media of stone aggregate conforming to clause


2504.2.2. of MoRTH specifications.
Machinery
Water Tanker of 6 KL capacity

hour

0.06

200.00

d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

P&M-060

1429.20
15721.17

Rate per cum = (a+b+c+d+e)/10

1572.12
say

2000,
1000 &
2200

12.00

M-012

2382.00

cost for 10 cum of Fiter Media = a+b+c+d+e

13.11

Remarks/
Input ref.

1572.00

Supplying, fitting and fixing in position true to line and


level cast steel rocker bearing conforming to IRC: 83(Pt.1) section IX and clause 2003 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a)

b)

Labour
Mate

day

0.06

151.44

9.09

L-12

Mazdoor (Skilled)

day

0.50

164.69

82.35

L-15

Mazdoor

day

1.00

136.69

136.69

L-13

each.

1.00

50000.00

50000.00

Material
Cast steel rocker bearing assembly of 250 tonne
design load capacity duly painted complete with all its
components as per drawing and specifications
Add 1 per cent of cost of bearing assembly for
foundation anchorage bolts, lifting arrangements,
grease and other consumables.

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

500.00

10145.62
6087.37

cost for 250 tonnes capacity bearing = a+b+c+d

66961.12

Rate per tonne capacity = (a+b+c+d)/250

267.84
say

13.12

2000 ,
1000 &
2200

M-065

268.00

Supplying, fitting and fixing in position true to line and


level forged steel roller bearing conforming to IRC:
83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as per
drawing and Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a)

b)

Labour
Mate

day

0.06

151.44

9.09

L-12

Mazdoor

day

1.00

136.69

136.69

L-13

Mazdoor (Skilled)

day

0.50

164.69

82.35

L-15

each.

1.00

41309.00

41309.00

Material
Forged steel roller bearing of 250 tonne design load
capacity duly painted complete with all its components
as per drawing and specifications
Add 1 per cent of cost of bearing assembly for
foundation anchorage bolts, lifting arrangements,
grease and other consumables.

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

413.09

8390.04
5034.03

cost for 250 tonnes capacity bearing = a+b+c+d

55374.28

Rate per tonne capacity = (a+b+c+d)/250

221.50
say

Page 14 of 264

221.00

M-067

Sr No
13.13

Ref. to
MoRTH
Spec.
2000 &
2200

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Supplying, fitting and fixing in position true to line and


level sliding plate bearing with PTFE surface sliding on
stainless steel complete including all accessories as per
drawing and Technical Specifications and BS: 5400,
section 9.1 & 9.2 (for PTFE)
and clause 2004 of
MoRTH Specifications.
Unit: one tonne capacity
Considering a 80 tonne capacity bearing for this analysis
a)

b)

Labour
Mate

day

0.06

151.44

9.09

L-12

Mazdoor

day

1.00

136.69

136.69

L-13

Mazdoor (Skilled)

day

0.50

164.69

82.35

L-15

each.

1.00

16378.00

16378.00

Material
PTFE sliding plate bearing assembly of 80 tonnes
design load capacity duly painted complete with all its
components as per drawing and Technical
Specifications

c)

Add 1 per cent for foundation anchorage bolts and


consumables.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

163.78
3353.98
2012.39

cost for 80 tonnes capacity bearing = a+b+c+d

22136.27

Rate per tonne capacity = (a+b+c+d)/80

276.70
say

13.14

2000 &
2200

M-069

277.00

Supplying, fitting and fixing in position true to line and


level elastomeric bearing conforming to IRC: 83 (Part-II)
section IX and clause 2005 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one cubic centimetre
Considering an elastomeric bearing of size 500 x 400 x 96
mm for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel
plates = 4545 cu.cm.
Hence volume of elastometer = 14655 cu.cm.
a)

b)

Labour
Mate

day

0.06

151.44

9.09

L-12

Mazdoor

day

1.00

136.69

136.69

L-13

Mazdoor (Skilled)

day

0.50

164.69

82.35

L-15

each.

1.00

15000.00

15000.00

Material
Elastomeric bearing assembly consisting of 7 layers of
elastomer bonded to 6 nos. internal reinforcing steel
laminates by the process of vulcanisation, complete
with all components as per drawing and Technical
Specifications.

c)

Add 1 per cent of cost of bearing assembly for


foundation anchorage bolts and consumables.
Overhead charges @ 0.2 on (a+b)

150.00

d)

Contractor's profit @ 0.1 on (a+b+c)

1845.37

cost for 19200cc of elastomeric bearing = a+b+c+d

20299.12

3075.62

Rate per cc of elastomeric bearing = (a+b+c+d)/19200

1.06
say

13.15

2000 &
2200

Supplying, fitting and fixing in position true to line and


level sliding plate bearing with stainless steel plate
sliding on stainless steel plate with mild steel matrix
complete including all accessories as per drawing and
Technical Specifications.
Unit: one tonne capacity
Considering the sliding bearing of 80 tonnes design capacity
for this analysis.
a) Labour
Page 15 of 264

1.00

M-066

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Mate

day

0.04

151.44

6.06

L-12

Mazdoor

day

0.75

136.69

102.52

L-13

Mazdoor (Skilled)

day

0.35

164.69

57.64

L-15

each.

1.00

16378.00

16378.00

b)

Material

c)

Supply of sliding plate bearing of 80 tonne design


capacity complete as per drawings and Technical
Specifications.
Add 1 per cent of cost of bearing assembly for
foundation anchorage bolts and consumables.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2004.96

cost for 80 tonnes of capacity bearing = a+b+c+d

22054.56

M-070

163.78
3341.60

275.68
say
13.16

2000 &
2200

276.00

Supplying, fitting and fixing in position true to line and


level POT-PTFE bearing consisting of a metal piston
supported by a disc or unreinforced elastomer confined
within a metal cylinder, sealing rings, dust seals, PTFE
surface sliding against stainless steel mating surface,
complete assembly to be of cast steel/fabricated
structural steel, metal and elastomer elements to be as
per IRC: 83 part-I & II respectively and other parts
conforming to BS: 5400, section 9.1 & 9.2 and clause
2006 of MoRTH Specifications complete as per drawing
and approved Technical Specifications.

Unit: one tonne capacity

387.20

Considering a Pot bearing assembly of 250 tonne capacity


for this analysis.
a) Labour

b)

Mate

day

0.08

151.44

12.12

L-12

Mazdoor

day

1.50

136.69

205.04

L-13

Mazdoor (Skilled)

day

0.50

164.69

82.35

L-15

each.

1.00

41309.00

41309.00

Material
Pot type bearing assembly consisting of a metal piston
supported by a disc, PTFE pads providing sliding
surfaces against stainless steel mating together with
cast steel assemblies/fabricated structural steel
assemblies duly painted with all components as per
clause 2006 and complete as per drawings and
Technical Specifications.

c)

Add 1 per cent of cost of bearing assembly for


foundation anchorage bolts and consumables.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

413.09
8404.32
5042.59

cost for 250 tonnes capacity bearing = a+b+c+d

55468.49

Rate per tonne capacity = (a+b+c+d)/250

221.87
say

Page 16 of 264

222.00

M-068

CHAPTER-14
SUPER-STRUCTURE
Sr No
14.1

Ref. to
MoRTH
Spec.

Description

1500
&1600
1700

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Furnishing and Placing Reinforced/ Prestressed cement


concrete in super-structure as per drawing and
Technical Specification
RCC Grade M20

Case I Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

5.12

5000.00

25600.00

M-081

Coarse sand

cum

6.75

710.46

4795.61

M-005

20 mm Aggregate

cum

8.10

1028.00

8326.80

M-053

10 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

Mate

day

0.86

151.44

130.24

L-12

Mason

day

1.50

223.36

335.04

L-11

Mazdoor

day

20.00

136.69

2733.80

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

233.00

1398.00

P&M-009

Generator 33 KVA

hour

6.00

406.80

2440.80

P&M-079

Labour

Machinery

Basic Cost of Labour, Material & Machinery (a+b+c)


for 15 cum
For formwork and staging add the following:
14.1A
Case I

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
15 cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

51188.00

51188.00
20.00

10237.60
12285.12
7371.07

Cost for 15 cum = a+b+c+d+e+f

81081.79

Rate per cum = (a+b+c+d+e+f)/15

5405.45
say

14.1A
Case I (i)

(q)

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

51188.00
25.00

12797.00
12797.00
7678.20

Cost for 15 cum = a+b+c+d+e+f

84460.20

Rate per cum = (a+b+c+d+e+f)/15

5630.68
say

14.1A
Case I (i)

(r)

5631.00

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 30 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

51188.00
30.00

15356.40
13308.88
7985.33

Cost for 15 cum = a+b+c+d+e+f

87838.61

Rate per cum = (a+b+c+d+e+f)/15

5855.91
say

14.1A
Case I

5405.00

Height 5m to 10m

(ii) For T-beam & slab, 25-35 per cent of (a+b+c)


(p)

Height upto 5m
Page 1 of 264

5856.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

51188.00
25.00

12797.00
12797.00
7678.20

Cost for 15 cum = a+b+c+d+e+f

84460.20

Rate per cum = (a+b+c+d+e+f)/15

5630.68
say

14.1A
Case I
(ii)

(q)

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 30 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

51188.00
30.00

15356.40
13308.88
7985.33

Cost for 15 cum = a+b+c+d+e+f

87838.61

Rate per cum = (a+b+c+d+e+f)/15

5855.91
say

14.1A
Case I
(ii)

(r)

5856.00

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 35 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

51188.00
35.00

17915.80
13820.76
8292.46

Cost for 15 cum = a+b+c+d+e+f

91217.02

Rate per cum = (a+b+c+d+e+f)/15


14.1A

5631.00

Height 5m to 10m

6081.13
say

6081.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

40.92

5000.00

204600.00

M-081

Coarse sand

cum

54.00

828.00

44712.00

M-004

20 mm Aggregate

cum

64.80

1028.00

66614.40

M-053

10 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

Mate

day

0.84

151.44

127.21

Mason

day

3.00

223.36

670.08

L-11

Mazdoor

day

18.00

136.69

2460.42

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2232.00

13392.00

P&M-002

Generator 100 KVA

hour

6.00

762.75

4576.50

P&M-080

Loader

hour

6.00

806.00

4836.00

P&M-017

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

Lead =1
km & P&M050

6.00

256.00

1536.00

P&M-007

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c)


for 120 cum
For formwork and staging add the following:
14.1A
Case II

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)


Page 2 of 264

402806.00

402806.00
20.00

80561.20
96673.44

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

58004.06

Cost for 120 cum = a+b+c+d+e+f

638044.70

Rate per cum = (a+b+c+d+e+f)/120

5317.04
say

14.1A
Case II
(i)

(q)

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

402806.00
25.00

100701.50
100701.50
60420.90

Cost for 120 cum = a+b+c+d+e+f

664629.90

Rate per cum = (a+b+c+d+e+f)/120

5538.58
say

14.1A
Case II
(i)

(r)

e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

402806.00
30.00

120841.80
104729.56
62837.74

Cost for 120 cum = a+b+c+d+e+f

691215.10

Rate per cum = (a+b+c+d+e+f)/120

5760.13
say

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

402806.00
25.00

100701.50
100701.50
60420.90

Cost for 120 cum = a+b+c+d+e+f

664629.90

Rate per cum = (a+b+c+d+e+f)/120

5538.58
say

(q)

e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

402806.00
30.00

120841.80
104729.56
62837.74

Cost for 120 cum = a+b+c+d+e+f

691215.10

Rate per cum = (a+b+c+d+e+f)/120

5760.13
say

5760.00

(r)

Height above 10m

402806.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 35 per cent of (a+b+c)

35.00

140982.10
108757.62

e)

Overhead charges @ 0.2 on (a+b+c+d)

65254.57

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

717800.29

Cost for 120 cum = a+b+c+d+e+f

5981.67

Rate per cum = (a+b+c+d+e+f)/120


14.1

5539.00

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1A
Case II
(ii)

5760.00

(ii) For T-beam & slab, 25-35 per cent of (a+b+c)


(p)

14.1A
Case II
(ii)

5539.00

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1A
Case II

5317.00

Height 5m to 10m

say

B
Case I RCC Grade M25
Using Concrete Mixer
Unit = 1 cum
Page 3 of 264

5982.00

Taking output = 15 cum


a)

Material

tonne

5.99

5000.00

29950.00

M-081

Cement

cum

6.75

710.46

4795.61

M-005

Coarse sand

cum

8.10

1028.00

8326.80

M-053

20 mm Aggregate

cum

5.40

1005.00

5427.00

M-051
L-12

10 mm Aggregate
b)

Labour

day

0.86

151.44

130.24

Mate

day

1.50

223.36

335.04

L-11

Mason

day

20.00

136.69

2733.80

L-13

Machinery

hour

6.00

233.00

1398.00

P&M-009

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

406.80

2440.80

P&M-079

Mazdoor
c)

Generator 33 KVA

14.1B
Case I

55538.00

(i)

Basic Cost of Labour, Material & Machinery (a+b+c)


for 15 cum
For formwork and staging add the following:

(p)

For solid slab super-structure, 20-30 per cent of (a+b+c)


Height upto 5m

55538.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 20 per cent of (a+b+c)

20.00

11107.60
13329.12

e)

Overhead charges @ 0.2 on (a+b+c+d)

7997.47

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

87972.19

Cost for 15 cum = a+b+c+d+e+f

5864.81

Rate per cum = (a+b+c+d+e+f)/15


14.1B
Case I (i)

say

Height 5m to 10m

55538.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 25 per cent of (a+b+c)

25.00

13884.50
13884.50

e)

Overhead charges @ 0.2 on (a+b+c+d)

8330.70

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

91637.70

Cost for 15 cum = a+b+c+d+e+f

6109.18

Rate per cum = (a+b+c+d+e+f)/15


14.1B
Case I (i)

say

55538.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 30 per cent of (a+b+c)

30.00

16661.40
14439.88

e)

Overhead charges @ 0.2 on (a+b+c+d)

8663.93

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

95303.21

Cost for 15 cum = a+b+c+d+e+f

6353.55

Rate per cum = (a+b+c+d+e+f)/15

say

6354.00

(ii)
(p)

For T-beam & slab, 25-35 per cent of (a+b+c)


Height upto 5m

55538.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 25 per cent of (a+b+c)

25.00

13884.50
13884.50

e)

Overhead charges @ 0.2 on (a+b+c+d)

8330.70

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

91637.70

Cost for 15 cum = a+b+c+d+e+f

6109.18

Rate per cum = (a+b+c+d+e+f)/15


14.1B
Case I
(ii)

6109.00

(r)

Height above 10m

14.1B
Case I

5865.00

(q)

say

(q)

Page 4 of 264

6109.00

Height 5m to 10m

55538.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 30 per cent of (a+b+c)

30.00

16661.40
14439.88

e)

Overhead charges @ 0.2 on (a+b+c+d)

8663.93

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

95303.21

Cost for 15 cum = a+b+c+d+e+f

6353.55

Rate per cum = (a+b+c+d+e+f)/15


14.1B
Case I
(ii)

say

Height above 10m

55538.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 35 per cent of (a+b+c)

35.00

19438.30
14995.26

e)

Overhead charges @ 0.2 on (a+b+c+d)

8997.16

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

98968.72

Cost for 15 cum = a+b+c+d+e+f

6597.91

Rate per cum = (a+b+c+d+e+f)/15


14.1B

6354.00

(r)

say

6598.00

Case II
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a)

Material

tonne

47.95

5000.00

239750.00

M-081

Cement

cum

54.20

828.00

44877.60

M-004

Coarse sand

cum

64.80

1028.00

66614.40

M-053

20 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

10 mm Aggregate
b)

Labour

day

0.84

151.44

127.21

Mate

day

3.00

223.36

670.08

L-12
L-11

Mason

day

18.00

136.69

2460.42

L-13

Machinery

hour

6.00

2232.00

13392.00

P&M-002

Batching Plant @ 20 cum/hour

hour

6.00

762.75

4576.50

P&M-080

Generator 100 KVA

hour

6.00

806.00

4836.00

P&M-017

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

Lead =1
km & P&M050

6.00

256.00

1536.00

P&M-007

Mazdoor
c)

Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km

Lead beyond 1 Km, L - lead in Kilometer

hour

Concrete Pump

14.1B
Case II

438122.00

(i)

Basic Cost of Labour, Material & Machinery (a+b+c)


for 120 cum
For formwork and staging add the following:

(p)

For solid slab super-structure, 20-30 per cent of (a+b+c)


Height upto 5m

438122.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 20 per cent of (a+b+c)

20.00

87624.40
105149.28

e)

Overhead charges @ 0.2 on (a+b+c+d)

63089.57

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

693985.25

Cost for 120 cum = a+b+c+d+e+f

5783.21

Rate per cum = (a+b+c+d+e+f)/120


14.1B
Case II
(i)

say

5783.00

(q)

Height 5m to 10m

438122.00

Basic Cost of Labour, Material & Machinery (a+b+c)


120 cum
Page 5 of 264

for

25.00

109530.50

d)

Formwork and staging 25 per cent of (a+b+c)

e)

Overhead charges @ 0.2 on (a+b+c+d)

109530.50
65718.30

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

722901.30

Cost for 120 cum = a+b+c+d+e+f

6024.18

Rate per cum = (a+b+c+d+e+f)/120


14.1B
Case II
(i)

say

Height above 10m

438122.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 30 per cent of (a+b+c)

30.00

131436.60
113911.72

e)

Overhead charges @ 0.2 on (a+b+c+d)

68347.03

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

751817.35

Cost for 120 cum = a+b+c+d+e+f

6265.14

Rate per cum = (a+b+c+d+e+f)/120


14.1B
Case II

say

For T-beam & slab, 25-35 per cent of (a+b+c)


Height upto 5m

438122.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 25 per cent of (a+b+c)

25.00

109530.50
109530.50

e)

Overhead charges @ 0.2 on (a+b+c+d)

65718.30

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

722901.30

Cost for 120 cum = a+b+c+d+e+f

6024.18

Rate per cum = (a+b+c+d+e+f)/120

say

438122.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 30 per cent of (a+b+c)

30.00

131436.60
113911.72

e)

Overhead charges @ 0.2 on (a+b+c+d)

68347.03

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

751817.35

Cost for 120 cum = a+b+c+d+e+f

6265.14

Rate per cum = (a+b+c+d+e+f)/120

say

6265.00

(r)

Height above 10m

438122.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 35 per cent of (a+b+c)

35.00

153342.70
118292.94

e)

Overhead charges @ 0.2 on (a+b+c+d)

70975.76

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

780733.40

Cost for 120 cum = a+b+c+d+e+f

6506.11

Rate per cum = (a+b+c+d+e+f)/120


14.1

6024.00

(q)

Height 5m to 10m

14.1B
Case II
(ii)

6265.00

(ii)
(p)

14.1B
Case II
(ii)

6024.00

(r)

say

6506.00

C
Case I RCC Grade M 30
Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a)

Material

tonne

6.10

5000.00

30500.00

M-081

Cement

cum

6.75

710.46

4795.61

M-005

Coarse sand

cum

8.10

1028.00

8326.80

M-053

20 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

10 mm Aggregate
b)

Labour

day

0.90

151.44

136.30

L-12

Mate

day

1.50

223.36

335.04

L-11

Mason

day

21.00

136.69

2870.49

L-13

Page 6 of 264

Mazdoor
c)

Machinery

hour

6.00

233.00

1398.00

P&M-009

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

406.80

2440.80

P&M-079

Generator 33 KVA

14.1C
Case I

56231.00

(i)

Basic Cost of Labour, Material & Machinery (a+b+c)


for 15 cum
For formwork and staging add the following:

(p)

For solid slab super-structure, 20-30 per cent of (a+b+c)


Height upto 5m

56231.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 20 per cent of (a+b+c)

20.00

11246.20
13495.44

e)

Overhead charges @ 0.2 on (a+b+c+d)

8097.26

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

89069.90

Cost for 15 cum = a+b+c+d+e+f

5937.99

Rate per cum = (a+b+c+d+e+f)/15


14.1C
Case I (i)

say

Height 5m to 10m

56231.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 25 per cent of (a+b+c)

25.00

14057.75
14057.75

e)

Overhead charges @ 0.2 on (a+b+c+d)

8434.65

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

92781.15

Cost for 15 cum = a+b+c+d+e+f

6185.41

Rate per cum = (a+b+c+d+e+f)/15


14.1C
Case I (i)

say

56231.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 30 per cent of (a+b+c)

30.00

16869.30
14620.06

e)

Overhead charges @ 0.2 on (a+b+c+d)

8772.04

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

96492.40

Cost for 15 cum = a+b+c+d+e+f

6432.83

Rate per cum = (a+b+c+d+e+f)/15

say

6433.00

(ii)
(p)

For T-beam & slab, 25-35 per cent of (a+b+c)


Height upto 5m

56231.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 25 per cent of (a+b+c)

25.00

14057.75
14057.75

e)

Overhead charges @ 0.2 on (a+b+c+d)

8434.65

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

92781.15

Cost for 15 cum = a+b+c+d+e+f

6185.41

Rate per cum = (a+b+c+d+e+f)/15


14.1C
Case I
(ii)

6185.00

(r)

Height above 10m

14.1C
Case I

5938.00

(q)

say

6185.00

(q)

Height 5m to 10m

56231.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 30 per cent of (a+b+c)

30.00

16869.30
14620.06

e)

Overhead charges @ 0.2 on (a+b+c+d)

8772.04

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

96492.40

Cost for 15 cum = a+b+c+d+e+f

6432.83

Rate per cum = (a+b+c+d+e+f)/15

say

Page 7 of 264

6433.00

14.1C
Case I
(ii)

(r)

Height above 10m

56231.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 35 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

35.00

19680.85
15182.37
9109.42
100203.64

Cost for 15 cum = a+b+c+d+e+f

6680.24

Rate per cum = (a+b+c+d+e+f)/15


14.1C

say

6680.00

Case II
Using Batching Plant, Transit Mixer and Concrete Pump.
Unit = cum
Taking output = 120 cum
a)

Material

tonne

48.79

5000.00

243950.00

M-081

Cement

cum

54.60

828.00

45208.80

M-004

Coarse sand

cum

64.80

1028.00

66614.40

M-053

20 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

10 mm Aggregate
b)

Labour

day

0.88

151.44

133.27

Mate

day

3.00

223.36

670.08

L-12
L-11

Mason

day

19.00

136.69

2597.11

L-13

Mazdoor
c)

Machinery

hour

6.00

2232.00

13392.00

P&M-002

Batching Plant @ 20 cum/hour

hour

6.00

762.75

4576.50

P&M-080

Generator 100 KVA

hour

6.00

806.00

4836.00

P&M-017

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

Lead =1
km & P&M050

6.00

256.00

1536.00

P&M-007

Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km

Lead beyond 1 Km, L - lead in Kilometer


Concrete Pump

14.1C
Case II

hour

442796.00

(i)

Basic Cost of Labour, Material & Machinery (a+b+c)


for 120 cum
For formwork and staging add the following:

(p)

For solid slab super-structure, 20-30 per cent of (a+b+c)


Height upto 5m

442796.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 20 per cent of (a+b+c)

20.00

88559.20
106271.04

e)

Overhead charges @ 0.2 on (a+b+c+d)

63762.62

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

701388.86

Cost for 120 cum = a+b+c+d+e+f

5844.91

Rate per cum = (a+b+c+d+e+f)/120


14.1C
Case II
(i)

say

Height 5m to 10m

442796.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 25 per cent of (a+b+c)

25.00

110699.00
110699.00

e)

Overhead charges @ 0.2 on (a+b+c+d)

66419.40

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

730613.40

Cost for 120 cum = a+b+c+d+e+f

6088.45

Rate per cum = (a+b+c+d+e+f)/120


14.1C
Case II
(i)

5845.00

(q)

say

6088.00

(r)

Height above 10m

442796.00
Page 8 of 264

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 30 per cent of (a+b+c)

30.00

132838.80
115126.96

e)

Overhead charges @ 0.2 on (a+b+c+d)

69076.18

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

759837.94

Cost for 120 cum = a+b+c+d+e+f

6331.98

Rate per cum = (a+b+c+d+e+f)/120


14.1C
Case II

say

(p)

For T-beam & slab, 25-35 per cent of (a+b+c)


Height upto 5m

442796.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 25 per cent of (a+b+c)

25.00

110699.00
110699.00

e)

Overhead charges @ 0.2 on (a+b+c+d)

66419.40

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

730613.40

Cost for 120 cum = a+b+c+d+e+f

6088.45

Rate per cum = (a+b+c+d+e+f)/120


14.1C
Case II
(ii)

say

442796.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 30 per cent of (a+b+c)

30.00

132838.80
115126.96

e)

Overhead charges @ 0.2 on (a+b+c+d)

69076.18

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

759837.94

Cost for 120 cum = a+b+c+d+e+f

6331.98

Rate per cum = (a+b+c+d+e+f)/120

say

6332.00

(r)

Height above 10m

442796.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 35 per cent of (a+b+c)

35.00

154978.60
119554.92

e)

Overhead charges @ 0.2 on (a+b+c+d)

71732.95

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

789062.47

Cost for 120 cum = a+b+c+d+e+f

6575.52

Rate per cum = (a+b+c+d+e+f)/120


14.1

6088.00

(q)

Height 5m to 10m

14.1C
Case II
(ii)

6332.00

(ii)

say

6576.00

D
Case I

RCC/PSC Grade M35


Using Concrete Mixer.
Unit = 1 cum
Taking output = 15 cum
a)

Material

tonne

6.33

5000.00

31650.00

M-081

Cement

cum

6.75

710.46

4795.61

M-005

Coarse sand

cum

8.10

1028.00

8326.80

M-053

20 mm Aggregate

cum

5.40

1005.00

5427.00

M-051
L-12

10 mm Aggregate
b)

Labour

day

0.90

151.44

136.30

Mate

day

1.50

223.36

335.04

L-11

Mason

day

21.00

136.69

2870.49

L-13

Machinery

hour

6.00

233.00

1398.00

P&M-009

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

406.80

2440.80

P&M-079

Mazdoor
c)

Generator 33 KVA

14.1D
Case I

57381.00

(i)

Basic Cost of Labour, Material & Machinery (a+b+c)


for 15 cum
For formwork and staging add the following:

(p)

For solid slab super-structure, 18-28 per cent of (a+b+c)

Page 9 of 264

Height upto 5m

57381.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 18 per cent of (a+b+c)

18.00

10328.58
13541.92

e)

Overhead charges @ 0.2 on (a+b+c+d)

8125.15

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

89376.65

Cost for 15 cum = a+b+c+d+e+f

5958.44

Rate per cum = (a+b+c+d+e+f)/15


14.1D
Case I (i)

say

Height 5m to 10m

57381.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 23 per cent of (a+b+c)

23.00

13197.63
14115.73

e)

Overhead charges @ 0.2 on (a+b+c+d)

8469.44

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

93163.79

Cost for 15 cum = a+b+c+d+e+f

6210.92

Rate per cum = (a+b+c+d+e+f)/15


14.1D
Case I (i)

say

57381.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 28 per cent of (a+b+c)

28.00

16066.68
14689.54

e)

Overhead charges @ 0.2 on (a+b+c+d)

8813.72

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

96950.94

Cost for 15 cum = a+b+c+d+e+f

6463.40

Rate per cum = (a+b+c+d+e+f)/15

say

For T-beam & slab, 23-33 per cent of (a+b+c)


Height upto 5m

57381.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 23 per cent of (a+b+c)

23.00

13197.63
14115.73

e)

Overhead charges @ 0.2 on (a+b+c+d)

8469.44

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

93163.79

Cost for 15 cum = a+b+c+d+e+f

6210.92

Rate per cum = (a+b+c+d+e+f)/15

say

6211.00

(q)

Height 5m to 10m

57381.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 28 per cent of (a+b+c)

28.00

16066.68
14689.54

e)

Overhead charges @ 0.2 on (a+b+c+d)

8813.72

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

96950.94

Cost for 15 cum = a+b+c+d+e+f

6463.40

Rate per cum = (a+b+c+d+e+f)/15


14.1D
Case I
(ii)

6463.00

(ii)
(p)

14.1D
Case I
(ii)

6211.00

(r)

Height above 10m

14.1D
Case I

5958.00

(q)

say

6463.00

(r)

Height above 10m

57381.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 33 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

33.00

18935.73
15263.35
9158.01
100738.08

Cost for 15 cum = a+b+c+d+e+f

6715.87

Rate per cum = (a+b+c+d+e+f)/15

say

Page 10 of 264

6716.00

14.1D
Case I

(iii)
(p)

For box girder and balanced cantilever, 38-58 per cent


of cost of concrete.
Height upto 5m

57381.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 38 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

38.00

21804.78
15837.16
9502.29
104525.23

Cost for 15 cum = a+b+c+d+e+f

6968.35

Rate per cum = (a+b+c+d+e+f)/15


14.1D
Case I
(iii)

say

Height 5m to 10m

57381.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 48 per cent of (a+b+c)

48.00

27542.88
16984.78

e)

Overhead charges @ 0.2 on (a+b+c+d)

10190.87

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

112099.52

Cost for 15 cum = a+b+c+d+e+f

7473.30

Rate per cum = (a+b+c+d+e+f)/15


14.1D
Case I
(iii)

6968.00

(q)

say

7473.00

(r)

Height above 10m

57381.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 58 per cent of (a+b+c)

58.00

33280.98
18132.40

e)

Overhead charges @ 0.2 on (a+b+c+d)

10879.44

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

119673.81

Cost for 15 cum = a+b+c+d+e+f

7978.25

Rate per cum = (a+b+c+d+e+f)/15

say

7978.00

Case II
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a)

Material

tonne

50.64

5000.00

253200.00

M-081

Cement

cum

54.00

828.00

44712.00

M-004

Coarse sand

cum

64.80

1028.00

66614.40

M-053

20 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

10 mm Aggregate
b)

Labour

day

0.88

151.44

133.27

Mate

day

3.00

223.36

670.08

L-12
L-11

Mason

day

19.00

136.69

2597.11

L-13

Mazdoor
c)

Machinery

hour

6.00

2232.00

13392.00

P&M-002

Batching Plant @ 20 cum/hour

hour

6.00

762.75

4576.50

P&M-080

Generator 100 KVA

hour

6.00

806.00

4836.00

P&M-017

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

Lead =1
km & P&M050

6.00

256.00

1536.00

P&M-007

Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km

Lead beyond 1 Km, L - lead in Kilometer


Concrete Pump

14.1D
Case II

hour

451549.00

(i)

Basic Cost of Labour, Material & Machinery (a+b+c)


for 120 cum
For formwork and staging add the following:

(p)

For solid slab super-structure, 18-28 per cent of (a+b+c)

Page 11 of 264

Height upto 5m

451549.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 18 per cent of (a+b+c)

18.00

81278.82
106565.56

e)

Overhead charges @ 0.2 on (a+b+c+d)

63939.34

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

703332.72

Cost for 120 cum = a+b+c+d+e+f

5861.11

Rate per cum = (a+b+c+d+e+f)/120


14.1D
Case II
(i)

say

(q)

Height 5m to 10m

451549.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 23 per cent of (a+b+c)

23.00

103856.27
111081.05

e)

Overhead charges @ 0.2 on (a+b+c+d)

66648.63

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

733134.96

Cost for 120 cum = a+b+c+d+e+f

6109.46

Rate per cum = (a+b+c+d+e+f)/120


14.1D
Case II
(i)

say

451549.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 28 per cent of (a+b+c)

28.00

126433.72
115596.54

e)

Overhead charges @ 0.2 on (a+b+c+d)

69357.93

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

762937.19

Cost for 120 cum = a+b+c+d+e+f

6357.81

Rate per cum = (a+b+c+d+e+f)/120

say

For T-beam & slab, 23-33 per cent of (a+b+c)


Height upto 5m

451549.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 23 per cent of (a+b+c)

23.00

103856.27
111081.05

e)

Overhead charges @ 0.2 on (a+b+c+d)

66648.63

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

733134.96

Cost for 120 cum = a+b+c+d+e+f

6109.46

Rate per cum = (a+b+c+d+e+f)/120

say

6109.00

(q)

Height 5m to 10m

451549.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 28 per cent of (a+b+c)

28.00

126433.72
115596.54

e)

Overhead charges @ 0.2 on (a+b+c+d)

69357.93

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

762937.19

Cost for 120 cum = a+b+c+d+e+f

6357.81

Rate per cum = (a+b+c+d+e+f)/120


14.1D
Case II
(ii)

6358.00

(ii)
(p)

14.1D
Case II
(ii)

6109.00

(r)

Height above 10m

14.1D
Case II

5861.00

say

6358.00

(r)

Height above 10m

451549.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 33 per cent of (a+b+c)

33.00

149011.17
120112.03

e)

Overhead charges @ 0.2 on (a+b+c+d)

72067.22

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

792739.42

Cost for 120 cum = a+b+c+d+e+f

6606.16

Rate per cum = (a+b+c+d+e+f)/120

say

Page 12 of 264

6606.00

14.1D
Case II

(iii)
(p)

For box girder and balanced cantilever, 38-58 per cent


of cost of concrete.
Height upto 5m

451549.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 38 per cent of (a+b+c)

38.00

171588.62
124627.52

e)

Overhead charges @ 0.2 on (a+b+c+d)

74776.51

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

822541.66

Cost for 120 cum = a+b+c+d+e+f

6854.51

Rate per cum = (a+b+c+d+e+f)/120


14.1D
Case II
(iii)

say

Height 5m to 10m

451549.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 48 per cent of (a+b+c)

48.00

216743.52
133658.50

e)

Overhead charges @ 0.2 on (a+b+c+d)

80195.10

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

882146.13

Cost for 120 cum = a+b+c+d+e+f

7351.22

Rate per cum = (a+b+c+d+e+f)/120


14.1D
Case II
(iii)

say

7351.00

(r)

Height above 10m

451549.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 58 per cent of (a+b+c)

58.00

261898.42
142689.48

e)

Overhead charges @ 0.2 on (a+b+c+d)

85613.69

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

941750.59

Cost for 120 cum = a+b+c+d+e+f

7847.92

Rate per cum = (a+b+c+d+e+f)/120


14.1

6855.00

(q)

say

7848.00

E
Case 1 PSC Grade M-40
Using concrete mixer.
Unit = 1 cum
Taking output = 15 cum
a)

Material

tonne

6.45

5000.00

32250.00

M-081

Cement

cum

6.75

710.46

4795.61

M-005

Coarse sand

cum

8.10

1028.00

8326.80

M-053

20 mm Aggregate

cum

5.40

1005.00

5427.00

M-051

10 mm Aggregate

kg

25.80

44.70

1153.26

M-180
L-12

Admixture @ 0.4 per cent of cement


b)

Labour

day

0.96

151.44

145.38

Mate

day

2.00

223.36

446.72

L-11

Mason

day

22.00

136.69

3007.18

L-13

Machinery

hour

6.00

233.00

1398.00

P&M-009

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

406.80

2440.80

P&M-079

Mazdoor
c)

Generator 33 KVA

14.1E
Case I

59391.00

(i)

Basic Cost of Labour, Material & Machinery (a+b+c)


for 15 cum
For formwork and staging add the following:

(p)

For solid slab super-structure, 20-30 per cent of (a+b+c)


Height upto 5m

59391.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)


Page 13 of 264

20.00

11878.20
14253.84
8552.30

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

94075.34

Cost for 15 cum = a+b+c+d+e+f

6271.69

Rate per cum = (a+b+c+d+e+f)/15


14.1E
Case I (i)

say

Height 5m to 10m

59391.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 25 per cent of (a+b+c)

25.00

14847.75
14847.75

e)

Overhead charges @ 0.2 on (a+b+c+d)

8908.65

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

97995.15

Cost for 15 cum = a+b+c+d+e+f

6533.01

Rate per cum = (a+b+c+d+e+f)/15


14.1E
Case I (i)

say

59391.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 30 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

30.00

17817.30
15441.66
9265.00
101914.96

Cost for 15 cum = a+b+c+d+e+f

6794.33

Rate per cum = (a+b+c+d+e+f)/15

say

For T-beam & slab, 25-35 per cent of (a+b+c)


Height upto 5m

59391.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 25 per cent of (a+b+c)

25.00

14847.75
14847.75

e)

Overhead charges @ 0.2 on (a+b+c+d)

8908.65

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

97995.15

Cost for 15 cum = a+b+c+d+e+f

6533.01

Rate per cum = (a+b+c+d+e+f)/15

say

59391.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 30 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

30.00

17817.30
15441.66
9265.00
101914.96

Cost for 15 cum = a+b+c+d+e+f

6794.33

Rate per cum = (a+b+c+d+e+f)/15

say

6794.00

(r)

Height above 10m

59391.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 35 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

35.00

20786.85
16035.57
9621.34
105834.76

Cost for 15 cum = a+b+c+d+e+f

7055.65

Rate per cum = (a+b+c+d+e+f)/15


14.1E

6533.00

(q)

Height 5m to 10m

14.1E
Case I
(ii)

6794.00

(ii)
(p)

14.1E
Case I
(ii)

6533.00

(r)

Height above 10m

14.1E
Case I

6272.00

(q)

say

7056.00

5000.00

258000.00

Case II
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a)

Material

tonne
Page 14 of 264

51.60

M-081

Cement

cum

54.00

828.00

44712.00

M-004

Coarse sand

cum

64.80

1028.00

66614.40

M-053

20 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

10 mm Aggregate

kg

206.40

44.70

9226.08

M-180
L-12

Admixture @ 0.4 per cent of cement


b)

Labour

day

0.94

151.44

142.35

Mate

day

3.50

223.36

781.76

L-11

Mason

day

20.00

136.69

2733.80

L-13

Mazdoor
c)

Machinery

hour

6.00

2232.00

13392.00

P&M-002

Batching Plant @ 20 cum/hour

hour

6.00

762.75

4576.50

P&M-080

Generator 100 KVA

hour

6.00

806.00

4836.00

P&M-017
P&M-049

Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km

Lead beyond 1 Km, L - lead in Kilometer


Concrete Pump

14.1E
Case II

(i)
(p)

hour

15.00

1017.00

15255.00

tonne.km

300L

2.03

610.20

hour

6.00

256.00

465833.00

Basic Cost of Labour, Material & Machinery (a+b+c) for


120 cum
For formwork and staging add the following:
For solid/voided slab super-structure, 18-28 per cent of
(a+b+c)
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 18 per cent of (a+b+c)

465833.00
18.00

83849.94
109936.59

e)

Overhead charges @ 0.2 on (a+b+c+d)

65961.95

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

725581.48

Cost for 15 cum = a+b+c+d+e+f

6046.51

Rate per cum = (a+b+c+d+e+f)/120


14.1E
Case II
(i)

say

465833.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 23 per cent of (a+b+c)

23.00

107141.59
114594.92

e)

Overhead charges @ 0.2 on (a+b+c+d)

68756.95

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

756326.46

Cost for 120 cum = a+b+c+d+e+f

6302.72

Rate per cum = (a+b+c+d+e+f)/120

say

6303.00

(r)

Height above 10m

465833.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 28 per cent of (a+b+c)

28.00

130433.24
119253.25

e)

Overhead charges @ 0.2 on (a+b+c+d)

71551.95

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

787071.44

Cost for 120 cum = a+b+c+d+e+f

6558.93

Rate per cum = (a+b+c+d+e+f)/120


14.1E
Case II

6047.00

(q)

Height 5m to 10m

14.1E
Case II
(i)

Lead =1
km & P&M050
1536.00 P&M-007

say

6559.00

(ii)
(p)

For T-beam & slab, 23-33 per cent of (a+b+c)


Height upto 5m

465833.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 23 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

Page 15 of 264

23.00

107141.59
114594.92
68756.95

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

756326.46

Cost for 120 cum = a+b+c+d+e+f

6302.72

Rate per cum = (a+b+c+d+e+f)/120


14.1E
Case II
(ii)

say

Height 5m to 10m

465833.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 28 per cent of (a+b+c)

28.00

130433.24
119253.25

e)

Overhead charges @ 0.2 on (a+b+c+d)

71551.95

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

787071.44

Cost for 120 cum = a+b+c+d+e+f

6558.93

Rate per cum = (a+b+c+d+e+f)/120


14.1E
Case II
(ii)

say

465833.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 33 per cent of (a+b+c)

33.00

153724.89
123911.58

e)

Overhead charges @ 0.2 on (a+b+c+d)

74346.95

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

817816.41

Cost for 120 cum = a+b+c+d+e+f

6815.14

Rate per cum = (a+b+c+d+e+f)/120

say

For cast-in-situ box girder, segment construction and


balanced cantilever, 38-58 per cent of cost of concrete.
Height upto 5m

465833.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 38 per cent of (a+b+c)

38.00

177016.54
128569.91

e)

Overhead charges @ 0.2 on (a+b+c+d)

77141.94

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

848561.39

Cost for 120 cum = a+b+c+d+e+f

7071.34

Rate per cum = (a+b+c+d+e+f)/120

say

465833.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 48 per cent of (a+b+c)

48.00

223599.84
137886.57

e)

Overhead charges @ 0.2 on (a+b+c+d)

82731.94

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

910051.35

Cost for 120 cum = a+b+c+d+e+f

7583.76

Rate per cum = (a+b+c+d+e+f)/120

say

7584.00

(r)

Height above 10m

465833.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 58 per cent of (a+b+c)

58.00

270183.14
147203.23

e)

Overhead charges @ 0.2 on (a+b+c+d)

88321.94

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

971541.30

Cost for 120 cum = a+b+c+d+e+f

8096.18

Rate per cum = (a+b+c+d+e+f)/120


14.1F

7071.00

(q)

Height 5m to 10m

14.1E
Case II
(iii)

6815.00

(iii)
(p)

14.1E
Case II
(iii)

6559.00

(r)

Height above 10m

14.1E
Case II

6303.00

(q)

say

F
PSC Grade M-45
Unit = 1 cum
Taking output = 120 cum
Page 16 of 264

8096.00

a)

Material

tonne

55.80

5000.00

279000.00

M-081

Cement

cum

54.00

828.00

44712.00

M-004

Coarse sand

cum

64.80

1028.00

66614.40

M-053

20 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

10 mm Aggregate

kg

223.20

44.70

9977.04

M-180
L-12

Admixture @ 0.4 per cent of cement


b)

Labour

day

0.94

151.44

142.35

Mate

day

3.50

223.36

781.76

L-11

Mason

day

20.00

136.69

2733.80

L-13

Mazdoor
c)

Machinery

hour

6.00

2232.00

13392.00

P&M-002

Batching Plant @ 20 cum/hour

hour

6.00

762.75

4576.50

P&M-080

Generator 100 KVA

hour

6.00

806.00

4836.00

P&M-017

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

Lead =1
km & P&M050

6.00

256.00

1536.00

P&M-007

Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km

Lead beyond 1 Km, L - lead in Kilometer


Concrete Pump

14.1F

(i)
(p)

hour

487584.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for 120 cum
For formwork and staging add the following:
For solid slab/voided slab super-structure, 16-26 per
cent of cost of concrete (a+b+c)
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 16 per cent of (a+b+c)

487584.00
16.00

78013.44
113119.49

e)

Overhead charges @ 0.2 on (a+b+c+d)

67871.69

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

746588.62

Cost for 120 cum = a+b+c+d+e+f

6221.57

Rate per cum = (a+b+c+d+e+f)/120


14.1F
(i)

say

Height 5m to 10m

487584.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 21 per cent of (a+b+c)

21.00

102392.64
117995.33

e)

Overhead charges @ 0.2 on (a+b+c+d)

70797.20

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

778769.16

Cost for 120 cum = a+b+c+d+e+f

6489.74

Rate per cum = (a+b+c+d+e+f)/120


14.1F
(i)

say

6490.00

(r)
Height above 10m

487584.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 26 per cent of (a+b+c)

26.00

126771.84
122871.17

e)

Overhead charges @ 0.2 on (a+b+c+d)

73722.70

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

810949.71

Cost for 120 cum = a+b+c+d+e+f

6757.91

Rate per cum = (a+b+c+d+e+f)/120


14.1F

6222.00

(q)

say

6758.00

(ii)
(p)

For T-beam & slab including launching of precast


girders by launching truss upto 40 m span, 21-31 per
cent of cost of concrete.
Height upto 5m

487584.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 21 per cent of (a+b+c)

21.00

102392.64
117995.33

e)

Overhead charges @ 0.2 on (a+b+c+d)

70797.20

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

778769.16

Page 17 of 264

Cost for 120 cum = a+b+c+d+e+f

6489.74

Rate per cum = (a+b+c+d+e+f)/120


14.1F
(ii)

say

Height 5m to 10m

487584.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 26 per cent of (a+b+c)

26.00

126771.84
122871.17

e)

Overhead charges @ 0.2 on (a+b+c+d)

73722.70

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

810949.71

Cost for 120 cum = a+b+c+d+e+f

6757.91

Rate per cum = (a+b+c+d+e+f)/120


14.1F
(ii)

say

487584.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 31 per cent of (a+b+c)

31.00

151151.04
127747.01

e)

Overhead charges @ 0.2 on (a+b+c+d)

76648.20

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

843130.25

Cost for 120 cum = a+b+c+d+e+f

7026.09

Rate per cum = (a+b+c+d+e+f)/120

say

For cast-in-situ box girder, segmental construction and


balanced cantilever, 36-56 per cent of cost of concrete.
Height upto 5m

487584.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 36 per cent of (a+b+c)

36.00

175530.24
132622.85

e)

Overhead charges @ 0.2 on (a+b+c+d)

79573.71

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

875310.80

Cost for 120 cum = a+b+c+d+e+f

7294.26

Rate per cum = (a+b+c+d+e+f)/120

say

487584.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 46 per cent of (a+b+c)

46.00

224288.64
142374.53

e)

Overhead charges @ 0.2 on (a+b+c+d)

85424.72

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

939671.88

Cost for 120 cum = a+b+c+d+e+f

7830.60

Rate per cum = (a+b+c+d+e+f)/120

say

7831.00

(r)
Height above 10m

487584.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 56 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

56.00

273047.04
152126.21
91275.72
1004032.97

Cost for 120 cum = a+b+c+d+e+f

8366.94

Rate per cum = (a+b+c+d+e+f)/120


14.1

7294.00

(q)
Height 5m to 10m

14.1F
(iii)

7026.00

(iii)
(p)

14.1F
(iii)

6758.00

(r)
Height above 10m

14.1F

6490.00

(q)

say

8367.00

G
PSC Grade M-50
Unit = 1 cum
Taking output = 120 cum
a)

Material

tonne

58.80

5000.00

294000.00

M-081

Cement

cum

54.00

828.00

44712.00

M-004

Coarse sand

cum

64.80

1028.00

66614.40

M-053

20 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

10 mm Aggregate

kg

235.20

44.70

10513.44

M-180

Page 18 of 264

Admixture @ 0.4 per cent of cement


b)

Labour

day

0.94

151.44

142.35

Mate

day

3.50

223.36

781.76

L-12
L-11

Mason

day

20.00

136.69

2733.80

L-13

Mazdoor
c)

Machinery

hour

6.00

2232.00

13392.00

P&M-002

Batching Plant @ 20 cum/hour

hour

6.00

762.75

4576.50

P&M-080

Generator 100 KVA

hour

6.00

806.00

4836.00

P&M-017

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

Lead =1
km & P&M050

6.00

256.00

1536.00

P&M-007

Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km

Lead beyond 1 Km, L - lead in Kilometer

hour

Concrete Pump

14.1G

(i)
(p)

503120.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for 120 cum
For formwork and staging add the following:
For cast-in-situ box girder, segmental construction and
balanced cantilever, 35-55 per cent of cost of concrete
Height upto 5m

503120.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 35 per cent of (a+b+c)

35.00

176092.00
135842.40

e)

Overhead charges @ 0.2 on (a+b+c+d)

81505.44

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

896559.84

Cost for 120 cum = a+b+c+d+e+f

7471.33

Rate per cum = (a+b+c+d+e+f)/120


14.1G
(i)

say

Height 5m to 10m

503120.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 45 per cent of (a+b+c)

45.00

226404.00
145904.80

e)

Overhead charges @ 0.2 on (a+b+c+d)

87542.88

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

962971.68

Cost for 120 cum = a+b+c+d+e+f

8024.76

Rate per cum = (a+b+c+d+e+f)/120


14.1G
(i)

say

8025.00

(r)
Height above 10m

503120.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 55 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

55.00

276716.00
155967.20
93580.32
1029383.52

Cost for 120 cum = a+b+c+d+e+f

8578.20

Rate per cum = (a+b+c+d+e+f)/120


14.1

7471.00

(q)

say

8578.00

H
PSC Grade M- 55
Unit = 1 cum
Taking output = 120 cum
a)

Material

tonne

63.50

5000.00

317500.00

M-081

Cement

cum

54.00

828.00

44712.00

M-004

Coarse sand

cum

64.80

1028.00

66614.40

M-053

20 mm Aggregate

cum

43.20

1005.00

43416.00

M-051

10 mm Aggregate

kg

254.00

44.70

11353.80

M-180

Admixture @ 0.4 per cent of cement


b)

Labour

day

0.94

151.44

142.35

Mate

day

3.50

223.36

781.76

L-11

Mason

day

20.00

136.69

2733.80

L-13

Page 19 of 264

L-12

Mazdoor
c)

Machinery

hour

6.00

2232.00

13392.00

P&M-002

Batching Plant @ 20 cum/hour

hour

6.00

762.75

4576.50

P&M-080

Generator 100 KVA

hour

6.00

806.00

4836.00

P&M-017

hour

15.00

1017.00

15255.00

P&M-049

tonne.km

300L

2.03

610.20

6.00

256.00

Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km

Lead beyond 1 Km, L - lead in Kilometer


Concrete Pump

14.1H

(i)
(p)

hour

527460.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for 120 cum
For formwork and staging add the following:
For cast-in-situ box girder, segmental construction and
balanced cantilever, 35-55 per cent of cost of concrete
Height upto 5m

527460.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 35 per cent of (a+b+c)

35.00

184611.00
142414.20

e)

Overhead charges @ 0.2 on (a+b+c+d)

85448.52

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

939933.72

Cost for 120 cum = a+b+c+d+e+f

7832.78

Rate per cum = (a+b+c+d+e+f)/120


14.1H
(i)

say

7833.00

(q)
Height 5m to 10m

527460.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 45 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

45.00

237357.00
152963.40
91778.04
1009558.44

Cost for 120 cum = a+b+c+d+e+f

8412.99

Rate per cum = (a+b+c+d+e+f)/120


14.1H
(i)

say

8413.00

(r)
Height above 10m

527460.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 55 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

55.00

290103.00
163512.60
98107.56
1079183.16

Cost for 120 cum = a+b+c+d+e+f

8993.19

Rate per cum = (a+b+c+d+e+f)/120

say

Note
1.Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers conforming IS: 9103
@ 0.4 per cent of weight of cement may be added for
achieving desired slump of concrete.
2. Cement provided for various components of the super
structure is for estimating purpose only. Actual quantity of
cement will be as per approved mix design. Similarly, the
provision for coarse and fine aggregates is for estimating
purpose and the exact quantity shall be as per the mix
design.
14.2

Lead =1
km & P&M050
1536.00 P&M-007

1600

3. The items like needle and surface vibrators are part of


minor T & P which is already covered under the overhead
charges. As such these items have not been added
separately in the rate analysis.
Supplying, fitting and placing HYSD bar reinforcement in
super-structure complete as per drawing and technical
specifications
Unit = 1 MT
Taking output = 1 MT
Page 20 of 264

8993.00

a)

Material
HYSD bars including 5 per cent for laps and wastage

tonne

1.05

45000.00

47250.00

M-082

Kg

8.00

100.00

800.00

M-072

day

0.44

151.44

66.63

L-12

day

3.00

264.50

793.50

L-02

day

8.00

136.69

1093.52

L-13

Binding wire
b)
Labour for cutting, bending, tying and placing in
position
Mate
Blacksmith
Mazdoor

50004.00
Basic Cost of Labour & Material (a+b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

10000.73
6000.44
66004.82

Rate per MT = a+b+c+d


14.3

say

66005.00

1800
High tensile steel wires/strands including all
accessories for stressing, stressing operations and
grouting complete as per drawing and Technical
Specifications
Unit = 1 MT
Taking output = 0.377 MT
Details of cost for 12T13 strand 40 m long cable (weight =
0.377 MT)
a) Material
H.T. Strand @ 9.42 kg/m including 2 per cent for
wastage and extra length for jacking
Sheathing duct ID 66 mm along with 5 per cent extra
length 40 x 1.05 = 42 m.
Tube anchorage set complete with bearing plate,
permanent wedges etc
Cement for grouting including 3 per cent wastage @
3.00 kg/m = 3 x 1.03 x 40 = 123.60 kg (say, = 125 kg)

b)

tonne

0.39

57453.00

22119.41

M-119

metre

42.00

304.00

12768.00

M-165

each

2.00

6064.00

12128.00

M-187

tonne

0.125

5000.00

625.00

M-081

2382.02

Add 0.50 per cent cost of material for Spacers,


Insulation tape and miscellaneous items
Labour

i) For making and fixing cables, anchorages

day

0.16

151.44

24.23

L-12

Mate

day

1.00

264.50

264.50

L-02

Blacksmith

day

3.00

136.69

410.07

L-13

Mazdoor
ii) For prestressing

day

0.05

151.44

7.57

L-12

Mate/Supervisor

day

0.25

230.00

57.50

L-08

Prestressing operator / Fitter

day

1.00

136.69

136.69

L-13
L-12

Mazdoor
iii) For grouting

day

0.05

151.44

7.57

Mate/Supervisor

day

0.25

223.36

55.84

L-11

Mason

day

1.00

136.69

136.69

L-13
P&M-040

Mazdoor
c)

Machinery

hour

2.50

129.00

322.50

Stressing jack with pump

hour

1.00

304.00

304.00

M-111

Grouting pump with agitator

hour

3.50

406.80

1423.80

P&M-079

Generator 33 KVA.

630.19

d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

378.12
54181.70

Cost for 0.377 MT (a+b+c+d+e)

143718.03

Rate per MT = (a+b+c+d+e)/0.377

say

Note
14.4

2702

Cost of HT steel has been taken for delivery at site. Hence


carriage has not been considered.
Providing and laying Cement concrete wearing coat M30 grade including reinforcement complete as per
drawing and Technical Specifications
Unit = 1 cum
Taking output = 1 cum

Page 21 of 264

143718.00

a)

Material

cum

1.00

3690.00

tonne

0.075

50004.00

b)

Cement concrete M30 Grade Refer relevant item of


concrete in Item 14.1 excluding formwork
HYSD bar reinforcement Rate as per item No
14.2(Excluding OH & CP)
Labour

day

0.15

136.69

Mazdoor for cleaning deck slab concrete surface.


c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Item
14.1(C)
3750.30 Item 14.2 A

20.50

L-13

1492.16
895.30
9848.26

Rate per cum (a+b+c+d)


14.5

3690.00

say

9848.00

515 &
2702
Mastic Asphalt
Providing and laying 12 mm thick mastic asphalt
wearing course on top of deck slab excluding prime
coat with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using
mastic cooker and laid to required level and slope after
cleaning the surface, including providing antiskid
surface with bitumen precoated fine grained hard stone
chipping of 9.5 mm nominal size at the rate of 0.005cum
per 10 sqm and at an approximate spacing of 10 cm
center to center in both directions, pressed into surface
when the temperature of surfaces not less than 100 deg.
C, protruding 1 mm to 4 mm over mastic surface, all
complete as per clause 515.

Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.
a) Labour

day

0.49

151.44

74.21

L-12

Mate

day

11.00

136.69

1503.59

L-13

Mazdoor

day

1.25

164.69

205.86

L-15

Machinery

hour

0.06

357.00

21.42

P&M-031

Mechanical broom @ 1250 sqm per hour

hour

0.06

319.00

19.14

P&M-001

Air compressor 250 cfm

hour

6.00

62.00

372.00

P&M-030

Mastic cooker 1 tonne capacity

hour

6.00

198.00

1188.00

P&M-005

Bitumen boiler 1500 litres capacity

hour

1.00

282.50

282.50

P&M-053

tonne

0.204

55132.00

11246.93

M-074

cum

0.39

476.80

185.95

M-021

tonne

0.36

4500.00

1620.00

M-188

cum

0.55

1005.00

552.75

M-051

cum

0.036

1213.00

43.67

M-142

kg

1.05

55.13

57.89

M074/1000

Mazdoor (Skilled)
b)

c)

Tractor for towing and positioning of mastic cooker and


bitumen boiler
Material

Base mastic (without coarse aggregates) = 60 per cent


Coarse aggregate(3.35mm to 9.5 mm size) = 40 per cent .
Proportion of material required for mastic asphalt with coarse
aggregates (based on mix design done by CRRI for a
specific case)
i) Bitumen 80/100 or 60/70 or 30/40 @ 10.2 per cent
by weight of mix. 2 x 10.2/100 = 0.204
ii) Crusher stone dust @ 31.9 per cent by weight of
mix = 2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 =
0.39
iii) Lime stone dust filler with calcium carbonate
content not less than 80 per cent by weight @ 17.92
per cent by weight of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40
per cent by weight of mix = 2 x 40/100 = 0.8 MT =
0.8/1.456 = 0.55
v) Pre-coated stone chips of 9.5 mm nominal size for
skid resistance = 72.46x0.005/10 = 0.036
vi) Bitumen for coating of chips @ 2 per cent by
weight = 0.036 x 1.456 x 2/100 = 0.001048MT =
1.05kg
d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Cost for 72.46 sqm = a+b+c+d+e

3474.78

2084.87
22933.55
316.50

Page 22 of 264

Rate per sqm = (a+b+c+d+e)/72.46

say

316.00

3690.00

15099.48

Note
1.The rates for 6 mm or any other thickness may be worked
out on pro-rata basis.
2. Where tack coat is required to be provided before laying
mastic asphalt, the same is required to be measured and
paid separately.

14.6

3.The quantities of binder, filler and aggregates are for


estimating purpose. Exact quantities shall be as per mix
design.
4.This rate analysis is based on design made by CRRI for a
specific case and is meant for estimating purposes only.
Actual design is required to be done for each case.
5.The quantity of bitumen works out 17 per cent of the
mastic asphalt blocks without aggregates and falls within the
standards laid down by MoRTH Specifications.

2703,
1500,
1600 &
1700

Construction of precast RCC railing of M30 Grade,


aggregate size not exceeding 12 mm, true to line and
grade, tolerance of vertical RCC post not to exceed 1 in
500, centre to centre spacing between vertical post not
to exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved
drawings and technical specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a)

Material

cum

4.09

Cement concreteM30 Grade Refer relevant item of


concrete in Item 14.1(C) by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos., External
area of vertical post 0.25x0.275 = 0.069sqm, Concrete
in Vertical posts = 0.069 x 28 = 1.932 cum, Hand rail in
3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175
= 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum.
(Refer MoRTH SD / 202).
Add 5 per cent of above cost for form work for casting
in casting yard.
HYSD bar reinforcement Rate as per item No
14.2(Excluding OH & CP)
Refer MoRTH SD / 202.

Item
14.1(C)

754.97

tonne

0.87

50004.00

43253.46 Item 14.2 A

2955.40
12412.66

b)

Add 5 per cent of (a) for handling and fixing of


precast panels in position
Overhead charges @ 0.2 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

81923.57

7447.60

Rate for 48 m (a+b+c)

1706.74

Rate per metre (a+b+c)/48

say

1707.00

3690.00

15099.48

Note

14.7

2703,
1500,
1600 &
1700

1.Quantities of material have been adopted from standard


plans of MoRTH vide drawing no. SD/202.
2.48 m length is the total linear length adding both sides of
24 m span.

Construction of RCC railing of M30 Grade in-situ with 20


mm nominal size aggregate, true to line and grade,
tolerance of vertical RCC post not to exceed 1 in 500,
centre to centre spacing between vertical post not to
exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved
drawings and technical specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a)

Material

cum

Page 23 of 264

4.092

Item
14.1(C)

Cement concreteM30 Grade Refer relevant item of


concrete in Item 14.1(C) by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos., External
area of vertical post 0.25x0.275 = 0.069sqm, Concrete
in vehicle posts = 0.069 x 28 = 1.932 cum, Hand rail in
3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175
= 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum.
(Refer MoRTH SD / 202).
Add 12 per cent of above cost for form work.

1811.94

tonne

0.87

50004.00

HYSD bar reinforcement Rate as per item No


14.2(Excluding OH & CP)
refer MoRTH SD / 202.
b)

Overhead charges @ 0.2 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

43253.46 Item 14.2 A

12032.98
7219.79
79417.64

Rate for 48 m (a+b+c)

1654.53

Rate per metre (a+b+c)/48

say

1655.00

Note

14.8

2703.2 &
1900

1. Quantities of material have been adopted from standard


plans of MoRTH vide drawing no. SD/202.
2. 48 m length is the total linear length adding both sides of
24 m span.
Providing, fitting and fixing mild steel railing complete
as per drawing and Technical Specification
Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a)

b)

Material:

tonne

2.95

45000.00

132570.00

M-179

1) ISMC 100 = 2.806 x 1.05 = 2.946 MT

tonne

1.01

45000.00

45540.00

M-179

2) MS Flat = 0.964 x 1.05 = 1.012 MT

tonne

0.18

45000.00

8100.00

M-179

3) MS bars = 0.17 x 1.05 = 0.180 MT

tonne

0.15

64070.00

9610.50

M130*1000

4) MS bolts, nuts and washers

9791.03

Add @ 5 per cent of cost of material for painting one


shop coat with red oxide primer and three coats of
synthetic enamel paint and consumables to safeguard
against weathering and corrosion.

1958.21

Add for cost of concrete for fixing vertical posts in the


performed recess @ 1 per cent of cost of material.
Add for electricity charges, welding and drilling
equipment, electrodes and other consumables @ 1 per
cent of cost of material.
Labour

1958.21

day

2.80

151.44

424.03

L-12

Mate

day

30.00

164.69

4940.70

L-15

Mazdoor (Skilled)

day

40.00

136.69

5467.60

L-13

Mazdoor

44072.05

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

26443.23
290875.55

Cost for 100 m steel railing = a+b+c+d

2908.76

Rate per metre (a+b+c+d)/100


14.9

say

2909.00

2705
Drainage Spouts complete as per drawing and Technical
specification
Unit = 1 No.
Taking output = 1 No.
a)

Material

Kg

4.00

46.53

186.10

M087/1000
M-056

Corrosion resistant Structural steel including 5 per cent


wastage
GI pipe 100mm dia

metre

6.00

65.00

390.00

each

6.00

13.00

78.00

M-110

GI bolt 10 mm Dia

each

2.00

25.00

50.00

M-101

day

0.02

151.44

3.03

L-12

Galvanised MS flat clamp


b)

Labour

For fabrication
Page 24 of 264

Mate

day

0.02

264.50

5.29

L-02

Skilled (Blacksmith, welder etc.)

day

0.02

136.69

2.73

L-13
L-12

Mazdoor
For fixing in position

day

0.01

151.44

1.51

Mate

day

0.01

223.36

2.23

L-11

Mason

day

0.20

136.69

27.34

L-13

Mazdoor

37.31

c)

Add @ 5 per cent of cost of material and labour for


electrodes, cutting gas, sealant, anti-corrosive
bituminous paint, mild steel grating etc.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

156.71

94.03
1034.29

Rate per metre (a+b+c+d)

say

1034.00

4066.00

4066.00

say

4066.00

3686.00

3686.00

Note
1. In case of viaducts in urban areas, the drainage spouts
should be connected with suitably located pipelines to
discharge the surface run-off to drains provided at ground
level.
14.10

2. In case of bridges, sufficient length of G.I Pipe shall be


provided to ensure that there is no splashing of water from
the drainage spout on the structure.

2700

PCC M15 Grade leveling course below approach slab


complete as per drawing and Technical specification
Unit = 1 cum
Taking output = 1 cum
Material

14.11

cum

1.00

Concrete, Rate as per item No. 12.8 (A) excluding


formworks
Rate per cum

1500,16
00,1700
& 2704

Item 12.8
(A)

Reinforced cement concrete approach slab including


reinforcement and formwork complete as per drawing
and Technical specification
Unit = 1 cum
Taking output = 1 cum
a)

Material

cum

1.00

Cement concreteM30 Grade Refer relevant item of


concrete in item 12.8(G)by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
(Excluding OH & CP)
( Refer relevant item of concrete in item No. 13.8 (G)
except that form work may be added at the rate of 2
per cent of cost against 3.5 per cent provided in the
foundation concrete.

50004.00

2500.20 Item 14.2 A

c)

Contractor's profit @ 0.1 on(a+b)

8263.09

751.19
say

Providing anti-corrosive treatment to HYSD


reinforcement with Fusion Bonded Epoxy Coating
(FBEC)
Unit = 1 MT
Taking output = 1 MT
Note

0.05

b)

The grade of reinforced cement concrete may be adopted as


M30 for severe conditions and M25 for moderate conditions.

1600

tonne

1251.98

Rate per cum (a+b+c)


14.12

73.72

HYSD bar reinforcement Rate as per item No


14.2(Excluding OH & CP)
Overhead charges @ 0.2 on (a)

Note

To be taken as per the prevailing market rates.

Page 25 of 264

Item 12.8
(G)

8263.00

14.13

1800 &
2300

Contractors generally do not have expertise for this item .


The job is therefore, got done from specialised firms who
have the expertise in the field of construction chemicals. The
prevailing rate in the market is required to be ascertained
from the market and added in the cost estimate. Detailed
guidelines in this regard have been issued by MoRTH vide
their circular no. RW/NH-34041/44/91-S&R dated 21.3.2000.
Precast - pretensioned Girders
Providing, precasting, transportation and placing in
position precast pretensioned concrete girders as per
drawing and technical specifications
Unit = 1 cum
Taking output = 1 cum
Grade of concrete - M40
a)

Material

tonne

0.47

5000.00

2350.00

M-081

Cement

cum

0.45

828.00

372.60

M-004

Coarse sand

cum

0.54

1028.00

555.12

M-053

20 mm Aggregate

cum

0.36

1005.00

361.80

M-051

10 mm Aggregate

Kg

1.88

44.70

84.04

M-180

Admixture @ 0.4 per cent of cement

tonne

0.10

45000.00

4500.00

M-082

HYSD steel .

tonne

0.06

57453.00

3447.18

M-119

HT strand with 5 per cent as wastage and extra length


for anchoring
LDO for steam curing

Litre

37.00

43.00

1591.00

M-122

132.62

Add consumables such as binding wire, foam, packing


tape, shuttering oil, HDPE pipe for unbonding of
strand, bolt & nuts etc @ 1 per cent of material cost
b)

Labour

(i) Cutting, bending, making reinforcement cage, placing


in position, binding etc. complete
Taking quantity of steel 100 Kg/cum of concrete
including laps and wastage
Mate
Mazdoor (Skilled)

day

0.06

151.44

9.09

L-12

day

0.35

day

1.40

164.69

57.64

L-15

136.69

191.37

L-13

Mazdoor
(ii) Cable cutting and threading in position including
binding by insulation tape with HDPE pipes etc.,
prestessing and cutting of extra length of HT strand
after de-stressing.
Taking quantity of HT strand 60 Kg/cum

day

0.02

151.44

3.03

L-12

Mate

day

0.14

164.69

23.06

L-15

Mazdoor (Skilled)

day

0.50

136.69

68.35

L-13

Mazdoor
(iii) Erection and dismantling of shuttering
Taking shuttering area 10 sqm/cum of concrete

day

0.12

151.44

18.17

L-12

Mate

day

1.00

164.69

164.69

L-15

Mazdoor (Skilled)

day

2.00

136.69

273.38

L-13

day

0.03

151.44

4.54

L-12

day

0.05

164.69

8.23

L-15

day

0.60

136.69

82.01

L-13

day

0.01

151.44

1.51

L-12

day

0.35

136.69

47.84

L-13

day

0.01

151.44

1.51

L-12

day

0.25

136.69

34.17

L-13

day

0.01

151.44

1.51

L-12

Mazdoor
(iv) Concreting by Batching plant and stationary
concrete pump
Mate
Mazdoor (Skilled)
Mazdoor
(v) Steam curing and manual curing
Mate
Mazdoor
(vi) Handling of precast girder, stacking in stockyard
and again loading in trailor
Mate
Mazdoor
(vii) Placement of girders in position over pier caps
including placement of sand jacks, channel, levelling
etc.
Page 26 of 264

Mate

day

0.06

164.69

9.88

L-15

Mazdoor (Skilled)

day

0.24

136.69

32.81

L-13

Mazdoor
c)

Machinery

i) At casting yard

hour

0.05

762.75

38.14

P&M-080

Generator 100 KVA

hour

0.05

2232.00

111.60

P&M-002

Batching Plant @ 20 cum/hour

hour

0.10

1017.00

101.70

P&M-049

Transit Mixer 4 cum capacity

hour

0.05

256.00

12.80

P&M-007

Concrete Pump stationary

hour

0.10

853.00

85.30

P&M-012

Crane 35 tonne capacity

hour

0.10

847.50

84.75

P&M-089

Trailor 30 tonne capacity

hour

0.05

806.00

40.30

P&M-017
P&M-012

Loader
ii) For transportation and placement at site
Crane 35 tonne capacity

hour

0.15

853.00

127.95

tonne.km

2.5xL

0.68

1.70

hour

0.15

847.50

127.13

Lead =1
km & P&M090

Trailer 30 tonne capacity for transporting to site.


(L - Lead in Kilometer)
Trailor 30 tonne capacity during placement.

d)

Cost of formwork, steam curing arrangement,


pretensioning arrangement etc @ 5 per cent of cost
material, labour and machinery
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

745.09
3180.72

1908.43
20992.75

Rate per cum = (a+b+c+d+e)


14.14

P&M-089

say

20993.00

1700 &
1800
Providing and fixing Helical pipes in voided concrete
slabs
Unit = 1 RM
Taking output = 1 RM
a)

Material

metre

1.00

2426.00

2426.00

M-117

Helical pipes 600mm diameter

each

1.00

49.00

49.00

M-183

Tie rods 20mm diameter

123.75

Consumables for sealing joints etc.@ 5 per cent of cost of


material
b) Labour

day

0.01

151.44

1.51

L-12

Mate

day

0.05

230.00

11.50

L-08

Fitter

day

0.20

136.69

27.34

L-13

Mazdoor

527.82

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

316.69
3483.62

Rate per cum (a+b+c+d)


14.15

800

14.16

800

say

3484.00

Crash Barriers
The rate analysis for rigid crash barrier in reinforced cement
concrete, semi-rigid crash barrier with metal beam and
flexible crash barrier with wire ropes have been made and
included in chapter-8 on Traffic and Transportation.
Painting on concrete surface
Providing and applying 2 coats of water based cement
paint to unplastered concrete surface after cleaning the
surface of dirt, dust, oil, grease, efflorescence and
applying paint @ of 1 litre for 2 sqm.
Unit = sqm
Taking output = 10 sqm
a)

Labour

day

0.01

151.44

1.51

L-12

Mate

day

0.25

223.36

55.84

L-18

Painter

day

0.25

164.69

41.17

L-15

Litres

5.00

31.00

155.00

M-190

Mazdoor (Skilled)
b)

Material
Page 27 of 264

c)

Water based paint of approved quality for cement


concrete surface
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

50.71
30.42
334.66

Cost for 10 sqm (a+b+c+d)

33.47

Rate per sqm (a+b+c+d)/10


14.17

say

33.00

2604
Burried Joint
Providing and laying a burried expansion joint,
expansion gap being 20 mm, covered with 12 mm thick,
200 mm wide galvanised weldable structural steel plate
as per IS: 2062, placed symmetrical to centre line of the
joint, resting freely over the top surface of the deck
concrete, welding of 8 mm dia. 100 mm long galvanised
nails spaced 300 mm c/c along the centre line of the
plate, all as specified in clause 2604.
Unit = Running meter
Taking output = 12 m
a)

Labour

day

0.02

151.44

3.03

L-12

Mate

day

0.40

136.69

54.68

L-13

Mazdoor

day

0.20

164.69

32.94

L-15

kg

237.50

54.57

12961.33

Mazdoor (Skilled)
b)

Material

c)

Galvanised M.S plate 200 mm wide,12 mm thick @


94.20 kg/sqm including 5 per cent wastage
Add 1 per cent of cost of steel plate cutting, welding
consumables and galvanised nails.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

M060/1000

129.61
2636.32
1581.79
17399.69

Cost for 12 m = (a+b+c+d)

1449.97

Rate per m = (a+b+c+d)/12

say

1450.00

Note
14.18

Guidelines laid down vide the MoRTH circular No. RW/NH34059/1/96-S&R dated 30.11.2000 and subsequent
corrigendum dated 25.01.2001 may be reffered for
expansion joints.

2605

(i)

Filler joint
Providing & fixing 2 mm thick corrugated copper plate in
expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a)

Labour

Cutting, bending, carrying & fixing etc.

day

0.04

151.44

6.06

L-12

Mate

day

0.50

136.69

68.35

L-13

Mazdoor

day

0.50

164.69

82.35

L-15

kg

55.00

290.55

15980.25

Mazdoor (Skilled)
b)

Material
Copper plate - 12m long x 250 mm wide

Area = 12 x 0.25 = 3 sqm


Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = 55 kg.
c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3227.40
1936.44
21300.84

Cost for 12 m = (a+b+c+d)

1775.07

Rate per m = (a+b+c+d)/12


14.18

say

(ii)
Providing & fixing 20 mm thick compressible fibre board
in expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
Page 28 of 264

1775.00

M-086

a)

Labour

For carrying, placing & fixing.

day

0.008

151.44

1.21

L-12

Mate

day

0.10

136.69

13.67

L-13

Mazdoor

day

0.10

164.69

16.47

L-15

sqm

3.00

486.00

1458.00

Mazdoor (Skilled)
b)

Material

20 mm thick compressible fibre board 12 m long x 25


cm deep.
Area = 12 x 0.25 = 3 sqm
c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

297.87
178.72
1965.94

Cost for 12 m = (a+b+c+d)

163.83

Rate per m = (a+b+c+d)/12


14.18

M-084

say

164.00

(iii)
Providing and fixing in position 20 mm thick
premoulded joint filler in expansion joint for fixed ends
of simply supported spans not exceeding 10 m to cater
for a horizontal movement upto 20 mm, covered with
sealant complete as per drawing and technical
specifications.
Unit = Running meter
Taking output = 12 m
a)

Labour

day

0.01

151.44

1.51

L-12

Mate

day

0.20

136.69

27.34

L-13

Mazdoor

day

0.10

164.69

16.47

L-15

sqm

3.60

965.00

3474.00

Mazdoor (Skilled)
b)

Material

c)

Premoulded joint filler 12 m long,20 mm thick and 300


mm deep.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

422.32
4645.50

Cost for 12 m = (a+b+c+d)

387.13

Rate per m = (a+b+c+d)/12


14.18

M-141

703.86

say

387.00

(iv)
Providing and filling joint sealing compound as per
drawings and technical specifications with coarse sand
and 6 per cent bitumen by weight
Unit = Running meter
Taking output = 12 m
12m long x 100 mm wide x 10mm deep recess
a)

Labour

day

0.02

151.44

3.03

L-12

Mate

day

0.50

136.69

68.35

L-13

Mazdoor

day

0.10

164.69

16.47

L-15

cum

0.012

710.46

8.53

M-005

cum

0.001

55132.00

55.13

M-074

Mazdoor (Skilled)
b)

Material
Sand

Volume 12 x 0.1 x 0.01 = 0.012 cum


Weight 0.012 x 1400 = 16.8kg
Bitumen
16.8 x 0.06 = 1 kg

30.30

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

18.18
199.98

Cost for 12 m = (a+b+c+d)

16.67

Rate per m = (a+b+c+d)/12

say

Note
For arriving at the final rate of filler joints per m
length and per cm depth of joint filling compound,
14.19

2600

the rates at Sl. No. i), ii), iii) & iv) shall be added
Asphaltic Plug joint

Page 29 of 264

17.00

Providing and laying of asphaltic plug joint to provide


for horizontal movement of 25 mm and vertical
movement of 2 mm, depth of joint varying from 75 mm to
100 mm, width varying from 500 mm to 750 mm (in
traffic direction), covered with a closure plate of 200mm
x 6mm of weldable structural steel conforming to IS:
2062, asphaltic plug to consist of polymer modified
bitumen binder, carefully selected single size aggregate
of 12.5 mm nominal size and a heat resistant foam
caulking/backer rod, all as per approved drawings and
specifications.

Unit = Running meter


Taking output = 12 m
a)

Labour

day

0.052

151.44

7.87

L-12

Mate

day

1.00

136.69

136.69

L-13

Mazdoor

day

0.30

164.69

49.41

L-15

Mazdoor (Skilled)
b)

2.4

Material

cum

0.75

1028.00

771.00

M-052

Crushed stone aggregate 12.5 mm nominal size

kg

77.50

38.74

3002.35

Polymer modified bitumen

kg

113.00

61.00

6893.00

M-078/
1000
M-103

Galvanised structural steel plate 200 mm wide,6 mm


thick, 12 m long (2.4 sqm) @ 47.10 kg/sqm including 5
per cent wastage

c)

108.60

Add 1 per cent for welding and foam caulking/backer


rod and other incidentals.
Machinery

hour

1.00

62.00

62.00

P&M-030

Mastic cooker 1 tonne capacity

hour

0.50

460.00

230.00

P&M-044

Smooth 3-wheeled steel roller 8-10 capacity


d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2252.19
1351.31
14864.42

Cost for 12 m asphalt plug joint = (a+b+c+d+e)

1238.70

Rate per m = (a+b+c+d+e)/12

say

1239.00

Note
14.20

2606

The nominal size of aggregates shall be 12.5 mm for depth


of joint upto 75 mm and 20 mm for joints of depth more than
75 mm.
Elastomeric Slab Steel Expansion Joint
Providing and laying of an elastomeric slab steel
expansion joint, catering to right or skew (less than 20
deg., moderately curved with maximum horizontal
movement upto 50 mm, complete as per approved
drawings and standard specifications to be installed by
the manufacturer/supplier or their authorised
representative ensuring compliance to the
manufacturer's instructions for installation and clause
2606 of MoRTH specifications for road & bridge works.
Unit = Running meter
Taking output = 12 m
a)

Labour

day

0.06

151.44

9.09

L-12

Mate

day

1.00

136.69

136.69

L-13

Mazdoor

day

0.50

164.69

82.35

L-15

metre

12.00

6064.00

72768.00

Mazdoor (Skilled)
b)

Material
Supply of elastomeric slab seal expansion joint
assembly manufactured by using chloroprene,
elastomer for elastomeric slab unit conforming to
clause 915.1 of IRC: 83 (part II), complete as per
approved drawings and standard specification
conforming to clause 2606 of MoRT&H Specification

c)

Add 5 per cent of cost of material for anchorage


reinforcement, welding and other incidentals.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)


Page 30 of 264

3638.40

15326.90
9196.14
101157.57

M-093

Cost for 12 m = (a+b+c+d)

8429.80

Rate per m = (a+b+c+d)/12


14.21

say

8430.00

2600
Compression Seal Joint
Providing and laying of compression seal joint
consisting of steel armoured nosing at two edges of the
joint gap suitably anchored to the deck concrete and a
preformed chloroprene elastomer or closed cell foam
joint sealer compressed and fixed into the joint gap with
special adhesive binder to cater for a horizontal
movement upto 40 mm and vertical movement of 3 mm.
Unit = Running meter
Taking output = 12 m
a)

Labour

day

0.036

151.44

5.45

L-12

Mate

day

0.60

136.69

82.01

L-13

Mazdoor

day

0.30

164.69

49.41

L-15

kg

446.00

61.00

27206.00

Mazdoor (Skilled)
b)

Material
1. Galvanised angle sections 100mm x 100mm of
12mm thickness weldable structural steel as per IS:
2062, 2 nos. of 12 m length each @ 17.7 kg/m and 5
per cent wastage.
Add 5 per cent of cost of above for structural steel for
anchorage, welding and other incidentals.
Preformed continuous chloroprene elastomer or closed
cell foam sealing element with high tear strength,
vulcanised in a single operation for the full length of a
joint to ensure water tightness.

c)

Add 1 per cent of cost of sealing element for lubricantcum-adhesive and other consumables.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

M-103

1367.14

metre

12.00

668.00

8016.00

M-143

80.16

7361.24
4416.74
48584.15

Cost for 12 m = (a+b+c+d)

4048.68

Rate per m = (a+b+c+d)/12

say

4049.00

Note
1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.

14.22

2607

2. The concreting for joining the expansion joint assembly


with the deck has not been included in this analysis as the
same is catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint assembly shall
be welded to the main reinforcement of the deck.
Strip Seal Expansion Joint
Providing and laying of a strip seal expansion joint
catering to maximum horizontal movement upto 70 mm,
complete as per approved drawings and standard
specifications to be installed by the
manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions
for installation.
Unit = Running meter
Taking output = 12 m
a)

Labour

day

0.05

151.44

7.57

L-12

Mate

day

1.00

136.69

136.69

L-13

Mazdoor

day

0.25

164.69

41.17

L-15

metre

12.00

7500.00

90000.00

Mazdoor (Skilled)
b)

Material
Supply of complete assembly of strip seal expansion
joint comprising of edge beams, anchorage, strip seal
element and complete accessories as per approved
specifications and drawings.

c)

Add 5 per cent of cost of material for anchorage


reinforcement, welding and other incidentals.
Overhead charges @ 0.2 on (a+b)

Page 31 of 264

4509.27

18938.94
11363.36

M-178

d)

Contractor's profit @ 0.1 on (a+b+c)

124997.01

Cost for 12 m = (a+b+c+d)

10416.42

Rate per m = (a+b+c+d)/12

say

10416.00

Note
1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.
14.23

2600

2. The concreting for joining the expansion joint assembly


with the deck has not been included in this analysis as the
same is catered in the quantities of RCC deck.
Modular Strip / Box Seal Joint
Providing and laying of a modular strip Box seal
expansion joint including anchorage catering to a
horizontal movement beyond 70 mm and upto 140mm,
complete as per approved drawings and standard
specifications to be installed by the
manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions
for installation.
Unit = Running meter
Taking output = 12 m
a)

Labour

day

0.056

151.44

8.48

L-12

Mate

day

1.00

136.69

136.69

L-13

Mazdoor

day

0.40

164.69

65.88

L-15

metre

12.00

1820.00

21840.00

Mazdoor (Skilled)
b)

Material
Supply of a modular strip/box seal joint assembly
comprising of edge beams, central beam,2 modules
chloroprene seal, anchorage elements, support and
control system, all steel sections protected against
corrosion and installed by the manufacturer or his
authorised representative.

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

M-127

4410.21

2646.13
29107.38

Cost for 12 m Modular strip/box seal joint = (a+b+c+d)

2425.62

Rate per m = (a+b+c+d)/12

say

2426.00

Note
1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.

14.24

2600

2. The concreting for joining the expansion joint assembly


with the deck has not been included in this analysis as the
same is catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint assembly shall
be welded to the main reinforcement of the deck.
Modular Strip / Box Seal Joint
Providing and laying of a modular strip box seal
expansion joint catering to a horizontal movement
beyond 140mm and upto 210mm, complete as per
approved drawings and standard specifications to be
installed by the manufacturer/supplier or their
authorised representative ensuring compliance to the
manufacturer's instructions for installation.
Unit = Running meter
Taking output = 12 m
a)

Labour

day

0.07

151.44

10.60

L-12

Mate

day

1.25

136.69

170.86

L-13

Mazdoor

day

0.50

164.69

82.35

L-15

metre

12.00

1820.00

21840.00

Mazdoor (Skilled)
b)

Material
Supply of a modular box/box seal joint assembly
containing 3 modules/cells and comprising of edge
beams, two central beams, chloroprene seal,
anchorage elements, support and control system, all
steel sections protected against corrosion and installed
by the manufacturer or his authorised representative.

Page 32 of 264

4420.76

M-128

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2652.46
29177.03

Cost for 12 m Modular strip/box seal joint = (a+b+c+d)


Rate per m = (a+b+c+d)/12

2431.42
say

Note
1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly
with the deck has not been included in this analysis as the
same is catered in the quantities of RCC deck.

Page 33 of 264

2431.00

También podría gustarte