Documentos de Académico
Documentos de Profesional
Documentos de Cultura
(CCPM)
Let us start.
Common Feature in most Projects
Time and Cost Overruns
But Why?
Tight deadlines
T many complexities
Too
l iti
Too many uncertainties
Too many administrative hassles
Poor training..
How to solve?
Address these issues
Provide cushions
How to solve?
Treat Variability as the most important performance
measure
Develop systems that minimise variability
But
How much cushions we generally provide in
Projects?
Past Data
Top
p Down or Bottom up
p approach
pp
Cushions for uncertainty
Activity
ct ty p
precedence
ecede ce ((network
et o tec
technique)
que)
Project Duration
10
Theory
12 14
8
10
26
Actual
30
So.
Though the typical belief is that the time buffer
given during planning is only around 15-20%,
studies have shown that normallyy much higher
g
buffer even up to 200% is given
Why Failures?
PROJECT
ORGANISATION
PROJECT
W t
Wastage
PROJECT
ORGANISATION
Parkinsons
Parkinson s Law
Work expands to fill its time
SelfSelf-protection
People fail to report early finishes out of fear that management will adjust their future
standards
t d d
Dropped batons
Early finishes may not lead to the start of next activity as people assigned next activity
are engaged
d somewhere
h
else
l
Student syndrome
-
only local
factors!
Project Dilemma
Avoid Effect of
Parkinsons
Law
Minimise
Project
L dti
Leadtime
Manage
Project
Successfully
Schedule
without buffers
(safety)
co
nfl
ict
Ensure Project
Promise
Provide for
Murphy
Schedule with
adequate
Buffers
Theory of Constraints
A system improvement philosophy (as opposed
to a process improvement philosophy)
g
live or die as systems,
y
not as
Organizations
processes
Success or failure is a function of how well
diff
different
t componentt processes iinteract
t
t with
ith
one another
Theory of Constraints
Theory of Constraints
Another basic principle of TOC
A large number of undesirable effects will be caused
by
y a relatively
y small number of core drivers
Eliminating a very few core problems can result in a
huge improvement
Theory of Constraints
Five Focusing Steps
1.
2.
3.
4.
5.
Revisiting activities
P
Power
off A
Aggregation
ti
Safety buffers
Conventional Project Schedule
Job 1
Job 2
Pooled buffers
J b3
Job
Job 4
Project Buffer,
Project buffer is safety time added to the end of the critical chain
to protect the completion date of the project.
Feeding
path
Project Buffer
Feeding Buffer
If Slack remains,
then schedule as
late as possible
Resource buffers
a wakeup call to alert resources to be ready to work on
critical tasks
Scheduled idle time can provide better info about resources
availability (capacity)
Feeding
Buffer
C iti l Ch
Critical
Chain
i
Alert Wkr A
Alert Wkr B
Resource
Buffers
Alert Wkr C
Project
Buffer
Project
j Buffer
About Buffers
Identify the points at which to place project, feeding,
and resource buffers
Buffer sizes determined approximately, based either on
average task duration estimates, or a combination of
g and worst-case duration estimates
average
Individual buffer sizes can be adjusted based on
intuitive assessment of risk
Buffer insertion may cause the Critical Chain, and
hence the project completion date, to be pushed later
6
A
8
D
4
G
10
J
8
B
6
C
6
E
10
F
12
H
16
I
10
K
6
L
6
A
8
D
8
B
6
C
6
E
10
F
4
G
10
J
8
M
Calculated critical path is
C-F-I-L-M = 46 days
Activity H and I
cannot be done
simultaneously
8
12
10
Suppose H & I share a common
resource?
M
H
K
16
6
Calculated critical chain is
L
I
B-E-H-I-L-M = 56 days
6
A
8
D
4
G
10
J
8
B
6
C
6
E
10
F
12
H
16
I
10
K
6
L
6
E
10
F
12
H
16
I
10
K
6
L
8
M
Calculated critical path is
C-F-I-L-M = 46 days
Activity H and I
cannot be done
simultaneously
M
Calculated critical chain is
B-E-H-I-L-M = 56 days
A
4
B
3
C
D
3
E
Feeding
Buffer
=7 days
K
8
Feeding
Buffer
=4 days
Slack = 1 days
13
Feeding
Buffer
=3
3 days
3
L
28
M
Project
Buffer
=14
14 days
Benefits
B
fit off C
Critical
iti l Ch
Chain
i
Better project status info allows managers to set clear
priorities
Buffer
B ff managementt h
helps
l resource manager tto allocate
ll
t
resources to those projects most in need
Focus on the key tasks and resources
Challenges
Ch ll
off Critical
C iti l Chain
Ch i
Doesnt provide any objective basis of determining buffer size
(include risk management)
Critical
C iti l Chain
Ch i project
j t managementt presented
t d as a
methodology
Culture change may be difficult
Incorporate those critical chain approach elements that are
applicable to your environment within border project
management methodology
THANKYOU
Rob
Carly
Ryan
Ryan
Lauren
Connor
Ryan
Dawn
Kevin
Issues?
8 -5
ffeeder buffers
ff where non
non--critical ppaths merge
g with the critical chain
8 -8