Documentos de Académico
Documentos de Profesional
Documentos de Cultura
ABSTRACT
Aim of the project is to study the POWER GRID MANAGEMENT THROUGH SCADA.
Grid Management is a combination of Art and Science, Power System Operators, who are the
Grid Managers Play a crucial role in achieving the objective of maintaining power supply ensuring
Power Systems have grown both in size and complexity over decades coupled with most
thrilling technical advancements in transmission technology like HVDC, FACTS, etc. With formation
of functionally distinct corporations for Generation, Transmission & Distribution, the operation of
This report gives a brief description about the POWER GRID MANAGEMENT THROUGH
SCADA.
ii
ORGANISATION OF THE PROJECT WORK
CONTENTS
BIBLIOGRAPHY 40
APPENDIX 41
ORGANISATION PROFILE 42
v
LIST OF FIGURES
3.5 CONTROL 21
vi
CHAPTER – 1
1.1. INTRODUCTION
In this chapter the objective and the overview of the project will be discussed.
The operation of Electrical Power System consisting of Generating station, Transmission lines
and distribution which is in dynamic nature as the power generated gets consumed instantly and it
cannot be stored. The Typical Power System for generation system, transmission system and
distribution system is shown in figure 1.1. The distribution system consists of substations,
transformers, circuit breakers, feeders, sectionalizing switches, capacitor banks, voltage regulators,
DSG’s and customers like HT customers and LT customers.
To ensure that the load incident matches with the generation for maintaining system frequency
at 50 Hz., the grid operators have to continuously work out the unit to brought or backed down or
loads to be interrupted and take action. The technical limitations of each type of generating units and
the stipulations in Power Purchase Agreement make Merit Order Dispatch a complex exercise. This
being so, every endeavor should be made to maintain it above 49.5 and below 50.5 Hz.
While the State Power System are monitored round the clock by the State Load Dispatch
Centers, the Regional grid as a whole is monitored by the Regional Load Dispatch Centre with a
watchful eye on various operating parameters like frequency, voltage, power flows ( both active and
reactive) through all lines and equipment.
The Load Dispatchers at Regional & State Level have to be provided with authority to enforce
grid discipline through remote control of identified elements in the power system in order to restore
system security wherever it is under threat.
1
Typical Po
Fig 1.1. Typical Power System
Generati
2
Any system has to function under specified norms and constraints in accordance with a
directed action. As the size and complexity of the power system consisting of generators, transmission
lines, power transformers, distribution transformers, etc. Increases, the possibility of any contingency
cropping up in its functioning also increases. As a result, it becomes inevitable to have a sophisticated
system to monitor any discrepancy arising in the functioning of the system and take necessary
corrective action. The ability to perform operations with remote control at an unmanned station from a
master station or operating centre and to have a definite indication that the operations have been
successfully carried out can provide significant cost savings in the operation of a power system In
most systems there are locations where operations, such as opening or closing of circuit breakers, must
be done from time to time, but the cost of providing and maintaining an operator attendance all the 24
hours in a day cannot be justified. Delays that could result from the need to send the operator to such
locations may lengthen and outage and deteriorate customer service. Furthermore, the cost of
providing attendance at remote stations or providing personnel to perform switching continues to
escalate. This makes operator attendance of remoter stations even more uneconomical.
1.3.CONCLUSION
In this the objective and overview of the project have been discussed.
3
CHAPTER – 2
2.1. INTRODUCTION
In the above chapter, the objective and overview of the project are discussed and in the present
chapter power grid operation is discussed.
Preamble
Grid Management is a combination of both Art and Science, Power System Operators, who are
the Grid Managers Play a crucial role in achieving the objective of maintaining power supply
uninterrupted ensuring quality, reliability and security of the Grid.
During peak and emergency periods it is required to shed some loads quickly to maintain grid.
The load management involves controlling systems, loads by remote control of feeder breakers at
substations, load terminals at DTs, and individual consumers and control of agricultural loads
Power Systems have grown both in size and complexity over decades coupled with most
thrilling technical advancements in transmission technology like HVDC, FACTS, etc. With formation
of functionally distinct corporations for Generation, Transmission & Distribution, the operation of
power systems has assured lot of commercial important.
Small sized power stations were feeding loads in their immediate vicinity till 1950s and the
State Power Grids were formed in India in 1960s to facilitate transfer of Power to various Load
Centers. The transmission voltage was 66 KV and 132 KV till 1960, when 220 KV lines have come
into service in most parts of the country. Many Inter-state 220 KV lines were commissioned between
1960 and 1970 to enable interstate exchange of power on bilateral basis and 400 KV lines have been
laid later.
4
Five Regional Grid are operating in the country with an overall installed capacity of 1, 08,000
MWs.
The EMS/SCADA system in AP is being implemented by M/S power grid under southern
region system co-ordination and control project. In this system the application servers,work stations,
front end processors, routers, UPS systems, batteries and D.G sets are installed at four area load
dispatch centres i.e mamidipally, Warangal, cuddapah and nunna and back-up SLDC, vidyut soudha.
The EMS/SCADA systems comprises of hard-ware and soft-ware with hierarchical control
philosophy. These hardware and software components are shown in the figure 2.1 and 2.2. that forms
an integral part of GRID systems aiding grid operator in day-to-day monitory, operation and
management of grid system in APTRANSCO and also the integrated southern region grid operation as
a whole from southern region load dispatch centre(SRLDC) Bangalore. The system is supplied and is
presently maintained by M/S. GE Energy, Florida, and U.S.A.
At present at back-up SLDC 2*10KVA UPS systems with only one battery bank back-up are
installed, for maintaining the un-interrupted power supply to the work stations and other equipment
installed at back-up SLDC. This configuration is giving problems it is require to take shut down on
one UPS and also if any one battery problem is causing interruption to the total UPS system. Hence
another battery bank may be procured and each UPS may be provided with independent battery bank.
In this configuration the reliability of the system will be improved. Battery chargers are proposed for
Warangal and nunna ALDCs for charging the spare battery cells. Load testing kits are proposed for
Warangal and Nunna ALDC to test the loading performance of battery banks.
5
2.5. CONTROL CENTRE SETUP OF LDCs
National Load Dispatch Centre (NLDC) is divided into 5 regional load dispatch centers. There
are Northern Regional Load Dispatch Centre (NRLDC), Eastern Regional Load Dispatch Centre
(ERLDC), Southern Regional Load Dispatch Centre (SRLDC), Western Regional Load
Dispatch Centre (WRLDC) and NorthEastern Regional Load Dispatch Centre (NERLDC).
The Southern Regional Load Dispatch Centre is divided into 6 states: Goa, Pondicherry,
Tamilnadu, APTransco, Karnataka and Kerala. From APTransco, it is supplied to Warangal (WGL),
Hyderabad (HYD), Vijayawada (VJA) and Cuddapah (CDP). They are clearly shown in the figure 2.
NLDC
WRLDC
Western Regional
AP
Goa Pondy TNEB Karnataka Kerala
Transco
NORTHERN REGION:
• Northern Region
• Western Region
• Southern Region
• Eastern Region
• North-Eastern Region
All the regional grids are monitored by Regional Load Dispatch Centers availing the advantage
of diversity in peak loads, hydro-thermal mix, off peak surplus etc. on a regional basis.
Formation of a National Grid is planned by 2011. in this inter-regional lines will be A.C.
Transmission with back to back facility (AC-DC-AC) and AC or DC Transmission and this will help
transfer of bulk power from one region to the other and also avoid cascade trappings in one region due
to the disturbances in the other region. As the system developed in more ways than one, we also have
• Investments in Transmission System not commensurate with capacity additions and load
growth
2.6.CONCLUSION
In this chapter, Power grid operation is discussed. The next chapter is about the SCADA which
CHAPTER – 3
SCADA
SCADA
3.1. INTRODUCTION
This chapter deals with the SCADA Overview , Architecture and Applications.
The major reasons for the development the development of SCADA (Supervisory Control and
There are conventional metering facilities in every powerhouse and substation. But storage of
such data at small intervals and generation of trend curves, graphs, reports etc., with high accuracy and
fast retrieval make the necessity of covering all power houses, substations with full fledged SCADA
systems.
SCADA (Supervisory Control and Data Acquisition) systems are used mainly for
acquisition of data for monitoring and also to have supervisory control in respect of selected
feeders/equipment. Since SCADA system monitors the power system in real time mode using the state
of art in computers and communication technologies. It allows speed isolation of faults and restoration
Date Acquisition:
In general the dynamical data acquired from remote end can be classified as below
DATA
ANALOG DIGITAL
SCADA stands for Supervisory Control and Data Acquisition. The primary function of
SCADA is Date Acquisition. In a power system SCADA, required date will be acquired from the
remote station/power house to the master computer centre. In order to gather the data from the fields,
one computer called Remote Terminal Unit (RTU) is used in the remote substation/power house. RTU
scans following data from the field at fast periodic intervals (milliseconds).The architecture of Scada
is shown in figure 3.1.
SCA
Fig: 3.1. SCADA SYSTEM ARCHITECTURE
The System Architecture shows us the Region AB in which Region AB is divided into Zone A
and Zone B. Zone A has station A1 and station A2. Zone B has station B1 and station B2.
11
To collect the data at Master Station from one or more Remote Stations periodically by polling
the RTUs sequentially, one computer called FEP (Front End Processor) is used like a reception
receiving the guest near the front of the house.FEP or another computer called Server/Workstation
may process the data acquired. The processed date is displayed on single line diagrams with converted
engineering values on another computer used by the dispatcher of shift engineer. This Computer
(Dispatcher’s Console) is also called Man Machine Interface (MMI) through which the operator can
interface or view the real time date of any selected station by using simple commands. The FEP,
Server, Workstation, Dispatch’s Console, Printers, etc are connected in LAN with redundancy.
At Remote location, the Transducer, Contact Multiplier Relays (CMR), Interposing Relays and
In conventional systems the substation/power house metering the analog parameters such
as voltage, current, MW, MVAR, frequency etc. are achieved making use of instrument transformers.
The secondary’s of Voltage transformers are rated for 110 volts and current transformers with 5A or
IA are commonly used. Since the RTU hardware cannot withstand 110 volts, IA inputs, Transducers
are used to take above inputs and give output with proportionate 4-20 mA.
Transducers are required for measurement of analog parameters. Some of them are:
• Frequency transducers
12
• Current transducers
• Voltage transducers
Transducers are also used classified as self powered or auxiliary powered depending upon the
usage of supply required for functioning of the units. Self-powered transducers do no need separate
voltage for normal functioning. They use PT secondary voltage given for its functioning. The normal
output will be 0 to 5mA, 0 to 5 volts etc. In respect of auxiliary powered transducers, they need extra
input voltage say 220 volts ac or 48 volts dc etc., for functioning. The outputs will be 4 to 20 mA
Contact multiplier relays (CMR) are used for providing potential free contacts from the used
contacts to acquire the status of circuit breakers etc. These are used where it is difficult to get spare
Interposer relays are used for execution of commands from the yard to the master station to
the remote equipment like CBs, Isolators, and OLTC. Separate relays are used for closing & opening
of CBs or isolators.
(iv) Remote Terminal Unit (RTU):
Remote Terminal Unit is a computer used at the remote station to scan all the analog and
digital date from the field. RTU also accepts and faithfully executes the commands issued by the
master station. RTU consists of following cards along with microprocessor, A/D converter and signal
conditioning units.
13
A L/R (Local/Remote) switches are provided in each RTU to totally block or enable remote
control operations. When the switch is placed in local mode and alarm is sent to the master station and
all control operations are electrically and programmatically blocked so that all other functions of RTU
RTU consists of the following components for receiving or transmitting the specific
parameters.
• Analog Input Card (AI Card) to scan parameters like MW, MVAR, KV, frequency, OLTC
indications.
• Digital Input Card (DI Card) to scan parameters like Breaker/Isolator status, SOE.
• Analog Output Card (AO Card) for driving trip chart recorders.
• CPU card for scanning all data from field and transmit to FEP for every few seconds.
Functions of RTU:
The RTU performs important function like scanning of data, time stamping of events occurred,
select before execute operation and Report by exception, which are briefly described below.
(i) Time Stamping of Events (SOE: Sequence of Events Occurred) the events occurring in the
power system have to be updated in the date base of host server in the same chronological order in
which they actually occur. This requires that the time of the clocks of all the RTUs of the entire
substation or power house within the whole system is the same. To facilitate this, each RTU in the
SCADA system is updated with the calendar information date and time down to millisecond from the
14
Master Station. Generally the standard reference time is acquired from the GPS (Global position
system) & RTU time is synchronized with the above Standard time at predefined short periodic
internal say few minutes. The RTU uses this time to Stamp ever event occurring in the power system.
by the operator, the select before execute sequence is performed. Here each command
from the master is actually executed as two distinct commands at the RTU to ensure that
correct equipment is selected to execute the Operation. The RTU reciprocates with a
positive or negative acknowledgment signal for confirmation by the operator. The master
station then sends and executes command to the RTU and completes the control cycle.
This function is provided to reduce the number of date transfers to the Master Station from the
RTU and thereby reducing the load on the communication channel. A Dead band is defined for each
analog such as voltage, current etc. individually. The RTU calculates the difference at every scan cycle
and accumulates the differences between the instantaneous value and the previously transmitted value.
Each analog value is transmitted to the MCC (Master Control Centre) only when the absolute value of
In respect of digital data, like status indication of CBs, isolators’ etc. data does not change frequently.
Hence such data is sent whenever there is a change i.e. report on exception or at comparatively
(i) Scanning of date (analog & digital) from the field continuously.
15
(vi) Executing control commands of host with priority and check before option.
gather data from all RTUs by frequent polling. FEP gathers date and also sends control commands
(ii) Host/Server/Workstation:
The data acquired by FEP by polling the RTUs is processed or sent to Host server for
16
• Limit checking.
It is the interface between man and the field (PH/SS) through which the operator can get the
display of all dynamic data on graphical pictures and can also control the required equipment at
remote field. User friendly GUI soft wares are available to develop single line diagrams of PH/SS or
common grid displayed with static lines and dynamic data. The entire system can be monitored and
controlled from the displays. All MMI functions are carried out through interactive dialogues. The
dialogues use icons, pop up and pull down menus, dialogue boxes etc. and hence do not require any
functional keyboard. With the latest advanced techniques, MMI design has assumed added importance
in recent years. In fact considerable success has been achieved in making these systems more and
The generation of trend curves, reports, etc can be done by using the software tools provided.
These MMIs (Man Machine Interfaces) do the following works:
• Report generation
Hardware Components
Software Components
17
HARDWARE COMPONENTS
SCAD
Fig : 3.2. HARDWARE COMPONENTS
The Communication takes place between the CC and RTU. The Communication between RTU
and Panels like Transducers by relays takes place. The AI (Analog Input), DI (Digital Input) is from
Panels to RTU and DO (Digital Output) is from RTU to Field. From Panels, the communication takes
Software Components :
• Data Acquisition
• Data Processing
• Control
• Alarm and Events
• Database
• Logging and Report
18
Data Acquisition
Transducers
/
Relays
/ IEDs
A
I
D Device
I Panel s
s
D
O
RTU FIELD
CC COMMUNICATIO
N
Panels like Transducers with the output voltage (0-10) DC by relays takes place by the field
value 11KV. The AI (Analog Input), DI (Digital Input) is from Panels to RTU and
DO (Digital Output) is from RTU to Field. From Panels, the communication takes place to
device. Where in data acquisition the connectivity between the field equipment will be taken
place. Multiple scan rates, multiple protocols (IEC/ Modbus/DNP), Time Synchronization, Data
types/ Data Resolutions (AI/DI/PI/BCD) (8/12/16). Acquisition will fetches data by reporting
19
Data Processing
SCADA – Software
Data Processing
Fig:3.4.DATA PROCESSING
The communication between CC and RTU takes place. The Communication between RTU and
Panels like Transducers with the output voltage (0-10) DC by relays takes place by the field value
11KV. The AI (Analog Input), DI (Digital Input) is from Panels to RTU and DO (Digital Output) is
from RTU to Field. From Panels, the communication takes place to device. Where in data acquisition
the connectivity between the field Equipment will be taken place. The engineering conversion with
linear, non-linear, piece wise, look up with the calculation of sub system by the zero suppression and
having the reasonability checking in the data in a line wise process. As shown in Fig:3.4.
20
Control
SCADA– Softwar
Fig: 3.5.CONTROL
Monitoring the whole distribution transformer, sub transmission system, distribution substation,
Three-phase Primary feeders, Dispersed Storage and generation (DSG), Sectionalizing switch, Voltage
Regulator, One-phase lateral feeder. Where the DSG maintains the solar and wind sources 100KW to
1MW. The photovoltaic power supply up to 100 KW. The control of the single, group, sequential and
closed loop control is also monitored by the LOW DISPATCH CENTER which is in A.P.GENCO.
The total control is being done by the visual center with the big screen which displays the whole state
wise stations and sub-stations in each lane to lane along with the distribution transformers which is
shown in fig:3.5. The select –check execute and immediate check is being done in spot on by
informing to the particular station or where the problem is being shown. To execute the problem there
21
is a immediate execute interlocks based on attributes and the output values will be as either analog
output (AO) or as digital output (DO), the pulse value is also being required to have the immediate
execution. If suppose any problem is occurred in the JNTU feeder then the immediate action will be
taken. As it will being displayed on the monitor in the low dispatch center as shown in fig: 3.6.
S C A D A– S oftw
C ontrol
Fig : 3.6. Example for controlling the feeder
S in g le , G r o u p , S e q u e n tia l a n d
22
S e le c-C
t h e c -kE x e c u te , I m m e d ia te
In te r lo c ks b a se d o n A ttr ib u te
SC A D A– Softw a
Control
Fig: 3.7 JNTU feeder CB closed
As shown in the above fig, if the problem occurs it will indicates like to close the feeder circuit
V oltage
Alarms & Events
24
Data Base
The data base is required for the online data base editing and grouping for the ACESS & LOG.
The data base library is also required for the data base acquisition in the supervisory control and
monitoring the status at each and every time in the log sheet.
After completing the Data acquisition,Data processing,Control,Alarm events and Data base,
then the Logging and Reporting takes place.
Now-a-days we find the usage of SCADA applications in all industries for their specific data
acquisition & supervisory control, Examples: in steel plants, gas plants, cement plants, etc. In power
• Power plants
• EHT substations
• Distribution automation
• SRLDC-Bangalore
• SLCD-Hyderabad
• Sub LDC-Warangal
25
• Sub LDC-Vijayawada
• ULDC-Layout
• Data acquisition.
• Supervisory Control.
• Limit checking.
• On-line LF studies.
• Contingency studies.
• Voltage/VAR scheduling.
26
• Remedy/prevention actuation.
• Voltage/VAR studies.
• Disturbances recording.
• Unit commitment.
3.8. CONCLUSION
In this chapter, the SCADA Overview, Architecture and Applications are discussed. The next
chapter is about the problems and rectifications of Power grid will be discussed in detail.
27
CHAPTER – 4
4.1. INTRODUCTION
This chapter deals with the Monitoring of Power grid parameters and the causes of grid
collapse.
The operation of Electrical Power System consisting of Generating station, Transmission lines
and distribution network is dynamic in nature as the power generated gets consumed instantly and it
cannot be stored. To ensure that the load incident matches with the generation for maintaining system
frequency at 50 Hz., the grid operators have to continuously work out the unit to be brought or backed
down or loads to be interrupted and take action. The technical limitations of each type of generating
units and the stipulations in Power Purchase Agreement make Merit Order Dispatch a complex
exercise. This being so, every endeavor should be made to maintain it above 49 and below 50.5 Hz.
While the State Power System are monitored round the clock by the State Load Dispatch
Centres, the Regional grid as a whole is monitored by the Regional Load Dispatch Centre with a
watchful eye on various operating parameters like frequency, voltage, power flows ( both active and
reactive) through all lines and equipment.
The Load Dispatchers at Regional & State Level have to be provided with authority to
enforce grid discipline through remote control of identified elements in the power system in order to
restore system security wherever it is under threat.
A grid collapse or a total blackout of a region may occur due to the following reasons.
Sudden large scale addition / reduction of load causes wide fluctuations in frequency and
tripping of lines on account of power swings or over voltages or generators experiencing low / high
frequency or low/high voltage. This may lead to cascade tripping of lines as well as generators causing
separation of State Grids. This may result in partial or total grid collapse.
As per Indian Electricity Grid Code (IEGC) addition or deletion of loads of more than 100
MW should be with prior intimation of RLDC except in cases of emergencies arising out of a need to
protect equipment.
When all the lines connected to an important grid substation trip due to a bus fault on the
operation of “Bus Bar protection” relays or operation of “LBB ( Local Breaker Backup) protection”
relay ( if faulty lines are not cleared due to problem in the circuit breaker), the other lines in the system
get overloaded and trip. This may lead to power swings and trigger a gird collapse.
Tripping of one or more heavily loaded critical lines on fault may cause overloading of parallel
lines and if Generating Stations are available on either side, large power swings occur resulting in
separation of systems or even a Grid collapse. Such occurrences may lead to total “Black-outs or
‘brown-outs”.
Low voltages occur at particular locations in the system due to high reactive nature of the loads
and if adequate capacitive compensation is not provided, this may cause overloading of lines beyond
surge impedance levels. Extremely low voltages at any node in the system will cause power swings on
transmission lines and if tripping of critical lines take place, it may lead to grid collapse.
29
The system frequency has to be maintained within ±1% of rated frequency as per I.E. Act. To
ensure the security of the grid, the frequency should be maintained above 49.5 Hz.
As per IEGC, each generating unit shall be capable of instantaneously increasing its output by
5% and maintain for minimum of 5 minutes when the frequency falls and when operating at any
loading upto 105% MCR, (Maximum Continuous Rating).
All generating units shall have their automatic voltage regulators in operation with appropriate
settings for maintaining voltage profile.
4.3. CONCLUSION
In this chapter, Monitoring of Power grid parameters and Causes of Grid Collapse are
discussed. The next chapter is about the Problems and Rectifications of Power grid.
30
CHAPTER-5
5.1. INTRODUCTION
This chapter deals with the problems experienced in Southern Regional Grid
• Under frequency operation for long spells due to large gap between generation
availability and demand.
• In S.R., the load in three major states is predominantly Agricultural. Dry spell for three
days causes 40% increase in hourly demand and rainfall causes in load crash.
• No, Spinning margins. Hence system disturbances likely for loss of even 200MW of
Generation.
• Heavy load shedding resorted both manually and by under frequency relays during dry
spells in Agricultural season.
• Even a small perturbation in the system causing power swings and cascade tripping.
• Grid Managers under severe strain maintaining round the clock vigil.
31
5.3. CONCLUSION
In this chapter, Problems of Power grid are discussed. The next chapter is about
400KV Maamidipally Substation and Unified Load Dispatch Control (ULDC).
32
CHAPTER – 6
6.1. INTRODUCTION
This chapter deals with 400KV MAAMIDIPALLY SubStation and Unified Load Dispatch
Control.
The electricity has become an essential commodity in today’s life and as such the demand for
the electricity is also growing day-by-day. With such a heavy demand in the fast developing city of
Hyderabad, uninterrupted supply of power and maintaining the voltage at the required constant level
has become a challenging job to the then Andhra Pradesh State Electricity Board. To over come these
two problems, the then Andhra Pradesh State Electricity Board has decided to increase its power
transmitting capacity from 220kv to 400 kV. Accordingly, it was decided to construct some 400kv
sub-stations in the state. As a part of that program, the capital city of the state, Hyderabad, for
providing constant and uninterrupted power supply to the city at required constant voltage. Thus a 400
kV Sub-Station has come up at MAAMIDIPALLY.
The generator is supplied and installed by M/s. SHANTI Electricals, Hyderabad in the sub-
station premises for supply of power to the switch–yard equipment, control room, PLCC batteries etc.,
in case of failure of regular power supply. It runs with high speed diesel and it has a diesel storage
capacity of 1000 Liters.
A unified load dispatch center is also established in the control room building of the Sub-
Station, for economic load dispatch and energy management at the state level. The sub-station has a
GPS satellite time synchronizing system, which will facilitate recording of all events in the sub-station
.The system felicities clinical fault analysis in view of the availability of sequence of events. The
33
present SCADA system is having on-line study facility in electrical management system. It has many
advantages such as dispatcher’s interface to SCADA real-time data and functions associated with a
single telemetered point is provided through the select user interface.
Optical Line Terminal equipment and Microwave & Multiplexing equipment are installed at
various sub-stations in the state for optical and microwave communications. A remote operated
centralized location transmission network management system has been installed at the 400 KV Sub-
Station at MAAMIDIPALLY, to control these equipment with the network management system, the
monitoring and acknowledging the alarms, configuring or modifying the equipment installed at
various sub-stations can be done remotely from the 400kv sub-station at MAAMIDIPALLY.
The P.L.C.C. Batteries required for the sub-station were procured from M/s. AMARRAJA
Batteries ltd., TIRUPATHI, since the sub-station has all costly equipment and machinery which
require utmost care, the sub-station equipment and machinery has been insured with M/s. new India
Assurance Ltd,.
After receiving power at 400kv strength, the voltage will be stepped down to 220 KV and the
same is being transmitted to various 220 KV sub-stations at Hyderabad. There are two lines connected
to the 220 KV sub station at GachiBouli, Hyderabad and another two line connected to the 220 kV
sub-station at ChandrayanaGutta, Hyderabad. Work is going on to establish a connection between the
400 kV sub-station at Hyderabad with the 220 kV sub-station at YedduMailaram, Hyderabad.
Data Acquisition System consists of transducers, relays and Remote Terminal Units (RTUs)
located at remote stations. Transducers interface with Current transformers (CT) and potential
transformers (PT) to measure MW/MVAR flows, voltage and frequency. Relays are used to acquire
status of circuit breakers and isolators. 11 Nos. RTUs are with 8085 Intel Processors and 10 Nose
RTUs are with 68000 Mobile based CPUs. There are two FEPs, one being active and the other at
serving as standby. The host computer will processes the data, converts into engineering value and
display the save as dynamic data in the displayed on single line diagram of station pictures for the
ready information of the shift engineer. Each shift engineer (load dispatcher) is provided with a
34
computer called MMI (Man machine interface) with 19” color monitor to view the dynamic data of
required station or overall grid in color graphics. The dispatcher can also generate trend curves,
current as well as historic reports making use of software tools provided.
PLCC is used as the main communication system for data transmission between RTUs to host
computer. The data over PLCC coming from 21 stations terminates at he 220 kV sub-stations at
sharoornagar and Chandrayanagutta near Hyderabad. The LD center and the above 220KV substations
connected by UHF links. Some RTUs are connected to LOAD DESPATCH CENTRE in multi drop
and other with point to point links. The PLCC is also used Telephone links are provided for voice
communication between LD Center and RTU station as different frequencies called express channel.
• Provide Real time data from all Nodal points of Sub LDCs to State LDC and from State
LDCs to RLDC.
35
A.P.ULDC(Andhra Pradesh Unified Load Dispatch and Communication) scheme covers all
generation stations, all 400KV substations, all 220KV substations, and three 132KV substations (total
90) in A.P. The system enables energy management, supervisory control of 132Kv feeders for the
present and extendable for automatic generation control as per merit order dispatch including inter
regional exchanges.
The state LDCs of Andhra Pradesh, Tamilnadu, Karnataka, Kerala and Pondicherry are all
interconnected to the southern Regional Load Dispatch Centre (SRLDC) at Bangalore for real time
integrated stable operation to provide a Stable power system.The ULD centre (SLDC) is provided with
powerful tools for efficient Energy Management System, Merit Order Dispatch and Stable System
Operation.
(i) EMS/SCADA
The communication network supporting the hierarchical system of Load Despatch Centres has
been established for transmission of large volumes of voice/data at high speeds from RTUs at
Substations/generating stations to ALDCs, ALDC to SLDC and SLDC to RLDC.Wide Band
Communication Network comprising Digital Microwave and OFC system has been installed.
36
• Time synchronization with GPS at all RTUs and control centres for time stamping of events
correct to a millisecond.
• OFC/MW Broad Band Communication back bone network interface with PLCC channels
sprouting out of it to reach end stations.
• Hot stand by facilities provided at PSU and CPU levels in the OFC/MW Communication
System to maintain uninterrupted communication round-the-clock.
• RTU support protocol conversion for information exchange between multiple masters with
multiple databases, fully integrated programmable logic control using Prologic station
automation with control features.
6.4.4. BENEFITS
• Improved quality of power supply of maintaining critical operating parameters like voltage,
frequency, etc.
6.5. CONCLUSION
In this chapter, 400KV Maamidipally Substation and Unified Load Dispatch Control is
discussed in detail.
38
CHAPTER – 7
CONCLUSION
CONCLUSION
7.1. CONCLUSION
In this project a sincere effort has made for the Power grid Management through Scada.The
present project gave us an opportunity to know about the Power grid Operation, Scada Overview,
Architecture and Applications and also the problems on Power grid and the 400KV Maamidipally
Substation and Unified Load Dispatch Control.
39
BIBLIOGRAPHY
BIBLIOGRAPHY
TEXT BOOKS :
WEBSITES :
1. www.wikipedia.org
2. www.google.search.com
40
APPENDIX
41
ORGANISATION PROFILE
APGENCO
Andhra Pradesh State Electricity Board is a statutory authority constituted under the provisions
of Electricity Supply Act 1948 charged with responsibility of generation, transmission and distribution
of electricity in the state of Andhra Pradesh. Consequent to reforms, APSEB was unbundled into two
corporation’s viz. Transmission Corporation of Andhra Pradesh Ltd. (APTRANSCO) and Generation
Corporation of Andhra Pradesh Ltd. (APGENCO).