Está en la página 1de 38

MECHANICAL & ELECTRICAL WORKS

MEASUREMENT (SBEQ3213)
Week 7 : Underground Drainage

Sr. Dr. Sarajul Fikri Mohamed


Faculty of Built Environment

PLUMBING WORKS
MEASUREMENT FOR PLUMBING WORKS
Divided into 4 section:

1. Cold water installation


2. Sanitary fittings
3. Soil, waste and vent pipe

4. Underground drainage

STAGES OF PLUMBING SYSTEM IN BUILDING


COLD WATER SERVICES

SANITARY FITTINGS

SOIL, WASTE & VENT PIPE

UNDERGROUND DRAINAGE

WASTE DISPOSAL SYSTEM

TYPES OF DRAINAGE
Drainage in building can be divided into two main types:

1. STORMWATER DRAINAGE
For surface water i.e rainwater. Normally it is included
under External Works. Sometimes called surface water
drainage.
2. FOUL/SOIL DRAINAGE

For wastewater from soil and waste pipe.

Separate system

Combined system

ITEMS TO BE MEASURED
1. Trench excavation

SECTION V DRAINAGE
Generally
V.1 Information
1. Work beyond the boundary of the site shall be so described and
any restriction regarding access, etc. shall be stated.
2. The nature of the ground in which the excavations are to be
made shall be given in accordance with clause D.1.

ITEMS TO BE MEASURED
Drains
V.2 Excavation
1. Excavating pipe trenches shall be given in METRES stating the

starting level, the depth-range in increments of 2.00 m and the


average depth within the depth-range to the nearest 0.25 m.
2. Excavating curved trenches shall be so described irrespective of

radius.
3. Earthwork support, treating bottoms, filling in compaction and
disposal of surplus soil shall be given in the description.

ITEMS TO BE MEASURED
Drains
V.2 Excavation (continued)
4.

Trenches next to roadway, next to existing building or in unstable

ground shall each be so described.


5.

Trenches in rock as defined in clause D.12.2 shall be described.


Alternatively rock may be given in METRES as EXTRA OVER the

trench in which they occur.


6.

Breaking

up

concrete,

reinforced

concrete,

brickwork,

tarmacadam and the like shall each be given separately in METRES

as EXTRA OVER the trench in which it occurs stating the pipe


diameter as clause V.2.3.

ITEMS TO BE MEASURED
V.3 Disposal of water
Disposal of water shall be given in accordance with
clause D.15 16.

METHOD
OF
CALCULATION
MH1
MH2
G.L = 10.00
I.L = 9.45

G.L = 10.00
I.L = 7.55

Adjustment to invert level for pipe support, sand blinding and thickness of pipe:
1

Thickness of pipe

19mm

Concrete support

100mm

Blinding

25mm

TOTAL

144mm
MH1

IL

MH2
IL

9.45

7.55

0.144

(less)

0.144

(less)

9.31

meter

7.41

meter

METHOD OF CALCULATION

Note: Excavation has to be divided into two section:


i) Not exceeding 2.00m
ii) Exceeding 2.00 but not exceeding 4.00m

METHOD OF CALCULATION
THEREFORE, THE AVERAGE DEPTH FOR (I) SECTION

THEREFORE, THE LENGTH OF EXCAVATION FOR (I) SECTION I.E X M:

Note: The length of (x+y) can be measured directly from drawing.

EXAMPLE : Trench excavation


Excavate trench for pipe not exceeding 200 mm nominal size starting
from ground level not exceeding 2.00 m deep average 1.50 m deep
including support, grading bottom, filling in, compaction and disposal of
surplus soil as directed.

Stage (i) n.e 2.00 m deep

METHOD OF CALCULATION
Once the length of x is known, the length for y can be establish by
subtracting the value of x from the length of (x+y).
AVERAGE DEPTH FOR SECTION (II):

EXAMPLE : Trench excavation


Excavate trench for pipe not exceeding 200 mm nominal size starting
from ground level exceeding 2.00 m but not exceeding 4.00 m deep
average 2.25 m deep as before described.

Section (ii) exc. 2.00 n.e 4.00 m deep

Using the same principles, calculation can be made from manhole to


manhole until it reaches the soil treatment system.

UNDERGROUND DRAINAGE
2.

Pipe/drain
Types of pipe/drain commonly used for underground drainage:

a. VITRIFIED CLAY PIPE (VCP)


Nominal size : 100 mm 900 mm diameter.
b. CONCRETE PIPE
Nominal size : 150 mm 1800 mm diameter.
c. CAST IRON PIPE
Nominal size: 75 mm 900 mm diameter.

UNDERGROUND DRAINAGE

CAST IRON PIPE,


300MM DIAMETER

UNDERGROUND DRAINAGE

INSPECTION
CHAMBER

UNDERGROUND DRAINAGE
V.5 Pipework and surface water channels

1.

Pipes (measured over all pipe fittings) shall each be given in


METRES stating the kind and quality of pipe, the nominal
size and the method of jointing. Any pipe not laid in bottom
of the trench shall be given separately and the depth stated in
accordance with the depth-range stages in clause V.2.1.

METHOD OF CALCULATION

P = Length of pipe in trench

D1 & D2 and (x+y) are known and using the


Pythagoras theorem:

EXAMPLE : Pipe/ drain


Vitrified clay pipe and fitting with roll-in rubber ring joint to B.S 65 and
B.S 2494 as described:

100 mm diameter drain pipe, laid on concrete support (m/s) in trench


(m/s).

(MH1 MH2)

UNDERGROUND DRAINAGE
3.

Pipe support
Types of pipe support:

a. Bed
b. Haunching
c. Surround
d. Class A
e. Class B
f. Class D

UNDERGROUND DRAINAGE
V. 4 Beds, benchings and coverings
1.

Beds, benchings and coverings shall each be given separately


in METRES stating:
a.
b.
c.

Nominal size of the pipe to be laid


Widths and thickness of the beds, benchings, haunching,
surround and the like.
Materials from which the beds, benchings, haunching,
surrounds and the like are to be constructed. Any
formwork required shall be deemed to be included.

EXAMPLE : Pipe support


100 mm thick mass concrete Grade 15 as described bed 457 mm wide
under 150 mm diameter pipe (m/s) including haunching on both sides to
center line of pipe including all necessary formwork

12.55

(MH1 MH2)

TYPICAL HAUNCHING

EXAMPLE : Haunching
150 mm thick x 450 mm wide mass concrete Grade 15 as described bed
under 150 mm diameter pipe (m/s) including surround with similar
concrete 150 mm thick including all necessary formwork.

(measured in metre)

EXAMPLE : Haunching
100 mm thick crusher run bed, 457 mm wide under 100 mm diameter
pipe (m/s) including filling crusher run to center line of pipe and backfill
with 300 mm thick (minimum) selected sand compacted to Architects
approval.

(measured in metre)

UNDERGROUND DRAINAGE
4.

Manhole
Sumps, manholes, soakways, cesspits, septic tanks, imhoff tank and
the like.
V.6 Generally
1. Sumps, manholes, soakways and the like shall each be grouped
together and GIVEN IN DETAIL under an appropriate heading
stating the number.
2.

Cesspits, septic tanks, imhoff tanks, oxidation ponds and the like
for the treatment and disposal of sewage shall each be grouped
together and GIVEN IN DETAIL under an appropriate heading
stating the number.

UNDERGROUND DRAINAGE
4.

Manhole (continued)
V.6 Generally
3. Excavation, concrete works, brickwork and other works shall be
given IN ACCORDANCE WITH THE APPROPRIATE SECTIONS.
4.

Building in ends of pipes shall be ENUMERATED stating the


nominal size of the pipe.

5. Channels, concrete benchings, step irons, covers and intercepting


traps shall each be ENUMERATED SEPARATELY stating the type,
the quality, the size and the method of bedding or fixing.

MANHOLE
ITEMS TO BE MEASURED
Before taking off for manholes is carried out, it is good practice to prepare
Schedule of Manholes referring to:

a.
b.
c.
d.
e.
f.

Size of manhole (internal and external)


Depth of manhole (invert and excavated level)
Thickness of brickwall
Ground level
Thickness of base and concrete cover slab
Other related information

The SMM requires a heading to be establish stating the number of


manholes to be measured.

EXAMPLE : manhole
The following in 6 Nos. manholes:

1. Excavation pit for manhole


Measured in CUBIC METRE (D.12.6) according to
depth classification as in clause D.10.

2. Disposal of excavated materials


Measured in CUBIC METRES whether disposal on site
(D.18) or off site (D.19).

EXAMPLE : manhole
The following in 6 Nos. manholes (continued):
3. Blinding
Measured in SQUARE METRES stating the material and
the thickness .
4. Concrete bed for base
Measured in CUBIC METRES stating the thickness
according to classification as clause F.2.1.
5. Brickwall
Measured in SQUARE METRES (measured mean
length x height) stating the thickness, kind and quality of
bricks, type of bond and composition and mix of mortar.

EXAMPLE : manhole
The following in 6 Nos. manholes (continued):

6. Plastering to internal surface of brickwall


Measured in SQUARE METRES stating the particulars
as in clause S.2.1 and measured the area in contact with
the base as in clause S.2.2.
7. Reinforced concrete suspended cover slab
Measured in CUBIC METRES stating the thickness
according to classification as clause F.2.1.

8. Formwork to soffit of suspended cover slab.


Measured in SQUARE METRES. No deduction shall be made
for voids not exceeding 1.00 m2.
.

EXAMPLE : manhole
The following in 6 Nos. manholes (continued):
9.

Formwork to edges of suspended cover slab


Measured in METRES stating the height of the edge
according to clause F.11.1.

10. Formwork to edges of concrete base slab


Similar to item (9).
11. Reinforcement to suspended cover slab/base slab
If the slab uses fabric reinforcement, it is measured in
SQUARE METRE the area covered. No deduction shall
be made for voids not exceeding 1.00 m2 (F.9.1 3).
.

EXAMPLE : manhole
The following in 6 Nos. manholes (continued):
12. Concrete benching
Measured in NUMBER stating the quality of concrete, size
method of bedding (V.6.5).
13. Screed to concrete benching
Measured in SQUARE METRE measured the area in contact
with the base (S.2.1 2).
14. Step iron
Measured in NUMBER stating the type, quality, the size or
girth and the method of fixing (V.6.5).

EXAMPLE : manhole
The following in 6 Nos. manholes (continued):
15. Channel
Measured in NUMBER stating the type, the quality, the size
and method of bedding (V.6.5).
16. Building in ends of pipes/drain to manhole
Measured in NUMBER stating the nominal size of pipe
(V.6.4).
17. Cast iron manhole cover
Measured in NUMBER stating the type, the quality, the
size and method of fixing (V.6.5).

EXAMPLE : manhole
The following in 6 Nos. manholes (continued):
18. Connection to main sewer
V.7 Generally
1. Connecting ends of drains to main, making good public
highway and other work which may only be carried by
a Public Undertaking or Local Authority shall be given
as PROVISIONAL SUM.
2. Connection to existing work shall be ENUMERATED
stating the size of pipe or drain and the structure.
Cutting openings, making good, jointing etc. shall be
deemed to be included with the item.

19. Testing of drains


V.8 Testing the drainage system shall be given as an
ITEM stating the method of testing.

EXAMPLE : Manhole
The following in 6 Nos. manholes (continued):
NOTE:
Usually, when a taking off is started using a heading, it must be
ended with a closing remarks.
i.e
(End of 6 NOS. manhole)

THANK YOU
for your kind attention

También podría gustarte