Presentation on DRR Schemes of

Laxmipur District Ramgati Upazila

Union wise Scheme Summary


District
Laxmipur

Upazilla
Ramgati

Union
Char Abdullah

Scheme Code Project Title/Details


LSM0613001

LSM0613002

LSM0613003

LSM0613004

Budget

Beneficiaries

Construction of Earthen Killa at Telirchar


Purbapara Village of ward # 02.

1555550

2,980

Re Excavation of Chairman Bazar Pond.

580562

1,500

Construction of Earthen Killa at Telirchar


Dakhinpara Village of ward # 04.

2635154

2,000

Construction of Earthen Killa at Telirchar


Purbapara Village of ward # 09.

1555550

1,950

Total

6,326,816

8,430

Presentation on Ramgati Upazila under Laxmipur Dist. DRR Schemes


Proposed scheme site

Pictorial view of Char Abdullah

Pictorial view of Char Abdullah

Pictorial view of Char Abdullah

Pictorial view of Char Abdullah

Proposed Interventions for Char Abdullah Union of Ramgati Upazila.


Total 4 Nos. of Schemes:
01. LSM0613001 : Construction of Earthen Killa at Telirchar Purbapara
Village of ward # 02.
02. LSM0613002 : Re Excavation of Chairman Bazar Pond.
03. LSM0613003 : Construction of Earthen Killa at Telirchar Dakhinpara
Village of ward # 04.
04. LSM0613004 : Construction of Earthen Killa at Telirchar Purbapara
Village of ward # 09.

Major Hazards and Impact of Char Abdulah Union of


Ramgati Upazila
Hazard
Cyclone , Tidal Surge & Draught:
* People and their livestock not have safe place during
Flood, cyclone and tidal surge.
* During Dry season Scarcity of sweet water.
Impact:
* This intervention shall ensure easy access to
Elevated land / Killa and safety of livestock and
human during flood, cyclone and Tidal surge.
* Availability of sweet water from Re-Excavated Pond
round year.

Rational for the Proposed Schemes at Char Abdullah.


Cahr Abdullah is very remote Union and island Cahr which is 35 KM

far from Ramgati Upazila HQ. Surroundated by Meghna River.


Char is unprotected and every day inundated by tidal water.
Presently In this Char have not adequate number of Killa where the
People and their livestock can take shelter during tidal surge and
cyclone.
Every Cyclone the Upazila administration of Ramgti have taken
initiative for evacuate the people from this risky char to safe place at
main land. But they did not take any initiative about Poultry and
livestock. Here mentioned that Large number of Cow and Buffalo are
rearing by the farmers. They produce huge amount of milk and every
day supply it in the urban area.
During dry season people face scarcity of sweet water as this area is
saline water zone.

Basic Information about the Scheme


01. LSM0613001 : Construction of Earthen Killa at
Telirchar Purbapara Village of ward # 02.
Bottom Area is 70.0 Meter X 70.0 Meter
Design height is 2.60 Meter.
Flood Level is 1.98 Meter.
Pre Nill at Khas land.
Net Volume of work 11399.26 cum.
Cost of Killa including one DTW & Two Latrine is
Tk. 1510243.00

Basic Information about the Scheme


02. LSM0613002 : Re Excavation of Chairman Bazar Pond.

Av. Present Depth of the pond is 3.0 Meter.

Design Depth of the is 5.00 Meter.


Re- Excavation of the pond with Construction of the

Bank and Provide necessary vegetation.


Volume of the work is 4764.85 Cum.
Cost of the intervention is Tk. 563652.00

Basic Information about the Scheme


03. LSM0613003 : Construction of Earthen Killa at

Telirchar Dakhinpara Village of ward # 04.


Bottom Area is 100.00 Meter X 100.00 Meter
Design height is 2.44 Meter.
Flood Level is 1.85 Meter.
Pre Nill at Khas land.
Net Volume of work 19899.00 cum.
Cost of Killa including one DTW & Two Latrine is Tk.
2558401.59

Basic Information about the Scheme


04. LSM0613004 : Construction of Earthen Killa at

Telirchar Purbapara Village of ward # 09.


Bottom Area is 70.0 Meter X 70.0 Meter
Design height is 2.60 Meter.
Flood Level is 1.980 Meter.
Pre Nill at Khas land.
Net Volume of work 11399.26 cum.
Cost of Killa including one DTW & Two Latrine is Tk.
1510243.00