INSPECTION & TESTING REQUIREMENTS

SAUDI ARAMCO FORM-175

SCOPE:

REVISION: 02/20/2012
REPLACES: 06/22/2011

CODE NUMBER:

IR340100

PAGE:

1 of 2

VALVES: Control, Steel, General Service, Pneumatic Operated, Up to and Including Class 2500 ratings.

TEST AND INSPECTION PER: 34-SAMSS-711, and Specifications As Noted Below.


(1) VISUAL INSPECTION WITNESSING BY INSPECTOR (Note 1)
(2) CERTIFICATES / RECORDS TO BE CHECKED BY INSPECTOR
(3) CERTIFICATES / DATA TO BE PROVIDED BY VENDOR / SUPPLIER / MANUFACTURER

0010
0010

***
X

Pre-Fabrication/Production Requirements

Specification Details / Notes:

Pre Inspection Meeting

0020

Material Test Reports

Shall be as specified in the ISS. See SAMSS for details.

0030

WPS/PQR /NDE

Qualification Records

0040

Data Sheet & Drawings

0020
0030
0010

***
***
X

0020

In process inspection & test requirement


Final inspection & test requirements

Specification Details / Notes:


Specification Details / Notes:

Impact Test

Only on low temperature service (below -46C) materials.

Workmanship, Components and Dimensions:

0030

a) Valve Manufacturing

Valve design, body pressure-temperature rating and minimum


wall thickness shall comply with ASME B-16.34.

0040

b) Flanged Connections

Raised Face (RF) or Ring-Joint (RJ) shall conform to ASME


B-16.5 and ASME B-16.20. (See Note 3)

0050

c) Face-to-face Dimensions:

0070

i) Flanged Globe Style

Shall comply with ANSI/ISA 75.08.01 Or ANSI/ISA 75.08.06.

0080

ii) Flanged Globe Style Angle

Face-to-Centerline Shall comply with ANSI/ISA 75.08.08.

0090

iii) Flangeless Valves

Shall comply with ANSI/ISA 75.08.02.

0100

iv) Butterfly Valves

Shall comply with API STD 609.

IR340100 Continued...

INSPECTION & TESTING REQUIREMENTS


SAUDI ARAMCO FORM-175

REVISION: 02/20/2012
REPLACES: 06/22/2011

CODE NUMBER:

IR340100

PAGE:

2 of 2

(1) VISUAL INSPECTION WITNESSING BY INSPECTOR (Note 1)


(2) CERTIFICATES / RECORDS TO BE CHECKED BY INSPECTOR
(3) CERTIFICATES / DATA TO BE PROVIDED BY VENDOR / SUPPLIER / MANUFACTURER
0110

0120

0130

d) Bolting

Bolting for body, bonnet, and cover shall be in accordance with


NACE MR0175/ISO 15156. Only for sour service.

e) Hardness & Heat Treatment Requirement

As per 34-SAMSS-711

f) Nondestructive Testing , Radiography

As per 34-SAMSS-711

Visual & Dimensional Inspection

As per 34-SAMSS-711

0140

0150

Seat Leakage Test

Shall meet the ANSI/FCI 70-2 class specified on the ISS.

0160

Functional & Performance Test with Actuator

If actuator specified in the Purchase Order.

0170

Shell Hydrostatic Test

Shall be conducted per ANSI/ISA 75.19.01.

0180

PMI

As per 34-SAMSS-711

Final Materials Disposition Report

0190

0200

Storage and Shipment

As per 34-SAMSS-711.

Notes:
(1) May only be waived by the responsible Saudi Aramco, ASC, or AOC Inspection Offices.
(2) See form SA175 - 000003 for instructions on using this form.
(3) Dimensions of flanges over 24 in size shall conform to the specified standard drawings.

End of IR340100