Documentos de Académico
Documentos de Profesional
Documentos de Cultura
1. GENERAL
Page - 01
Project Name
Contract Number
Project Code
31/May/10
Monthly meeting on
2. PROJECT DATA
Employer
Consultant / Engineer
Maga PM / SM
Mr.P.A.S Piyawickrama.
Construction of 15 Storeyed Building with 200ft Height and Total floor area 100,000ft 2
3. CONTRACT DATA
Original
Contract value Rs.
###
Commencement date
11/Nov/09
Original
Completion date
Revised
784,364,278.78
Contract Type
Revised Approved
11/Nov/11
11/Nov/11
Up to ( date)
24
18
Requested
Approved
17
11
Remaining period ( % )
71%
61%
Balance Work
Remarks :
4. FINANCIAL DATA
Cost surplus /overrun
CURRENT
Up to ( date )
Rs.
AT COMPLETION
Rs.
Budgeted
31/May/10
(12,940,956.51)
-2%
Budgeted
59,401,368.71
Actual
31/May/10
23,873,070.55
3%
Expected
95,000,000.00
5. PROGRESS DATA
Up to
5/31/2010
PLANNED
Rs.
%
107,876,221.31
13.8%
%
12.1%
827,076.45
Total
107,876,221.31
676,488,057.47
ACTUAL
Rs.
94,647,646.12
95,474,722.57
86.2%
689,716,632.66
87.9%
Page - 01
235 M
23/Jun/10
26/Jun/10
area 100,000ft 2
87.9%
AT COMPLETION
%
8%
12%
Lead / Lag
-13,228,575.19
-1.69%
MPRR Continued .
Page - 02
23/Jun/10
Amount submitted
Date
Amount certified
Date
Rs.
Amount Received
Date
Bal. to be received
Total
work done up to
28/Feb/10
31/Mar/10
30/Apr/10
31/May/10
Submitted date
22/Mar/10
29/Apr/10
26/May/10
22/Jun/10
PC due date
Total
Amount
48,476,509.02
22,198,754.72
7,776,170.16
15,518,197.93
93,969,631.83
BILLS TO BE SUBMITTED
IPC No:
work done up to
date to be submitted
PC due date
Amount
Total
Total
Submitted date
Date to be submitted
Amount (Rs.)
MPRR Continued .
Project :
Progress data up to
Page - 03
Proposed Administration Building, Hambantota Port Development
23/Jun/10
Project Architect
Site Managers
Planning Engineers
Quality Assurance Engineers
Materials / Elec. / Mech.Engineers
Total
AVAILABLE
requirement
as per
BOQ/Budge Maga Sub
Total
Con.
t
1
1
1
1
1
1
1
2
Site Engineers
Assistant Engineers
Engineering Assistants
Surveyors
Technical officers
Lab technicians
Electricians
Plumbers
Forman
Supervisors
Quantity Surveyors
Draughtsman
Safety & Environment officers
Accounts & Admin staff
Store staff
Drivers
Operators
Mechanics
Security
Watchers
Cook
Masons
Carpenters
Bar benders
Riggers
Helpers
Laborers
1
30
25
25
8
40
25
1
4
3
1
1
19
22
Total
212
83
1
3
1
6
5
4
3
2
1
1
3
2
8
4
1
6
4
4
3
2
1
0
2
2
7
2
1
4
17
19
37
77
1
1
2
4
4
3
2
1
2
2
7
2
1
4
1
4
20
20
1
56
22
160
Can be
Released
REQUIRED
Maga
Sub
Con.
Total
1
-
Total
MPRR Continued .
Project :
Progress data up to
Page - 04
Proposed Administration Building, Hambantota Port Development Pr
23/Jun/10
Category
Total
Can be
REQUIRED
requirement AVAILABLE
Released
as per
BOQ /
Maga Hired Total Capacity Maga Hired Total
Total
Budget
Batching Plant
Tower Crane
Tractor
Light Vehicle
Wheel Loader
Water Bowser
Vibrator/poker
Welding Plant
Air Compressor
Generator at Site
Hoist
Truck Mixer
Roller 1 Ton
Excavator
Plate Compactor
Baby Dumper
Rammer
Total
36
29
29
MPRR Continued .
Project :
Page - 05
Data up to
23/Jun/10
11
Total BOQ
Qty after
Unit variations if
any
Qty
Nos.
Piling Works
Pile Cap Excavation
Pile Cap Concreting
Pile Cap Reinforcement
Pile Cap Form work
Planned
Physical progress
Progress
This month
To date
Qty - %
Qty - %
Qty - %
Balance
Required
Qty - %
2.00
100.00
100.00
###
Nos.
81.00
100.00
100.00
###
m3
585.68
100.00
100.00
m3
385.00
100.00
80.00
10.00
###
30.80
100.00
85.00
10.00
5.00
166.00
100.00
80.00
10.00
###
T
m2
10. Brief description of major activities of work to be done during next month
Item description
Excavation for Retaining wall,sump
Unit
m2
QTY
550.00
Value Rs.
649,550.00
Dewatering
Item
900,000.00
Antitermite treatment
m2
1,108.00
Ton
24.86
3,314,061.74
503.00
597,081.12
241.00
4,474,875.95
Retaining wall
186,975.00
6,200,000.00
3,229,634.77
Waterproofing work
1,818,948.95
21,371,127.53
MPRR Continued .
Page - 06
23/Jun/10
Ite
m
No.
Description
Cumulative
Total Cumulative Quantity
Required Quantity Received/
Total Total
Balance
Unit as per
Variation
Purchased transferred
QTY QTY
in stock
BOQ /
from
from
Received Billed
Budget Suppliers
Plants /
Sites
cement bulk
Ton
855.59
855.59
22.82
Sand
Cu
844.00
844.00
427.76
Metal
Cu
727.97
727.97
185.85
32 mm
Nos
643.00
643.00
283.00
25 mm
Nos
946.00
946.00
485.00
20 mm
Nos
1509.00
1509.00
1285.00
16 mm
Nos
1610.00
1610.00
1112.00
12 mm
Nos
383.00
383.00
56.00
10 mm
Nos
2424.00
2424.00
1050.00
310.00
310.00
150.00
Steel
Timber (2''x4'')
Ft
8969.00
8969.00
395.00
Timber (2''x2'')
Ft
24070.00
24070.00
15000.00
Reasons
MPRR Continued .
Page - 07
Month
Nov-09
12,638,517.08
12,638,517.08
0.00
0.00
12,638,517.08
Dec-09
Jan-10
Feb-10
Mar-10
Apr-10
May-10
Jun-10
Jul-10
Aug-10
Sep-10
Oct-10
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
4,870,800.00
11,970,433.13
21,546,779.63
20,063,207.25
13,235,478.32
23,551,005.90
24,518,264.71
44,006,946.87
42,686,560.48
50,239,104.60
58,216,419.74
63,118,394.89
29,413,409.59
41,588,224.09
49,024,591.73
140,930,532.19
119,013,523.75
13,732,090.21
17,509,317.08
29,479,750.21
51,026,529.84
71,089,737.09
84,325,215.41
107,876,221.31
132,394,486.02
176,401,432.89
219,087,993.37
269,327,097.97
327,543,517.71
390,661,912.60
420,075,322.19
461,663,546.28
510,688,138.01
651,618,670.20
770,632,193.95
784,364,284.16
0.00
0.00
50,245,717.74
23,381,974.11
6,651,783.40
14,368,170.87
0.00
0.00
50,245,717.74
73,627,691.85
80,279,475.25
94,647,646.12
17,509,317.08
29,479,750.21
780,812.10
(2,537,954.76)
4,045,740.16
13,228,575.19
M ay-11
M ar-11
Jan-11
Nov-10
Sep-10
Jul-10
May-10
Mar-10
Jan-10
0.00
Nov-09
Rs.
Cumulative
Variance ( Rs)
Actual
Month
MPRR Continued .
Page - 08
31/May/10
Month
Cumulative Rs.
Budgeted Cash in
78,400,000.00
88,370,385.69
92,212,905.69
101,656,247.38
118,654,262.42
134,481,903.69
144,923,225.48
163,502,352.36
182,844,538.97
217,561,130.39
251,236,083.66
290,869,155.07
336,795,441.76
386,588,842.17
409,792,754.18
442,601,242.07
481,276,197.77
592,454,728.72
693,568,974.55
745,146,069.68
784,364,283.62
Nov-09
Dec-09
Jan-10
Feb-10
Mar-10
Apr-10
May-10
Jun-10
Jul-10
Aug-10
Sep-10
Oct-10
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11
Jul-11
Cumulative Rs.
Cumulative Rs.
Cumulative Rs.
Variance ( Rs)
Actual Cash in
78,400,000.00
78,400,000.00
78,400,000.00
78,400,000.00
78,400,000.00
22,969,320.82
37,547,967.07
47,876,821.26
57,093,642.49
70,774,575.57
800,000,000.00
600,000,000.00
Rs.
400,000,000.00
200,000,000.00
0.00
Budgeted Cash in
Jul-11
Jun-11
Apr-11
May-11
Mar-11
Jan-11
Feb-11
Dec-10
Nov-10
Sep-10
Oct-10
Jul-10
Aug-10
Jun-10
Apr-10
May-10
Mar-10
Jan-10
Feb-10
Dec-09
Nov-09
-200,000,000.00
Month
Actual
Cash in
MPRR Continued .
Project:
Page - 09
31/May/10
Progress data up to
QUANTITY
Work item
Unit
BOQ
Work done
Total QTY
QTY
Initial BOQ
Rate
BOQ
Budgeted
Current
Variance
Rate
Rate
Rate
Rs.
Site office
2,164,589.87
Labour accommodation No 01
761,109.20
Labour accommodation No 02
607,230.55
Stores
342,789.33
Canteen
335,884.80
Curing tank
21,639.63
Temporary fence
994,906.54
Driver Accommodation
176,753.65
Security huts
31,203.25
Labor toilets
97,749.03
Main gate
147,914.44
Pilling work
47,023,216.54
Excavation Up to Basement
m3
2,677.17
892.00
1,403.04
786.71
778.00
m3
867.03
63.26
18,567.95
12,309.00
12,295.70
Reinfocement work
691.64
6.05
133,309.91
105,170.00
104,140.00
Form work
m2
29,666.45
91.09
1,187.04
760.00
650.00
m2
2,330.00
571.00
9,180.00
5,075.00
4,200.48
Up to last month
This month
Month
Apr-10
May-10
May-10
( A ) Preliminaries
80,279,475.25
94,647,646.12
80,279,475.25
% to value of
work done
Budgeted %
0.00%
12,384,698.18
3,638,082.32
16,022,780.50
19.96%
Staff
1,757,838.22
578,005.42
2,335,843.64
2.91%
Workers
2,036,528.62
648,314.38
2,684,843.00
3.34%
( B ) Manpower Cost
Labour subcontract
Total
( C ) Material Cost
80,410.63
531,448.28
611,858.91
0.76%
3,874,777.47
1,757,768.08
5,632,545.55
7.02%
34,036,019.83
6,714,749.83
40,750,769.66
50.8%
1,944,647.50
788,991.50
2,733,639.00
3.4%
0.00%
Company
Hired
Total
1,944,647.50
788,991.50
( E ) Site Overhead
( F ) H/O Overhead 6%
TOTAL COST ( Rs. )
2,733,639.00
-
0.0%
3%
0.00%
0.0%
4,853,499.51
874,983.84
5,728,483.35
7.1%
57,093,642.49
13,774,575.57
70,868,218.06
88.28%
0.00%
6050
7000
5500
5500
7000
4650
5600
4500
6900
52700
300mm
2.4
600mm
3.458
3.486
1.752
8.696
2.01
17.48
900mm
2.464
2.01
4.95
13150
27000
42500
20000
77.76
17.48
4.95
8
5000
51.38
1,022,544.00
471,960.00
210,375.00
160,000.00
256,900.00
2,121,779.00