Documentos de Académico
Documentos de Profesional
Documentos de Cultura
PROJECT DESIGN
Project Design
Introduction
Proposed Project Layout
The Buguias I Mini-hydro potential has a gross head of 152 meters. A low
diversion weir will be constructed to divert the river flow into a 11 OOmm
diameter low pressure headrace approximately seven hundred fifty meters
long. A johnson type surge tank with 4 meters diameter and 10 meter high
will be used at the end of the low pressure headrace, before the beginning of
the penstock pipe.
A penstock pipe approximately 513 meters long will be laid on the mountain
slope to convey pressurized water to the turbines. The penstock, with
thickness ranging from 6 mm at the top to 16 mm thick at the bottom part,
has a general diameter of 813mm. A portion of the penstock pipe will be
buried where it traverses vegetable gardens and terraces. An asphaltic
coating will be applied on the outer surface of the steel pipe to prevent
COITOSIOn.
The power house, of concrete construction will house two (2) cross-flow
type turbine units. Its inside dimensions are 8m wide by 16meters long. It
is also equipped with a three-ton capacity overhead crane.
The two turbines will be installed driving synchronous alternators of750 kW
capacity each. At the rated head of 145 meters, for the three turbine setting,
each turbine has a rated flow of 700 liters per second (Ips) or a total
required flow of 1,400 Ips.
The step-up transformers, 0.44/23kV, with a total rated capacity of 3 x
666kVa will be installed in the open air. The proposed transmission line
tapping points for the interconnection of the proposed generating plant is
the BENECO transmission line along the Halsema National Highway.
Page 3-1
Project Design
Page 3-2
Project Design
Horizontal Loads
Headwater (Ht):
Hflood =
Tailwater (Hs)
Vertical Loads
Weight ofDam (V 1)- The unit weight of material in the dam is determined as
accurately as possible.
Unit wt of Concrete= 2,400 kg/cu.m
Unit wt of Rubble Masonry = 2,300 kg/cu.m
[Buguias I Mini Hydropower Project]
Page 3-3
Project Design
Vertical Water Loading (V2)- Imposed on any sloping surface of the dam,
usually the upstream face, but also on the downstream for overflow dams.
Uplift (V3)- Hydrostatic forces acting within a dam
and its foundations including interstitial or pore
pressures. Drainages will be used to prevent
occurence of uplift, assuming the drainage will be
effective for the entire life on the dam, therefore
some inclusion for uplift must be included in the
design. See diagram for distribution of pressure. [k
values vary between 0.25 to 0.50 depending on
conditions.]
Seismic Force (V4)- Force acting on dam in vertical
plane.
Fss=
(L:H/L:V) -tan a!
1+ (L:H/L:V)tana!
cA
s = ----
Fsf=L:H
+L:Vtan(cf>+a!)
COSO!(l-tancf>tanO!)
Page 3-4
Project Design
Page 3-5
Project Design
Design of Spillway
Crest Profile
the crest of an overfall "'
spillway is usually dimensioned to conform
to the underside of the nappe of the freefalling jet. Greater efficiency is obtained by
operating a spillway at greater than design
head, as can be seen in the figure showing
the effect of nappe profile on coefficient.
f.-----------,
0 .2
o .~
r:r~lic-
o.a o.a
1.0 1.-2 t4
l{e:sd on trl!'t1
r'IOI)~e
It is common practice to choose the design head for the nappe as 75o/o-80%
of the maximum expected head. When the spillway so designed does pass
the greater flows, pressures lower than atmosphere will occur over the crest,
causing problems associated with cavitation.
The flow over a spillway gives rise to self-excited vibration, in which three
coupled elements are involved; the jet, the overflow crest and the air cushion
between dam and jet. This can be avoided by using splitters on the crest.
The passage of flood waters from upper level to lower level will involve the
dissipation of vast energy. The velocities and pressures involved are huge
and destructive.
Flip Bucket Spillways - the purpose of this type is to throw the water well
clear of the structure. The jet of a ski jump spillway leaves horizontally
whereas the jet of a flip bucket is deflected upwards to induce disintegration
in the air. The spray produced can cause damage to the countryside and may
adversely affect nearby electrical installations.
Page 3-6
Project Design
SWZ>=<
B. Deflector Bucket
.............
~:;:;;;
~
~
Sluice Gates
The Buguais I MHP diversion or weir will be installed with sluice gate to
rid the upstream of the dam from accumulated silt and bed load periodically.
The gates will be manually operated.
30 meters
2 meters
Ogee Type Profile
20 meters
Mechanically Raised
1.5m x 1.5m
Page 3-7
Project Design
Page 3-8
Project Design
The conveyance system shall be designed with a capacity of 1.5 cu.m per
second flow. A design slope of 111000 shall be adopted to minimize
headloss.
The full length of the low pressure conveyance system will involve a steel
p1pe conveyance.
Headrace Total
Length
Diameter
Slope
750m
1.2m
1:1000m
Thickness:
6mm thkMS
Due to the utilization of a surge tank the hydraulic conveyance shall fall
under the Full Flowing pipe.
Outcropped Steel Conveyance
Where the steel conduit pipes are exposed and unprotected from excessive or
corrosive condition, pipe sleepers or block carrying the pipe off the ground
shall be employed to prolong life of steel pipe materials. Where the steel
pipes will be subject to harsh conditions or will be subject to be buried, a
bituminous coating will be applied on the external surface of the steel pipe.
Page 3-9
Project Design
(~ .16 )
/(
I,
/f
---v
.l
//
-'I
il
/I
t( .
I_____
1~.~--------------~!
l!.l .s
0
'== 2.4 .8
f- = heacloss :m11)
J~
tl
,,
~
1.7 1.0 0.8
= ba 1ickn~ss lmm)
b :: V'tidt betwee ba"S (
V =aJoroac JelcCJty 11.s)
g = gravi aliCtlal ctt~s'a I
cp =a<g ~ of inc rratior 'O'TT oizoltal
Page 3-10
Project Design
(~-, . 11"
')
For a ratio up to dD = 0.76. Kc approximately follmvs. the furmtlla:-
(2.18)
the ye~ many empirical formulae. ba!>M on accumulated expenence-. have been de.-e'loped.
They are. generally. nor based on sound phy!>ics principles and eeu. occasionally. lack dime-mional
coherence. but are innutiYely ba->ed on rhe lx-lief that the friction on a dosed full pipe is:
l. Independent of the water pres!>llr<:'
1
Page 3-11
Project Design
Q=..:...
!I
-~
( l.-1 :
.)
(2 . 13)
p: ~
(2.1-1-)
(2 .1-1-a)
~L-uwing
w elded '>ted
Polyethylene (PE)
PYC
Asbestos cement
Ductile iron
Ca'it iron
V/ood-staw (new)
Concrete (steel forms smooth fuush)
0.012
0.009
0.009
0.011
0.0 15
0. 01-t
0.012
0.01-t
Page 3-12
Project Design
Surge tanks
Surge tanks are required to protect long penstocks from excessive water
hammer pressure rise, to control excessive generator runaway speeds and
to contribute to system speed regulation. Alternatives to surge tanks
providing some of the benefits of surge tanks, include:
-addition of extra machine inertia (typically by adding a flywheel to a
horizontal axis unit or extra mass to a vertical axis generator).
- installing turbine bypass valves.
- pressure relief devices.
A preliminary design methodology for surge tanks is outlined below. It is
conservative.
Highest up-surge:
In order to dimension the surge tanks it is also necessary to know the
maximum and minimum water levels that can be expected. An approximate
method is shown below that is based on Parmakian' s method for balanced
design (Parrnakian - 1960). This method provides equations relating the
following parameters from which the maximum and minimum surge levels
can be calculated:
Page 3-13
Project Design
* (Asg/(L/A))"0.5
Sb = l.OSb"-0.89
* Hf
0. 88bo"-O. 91
* Sf
Page 3-14
Project Design
Penstocks
Penstock Intake
The concrete volume of a typical penstock intake is approximately 15 .QP rm
and net cost can be estimated as:
CI = 15.Qp.fi
Where:
Penstock
Check head /length (H/L) ratio of the proposed penstock layout, if HIL > 5 a
surge tank or turbine bypass valve may be required. Exceptions to these
requirements are:
-Mini hydro plants with load controller.
- High head plants with Pelton turbines
Page 3-15
Project Design
* Q/3.0
(Sarkaria's Equation)
Page 3-16
Project Design
Powerhouse
Design Considerations
The power house shall be of the conventional type concrete and steel
construction to house and protect the generating units and other control and
auxiliaries are located on the ground floor with the turbines. The draft tubes
are cast integrally with the substructure when it is poured in, with steel liners
serving as forms.
A working bay is provided at one end of the power house where equipment
maybe unloaded and repaired.
An overhead crane, with a capacity large enough to lift the heaviest piece of
equipment over other machinery, is installed to lift and move the heavy
equipment to and from the repair bay for replacement into their positions.
Tailrace
The tailrace is designed taking into consideration the maximum gross head
that can be utilized. Due to the proximity of the power house to the
discharging stream, a wide tailrace is selected to minimize tailwater
elevation rise resulting in decrease of gross head for the plant, particularly
during flood flow conditions.
To unwater draft tubes for repairs, stoplogs or sectional gates will be
installed between the tailrace piers to shut off water from the draft tube
during unwatering. A hoisting mechanism shall be provided for the gates or
stop logs.
Page 3-17
Project Design
Electro-Mechanical Equipment
Selection
...~
'~D
~....
'h.
't>
.,
~~
:::::.
S'aPo
~_,o
~?<-
"
i
5 -
J
-1
.I
CROSSFL<>jW
TURBINE
sa
I'
;oo
I
500
I
!COO
0Jscitorg<>
I '
sooo
I/ s
raooo
Page 3-18
Project Design
Page 3-19