Basic function of Boiler feed water pump is to produce sufficient amount of pres

sure required to turbine inlet with added amount of pressure drop of flow path o
f boiler components.
Pressure required to develop through bfp = Turbine inlet pressure + Pressure dr
op of boiler components
and also its a prime important in case of develop more than saturation pressur
e in case of supercritical boiler segments concern

Boiler feed pump is used to feed water to steam generator boiler drum at desired
pressure and temperature.
Need of boiler feed pump?
As the water is fed to the steam generator it has to be at the temperature & Pre
ss
ure that of the steam generator.
Boiler feed pump
Process of water flow?
Boiler feed pump extract water from de-aerator and feed it to the boiler drum vi
a H.P heaters and economizer.
General configuration of Boiler feed pump?
Generally 2 Turbine driven boiler feed pumps (1 Working & 1 Standby) & 1 Motor d
riven boiler feed pump is used for 1 unit.
Turbine driven boiler feed pump: It works with the steam extraction from Interme
diate Pressure (I.P.) turbine exhaust.
Motor driven boiler feed pump: It works with a motor as the name specifies.

Swas room

Steam Water Analyzer System Room, it is used to analyze boiler steam and water.
The following parameter are there
i) Spec Conductivity (insertion type)on both side
5.08.03 Cond. Pump(CEP) Discharge
i) Cat Conductivity
ii) pH
iii) Dissolved Oxygen
iv) Specific Conductivity
v) Silica
vi) Sodium
5.08.04 Condenser Cooling Water
i) pH
ii) Specific Conductivity
5.08.05 Deaerator Inlet
i) PH
ii) Dissolved Oxygen
iii) Specific Conductivity
5.05.06 Deaerator Outlet
i) Dissolved Oxygen
5.08.07 Feed Water at ECO I/L
i) Hydrazine
ii) Specific Conductivity
iii) Phosphate
iv) pH
v)Dissolved Oxygen
vi)cat conductivity
5.08.08 Drum Water
i) Specific Conductivity
ii) pH
iii) Sodium
iv) Silica
v) Phosphate
vi) chloride
5.08.09 Saturated Steam (SH out)
i) Specific Conductivity
ii) Cat Conductivity
iii) pH
5.08.10 Main Steam (after attemperation)
i) Specific Conductivity
ii) PH
iii) Silica
iv) Cat conductivity
v) Sodium

vi) chloride
5.08.11 HRH Steam
i) Specific Conductivity
ii) pH
5.08.12 CBD
i)Phosphate
5.08.13 ECW pump discharge
i)PH
5.08.14 Cond discharge after CPU
i) sp conductivity
ii)cat conductivity
iii)pH
IV) Sodium
v) Silica
5.08.15 DMCW water
i)pH
Li

Variable Frequency Drive


Why VFD is required?
Variable frequency drives allow reducing power consumption up to 30% or more and
obtaining a payback time on the investments often lower than 1
2 years. Moreove
r, the quality of the equipments and the lower mechanical stress on the installe
d machinery guarantee it a longer life time and a substantial cut on its mainten
ance costs. The present document aims to examine the energy benefits of a viable
technology change on the existing motorized systems at Lanco. Changes may inclu
de replacements of motors with low efficiency and / or system upgrade through th
e retrofit of variable speed drives to the existing motors. The energy consumpti
on analysis also leads to an economical estimation of the savings and a balance
to the possible investment.
What is VFD?
A variable frequency drive (VFD) is an electrical variable speed drive that is a
dded to motor-driven systems to help save energy. Motor-driven systems are desig
ned to handle peak loads. When these operating systems work for extended periods
of time at a reduced load, it wastes energy. Adding a VFD allows you to adjust
the motor-speed capability and match it with motor-output load. This is how it s
aves energy. The motor-driven system is connected to the VFD and allows us to ha
ve speed control by changing the frequency of the motor-supply voltage.
How VFD functions?
A motor-driven system is controlled by the frequency of the supply voltage and r
otates on a fixed speed. An alternating current that is applied produces a magne
tic field that rotates at synchronous speed. The only way to alternate synchrono
us speed is through a VFD, which converts the power in three stages. In the rect

ifier stage, the power is converted to a higher adjustable DC voltage. In the in


verter stage, the power transistors in the rectified DC are switched off and on.
This produces a voltage waveform at the frequency you want. In the control syst
em, the voltage wave form receives information from the motor-driven system and
will adjust the output voltage to the selected value.

CURRICULUM VITAE :
ASHISH SHARMA
E-mail :- ashishsharma1100 AT gmail.com , ashishsharma.ritee AT yahoo.com
CAREER OBJECTIVE : -Intend to a build a career a with leading corporate of hi-te
ch and environment with committed & dedicated people which will help me to explo
re myself fully & realizemy potential, willing to work as a key player challengi
ng & creative environment.
CAREER PATH : WORKING EXPERIENCE:
- Total 2 Years 1 Month experience in power plant operation and maintenance. Pre
sently associated with Operation Team of 30 MW Thermal Power Plant in NECO GROUP
OF COMPANY at Raipur dist. Since May 15 as an Engineer.
- Designation : Engineer (O & M)
- Post : EngineerCompany Profile : NECO GROUP OF COMPANY (POWER PLANT) Jayaswal Neco Industries L
imited which started in 1976 as a small scale iron foundry unit at Nagpur is the
flagship company of Neco Group of Industries which has now become an integrated
steel plant of 1 Million Tonne capacity through Blast Furnace route, Sinter Pla
nt, Oxygen Plant, Coke Oven, Power Generation with one of the finest infrastruct
ural facilities at its Siltara, Raipur Plant. It produces alloy steel bars and r
ods from 5 mm in coils to 60 mm bars. Another Unit at Siltara produces narrow wi
dth HR Coils.Now it also has its own Coal and Iron Ore mines in the State of Chh
attisgarh and Jharkhand and has undertaken setting up of Thermal Power Stations
of 3240 MW in the State of Chhattisgarh and 500 MW in Jharkhand in the next few
years.
JOB PROFILE& RESPONSIBILITY : -- Presently working As an Engineer in Operation o
f Power Plant.- O&M of 40 TPH AFBC fired BOILER, 3*30TPH Oil fired Boiler and it
s auxiliaries, 65 MW condensing Turbine and its auxiliaries.- Performance monito
ring and maintain the require parameter forsmooth and efficient operation.- Plan
ning of effective maintenance schedule of boiler, turbine and their auxiliaries
like condenser, ejector, cooling tower, air compressor etc.- Synchronizing the T
G Set with Grid Power.- Coordinating the different department and working people
.- Emergency handling of Boiler as well as turbine.
- Involved in Smooth Desk Operation and Mechanical Maintenance of Thermal Power
Plant & its auxiliaries. Monitoring the performance and maintaining the required
parameter for running the operation smoothly and efficiently.
Having Sound knowledge of Steam Turbine, Various Type of BOILER (AFBC, BLAST FUR

NACE GAS
OIL Fired & WHRB) , ASH HANDLING PLANT, Fuel Handling like (Furnace Oil,
HSD Oil) COAL HANDLING PLANT, DM PLANT, SCREW COMPRESSOR etc.
Involved in checking field Boiler and TG water report analysis and instruct the
DM plant operator to fulfill the desired requirement of water.
Plant Start up : Boiler Light up & Turbine Rolling in Various Conditions. Superv
ision of all the equipments for their functioning and attending to all the probl
ems encountered. Planned Shutdown of unit for Maintenance activities etc.
To Look after Maintenance of High Pressure Boilers & Turbine and their auxiliari
es. Plan and Execute Breakdown and preventive maintenance on all rotating and st
atic equipments.
Guide & lead a team of skilled and unskilled technicians to perform Proper Lubri
cations and equipments checks in shift as per schedule and instructions. Experti
se on Troubleshooting of Rotating equipment and fault diagnosis.
Shift routine daily entries in the control room log sheet, Prepare daily, weekly
and monthly reports as required, Provides on the job training for Lead Field Op
erators.For six months in Mech. Maintenance department with planned preventive M
aintenance schedules.- Handling all the activities during unit shut down.- Manpo
wer handling & proper utilization.
PROFESSIONAL QUALIFICATION :
B.E. (Hons) in Mechanical Engineering from Raipur Institute of technology, Raiga
rh(C.G.) Aggregate 73.86% year 2011.
EDUCATIONAL QUALIFICATION :
-Passed High School Certificate Examination in the year 2005 with 80% from Chhat
tisgarh Board, Raipur
- Passed Higher Secondary School certificate Examination in the year 2007 with 8
3.64% from C.G. Board, Raipur.
Sponsored Links:

STRENGTH :
- Basic knowledge and operating incomputer.
- Negotiation, strategic thinking.
- Hard work & sincerity is my key element.
- Team sprit & fun loving.
- Comfortable in any environment.
- Effective communication and interpersonal skills with strong analytical, probl
em solving & organizational abilities.
- Self confidence, target orientation, time management and quality consciousness
.
PERSONAL INFORMATION : Date of Birth : 11 October 1989
Nationality : Indian
Language Known : Hindi & English
Hobby : Listen Music & Play Cricket
Marital status : Unmarried
DECLARATION : - I hereby declare that all the information furnished in this curr
iculum vitae is true & correct to the knowledge & belief.
Place : - Raipur (C.G.)
(Ashish Sharma)

También podría gustarte