Development of
Punjab Habitat
Centre
at Mohali
Pre-bid Meeting
Aug 20, 2008
Punjab Infrastructure Development
Board
Habitat Centre
It should provide finest convention facilities and
should be able to host premier cultural and
entertainment events
It should cover a wide range of activities that
would maximize the effectiveness of individuals
and institutions
It should have a variety of restaurants with
elaborate menu options
The principal resolve should be restore
environment and ecology to reflect a balanced,
harmonious and improved way of life
Conceptual Idea
Built Configuration
The drawing shown is for illustrative purpose only. Actual design may be different
Site Details1
Location Sector 68
Area 4.787 acres of prime land
Adjoining Municipal Council Building
Surrounded by roads on two sides
Proposal to develop adjoining road into urban
expressway within Mohali by GMADA in order to
provide fast airport connectivity
Proposed IT Park located in the plot opposite
Municipal Building
Site Details2
Mohali City Centre
About 2 Kms
Mohali Stadium
About 2 Kms
About 7 kms
About 10 kms
Proposed IT Park
Opposite
Location
Proposed Site
Location
Sector 68
Proposed Site for
Habitat Centre
Area 4.787
acres
Municipal Bhavan
Project Brief1
Project Structure : Design, Build, Operate, Transfer
GMADA Area(About 10% of BUA):
Certain Facilities would be built and handed over to
GMADA free of cost immediately after construction
Interiors of GMADA area would be done by GMADA at its
own cost
Operation & Maintenance of GMADA area would be under
GMADA
Design and Architecture of GMADA Area shall be consistent
with the overall design and concept
Project Brief2
Project Brief3
Project Brief4
Project Brief3
Project Implementation
15
Development Brief1
The spatial, infrastructural and aesthetical demands of
all facilities should be blended well with the
aesthetics, design, energy conservation concepts, ecofriendliness and green building architecture.
Detailed design should conform to the prevalent
building bye-laws and development regulations
The design should also conform to LEED INDIA
Green Building Rating System, Abridged Reference
Guide- For New Construction & Major Renovations
(LEED NC) Version 1.0 such that the Project gets
LEED Certified rating under the Rating system.
Development Brief2
Scope of Work
Conceptualization, Planning, Designing, Detailing,
Construction and Implementation of the Project
Facilities and Support Facilities
Carry out Minimum Development Obligations
Technical and Financial Closure
Marketing of the Project.
Development Brief2
Scope of Work
Routine and Periodic Maintenance of Project
Components in Developer Area; and Common
Areas
Operation & Management of Project Facilities in
Developer Area
Transfer of Project Facilities to GMADA at the
end of Authorization Period as prescribed in RFP
Pictures shown are for illustrative purpose only. Actual design may be different
Pictures shown are for illustrative purpose only. Actual design may be different
Administration Block
(4500 sqft minimum)
Pictures shown are for illustrative purpose only. Actual design may be different
Pictures shown are for illustrative purpose only. Actual design may be different
Ethnic/High-end Shopping
(indicative area -31050 sqft )
Pictures shown are for illustrative purpose only. Actual design may be different
Pictures shown are for illustrative purpose only. Actual design may be different
Pictures shown are for illustrative purpose only. Actual design may be different
(7000 sqft)
Pictures shown are for illustrative purpose only. Actual design may be different
Pictures shown are for illustrative purpose only. Actual design may be different
Bidding Process
PIDB & IL&FS IDC
Proposal Requirement1
Each Bidder shall submit only one proposal
Special Purpose Company to be mandatorily incorporated by the
preferred bidder/bidding consortium
Maximum number of members/partners in consortium,
partnership or joint venture allowed is limited to 5, including the
Lead Member
Lead Member of Consortium shall hold at least 51% equity in the
SPC. Other members shall hold at least 10% equity in the SPC at
all times during a period which shall not be less than eight (8)
years from the date of signing of the Concession Agreement.
Proposal Requirement2
Period of Proposal Validity:
Proposal
No of Copies of Proposal:
Original + 2 Copies
Concession Period:
Outer Envelope
Pictures shown are for illustrative purpose only. Actual design may be different
Pictures shown are for illustrative purpose only. Actual design may be different
Pictures shown are for illustrative purpose only. Actual design may be different
Pictures shown are for illustrative purpose only. Actual design may be different
A nominee of CA
A nominee of Concessionaire
Independent Engiineer
Such other members as the Concessioning Authority
may determine
Pictures shown are for illustrative purpose only. Actual design may be different
Queries
1.What happens if there is a holiday or other event like BAND etc. in other states?
2.Why there is so heavy amount as Bid Security, Project Development Fee & Construction Performance
security for the land measuring 4.7 acres as compared to MOHALI & PATIALA Bus Terminals? These
as well as Operations & Maintenance performance security should be revised.
3.Is there any Minimum Upfront Concession fee?
4.What is the tentative schedule for opening of BIDS?
5.How & who will be maintaining GAMADA/PIDB area handed over to them after construction?
6.What will be the number of Banquet halls in Concessionaire control are of 47250 sq. ft.?
7.Is there any minimum number of offices in head OFFICE COMPLEX?
8.No Restaurants is provisioned for the bidder/concessionaire, Why? You should allow at least one
Restaurant to be run by concessionaire for the concession period.
9. Is there any minimum area defined for parking & support facilities?
10.Are there any specifications for ON Site Infrastructure as well?
11.GAMADA/PIDB should book rooms at least 3-4 days in advance otherwise there could be
any problem regarding availability of rooms as one day notice is very short duration?
12.Validity of BID Security Should be 180 days?
13.Can you please elaborate ESCALATION in Annual Concession Fees?
14.You have mentioned 2 types of Annual Fees to GAMADA vi a vis Annual Concession Fees &
Annual lease Rental. One should be waived off / eliminated from list.
15.You have mentioned 21 days in Numerals while 15 Days in words on page 36 of Volume I:
Section I Instructions to Bidders to deposit the Project Development Fees to PIDB. Can you
correct & clarify the correct time period?
16. Concession period defined on page 36 of Volume I: Section I Instructions to Bidders is 33
years whereas it has been defined 35 years elsewhere. Could you please check & correct?
17.Could you please reserve some memberships offered for Punjab habitat Centre for Bidder /
Concessionaire?
18.Could you explain Point (d) of article 4.5.1 on page 20 of Volume I: Section I Instructions
to Bidders?
19.Is there any provision for the Concessionaire to get Share in Revenue Receivable to
GAMADA/PIDB from the Facilities to be handed over to them soon after the construction?
20.When Concessionaire is supposed to build Boarding & Lodging Facilities that means a hotel
of 3 star rating or above then we need to run Restaurants, Banquets & Health club etc.
Therefore it is requested to give Restaurants, Swimming pool & Health Club Facilities under
the control of Concessionaire. In turn revenue sharing or Privileged Membership could be
mutually decided between Concessionaire & GAMADA/PIDB
21.As per the Draft Concession agreement page No 18 the Environment Clearance is the
liability of the Concessionaire. Our view is that the liability of the same should be of the client
Thank You