Documentos de Académico
Documentos de Profesional
Documentos de Cultura
ENVIRONMENTAL CONSTRUCTION
STANDARDS
July 2011
These 2011 Environmental Construction Standards (ECS) for the Minisink Compressor
Project (Project) amend previous versions of the ECS by incorporating the Project-specific
environmental requirements. To that end, the ECS collate the procedures that are to be
followed to maintain compliance with Project environmental regulatory requirements during
typical compressor station construction activities, and are designed for use in the field during
construction activities, along with the Construction site drawings, and any site-specific
construction and environmental mitigation plans.
Millenniums construction inspectors and contractors are required to understand and follow
the requirements of these permits, certificates, and plans, as applicable to environmental
compliance.
ii
TABLE OF CONTENTS
Page
I.
INTRODUCTION ..................................................................................................................... 1
iii
V.A
GENERAL .................................................................................................................. 16
V.A.1 Pre-Construction Surveys and Wetland Flagging ........................................... 16
V.B
CONSTRUCTION TECHNIQUES............................................................................ 16
V.C
CLEARING ................................................................................................................ 16
V.D
GRADING .................................................................................................................. 17
V.E
BLASTING................................................................................................................. 17
V.F
RESTORATION ......................................................................................................... 17
VI. MAINTENANCE ................................................................................................................... 18
VI.A GENERAL .................................................................................................................. 18
VI.B UPLAND AREAS ...................................................................................................... 18
VI.C WATERBODIES, WETLANDS, AND ENVIRONMENTALLY SENSITIVE
AREAS ....................................................................................................................... 19
LIST OF TABLES
Table 2a
Table 2b
Table 2c
ATTACHMENTS
Attachment A SPILL PREVENTION, CONTAINMENT AND CONTROL PLAN
Attachment B TYPICAL FIGURES
Figure 1 Figure 2 Figure 3 Figure 4 Figure 5 Figure 6 Figure 7 Figure 8 Figure 9 Figure 10 Figure 11 Figure 12 Figure 13 Figure 14 Figure 15 Figure 16 Figure 17 Figure 18 Figure 19 Figure 20 Figure 21 Figure 22 Figure 23 Figure 24 -
iv
I.
INTRODUCTION
In constructing and operating its Minisink Compressor Project (Project), the Millennium Pipeline
Company, L.L.C. (Millennium) is committed to complying with applicable environmental rules and
regulations, including the Project-specific requirements contained in the approvals issued by the
Federal Energy Regulatory Commission (Commission) and the New York State Department of
Environmental Conservation (NYSDEC); these are collectively referred to as the Environmental
Requirements.
It is Millenniums policy that the Project construction, operation, and maintenance activities be
conducted in a safe manner that minimizes adverse effects on the environment. To this end,
Millennium has prepared these Project-specific 2011 Environmental Construction Standards (ECS).
In doing so, Millennium has incorporated the Commissions Upland Erosion Control, Revegetation,
and Maintenance Plan (Plan) and Wetland and Waterbody Construction and Mitigation
Procedures (Procedures) (January 17, 2003). (Attachment C)
The ECS compiles the Environmental Requirements specific to each Project construction task in an
organized format. This format is designed to facilitate the use of the ECS, along with Millenniums
Construction design drawings, in the field during construction. It is anticipated that the ECS will be
used by Millenniums Environmental Inspector (EI), other inspectors, and the construction
contractors.
The ECS represents the procedures that are to be followed to maintain compliance with Project
regulatory requirements during typical construction activities. However, in addition to the ECS,
Millennium has developed separate construction plans or environmental mitigation measures for the
protection of known or potential environmental and cultural resources (inadvertent discovery of
archaeological resources).
During construction, site-specific modifications to the ECS procedures may be required in
response to field conditions. However, any such modifications must be to achieve the same level
of environmental protection as detailed in the ECS and must be documented by the Millennium
EI in his/her daily environmental report.
Sections IV and V discuss the standards for crossings of streams and wetlands, respectively.
Ensuring compliance with the requirements of the ECS, the environmental conditions of
Federal and state environmental permit conditions, and the mitigation measures proposed by
Millennium.
Verifying that the limits of authorized construction work areas and locations of the access
driveway are properly marked before clearing.
Verifying the location of signs and highly visible flagging marking the boundaries of
sensitive resource areas, waterbodies, wetlands, or areas with special requirements along the
construction work area.
Ensuring that the location of dewatering structures and slope breakers will not direct water
into known cultural resources sites or locations of sensitive species.
Verifying that trench dewatering activities do not result in the deposition of sand, silt, and/or
sediment near the point of discharge into a wetland or waterbody. If such deposition is
occurring, the dewatering activity shall be stopped and the design of the discharge shall be
changed to prevent reoccurrence.
Advising the Chief Inspector when conditions (such as wet weather) make it advisable to
restrict construction activities to avoid excessive rutting.
Determining the need for and ensuring that erosion controls are properly installed, as
necessary to prevent sediment flow into wetlands, waterbodies, sensitive areas, and onto
roads.
Inspecting and ensuring the maintenance of temporary erosion control measures at least:
o
o
o
Ensuring the repair of all ineffective temporary erosion control measures within 24 hours of
identification.
Keeping records of compliance with the environmental conditions of Federal and state
permits, and the mitigation measures proposed by Millennium during active construction and
restoration.
Identifying areas that should be given special attention to ensure stabilization and restoration
after the construction phase.
GENERAL
The Project will be constructed in compliance with applicable Federal regulations and guidelines, and
the specific requirements of the necessary permits. Key guidelines and Federal requirements include:
Millenniums Construction Specifications and Procedures
18 CFR Part 380 Guidelines to be Followed by Natural Gas Pipeline Companies in the
Planning, Clearing and Maintenance of Right-of-Way and the Construction of Aboveground
Facilities.
49 CFR Part 192 Transportation of Natural Gas and Other Gas by Pipeline: Minimum
Federal Safety Standards.
Pipeline
Pipeline work is limited to the installation of suction and discharge piping to connect the Minisink
Compressor Station to Millenniums existing mainline. This work is appurtenant to the construction
of the new compressor station and thus the construction procedures are discussed below.
Aboveground Facilities
The compressor station facility will be constructed in compliance with Federal regulations and
guidelines, and in accordance with the specific requirements of applicable Federal and state
approvals. The construction and restoration methods in the Commissions Plan and Procedures will
be followed, as applicable. Generally, facilities are sited to avoid cultural and natural resource
impacts to the extent practicable. The following is a brief description of the typical construction
sequence for the facilities.
Construction is performed with different construction crews performing various construction
techniques in an efficient, planned sequence, within a pre-defined work space, referred to as the
facilities or Construction Work Area (CWA). These techniques are required for the installation of the
facilities safely and reliably, in accordance with the requirements and regulations of the U.S.
Department of Transportation and the Occupational Safety and Health Administration.
Construction activities typically involve the following activities:
Preconstruction activities (e.g., surveying and staking the CWA boundaries, flagging or
otherwise delineating environmental features, installing signs)
Clearing
Grading
Piping
Infrastructure Facilities
Specific standards for crossings of streams and wetlands are included in ECS Sections IV and
V, respectively.
III.B
The access driveway will be 16 feet wide paved (travel lane), with additional width at the
intersection with Jacobs Road.
The access driveway will be permanent (used during and after construction for operation and
maintenance of the Project facilities).
The access driveway development (e.g., grading, clearing, stabilization, erosion and
sedimentation control measures) will be in accordance with standard environmental
requirements. Roadbed stabilization may include the addition of gravel or mulch/wood chips
(e.g., an erosion control mix type provided the road bed is not within 50 feet of waterbodies
or wetlands), based on site-specific conditions and the recommendations of Millenniums
inspectors.
Safe and accessible conditions will be maintained at the driveway access point during
construction and restoration.
The access driveway gradient will follow the local topography to the extent practical.
Erosion and sediment control devices will be installed as needed.
The access driveway will cross the intermittent stream as close as possible to a right angle.
Culverts will be sized and placed to permit water flow under the driveway.
Additional access roads may not be utilized without first obtaining the approval of the
Commission (if no water resources are involved) or other appropriate regulatory bodies if
water resources are involved.
b.
Additional contractor wareyards may not be utilized, and existing yards cannot be
expanded, without first obtaining the approval of the Commission (if no water resources are
involved) or other appropriate regulatory bodies if water resources are involved.
III.C
CLEARING
The CWA will be cleared to the dimensions specified on the site plan. The following procedures will
be used during clearing:
1. Before commencing vegetation removal, the limits of the CWA will be established in the
field by flagging or staking, per the site plan.
2. Any trees to be saved will be clearly marked or otherwise protected.
3. All clearing activities will be confined to the limits of the CWA.
4. During clearing operations, brush and trees will be felled into the CWA where practical, to
minimize the potential for damage to off-CWA areas.
5. The clearing crew and related equipment, as well as equipment necessary for the installation
of the access driveway, will be permitted a single pass through the stream prior to equipment
crossing installation. (Commission Procedures, Section V.B.5, p. 7)
III.C.1 Wood Products and Materials
1. All woody materials, including stumps, may be removed from the CWA, or chipped/mulched
on the CWA. If chipped/mulched, such materials may be given away, buried, or thinly
spread across the CWA as described in Section II.C.2.
III.C.2 Brush
All cleared brush will be disposed by one of the following methods:
1. Brush may be piled just off the CWA in upland areas, but not within 50 feet of streams or
wetlands. Equipment used to stack the brush will not leave the CWA. Brush piles will be
constructed a maximum of approximately 12 feet wide and compacted to approximately 4
feet high, with periodic breaks at a minimum of approximately every 200 feet to permit
wildlife travel.
2. Brush may be hauled off the CWA to an approved disposal site.
3. Brush may be chipped or mulched. Chips/mulch will be given away, buried, or during
construction thinly spread (an approximately 2 thick layer) over the CWA or piled off the
CWA except within 50 feet of streams or wetlands.
2. Hay or straw bales used on equipment bridges or on mats across the equipment travel lane
will not be staked or trenched in place.
3. Temporary erosion and sediment control devices will be inspected according to the following
schedule:
Any controls requiring maintenance will be promptly reported to the Contractor (verbally and/or
via a daily punch list).
NOTE: If temporary erosion controls must be maintained over winter, inspections and
maintenance activities will be suspended during frozen conditions. Such inspections will
resume as soon as runoff occurs or prior to the re-commencement of construction, whichever
comes first.
4. Temporary erosion and sediment controls will be maintained until permanent revegetation is
successful or the upland areas adjacent to waterbodies, wetlands, and roads are otherwise
stabilized.
During clearing and all other construction work, the CWA will be kept clean of all rubbish and debris
resulting from the work. Non-hazardous materials and waste will be disposed in an approved landfill.
Hazardous materials and waste will be disposed in accordance with all applicable Millennium policies
and Federal, state, and local regulations.
III.D. GRADING
Grading is necessary to provide a smooth and level surface for the safe operation of the heavy
equipment involved in Project construction. Grading will be the minimum amount necessary and
includes prompt installation of erosion control devices, such as interceptor diversions, sediment filter
devices, and equipment crossings at streams to minimize soil loss and subsequent sedimentation.
III.D.1 Grading Near Watercourses
Within 25 feet of the edge of a watercourse, initial grading will be limited to the areas required to
install construction equipment crossings and any associated temporary work space.
Buried within the CWA except in water resource/wetland areas and not within the area of the
permanent facility.
For erosion control purposes in certain areas (e.g., steep slopes along the edge of the CWA
adjacent to roads), cut flush with the ground using a stump grinder or equivalent.
Hauled from the CWA and disposed in an approved landfill or other suitable area.
Rock
Rock (including blast rock) will be disposed as follows:
Buried within the CWA, including for use in fill during grade cut restoration.
Stored temporarily along the CWA and used as a deterrent for unauthorized use.
Crushed on site and then graded into the CWA as part of restoration.
NOTE: On a site-specific basis, mulch, rock, and stumps may also be buried within the CWA in
deep side hill cuts, as part of the restoration of such areas.
III.D.3 Erosion Control Devices Installed During Grading
Temporary erosion and sediment controls will be installed immediately after the initial disturbance of
soils (refer to Commissions Plan, Section IV.F, p. 8). Such controls may involve hay or straw bales, silt
fence, compacted earth, ground up (chipped/mulched) woody material, or sand bags, as well as
drivable berms across travel lanes within the CWA), etc. (refer to Figures 5, 6, and 7).
Temporary erosion controls must be properly maintained throughout construction (on a daily basis)
and reinstalled as necessary (such as after backfilling of the trench) until replaced by permanent
erosion controls or restoration is complete. (Refer to Commissions Plan, Section IV.F, pp. 8-9)
1. Temporary Slope Breakers
a. Temporary slope breakers are intended to reduce runoff velocity and divert water off the
construction right-of-way. Temporary slope breakers may be constructed of materials such as
soil, silt fence, staked hay or straw bales, or sand bags.
b. Install temporary slope breakers as necessary to avoid excessive erosion. Temporary slope
breakers must be installed on slopes greater than 5 percent where the base of the slope is less
than 50 feet from waterbody, wetland, and road crossings at the following spacing (closer
spacing should be used if necessary):
Slope (%)
5 - 15
>15 - 30
>30
Spacing (feet)
300
200
100
c. Direct the outfall of each temporary slope breaker to a stable, well vegetated area or construct an
energy-dissipating device at the end of the slope breaker and off the CWA.
d. Position the outfall of each temporary slope breaker to prevent sediment discharge into
wetlands, waterbodies, or other sensitive resources.
2. Sediment Barriers
a. Sediment barriers are intended to stop the flow of sediments and to prevent the deposition of
sediments into sensitive resources. They may be constructed of materials such as silt fence,
staked hay or straw bales, compacted earth (e.g., drivable berms across travelways), sand bags,
or other appropriate materials.
b. At a minimum, install and maintain temporary sediment barriers at the base of slopes greater
than 5% where the base of the slope is less than 50 feet from a waterbody, wetland, or road
crossing until revegetation is successful as defined in the Commission requirements. Leave
adequate room between the base of the slope and the sediment barrier to accommodate ponding
of water and sediment deposition.
c. Where wetlands or waterbodies are adjacent to and downslope of construction work areas,
install sediment barriers along the edge of these areas, as necessary to prevent sediment flow
into the wetland or waterbody.
Such controls will be maintained until replaced by permanent erosion controls or sites are determined
to be stabilized and restoration complete.
III.D.4 Temporary Road Entrances
Where the CWA intersects public roads, temporary road entrances will be installed as shown on
Figure 9.
Temporary road entrances will be maintained to promote safe conditions and to prevent or minimize
construction equipment tracking of soil or mud onto public roads.
If mud and/or soil is tracked onto public roads from the CWA, the tracked material will be swept,
shoveled, or scraped as necessary to keep the road surface safe for motorists.
III.E
TRENCHING
Generally, the trench will not remain open for more than 30 days, except at tie-in and pressure test
locations, unless authorized by the EI. When the trench must remain open for a greater length of time
(i.e. pressure test locations), appropriate erosion controls and safety measures will be employed as
directed by the EI.
Spoil piles from trench excavation (or other CWA grading) must be placed at least 50 feet upgradient
from the edge of waterbodies. Spoil piles must be contained with erosion and sediment controls to
prevent spoil or silt-laden water from entering waterbodies or wetlands.
Excess material from trench excavation (or other construction activity), will be stored in uplands and
stabilized to prevent runoff into wetlands or watercourses.
III.E.2 Blasting
All drilling and blasting will be conducted in a cautious manner and suitable precautions will be taken
to avoid injury or damage to persons, livestock, or other property.
Adjacent landowners will be given timely notice (1 weeks notice with at least 1 day confirming
notice) prior to blasting.
Millennium will hire an independent contractor to perform pre- and post-blast structural inspections
and seismographic monitoring, if necessary.
III.E.3 Temporary Trench Plugs
Temporary trench plugs are in-trench barriers that typically consist of sand bags or compacted subsoil
(referred to as soft plugs), or unexcavated portions of the trench (referred to as hard plugs).
Such temporary plugs serve to segment an area of open trench, thereby reducing erosion and
sedimentation down the trench and assisting in reducing dewatering issues at the base of slopes where
water resources are often found.
Trench plugs will be installed as deemed appropriate by the EI.
III.E.4 Temporary Construction Access over the Trench
Where access across the trenchline is required, temporary facilities such as trench plugs, timber mats,
or steel plates will be constructed or installed to permit safe crossing of vehicles, equipment and
persons from one side of the trench to the other.
Safety fencing (or equivalent) may be installed along both sides of the trench as necessary to block
entry to the trench area except at the temporary access point.
III.F
Lowering-in involves placing the completed pipe sections in the trench, where a tie-in weld will be
made. Before the pipe is lowered- in, the trench will be dewatered, cleaned of debris, and padded as
necessary.
III.F.2 Trench Dewatering
Trench dewatering will be performed as required to remove accumulated water from the trench (or
other pipe excavations) prior to and after the installation of the pipe or footers. Any dewatering,
either on or off the CWA, will be conducted so as not to discharge any heavily silt-laden water from
the trench directly into wetlands or waterbodies. (refer to Commission Procedures, Sections V.B.11, p. 12
and VI.B.4, p. 19)
If necessary to pump water from the trench, the water will be pumped into one of the following:
Through a sediment filter or energy dissipating device, as illustrated in Figures 6 and 7, that
is placed at least 50 feet from any stream or wetland.
If dewatering/discharge activities must be located off the CWA, locations will be selected that
minimize impacts, including impacts to sensitive resources.
If possible, the intakes of hoses used to pump water from the trench will be elevated and may be
screened to minimize the amount of sediment carried in the discharge.
Dewatering devices or structures will be removed after the completion of all dewatering activities in
an area.
III.G
BACKFILLING
III.G.1 General
Backfilling will follow the lowering-in of the piping as close as practical. Backfill will consist of the
material removed from the trench or other fill material brought to the site if the existing trench spoil is
not suitable for use as backfill.
Where the trench bottom is irregularly shaped (e.g., due to rock) or excavated spoil is not suitable for
use as backfill around the pipe, padding (typically consisting of sand or screened spoil from the
excavation) may be required.
Soil that has been excavated during construction and not used for backfill will be evenly
spread over upland areas of the CWA or removed from the site and properly disposed in an
upland area.
All waste materials (e.g., barrels, cans, drums, stumps, coating and wrap, rubbish, or other
refuse) will not be placed in the trench and will be removed from the CWA.
Excess rock, including blast rock, may be used to backfill the trench to the top of the existing
bedrock profile once the pipe is properly padded.
10
An engineer or similarly qualified professional will determine the need for and spacing of
trench breakers; otherwise, trench breakers will be installed at the same spacing as and
upslope of permanent slope breakers (refer to Section II.H).
Trench breakers will be installed at the base of slopes greater than 5% where the base of the
slope is less than 50 feet from a waterbody or wetland and where needed to avoid draining a
waterbody or wetland.
III.H
Restoration of the CWA begins with rough grading, which will commence promptly after or in
conjunction with backfilling. Thereafter, disturbed areas along the CWA will be stabilized either by:
Temporary stabilization measures to prevent erosion and sedimentation until final grading
and restoration can be completed.
All construction debris (e.g., used wetland filter bags, skids, trash) will be removed from the CWA.
III.H.1 Final Grading
Reasonable efforts will be made to complete final grading and installation of permanent
erosion control devices within 20 days of backfilling the trench. If related construction in the
area or seasonal or other weather or soil conditions prevent compliance with these time
frames, temporary erosion controls (e.g., temporary slope breakers, silt fence/hay (straw) bale
erosion/sediment controls) will be maintained until conditions do allow final grading and
restoration. (refer to Commission Procedures, Section V.A.1, p. 11)
In preparation for reseeding, the CWA will be re-graded as shown on the site plan.
In no case will final grading be delayed beyond the end of the next recommended seeding
season.
If final grade can be established, but conditions are not ideal for permanent seeding,
temporary stabilization measures (including temporary seeding) will be applied; the
concurrent application of final seed mix and mulch (as provided in Table 2a) also may be
considered, with the understanding that subsequent restoration will be required in the
following growing season if the revegetation effort is not successful.
11
Breakers will be constructed and maintained along the CWA per the following spacing:
Slope (%)
5 - 15
>15 - 30
>30
Spacing (feet)
300
200
100
Slope breakers will be constructed to divert the surface flow to a stable area or if no such area
is available, an energy-dissipating device will be installed at the end of the breaker.
Slope breakers may extend slightly off the CWA (e.g., about 4 feet).
III.H.3 Restoration
Restoration will begin after final grading, weather and soil conditions permitting.
Steep slopes will be restored immediately after final grading, weather permitting, or otherwise
stabilized. Figure 14 illustrates the typical installation of biodegradable erosion control
netting/matting for stabilization of steep slopes.
ALL EROSION CONTROL MATTING/NETTING MUST BE MADE FROM
BIODEGRADABLE MATERIALS IF INTENDED TO BE LEFT IN PLACE
PERMANENTLY.
The typical application rates for seed and mulch are listed in Tables 2a and 2b. The seed will be
uniformly applied and covered in accordance with the written recommendations of the local soil
conservation authorities.
III.H.4 Temporary Stabilization Measures
When the EI determines that temporary stabilization measures are required, they will be completed as
soon as possible. Seeding and mulching application rates will be as shown in Table 2b.
Consideration will be given to the following when determining if temporary stabilization measures
are to be implemented:
If temporary stabilization measures are utilized, final grading and/or restoration will commence once
weather and soil conditions permit.
Mulch will be applied in accordance with the specifications outlined in this section except when
mulching before seeding. The mulch application on all 8% or greater slopes within 100 feet of
waterbodies and wetlands will be at a rate of 3 tons/acre.
III.I
PRESSURE TESTING
The compressor station piping will be pressure tested in accordance with U.S. Department of
Transportation (USDOT) 49 Code of Federal Regulations (CFR) Part 192 requirements to ensure its
integrity for the intended service and operating pressures. The compressor station piping will be
tested with water, air or inert gas. Test pressure will be obtained by adding the appropriate testing
medium to the test section with a high-pressure pump.
Millennium Pipeline Company, L.L.C.
12
If water is used, it will be sourced and discharged according to applicable permits and authorizations.
At the completion of the hydrostatic test, the pressure is relieved and the water is removed from the
test section. If necessary, additional drying may be performed to remove any residual water from the
pipeline. Hydrostatic test water will be obtained from off-site sources and delivered to the site in
tanker trucks. All hydrostatic test discharge activities will be performed in accordance with the
Commission Plan and Procedures and applicable permit requirements.
Test Water Discharge
Hydrostatic test water will be discharged in a manner that minimizes erosion. (refer to Commission
Procedures Section VII.C.1, p. 22)
The discharge rate of the released test water will be regulated by using energy dissipation devices
and/or sediment barriers to prevent erosion, streambed scour, suspension of sediments, or excessive
stream flow.
Water will be discharged as follows:
During the discharge, the EI will ensure that erosion and sedimentation are properly controlled.
Methanol may be injected, after discharging the water, to dry the pipe. Excess methanol will be
collected from the facility and disposed of in accordance with applicable state and local regulations.
IV.
WATERBODY CROSSINGS
IV.A
GENERAL
The main objective of any waterbody crossing is to complete the work in a manner that minimizes
erosion and subsequent sedimentation into the waterbody. The following general procedures will
apply to the access driveway crossing of the intermittent stream:
The EI will conduct pre-construction walkovers of the CWA to identify the stream crossing
boundaries.
The access driveway crossing will be constructed as close as possible to a right angle with the
stream channel.
Adequate downstream flow rates will be maintained at all times to protect aquatic life and
prevent the interruption of existing downstream uses.
Where the stream is adjacent to the CWA, sediment barriers will be installed along the edge
of the CWA as necessary to contain spoil and sediment.
13
Millennium will monitor the status of the access driveway crossing and will have adequate
staff and equipment available to prevent or avoid adverse environmental effects.
Spill response materials will be available at the access driveway crossing site and no
equipment will be serviced and no petroleum products stored within 100 feet of any
waterbody except under special circumstances as described in the Spill Containment and
Control Plan (refer to Attachment A).
Under normal conditions, all in-stream construction will be accomplished within the time
frames established in Millenniums plans.
IV.B
EQUIPMENT CROSSINGS
CLEARING
Clearing of stream bank vegetation will be limited to the area of the access driveway. If extra work
space is needed, it will be as specified on the site plans or otherwise setback at least 25 feet from the
stream bank to minimize riparian vegetation disturbance.
All cleared materials will be disposed at least 50 feet from the waters edge.
IV.D
GRADING
Grading equipment will not enter the stream to grade the banks. Stream banks will be graded only
where, and as much as, necessary to permit safe and efficient operation of construction equipment.
Initial grading within 25 feet of the waters edge will be limited to only the area needed to install the
access driveway and any associated temporary work space.
During grading operations, sediment filter devices will be installed promptly as close to the water as
practical. All disturbed areas within 50 feet of the waters edge will be promptly mulched. The
mulch will be maintained until the waterbody crossing restoration is complete.
Spoil from CWA grading will be piled at least 25 feet from the waters edge and immediately
protected with sediment filter/erosion control devices to avoid or minimize the potential for erosion
into the waterbody.
IV.E
BLASTING
IV.E.1 Notifications
Millennium will comply with the notifications required under all local blasting permits.
IV.E.2 Procedures
During the pre-planning of the access driveway across the intermittent stream, an evaluation (usually
test pits dug with a backhoe) will be made concerning the need for blasting. If the evaluation is
inconclusive, the stream bed will be tested for consolidated rock prior to trenching.
If the stream bottom is consolidated rock, it can be drilled and shot at any time prior to commencing
construction of the access driveway. However, removal of shot rock, and any additional drilling,
14
shooting, and material removal, will be completed within the minimum number of consecutive
calendar days practical.
Blasting will be supervised by a blasting consultant and will be performed so as to avoid the
permanent deposition of shot rock in wetlands.
Millennium will verify that no water birds (i.e., waterfowl, shorebirds, or wading birds) are within
500 feet on any waterbody or wetland prior to blasting.
The sediment filter devices across the CWA at the access driveway will be promptly reinstalled after
installation.
IV.F
RESTORATION
IV.F.1 General
With the exception of the areas required for the permanent access driveway:
Stream banks and adjacent areas will be rough graded to a distance of 25 feet from
the ordinary high water mark. As part of stabilization, temporary sediment and
erosion control measures will be installed or re-installed.
Asphaltic emulsions will not be used to stabilize mulch within 100 feet of waterbodies. Liquid mulch
binders will not be used within 100 feet of waterbodies.
Replacement of stream banks will be at the approximate original contour. If the stream banks are
such that an unstable final soil grade could result and vegetative stabilization would be inadequate,
the EI will require mechanical stabilization of the stream banks. Mechanical stabilization typically
may include native stone, riprap, biodegradable jute netting, etc.
Temporarily disturbed riparian areas will be revegetated with conservation grasses and legumes or
native plant species.
IV.F.2 Non-Vegetative Bank Stabilization
If non-vegetative bank stabilization measures are required immediately adjacent to the access
driveway culvert, the first preference will be to use native rocks or boulders from the CWA. The
objective is to stabilize the stream banks while matching pre-construction and off-CWA conditions to
the extent practical. If used, riprap will only be placed on stream banks and will be large enough to
prevent normal waterbody current from moving it. The need for and installation of non-native riprap
will be coordinated with the EI.
Biodegradable erosion control fabric will be installed as needed, on the stream banks at the time of
final bank recontouring.
Once permanent revegetation is successful, sediment and erosion control devices will be removed
from the CWA and properly disposed.
Any excess spoil material not taken off site to an approved location will be disposed in an upland area
and adequately stabilized to prevent return flow or sedimentation to wetlands or other waterbodies.
Millennium Pipeline Company, L.L.C.
15
V.
WETLAND CROSSINGS
V.A
GENERAL
CONSTRUCTION TECHNIQUES
Approximately 0.09 acres of wetlands will be permanently impacted as a result of the installation of a
paved access driveway with a culvert. Temporary wetland impacts may include soil disturbance,
temporary alteration of hydrology and loss of vegetation during construction. Wetland areas adjacent
to the access driveway will be restored and will be allowed to regenerate to pre-construction
conditions.
Millennium will protect and minimize potential adverse impacts on wetlands as follows:
limiting the amount of equipment and construction activities within wetlands to minimize soil
disturbance;
stabilizing upland areas near wetlands with erosion control measures and vegetative cover as
soon as practicable;
inspecting the disturbed site periodically during and after construction and repairing any erosion
control or restoration features as needed until permanent revegetation is successful.
CLEARING
Tree and brush clearing in wetlands will be performed so that vegetation will be cut off at ground
level, leaving the existing root systems in place where practical. Tree stumps will be removed in
areas to receive fill.
All cut vegetation will be removed from the wetland for disposal. Chipping or mulching of slash,
brush, or other woody materials in wetlands is prohibited, as is burning of such materials.
Millennium Pipeline Company, L.L.C.
16
Slash, brush, or cleared timber will not be buried, windrowed, or stacked in wetlands or other
waterbodies.
V.D
GRADING
Grading in wetlands will consist of the minimum necessary for safe and efficient construction of the
access driveway.
Stumps will be removed within the area required for the access driveway to create a safe and
level equipment access/work area and areas to receive fill. 1
No grading or removal of stumps or root systems from the rest of the CWA in wetlands will
occur unless the Chief Inspector and EI determine that safety-related construction constraints
require removal of tree stumps.
No tree stumps, rock, soil imported from outside the wetland, or brush will be used to
stabilize the CWA or as equipment pads in wetlands.
Where wetlands are adjacent to the CWA, sediment barriers will be installed along the edge of the
CWA as necessary to prevent sediment flow into the wetland. Sediment barriers will be removed
only after successful CWA restoration.
Sediment filter devices will be installed promptly across the CWA during grading at the wetland edge
and maintained until CWA revegetation is complete. Temporary interceptor diversions will be
installed adjacent to wetlands.
V.E
BLASTING
During the pre-planning of crossing wetlands for the access driveway, an evaluation will be made
concerning the need for blasting. If the evaluation is inconclusive, the wetland will be tested for
consolidated rock prior to access driveway installation. If the wetland has consolidated rock, it will
be drilled and shot as part of the single construction entity.
Blasting mats will be used in wetland areas (except those with standing water) during blasting
operations.
Blasting will be supervised by a blasting consultant and will be performed so as to avoid the
permanent deposition of shot rock in wetlands. Millennium will verify that no water birds (i.e.,
waterfowl, shorebirds, or wading birds) are within 500 feet on any waterbody or wetland prior to
blasting.
V.F
RESTORATION
With the exception of the access driveway, wetland crossing areas will be restored to preexisting contours and rough graded to a distance of 100 feet from the delineated federal
jurisdictional boundary of the wetland within 48 hours of backfilling. If site-specific conditions
or inclement weather do not allow such restoration within this 48-hour period, appropriate
temporary erosion and sediment controls will be applied. Millenniums EI will document the
reasons for the delay and the temporary stabilization measures taken to minimize adverse
effects, as well as the scheduled and actual completion of the work. Such documentation shall
be provided in the EIs daily report and conveyed to the Commissions Compliance Monitor.
1
Stumps may be removed during clearing, depending on the type of clearing equipment used.
17
Upon completion of construction of the access driveway in wetland areas with standing water or
saturated soils, the wetlands will be restored to original contours and seeded with either an annual rye
or native perennial seed mix (refer to Table 2c). Any seeding of the CWA in wetlands will be
performed by hand.
Fertilizer or lime will not be used in wetlands.
Asphaltic emulsions will not be used to stabilize mulch within 100 feet of wetlands.
Liquid mulch binders will not be used within 100 feet of wetlands.
When permanent revegetation is successful and restoration work is complete, all remaining sediment
filter devices including silt fence fabric materials including fragments of fabric material, other
construction debris, and remaining hay bales will be removed from the CWA and properly disposed.
VI.
MAINTENANCE
VI.A
GENERAL
Maintenance activities will be performed with emphasis on preservation and enhancement of the
environment. All applicable certificate and permit conditions will be incorporated into the future
maintenance plan for the facility.
VI.B
UPLAND AREAS
The compressor station facility will be maintained by mowing or other mechanical means.
Herbicides and pesticides will not be used within 100 feet of a waterbody or wetland.
Plant growth on the permanent facility site and the permanent erosion control devices will be
inspected regularly and maintained for the life of the facility.
Revegetation will be considered successful if perennial non-nuisance vegetation is similar in density
to adjacent undisturbed land. If revegetation is not successful, the area will be restored as soon as
practical. If vegetative cover and density are not similar or there are excessive noxious weeds after
two full growing seasons, a professional agronomist will determine the need for additional restoration
measures (such as fertilizing or reseeding). The agronomists recommendations will be implemented
as soon as possible.
Problems with drainage resulting from construction activities will be reported to the local operations
supervisor. Corrective measures will be performed as needed.
Erosion at the facility and access driveway will be reported to the local operations supervisor.
Corrective measures will be performed as needed provided the problem resulted from construction or
operation of the facility. Erosion control devices that are no longer required may be removed at the
discretion of the local operations supervisor. Similarly, additional erosion control devices may be
installed.
All temporary sediment barriers will be maintained in place until permanent revegetation measures
are successful or the upland areas adjacent to wetlands, waterbodies, or roads are stabilized.
Temporary sediment barriers will be removed from an area once that area is successfully restored.
Efforts to control unauthorized ORV use will continue throughout the life of the project. Signs and
gates will be maintained as necessary.
18
VI.C
During the operation of the pipeline system, Millennium will work cooperatively with appropriate
government agencies in an effort to minimize the impacts of facility maintenance in waterbodies,
wetlands, and other environmentally sensitive areas. The following procedures will be applied to
ROW maintenance activities:
Attempts will be made to prevent the invasion or spread of undesirable exotic vegetation (i.e.,
purple loosestrife, Japanese knotweed, and Phragmites) within wetland areas disturbed
during construction. Typically, these efforts will be limited to the use of Millenniums
standard wetland construction techniques.
19
The Chief Inspector reports directly to the Construction Manager and is the
individual responsible for managing all inspection activities during construction.
The Chief Inspector supervises a team of inspectors including clearing, grading,
welding, backfilling, restoration, and environmental.
COMPLIANCE
MONITOR:
CWA:
The Construction Work Area includes, but is not limited to, permanent and
temporary construction ROW, extra work spaces, contractors wareyards and
access roads. The CWA is depicted on the site drawings.
ECS:
EI:
FINAL GRADING:
INSPECTOR:
INTERMITTENT
STREAM:
Roles and
MILLENNIUM:
NRCS:
NYSDEC:
ORDINARY HIGH
WATER (OHW) MARK:
The term 'ordinary high water mark' means that line on the shore established
by the fluctuations of water and indicated by physical characteristics such as a
clear, natural line impressed on the bank, shelving, changes in the character of
soil, destruction of terrestrial vegetation, the presence of litter and debris, or
other appropriate means that consider the characteristics of the surrounding
areas.
ORV:
Off-road vehicle.
ROW:
Right-of-way.
SEDIMENT FILTER
DEVICE:
Includes properly embedded silt fence or staked straw or hay bales, as well as
other erosion and sedimentation control options.
SPCC:
STEEP SLOPE:
TEMPORARY
STABILIZATION
20
MEASURES:
UPLAND:
WATERBODY:
WETLAND:
An area of special concern with soils prone to holding water for long periods of
time, generally also characterized by distinctive plants such as rushes, sedges,
cattails, or certain shrubs/trees. Includes any area that satisfies the requirements
of the current Federal methodology for identifying and delineating wetlands.
21
TABLE 2a
SEED MIX REQUIREMENTS FOR CWA AND WATERBODY CROSSINGS
USDA NRCS Recommended
Restoration Seed Mixtures
Rate
(lbs/acre)
0.75
Seed
White Clover
Creeping Red Fescue
6.00
Tall Fescue
7.00
Annual Ryegrass
5.00
Climax Timothy
3.00
2.20
TABLE 2b
SEED MIX REQUIREMENTS FOR TEMPORARY STABILIZATION
Type
Rate (lbs/acre)
Seed
Annual Rye
40
Mulch
Hay or Straw
6000
TABLE 2c
SEED MIX REQUIREMENTS IN WETLANDS
Type
Seed
Rate (lbs/acre)
Annual Rye*
40
* Annual Rye is used as a temporary re-vegetative measure until indigenous plants re-establish cover.
22
ATTACHMENT A
SPILL PREVENTION, CONTAINMENT AND CONTROL PLAN
A-1
July 2011
TABLE OF CONTENTS
Page
I.
INTRODUCTION .................................................................................................................. 1
II.
TRAINING ............................................................................................................................. 1
III.
IV.
V.
VI.
REFUELING .......................................................................................................................... 3
ATTACHMENTS
Attachment 1
Attachment 2
INTRODUCTION
During the construction of the Millennium Pipeline Company, L.L.C. (Millennium) Minisink
Compressor Station Project (Project), all efforts will be made to prevent spills or releases of any
amount of petroleum products or other polluting materials to the environment. This Spill Prevention,
Containment and Control Plan (SPCC Plan) describes the measures to prevent spills and, in the event
that spills occur, to control and minimize the effects of a release of petroleum products or hazardous
substances. The contractor will be responsible for preparing response plans that are compliant with
appropriate Federal, state and local regulations.
II.
TRAINING
During the Project Environmental Awareness Training, all Millennium inspectors and construction
contractor personnel will be briefed on the requirements of this SPCC Plan. Training will emphasize
the following:
III.
The contractor will ensure that all employees handling fuels and, as applicable, hazardous
materials will be properly trained.
Precautionary equipment maintenance and refueling procedures are to be followed to
minimize the potential for releases.
Standard operating procedures are to be followed in the event of a release, including the
deployment and maintenance of spill response materials.
Standard equipment, materials and supplies are to be available for cleanup of a release.
ENVIRONMENTAL INSPECTOR REQUIREMENTS
Prepare a pre-job, written inventory of lubricants, fuels, and other materials, which could be
accidentally discharged during construction. This information shall be supplied to the
environmental inspector (EI) by the Contractor.
Consult with Millennium to determine reportable spill quantities for each material on the prejob inventory.
Consult with Millennium to classify, in the event of an accidental release, each material on
the pre-job inventory as hazardous or non-hazardous waste under RCRA regulations.
Identify and prepare, in conjunction with appropriate Millennium personnel a written
inventory of approved waste transporters and disposal sites for both hazardous and nonhazardous wastes near the construction site.
Approve the Contractors list of equipment and spill procedures and impact minimization
measures submitted.
Define the duties and coordinate the responses of all persons involved in cleaning up a spill.
Maintain, with support from Millennium, an up-to-date list of names, addresses, and phone
numbers of all persons to be contacted in case of a spill.
Assure that the Contractor conducts mandatory training and instruction for spill prevention
and impact minimization.
IV.
V.
The following procedures will be followed when storing fuels and hazardous materials to help avoid
spills and minimize the impact of spills that accidentally occur:
VI.
Bulk quantities of diesel fuel, gasoline and hazardous liquids (e.g., solvents and lubricants)
will be stored in the onsite contractor staging area. Adequate spill containment measures,
such as containment dikes with a capacity for at least 110% of the maximum storage volume,
combined with impervious lining, will be installed before fuel storage tanks are filled, and
will be maintained throughout the Project. The contractor will provide Millenniums EI with
copies of the Material Safety Data Sheets (MSDS) for each hazardous material on site and
will maintain such MSDSs on-site.
Lesser quantities of fuels, solvents and lubricants (e.g., motor oils, hydraulic fluid) may be
stored within the construction work area (CWA) as necessary to service equipment used on
the Project, provided that this storage does not conflict with other parts of this plan. Sorbent
booms and clean-up kits will be kept at all storage locations. No equipment servicing or
maintenance will be performed and no petroleum products will be stored within 100 feet of
any watercourse or wetland.
All storage areas will be located at least 100 feet from streams, ponds or wetlands; at least
200 feet from active or private water wells; and at least 400 feet from municipal water wells.
Use of hazardous materials for equipment and vehicle maintenance will follow the same
requirements specified above for equipment refueling. Impervious or sorbent materials will
be placed under the work area before the work begins. Additional sorbent materials will also
be readily available.
Waste materials created during maintenance (e.g., used oil) will be collected for proper
disposal. All waste materials, including partially used or empty containers, discarded parts,
clean-up rags and used sorbent materials, as well as discarded hazardous material containers
(e.g., oil cans, grease tubes), will be collected and placed in drums for proper disposal.
All motor fuel, lube oil, chemicals and other polluting substances will be tightly sealed and
clearly labeled during transportation and storage.
All equipment will be inspected daily for leaks prior to beginning work. Steps will be taken
to repair leaks or remove the equipment from service, if necessary.
REFUELING
Generally, fuel will be stored at the contractor staging area and as much equipment as
practical will be refueled there.
Refueling equipment will be manned throughout the refueling operation.
Spill kits will be carried on all construction equipment.
Equipment refueling will not be performed within 100 feet of any waterbody or wetland, with
the following exceptions:
o Areas of rugged terrain or steep slopes where movement of equipment outside of
such 100-foot buffers would cause excessive disturbance to the work area
o Areas where removing equipment from a wetland or from near a watercourse for
servicing or refueling would increase adverse impacts to the wetland
o Refueling of immobile equipment.
During refueling, all necessary precautions will be taken to avoid or minimize the potential
for an accidental spill. Appropriate spill kits/absorbent materials will be available at all
refueling sites.
Care will be taken during refueling not to overfill or spill fuel onto the housing of equipment.
Refueling areas will be located hydraulically down gradient and outside aquifer protection
areas, whenever possible, and if located within an aquifer protection area, the refueling area
will be lined. The fueling nozzle will be wrapped with absorbent pads and carried from the
dispensing equipment to the equipment being fueled.
Fuel trucks, pumps, mechanics vehicles, the contractor foremens vehicles, inspectors
vehicles and all vehicles working within aquifer protection areas and public water supply
watersheds will be equipped with spill kits containing absorbent materials approved for
petroleum products.
Construction equipment will not be washed in any waterbody or wetland, nor will runoff
resulting from washing operations be permitted to directly enter any waterbody or wetland
area.
Construction equipment and vehicles will not be serviced or parked overnight within 100 feet
of waterbodies or wetlands.
Considerations
The Contractor will assure that all refueling be done pursuant to the following conditions:
Impact minimization measures and equipment will be sufficient to prevent discharged fluids
from leaving the CWA or reaching wetlands or waterbodies, and be readily available for use.
These will include some combination of the following:
o dikes, berms or retaining walls sufficiently impervious to contain spilled oil
o absorbent and barrier materials in quantities determined by the Contractor to be
sufficient to capture the largest reasonably foreseeable spill
o disposable drums or containers suitable for holding and transporting contaminated
materials
o curbing
o culverts, gutters, or other drainage systems
o weirs, booms, or other barriers
o spill diversion or retention ponds
o sumps and collection systems
The Contractor will prepare for approval by Millennium a list of the type, quantity, and the
storage location of containment and clean up equipment to be used during construction. The
list will include the procedures and impact minimization measures to be used in case of a
spill.
VII.
All spills will be cleaned up immediately. In no case will containment equipment be used for
the storage of contaminated material.
SPILL RESPONSE
Stopping the source and containment is the immediate priority in the case of a release. Cleanup
procedures will begin immediately after a release is contained. In the event of a spill, Millennium
will take immediate action to ensure that the impact of the spill is minimized, and to see that
appropriate cleanup action is immediately undertaken.
The first person to notice a spill (e.g., contractor personnel, Millennium inspectors) will take
immediate steps to stop and contain release.
Spill kits consisting of the appropriate materials, as specified by Millennium, will be required in all
heavy construction equipment associated with this project. At a minimum, small vehicles used to
transport Millennium and Contractor personnel will be required to contain absorbent pads. General
equipment that the contractor will use for spill containment and cleanup includes:
absorbents including pillows, socks, and wipe sheets for containment and pick up of spilled
liquids
commercially available spill kits (or the functional equivalent thereof) that are self-contained
and prepackaged with a large variety of sorbents for both small to large spills
structures such as gutters, culverts, and dikes for immediate spill containment, where
available and appropriate
shovels, backhoes, etc, for excavating contaminated materials
sumps and collection systems
drums, barrels, and temporary storage bags to clean up and transport contaminated materials
Millennium personnel (e.g., EI) will complete a Spill Report Form (refer to Attachment 1).
VIII.
SPILL NOTIFICATION
Spills will be reported immediately to Millenniums EI, who will then notify the Columbia Gas
Transmission Corporation (Columbia 1) Monitoring Center. Columbia will contact the appropriate
Federal, state and local agencies, if the spills are of a reportable quantity.
Attachment 2 lists the primary telephone numbers for such notifications.
Columbia, a subsidiary of NiSource (one of Millenniums owners), currently provides operational services to
Millennium and will operate the Project facilities on an integrated basis with Millenniums existing facilities
and in accordance with Columbias own operating procedures.
ATTACHMENT 1
Weather Conditions:
Parcel No.:
Town:
Milepost/Station No.:
Material Spilled:
Quantity Spilled:
10 gallons or less:
A1-1
Has spill cleanup begun? If so, what methods are being or will be used?
A1-2
ATTACHMENT 2
NOTIFICATIONS
SPILL RESPONSE REPORTING
PRIMARY EMERGENCY CONTACTS
Contact
Telephone
(800) 835-7191
(800) 457-7362
(518) 457-7362
(800) 424-8802
Telephone
(845) 615-0400
(911 within local area)
A2-1
ATTACHMENT B
TYPICAL FIGURES
B-1
SPOIL SIDE
WORKING SIDE
<.9
I~
UJ
LLJ
LLJ
LLJ
<.9
Cl
Cl
25 FT. TEMPORARY
CWA
75 FT. CWA
SPOIL SIDE
L.L
L.L
UJ
UJ
Cl
<.9
LLI
<.9
Cl
UJ
25 FT. TEMPORARY
CWA
25 FT. NEW
PERMANENT ROW
50 FT.
EXISTING PERMANENT ROW
75 FT.CWA
I...
~I
NOT TO SCALE
TYPICAL UPLAND
CONSTRUCTION
WORK AREA
FIGURE 2
D
CONSTRUCTION GATE POST -
.....
BRACE
DETAIL "A"
GATE 25 FL MIN.
I~
i-'OI-------
--------..t1O>II
EXISTING \
FENCE
----R-----v------IJ---
NOTES:
MIl'LENNIUM
p.tl P EII N EBM
TEMPORARY
CONSTRUCTION
GATE
NOT TO SCALE
FIGURE 3
TOPSOIL
PILE
SUBSOIL MAY BE SPREAD ON Tl1E
WORKING SIDE AS AN ALTERNATIVE
SUBSOIL
PILE
,------:::J'----------
STRIPPED
-~-------,
AREA
NOTE 2
\--
WORKING SIDE
PROPOSED
PIPELINE
EXISTING ~
AREA
TOPSOIL
i
I
'-~==
EXISTING
PIPELINE
A
PIPELlNE~
RESTORED
NOTES:
NNIUM
PEL IN
ESM
TYPICAL TOPSOIL
CONSERVATION IN
RESIDENTIAL AREAS
FIGURE 4
SLOPE
NOTE 1
< 5%
5-15%
15-30%
>30+ %
SPACING
RESTORED
GRADE
NONE
300 FEET
200 FEET
100 FEET
COMPACTED
FILL
MIN. 4:1 WHERE
VEHICLES CROSS
2MIN. TAPPROX.
~1
INTERCEPTOR SPACING
BACKFILLED TRENCH -
..
EDGE OF CLEARED /
GRADED AREA
SEDIMENT FILTER ----,
DEVICE AS
NECESSARY (NOTE 3)
NOTES:
ENNIUM
PEL IN ESM
ENVIRONMENTAL CONSTRUCTION STANDARDS
PERMANENT
INTERCEPTOR
DIVERSIONS
NOT TO SCALE
FIGURE 5
(PAGE 1 OF 3)
SILT FENCE
SPARSELY
VEGETATED
AREA
,
ROCK APRON
NOTE:
1. SIL T FENCE REMOVED WHEN
VEGETAnON ESTNlUSHED.
~ ~ ~---~----~---i
N
s"
/
"
o
PIPELINE
FIGURE 5
PERMANEN T
INTERCEP TOR DIVERSIONS
OUTLE T DESIGNS
(PAGE 2 OF 3)
-c
/
L :E;.
N:.:.;
V I:RO
:.:::.:.;
N:::::
ME::,:
N..:.,:
T AL
.::;...::
C.::;
ON
.:..::
5..:.,:
TR:.::::U.::.,:
CT..:;:
IO::.:.N...::,
5..:.,:TAN
..::..::::.:DAR.::..::D::..:::5~
...L
..J
COMPACTED FILL
POSITIVE DRPJNAGE TO
EXISTING VEGETATION
OR
POSITIVE DRPJN AGE
TO SILT FENCE
SPACING DETERMINED
BY DEGREE OF SLOPE
NOTE: STRAW BPJLES MAY BE USED
AT VEHICLE ACCESS POINTS.
N
~
if,
eo
o
o
a,
W
~
i>
!, h~-~---~-I
~
s
/
I'il ! L L = lJ I l l! lJ I'i)
PI PELI.N E
u
/
INTERCEPTOR DIVERSIONS
DURING CONS TRUC TION
FIGURE 5
(PAGE 3 OF 3)
I'
8'-0" MAXIMUM
POST SPACING
'I
SILT FENCE
:::;;
:::>
:::;;
'"
'"
N
GR.ADE
/ /,.=;>"/ /
:::;;
:::>
:::;;
'",
'":;,.
4"
BURlED FENCE
SIDE VIEW
:::;;
:::>
:::;;
'"
a
-
4"
4-6"
NOTES:
1. SILT FENCES ARE CONSTRUCTED FROM SYNTHETIC MESH MATERI AL DESIGNED TO RETAJN SILT WHILE
ALLOWING WATER TO PASS THROUGH. (AMOCO CONSTRUCTION FABRIC 1380 SILT STOP OR APPRO VED EQUAL ).
;;;
s.
co
o
o
m
W
i>
jj l---------------~-------------~--------I
",
o
w
o
"
~
/
N
s
~
-o
/
FIGURE 6
WOOD STAKES
1-1/2" X 1-1/ 2" X 5 FT .
(EMBED 1-1/2 FT. TO 2 FT.l
/>NGLE FIRST STAKE TOWARD
PREVIOUSLY LPJD BALE
HAY OR STRAW BALES
EMBED BALES IN
EAR TH 4 IN. MIN.
SIL T FENCE
WOOD STAKE
STRAW BALE
STRAW/HAY BALES
&SILT FENCE
, r-----:~--__r----~--I
-o
"o
g
/
N
a
~
PIPEL I NE
FIGURE 7
-c
/
L..:E
:;.:N..:.;
VI:..:..:
RO:..:..:
N;;;:ME:;.;N.;.;.
TA;:..L...:
C~ON...:S.;.;.TR:..:.UC:...;T.:..:IO.:..;.N...:S.;.;.TAN.:..;;D:.:..A:..:..:
RD:..::
S...l-
....l....
--l
75 FT. MIN
NOTES:
2.
3.
4.
5,
6.
ENNI
P E II N ESM
ENVIRONMENTAL CONSTRUCTION STANDARDS
TEMPORARY ROAD
ENTRANCE
ROCK PADS
FIGURE 8
15' MIN.
I'
,
,
:Z -'
w
.,.,e-
,
~~
DITCH LINE
,
,
~~
x .,
,
~~
,
- x - - x--+-x-- x -
~~
~~
""'-"
~~
~~
:> >
-c
~~
x --
x-
~-~~~~
-~
~4 ~ ~.::iLl~4 ~ .~~~
. LI
--- -----
- -
- -
~ -
- -
!J ~ - ~ -' - ' - -
-4- .
I,
- -
-4
'
'------+4-
A2I LI
.1
N.T.S.
a
a
Q
co
a
a
'T
;<'
NOTES'
1. STONE SIZE WILL BE AASHTO NUMBER 1COMSE AGGREGATE
OR EQUIVALENT. (4 INCH DIAMETER MINIMUM.l
2. ROCK PAD WILL BE AT LEAST 6 INCHES THICK.
3. THE ROAD ENTRANCE WILL HAVE A GEOTE XTILE FABRIC
BENEATH THE ROCK PAD.
4. IF ROCK PAD BECOMES COVERED WITH MUD SO AS TO
BECOME INEFFECTI VE, ADDITIONAL STONE WILL BE ADDED.
5. ALL STONE AND FABRIC MUST BE REMOVED DURING ROW
RESTORATION.
6 REMOVE TOPSOIL PRIOR TO INSTALLATION IN AGRICULTURAL LAND.
:;, I-----::~--~----~--I
-c
oi
.2'
:;
N
"
7
a
E
-o
PIPELINE
GRAVEL/ ROC K
TEMPORARY DRIVEW AY
FROM PUBLIC ROADS
FIGURE 9
I
I
I
I
I
T......_...... ,~
......
-,
~~~\Px
*:
I
- - - SPOIL PILE
I
I
I
I
!
I
I
:r:--~-
CULVERT PIPE
(AS NECESSARY
FOR DRAINAGE)
I....
Ct- ROAD
NOT TO SCALE
ENNIUM
P E II N t,
TYPICAL EROSION
CONTROL MEASURES
AT ROAD CROSSINGS
FIGURE 10
HARD
TRENCH PLUG
D
d
'
. ..,
""-
"-
"0
Cl
SOF T
TRENCH PLUG
..
n
N
eo
a
a
'i1"
SLOPE
SPACING
< 5/.
5-15/.
15-30/.
) 30'/'
NONE
300 FEET
200 FEET
100 FEET
u,
NOTES:
1. TEMPORAR Y TRENCH PLUGS MAY BE USED IN CONJUNCTION WITH INTERCEPTOR DIVERSIONS TO PREVENT
WATER FROM OVERFLOWING INTO SENSITIVE RESOURCE ARE AS.
2. DIVERT TRENCH OVERFLOW TO A WELL-VEGETATED OFF-R.O.W. LOCATION OR INSTALL APPROPRIATE
ENERGY DISSIPATING DEVICE.
3. 00 NOT USE TOPSOIL FOR INSTALLING TEMPORAR Y SOFT PLUGS.
,,
/
'"
o
~
TEMPORARY
TRENCH BREAKERS
FIGURE 11
-o
/
"
~ L.:E:.;.;N..:.;
V I..:.;
R O~NM
=E;;.;,
NT,;,.:.A::..
L ..:,
CO.:.;,N;.:,
ST,;,.:.R..:.UC:..;,T..:,I
O..:.
N ..:,
S,;,.:.TA;;.;;
ND:.;,.A:.;,:RD:.:,
S..l-
....l-
...J
BOTTOM
OF DITCH
S/lNDBAGS OR FOAM
PIPELINE
SPACING DETERMINED
BY DEGREE OF SLOPE
PROFILE
N.T.S.
RES TORED
GRADE
12" MIN.
S/lNDBAGS OR FOAM
v
PIPELINE
eo
o
o
't'"
'"
W
..,
N
.<>
/
N
s
V
PIPELI NE
FIGURE 12
PERMANENT
TRE NCH BREAKERS
(PAGE 10F 2)
-o
/
s:
~ L..:E:::N~
VI:.:..:
R O:.:..:
N:.::.::ME:.:..:.
N T.:..:.A:::..L...:::C.:::,ON:..::.
S.:..:.TR:.:::.
UC::.,:T,:::
IO.:..:.N...:::S.:..:.
T A.::..:
ND~AR:..::D:,,::S...L.-
--I-
...J
,-,---------"
'\
~~, ~--,
"--)\
---
TRENCH
BREN<ERS
00
o
o
PIPELINE
m
W
i>
c l-
-.-
,-
----j
..
'>
,g'
/
N
<0
~
FIGURE 12
TRENCHLINE BARRIERS
AND BREAKERS
(PAGE 2 OF 2)
-o
/
~
~ L...:E::..:N..::
VI~
R O:.:..:.NM:::.::E:.:..:.NT.:..:..A::...
L ..:;.
CO::.:.N:.:::.
S.:..:..TR~UC:.:..:.T.::::IO.:..:..N..:;.
S.:..:..TA::;ND::.:..
A::.::
RD:..:;:
S..L-
....l....
..J
-,
-,
,,
-,
PUMP
DISCHARGE
HOSE
, -,
-,
16'
'
-,
-,
-,
,
I
/ I
,,,
I
I
I
I
I
, - -
METAL HOSE
FITTING INSIDE
BAG OPENING
I
.....
,I
, I
'I
\
'- - - -
,
1
- U ------'
I
I
\
-,
-- - -
SECURED WITH
CLAMP OR WIRE
"'g
co
o
o
cD
't-
i!'
NOTES:
1. INSTALL AND OPERATE IN ACCORDANCE WITH MANUFACTURER'S SPECIFICATIONS.
2. GEOTEXTILE FILTER BAG LOCATION SHALL BE FLAGGED SO THAT BAG CAN BE REMOVED.
3. SEDIMENT FROM FILTER BAG MUST BE DISPOSED OF IN COMPANY APPROVED UPLAND.
4. NO WOVEN -F.ABRIC BAGS WILL BE USED.
.,
-o
.,
~
;;
SEDIMENT TRAP
GEOTEX TILE FILTER BAG
a
~
-o
/
~
FIGURE 13
(PAGE 10F 4)
PORTN3LE
PUMP
NOTE:
FILTER
USE FLOATATION
TO PREVENT WITHDRAWAL
OF DIRT & SEDIMENT
PORTN3LE
PUMP
NOTE:
FILTER
USE FLOATATION
TO PREVENT WITHDRAW AL
OF DIRT & SEDIMENT
SEDIMENT TRAP
FIGURE 13
(PAGE 2 OF 4)
STEP 1
ON LEVEL LAND, DIG A SUMP DEPENDING ON ACTUAL
FLOW RATES APPROXIMATELY 200 SQ. FT., WHICH IS
2" DEEP AT THE CENTER. PLACE A LAYER OF STRAW
BALES AS SHOWN, TO COMPLETELY SURROUND THE
SUMP.
STEP 2
INSTALL SILT FENCE ALL AROUND THE STRAW BALES,
(IF LAND IS LEVEll DIG IN SILT FENCE 6".
STEP 3
INSTALL AN OUTER LAYER OF BALES AROUND THE SILT
FENCE, AND SECURE EACH BALE USING
WOODEN STAKE. COVER THE ENTIRE SUMP WITH
HI-VELOCITY EROSION CONTROL FABRIC (CURLEX
OR EQUAL) BEFORE PUMPING THE WATER INTO THE
FACILITY.
NOTE: PUMP INTAKE HOSE MUST NOT BE ALLOWED TO REST ON THE TRENCH BOT TOM THROUGHOUT
DEWATERING. PROVISIONS MUST BE MADE TO ELEVATE THE INLET HOSE TO AT LEAST ONE
FOO T ABOVE THE TRENCH BOTTOM UNTIL BOTTOM DEWATERING IS NECESSAR Y.
EROSION CONTROL DURING PIPELINE DITCH,
AND HYDROSTATIC TEST DE WATERING
FOR LEVEL AREAS WITH SPARSE VEGETATION
!, r--::~----r-----~-~
..
',
~
SEDIMENT TRAP
FIGURE 13
(PAGE 3 OF 4)
"
~
E
-c
/
--'
-'
DISCHARGE PIPE
ENERGY
DISSIPATOR
DEVICE
PLAN VIE W
INO T TO SC.'J.EJ
SILT FENCE
GEOTEXTILE FILTER FABRIC
OPTION 2
OPTION 1
NOTES:
1. INSTALL A STRAW BALE DEWATERING STRUCTURE WHEREVER IT IS NECESSARY AND AS DIRECTED BY THE
ENGINEER TO PREVENT THE FLOW OF HEAVILY SILT LADEN WATER INTO WATER BODIES OR WETLANDS.
ALL DEWATERING ACTIVITIES SHALL BE CONDUCTED IN ACCORDANCE WITH PERMIT CONDITIONS.
2. DISCHARGE SITE SHOULD BE WELL VEGETATED AND LOCATED AT LEAST 100FT . FROM AN Y WATERCOURSE.
THE TOPOGRAPHY OF THE SITE SHOULD BE SUCH THAT WATER WILL FLOW INTO THE DEWATERING STRUCTURE
AND AWAY FROM AN Y WORK AREAS. THE AREA DOWNSLOPE FROM THE WATERING SITE MUST BE REASONABLY
LEVEL OR STABILIZED BY VEGETATION OR OTHER MEANS TO ALLOW THE FILTERED WATER TO CONTINUE AS
SHEET FLOW.
3. DIRECT THE PUMPED WATER ONTO A STABLE SPILL PAD CONSTRUCTED OF STRAW BALES, ROCK FILL,
WEIGHTED TIMBERS, OR A WOVEN GEOTEXTILE STAKED TO THE GROUND SURFACE.
4. DISCH ARGE RATES SHOULD BE SUCH THAT THE STRUCTURE WILL NOT OVERFLOW.
5. DISCHARGE WATER TO BE FORCED INTO SHEET FLOW IMMEDIATELY BEYOND THE SPILL PAD USING A
COMBINATION OF STRAW BALES AND THE NATURAL TOPOGRAPH Y. RECESS STRAW BALES A MINIMUM OF 4 in.
DRIVE TWO STAKES OR REBAR INTO EACH BALE TO ANCHOR THEM IN PLACE.
6. MANUFACTURED FILTER BAGS ARE A SUITABLE ALTERNATIVE TO STRAW BALE STRUCTURES FOR TRENCH
DEWATERING.
7. ENERGY DISSIPATOR DEVICE SHALL BE ANCHORED BY CONTRAC TOR.
! r--::~--~----~--I
,
..,
~
/
"
~
-o
/
~ L..:E~N.;,;
V I:..:..:
R O:..:..:
N;;:.;ME:..:..:
N .:.;.
T A=.L..;:.
C.:.;.ON..;:.
S.:.;.TR;;;.UC:....:T.:.,:I
O:..:...N..;:.
S.;.;.TAN.:..;;D:.:..
A::..;;RD:..:
S...l...-
SEDIMENT TRAP
FIGURE 13
(P AGE 4 OF 4)
....l....
-1
STRAW
MATTINGINETTING f ROM
WATER'S EDGE TO 5'
BEHIND TOP Of BANK
MULC~
15' H
~
~- RE ST O R ED
GRADE
PIPELINE
PROFILE
(NOT TO SCAlE)
- ~-- - - -I - ~- - -- ~ -~-~
1""\
INTERIOR STAPLES
1PER SQ. YARD
r""\
,..."
jA
"
NOTES'
1. RIGHT-or-WAY TO BE MULCHED PRIOR TO THE INSTALLATION Of MATTING/ NET TING.
2. MATTING/NETTING SHALL BE RUN HORIZONTAL AND PARALLEL TO THE GROUND CONTOUR.
3. STAPLES SHALL BE IO"-LONG, STANDARD MATTING/ NETTING STAPLES.
g r------=~---r--------r-~
,.
:;
N
o
~
I'i I J !. '!.
=I J II]
:I.Y I'll
PIPELINE
BIODEGRADABLE
EROSION CONTROL
BL ANKET
FIGURE 14
/
~
l-'E:.;.;
N..:.;
V I..:.;
RO..:.;
N..:.;ME:.;.;N..:.;
T AL.;:....:
C,,-ON..:.;S..:.;TR..:.;U,,C T.;.;.IO:.;.;N..:.;S:.;.;
T.:...:AN.;:;
D.:...:AR.;:;D.::..
S .L.-
---l..
--l
,P1~i~f~~~;~",
l~
5 FT.ht
TOPSOIL
REMOVED
25 FT.
<t
50 FT.
25 FT.
TOPSOIL
STORAGE
AREA
PROPOSED
(1YP.) ,
PIPELINE
<t EXISTING
I"
25 FT. liP.) ~ PIPELINE
,
,
I 50 FT. EXISTING PERMANENT R.OW.
TEMPORARY
PERMANENT
ROW
ROW
15 FT.
EXCESS
SPOIL
STORAGE
NATURAL GROUND
<t
25 FT.
TOPSOIL
STORAGE
AREA
PROPOSED
PIPELINE
50 FT.
PERMANENT
ROW
25 FT.
TEMPORARY
ROW
100 FT. CWA
NOTE:
1. DEPTH OF COVER IN CROPLAND TO
BE 4 FT. OR 1 FT. BELOW EXISTING
FIELD TILE,WHICH EVER IS GREATER.
(FIGURE 17)
2. OTHER CONFIGURATIONS OF TOPSOIL AND
SUBSOIL ARE ACCEPTABLE PROVIDED THEY
ARE KEPT SEPARATE.
3. UP TO 16 INCHES OF TOPSOIL REMOVED.
4. TOPSOIL AND SUBSOIL PILES WILL BE ADEQUATELY
PROTECTED FROM EROSION AND SEDIMENTATION
BY USE OF SEDIMENT FILTER DEVICES OR STRAW
MULCH.
5. A 1 IN. THICK STRAW VISUAL BARRIER MUST BE
INSTALLED PRIOR TO SUBSOIL SPOILING OVER TOPSOIL.
ENNIUM
P E II N ESM
TYPICAL
TOPSOIL
CONSERVATION
IN AGRICULTURAL LAND
NOT TO SCALE
FIGURE 15
METHOD 1
METHOD 2
NOTES:
NOT TO SCALE
ENNIUM
P EII N ESM
FIELD TILE
REPLACEMENT
METHODS
FIGURE 16
(PAGE 1 OF 2)
NATURAL GROUND
3'-0" MIN.
EACH SIDE
INSERT INTERNAL COUPLER
BETWEEN EXISTING TILE AND
NEW TILE AT BOTH ENDS.
PIPELINE
SANDBAG SUPPORTS
OR BAGS OF SACKRETE
BACK FILL TO BE TAMPED IN 6" LAYERS
BENEATH AND AROUND SUPORT PIPE
WHEN SOIL IS NOT OVER SATURATED.
DRAINAGE TILE
SUPPORT SIZE
3 TO 5
6" PIPE
6"
8" PIPE
7" TO 8"
10" PIPE
9" TO 10"
12" PIPE
12"
W12X1 4
IS" TO 18"
W16X26
OVER 18"
W18X46
11
11
SECTION A-A
FOR UP TO
10" DRAIN TILE
TILE TO BE
WIRED TO
SUPPORT BEAM
EVERY 6 FEET.
DRAINAGE TILE
SUPPORT
BEAM
NOTES:
1. SUPPORT PIPE TO BE OF 0.250" WALL THICKNESS OR HEAVIER.
WHERE THE SUPPORT PIPE IS OVER 30' IN LENGTH OR IN SATURATED
AREAS, PERFORATIONS TO THE SUPPORT PIPE MAY BE REQUESTED.
2. REPLACEMENT TILE TO BE HEAVY DUTY HIGHWAY GRADE
PERFORATED PLASTIC DRAIN TUBING (ADS TYPE N-12!.
3. IF THE TRENCH WIDTH EXCEEDS 10' CHANNEL IRON STIFFENERS
SHALL BE WELDED TO THE SUPPORT PIPE OR SUPPORT BEAM.
SECTION A-A
FOR OVER
10" DRAIN TILE
! r-----=~---~----___r_-~
..,,
w
,g'
/
N
o
E
'11 I
~ ~
=I ~
)'11 l.!J
PI.P EL I NE
Ii i
FIGURE 16
FIELD TILE
REPLACEMENT METHODS
(PAGE 2 OF 2)
"
-c
/
~
<;.o LENVIRONMENTA
L CONSTRUCTION
STANDARDS
-'-_
_-'---'--'-....:........:.......l...-
---J
--'
TOPSOIL ~
4FT. MIN
COVER
PROPOSED
PIPELINE
TOPSOIL
0'/'IZZ:4oII--
LATERAL INTERCEPT
/
DRAIN TILE ~
1FT. MIN
VERTICAL
SEPARATION
4FT. MIN
COVER
PROPOSED
PIPELINE
NOTES:
NOT TO SCALE
ENNI M
P E II N ESM
TYPICAL
AGRICULTURAL
LAND
CROSS - SECTION
FIGURE 17
10 FT. MIN.
NOTE 2
PIPE TRENCH
SAND BAGS TO
CHANNEL STREAM
FLOW
TRENCHLINE BARRIER
SEDIMENT FILTER DEVICE
ROSSING
NOTE 1
SEDIMENT FILTER
DEVICE
K~~~
SCOUR PROTECTION
(MIN. ROCK SIZE
4 TO 6 INCHES)
50 FT. BUFFER
NOTES:
2. GRADE AND TRENCH SPOIL WILL BE STOCKPILED AT LEAST 10 FEET FROM THE WATER'S
EDGE, TOPOGRAPHY PERMITTING,
3, INSTALL FLUME PIPE AFTER BLASTING, BUT BEFORE TRENCHING.
4. USE SAND BAG OR SAND BAG AND PLASTIC SHEETING DIVERSION STRUCTURE, OR EQUIVALENT.
5. PROPERLY ALIGN FLUME PIPE,
6. DO NOT REMOVE FLUME PIPE DURING TRENCHING, PIPELAYING, OR BACKFILLING ACTIVITIES.
7. REMOVE ALL FLUME PIPES AND DAMS THAT ARE NOT ALSO PART OF THE EQUIPMENT BRIDGE
AFTER FINAL CLEANUP BUT BEFORE PERMANENT SEEDING,
NOT TO SCALE
ENNIUM
P EII N ESM
TYPICAL
STREAM CROSSING
DRY-DITCH
(FLUME)
FIGURE 18
10 FT, MIN.
NOTE 2
UPSTREAM DAM
(SAND BAGS)
G
U-
~
~
:::J
PUMP HOSE
SEDIMENT FILTER
DEVICE
50 FT. BUFFER
NOTES:
2. GRADE AND TRENCH SPOIL WILL BE STOCKPILED AT LEAST 10 FEET FROM THE WATER'S
EDGE, TOPOGRAPHY PERMITIING,
3. SET UP PUMP AND HOSE AS SHOWN, OR USE OTHER PRACTICAL ALTERNATIVES. PUMP
SHOULD HAVE TWICE THE PUMPING CAPACITY OF ANTICIPATED FLOW.
4. CONTRACTOR TO ENSURE A SUFFICIENT NUMBER OF ACTIVE AND BACKUP PUMPS TO MAINTAIN
THE CAPACrrY OF THE STREAMFLOW AT ALL TIMES DURING INSTALLATION.
5. ALL INTAKE HOSES WILL BE SCREENED,
6, DISMANTLE DOWNSTREAM DAM, THEN UPSTREAM DAM. KEEP PUMP RUNNING TO MAINTAIN
STREAM FLOW.
NOT TO SCALE
ENNIUM
P E II N ESM
TYPICAL
STREAM CROSSING
DRY-DITCH
(DAM AND PUMP)
FIGURE 19
10 FT. MIN.
NOTE 2
SEDIMENT FILTER
DEVICE
'"""'11--_
PIPE 1RENCH
TRENCHLINE BARRIER
CROSSING
NOTE 1
SCOUR PROTECTION
(MIN, ROCK SIZE 4
TO 6 INCHES)
....-~--
50 FT. BUFFER
NOTES:
ENNIUM
P E II N ESM
TYPICAL
STREAM CROSSING
WET-DITCH
FIGURE 20
10 FT, MIN,
NOTE 2
""'11I-----
SAND BAGS
~<E----
PIPE TRENCH
QPROPOSED
PIPELINE
TRENCHLINE BARRIER
SEDIMENT FILTER DEVICE
50 FT, BUFFER
NOTES:
ENNIUM
PEL IN ESM
TYPICAL
STREAM CROSSING
INTERMITIENT
STREAMS
FIGURE 21
4 TO 6 INCH DIAMElER
CRUSHED STONE
NOTES:
1.
NOT TO SCALE
ENNIUM
P E II N Es~
TEMPORARY
EQUIPMENT CROSSING
CULVERT AND STONE
FIGURE 22
3FT. MIN.
------j.oalI---7fE-_
~&IiI~;li:: r:
u..,,-
c~
&~
:::=:;=:=\:
\
\
- . EQUIPMENT PAD
(lYP, DIMENSIONS ARE
4FT, WIDE, 20 FT.
LONG, AND 8 IN. THICK)
NOTES 2 AND 3
STEEL
CULVERT
NOTE 1
NOTES:
NOT TO SCALE
ENNIUM
PEllNEsM
TEMPORARY
EQUIPMENT CROSSING
EQUIPMENT PADS
FIGURE 23
WETlAND
..J<.
.*..
.*..
..4c..
.*..
WORKING SIDE
~
.*..
.*..
.*..
t:>::
!,Q
PIPELINE
CENTERLINE
tL:
t:L:
t:L:
t:L:
---------------'----1----------
= PLANTED AREA
NOTES:
1. WHERE STUMPS HAVE BEEN REMOVED, WOODY VEGETATION ADAPTED TO WETLANDS WILL BE
ENNIUM
P E II N ESM
TYPICAL FORESTED
WETLAND PLANTING
FIGURE 25
-*-*-
u..J
-*-
-*-
-*-
-*-
-*-*-
-*-
-*-
-*-
-*-
t:L::
~
-*-
-*-
-*-
-*-
-*-
-*-
-*-
-*-
-*-
-*u..J
z:
:z:
tL:
<>:
::;:S3= dJ
<>:
dJ3=
00--
"""'0
~=
=~
o--~
:z:
~o-:z:
LU
LU
z: 5:
<>:
5: :z:
-ec
0
::;;;:=
C>
0-
= ::;;;:
ffit:L::
=
IO-::;:s
ffi~
---'
---'
L.L
-*-
-*-
..4t..
..4t..
..4t..
..4t..
-*-
-*-
-*-
-*-
-*-
tL:
~
-*-
-*-
-*-
-*-
-*-
-*-
.*-.
.*-.
.*-.
= HERBACEOUS PLANTS
=
~ =
NOTES:
NON-MAINTAINED AREA
SHRUB & HERBACEOUS PLANTS
15 FEET TALL MAY BE SELECTIVELY CUT AND REMOVED FROM THE ROW.
(SHRUB AND HERBACEOUS PLANTS)
4. STUMPS AND ROOTS WILL BE LEFT IN PLACE.
ENNIUM
PEL IN ESM
ROW MAINTENANCE
WETLANDS
NOT TO SCALE
FIGURE 26
-'
-'
l..L
NOTES:
TREE
NOT TO SCALE
ENNIUM
P E II N ESM
ROW MAINTENANCE
PERENNIAL STREAMS
FIGURE 27
I~
~I
= TREE
NOTES:
ENNIUM
P E II N ESM
ROW MAINTENANCE
ENVIRONMENTALLY
SENSITIVE AREAS
FIGURE 28
ATTACHMENT C
FEDERAL ENERGY REGULATORY COMMISSION
UPLAND EROSION CONTROL, RE-VEGETATION AND
MAINTENANCE PLAN
AND
WETLAND AND WATERBODY CONSTRUCTION AND
MITIGATION PROCEDURES
C-1
01/17/2003 VERSION
I.
APPLICABILITY .............................................
II.
2
2
2
4
4
4
5
5
5
5
5
IV.
INSTALLATION .............................................. 6
A.
APPROVED AREAS OF DISTURBANCE ........................ 6
B.
TOPSOIL SEGREGATION .................................. 7
C.
DRAIN TILES .......................................... 7
D.
IRRIGATION ........................................... 8
E.
ROAD CROSSINGS AND ACCESS POINTS ..................... 8
TEMPORARY EROSION CONTROL ............................ 8
F.
Temporary Slope Breakers ........................ 8
1.
Sediment Barriers ............................... 9
2.
Mulch .......................................... 10
3.
V.
RESTORATION ..............................................
CLEANUP .............................................
A.
B.
PERMANENT EROSION CONTROL DEVICES ...................
1.
Trench Breakers ................................
2.
Permanent Slope Breakers .......................
C.
SOIL COMPACTION MITIGATION ..........................
D.
REVEGETATION ........................................
1.
General ........................................
Soil Additives ................................
2.
Seeding Requirements ...........................
3.
11
11
12
12
13
13
14
14
14
14
VI.
16
16
16
17
01/17/2003 VERSION
APPLICABILITY
A.
2.
3.
01/17/2003 VERSION
II.
B.
ENVIRONMENTAL INSPECTION
1.
2.
3.
2.
3.
4.
01/17/2003 VERSION
5.
6.
7.
8.
9.
10.
11.
12.
13.
b.
c.
01/17/2003 VERSION
14.
15.
16.
B.
2.
2.
3.
Develop procedures for constructing through draintiled areas, maintaining irrigation systems during
construction, and repairing drain tiles and
irrigation systems after construction.
4
01/17/2003 VERSION
4.
C.
GRAZING DEFERMENT
Develop grazing deferment plans with willing landowners,
grazing permittees, and land management agencies to
minimize grazing disturbance of revegetation efforts.
D.
E.
DISPOSAL PLANNING
Determine methods and locations for the disposal of
construction debris (e.g., timber, slash, mats, garbage,
drilling fluids, excess rock, etc). Off-site disposal in
other than commercially operated disposal locations is
subject to compliance with all applicable survey,
landowner permission, and mitigation requirements.
F.
AGENCY COORDINATION
The project sponsor must coordinate with the appropriate
local, state, and Federal agencies as outlined in this
Plan and in the Certificate.
G.
1.
2.
01/17/2003 VERSION
IV.
INSTALLATION
A.
2.
b.
01/17/2003 VERSION
c.
TOPSOIL SEGREGATION
1.
C.
b.
residential areas;
c.
hayfields; and
d.
2.
3.
4.
5.
DRAIN TILES
1.
2.
01/17/2003 VERSION
D.
3.
4.
IRRIGATION
Maintain water flow in crop irrigation systems, unless
shutoff is coordinated with affected parties.
E.
F.
2.
01/17/2003 VERSION
b.
2.
Spacing (feet)
300
200
100
c.
d.
Sediment Barriers
a.
b.
01/17/2003 VERSION
c.
3.
Mulch
a.
b.
c.
(2)
d.
e.
10
01/17/2003 VERSION
V.
f.
g.
h.
RESTORATION
A.
CLEANUP
1.
2.
3.
01/17/2003 VERSION
B.
4.
5.
Grade the construction right-of-way to restore preconstruction contours and leave the soil in the
proper condition for planting.
6.
7.
Trench Breakers
a.
b.
c.
d.
01/17/2003 VERSION
2.
b.
C.
Spacing (feet)
300
200
100
c.
d.
01/17/2003 VERSION
2.
3.
D.
REVEGETATION
1.
2.
General
a.
b.
Soil Additives
Fertilize and add soil pH modifiers in accordance
with written recommendations obtained from the local
soil conservation authority, land management
agencies, or landowner. Incorporate recommended
soil pH modifier and fertilizer into the top 2
inches of soil as soon as possible after
application.
3.
Seeding Requirements
a.
01/17/2003 VERSION
b.
c.
d.
e.
f.
g.
Use seed
01/17/2003 VERSION
VI.
Signs;
B.
C.
D.
2.
3.
4.
16
01/17/2003 VERSION
B.
5.
6.
REPORTING
1.
2.
b.
acreage treated;
c.
d.
e.
17
01/17/2003 VERSION
01/17/2003 VERSION
I.
APPLICABILITY .............................................
II.
IV.
V.
5
5
6
6
6
6
7
7
8
10
11
11
12
12
13
14
VI.
14
14
16
16
17
19
19
20
21
22
22
22
22
23
01/17/2003 VERSION
APPLICABILITY
A.
2.
3.
01/17/2003 VERSION
B.
DEFINITIONS
1.
2.
II.
b.
c.
PRECONSTRUCTION FILING
A.
B.
2.
2.
3.
4.
IV.
A.
B.
PRECONSTRUCTION PLANNING
A.
b.
The
01/17/2003 VERSION
2.
c.
d.
e.
f.
b.
01/17/2003 VERSION
B.
c.
d.
AGENCY COORDINATION
The project sponsor must coordinate with the appropriate
local, state, and Federal agencies as outlined in these
Procedures and in the Certificate.
V.
WATERBODY CROSSINGS
A.
2.
3.
4.
01/17/2003 VERSION
B.
INSTALLATION
1.
2.
3.
a.
b.
b.
c.
d.
01/17/2003 VERSION
4.
5.
b.
c.
d.
e.
f.
b.
Equipment Bridges
a.
01/17/2003 VERSION
b.
6.
c.
d.
e.
f.
01/17/2003 VERSION
b.
(2)
(ii)
(iii)
(iv)
(v)
c.
Flume Crossing
The flume crossing method requires
implementation of the following steps:
(1)
(2)
(3)
(4)
(5)
d.
7.
(1)
(2)
(3)
b.
10
01/17/2003 VERSION
c.
8.
9.
a.
b.
c.
11
01/17/2003 VERSION
10.
11.
a.
b.
c.
Trench Dewatering
Dewater the trench (either on or off the
construction right-of-way) in a manner that does not
cause erosion and does not result in heavily siltladen water flowing into any waterbody. Remove the
dewatering structures as soon as possible after the
completion of dewatering activities.
12
01/17/2003 VERSION
C.
RESTORATION
1.
2.
3.
4.
5.
6.
7.
8.
13
01/17/2003 VERSION
D.
VI.
POST-CONSTRUCTION MAINTENANCE
1.
2.
WETLAND CROSSINGS
A.
GENERAL
1.
b.
c.
d.
14
01/17/2003 VERSION
2.
3.
4.
5.
spoil control;
b.
equipment bridges;
c.
d.
15
01/17/2003 VERSION
6.
B.
e.
f.
INSTALLATION
1.
b.
c.
d.
16
01/17/2003 VERSION
2.
Crossing Procedures
a.
b.
c.
d.
e.
f.
17
01/17/2003 VERSION
g.
h.
i.
j.
k.
l.
m.
18
01/17/2003 VERSION
3.
4.
a.
b.
c.
Trench Dewatering
Dewater the trench (either on or off the
construction right-of-way) in a manner that does not
cause erosion and does not result in heavily siltladen water flowing into any wetland. Remove the
dewatering structures as soon as possible after the
completion of dewatering activities.
19
01/17/2003 VERSION
C.
RESTORATION
1.
2.
3.
4.
5.
6.
20
01/17/2003 VERSION
7.
D.
POST-CONSTRUCTION MAINTENANCE
1.
2.
3.
4.
21
01/17/2003 VERSION
B.
C.
2.
3.
GENERAL
1.
2.
3.
2.
3.
01/17/2003 VERSION
4.
D.
2.
23
01/17/2003 VERSION