Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Performance Budgeting
CONTENTS
INDUSTRY OVERVIEW
COMPANY ANLYSIS
1. BACKGROUND
2. CORPORATE VISION
3. CORPORATE MISSION
4. CORPORATE OBJECTIVES
5. CORPORATE CORE VALUES
6. PROJECTS OF NTPC
7. SERVICES OF NTPC
8. GROUP COMPANIES
9. FINANCIAL PERFORMANCE
10. OPERATIONAL PERFORMANCE
11. STRATEGIES ADOPTED BY NTPC
PROJECT
1.
2.
3.
4.
5.
6.
7.
8.
CONCEPT
OBJECTIVES
SCOPE OF CAPITAL BUGETING
FORMULATION AND APPROVAL
REVIEW AND MONITORING
COMPILATION OF ANNUAL PLAN
FINANCIAL ANLYSIS OF SELECTED PROJECTS
ANNUAL PLAN ANALYSIS
Performance Budgeting
Industry overview
The Indian electricity sector has grown manifold over last 50 years and India
is the third largest producer of power in Asia today.
Initially the growth in the power sector was achieved through state
electricity board, which was constituted by the state government. About 58%
of the generation capacity and the bulk of the distribution take place through
various SEB system. The efforts of the SEBs were further supplemented by
the advent of central sector power generating companies (viz. NTPC Limited
and National Hydroelectric power corporation Limited) in the public sector.
Contribution of central sector has been growing steadily since MID 70s.
Despite the massive growth in power generation, India is still facing an acute
power shortage.
Hitherto, development of the Electricity sector has been primarily the
responsibility of the state and central government, with relatively small
contribution from the private sector. As on March 2006, Indias power
system had an installed generation capacity of 124,287 MW. During the year
2005-06 the total power generated in the country in the country was 617.38
billion. As far as the ownership of the power generating capacities are
concerned, the state government owned generating utilities accounted for
55% of the capacities, while the central government owned power utilities
accounted of approximately 32% and private players accounted for
approximately 13%. The strategies adopted in the short term to meet the
demand of electricity include acquiring capability to achieve inter regional
exchange of electricity, minimizing transmission and other distribution
losses and improving the capacity utilization of existing operating plants. In
this background, GOI has resolved to mobilize additional resources to help
bridge the gap in supply by encouraging greater participation by the private
sector in electricity generation and distribution field. To give further
encouragement to attracting investment in the power sector, the electricity
act 2003 has been enacted by Govt. in India.
Performance Budgeting
NTPC LTD
BACKGOUND
NTPC limited was incorporated on 7th November 1975 in the central sector as a thermal
power generating company, with the objective of planning, promoting and organizing an
integrated development of thermal power in the country. NTPC has since diversified its
activities and is now going for hydropower, coal mining, nuclear power, oil exploration,
wind power and other non-conventional sources of energy. Within the span of 28 years,
NTPC has emerged as a leading national power generating facilities in all the major
regions of the country.
NTPCs core business is1. Engineering, construction and operation of power generating plants
2. Provides consultancy to power utilities in India and abroad.
With a total installed capacity of 227404 MW, NTPC during the year 2006-2007
generated 188.67 Bus of electricity resulting in an increase of 10.46% over the previous
years generation. With 20.18% of total installed capacity in the country NTPC has
contributed 28.50% of all India thermal Generation. During the year 2006-2007 NTPC
coal station achieved a PLF of 89.43%.
NTPC was among the first public sector enterprises to enter into memorandum of
understanding (MOU) with the government in 1987-88. NTPC has been placed under the
EXCELLENT CATEGORY every year since the MOU system became operative. In
recognition of its excellent performance and vast potential, Government of India has
identified NTPC as one of the jewels of Public sector Navratnas- a potential global
giant.
NTPC Ltd is marching ahead from strength to strength. During the year 2005-06, its
stations performed at the highest ever plant load factor of 87.54% and generated 170.88
billion units of electricity which was 7.40% higher than the previous years generation of
159.11 billion units and accounted for almost 28% of power generated units in India.
Performance Budgeting
VISION
A WORLD CLASS INTEGRATED POWER MAJOR,
POWERING INDIAS GROWTH,
WITH INCREASING GLOBAL PRESENCE
CORE VALUES
(B-COMIT)
BUSINESS ETHICS
CUSTOMER FOCUS
ORGANISATIONAL & PROFESSIONAL PRIDE
MUTUAL RESPECT & TRUST
INNOVATION & SPEED
TOTAL QUALITY FOR EXCELLENCE
CORPORATE MISSION
DEVELOP AND PROVISE RELIABLE POWER, RELATED PRODUCTS
AND SERVICES AT COMPETITIVE PRICES, INTEGRATING MULTIPLE
ENERGY SOURCES WITH INNOVATIVE AND ECO-FRIENDLY
TECHNOLOGIES AND CONTRIBUTE TO SOCIETY
Performance Budgeting
CORPORATE OBJECTIVES
To realize the vision and mission, different key corporate objectives have been identified.
These objectives would provide the link between the defined mission and the functional
strategies:
Business portfolio growth
Customer focus
Agile Corporation
Performance Budgeting
Performance leadership
Performance Budgeting
Completed projects
S.No
1
2
3
4
5
6
7
8
Singrauli
Korba
Ramagundam
Farakka
Vindhyanchal-I
Rihand
Talcher-I
Kahalgaon
2000
2100
2100
1600
1260
1000
1000
840
Uttar Pradesh
Chhattisgarh
Andhra Pradesh
West Bengal
Madhya Pradesh
Uttar pradesh
Orissa
Bihar
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
9
10
11
12
13
14
15
16
NCTPP, Dadri
Talcher (TRS)
Unchahar-I
Dadri Gas
Auriya
Jhanor-Gandhar
Kawas
Anta
840
460
420
817
652
648
645
413
Uttar pradesh
Orissa
Uttar pradesh
Uttar pradesh
Uttar pradesh
Gujarat
Gujarat
Rajasthan
Coal
Coal
Coal
Gas
Gas
Gas
Gas
Gas
17
18
19
20
21
22
23
Kayamkulam
Tanda
Vindhyanchal-II
Unchahar-II
Faridabad
Simhadri - I
Talcher-II
350
440
1000
420
430
1000
2000
Kerala
Uttar pradesh
Madhya pradesh
Uttar pradesh
Haryana
Andhra pradesh
Orissa
Naphtha
Coal
Coal
Coal
Gas
Coal
Coal
Performance Budgeting
Capacity
(MW)
Location
(State)
Primary
fuel
24
Vindhyanchal III
1000
Madhya Pradesh
Coal
25
Unchahar III
210
Uttar Pradesh
coal
ONGOING PROJECTS
S.NO
Name of projects
Sipat-II
1000
Sipat-I
1980
1980
Barh
1980
1980
Korba-III
500
500
500
600
600
Farakka-III
500
500
10
NCTPP-II, Dadri
980
980
11
Simhadri
1000
1000
12
Tapovan Vishnugarh
520
Sub-total
11860
Performance Budgeting
Capacity By
march 2007-12
20007
500
800
500
11360
Performance Budgeting
10
FINANCIAL PERFORMANCE
The net worth of the company at the end of fiscal year 2006 was Rs. 449,587
million an increase of Rs. 31,824 million over the previous year mainly due
to retained earnings.
The gross revenue for the year 2005-06 were Rs. 287 billion and grew by
more than 15% over the previous year. The reported profit after tax for the
year was almost the same as in the previous year at Rs. 58 billion. However,
on an adjusted basis the profits grew by almost 18%.
OPERATIONAL PERFORMANCE
With a total installed capacity of 24249 MW, NTPC during the year 2005-06
generated 170.88 Bus of electricity resulting in an increase pf 7.40% over
the previous years generation. With 19.51% of total installed capacity in the
country NTPC has contributed 27.68% of all India Thermal Generation.
STRATEGIES
While maintaining its thrust on getting maximum out of the existing
capacities NTPC is also giving utmost priority to its future. The strategy is to
increase its already substantial (nearly 20%) market share in the Indian
power sector through rapid capacity expansion. NTPC is planning to be a 51
GW company by the year 2012 and 70 GW plus company by 2017.
Currently NTPC LTD is a 26 GW company.
MULTI PRONGED GROWTH APPROACH
NTPC is adopting a multipronged strategy for capacity addition through
green fields projects, expansion of existing stations, acquitions and takeover
and joint ventures and subsidiary to accomplish its growth plans.
Performance Budgeting
11
GROUP COMPANIES
SUBSIDIARIES
Name of the company
Proportion of ownership
interest (%)
100
100
100
100
51% to 74%
JOINT VENTURE
NTPC has envisaged joint venture as growth engines for future, which will help NTPC in
its foray into setting up of power plants and related areas like consulting, power trading
etc. the short descriptions of existing JVs are as follows:
NTPC Tamil Nadu Energy Company LtdA 50:50 JV between Tamil Nadu Electricity board and NTPC was formed
to establish and operate a 1000 MW thermal power project in Tamil Nadu
Utility Powertech Ltd (UPL)This 50:50 JV of NTPC and of NTPC and Reliance Energy takes up
projects in construction, erection and supervision of power sector and other sector
in India and abroad.
NTPC SAIL Power Co. Private Ltd (50% share)This JV owns and operates the captive power plants of Durgapur and
Rourkela and Bhilai steel plants of SAIL.
Performance Budgeting
12
Ratnagiri Gas and Power Private ltd(50%)Ratnagiri Gas and Power Ltd has been formed as joint venture between
NTPC, GAIL, MSEB holding company Ltd. And Indian Financial Institutions
with NTPC having a stake of 28.33% for taking over and operating erstwhile
Dabhol Power Project. The company has invested Rs. 5000 million as equity.
PERFORMANCE BUDGETING
Performance budgeting presents the budget in terms of functions programme and corelation the physical and financial aspects of the individual schemes in order to facilitate
a better understanding and fuller review of the budgetary allocations and the department
working. It provides a review of the relationship between the estimated input and
expected output acts as a tool for management and serves as an instrument for evaluation
of performance.
The success of budgeting process depends on the following essential elements:
Reasonable flexibility:
The budget must have a certain degree of flexibility in order to adapt to
varying situations. It must be neither too rigid nor too flexible, as too much
flexibility will weaken the cost control and he budget will become inoperative.
Similarly too much rigidity in not permitting reasonable deviations will create
problems and restrictions in the implementation of the budget.
Performance Budgeting
13
To bring about cost control mechanisms whereby the cost overruns and other
contributory factors for deviations and cost escalations are contained and checked.
To provide the basis for central plan allocation and budgetary support by GOI.
SOURCE DOCUMENTS
The corporate plan and master network (L-1) schedules for the projects, which are
finalized in conjunction with national plan, are the key factors for formulation of the
budget and annual plan.
The L-2 network indicates the major areas constituting each work, the physical
target and monthly phasing of schedules. The first step in the preparation of budgets is
drawing up of L-2 networks or updating of L-2 networks for works within the timeframe
of the master network schedules and should be drawn up by the field managers with due
regard to firm contract schedules. The field managers are also responsible for drawing up
Performance Budgeting
14
the detailed budgets, indicting physical progress and monetary outlay, in the following
manner:
B. NEW SCHEMES
In the case of the new schemes, yet to be approved by the Board, budget provision should
be based on project estimates in the feasibility report. Schedules and payments terms for
similar contracts for continuing schemes should also be taken in account.
Performance Budgeting
15
These include the left out works though approved in FR/ subsequent
approval stages but the execution of which may continue even after the
commissioning of the units. They may be Ash Dyke raising, Ash handling plant, EAP
or administrative building, part of township etc.
Performance Budgeting
16
MBOA BUDGET
Performance Budgeting
17
b.
The policy and procedures proposed for consideration, processing and approval of
OCAW proposals is as follows:
DEFINITION:
The work under the above head shall include:
I. Works not covered in approved FR/RCE but arising due to policy decisions and
site-specific requirements.
II. Left out works though approved as FR/ subsequent approval stages such as
administrative building, part of township works etc. execution of which may
continue after commissioning if units.
III. EAP and other related packages.
This is in addition to the packages budget to be submitted by those
projects in the prescribed formats. Adequate care must be taken that no new items
are included in the budget proposal except for:
i.
ii.
iii.
iv.
v.
vi.
The provision in the budget proposal for items except (i & ii) should made only
after technical/administrative approval of the items. And the status of remarks column if
the proposal wherever proposals are not approved at the time of preparation of budget
proposals but are likely to be approved in due course. Copies of the competent should be
enclosed.
The expenditure on other capital addition works should be incurred within one
years of the start of commercial operation of the last unit, to get back those costs in the
form of tariff. Accordingly, after the commercial start of the project, shall have to be
completed within the stipulated time period of One year. However, for expenditure
related to construction of ash dyke works, a separate proposal is under approval.
c.
R&M BUDGET
R&M scheme comprises of various works of renovation and
modernization, up gradation of the plant/equipment in main plants and auxiliaries
that have been rendered obsolete, unusable or are not as productive is as to sustain
the expected production level. Additions to update those systems in which rate if
obsolescence is fast, shall also be covered under R&M schemes.
Performance Budgeting
18
i.
ii.
iii.
iv.
v.
vi.
These covers most of the power plants which are of more than 10 years old and have
clocked 70000 operating hours, needs to be renovated and modernized so as to set aside
the obsolescence and achieve more efficiency and life of the plant.
Schemes covered under this, should also be included in the capital budgets both in the
annual plan as well as in the long term capital budget and they should be submitted to the
board for their approval to the outlay as a part of annual plan.
d.
i.
ii.
iii.
Performance Budgeting
19
UNITS OF MEASUREMENT
BUDGET PHYSICAL PROGRESS MEASUREMENT
ITEMS PARTICULARS
UNITS OF MEASUREMENT
Mechanical Items
-TG
-SG
-ESP
------ON TONNAGE BASIS------CHP
-Ash handling plant
CIVIL WORKS
-Brick works
-RCC
-Plastering
-Site leveling
-Foundation
-Painting
-Door/window
-Finishing work
Performance Budgeting
-Cum
-Cum
-Sq. Mt
-Cum
-Cum
-Sq. Mt
-Lump sum contract
-% Of completion
20
Cost of land
Infrastructure facilities
Civil/mechanical/electrical works
Township
MGR and constructional facilities.
2. COMMISSIONING EXPENSES
All direct expenses for running of individual units up to the date of
commercial operation since the date of synchronization of units incl. Fuel cost, start
up power, chemical and lubricants, consumption and anticipated sale of energy during
the trial run are to be indicated.
3. CONSTRUCTION MATERIALS
Provision to be made for accretion/decretion of stock, construction
materials such as structural steel,, reinforcement cement and other materials.
Performance Budgeting
21
4. TECHNICAL CONSULTANCY
Payment t technical identifiable with systems such as MGR, coal handling,
C&I, prime consultants, retainer consultant are to be incl.under this head.
5. TRAINING AND RECRUITEMENT COST
Expenses for training of executive and non-executive and trainees incl.
Stipends, faculty fees, course materials, TA for trainees rent for training hall and
expenses on management development courses.
6. IEDC (incidental expenditure during construction)
-Employees cost: c.7.1
These comprise of salaries, DA incentives, wages, allowances,
contribution to Pf and other welfare and expense such as LTC, medical
reimbursement, canteen subsidy etc. the provision for arrears of salary should be
shown separately.
-Other establishment expenses: c.8
Expenses incidental to construction and capital works not traceable
directly to any capital activity are chargeable to incidental expenses during
construction, RM for building, construction equipment, vehicle running expenses,
office rent, LC charges, cost of drawing, traveling expenses, printing & stationary,
communication expenses, advertisement for tenders are major items falling in
this category.
All miscellaneous expenses remaining are to be shown under this head
7. MBOA (Misc. Bought Put Assets)
It covers expenses on vehicles, furniture and fixtures, office/ other
equipment, hospital and other medical equipment, cable T.V. equipment, canteen eqpt,
township eqpt, fire fighting eqpt, EDP-PC/printer/LAN, communication eqpt, safety
eqpt, substation eqpt, DG set, conference hall and project system.
Performance Budgeting
22
8. Borrowings Cost
Interest on loans and bonds, upfront fee, agency commission, guarantee
commission, commitment charges and any other charges and expenses payable
towards raising of loans which are accrued and to be capitalized during the
construction period has to be estimated and included in this budget.
9. WORKING CAPITAL MARGIN: C.11
Increase in working capital forms the base for calculating working capital
margin component.
10. CAPITAL EXPENDTURE NOT REPRESENTED BY ASSETS:
It includes of construction of approach roads, canal lining, property
belonging to the local community/ SEBs. These items should icl. U/ this budget heads
in DCO and these should also be presented separately in the format for capital
expenses not represented by assets.
The budget proposal for these be supported by specific approval from
competent authority and write-up giving detailed justification.
BUDGET FORMATS
Standard budget formats are systematic preparation of budget and its
meaningful analysis. It brings correlation between budgets prepared by different projects/
entities making its final consolidation a lot easier. Without the standard formats,
uniformity in the presentation of the budget cannot be ensured and thereby causing
distortions in consolidations of budgets at CC level. They are in different series:
S.NO
FORMATS
SERIES
A-series
2
3
B-series
C-series
4
5
D-series
E-series
Performance Budgeting
23
F-series
DESCRIPTION
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
A-2
B-1
B-4
C-1.1
C-1.2
C-2.1
C-2.2
C-2.3
C-3
C-4.1
C-4.2
C-5
C-6
C-7.1
C-7.2
C-8
C-9
C-11
D-2
E-2
The above budget formats are most commonly used forms and are generally used by the
almost every project/budget center without default.
RESPONSIBILITY CENTRES
The responsibility for utilization of budgets of respective rest with the head of
divisions/ budget centers. In case of generation project budgets- even though contracts
and expediting in the task force and corporate contracts are responsible for supply of
equipment, GMs of the project and ED of the region are equally responsible for the
utilization pf their respect budgets. However, for monitoring purposes, responsibility is to
be identifies for anticipated payments relating corporate center, task force and site
separately.
In performance budget of various New and approved/ongoing/completed
schemes, for each CAPEX the outlay, the allocation is done between the CC/projects
based on payments made by contract awarding authorities.
Performance Budgeting
24
BUDGET COMMITTEE
The CAPEX budget of any project/ budget center runs through a series of
meticulous analysis and consideration by different department before its finalization, of
which the budget committee is the Apex decision-making authority. The budget
committee of the project and corporate consist of various experts of different department
who are responsible as per DOP of NTPC to finalize and adopt the budget proposals.
Through this a transparency is bought in the budget making exercise.
PROJECT BUDGET COMMITTEE
The project budget committee consisting of finalizes budget proposals of the
generation projects:
GM (project)
Manager (P&S)
CEM
CMM
CCM
CFM/DGM
In charge budget
chairman
member
member
member
member
member
secretary
Budget proposals of regional divisions are finalized by the chief (F&A) of the region in
consultation with HODs.
CORPORATE BUDGET COMMITTEE
After finalization of budget proposals of generation projects and subsequently
discussed in full strength by the ED of the Region, the same shall be sent to corporate
divisions corporate contracts who will in turn will forward the same to after their
remarks to corporate budget committee by latest 15th August of each year for final
approval.
Budget proposals of regional divisions are finalized by the chief (F&A) of the
region in consultation with HODs.
Performance Budgeting
25
BUDGET CIRCULARS
Corporate budget issues budget circulars indicating the compliance aspects of
methodology of preparation, formulation and approval of budget. The budget circulars
are issued in line with the notification issued by the planning commission in
consultation with the department of expenditure and department of programme
implementation. So in a way they are the month of management as well as government of
India.
The budget circulars issued in month of May each year indicating an array of
compliance aspects to be adhered by the budget centers/ project. Some of such list is
given below:
-
Performance Budgeting
26
INITIAL EXERCISE
1. Site finance of all the projects will furnish budget head wise actual expenditure up
to the end of previous year reconciled with the balance sheet in format No. F-6
and actual expenditure up to the end of June of the current year in Format No. F-1
to the concerned agencies responsible for formulation of budgets.
2. This being the starting point for formulation of budget, site finance of all projects
office, regional finance and the corporate budget should ensure that above
information reaches concerned agencies by 15th July.
3. DGM (CS), corporate center and CTFs will furnish data regarding initial/
mobilization advances, equipment supply and other payment against A
contracts and payments against technical consultancy format No. C-2 & 5, D-2&
5 and E-2& 5 to regional finance and account by 10 th August. Regional finance
and accounts in consolidation with regional P&S will review and consolidate the
above information and forward the same to GMs of the projects by 15th August.
4. The training and recruitment budgets are to be drawn by HR and Admin.
Departments.
5. Head of Department are responsible for control and co-ordination of Capex
budget of contact coordinators within the department and also for preparation of
budget establishments expenses within their control.
6. All department budgets should be forwarded to budget coordinators identifies by
GMs/ HODs for each division by 15th August- mostly the finance and accounts
acts as budget coordinator.
7. The budget coordinator of each division should prepare the total divisional budget
and forward the same with the approval of GM/ HOD to the secretary of the
concerned budget committee- project budget in case of project, regional finance in
the case of regional HQ and corporate budget in the cases of corporate divisions.
BUDGET MEETING
After receipt of approved project budgets by the corporate budget, the same is
scrutinized to check every possibility of its veracity. After the same, the budget
meeting is organized with the participation of project budget representatives,
corporate monitoring group and corporate planning department. Corporate budget
group supervises the budget meeting and the head of corporate budget is secretary
of the meeting.
Performance Budgeting
27
In the meeting every outlay proposal is discussed in its length and breadth. How
much BE is to kept for the Next ear and RE estimation and physical progress etc,
are discussed to sort out the proposed outlay wherever possible. The business of
this meeting is recorded on the minute book and signed by all the members of
meeting. The outcome of the meeting is finally incorporated in the BE/RE
provision.
ANNUAL EXPENDITURE REPORT
In addition to the monthly expenditure report furnished by finance to concerned
agencies, cumulative expenditure up to 31st March of every year based on audited
balance sheet also needs to be compiled for all divisions/ projects for which the
budgets are formulated.
In case the audited balance sheet is not available the information may be compiled
based on the provisional balance sheet. In such cases, changes, if any should be
communicated subsequently based on audited balance sheet. The budgets head
given in Annexure-I for DCO. And for other expenditure, the report is to be
prepared for each of the items mentioned in respective budgets. F&A department
at project/ regional/ CC will prepare the report.
This report so compiled will be sent to the followings:
General manager (project)
All HODs at project
Regional finance
Regional P&S department CTF
Corporate contracts
Cost Engg. Cell in CC
For regional establishments expenses, the report will be compiled by regional
finance and forwarded to all divisional heads in the region and corporate budgets.
Similarly, in case of CC expenses, the actual expenditure report will be compiled
by corporate accounts and forwarded the same to all divisional/ project head in
addition to corporate budget.
Since the actual expenditure up to the end of previous year is the starting point for
formulation of revised estimates and budget estimates, it must be ensured that this
report (i.e. actual expenditure) reaches the concerned departments latest by 15 th
July in form No. F-6
REVIEW AND
BUDGETS
Performance Budgeting
MONITORING
OF
PERFORMANCE
28
For success of any task, the role of review and monitoring is quite vital.
The same can be equally being applied to the performance budget of NTPC.
NTPC has evolved a comprehensive model to review the performance if project
budget. The budget is reviewed inline with its BE outlay and RE as compared to
the actual expenditure on quarterly and monthly basis.
A.
Project budget report the actual expenditure against budgets heads on form No. F1.1 to 1.4 every month to the following:
I. In case of Generation of project
- GM (project)
- Project planning and systems
- Regional finance
- CTF
- Corporate budget
- Corporate contracts
The respective project review teams examine the monthly budget review. The
reasons for major variations (in case of each budget head exceeding 10% of
BE/RE or Rs. 10 lacs, which ever is lower) are analyzed indicating the
responsibility for corporate center, task force and site and recorded in the minutes
of respective review team meeting. The scheme for monthly review of projects
budgets is given in flow chart No.3.
In addition to the budget review, the project finance also furnish actual
purchase of construction materials vi., steel, cement and other stores in form No.
F-1.9 as compared to the budget for year. The status of purchase as well as
outstanding advances against procurement of materials will also be reviewed as
part of the monthly review of project budget in respective PRT meetings.
The procedures for monthly review is illustrated in flow-chart No. III.
B.
29
Performance Budgeting
30
Volume I
Performance Budgeting
31
A. CONSTRUCTION ACTIVITITIES
It contains the overall proposal of financial outlay for NTPC as whole. The overall
proposal covers the followings:
1. Brief write up about NTPC.
2. Power programme- outlay and expenditure and expenditure (form-PR I)
PR-I contains the followings:
- Annexure I commissioning schedule of generation projects
- Annexure II IXth plan programme outlay summary
-Annexure III -- state wise central sector outlay
3. Phasing of benefits from the Generation projects in terms of MW PTII
4. External assistance for aided projects PR IX
It provides the external assistance component and its magnitude in the
form of external assistance route through budget, flow of ECBs-indicating
its deployment for various projects and the ECBs stage of funding
committed or uncommitted. Details given in the statement PR IX gives
the detail of an agreement organization name, amount of aid, credit no,
terminal date of assistance etc.
5. Financing of the projects- central sector plan expenditure PR X
- Through internal resources (retained earning plus dep)
- Loan from Govt. of India.
- Domestic borrowing in the form of loans from Fis and Bond
- External commercial borrowing
- Syndicated loan ECA and Euro bonds
- Budgetary support from Govt. of India
it basically, gives the financial statistics of last 5 years indicating the movement of Gross
Internal resources Generation, accretion to working capital, net internal resources and
extra budgetary support for all those five financial years. The purpose of this statement is
Performance Budgeting
32
to calculate the proposed budgetary support to fill up the gap found in the above
resources to go ahead with the construction activities.
-
in this Performa, the details regarding receipts and expenditure and revenue and capital
account.
-
it shows actual expenditures, BE, RE, BE(next year) for installed capacity (MW terms),
energy generation (MU), PLF, expenditure on employee and the cost of Generation.
Details of energy sales/ revenue in Proforma III, indicating the category of
users/ customers in actual, BE, RE, BE (NY) budget estimates.
-
it is a statement showing the rate of return on net fixed assets employed at the beginning
of the year as required under the latest section 59 if electricity (supply) Act 1948.
-
It shows the SEB wise revenue arrears-O/S including its surcharge for the late payments.
C. PHYSICAL ASPECTS
Under this the physical progress of various construction activities is shown
indicating the major Milestone achieved and also the time schedule of construction
activities to undertake in the future.
VOLUME II
In the volume II the BE estimates of the current year along with its corresponding RE
figure and the actual expenditure for each project wise-whether it is on-going schemes or
R & M or new project or other capital Misc. schemes.
VOLUME III
It is specifically meant for the physical schedule of different construction activities and
other project activities. It details up the activities in month wise manner. The information
given under this volume is quite helpful to now the status quo of different activities very
Performance Budgeting
33
minutely. It is as per scheduling of Master Network diagram along with its comparison
with actual position.
VOLUME IV
This volume shows the budget outlay for the completed schemes, which were completed
in seventh and eighth plan period but on which still some expenditure, are incurred as
capital outlay.
Description
Responsibility
Annexure I
Physical achievements
Corporate planning
Annexure II
Corporate budget
Corporate budget
Performance Budgeting
34
Annexure III
Financial outlays
Corporate budget
Annexure IV
Scheme-wise outlays
Corporate budget
Annexure VI
Annexure VI
Form PR-I
Form PR-II
Phasing
of
benefits
generation projects
Master Control Network
Corporate budget
and
and
The following points may be kept in view while filling in data for annual plan:
1
The programme and targets are to be based on completion dates indicated by the
Govt. Of India in the administrative sanction for on-going projects and target dates
indicated in the feasibility reports for new schemes. The network, the resources based
network and the approved project schedules or schedule indicated in the feasibility
reports. Unit-wise data of physical targets and milestones are to be furnished in the case
of boiler and turbo-generator both in the master network and resources based network.
2
The annual plan proposal is to be based on the budget estimates, which are
finalized during the last week of September. As soon as the budgets are finalized, regional
finance will provide copies of budgets as approved by corporate budget committee to
regional planning and systems to enable the later to complete the fund requirement and
activity chart for the remaining period of the project in statement PR-IV.
3.
The master control network is to be prepared by corporate planning and
monitoring department and forward the same to regional finance, regional P&S and
corporate budgets. The master control; network is to be prepared for each of the units for
generation projects.
4.
In the forms PR-IV and PR-V, the current estimates to be indicated for the project
will be as per performance budget (form No. C-2.1). in cases where this information is
Performance Budgeting
35
not, available (new approved scheme) estimates form the latest available feasibility
report/ detailed report/ revised cost estimates should be adopted which will be forwarded
by cost engineering cell in the corporate center to regional finance. The information
should also include reasons for variations between the current estimates as adopted in the
annual plan and latest approved cost estimates under the following heads.
a. Domestic price inflation
b. Inflation for the items imported
c. Exchange rate variation of supply of capital goods
d. ERV of the loan from international agencies
e. Change in the scope of work
f. Other reasons
5. The work head to be indicated in the PERT networks, resources based network
and cost estimates should coincide with the budget heads so that a comparison could
be effected between the project outlay, actual expenditure, budget provision and
phasing of funds against each work head. This requirement may be considered very
important as the planning commission every year is insisting this upon.
METHODOLOGY
This project has been prepared to with limited access to records and related documents
relating to the performance Budget of NTPC. The contents of this report are fully pf
academic pursuits. With limited access to Annual plan, project budget proposal and
Performance Budgeting
36
budget Manual of NTPC. Certain financial analysis has been done which should not be
construed as nay-authentic fact.
The budget annual has been referred in most of the cases. The annual report of 20062007 has been taken into consideration. Certain soft copy of budget database has been
somewhere in this project report with the prior permission of concerned authority.
Performance Budgeting
37