Está en la página 1de 80

DP Conference MTS Symposium

Flow Assurance
Elijah Kempton
Tommy Golczynski
Marine Technology Society
September 30, 2004
Return to session directory

Session Outline
Flow Assurance Overview
Key Flow Assurance Issues
Wax
Hydrates
Slugging

Deepwater Impacts on Flow Assurance


Emerging Technologies

Design Considerations
Black Oil Systems
Gas Condensate Systems

Flow Assurance Overview

What is Flow Assurance?


Analysis of the entire production system to ensure that
the produced fluids continue to flow throughout the life
of the field.

Optimization of the design and operating procedures to


cost effectively prevent or mitigate slugging, surge
volumes, wax deposition, gelling, hydrates,
asphaltenes, etc.

Key Flow Assurance Issues


Wax (Paraffin) What is it?
A solid hydrocarbon which precipitates
from a produced fluid
Forms when the fluid temperature drops
below the Wax Appearance Temperature
(WAT)
Melts at elevated temperatures (20F+
above the WAT)
Rate of deposition can be predicted for
pigging frequency

Key Flow Assurance Issues


Wax
Since 1996, there have been 51 major
occurrences that the MMS had to be involved in
All were paraffin-related

Means of remediation
Pigging
Continuous inhibition (150-250 ppm for Gulf of Mexico)
Reduced wax deposition rate by 60-90%

Industry Technology
Modeling is overly-conservative (6X pigging
frequency)

Key Flow Assurance Issues


Example WAT Measurement

Above WAT

Wax Crystals (WAT)

Seabed Temp. (40F)

Key Flow Assurance Issues


Factors effecting wax deposition rate
Wax Appearance Temperature, WAT
Production Fluid Temperature
Flowline U-value
Fluid Properties
Viscosity
N-Paraffin Content

Key Flow Assurance Issues


Wax Deposition Insulation Impact

Key Flow Assurance Issues


Hydrate What is it?
An Ice-like solid that forms
when:
Sufficient water is present
Hydrate former (i.e., methane)
is present
Right combination of Pressure
and Temperature (High
Pressure / Low Temperature
Molecular
Structure of
Hydrate Crystal

Key Flow Assurance Issues


Hydrates
Primary cause for insulated flowlines
Deepwater operations
Increased operating pressure
Cold ambient temperatures

Means of remediation
Crude oil displacement (looped flowlines)
Depressurization
Coiled tubing
Continuous Inhibition (Prevention Only)
Methanol/MEG
LDHI

Key Flow Assurance Issues


Hydrates Base Information
10000
9000
8000

Pressure, psia

7000
6000
5000

No
Hydrates

Hydrates

4000
3000

Pure Water

2000

Sea Water
1000

Produced Water

0
40

45

50

55

60

65

Temperature, F

70

75

80

85

Key Flow Assurance Issues


Hydrates Base Information
50
0.600

5% Water Cut

45
0.575

10% Water Cut

40
0.550

25% Water Cut

20% Water Cut

Methanol Dosage,
BBL MeOH/BBL
Water
Methanol
Rate, gpm

30% Water Cut


0.525
35
0.500
30

40% Water Cut


50% Water Cut

0.475

25 GPM

25
0.450
20
0.425
0.400
15
0.375
10
0.350
5
0.325

0
0.300
1000
50

2000
75

3000
100

4000
125

5000
150

175

6000

Flowrate,
B/d bara
Shut-in
Pressure,

200

7000

225

761 GOR

1100 GOR

1700 GOR

2500 GOR

8000

250

9000
275

10000
300

Key Flow Assurance Issues


Slugging What is it?
Periods of Low Flow
Followed by Periods of
High Flow
Occurs in Multiphase
Flowlines at Low Gas
Velocities

Key Flow Assurance Issues


Slugging
Causes
Low fluid velocity
Bigger Better

Gas Lift
Overview

Seabed bathymetry (downsloping)


Riser type
Advantages
Lazy-S is a slug generator

Means of prevention
Increase flowrate
Separator pressure
Gas lift

Disadvantages

Proven
Technology

Erosion
Concerns

Relative
Inexpensive

Lower
Temperatures
Difficult with
Catenary Risers

Key Flow Assurance Issues


Slugging Gas Lift Impacts
150
60000
25000
40000

Liquid
Outlet
Liquid
OutletFlowrate
Flowrate
(B/d)
Liquid
Accumulation
Above(B/d)
Normal (bbl)

35000
100
50000

0 MMSCFD Gas Lift

Surge
MMSCFD
Gas
5 MMSCFD0
Gas
LiftVolume
10
MMSCFD
GasLift
Lift

5 MMSCFD Gas Lift


10 MMSCFD Gas Lift

20000
30000
50
40000
25000
15000
0
30000
20000

10000
15000
-50
20000

10000
-100
5000
10000
5000

-150
3.0
0
3.0

3.5
3.5
3.5

4.0
4.0
4.0

4.5
4.5
4.5

5.0
5.0
5.0

5.5
5.5
5.5
Time (hours)

Time(hours)
(hours)
Time

6.0
6.0
6.0

6.5
6.5
6.5

7.0
7.0
7.0

7.5
7.5
7.5

8.0
8.0
8.0

Key Flow Assurance Issues


Chemical Inventory

Other Issues
Asphaltenes
Scale
C-Factors
Surge Volume

Pour Point
Corrosion
Emulsions

Flare Capacity

Cooldown Times
Sand

Liquids Management

Erosion
Depressurization

Pigging

Deepwater Impacts on Flow


Assurance
Hydrate Formation/Wax Deposition
Leads to:
Insulation / dual flowlines
Dry oil flushing
Active heating
Chemicals
Revamped operating strategies

Lack of pressure / need for boosting


Deepwater + high water cut + long tiebacks
Riser base gas lift
Multiphase pumping
Subsea separation

Deepwater:
Temperature Losses
Potential Energy Losses
Gas does work in moving fluids
Function of water depth
Expansion Cooling (Joule-Thomson Effect)
Exacerbated at large pressure differentials
RISER DOMINATES DEEPWATER SYSTEMS
Insulation may not be the answer!

Deepwater:
Temperature Losses

125

FLOWLINE
120

RISER BASE

WELLHEAD
Temperature (F)

115

110 Potential Energy

Surroundings
(U-Value)
6%

(Work)
48%

RISER

105

Joule-Thomson
Cooling
46%

100

TOPSIDES
95
0

Distance (miles)

Deepwater:
Temperature Losses
Flowline
Length
(miles)

Temperature Drop (F)


Flowline

Riser

1.2

16.6

2.9

16.6

15

9.2

16.5

Deepwater:
Temperature Losses

Heat transfer coefficient (U-value) dictates


steady state temperatures

Q (heat loss) = UAT

U-Value , Q T

Thermal mass (, Cp) impacts transient


performance

Measure of heat storage

Prolongs cooldown times

Prolongs warm-up times

Transient Temperature Loss


110

100

Temperature (F)

90

80

HIGH (Gelled Fluid #2 Water Base)


70

MEDIUM (Gelled Fluid #1 Oil Base)


60

LOW (Nitrogen)
50

40
0

10

15

20

Time(hours)

25

30

35

40

Deepwater:
Pressure Losses
2500

WELLHEAD
RISER BASE

2000

FLOWLINE

Pressure (psia)

1500

RISER
1000

500

TOPSIDES
0
0

Distance (miles)

Deepwater:
Pressure Losses
Flowline
Length
(miles)

Pressure Drop (psia)


Flowline

Riser

143

1812

238

1791

15

405

1764

Deepwater:
Dry Trees vs. Subsea Tieback
Dry trees preferred for accessibility
Dry trees more difficult for flow assurance
Typically cannot depressurize
Short cooldown times (2-8 hours)
Fewer insulation/heating options than subsea
Limited chemical (MeOH/MEG) deliverability
Wax deposition more difficult to remediate

Dry Tree:
Conduction / Convection / Radiation
Dry Tree Analysis: Cooldown Comparison
Production Fluid Temperature
100
95
90
85

Temperature (F)

80
75
70
HYDRATE FORMATION TEMPERATURE
65
60
55

Solid - Conduction

50

Liquid - Conduction+Convection

45

Gas - Conduction+Convection+Radiation

40
0

6
Tim e (Hours)

10

11

12

Dry Tree:
Concentric vs. Non-Concentric
Accommodate Auxiliary Lines?

Concentric

Non-Concentric

Heat Transfer: Q = kAT / L


(Conduction Only)

Dry Tree:
Concentric vs. Non-Concentric

Dry Tree:
Gas Properties
100

90

Temperature (F)

80

70

60

15 psia N2
30 psia N2
59 psia N2
102 psia N2

50

40
0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

Time (Hours)

4.0

4.5

5.0

5.5

6.0

Design for Expansion


Transient issues drive deepwater design
Cooldown / restart - Hydrates
Typical deepwater practice
Dual flowlines / crude oil displacement
Typically cannot depressurize (oil systems)
Consider potential for future expansion
Insulation
Topsides facilities

Design for Expansion


22
.5

km

m
k
8

km

10

km

Total Time to Displace Existing System = 22 Hours (Sequential)


Total Time to Displace Integrated System = 45 Hours (Sequential)
High Level Insulation, or Additional Topsides Facilities Required!

Emerging Technologies
Artificial Lift
Subsea Separation (-)
Multiphase Pumping (+)
Gas Lift (+ / -)
Passive Insulation Solutions
Microporous Insulation
Phase Change Materials

Emerging Technologies
Active Heating
Hot Water Circulation
Electrically Heated
Electrically-heated ready
Chemicals
Low Dosage Hydrate Inhibitors
Cold Flow

Design Considerations:
Black Oil and
Gas Condensate Systems

Black Oil System:


Steady State Design Checklist
Hydraulics
Line sizing
Dry tree vs. subsea tieback
Single vs. dual flowlines
Dual flowlines becoming standard for deepwater

Pressure drop
Velocity / erosion (minimum / maximum)
Slugging

Thermal
Insulation requirements
Hydrate formation
Wax deposition
Gel formation

Black Oil System:


Transient Design Checklist
Shutdown
Planned
Unplanned

Depressurization
Restart
Warm
Cold

Fluid displacement / pigging


Flowline preheating

Black Oil Systems:


Steady State Design Considerations

Black Oil System:


Steady State Hydraulics
2500

Pressure drop effects


Physical

2000

Pressure (psia)

1500

Line size
Tieback distance
Water depth
Multiphase flow:
Head losses <> head gains

1000

500

0
0

Pipe roughness (typical values)


Steel:
Tubing:
Flexible pipe:

0.0018
0.0006
ID/250

Fluid properties
Gas/oil ratio (GOR)
Density
Viscosity
May require insulation to limit viscosity

Distance (miles)

Black Oil System: Slugging


Hydrodynamic
High frequency
Minimal facilities impact

Hydrodynamic Slugging
Gas Outlet Flow
7

Terrain

High liquid / gas flowrates


Topsides concern
Riser fatigue concern
Utilize gas lift

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

5.0

5.5

4.5

5.0

5.5

6.0

Time (hours)

Terrain Slugging
Liquid Outlet Flow
80000

70000

60000

50000

40000

30000

20000

10000

0
1.0

1.5

2.0

2.5

3.0

3.5

Time (hours)

4.0

6.0

Black Oil System: Slugging


Slugging issues
Sensitivity to Fluid GOR / water cut
Water Cut (%)

Terrain Slugging Regime (BPD) /


Surge Volume (BBL)
760 GOR

1300 GOR

1800 GOR

15000 / 150

12500 / 100

7500 / 75

20

20000 / 160

17500 / 100

15000 / 125

40

24000 / 175

20000 / 125

15000 / 130

60

26000 / 325

17500 / 250

10000 / 200

80

DNF

5000 / 400

5000 / 300

Black Oil System: Slugging


Slugging issues
Sensitivity to Trajectory: up vs. downslope
-7500
Original Route - 40 miles total length
-7600

Alternate Route #1 - 36 miles total length


Alternate Route #2 - 45 miles total length

-7700

-7800

-8000

400

-8100

-8200

Original Route
Alternate Route #1
Alternate Route #2

350
WELLHEAD

-8300

RISER BASE

-8400

-8500

-8600
0

10

12

14

16

18

20

22

Distance, miles

24

26

28

30

32

34

36

38

40

Liquid Accumulation Above Normal* (bbl)

Water Depth, ft

-7900

300

>24 hour Ramp-up Required


250

200

10 hour Ramp-up Required


150

100

50 bbl Slug Catcher Capacity

50

0
0

Time (hours)

Black Oil System:


Steady State Thermal Design
Hydrates
Maintain steady state temperature
above hydrate formation region,
down to reasonable flowrate
Looped flowline ~ 25% of field
production (50% per flowline)

For low water-cut systems,


continuous hydrate inhibition is
possible
Future: continuous LDHI inhibition

Black Oil System:


Steady State Thermal Design
Wax
Maintain temperature above WAT (stock
tank), down to reasonable flowrate
Looped flowline ~ 25% of field production
(50% per flowline)

Maintain viscosity at acceptable levels to


reduce pressure drop
Insulate to minimize pigging frequency
Pigging frequency > residence time

Continuous paraffin inhibition (if


necessary)

Black Oil System:


Steady State Thermal Design
Insulation Option

Achievable U-value
(BTU/hr-ft-F)

Issue / Concern

Flexible

0.75 1.50

Limited insulating capacity

Wet (Syntactic)

0.50 0.75

Buoyancy issues

Burial

0.50 1.00

Dependant on soil properties


Combined with insulation

Pipe-in-pipe

0.20 0.25

Riser installation difficulties

Micro-porous

0.08 0.10

Industry acceptance

Black Oil System:


Steady State Thermal Design
Arrival Temperature
Water Cut = 0%
50.0

Adiabatic (0 BTU/ft hr F)

48.0
46.0

0.09 BTU/ft hr F

44.0

0.20 BTU/ft hr F

42.0

Arrival temperature (C)

40.0

0.30 BTU/ft hr F

38.0
36.0

0.50 BTU/ft hr F

34.0
32.0
30.0
28.0

0.5 W/m.K
1.0 W/m.K
2 W/m.K
3.0 W/m.K
no heat loss

26.0
24.0
22.0
20.0
7500

10000

12500

15000

17500

20000

22500

25000

Liquid Flowrate (blpd)

27500

30000

32500

35000

37500

40000

Black Oil Systems:


Cooldown Design Considerations

Black Oil System:

Cooldown

Shutdown statistics
Typical shutdown durations
89% shutdowns
94% shutdowns
99.9% shutdowns

< 10 hours
< 12 hours
< 24 hours

Typical shutdown causes


Pumps
Scale
Corrosion
Sand
Paraffin
Hydrates
Asphaltenes
Separation
Other

Black Oil System: Cooldown


Planned shutdown Procedure
Inject hydrate inhibitor for one residence time
(minimum)
At high water cuts, may need to reduce flowrate to
effectively treat system

Inject hydrate inhibitor into subsea equipment


Particular attention to horizontal components
Self-draining manifold / jumpers
Treat upper portion of wellbore
SCSSV vs. top ~50 ft

Shut-in system

Black Oil System:

Cooldown

Unplanned shutdown Procedure


Determine minimum cooldown times
No-Touch Time
~2-4 hours / no action taken subsea

Light Touch Time


~2-4 hours / treat critical components
Time is a function of chemical injection philosophy / number of wells

Preservation Time
Time required to depressurize or displace flowlines with non-hydrate
forming fluid

Time=0
No-Touch

Time=4
Light Touch

Time=8
Preservation

Black Oil System:


Insulation selection

150
Pipe-in-Pipe (0.20 BTU/hr-ft-F)

Cooldown time determined


by:

140
Wet Insulation (0.75 BTU/hr-ft-F)
130
120

Thermal mass (, Cp)

110

Line size impacts


Bigger = More
Thermal Mass

Gas / liquid interface


typically controlling point
Gas = low thermal mass

Temperature (F)

U-Value
Measure of heat
storage

Flexible Pipe (1.00 BTU/hr-ft-F)

100
90
80
70
60

HYDRATE FORMATION(PURE WATER)

50
40
0

Highest pressure
Coldest temperature

Cooldown

10

12

14

16

18

20

Time (hours)

22

24

26

28

30

32

34

36

Black Oil System: Cooldown


140
0 hours (Steady State)
1 hours

130

RESERVOIR

2 hours

WELLHEAD

4 hours

120

6 hours

FLOWLINE

8 hours

110

10 hours
12 hours

Temperature (F)

100

18 hours
24 hours

90
80
70
60
50
40

RISER

30
0.0

0.5

1.0

1.5

2.0

2.5

3.0

Distance (miles)

3.5

4.0

4.5

5.0

5.5

6.0

Black Oil System: Cooldown


6000

RESERVOIR
0 hours (Steady State)

5500
24 hours

5000
4500

Pressure (psia)

4000

WELLHEAD

3500
3000
2500
2000

FLOWLINE
RISER

1500
1000
500
0
0.0

0.5

1.0

1.5

2.0

2.5

3.0

Distance (miles)

3.5

4.0

4.5

5.0

5.5

6.0

Black Oil System: Cooldown


1.0
RESERVOIR

FLOWLINE
WELLHEAD

0.9

0.8

Liquid Holdup (-)

0.7

0.6

0.5

0.4

0.3

0.2

0.1
0 hours (Steady State)

RISER

24 hours

0.0
0.0

0.5

1.0

1.5

2.0

2.5

3.0

Distance (miles)

3.5

4.0

4.5

5.0

5.5

6.0

Black Oil System: Cooldown


60
WELLHEAD

50

RESERVOIR
FLOWLINE

Hydrate Propensity, T-Thyd (F)

40

30

20

10

0 hours (Steady State)


1 hours

2 hours
4 hours
6 hours

-10

8 hours
10 hours
12 hours

-20

RISER

18 hours
24 hours

-30
0.0

0.5

1.0

1.5

2.0

2.5

3.0

Distance (miles)

3.5

4.0

4.5

5.0

5.5

6.0

Black Oil System:


Cooldown Checklist

Is there adequate chemical injection to treat subsea components within


cooldown time?
Wellbore
Trees
Jumpers
Manifolds
What is the subsea valve closure philosophy?
Packed:
More liquid / higher pressures
Un-packed:
Less liquid / lower pressures
Does insulation provide sufficient cooldown time?
No-touch
Light-touch
Preservation
Is gel formation a possibility?
If yes, system design philosophy changes
Is SCSSV set deep enough to avoid hydrates?

Black Oil Systems:


Depressurization Design
Considerations

Black Oil System: Depressurization


Hydrate remediation strategy
Reduce pressure below hydrate formation pressure at seabed

Effectiveness based on:

10000
9000

Fluid properties
GOR
Water cut
Upslope
Downslope

Pressure, psia

7000

Seabed bathymetry

6000
5000
4000

Phyd ~ 200 psia

3000

Pure Water

2000

Sea Water
1000

Produced Water

Deepwater issues
Time=0

8000

40

45

50

55

60

65

70

75

Temperature, F

Reduce pressure to ~200 psia at seabed


Maintain pressure below hydrate conditions during restart
Time=4
Time=8

No-Touch

Light Touch

Preservation:
Depressurization

80

85

Depressurization:Subsea Tieback
4500

BOTTOM HOLE

4000
3500

FLOWLINE
3000
0.0 hours
0.5 hours
1.0 hours

Pressure (psia)

2500
2000

MUDLINE

1500
1000
500

RISER BASE

0
0

Distance (miles)

Depressurization Dry Tree


4500

BOTTOM HOLE

4000

0.0 hours
3500

0.5 hours
1.0 hours

Pressure (psia)

3000
2500
2000
1500

MUDLINE
1000

SCSSV
GAS/LIQUID
INTERFACE

500
0
0

2000

4000

6000

Distance (feet)

8000

10000

12000

Black Oil System:


Depressurization Checklist
Can you depressurize below hydrate formation conditions?
If YES, can you depressurize in late-life at high water cuts?
If YES, can you maintain pressure below hydrate formation conditions
during restart?
Difficult for deepwater

If YES, is there a pour point concern?


Depressurization increases restart pressure requirements

If NO, consider the following for hydrate prevention:


Displacement (dual flowlines)
Active heating
Continuous chemical inhibition

Black Oil Systems:


Displacement Design
Considerations

Black Oil System: Displacement


Hydrate Prevention - Shutdown
During Prevention time, displace produced
fluids from flowline
Unable to get hydrate inhibitor to in-situ fluids
during shutdown
Dual flowlines required
Sufficient insulation / cooldown time
Function of flowline length
Time=0
No-Touch

Time=4
Light Touch

Time=8
Preservation:
Displacement

Black Oil System: Displacement


Discharge Pressure Required

HOLD BACKPRESSURE AT OUTLET

Black Oil System: Displacement


Hydrate Prevention - Shutdown
Dead Oil Flushing - Year 5
FPSO Pump Discharge Pressure
FPSO Arrival Pressure Controlled at 1500 psia
1800

Gas breaks
through
second riser

Produced fluids move


up second riser

1600

1400

Pig moves up
second riser

1200

1000

800

600

400

200

Pig reaches base of first riser

0
0

0.5

1.5

Time (H)

2.5

3.5

Black Oil System: Displacement


Hydrate Prevention - Shutdown
During Prevention time, displace produced fluids
from flowline
Topsides design considerations
Available backpressure
Circulation rate
Limited by pig integrity
Typically 3-5 ft/sec
May be faster for straight-pipe

Storage volume
Circulation passes
With pig: 1 residence time
Without pig: 2-3 residence times for efficient water removal

Black Oil System: Displacement


Hydrate Prevention Dry Tree
During shutdown, how quickly will fluids fall below
SCSSV?
Very little work done with L/D ratios >100 (deepwater riser
~10000)
Field data shows oil/water separation ~ 70-80 ft/hr

Bullhead / displace with non-hydrate forming


chemical to SCSSV
Methanol/MEG (volume concerns)
Heavy diesel (high density, by-pass produced fluids)
Dead oil
Ability to bullhead a function of displacement rate

Black Oil System:


Displacement Checklist
Is there sufficient time to accomplish displacement
operation?
Sufficient insulation / Cooldown time

Is the topsides facility designed to accomplish displacement


operation?
Pump capacity
Storage capacity

Can system be restarted into crude-oil filled flowline?


Displace with gas?
High pour point fluids what is the restart pressure required?

For dry trees, is a proper fluid available for displacement?

Black Oil Systems:


Restart Design Considerations

Black Oil System: Cold Restart


System pressure < hydrate formation conditions throughout
restart?
For deepwater, hydrostatic pressure in riser too high
Separator pressure:
may need alternate start-up vessel

Hydrate inhibition required until arrival temperature reaches


Safe Operating Temperature (SOT)
Maintain hydrate inhibitor rate:
Reduce hydrate inhibitor rate:
shut-in conditions

Fluid completely inhibited


Fluid not completely inhibited to

SOT is minimum topsides temperature that provides


sufficient cooldown time, in the event of an interrupted restart

Black Oil System: Cold Restart


0.60

Methanol Dosage, BBL MeOH/BBL H2O

0.55

0.50

PURE WATER
SEA WATER

0.45

0.40

PRODUCED
WATER
0.35

0.30
1000

1200

1400

1600

1800

2000

2200

Shut-in Pressure, psia

2400

2600

2800

3000

Black Oil System: Cold Restart


50

75% WATER
45

50% WATER

Methanol, gpm

40
35
30
25

25% WATER

20
15
10

5% WATER

5
0
2000

3000

4000

5000

6000

7000

Flowrate, BPD

8000

9000

10000

Black Oil System: Cold Restart


Achievable restart rates determined by:

Shut-in conditions
Fluid GOR
Water cut
Hydrate inhibitor

Rule of Thumb: Greater inhibitor injection rates result in


lower overall inhibitor volumes used during restart
Small tiebacks: 5-10 gpm / well
Large deepwater: 25+ gpm / well

Warm-up trends:
Wellbore: Very quick (<30 minutes)
Flowline: Function of flowrate / water cut / length / insulation

Black Oil System: Cold Restart

Black Oil System: Cold Restart

Cold Restart: Case Study


3 Mile Tieback Warm-up Time
Insulation
Type

5000
STBPD

10000
STBPD

Max
Flowrate

Micro-porous

5.8

2.9

1.1

Pipe-in-pipe

6.1

3.0

1.1

Conventional

9.2

3.5

1.2

Flexible

10.6

3.2

1.1

Buried

> 24

8.4

1.5

Cold Restart: Case Study


15 Mile Tieback Warm-up Time
Insulation
Type

5000
STBPD

10000
STBPD

Max
Flowrate

Micro-porous

> 24

13.0

7.0

Pipe-in-pipe

> 24

14.0

7.2

Conventional

> 24

> 24

10.9

Flexible

> 24

> 24

12.3

Buried

> 24

> 24

> 24

Cold Restart: Case Study


15 Mile Tieback MeOH Volume
Insulation
Type

5000
STBPD

10000
STBPD

Max
Flowrate

Micro-porous

> 850

798

772

Pipe-in-pipe

> 850

814

781

Conventional

> 850

> 1700

1074

Flexible

> 850

> 1700

1053

Buried

> 850

> 1700

> 2300

Black Oil System:


Restart Checklist
Is there sufficient hydrate inhibitor available?
Delivery rates
Storage volumes

How will multiple wells be restarted?


Single well at max. rate
Multiple wells at reduced rate
Single flowline vs. dual flowline

What is the minimum temperature required to


achieve safe conditions?
Safe Operating Temperature (SOT)

Black Oil System:


Summary of Design Considerations
Hydraulics
Ensure Production Delivery Throughout Field Life
Minimize Slugging

Wax Deposition
Minimize Wax Deposition (Insulation/Pigging/Chemicals)

Hydrate Formation
Avoid Steady State Hydrate Formation
Optimize Cooldown Times (Insulation)
Prevent Transient Hydrate Formation
(Depressurization/Displacement/Chemicals)
Minimize Inhibitor Consumption

También podría gustarte