Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Scheduling
Useful Abbreviations
l CPM
Background
l
l
l
l
l
Background
l Most
Continued
framework
l Shows interdependences
l Shows when resources are needed
l Ensures proper communication
l Determines expected completion date
l Identifies critical activities
l Shows
Terminology
l
l
l
Drawn left-to-right
Connections represent predecessors
Terminology
l
l
Continued
Terminology
l
l
l
Continued
Terminology
l Activity
Continued
Figure 8-2
Figure 8-3
l Add
Gantt Charts
l Developed
by Henry L. Gantt
l Shows planned and actual progress
l Easy-to-read method to show current
status
understood
l Provide a picture of the current state of
a project
l Difficult
Figure 8-11
Figure 8-12
Table 8-1
Figure 8-14
(
a + 4m + b )
TE =
6
(b a )
=
6
2
The Results
Table 8-2
Figure 8-15
Continued
Figure 8-16
Slack
Figure 8-16
Slack Values
Table 8-3
Precedence Diagramming
l Finish
to start
l Start to start
l Finish to finish
l Start to finish
Figure 8-17
Microsoft Projects
Table 8-4
Gantt Chart
Figure 8-18
AON Network
Figure 8-19
Figure 8-23
Example
Z=
(D )
50 43)
(
=
=
33
7
= 1.22
5.745
The probability value of Z=1.22 is almost 89% likehood that project will be
completed within 50 days (see Table 8-5)
Example