PROJEK MASS RAPID TRANSIT LEMBAH KELANG JAJARAN SUNGAI BULOH KAJANG
Reference No.
:
Revision
:
00
Date Issued
:
2013
Prepared by
Reviewed by
Approved by
Name:
Tan Jun Jing
Name:
Nigel Maw
Name:
Ian M. Thoms
Position:
Senior Engineer
Position:
HOD SHE
Position:
Project Director
Department
Page 1 of 12
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
AMENDMENT HISTORY
REVISION
DETAILS OF AMENDMENT
NO.
00
First Issue
Page 2 of 12
Table of Contents
1.
PURPOSE
2.
SCOPE
3.
DEFINITIONS
4.
RESPONSIBILITIES
5.
PROCEDURE
6.
CROSS REFERENCE
7.
FLOW CHART
8.
APPENDICES
4
5
7
9
Revision: 00
Page 3 of 12
1.
PURPOSE
The purpose of this procedure is to ensure that the movement of a crane, piling rig or other large plant
item, in high risk areas of the site, is carried out in a safe manner, with all safety measures and
precautions taken to mitigate the hazards identified. This procedure is not intended to control the
slewing or luffing motion of the crane or localized tracking or spragging at the point of work.
This procedure is developed to strengthen the existing control measures implemented by the Works
Package Contractor (WPC) and is in addition to the requirements of the relevant legislation, contract
requirements and WPCsown procedures. The implementation of this procedure does not relieve the
WPC of their statutory or contractual requirements or obligations.
2.
SCOPE
This Procedure is applicable to all PDP Works related to the KVMRT Project carried out by the Works
Package Contractors (WPCs). It is mandatory for the WPCs and their Sub-contractors.
3.
DEFINITIONS
Supervising Consultant
CRE/SRE
RE (Safety)
SIow/IoW
WPC
Appointed
Supervisor
drilling operations.
High Risk
Area(s)
Area(s) in the site in which the operation of a crane and/or piling rig
may affect the safety of members of the public and which include, but
not limited to areas adjacent to schools, public footpaths, roads,
highways, railways, overhead power lines, public areas and premises.
piling rig
Spragging
RESPONSIBILITIES
Identification of High Risk Areas
The WPC shall carry out an assessment of the site area(s) under his responsibility, to identify any high
risk areas within the boundaries of the site and shall record the same on a site layout drawing.
The layout drawing is to be submitted to the CRE/SRE for review and comment.
The classification of an area may change, depending on the length of the jib or boom of the crane or
piling rig being used.
The layout drawing shall be up-dated immediately by the WPC, if there is a change in the designation
of the site area.
A copy of the layout drawing showing the areas of the site which are classed as high risk, shall be
posted at each entrance to site, on appropriate notice boards and in the site office. In addition, each
crane and piling rig operator shall be issued with a copy which shall remain in the cab at all times.
The WPC shall inform all their supervisors and operators of the locations of the high risk areas and
requirements of the permit to move system.
Apart from localized movements in the immediate vicinity of the work permit, movement of a crane or a
piling rig in a high risk area is prohibited until a permit to move is issued by the WPCs
Appointedupervisor. S
Page 5 of 12
Provide sufficient resources, instruction, supervision and training to ensure the effective implementation of this
procedure, Permit to Move system and install adequate safety measures to mitigate the hazards.
To appoint adequate supervisors (Appointed Supervisors) to be responsible for the issuing of Permit to Move and for
monitoring the crane or piling rig during the move.
To delegate sufficient authority to the Appointed Supervisors and Operators to ensure that they can carry out their
duties in this procedure effectively and may suspend work where they believe it is unsafe to continue.
To provide the SC (CRE/SRE) with a list of the names of the Appointed Supervisors.
Monitor and ensure the effective implementation of this procedure and the Permit to Move system
The banksman must place himself in a position visible to the crane/ rig operator at all times.
Page 6 of 12
Agree with the Appointed Supervisor, the safety measures which must be taken before the movement of the crane or
piling rig.
Ensure that all the required safety measures identified by the Appointed Supervisor have been implemented prior to
the movement of the crane or piling rig.
Understand and comply with the restrictions and safety requirements stipulated in the Permit to Move.
PROCEDURE
Issuance of a Permit to Move
The Permit to Move can only be issued subject to the following conditions:
After the Appointed Supervisor and the Operator have both agreed that the requirements listed on the Permit to Move
have been satisfied, they shall both sign the Permit to Move.
A copy of the Permit to Move shall be readily available in the driving cab of the crane or piling rig, for inspection.
The duration of the Permit to Move shall be kept to a minimum, but shall be no longer than 3 working days and shall
be retained in the driving cab of the crane or piling rig, for inspection for at least 7 days following the move.
The Permit to Move shall remain valid, only if the Appointed Supervisor, Operator, hazards, ground conditions, and
size of the crane or piling rig do not change.
Following significant heavy rainfall for a prolonged period on the site, all Permits to Move shall be re-assessed.
5.2.3
The SC shall conduct random checks on the validity of the Permit to Move issued to
the crane and piling rigs and shall suspend any non- conformance, and report the
situation to the CRE/SRE and WPCs senior management immediate
Page 7 of 12
WPC shall provide specific training on crane and piling rig safety to all Operators of crane and piling rigs
Specific initial training on crane and piling rig safety
Specific refresher training on crane and piling rig safety every 6 months;
Training on the requirements of the Permit to Move Procedure; and
Weekly tool box talks to discuss crane and piling rig safety issues and up- date the Operators on relevant
information regarding the Permit to Move system.
When conducting the initial training, the Crane and Piling Rig Operators Safety Training pack produced by the WPC
are to be reviewed and agreed with the CRE/SRE, and RE(Safety) before use. The WPC may add additional
information that will be beneficial for the training as deemed fit.
The WPC shall issue a course attendance card to the Operators who have attended the training. A sample of the
Crane and Piling Rig Operators Safety Refresher Course attendance card is available under Appendix B.
Disciplinary Actions
Appointed Supervisors and Operators, who willfully contravene the requirements in this procedure, or contravene
any requirement for the safe movement or safe use of cranes or piling rigs, shall be liable to be removed from the
Page 8 of 12
Records
The table below details the records to be kept
Record Description
Record Location/
Minimum
Retention Responsibility
Retention Time
Expired Permit to
ContractorsOffice
6 months
Move
Current Permit to
Control cabin of the crane or piling rig
As long as the permit is
Move
effective and 7 days after
ContractorsOffice
CROSS REFERENCE
Permit to Operate - Cranes and Piling Rigs Working in High Risk Area
FLOW CHART
Nil
APPENDICES
Appendix A - Sample of Permit to Move (English & Bahasa Malaysia)
Appendix B - Sample of Appointed SupervisorsandPilingRigSafety Courserane
Attendance Card
Sample of Crane and Piling Rig Operators Refresher Course Attendance Card
Page 9 of 12
Appendix A
Sample of Permit to Move (English)
I - DESCRIPTION
Contract No:
Date:
/
Time:
In force until:
(Maximum 3 days)
Date:
/
Time:
Move From
To
Model / Type :
Crawler
Hydraulic
Piling Rig
Serial No :
Other :
Name of Operator :
Licence No :
Name of Banksman :
TICK AS APPROPRIATE
Excavations
Public Areas
Other Cranes
Slopes
Roads
Culverts
Railways
Uneven Ground
Schools
Vicinity
Overhead Lines
Public Footpaths
Other
Underground Services
Buildings
TICK AS APPROPRIATE
as possible
to the plant
parking position
Others:
Others:
Others:
IV AUTHORITY TO MOVE
I HAVE ASSESSED THE HAZARDS IN THE AREA IN WHICH THE CRANE OR PILING RIG IS TO BE MOVED. I AM SATISFIED
THAT THE AREA IS SAFE FOR THE MOVEMENT OF THE CRANE OR PILING RIG AND I AUTHORISE THE MOVE TO PROCEED.
Appointed Supervisor
Name
Signature
Date
V OPERATOR
I AM AWARE THAT AS THE OPERATOR, I AM RESPONSIBLE FOR THE SAFE MOVEMENT OF THE CRANE OR PILING
RIG. I AM AWARE OF THE HAZARDS IN THE AREA AND I AM SATISIFIED THAT THE NECESSARY SAFETY
PRECAUTIONS HAVE BEEN TAKEN. I AM SATISFIED THAT THE CRANE OR PILING RIG IS SAFE TO MOVE.
Operator
Name
Signature
Date
Page 10 of 12
Xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
Appendix A
Sample of Permit to Move (Bahasa Malaysia)
I - BUTIRAN
No Kontrak :
Tarikh :
Masa:
Masa:
Bergerak Dari :
Ke :
Kren Hidraulik
Mesin Cerucuk
No Siri:
Lain - Lain :
Nama Operator :
No Lesen:
Nama Banksman :
Pengorekan
Kawasan Awam
Kren Lain
Cerun
Jalan Raya
Paip Pembetung
Kereta Api
Sekolah
Berdekatan
Lain-Lain
Bangunan
tersebut
parkir
Lain-Lain:
Lain-Lain:
Lain-Lain:
SAYA TELAH MENGENAL PASTI BAHAYA DI KAWASAN INI BAGI PERGERAKAN KREN/MESIN CERUCUK. SAYA BERPUAS
HATI BAHAWA KAWASAN TERSEBUT ADALAH SELAMAT UNTUK KREN/MESIN CERUCUK DAN MEMBENARKAN
Penyelia Dilantik :
Nama
Tandatangan
Tarikh
V OPERATOR
SAYA MENYEDARI BAHAWA SEBAGAI OPERATOR, SAYA BERTANGGUNGJAWAB UNTUK MEMASTIKAN PERGERAKAN
KREN/MESIN CERUCUK SELAMAT. SAYA SEDAR AKAN BAHAYA DI SEKITAR KAWASAN KERJA DAN JUGA TELAH
MEMASTIKAN SEMUA LANGKAH KESELAMATAN TELAH DIAMBIL. SAYA BERPUAS HATI BAHAWA KREN/MESIN
Operator
Nama
Tandatangan
Tarikh
Page 11 of 12
Xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
Appendix B
Sample of Supervisor Crane and Piling Rig Safety Course Attendance Card
Date of Issue :
Attendance Certificate at
Supervisor Crane and Piling Rig
Safety Course
KVMRT PROJECT
Holders Name :
Reference No :
Sample of Crane and Piling Rig Operators Refresher Course Attendance Card
Attendance Certificate at
Crane and Piling Rig Operator Safety
Refresher Course
KVMRT PROJECT
Holders Name :
Page 12 of 12