Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Work Item
Quantity
(User input)
Unit
Production
Days
Rate
(Calculated)
Lin. Ft.
3,001
CY
20
Lin. Ft.
8
SY
6,209
Lin. Ft.
2,001
Lin. Ft.
754
CY
1,144
CY
650
CY
2,198
CY
2,353
CY
3,600
CY
4,705
CY
99
CY
1,120
CY
1,503
SF
8,070
CY
2,777
CY
1,667
CY
63
SY
172
Lin. Ft.
121
Category Total:
CY
157
CY
21
Lin. Ft.
148
Lin. Ft.
148
Lin. Ft.
98
Lin. Ft.
69
Lin. Ft.
49
Lin. Ft.
200
Each
2
Each
2
Each
2
Each
5
Category Total:
ROADWORK
Removal, Concrete
Removal, Concrete Curb & Gutter
Pavement Removal
Pavement Cutting (AC)
Pavement Cutting (PCC)
Foundation Excavation
Excavation, Channel
Embankment
Excavation (Highway Trucks)
Excavation (Scrapers)
Excavation (excavator off road)
Excavation, Rock
Granular Embankment, Special
Stone Embankment
Subgrade Stabilization (1'-8" Average Depth)
Cement Treated Base (Max)
Cement Treated Base (Min)
Riprap
Riprap, Concrete
Pipe Removal
1 of 4
Each
150
Lin. Ft.
249
Lin. Ft.
351
Lin. Ft.
298
Lbs
2,500
Lbs
5,001
CY
10
SF
4,304
Lbs
25,005
Lin. Ft.
79
Lin. Ft.
79
Lin. Ft.
79
Lin. Ft.
295
SF
495
SF
1,076
SF
215
Lin. Ft.
26
SF
1,614
Lin. Ft.
492
Lin. Ft.
800
Lin. Ft.
492
SF
6,994
Category Total:
SF
126,538
SF
72,307
CY
2,778
CY
2,778
TONS
1,485
CY
399
CY
481
CY
399
CY
3,472
CY
2,083
Category Total:
SF
SF
TONS
TONS
Days
Lin. Ft.
SF
Lin. Ft.
SF
SF
Lin. Ft.
Lin. Ft.
BASES
Cold Plane Pavement Removal (Max)
Cold Plane Pavement Removal (Min)
Aggregate Base
Aggregate Shoulder
Chip Seal (Add 1 Day to Broom)
Rock Production (1/2"-3/8")
Rock Production (3/4"-0)
Rock Production (3/8"-#10)
Rock Production (Max)
Rock Production (Min)
WEARING SURFACES
Recycling, Cold In Place
Recycling, Hot In Place
A.C. Paving (Max.)
A.C. Paving (Min.)
Mix Design (AC)
Paved Ditch
Concrete Pavement, Continuously Reinforced
PCC Reinf.
PCC Pavement, Unreinf. 6" (Max)
PCC Pavement, Unreinf. 6" MM (Min)
Curb & Gutter, Concrete
Curb, Concrete (3 Day Minimum, Cure 1 Week)
317,420
166,780
1,980
1,320
28
298
2,195
1,476
56,490
32,280
298
1,000
2 of 4
SF
SF
1,076
247
Category Total:
Lin. Ft.
1,000
Lin. Ft.
1,000
Each
500
SF
43
Lin. Ft.
14,996
Lin. Ft.
20,008
Category Total:
SF
355
Days
120
Lin. Ft.
374
Days
45
Days
70
Days
90
Days
110
Days
130
Days
120
Each
4
Each
4
Each
4
Category Total:
CY
350
SF
904
Each
22
Each
2,000
Each
17
Each
300
Lin. Ft
200
Lin. Ft
492
Each
10
Category Total:
TONS
TONS
SF
TONS
GAL
Lbs
Lin. Ft.
CY
CY
CY
OTHER
Bituminous Base (Max)
Bituminous Base (Min)
Bituminous Concrete Base Course Widening 9"
Bituminous Concrete Binder & Surface Course, Sub 1-11
Bituminous Materials Pumped
Cleaning and Painting
Electric Cable
Excavation, Cofferdams
Grading (Broken)
Grading (Max)
1,980
792
1,098
524
500
10,309
2,499
74
601
1,961
3 of 4
CY
784
CY
299
CY
1,120
CY
1,120
CY
1,120
Lin. Ft.
499
SF
3,002
Days
21
Days
35
SF
3,002
Lin. Ft.
2,640
Lin. Ft.
10,562
SF
75
SF
2,195
SF
1,194
SF
97
Lin. Ft.
8,178
Lin. Ft.
499
Days
25
Lin. Ft.
33
Lin. Ft.
16
Lin. Ft.
98
Each
30
Category Total:
4 of 4