TRANSPORTATION PROJECT SCHEDULING WORKSHEET

PRODUCTION RATES - ENGLISH


PRODUCTION RATES ARE AVERAGE VALUES.
RATE MODIFICATIONS MAY BE NECESSARY TO MEET SPECIFIC PROJECT CONDITIONS.
USER ASSUMES ALL RESPOSIBILITY FROM USE AND/OR MODIFICATION OF THESE RATES.

Work Item

Quantity
(User input)

Unit

Production
Days
Rate
(Calculated)

MOBILIZATION AND TRAFFIC CONTROL


Barrier, Temporary

Lin. Ft.

3,001

CY
20
Lin. Ft.
8
SY
6,209
Lin. Ft.
2,001
Lin. Ft.
754
CY
1,144
CY
650
CY
2,198
CY
2,353
CY
3,600
CY
4,705
CY
99
CY
1,120
CY
1,503
SF
8,070
CY
2,777
CY
1,667
CY
63
SY
172
Lin. Ft.
121
Category Total:

CY
157
CY
21
Lin. Ft.
148
Lin. Ft.
148
Lin. Ft.
98
Lin. Ft.
69
Lin. Ft.
49
Lin. Ft.
200
Each
2
Each
2
Each
2
Each
5
Category Total:

ROADWORK
Removal, Concrete
Removal, Concrete Curb & Gutter
Pavement Removal
Pavement Cutting (AC)
Pavement Cutting (PCC)
Foundation Excavation
Excavation, Channel
Embankment
Excavation (Highway Trucks)
Excavation (Scrapers)
Excavation (excavator off road)
Excavation, Rock
Granular Embankment, Special
Stone Embankment
Subgrade Stabilization (1'-8" Average Depth)
Cement Treated Base (Max)
Cement Treated Base (Min)
Riprap
Riprap, Concrete
Pipe Removal

DRAINAGE AND SEWERS


-Trench and Backfill
-Trench and Backfill - low production
-Storm Sewer (1' - 2' dia)
Pipe under pavement
-Storm Sewer (2' + dia)
-Storm Sewer in Rock (Max)
-Storm Sewer in Rock (Min)
-Storm Sewers
drywells, New
Inlets, New
Manholes, New
Inlets, Adjust

1 of 4

TRANSPORTATION PROJECT SCHEDULING WORKSHEET


BRIDGES AND STRUCTURES
Holes Drilled, Concrete 4" dia
Piles, Driving Concrete
Piles, Driving Steel
Piles, Driving Timber
Reinforcement (Substructure)
Reinforcement (Superstructure)
Structural Concrete, Lightweight
Class 1 Deck Preparation
Structure Steel, Erecting
Handrail, Erecting
Handrail, Metal
Handrail, Aluminum
Rail, Type F - Pour Concrete
Membrane Waterproofing
Wall, MSE (Max)
Wall, MSE (Min)
Walls, Bin (Add 1/2 Day for Backfill)
Walls, Sound - Block Masonry
Walls, Sound - Block Masonry Footing(Exc.,Form, Pour)
Walls, Sound - Post & Panel (8' x 8' Max)
Walls, Sound - Post & Panel(8' x 8' Min)
Microsilica Overlay( 3" Deep)

Each
150
Lin. Ft.
249
Lin. Ft.
351
Lin. Ft.
298
Lbs
2,500
Lbs
5,001
CY
10
SF
4,304
Lbs
25,005
Lin. Ft.
79
Lin. Ft.
79
Lin. Ft.
79
Lin. Ft.
295
SF
495
SF
1,076
SF
215
Lin. Ft.
26
SF
1,614
Lin. Ft.
492
Lin. Ft.
800
Lin. Ft.
492
SF
6,994
Category Total:

SF
126,538
SF
72,307
CY
2,778
CY
2,778
TONS
1,485
CY
399
CY
481
CY
399
CY
3,472
CY
2,083
Category Total:

SF
SF
TONS
TONS
Days
Lin. Ft.
SF
Lin. Ft.
SF
SF
Lin. Ft.
Lin. Ft.

BASES
Cold Plane Pavement Removal (Max)
Cold Plane Pavement Removal (Min)
Aggregate Base
Aggregate Shoulder
Chip Seal (Add 1 Day to Broom)
Rock Production (1/2"-3/8")
Rock Production (3/4"-0)
Rock Production (3/8"-#10)
Rock Production (Max)
Rock Production (Min)

WEARING SURFACES
Recycling, Cold In Place
Recycling, Hot In Place
A.C. Paving (Max.)
A.C. Paving (Min.)
Mix Design (AC)
Paved Ditch
Concrete Pavement, Continuously Reinforced
PCC Reinf.
PCC Pavement, Unreinf. 6" (Max)
PCC Pavement, Unreinf. 6" MM (Min)
Curb & Gutter, Concrete
Curb, Concrete (3 Day Minimum, Cure 1 Week)

317,420
166,780
1,980
1,320
28
298
2,195
1,476
56,490
32,280
298
1,000

2 of 4

TRANSPORTATION PROJECT SCHEDULING WORKSHEET


Sidewalks, Concrete
Pavers, Unit (Max.) See Means Data

SF
SF

1,076
247
Category Total:

PERMANENT TRAFFIC CONTROL AND GUIDANCE DEVICES


Guard Rail (3 Day Minimum)
Barrier, Permanent
Delineators
Pavement Marking Symbol, Thermoplastic
Pavement Marking, Thermoplastic
Pavement Marking, Permanent Painted

Lin. Ft.
1,000
Lin. Ft.
1,000
Each
500
SF
43
Lin. Ft.
14,996
Lin. Ft.
20,008
Category Total:

PERMANENT TRAFFIC CONTROL AND ILLUMINTATION SYSTEMS


Signs
Illuminaire Poles (Manufacture & Test)
Signal Conduit, Laying
Signal Construction (1 Signal)
Signal Construction (2 Signals)
Signal Construction (3 Signals)
Signal Construction (4 Signals)
Signal Construction (5 Signals)
Signal Poles (Manufacture & Testing)
Traffic Signal Head Alterations
Traffic Signal Posts
Traffic Signal Posts, Relocate Existing

SF
355
Days
120
Lin. Ft.
374
Days
45
Days
70
Days
90
Days
110
Days
130
Days
120
Each
4
Each
4
Each
4
Category Total:

CY
350
SF
904
Each
22
Each
2,000
Each
17
Each
300
Lin. Ft
200
Lin. Ft
492
Each
10
Category Total:

TONS
TONS
SF
TONS
GAL
Lbs
Lin. Ft.
CY
CY
CY

RIGHT-OF-WAY DEVELOPMENT AND CONTROL


Top Soil
Sodding
Trees, Evergreens
Trees, Seedling
Trees, Shade
Shrubs
Fence, Chain Link
Fence, Woven Wire
Mail Boxes (3 Day Minimum)

OTHER
Bituminous Base (Max)
Bituminous Base (Min)
Bituminous Concrete Base Course Widening 9"
Bituminous Concrete Binder & Surface Course, Sub 1-11
Bituminous Materials Pumped
Cleaning and Painting
Electric Cable
Excavation, Cofferdams
Grading (Broken)
Grading (Max)

1,980
792
1,098
524
500
10,309
2,499
74
601
1,961

3 of 4

TRANSPORTATION PROJECT SCHEDULING WORKSHEET


Grading (Small)
Granular Backfill
Gravel or Crushed Stone Base Course
Gravel or Crushed Stone Shoulders
Gravel or Crushed Stone Surface Course
Gutter, Concrete
Median Surface (Concrete)
Mix Design (CTB)
Mix Design (PCC)
Patching, Cold 2"
Pavement Marking, Durastripe Non-Profile Inlaid
Pavement Marking, Durastripe Non-Profile Overlay
Pavement Removal and Replacement
PCC Base Course
PCC Base course Widening
PCC Driveway
PCC Stringline
Pipe Underdrains
Qualify Pit
Rail Demolition (Std. Dwg. BR280)
Rail Retrofit - Drill holes & place steel (Std. Dwg. BR280)
Rail, Type F, Tie Steel Cages (Std. Dwg. BR280)
Right of Way Markers, Erecting

CY
784
CY
299
CY
1,120
CY
1,120
CY
1,120
Lin. Ft.
499
SF
3,002
Days
21
Days
35
SF
3,002
Lin. Ft.
2,640
Lin. Ft.
10,562
SF
75
SF
2,195
SF
1,194
SF
97
Lin. Ft.
8,178
Lin. Ft.
499
Days
25
Lin. Ft.
33
Lin. Ft.
16
Lin. Ft.
98
Each
30
Category Total:

4 of 4