Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Key Messages
PV power plant is a cost-effective energy resource
Inverters
Combiner
Boxes
Transformers
300 to
690V (AC)
1000V (DC)
Photovoltaic
Combining
Switchgear
Substation
Gen Tie-line
Power Grid
69 to 525kV (AC)
PV Module
PV Module
Arrays
1000V (DC)
Combiner Box
Combiner
Boxes
(80KW-160KW)
Provides single dc output to inverter
1000V (DC)
1000V (DC)
Transformer
Increases low AC voltage to medium
Transformers
300 to
690V (AC)
Photovoltaic
Combining
Switchgear
10
step up transformer
Delivers electricity to the grid
Substation
Gen Tie-line
Power Grid
69 to 525kV (AC)
11
12
Reliable bulk power generation utilizing advanced plant controls and forecasting
AGUA CALIENTE
13
COPPER MOUNTAIN 1
14
GREENOUGH RIVER
15
16
PHALODI
17
18
19
20
Power
Flow
Power
Flow
Conventional Centralized
Generation
22
Source: U.S. Department of Energy. "Benefits of Using Mobile Transformers and Mobile Substations for Rapidly Restoring Electric Service: A Report to the United States Congress
Load
Increase
100kW
respond instantly to
change its output
Bulk electricity storage is
not common
23
Source: U.S. Department of Energy. "Benefits of Using Mobile Transformers and Mobile Substations for Rapidly Restoring Electric Service: A Report to the United States Congress
Load
Increase
100kW
Load
Decrease
500kW
24
Source: U.S. Department of Energy. "Benefits of Using Mobile Transformers and Mobile Substations for Rapidly Restoring Electric Service: A Report to the United States Congress
25
12
Time of Day
18
24
day ahead)
26
Actual
Load
12
Time of Day
18
24
27
Regulation:
output (secs to
minutes)
Regulation = Actual Load Real-time Forecast Load
Load Following = Real-time Forecast Load Hourly Schedule
Automatically
adjusts generator
28
Load Balancing
Milliseconds to Minutes
Hours to Days
Years
PV solar
intermittency raises
grid stability and
reliability concerns
PV Variability
increases
operational
complexity
Higher PV
penetration
requires increased
grid flexibility
29
Load Balancing
Msec to Minutes
Hours to Days
Years
CONCERN
LEARNING
30
31
Substation
House 2
20 kV
0,4 kV
Conductor
House 1
Transformer
Reverse Flow
Voltage
Violation
Distance
Normal Flow
Voltage Drop
Maximum
Load
P
Last 1
Allowable
Range
Voltage
Q
Last 2
High Feed-in
Low Load
High Feed-in
Low Load
+ Reactive Power
Source: Bernd Engel, SMA
MV Grid
IEEE 1547
prohibits
voltage
control
32
Voltage Regulation
34
Reduced
Power
35
Combiner
Boxes
Photovoltaic Combining
Switchgear (PVCS)
Substation
Power Grid
Inverters
Transformer
Checks grids actual conditions and
required set points
Real-time Controllers
Short Term
Forecasting
Set Points
Satellite Imagery
36
Inverter
Curtailed
Locally
Plant
Output Limit
37
Plant
Plant
Output
OutputLimit
Limit
38
Inverters
Change
VAr Output
Source: Agua Caliente PV Plant in Yuma, Arizona, USA May 23, 2012. ~212MW on-line.
Reaches 90%
Steady State Value
in ~ 3.2 seconds
40
Set Point
Reduced
Source: Agua Caliente PV Plant in Yuma, Arizona, USA March 13, 2012. ~90MW on-line.
Set Point
Increased
41
Source: Agua Caliente PV Plant in Yuma, Arizona, USA March 13, 2012. ~90MW on-line.
Plant Start
Command
Inverters are
Turned Off in
Sequence;
Ramp Rates
are Controlled
Inverters are
Started in
Sequence
42
43
(Source: SMA)
44
45
Load Balancing
Msec to Minutes
Hours to Days
Years
CONCERN
Solar Generation is not fully dispatchable
Load Balancing
Hours to Days
LEARNING
46
Net Demand
LoadCurve
(MW) (MW)
Net Load
12
Time of Day (Hours)
24
Source: SEC Data. 2020 Load and Generation Mix Projected @5.6% annually for illustration purposes only. FS estimate on PV contribution. Actual resource distribution likely to be different.
Daily Load
PV Solar
47
Single Location
20 Bundled Locations
48
Average Irradiance
49
Yuma County
Dateland, Arizona USA
2,400 Acres
39,000 Tons Steel
PPA: PG&E
EPC/O&M: NRG
3.0 Miles
North America
Largest PV Plant
Enbridge Sarnia
80 MW
50
3.9 Miles
3.1 Miles
NRG Agua
290MW ac
51
Load Balancing
Msec to Minutes
Hours to Days
Years
CONCERN
Variable generation requires grid flexibility
LEARNING
52
53
Hydro
Gas GT
Generation
Peaking
Generation
Gas CCGT
Mid-Merit
Generation
Mid-Merit
Generation
Base Load
Generation
Base Load
Generation
System Load
Peaking
54
20000
15000
Dispatchable Renewables
Wind
Solar
5000
0
2006 (~10%)
2012 (20%)
2020 E (33%)
Operators have managed high penetration. Others can leverage this learning.
CAISO Testimony in 2010 CPUC LTPP Docket No. R.10-05-006; July 1, 2011; Exhibit 1, slide 5; trajectory scenario
10000
55
Source: CAISO
Matt Burkhart
SDGE, Sempra
Feb 13,2013
Solar Power Gen San Diego
56
56
Source: CAISO
Matt Burkhart
SDGE, Sempra
Feb 13,2013
Solar Power Gen San Diego
57
57
Study needed to determine shape of Flexibility Supply Curve and Quantify Costs
Storage
Wind/Solar
Curtailment
Traditional
Storage
Flexible
Generation
Hydro with Dams
Pumped Hydro
Gas Storage
Markets
Low
Cost
Real-Time
Hour Ahead
Day-Ahead
Price Responsive Load
Ancillary Service
In Range of
1 or 2%
Batteries
Flywheels
CAES
PHEV
Simple Cycle GT
Combined Cycle
Some Coal Plants
Sources of Flexibility
High
Cost
58
Conclusions
Modern PV plants can contribute actively to grid stability and
reliability
PV variability can be managed without significant impact to
existing grid infrastructure through site diversity and
forecasting
59