Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Executive Summary
1
The publications department has currently recognized a problem with the review process
which directly impacts the departments’ rate and sales. Schwalbe (2009) takes on the definition
“temporary endeavor undertaken to create a unique product, service or result.” The result we
would like to accomplish here is to reduce the length of the review process. In doing, so we hope
system (GEMS) to help facilitate the review process. To meet this goal, we will build a project
team that is to accomplish this project within a 12 month timeframe with a budget of $5000. The
project entails building a work breakdown schedule with assigned tasks. Furthermore we assess
In this project plan we will present a defined scope, a disciplined timeline, and adequate
processes, which address topics such as risk management and staffing needs critical to the
success of the project. The success of this project is critical to shortening the review process
Table of Contents
2
Contents
I. INTRODUCTION__________________________________________________4
II. PROJECT MANAGEMENT PLAN___________________________________4
III. PROJECT OVERVIEW_____________________________________________4
Project Goal ______________________________________________________4
Definitions and Acronyms ___________________________________________4
Stakeholder Analysis _______________________________________________5
Project Manager ___________________________________________________5
Project Team _____________________________________________________5
Team Contract ____________________________________________________5
Project Deliverables ________________________________________________5
Introduction
3
The publications department at American Geophysical Union (AGU) is one of the major
sources of revenue for the organization. Specifically the department contributes to 69% of the
organizations profits. (www.agu.org). Publication covers research in non-organic science which
is disseminated through journals and books. The peer review process is a necessary criterion for
all publications at AGU. Recently the process has been deemed lengthy and time consuming and
this in turn directly impacts the number of journals and books that are published in a year.
Geophysical Electronic Manuscript Submission System (GEMS) is used with the help of the
Editor’s Assistants (EA) to facilitate the review process. Submissions, reviews and decisions are
submitted respectively by authors, reviewers and editors, through the GEMS.
Our goal is to devise a plan that will enhance the review process with the help of GEMS and
as a result increase the publications of journals and books. By increasing our publication of
journals and books we expect to see an increase in sales and revenue.
Project Goal: The goal for this project is to increase publications of journals and books by 5% by
making the review process more efficient with the help of GEMS. Our time frame for assessing
GEMS will be one year, from January 4th ending December 20th.
Acronym Definition
AGU American Geophysical Union
4
Stakeholder Analysis: Stakeholders for this project are reviewers, editors, associate editors,
assistant editors, and authors. Stakeholders are affected because changes to GEMS will increase
efficiency and ensure effective manuscript submission process. Due to changes in GEMS work
assignments may shift or be eliminated to allow ease of use.
Project Manager: Rochelle Odon
Project Team:
Senior Editor’s Assistant
Editor’s Assistant 1
Editor’s Assistant 2
Editor
Associate Editor
GEMS onsite personnel
GEMS Contractor
Team Contract: Our project team is governed by a structure of rules that encourage open
communication and progressive contributions, including constructive input where each
participant explores all plausible options in the pursuit of the successful completion of our agreed
objective. Additionally, each member agrees to continually contribute ideas for improving and
enhancing the functionality and utility of the project as needed.
Project Deliverables: Weekly reports would be used to identify and analyze the progress of the
project and any problems occurring within the project. The team members will meet weekly to
discuss the reports. At the conclusion of the project all necessary data such as lessons learned,
project summary and assessments will be assembled and made available to all members for
referral.
5
II. Project Organization
Organizational Structure:
Project
Manager
Rochelle
Tamika
Senior
GEMS
Editor’s
Contractor
Assistant
Organizational Boundaries and Interfaces: The organizational flow of duties reflects two team
members, the GEMS Contractor and the Senior Editor’s Assistant, reporting directly to the
project manager. These two team members are responsible for supervising the remaining team
members, managing the execution of duties and the progress in regards to the completion of the
project. With that feedback, they continuously synthesize the updated data and adjust outlined
objectives accordingly.
Dependencies:
Tasks completed through GEMS are independent of order. However in the project analysis, the
first few phases will be a finish-to-start process where the forerunner task finishes, the successor
task starts. The last phases will be more of a task that continues only as long as another task is in
progress.
Resource Requirements:
Editor’s assistant will be in charge of testing so each will be assigned responsibilities that match
their skill area. Our onsite GEMS help desk personnel will assist EA’s with their responsibilities
and provide necessary feedback and suggestions requirements. Our onsite GEMS personnel will
also ensure that the necessary programs and software are in place to ensure effective testing and
analysis.
Budget Requirements: Cost for improvement should not exceed $5000. The Idea here is to
restructure GEMS to be more efficient without having to spend too much money on upgrades.
We established that some enhancements may cost more and these would be adopted on a
necessity basis.
7
Schedule:
Schedule:
Identify constraints
8
June 15 Receive final approval on test site
Close out
9
Project Responsibilities: Team members are responsible for the completion of their assigned
tasks. The Project manager will supervise the progress of the each member’s tasks and will
support the team in completing all tasks within the agreed time frames. The GEMS help desk
will support and advice team members on assigned tasks.
IV. Managerial Process
Assumptions, Dependencies, and Constraints: This project relies on assigned duties being
completed on time. The project team will implement plan with full to complete time. The feat of
this project is dependent upon the corporation of the department’s manager and GEMS help desk
personnel. Constraints identified within this project relate to enhancements that may needed yet
due to limits on funds that will not permit upgrades. Both IT personnel and team members need
to work together as a team in order for project to be deemed successful. If a problem arises the
team will work to correct the problem efficiently.
Risk Management: The team will develop the availability of risk tools and practices such as
checklists, risk scorecard, change management processes, risk quantification sessions, and risk
response strategies. To evaluate identified risk, the project team will employ the Risk & Control
Matrix (RCM) to calculate the likelihood of the risk happening and the impact if the risk does
occur (Schwalbe, 2009)
Monitoring and Controlling Mechanisms: To ensure that projects are meeting organizational
objectives project managers will setup effective communication and controlling mechanisms that
is based on up-to-the-minute facts about the project. This will permit the project manager to
constantly improve and regulate to the varying needs of our department. In addition to progress
reports, Gantt chart and change requests will be implemented to improve project success.
10
V. Operations Management Plan
Information System Objectives: The objective here is to use our Information’s System
department to help restructure GEMS to be more efficient. The IS department is responsible for
constructing a testing site that will mimic the actual GEMS site. This will enable EAs to
thoroughly analyze GEMS to identify problem areas.
Hardware/Software Requirements: All hardware and software needed for the success of the
project is currently available. If new equipments are needed, a request will be sent to the project
manager for approval.
Information Management Reports: The data analyst will compile and analyze other electronic
manuscript submission systems and present data to project manager
VII. Conclusion
The restructure of GEMS to make the review process more efficient was deemed successful.
Additionally by restructuring GEMS with the help of the information’s systems department and
the project members, we were able to eliminate problems that were not just related to the review
process but also to general tasks in GEMS that made the system much more efficient.
11
References
Baltzan, P., & Phillips, A. (2009). Business driven information systems. McGraw-Hill/Irwin
ISBN
Jacobs, F.R., & Chase, R.B. (2008). Operations and supply management: the core. New York:
McGraw Hill/Irwin
Operations Management. Free management library. Retrieved on December 10th, 2009 from
http://managementhelp.org/ops_mgnt/ops_mgnt.htm
12