Project : Proposed Construction of Retaining Wall at Tamion Production Well

Location : Lower Tamion, Vitali, Zamboanga City


Scope of Works : Construction of 30.00 Linear Meters of Concrete Retaining Wall
A. NON- ENGINEERING BASIC ITEMS
A. SUPERVISION
B. Construction of Temp. Facilities
B. ENGINEERING BASIC ITEMS
I. MOBILIZATION/HAULING OF MATERIALS
II. DEMOLITION OF EXISTING 28.00 LINEAR METERS RIP-RAP
III. DIVERSION WORKS
IV. CONCRETING WORKS
V. SCAFFOLDING WORKS
VI. REBAR WORS
VII. DEMOBILIZATION
Cost of Project :
Qty Unit Unit Cost Sub - Total Total
A. NON- ENGINEERING BASIC ITEMS
A. SUPERVISION
1 - Engineering Assistant 48 days 542.00 26,016.00 26,016.00
Direct Cost 26,016.00
OCM 2602.00
Total Cost of Item A 28,618.00
B. CONSTRUCTION OF TEMP. FACILITIES (Area = 3.00mtrs. X 5.00mtrs., 1 - Unit)
A. Materials
26 pcs. - 2" x 4" x 10' Coco Lumber 173 bd.ft. 20.00 3,460.00
18 pcs. - 2" x 3" x 10' Coco Lumber 90 bd.ft. 20.00 1,800.00
16 pcs. - 2" x 2" x 10' Coco Lumber 53 bd.ft. 20.00 1,060.00
12mm thk x 1.20m x 2.40m Ordinary Plywood 18 shts. 750.00 13,500.00
Gauge 26 x 1.80m Length Corrugated G.I. Roofing Sheets 18 shts. 221.00 3,978.00
Gauge 26 x 1.20m x 2.40m G.I. Plain Sheet 1 sht. 425.00 425.00
2" C.W. Nail 2 kgs. 70.00 140.00
3" C.W. Nail 1 kg. 63.00 63.00
4" C.W. Nail 2 kg. 63.00 126.00
Padlock (Big) 1 pc. 150.00 150.00
3-1/2" Loose Pin Hinges 3 pairs 220.00 660.00
1/8" G.I. Chain (1Kg. Equal to 2mtrs.) 1 kg. 110.00 110.00
2" C.W. Umbrella Roofing Nails 2 kgs. 65.00 130.00 25,602.00
B. Labor:
2 - Carpenters 6 days 366.00 4,392.00
4 - Laborers 6 days 317.00 7,608.00 12,000.00
37,602.00
B. ENGINEERING BASIC ITEMS
I. MOBILIZATION/HAULING OF MATERIALS
A. Equipment Rental
1 - Unit Forward Truck (w/Driver) 14 days 5,500.00 77,000.00
Diesel 2,800 liters 49.00 137,200.00 214,200.00
B. Labor
4 - Laborers 14 days 317.00 17,752.00 17,752.00
Direct Cost 231,952.00
OCM 23195.00
Total Cost of Item I 255,147.00
II. DEMOLITION OF EXISTING 28.00 LINEAR METERS RIP-RAP
A. Labor
2 - Carpenter 8 days 366.00 5,856.00
4 - Mason 8 days 366.00 11,712.00
4 - Steelman 8 days 366.00 11,712.00
10 - Laborers 8 days 317.00 25,360.00 54,640.00
Direct Cost 54,640.00
OCM 5,464.00
Total Cost of Item II 60,104.00
III. DIVERSION WORKS
Note: Diversion the flow of water from river.
A. Labor:
2 - Carpenter 10 days 366.00 7,320.00
4 - Mason 10 days 366.00 14,640.00
4 - Steelman 10 days 366.00 14,640.00
10 - Laborers 10 days 317.00 31,700.00 68,300.00
Php1,582,808.00
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
BILL OF MATERIALS AND COST ESTIMATE
Item Description
Page 1 of 19
B. Equipment Rental/Fuel:
1 - Water Pump 10 days 500.00 5,000.00
Gasoline 40 liters 57.00 2,280.00 7,280.00
Direct Cost 75,580.00
OCM 7,558.00
Total Cost of Item III 83,138.00
IV. CONCRETING WORKS
A. Materials:
Concrete
Portland Cement 1,337 bags 230.00 307,510.00
Washed Sand 51 cu.m. 1,000.00 51,000.00
Gravel (G-1) 101 cu.m. 1,000.00 101,000.00 459,510.00
Forms
12mm thk x 1.20m x 2.40m Ordinary Plywood 21 shts. 750.00 15,750.00
124 124pcs. - 2" x 3" x 8' Coco Lumber 496 bd.ft. 20.00 9920.00
2" C.W. Nail 12 kgs. 63.00 756.00
4" C.W. Nail 16 kgs. 63.00 1008.00 27,434.00
B. Labor:
2 - Carpenter 28 days 366.00 20496.00
4 - Mason 28 days 366.00 40992.00
4 - Steelman 28 days 366.00 40992.00
10 - Laborers 28 days 317.00 88760.00 191,240.00
C. Equipment Rental/Fuel:
1 - Unit Concrete Bagger Mixer 17 days 2,600.00 44,200.00
1 - Concrete Vibrator 17 days 500.00 8,500.00
Special Gasoline 374 liters 57.00 21,318.00 74,018.00
Direct Cost 752,202.00
OCM 75,220.00
Total Cost Item IV 827,422.00
V. SCAFFOLDING WORKS
A. Materials:
84 84pcs. - 2" x 4" x 10' Coco Lumber 560 bd.ft. 20.00 11,200.00
74 74pcs. - 2" x 3" x 10' Coco Lumber 369 bd.ft. 20.00 7,380.00
4" C.W. Nail 28 kgs. 63.00 1,764.00 20,344.00
B. Labor:
2 - Carpenter 14 days 366.00 10,248.00 10,248.00
Direct Cost 30,592.00
OCM 3,059.00
Total Cost Item V 33,651.00
VI. REBAR WORS
A. Materials:
16mm x 6.00m Def. Reinforcing Steel Bar 402 pcs. 511.00
12mm x 7.50m Def. Reinforcing Steel Bar 120 pcs. 363.00
12mm x 6.00m Def. Reinforcing Steel Bar 451 pcs. 290.00 130,790.00
Hacksaw Blade 12 pcs. 53.00 636.00
#16 G.I. Tie-wire 139 kgs. 65.00 9,035.00 140,461.00
B. Labor:
4 - Steelman 30 days 366.00 43,920.00
4 - Laborers 30 days 317.00 38,040.00 81,960.00
C. Equipment Rental
1 - Unit Bar Cutter 15 days 300.00 4,500.00 4,500.00
Direct Cost 226,921.00
OCM 22,692.00
Total Cost Item VI 249,613.00
VII. DEMOBILIZATION
A. Labor:
2 - Carpenter 1 day 366.00 732.00
4 - Mason 1 day 366.00 1464.00
4 - Steelman 1 day 366.00 1464.00
10 - Laborers 1 day 317.00 3170.00 6,830.00
Direct Cost 6,830.00
OCM 683.00
Total Cost Item VII 7,513.00
Page 2 of 19
A. NON- ENGINEERING BASIC ITEMS
A. SUPERVISION
B. Construction of Temp. Facilities
B. ENGINEERING BASIC ITEMS
I. MOBILIZATION/HAULING OF MATERIALS
II. DEMOLITION OF EXISTING 28.00 LINEAR METERS RIP-RAP
III. DIVERSION WORKS
IV. CONCRETING WORKS
V. SCAFFOLDING WORKS
VI. REBAR WORS
VII. DEMOBILIZATION
Prepared by: Reviewed & Checked by: Submitted by:
FELIXBERTO R. CAARE, JR. MARIE CLAIRE C. BONGO MARLI P. ACOSTA-DE FIESTA
Researcher/Analyst A, (J.O.) Officer-In-Charge Officer-In-Charge
Planning & Development Section Planning & Development Section Planning & Design Division
Recommending Approval for
Approved by: Certified as to Availability of Funds: Project Implementation:
CARLOS L. PEREZ, SR. ROBERTO R. MENDOZA ALEJO S. ROJAS, JR.
Officer-In-Charge Assist. General Manager Assistant General Manager
Engineering Department For Finance and Administration Group for Operations
Approved for Project Implementation:
LEONARDO REY D. VASQUEZ
General Manager
37,602.00 PhP
249,613.00 PhP
S U M M A R Y
33,651.00 PhP
7,513.00 PhP
1,582,808.00 PhP
28,618.00 PhP
255,147.00 PhP
60,104.00 PhP
83,138.00 PhP
827,422.00 PhP
Page 3 of 19
PROJECT : Proposed Construction of Retaining Wall at Tamion Production Well
Location : Lower Tamion, Vitali, Zamboanga City
Project Cost :
Project Duration : FIFTEEN (15) Calendar Days
Manpower Requirements : 21 Manpower (1-Engineering Assistant, 10-Laborers, 4-Steelman, 2-Carpenters, & 4-Masons)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
A. NON- ENGINEERING BASIC ITEMS
A. SUPERVISION 1.81%
B. Construction of Temp. Facilities 2.38%
B. ENGINEERING BASIC ITEMS 0.00%
I. MOBILIZATION/HAULING OF MATERIALS 16.12%
II. DEMOLITION OF EXISTING 28.00 LINEAR METERS RIP-RAP 3.80%
III. DIVERSION WORKS 5.25%
IV. CONCRETING WORKS 52.28%
V. SCAFFOLDING WORKS 2.13%
VI. REBAR WORS 15.77%
VII. DEMOBILIZATION 0.47%
TOTAL PROJECT COST 100%
CASH OUTLAY REQUIREMENT
TARGETED COMPLETION THIS PERIOD
COMMULATIVE COMPLETION TO DATE
Recommending Approval for
Prepared by: Reviewed & Checked by: Submitted by: Approved by:Project Implementation :
FELIXBERTO R. CAARE, JR. MARIE CLAIRE C. BONGO MARLI P. ACOSTA-DE FIESTA CARLOS L. PEREZ, SR. ALEJO S. ROJAS, JR.
Researcher/Analyst A (J.O.) Officer-In-Charge Officer-In-Charge Officer-In-ChargeAssistant General Manager for Operation
Planning & Development Section Planning & Development Section Planning & Design Division Engineering Department
Approved for Project Implementation:
LEONARDO REY D. VASQUEZ
General Manager
0.00
0.00%
0.00%
0.00
0.00%
0.00%
% Perfected
C A L E N D A R D A Y S
255,147.00 Php
60,104.00 Php
33,651.00 Php
GANTT CHART
1,582,808.00 Php
Work Item Amounts
37,602.00 Php
1,582,808.00 Php
28,618.00 Php
249,613.00 Php
7,513.00 Php
83,138.00 Php
827,422.00 Php
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar St., Zamboanga City
I. Excavation Works
a. Wall Footing
L: 56.46 m
w: 0.3 m
depth: 0.55 m
Vol: 9.32 cu.m.
10
Rate: 0.7 cu.m./day
Due: 2 days
b. Footing Column
L: 0.4 m
w: 0.4 m
depth: 0.55 m
n: 20 units
Vol: 1.76 cu.m.
10
Rate: 0.7 cu.m./day
Due: 1 day
II. Concreting Works
a. Wall Footing
L: 56.46 m
w: 0.3 m
d: 0.15 m
Vol: 2.54 cu.m.
Cement 25 bags
1 cu.m.
2 cu.m.
b. Footing Column
L: 0.4 m
w: 0.4 m
d: 0.2 m
n: 20 units
Vol: 0.64 cu.m.
Column
L: 0.15 m
w: 0.15 m
d: 1.05 m
n: 20 units
Vol: 0.47 cu.m.
volt: 1.11 cu.m.
Cement 11 bags
0.5 cu.m.
1 cu.m.
Forms and Scaffolding
P = 2 (a+b) + 0.20
Washed Sand
G (G-1)
Washed Sand
G (G-1)
Manpower:
Manpower:
a: 0.15 m
b: 0.15 m
h: 0.85 m
P = 0.8 m
A: 0.68 sq.m.
n: 20 units
5 pcs. Of plywood
Frame 153 bd.ft. - 2" x 3" wood
31 pcs. - 2" x 3" x 10' wood
Steel Works
L: 112.92 m
n: 19 pcs. - 50mm G.I. Pipe
n: 24 pcs. - 50mm x 50mm Mesh x 1.20m x 2.40m Steel Matting
Gate:
6.5 m
1 pc. - 50mm G.I. Pipe
Painting Works
50mm G.I.
A: #REF! sq.m.
n: #REF! gals. - Red Lead Metal Primer
n: #REF! gals. Quick Dry Enamel (Royal Blue)
n: #REF! gals. Paint Thinner
Steel Matting
A: #REF! sq.m.
n: #REF! gals. - Red Lead Metal Primer
n: #REF! gals. Quick Dry Enamel (Royal Blue)
n: #REF! gals. Paint Thinner
Laying of 4" CHB
@ wall footing
L: 56.46 m
d: 0.4 m
A: 23 sq.m.
n: 288 pcs. - 4" CHB
@ wall
L: 54.46 m
H: 0.5 m
A: 27 sq.m.
n: 338 pcs. - 4" CHB
Rebar
vertical
L: 1.2 m
n: 95 pcs.
n per 6m: 5 pcs.
N: 19 pcs. - 10mm Bars
Horizontal
L: 56.46
n: 10 pcs. - 10mm Bars
Tie-wire 2 kgs.
Plastering
A: 55.86 sq.m.
thk: 16 mm 0.192 20.91264
22 bags
2 cu.m.
Rebar Works
10mm Bars #REF! pcs. 3.696 kg. #REF! kgs.
10 kgs./hr./1 steelman
2 steelman
#REF! day - fab.
#REF! day - instal.
#REF!
#REF!
2.3275
Painting @ Masonry
@ 4" CHB Wall
A: 54 sq.m.
@ Ground Tank
A: 76.8 sq.m.
1. Concreting of Plain Flooring 2 men pour 1.2
2. Concreting of Reinf. Flooring 2 men pour 0.84
3. Concreting of Column & Beam 2 men pour 0.50
4. Finishing of Flooring (rough) 2 men finishes
5. Finishing of CHB Joints 2 men finishes
6. Plastering of CHB 2 men plaster
7. Laying of CHB 2 men lay 100
8. Breaking old RC Flooring 2 men break 0.3
9. Laying of glazed tile 4"x4" 2 men lay 100
10. Laying of glazed tile 6"x6" 2 men lay 72
11. Installation of Water Closet 2 men install 1
12. Installation of Lavatory 2 men install 1
13. Installation of G.I. Sheets 32"x8" on Steel Frames 2 men install 11
14. Installation of G.I. Sheets 32"x8" on Wooden Frames 2 men install 20
15. Installation of G.I. Sheets 32"x12" on Steel Frames 2 men install 10
16. Installation of G.I. Sheets 32"x12" on Wooden Frames 2 men install 15
17. Fabricating and Installation of Gutter Downspout, Ridge roll 2 men fab. Install
18. Installation of G.I. Pipe 1/2 x 20" 2 men install 20
19. Installation of Doors and Window Jamp 1 men install 3
20. Installation of Door (Complete of Hinges and Knob) 1 men install 2
21. Fabrication of Doors (Excluding Planning of Frames) 1 men makes 3
22. Planning Rough Lumber (Including Allignment) 1 man Planes 48
23. Planning Rough Lumber (No Allignment) 1 man Planes 120
24. Installation of Plywood Board 2 men install 15
25. Installation of Wooden Post 2 men install 96
26. Installation of Wood Jalousies Windows 1 men install 18.75
I. Earth Works:
a. Excavation 1.82 man hours/cu.m.
b. Backfill 1.34 man hours/cu.m.
II. Form Works:
a. Footing, grade, 2.5 man hours/sq.m.
column
b. Beams, bond beams, 2.8 man hrs./sq.m.
floor slab
c. Roof beams & bond 3.01 man hrs./sq.m.
beams
d. Roof slab 3.34 man hrs./sq.m.
e. Retaining Walls 2.4 man hrs./sq.m.
f. Stairs & Landing 2.48 man hrs./sq.m.
g. Form oil application 6 man hrs./sq.m.
III. Reinforcement:
a. Reinforcement of 9 man hours/100 kilos
footing up to roofing
Labor Estimate
Activities
CONSTRUCTION WORK CAPACITIES IN MAN HOURS
b. Grade Slab EWP 13 man hours/100sq.m.
c. Floor membrane 15 man hours/100sq.m.
d. Roof beams & bond 2.88 man hours/cu.m.
beams
e. Stairs 2.6 man hours/cu.m.
f. Roof Slab 2.91 man hours/cu.m.
g. Curing (water) 2 man hours/day for 7 days
h. Equipment:
1 Vibrator 16 min./cu.m.
2 Crane 4 cu.m./man hour
FORMWORKS
MANHOURS PER SQUARE METER
ITEMS
Carpenter Laborer
1. Continous Wall Type (CHB) 0.70 0.40 1.10
2. Foundation on Pile Caps 1.50 0.65 2.15
3. Grade Beam or FTB 0.75 0.40 1.15
4. Walls Ground to 8 ft. high 1.10 0.72 1.82
5. Walls 8 ft. to 16 ft. high 1.21 0.78 1.99
6. Walls 16 ft. to 20 ft. high 1.35 0.90 2.25
7. Columns 1.22 0.80 2.02
8. Beams & Girders 1.90 1.22 3.12
9. Elevated Slabs (word shores) 1.15 1.16 2.31
10. Elevated Slabs (adjusted shores) 0.70 0.90 1.60
SCAFFOLDING
LENGTH
Erect Dismantle Total Erect
1 to 2 Section Long 1.20 0.35 1.55 1.40
3 to 5 Section Long 0.75 0.5 1.25 0.85
6 section or more long 0.65 0.35 1.00 0.75
1. Common Excavation (Manual) 6.00 MH/cu.m.
2. Common Excavation (Machine) 0.50 MH/cu.m.
3. Hook Excavation (Manual & Machine) 8.00 MH/cu.m.
4. Structural Backfill (Manual) 5.00 MH/cu.m.
5. Structural Backfill (Machine) 2.00 MH/cu.m.
6. Hauling Spoils 1.00 MH/cu.m.
7. Trenching by Hand 6.00 MH/cu.m.
8. Trenching by Machine 0.20 MH/cu.m.
9. Piping Installation
CONCRETE FOUNDATION AND ELEVATED CONCRETE UNIT MANHOURS
1. GRADE MEMBER
Formwork 2.54 MH/sq.m.
MANHOURS
Total
1 or 2 Section High More than 2 Sec. High
Dismantle
1.00
0.60
0.40
UNIT MANHOURS ITEM OF WORK
Concreting 8.54 MH/sq.m.
Rebar Works 0.07 MH/sq.m.
Finishing 0.40 MH/sq.m.
2. SUSPENDED MEMBER
Formwork 3.28 MH/sq.m.
Concreting 16.70 MH/sq.m.
Rebar Works 0.08 MH/sq.m.
Finishing 0.80 MH/sq.m.
Excavation 1.35 cu.m./man day
Backfill 3.87 cu.m./man day
Disposal of spoils 4.70 cu.m./man day
Formworks 2.70 cu.m./man day
Steelworks 10.00 kg./man day
Concreting 0.91 cu.m./man day
Finishing 11.80 cu.m./man day
CHB Zocalo wall 2.40 sq.m./man day
Ground floor slab (concreting) 1.00 cu.m./man day
6 mm 0.222 0.2827 1.332 1.665 1.998
10 mm 0.616 0.7854 3.696 4.62 5.544
12 mm 0.887 1.131 5.322 6.6525 7.983
16 mm 1.577 2.011 9.462 11.8275 14.193
20 mm 2.463 3.142 14.778 18.4725 22.167
25 mm 3.848 4.919 23.088 28.86 34.632
28 mm 4.827 6.1575 28.962 36.2025 43.443
32 mm 6.305 8.0425 37.83 47.2875 56.745
36 mm 7.98 10.179 47.88 59.85 71.82
FORMULAS TO FIND APPROXIMATE NUMBER OF NAILS REQUIRED
Number of Pounds (12d + 60d, framing) = d/6 x BF/100
Number of Pounds (2d to 12d, sheating) = d/4 x BF/100
where
d = size of desired nail in pennies
BF = total board feet to be nailed
MISCELLANEOUS LABOR OUTPUT
PHILIPPINE STANDARD WEIGHT OF REINFORCING BARS
Nominal
diameter
Unit Wt.
kg./meter
Nominal
sectional
6.00m
kilograms
7.50m
kilograms
9.00m
kilograms
10.50m kilograms 12.00m kilograms
2.331 2.664
6.468 7.392
9.3135 10.644
16.5585 18.924
25.8615 29.556
40.404 46.176
83.79 95.76
50.6835 57.924
66.2025 75.66
cu.m. concrete/day
cu.m. conc./day
cu.m. conc./day
72 sq.m./day
420 pcs./day
8 sq.m./day
pcs./day
cu.m./day
pcs./day
pcs./day
set water closet/2 days
set Lav./1 1/2 day
sheets/day
sheets/day
sheets/day
sheets/day
5 sheets: 32"x8" G.I. sheets/day
lights/day
pcs. 2"x5"x16" or 40 bd.ft./day
pcs. Door/day
pcs./day
bd.ft./day
bd.ft./day
sheets 4'x8'/day
bd.ft./day
sq.ft/day
88.88889
Labor Estimate
CONSTRUCTION WORK CAPACITIES IN MAN HOURS
Total
2.40
1.45
1.15
More than 2 Sec. High
Dismantle
1.00
0.60
0.40
MISCELLANEOUS LABOR OUTPUT
PHILIPPINE STANDARD WEIGHT OF REINFORCING BARS
12.00m kilograms
2.664
7.392
10.644
18.924
29.556
46.176
95.76
57.924
75.66
1. Concreting of Plain Flooring 2 men pour 1.2 cu.m. concrete/day
2. Concreting of Reinf. Flooring 2 men pour 0.84 cu.m. conc./day
3. Concreting of Column & Beam 2 men pour 0.50 cu.m. conc./day
4. Finishing of Flooring (rough) 2 men finishes 72
5. Finishing of CHB Joints 2 men finishes 420
6. Plastering of CHB 2 men plaster 8
7. Laying of CHB 2 men lay 100 pcs./day
8. Breaking old RC Flooring 2 men break 0.3 cu.m./day
9. Laying of glazed tile 4"x4" 2 men lay 100 pcs./day
10. Laying of glazed tile 6"x6" 2 men lay 72 pcs./day
11. Installation of Water Closet 2 men install 1 set water closet/2 days
12. Installation of Lavatory 2 men install 1 set Lav./1 1/2 day
13. Installation of G.I. Sheets 32"x8" on Steel Frames 2 men install 11 sheets/day
14. Installation of G.I. Sheets 32"x8" on Wooden Frames 2 men install 20 sheets/day
15. Installation of G.I. Sheets 32"x12" on Steel Frames 2 men install 10 sheets/day
16. Installation of G.I. Sheets 32"x12" on Wooden Frames 2 men install 15 sheets/day
17. Fabricating and Installation of Gutter Downspout, Ridge roll 2 men fab. Install 5
18. Installation of G.I. Pipe 1/2 x 20" 2 men install 20 lights/day
19. Installation of Doors and Window Jamp 1 men install 3 pcs. 2"x5"x16" or
20. Installation of Door (Complete of Hinges and Knob) 1 men install 2 pcs. Door/day
21. Fabrication of Doors (Excluding Planning of Frames) 1 men makes 3 pcs./day
22. Planning Rough Lumber (Including Allignment) 1 man Planes 48 bd.ft./day
23. Planning Rough Lumber (No Allignment) 1 man Planes 120 bd.ft./day
24. Installation of Plywood Board 2 men install 15 sheets 4'x8'/day
25. Installation of Wooden Post 2 men install 96 bd.ft./day
26. Installation of Wood Jalousies Windows 1 men install 18.75 sq.ft/day
I. Earth Works:
a. Excavation 1.82 man hours/cu.m.
b. Backfill 1.34 man hours/cu.m.
II. Form Works:
a. Footing, grade, 2.5 man hours/sq.m.
column
b. Beams, bond beams, 2.8 man hrs./sq.m.
floor slab
c. Roof beams & bond 3.01 man hrs./sq.m.
beams
d. Roof slab 3.34 man hrs./sq.m.
e. Retaining Walls 2.4 man hrs./sq.m.
f. Stairs & Landing 2.48 man hrs./sq.m.
g. Form oil application 6 man hrs./sq.m.
III. Reinforcement:
a. Reinforcement of 9 man hours/100 kilos
footing up to roofing
b. Grade Slab EWP 13 man hours/100sq.m.
c. Floor membrane 15 man hours/100sq.m.
d. Roof beams & bond 2.88 man hours/cu.m.
Labor Estimate
Activities
CONSTRUCTION WORK CAPACITIES IN MAN HOURS
beams
e. Stairs 2.6 man hours/cu.m.
f. Roof Slab 2.91 man hours/cu.m.
g. Curing (water) 2 man hours/day for 7 days
h. Equipment:
1 Vibrator 16 min./cu.m.
2 Crane 4 cu.m./man hour
FORMWORKS
MANHOURS PER SQUARE METER
ITEMS
Carpenter Laborer
1. Continous Wall Type (CHB) 0.70 0.40 1.10
2. Foundation on Pile Caps 1.50 0.65 2.15
3. Grade Beam or FTB 0.75 0.40 1.15
4. Walls Ground to 8 ft. high 1.10 0.72 1.82
5. Walls 8 ft. to 16 ft. high 1.21 0.78 1.99
6. Walls 16 ft. to 20 ft. high 1.35 0.90 2.25
7. Columns 1.22 0.80 2.02
8. Beams & Girders 1.90 1.22 3.12
9. Elevated Slabs (word shores) 1.15 1.16 2.31
10. Elevated Slabs (adjusted shores) 0.70 0.90 1.60
SCAFFOLDING
LENGTH
Erect Dismantle Total Erect
1 to 2 Section Long 1.20 0.35 1.55 1.40
3 to 5 Section Long 0.75 0.5 1.25 0.85
6 section or more long 0.65 0.35 1.00 0.75
1. Common Excavation (Manual) 6.00 MH/cu.m.
2. Common Excavation (Machine) 0.50 MH/cu.m.
3. Hook Excavation (Manual & Machine) 8.00 MH/cu.m.
4. Structural Backfill (Manual) 5.00 MH/cu.m.
5. Structural Backfill (Machine) 2.00 MH/cu.m.
6. Hauling Spoils 1.00 MH/cu.m.
7. Trenching by Hand 6.00 MH/cu.m.
8. Trenching by Machine 0.20 MH/cu.m.
9. Piping Installation
CONCRETE FOUNDATION AND ELEVATED CONCRETE UNIT MANHOURS
1. GRADE MEMBER
Formwork 2.54 MH/sq.m.
Concreting 8.54 MH/sq.m.
Rebar Works 0.07 MH/sq.m.
Finishing 0.40 MH/sq.m.
2. SUSPENDED MEMBER
MANHOURS
Total
1 or 2 Section High More than 2 Sec. High
Dismantle
1.00
0.60
0.40
UNIT MANHOURS ITEM OF WORK
Formwork 3.28 MH/sq.m.
Concreting 16.70 MH/sq.m.
Rebar Works 0.08 MH/sq.m.
Finishing 0.80 MH/sq.m.
Excavation 1.35 cu.m./man day
Backfill 3.87 cu.m./man day
Disposal of spoils 4.70 cu.m./man day
Formworks 2.70 cu.m./man day
Steelworks 10.00 kg./man day
Concreting 0.91 cu.m./man day
Finishing 11.80 cu.m./man day
CHB Zocalo wall 2.40 sq.m./man day
Ground floor slab (concreting) 1.00 cu.m./man day
6 mm 0.222 0.2827 1.332 1.665 1.998
10 mm 0.616 0.7854 3.696 4.62 5.544
12 mm 0.887 1.131 5.322 6.6525 7.983
16 mm 1.577 2.011 9.462 11.8275 14.193
20 mm 2.463 3.142 14.778 18.4725 22.167
25 mm 3.848 4.919 23.088 28.86 34.632
28 mm 4.827 6.1575 28.962 36.2025 43.443
32 mm 6.305 8.0425 37.83 47.2875 56.745
36 mm 7.98 10.179 47.88 59.85 71.82
FORMULAS TO FIND APPROXIMATE NUMBER OF NAILS REQUIRED
Number of Pounds (12d + 60d, framing) = d/6 x BF/100
Number of Pounds (2d to 12d, sheating) = d/4 x BF/100
where
d = size of desired nail in pennies
BF = total board feet to be nailed
MISCELLANEOUS LABOR OUTPUT
PHILIPPINE STANDARD WEIGHT OF REINFORCING BARS
Nominal
diameter
Unit Wt.
kg./meter
Nominal
sectional
6.00m
kilograms
7.50m
kilograms
9.00m
kilograms
10.50m kilograms 12.00m kilograms
2.331 2.664
6.468 7.392
9.3135 10.644
16.5585 18.924
25.8615 29.556
40.404 46.176
83.79 95.76
50.6835 57.924
66.2025 75.66
cu.m. concrete/day
cu.m. conc./day
cu.m. conc./day
sq.m./day
pcs./day
sq.m./day
set water closet/2 days
set Lav./1 1/2 day
sheets: 32"x8" G.I. sheets/day
pcs. 2"x5"x16" or 40 bd.ft./day
pcs. Door/day
sheets 4'x8'/day
Labor Estimate
CONSTRUCTION WORK CAPACITIES IN MAN HOURS
Total
2.40
1.45
1.15
More than 2 Sec. High
MISCELLANEOUS LABOR OUTPUT